CN201362691Y CNU2009200796754U CN200920079675U CN201362691Y CN 201362691 Y CN201362691 Y CN 201362691Y CN U2009200796754 U CNU2009200796754 U CN U2009200796754U CN 200920079675 U CN200920079675 U CN 200920079675U CN 201362691 Y CN201362691 Y CN 201362691Y
Authority
CN
China
Prior art keywords
outlet
communicated
smoke
combustion chamber
full
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2009200796754U
Other languages
Chinese (zh)
Inventor
张扬福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2009200796754U priority Critical patent/CN201362691Y/en
Application granted granted Critical
Publication of CN201362691Y publication Critical patent/CN201362691Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model provides a full-automatic ignition plant gasification furnace, which comprises an ignition controller, a furnace body, a smoke converter, a blower and a gas furnace bag; wherein the ignition controller is provided with an automatic reset ignition button; the furnace body is provided with an ignition combustion chamber and a smoke-producing combustion chamber which is arranged at the top of the ignition combustion chamber and is provided with an air inlet and a smoke outlet; a furnace cover is hermetically matched with the top of the furnace body; the ignition combustion chamber is provided with resistance wires which are controlled by the ignition controller; the air inlet of the smoke-producing combustion chamber is communicated with an air outlet of the blower through a pipeline; an air inlet valve is arranged at the air inlet; the smoke converter is provided with a primary smoke conversion chamber which is communicated with the smoke outlet and a secondary smoke conversion chamber which is communicated with an air outlet of the primary smoke conversion chamber; a gas valve is arranged at an outlet of the secondary smoke conversion chamber; and the gas furnace bag is connected with the outlet of the secondary smoke conversion chamber through a pipeline. The full-automatic ignition plant gasification furnace has the advantages that the automatic ignition is realized, the smoke discharge time is short, the indoor pollution is avoided, and the gasification furnace is beneficial for environmental protection.

