CN201242769Y - System for fuzzy evaluation of underground gas pipe net risk - Google Patents

System for fuzzy evaluation of underground gas pipe net risk Download PDF

Info

Publication number
CN201242769Y
CN201242769Y CNU2008200493441U CN200820049344U CN201242769Y CN 201242769 Y CN201242769 Y CN 201242769Y CN U2008200493441 U CNU2008200493441 U CN U2008200493441U CN 200820049344 U CN200820049344 U CN 200820049344U CN 201242769 Y CN201242769 Y CN 201242769Y
Authority
CN
China
Prior art keywords
pipeline
risk
module
fuzzy
information acquisition
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008200493441U
Other languages
Chinese (zh)
Inventor
许俊城
黄崇智
温浩胜
袁金彪
伍波
李秀怀
李军
陈国华
曾静
周剑峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China University of Technology SCUT
Guangzhou Gas Group Co Ltd
Original Assignee
Gas Co Ltd Of Guangzhou City
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gas Co Ltd Of Guangzhou City, South China University of Technology SCUT filed Critical Gas Co Ltd Of Guangzhou City
Priority to CNU2008200493441U priority Critical patent/CN201242769Y/en
Application granted granted Critical
Publication of CN201242769Y publication Critical patent/CN201242769Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model provides a system for a fuzzy assessment on the risk of the underground fuel gas pipe network, which comprises an information acquisition input end and an enterprise management end connected through the network; wherein, the information acquisition input end is arranged into a plurality of computers which can receive and output the test data related to a gas pipeline and the environmental data around the gas pipeline; the enterprise management end comprises a pipeline subsection management module, a management module of information around a pipeline section, a pipeline fuzzy risk assessment module, a pipeline risk pre-alarming module and an auxiliary management module; and the computers of the information acquisition input end are connected with the enterprise management end through the network. The system for a fuzzy assessment on the risk of the underground fuel gas pipe network establishes an integrated underground fuel gas pipe network safety assessment system through a network connection of the information acquisition end and the enterprise management end and the cooperation of four modules of the enterprise management end by using the computer technology, thus realizing the goal of Tracking inspection-safety assessment-programmatic restoration, and changing a positive emergency repairing method of the gas leakage rescue into an active safe inspection and assessment management mode.

