CN201335404Y CNU2009201438041U CN200920143804U CN201335404Y CN 201335404 Y CN201335404 Y CN 201335404Y CN U2009201438041 U CNU2009201438041 U CN U2009201438041U CN 200920143804 U CN200920143804 U CN 200920143804U CN 201335404 Y CN201335404 Y CN 201335404Y
Authority
CN
China
Prior art keywords
cfbb
boiler
fluid bed
circulating fluid
conveying device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2009201438041U
Other languages
Chinese (zh)
Inventor
张德君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2009201438041U priority Critical patent/CN201335404Y/en
Application granted granted Critical
Publication of CN201335404Y publication Critical patent/CN201335404Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

The utility model relates to an igniting device of a circulating fluid bed boiler, which comprises circulating fluid bed boilers, cyclone separators and return feeders mounted below the cyclone separators. The igniting device is characterized in that one end of an iron oxide slag delivery device is connected with a deslagging pipe and a discharge port of the return feeder through two branch pipes and the other end thereof is connected with a deslagging pipe and a discharge port of the return feeder on the adjacent circulating fluid bed boiler; and the pipes at the two ends of the iron oxide slag delivery device are provided with valves respectively. Since the two adjacent circulating fluid bed boilers are connected through the iron oxide slag delivery device, when either of the boilers is ignited after maintenance, the high-temperature iron oxide slag (800 DEG C to 900 DEG C) in the other boiler is utilized to start the boiler, thereby greatly saving fuel. The igniting device has the advantages of simple structure and easy operation, and can effectively reduce the starting cost after maintenance of the boiler.

Description

CFBB point furnace apparatus
Affiliated technical field
The utility model relates to a kind of CFBB point furnace apparatus.
Background technology
It is ripe that present large-size circulating fluidized bed technology has been tending towards, is mainly used in coal-fired thermal power generation.The basic procedure of CFBB is: after coal and desulfurizing agent are sent into burner hearth, surrounded by a large amount of inertia high-temperature materials rapidly, fire burns, carry out desulphurization reaction simultaneously, and under the effect of rising flue gas stream, move to upper furnace, to other heating surface heat releases of arranging in water-cooling wall and the stove.Oversize grain enters the back, zone that suspends and depart from primary air under gravity and external force effect, thereby adherent dirty.Gas-solid mixture enters high temperature cyclone separator after leaving burner hearth, and a large amount of solid particles as coal grain, the desulfurizing agent loopback burner hearth that is separated, carry out circulating combustion.The fine particle that is not separated enters back-end ductwork with flue gas, with heating superheater, economizer and air preheater, drains into atmosphere through deduster.Because CFBB is under the high velocity air state, carries out work, so just causes serious wear, need frequent shutdown maintenance.After each maintenance, all need a large amount of fuel oils the solid material in the boiler to be heated at the boiler startup initial stage, after the safety that makes the temperature of solid material can reach coal uses temperature, could throw coal and carry out operate as normal, how reducing the payment for initiation usefulness of maintenance back CFBB, is the target that each CFBB uses enterprise to pursue.
Summary of the invention
The utility model is with the isolated high temperature combustible of adjacent circulation fluidized-bed combustion boiler cyclone separator, introduces in the CFBB after overhauling, and this boiler is carried out the CFBB point furnace apparatus of heating starting.
For achieving the above object, the technical solution of the utility model is: a kind of CFBB point furnace apparatus, comprise CFBB, cyclone separator, standpipe and be installed in material returning device under the cyclone separator, an end that it is characterized in that red slag conveying device links to each other with discharging opening with the scum pipe of material returning device respectively by two bye-passes, the scum pipe of the material returning device on the other end and the adjacent CFBB links to each other with discharging opening, is separately installed with valve on the pipeline at red slag conveying device two ends.
Above-mentioned red slag conveying device is a Pneumatic conveyer.
Above-mentioned red slag conveying device is scraping plate conveying device or bucket type conveying device.
Device of the present utility model is between two CFBBs, by red slag conveying device two boilers are connected, when lighting a fire behind boiler maintenance so therein, can utilize the red slag of 800-900 ℃ of high temperature of another boiler, boiler after the maintenance is carried out heating starting, need not to use fuel oil to heat, saved a large amount of fuel oils.As overhauling 12 times in 470 tons CFBB year, when lighting a fire at every turn, generally need the light diesel more than 20 tons to carry out heating starting, and after adopting this device, just can save this part expense, about 1,200,000 yuan of year saving diesel oil expenses.It is simple in structure, easy to use that this device has, and can effectively reduce the start-up cost behind the boiler maintenance.
Description of drawings
Accompanying drawing 1 is a structural representation of the present utility model.
The specific embodiment
As shown in Figure 1, the left side is the I CFBB, and the right side is the II CFBB.Every CFBB comprises cyclone separator 1, standpipe 2 and is installed in material returning device 5 under the cyclone separator.Be connected with red slag conveying device on the scum pipe 6 of two boiler material returning devices, 5 lower ends, this device is separately installed with valve for Pneumatic conveyer between this Pneumatic conveyer and the scum pipe 6.On the discharging opening 4 that material returning device and boiler are connected, be connected with respectively with the power conveying device together with bye-pass, on this bye-pass, be separately installed with valve.
When needing ignition trigger after the maintenance of I CFBB, valve I 7, valve III11 are closed, valve II 8 and valve IV12 open, this moment, the red slag of high temperature of II CFBB just passed through valve IV12, pneumatic carrier 10, bye-pass and the valve II8 on it, enter the discharging opening 4 of I CFBB material returning device, be inhaled in the burner hearth 3 then, boiler is heated.After the I CFBB reaches start-up temperature, valve-off II 8 and valve IV12, the I CFBB is thrown coal and is normally moved.
When needing ignition trigger after the maintenance of II CFBB, valve I 7, valve III11 are opened, valve II8 and valve IV12 close, and the red slag of high temperature is transported in the II CFBB by the I CFBB.
Above-mentioned Pneumatic conveyer comprises pneumatic carrier 10 and is installed in the high-pressure air hose 9 at pneumatic carrier two ends.The high-pressure blast of high-pressure air hose can utilize the wind regime in the steam generator system, as once or the secondary wind regime.
Red slag conveying device also can be utilized existing scraping plate conveying device or bucket type conveying device, its objective is the red slag of high temperature is carried between two boilers.