Description

Full-automatic igniting plant gasfier
Technical field:
The utility model is relevant with vapourizing furnace, and is relevant with full-automatic igniting plant gasfier especially.
Background technology:
Along with science and technology development, people's environmental consciousness is also more and more stronger.Plant gasfier is more and more.The straw gasification stove that has now emerged uses very inconvenient, and particularly very bad control when igniting if do not light, also will be drawn out all fuel and do regnition.Smoke combustion bucket and ignition are one, and the fuel in the bucket can not fully burn, and the reinforced number of times that has increased the user has also expended a large amount of time (having nearly 1/3rd more fuel not burn).Reinforced chronic, discharged fume in about 15 minutes, also be difficult to the surplus cigarette in the bucket arrange, so when feeding in raw material, still do not break away from impression that smoke fire in several thousand burns and indoor pollution.
The utility model content:
The purpose of this utility model is in order to overcome above deficiency, and providing a kind of can light a fire automatically, and the smoke evacuation time is short, avoids indoor pollution, is beneficial to the full-automatic igniting plant gasfier of environmental protection.
The purpose of this utility model is achieved like this:
The utility model plant gasfier of automatically lighting a fire, include the igniting of the start button that automatically resets, controller, body of heater, the smog transmodulator, gas blower, the gas furnace bag, pilotchamber and the product cigarette combustion chamber that contains inlet mouth and exhanst gas outlet that is positioned at the pilotchamber top are arranged in the body of heater, bell cooperates with the body of heater top seal, the resistance wire that is subjected to ignition controller control is arranged in the pilotchamber, the inlet mouth that produces the cigarette combustion chamber is communicated with blower outlet by pipeline, there is air intake valve at the inlet mouth place, one-level smog switch room that is communicated with exhanst gas outlet and the secondary smoke switch room that is communicated with one-level smog switch room air outlet are arranged in the smog transmodulator, there is burnt gas valve in secondary smoke switch room exit, and the gas furnace bag is connected with the outlet of secondary smoke switch room by pipeline.
Above-mentioned bottom of furnace body has the combustion chamber blast inlet that is connected with blower outlet by pipeline, and combustion chamber air intake valve is equipped with at blast inlet place in combustion chamber.
There is the oxygen supply port that communicates with blower outlet by pipeline in above-mentioned secondary smoke switch room exit, and the oxygen supply valve is equipped with at the oxygen supply port place.
Above-mentioned pilotchamber is shaped as down the little big cone that.
In the above-mentioned ignition controller alternating current contactor is arranged, the time relay that is connected with alternating current contactor, the earth leakage circuit-breaker that is connected with the time relay with alternating current contactor.
There is periphery that the first step cooling room of first step cooling water tank is arranged in the above-mentioned one-level smog switch room, first end stretches in the first step cooling room by second end of the first step smog transition duct that pipeline is communicated with the body of heater exhanst gas outlet, first step gasification gas passage is communicated with first step cooling room, there is periphery that the second stage cooling room of second stage cooling water tank is arranged in the secondary smoke switch room, first end of second stage intake ducting and first step gasification gas passage air outlet is communicated with and second end stretches in the cooling room of the second stage, and second stage outlet passageway is communicated with second stage cooling room.
During the utility model work; open bell, igniter fuel and product cigarette fuel are contained in respectively in pilotchamber and the product cigarette combustion chamber, shut bell; the earth leakage circuit-breaker energising; ignition controller just is in holding state, presses the button ignition switch that automatically resets, and alternating current contactor is started working; the time relay picks up counting; resistance wire is started working, the igniter fuel that the firing point fire burns is indoor, and gas blower was started working when the start button that automatically resets igniting resetted.Ignite by the burnt fuel of pilotchamber and to produce fuel (the pilotchamber funnel of cigarette combustion chamber, the fuel that produces the cigarette combustion chamber is burnt comprehensively), thereby produce a large amount of smog, enter the smog transmodulator by pipeline and be converted to gas and use for the user.After during reinforced smoke evacuation all pipeline valves being closed, opened smoke-discharging valve, and then opened smoke-discharging air intake valve.
Compare with existing straw gasification stove, the utlity model has following advantage:
1, a lot of drawbacks of manual ignition have been removed in igniting from automatically, have reduced ignition time to a great extent, have avoided the secondary relight, and the length of ignition time can be decided by based on fuel, and button ignition switch automatically resets, and has avoided smoke fire to burn and indoor pollution.
2, gas blower is work automatically synchronously when button ignition switch automatically resets, and has avoided the unpunctual phenomenon of Artificial Control air intake,
3, the pilotchamber funnel, air intake makes the full combustion of fuel of the inside comprehensively, thus the fuel that produces the cigarette combustion chamber that ignites burns more completely, and the output of flue gas is greatly improved, and has reduced reinforced number of times.
4, the flue gas gasification that the secondary smoke switch room can not be gasified totally one-level smog switch room, tar and the impurity that does not have to have filtered are removed fully, make combustion efficacy more abundant.
5, reinforced smoke evacuation does not need to wait for a long time, just can drain the surplus cigarette of the inside in 1.5 minutes.
6, avoided indoor pollution, be beneficial to environmental protection.
Description of drawings:
Fig. 1 is the utility model structural representation.
Fig. 2 is the ignition controller schematic diagram.
Embodiment:
Referring to Fig. 1, the present embodiment plant gasfier of automatically lighting a fire comprises ignition controller 1, body of heater 2, smog transmodulator 3, gas blower 4, infrared rays gas furnace bag 5.Pilotchamber 6 and the product cigarette combustion chamber 9 that contains inlet mouth 7 and exhanst gas outlet 8 that is positioned at the pilotchamber top are arranged in the body of heater.Bell 32 cooperates with the body of heater top seal.Pilotchamber is shaped as down the little big cone that.The resistance wire 10 that is controlled by the controller is arranged in the pilotchamber.The inlet mouth that produces the cigarette combustion chamber is communicated with blower outlet by pipeline.There is air intake valve 11 at the inlet mouth place.One-level smog switch room 12 that is communicated with exhanst gas outlet and the secondary smoke switch room 13 that is communicated with one-level smog switch room air outlet are arranged in the smog transmodulator.There is burnt gas valve 14 in secondary smoke switch room exit.Gas furnace bag 5 is connected with the outlet of secondary smoke switch room by pipeline.There is periphery that the first step cooling room 16 of first step cooling water tank 15 is arranged in the one-level smog switch room, first end stretches into first step cooling room by second end of the first step smog transition duct 17 that pipeline is communicated with the body of heater exhanst gas outlet, and first step gasification gas passage 18 is communicated with first step cooling room.There is periphery that the second stage cooling room 20 of second stage cooling water tank 19 is arranged in the secondary smoke switch room, first end in second stage inlet pipe 21 roads and first step gasification gas passage air outlet is communicated with and second end stretches in the cooling room of the second stage, and second stage outlet passageway 22 is communicated with second stage cooling room.
Bottom of furnace body has the combustion chamber blast inlet 23 that is connected with blower outlet by pipeline.Combustion chamber air intake valve 24 is equipped with at blast inlet place, combustion chamber.
There is the oxygen supply port 25 that communicates with blower outlet by pipeline in smog transmodulator secondary smoke switch room exit.Oxygen supply valve 26 is equipped with at the oxygen supply port place.
Referring to Fig. 2, the button ignition switch 27 that automatically resets in the ignition controller, working index lamp 28, alternating current contactor 29, the time relay 30 that is connected with alternating current contactor, the earth leakage circuit-breaker 31 that is connected with the time relay with alternating current contactor.