Description

A kind of system that is used to carry out underground gas ductwork risk fuzzy evaluation
Technical field
The utility model belongs to field of computer technology, specifically relates to a kind of system that is used to carry out underground gas ductwork risk fuzzy evaluation.
Background technology
Along with the continuous laying of oil, natural gas line, the risk management of pipe-line has caused global vast concern, the continuous development of science and technology, and feasible risk by the computer system management pipeline has become a kind of inevitable trend.Domestic speedily carrying out rescue work about gas leak is passive emergency maintenance method at present, still do not have good computer management system to realize the active management such as evaluation early warning of pipeline risk.
The utility model content
The purpose of this utility model is to overcome the deficiencies in the prior art, and a kind of fuzzy risk evaluating system of surrounding enviroment information management and risk assessment and the early warning at gas pipeline is provided.
To achieve these goals, the technical scheme of employing is as follows:
A kind of system that is used to carry out underground gas ductwork risk fuzzy evaluation is provided, comprise the information acquisition typing end and the business administration end that connect by network, described information acquisition typing end is arranged to several can receive and export gas pipeline relevant test data, gas pipeline surrounding enviroment data computing machine;
Described business administration end is provided with: duct segments administration module, pipeline section peripheral information administration module, pipeline fuzzy risk analysis module, pipeline Risk-warning module and auxiliary administration module;
The computing machine of described information acquisition typing end is connected by network with described business administration end.
Described auxiliary administration module comprises database, weight administration module and output function module.
Described network can be LAN (Local Area Network) or internet.
The beneficial effects of the utility model are: utilize computer technology, be connected by the network of information acquisition with the business administration end, and the cooperation of four modules of business administration end, set up complete underground gas pipe network safety evaluating system, to realize the target of " follow the tracks of and detect---safety assessment---planned reparation ".It is passive emergency maintenance method that gas leak is speedily carried out rescue work, and becomes safety detection, assessment and management mode initiatively.
Description of drawings
Fig. 1 the utility model system architecture synoptic diagram
Fig. 2 embodiment 1 the utility model system applies synoptic diagram
Embodiment
Below in conjunction with accompanying drawing and under institute of Gas Co Ltd of Guangzhou City jurisdiction the fuzzy risk evaluating pilot EXPERIMENTAL EXAMPLE of gas pipeline the utility model is described further.
Embodiment 1
The utility model system architecture synoptic diagram is seen accompanying drawing 1, and the fuzzy risk evaluating pilot of gas pipeline has been used the system that is used to carry out underground gas ductwork risk fuzzy evaluation under institute of Gas Co Ltd of Guangzhou City jurisdiction, as shown in Figure 2.Wherein 1,2,3 for the computing machine of information acquisition typing end, can be arranged at each information gathering point, each information gathering point is specially the pipeline of segmentation, the zone of burst or street, Guangzhou Tianhe District for example, the Yuexiu District, the underground gas ductwork of Huangpu District, different detecting instruments is set, also can carry out the collection conduit data message by artificial hand-held testing tool, the data message input information is gathered the computing machine 1 of typing end, 2,3, computing machine 1,2,3 by LAN (Local Area Network) or internet 4 with information data transmission to business administration end 5, described business administration end 5 is provided with: duct segments administration module 6, pipeline section peripheral information administration module 7, pipeline fuzzy risk analysis module 8 and pipeline Risk-warning module 9 and auxiliary administration module 10.
Described pipeline section peripheral information administration module institute information of managing comprises that pipeline essential information, third party destroy data, corrosion failure data, design factor data, maloperation factor data, consequence severity data.
Described pipeline section peripheral information administration module also provides the interface of checking of pipeline evaluating information and risk assessment object information.
The pipeline evaluating of described pipeline fuzzy risk analysis typing that module receives comprises accident possibility occurrence and damage sequence severity two parts, the evaluating of described accident possibility occurrence comprises third party's destruction, corrosion failure, design defect, misuse failure, and the evaluating of described damage sequence severity comprises combustion gas and ambient conditions, physical damage, non-physical loss.
The set evaluation algorithms of described pipeline fuzzy risk analysis module is based on fuzzy mathematical model, and is provided with the submodule that calculates pipeline evaluating index weight, and this submodule is passed to evaluation algorithms with the parameter weight that calculates.
Described pipeline fuzzy risk analysis module also is provided with auxiliary administration module and equipment, comprises the database that is used to preserve the risk assessment object information and storer etc.
The instrument of the described detection of the utility model information, record, detection can be routine measurement instrument, scanner, monitoring camera-shooting device etc., the segmented conduit peripheral information of gathering is gathered the computing machine of typing end by typing interface and data line input information, the computing machine of information acquisition typing end is exported to the business administration end by LAN (Local Area Network) or internet with data, the module of business administration end is carried out risk assessment according to tube circumference information to gas ductwork, and each module characteristic is as follows:
1, duct segments administration module
Realize piping unit sectional management function by the duct segments administration module, provide as basic data management operations such as interpolation, modification, deletions.
Interpolation comprises to be added evaluation unit and adds waypoint, and adding evaluation unit is the pipeline in a highway section of interpolation, and as the Tianhe North Road, Guangzhou City, highway section titles such as Zhong Shan main road are to add the sub-pipeline section that certain bar highway section is divided down and add waypoint.Sub-pipeline section is the evaluation object of risk assessment, is " day northern 2# valve from east to west 442 " as the waypoint in Milky Way North Road.
2, pipeline section peripheral information administration module