Claims (3)

1, a kind of CFBB point furnace apparatus, comprise CFBB, cyclone separator, standpipe and be installed in material returning device under the cyclone separator, an end that it is characterized in that red slag conveying device links to each other with discharging opening (4) with the scum pipe (6) of material returning device respectively by two bye-passes, the scum pipe of the material returning device on the other end and the adjacent CFBB links to each other with discharging opening, is separately installed with valve on the pipeline at red slag conveying device two ends.
2, CFBB point furnace apparatus according to claim 1 is characterized in that above-mentioned red slag conveying device is a Pneumatic conveyer.
3, CFBB point furnace apparatus according to claim 1 is characterized in that above-mentioned red slag conveying device is scraping plate conveying device or bucket type conveying device.
CNU2009201438041U 2009-01-14 2009-01-14 Igniting device of circulating fluid bed boiler Expired - Lifetime CN201335404Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2009201438041U CN201335404Y (en) 2009-01-14 2009-01-14 Igniting device of circulating fluid bed boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2009201438041U CN201335404Y (en) 2009-01-14 2009-01-14 Igniting device of circulating fluid bed boiler

Publications (1)

Publication Number Publication Date
CN201335404Y true CN201335404Y (en) 2009-10-28

Family

ID=41287058

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2009201438041U Expired - Lifetime CN201335404Y (en) 2009-01-14 2009-01-14 Igniting device of circulating fluid bed boiler

Country Status (1)

Country Link
CN (1) CN201335404Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105276575A (en) * 2014-06-12 2016-01-27 国网山西省电力公司电力科学研究院 Boiler heating system
CN105674256A (en) * 2015-11-29 2016-06-15 集美大学 Quick-start system and method for circulating fluidized bed boilers
CN106958811A (en) * 2017-05-16 2017-07-18 中国华能集团清洁能源技术研究院有限公司 A kind of method and system using this stove of adjacent stove Hot-blast Heating
CN114060802A (en) * 2021-11-19 2022-02-18 无锡华光环保能源集团股份有限公司 High-pressure air plugging method for processing material return interruption of circulating fluidized bed boiler

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105276575A (en) * 2014-06-12 2016-01-27 国网山西省电力公司电力科学研究院 Boiler heating system
CN105674256A (en) * 2015-11-29 2016-06-15 集美大学 Quick-start system and method for circulating fluidized bed boilers
CN105674256B (en) * 2015-11-29 2019-09-27 桂林航天工业学院 Circulating fluidized bed boiler quick start system and method
CN106958811A (en) * 2017-05-16 2017-07-18 中国华能集团清洁能源技术研究院有限公司 A kind of method and system using this stove of adjacent stove Hot-blast Heating
CN114060802A (en) * 2021-11-19 2022-02-18 无锡华光环保能源集团股份有限公司 High-pressure air plugging method for processing material return interruption of circulating fluidized bed boiler

Similar Documents

Publication Publication Date Title
CN102901212B (en) Low-range circulating fluidized bed water boiler for combusting inferior fuel and combustion method thereof
CN200975663Y (en) Circulating fluid bed boiler by burning biomass
CN102042600B (en) Circulating fluidized bed refuse incineration boiler
CN101545676B (en) High-efficiency energy-saving emission-reduction circulating fluid bed organic heat carrier boiler
CN201335404Y (en) Igniting device of circulating fluid bed boiler
CN102287813A (en) Boiler device adopting cyclone-burning method
CN201526976U (en) Refuse-fired boiler for circulating fluidized bed
CN101464005B (en) Circulating fluidized bed boiler ignition apparatus and method thereof
CN201697155U (en) Special matching fluidized bed furnace for drying for coal mill
CN101551107A (en) Circulating fluid bed incinerator for waste residue of agricultural chemicals and waste liquid incineration
CN105202575A (en) Ignition method and device through high-temperature high oxygen torch generated by coal powder or crushed coal combustion
CN109539821A (en) A kind of heat energy recycle method and device of high-temperature metallurgical slag
CN105157022A (en) Horizontal circulating fluidized bed boiler with bed material out circulation function
CN1888531B (en) Large coal powder boiler flying ash recycling method and apparatus
CN101629716B (en) Vertical arrangement method of low-NOx solid-liquid state deslagging pulverized coal burner
CN208546960U (en) The furnace grate of incendivity biomass fuel and fossil fuel
CN107162443B (en) Boiling lime kiln
CN102095254B (en) Organic heat carrier boiler of fluidized bed, with low cost, environment protection, energy saving and emission reduction
CN101408308A (en) Coal-burning boiler
CN201421186Y (en) High-efficiency energy-saving emission-reducing organic heat carrier boiler of circulating fluidize bed
CN212869743U (en) Double-fuel boiler capable of burning pure gas
CN100478612C (en) Circulating fluidized bed combustion device and its combustion method
CN104251487A (en) Method for improving boiler combustion economy of tangential combustion anthracite coal boiler
CN204704820U (en) Solid fuel gasification burning boiler
CN203836941U (en) High-efficiency cleaning suspension fluidization burning coal water slurry fired boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20091028

Effective date of abandoning: 20090114