Claims (7)

1, full-automatic igniting plant gasfier, it is characterized in that including the ignition controller of button ignition switch of automatically reseting, body of heater, the smog transmodulator, gas blower, the gas furnace bag, pilotchamber and the product cigarette combustion chamber that contains inlet mouth and exhanst gas outlet that is positioned at the pilotchamber top are arranged in the body of heater, bell cooperates with the body of heater top seal, the resistance wire that is subjected to ignition controller control is arranged in the pilotchamber, the inlet mouth that produces the cigarette combustion chamber is communicated with blower outlet by pipeline, there is air intake valve at the inlet mouth place, one-level smog switch room that is communicated with exhanst gas outlet and the secondary smoke switch room that is communicated with one-level smog switch room air outlet are arranged in the smog transmodulator, there is burnt gas valve in secondary smoke switch room exit, and the gas furnace bag is connected with the outlet of secondary smoke switch room by pipeline.
2, full-automatic igniting plant gasfier as claimed in claim 1 is characterized in that bottom of furnace body has the combustion chamber blast inlet that is connected with blower outlet by pipeline, and combustion chamber air intake valve is equipped with at blast inlet place in combustion chamber.
3, full-automatic igniting plant gasfier as claimed in claim 1 or 2 is characterized in that there is the oxygen supply port that communicates with blower outlet by pipeline in secondary smoke switch room exit, and the oxygen supply valve is equipped with at the oxygen supply port place.
4, full-automatic igniting plant gasfier as claimed in claim 1 or 2 is characterized in that pilotchamber is shaped as down the little big cone that.
5, full-automatic igniting plant gasfier as claimed in claim 3 is characterized in that pilotchamber is shaped as down the little big cone that.
6, full-automatic igniting plant gasfier as claimed in claim 1 or 2 is characterized in that alternating current contactor is arranged in the controller, the time relay that is connected with alternating current contactor, the earth leakage circuit-breaker that is connected with the time relay with alternating current contactor.
7, full-automatic igniting plant gasfier as claimed in claim 1 or 2, it is characterized in that having in the one-level smog switch room periphery that the first step cooling room of first step cooling water tank is arranged, first end stretches in the first step cooling room by second end of the first step smog transition duct that pipeline is communicated with the body of heater exhanst gas outlet, first step gasification gas passage is communicated with first step cooling room, there is periphery that the second stage cooling room of second stage cooling water tank is arranged in the secondary smoke switch room, first end of second stage intake ducting and first step gasification gas passage air outlet is communicated with and second end stretches in the cooling room of the second stage, and second stage outlet passageway is communicated with second stage cooling room.
CNU2009200796754U 2009-03-20 2009-03-20 Full-automatic ignition plant gasification furnace Expired - Fee Related CN201362691Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2009200796754U CN201362691Y (en) 2009-03-20 2009-03-20 Full-automatic ignition plant gasification furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2009200796754U CN201362691Y (en) 2009-03-20 2009-03-20 Full-automatic ignition plant gasification furnace

Publications (1)

Publication Number Publication Date
CN201362691Y true CN201362691Y (en) 2009-12-16

Family

ID=41473353

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2009200796754U Expired - Fee Related CN201362691Y (en) 2009-03-20 2009-03-20 Full-automatic ignition plant gasification furnace

Country Status (1)

Country Link
CN (1) CN201362691Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102183914A (en) * 2011-03-11 2011-09-14 四川鑫星铝业有限责任公司 On-line air-removing automatic ignition heat preservation control system
CN108441265A (en) * 2018-05-17 2018-08-24 长春市鲲鹏节能环保科技有限公司 A kind of intelligent controlling device of biomass gasifying furnace

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102183914A (en) * 2011-03-11 2011-09-14 四川鑫星铝业有限责任公司 On-line air-removing automatic ignition heat preservation control system
CN102183914B (en) * 2011-03-11 2012-08-29 四川鑫星铝业有限责任公司 On-line air-removing automatic ignition heat preservation control system
CN108441265A (en) * 2018-05-17 2018-08-24 长春市鲲鹏节能环保科技有限公司 A kind of intelligent controlling device of biomass gasifying furnace
CN108441265B (en) * 2018-05-17 2024-01-23 长春市鲲鹏节能环保科技有限公司 Intelligent control device of biomass gasification furnace

Similar Documents

Publication Publication Date Title
CN103267293A (en) Rubbish gasification furnace
CN105698192B (en) A kind of waste incinerator air inlet control device
CN201362691Y (en) Full-automatic ignition plant gasification furnace
CN211694945U (en) Landfill marsh gas torch
CN201354361Y (en) Biomass gasifier
CN201306835Y (en) Smokeless and dustless reverse heat pipe coal burning boiler
CN203323134U (en) Rubbish gasification furnace
CN206222323U (en) Full gasification boiler
CN201407687Y (en) Direct-combustion straw bath heating furnace
CN201396815Y (en) Straw gasification furnace
CN101672469A (en) Method and device for igniting coal gas in heat storage chamber and flue during kiln reversing
CN202692158U (en) Gasifier
CN201569015U (en) Improved structure for cooking range
CN215112713U (en) Rice hull conveyor for rice hull gasification furnace
CN108443869A (en) A kind of hybrid low NO of flue gas, boiler and its application method with it
CN2437683Y (en) Small household multifunction stalk gasifying device
CN201412886Y (en) Biological fuel gasification burner
CN201748487U (en) Negative-pressure gasifier
CN107606782A (en) A kind of normal-pressure hot-water boiler of agricultural crop straw or coal gasification combustion
CN209147071U (en) A kind of double combustion energy saving no-smoke furnaces of down-firing
CN201852148U (en) Tertiary air inlet system device of coal furnace
CN101749739B (en) Improved stove structure and fire using method thereof
CN201589296U (en) Multifunctional direct biomass combustion furnace
CN201964467U (en) Mixed fuel furnace system
CN201233028Y (en) Gas water heating stove

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091216