The fuzzy risk analysis that with the pipeline section is carrier need be collected a series of pipeline section surrounding enviroment data message, to information add, the database manipulation of deletion, modification etc.The present invention by pipeline section peripheral information administration module provide pipeline section surrounding enviroment information typing, deletion, revise, browse and quick positioning function.Comprise that pipeline essential information, third party destroy data, corrosion failure data, design factor data, maloperation factor data, consequence severity data, the look facility of pipeline evaluating information and risk assessment object information also is provided simultaneously.The typing of information can be passed through external input device, manually or automatically imports by the hardware accessory.
3, fuzzy risk analysis module
Fuzzy risk analysis will be imported evaluating earlier, the evaluating inputting interface that provides by pipeline fuzzy risk analysis module.The user can pass through external input device, manually or automatically imports.The pipeline fuzzy risk analysis respectively from the accident possibility and damage sequence severity two aspects estimate, the accident possibility occurrence comprises the content of 4 aspects: third party's destruction, corrosion failure, design defect, misuse failure.When pipeline is not estimated as yet, evaluating is empty, needs the user to carry out the selection input of parameter according to the environmental aspect of tube circumference, and the pipeline fuzzy risk analysis need be determined the object estimated, be evaluation unit and the waypoint of determining in the duct segments management, thereby determine the pipeline section of needs assessment.
Accident possibility occurrence as one of system ambiguous risk assessment parameter of the utility model comprises 4 aspects: third party's damage parameter, corrosion failure parameter, design defect parameter and misuse failure parameter.
Third party's damage parameter input item is to bury the ground degree of depth, pipeline ten contents of accordance of situation, pipeline subsurface picture, resident's situation, construction activities, line walking management, vehicle activity, geological condition, squatter building situation and planning on the ground.According to national standard " Code for design of city gas engineering " regulation (GB50028-2006), different geological conditions buries the scope difference of the ground degree of depth.Therefore bury the parameter of the ground degree of depth and select to be divided into 3 kinds of situations: driveway, walkway, paddy field.
Corrosion failure evaluating: consider the actual difficulty that city buried steel gas pipeline excavation detects, the native system evaluation module has been set up respectively based under the non-excavation situation of pipeline and based on the appraisement system parameter under the pipe excavation situation, thereby can carry out the fuzzy risk analysis of two kinds of situations to pipeline.Based on the evaluating under the non-excavation situation of pipeline be: 6 of pipeline external anti-corrosion layer, soil corrosivity, pipeline section wall thickness, cathodic protection, current interference and active times; Based on the evaluating under the pipe excavation situation be: 5 of soil, anticorrosive coat outward appearance (marking), joint, pipeline and active times.
The design defect evaluating comprises: the integrality of steel pipe safety coefficient, system's hydraulic testing, design data, designing unit's qualification and 5 contents of designing unit's experience.The misuse failure evaluating comprises: working specification formulation and implementation status, operator training, construction maloperation, 4 contents of workmen's quality.
Two damage sequence severity parameter input as the utility model system evaluation module evaluating comprises 3 aspects, that is: combustion gas and ambient conditions, physical damage, non-physical loss.
And combustion gas and ambient conditions include: 5 of the possibilities of medium toxic hazard, repairing control, natural situation, pipeline surround ground situation, second accident.
Physical damage then comprises: the damage of accident point population situation, buildings, the economy of repairing drop into 3.
Non-physical loss then comprises: to corporate reputation and influence of society, to the influence of environment, to the public's influence 3.
After all parameter inputs finish, determine evaluation object again, just can begin to carry out the fuzzy risk analysis of pipeline section.And evaluation result preserves database automatically, so that the user extracts the information of checking this segment pipe in the future.
4, Risk-warning module
The utility model is that the risk size of pipeline is carried out early warning by pipeline Risk-warning module.Pipeline need just can carry out Risk-warning through behind the fuzzy risk analysis.Pipeline Risk-warning module is selected corresponding grade early warning according to the alert degree of wanting early warning, finds the pipeline of the various early warning of response.Select " tertiary risk early warning (yellow early warning) " as the user, then pipeline Risk-warning module will be listed the pipeline section that meets the tertiary risk early warning by its user interface that provides, and accident possibility occurrence evaluation of indexes grade, and provide early warning measure and suggestion.
5, described business administration end also is provided with auxiliary administration module.
Auxiliary administration module comprises database, and system is backed up and reduces, and system database all needed to back up in operation a period of time.When system provides the DB Backup function, also provide the function of database reduction.
Auxiliary administration module also comprises the weight administration module, and in fuzzy risk analysis, weight is to estimate the most important condition of being carried out, and also is key factor.The weight administration module of described module comprises interpolation, deletion and adjusts operation.Particularly, provide the adjustment function of one-level factor weight, that is: the weight adjustment of third party's destruction, corrosion failure, design defect and four one-level factors of misuse failure for the weight adjustment.
As shown in Figure 2, auxiliary administration module 10 can also comprise output function, drive printer 11 and print assessment result, perhaps electronic display 12 is exported data presentation intuitively, perhaps directly drive warning facility 13 and report to the police, also can connect the instrument that usb 14 connects other conventional output result directly perceived.

Claims (2)

1, a kind of system that is used to carry out underground gas ductwork risk fuzzy evaluation comprises information acquisition typing end and business administration end, it is characterized in that:
Described information acquisition typing end is arranged to several can receive and export gas pipeline relevant test data, gas pipeline surrounding enviroment data computing machine;
Described business administration end is provided with: duct segments administration module, pipeline section peripheral information administration module, pipeline fuzzy risk analysis module, pipeline Risk-warning module and auxiliary administration module;
The computing machine of described information acquisition typing end is connected by network with described business administration end.
2,, it is characterized in that described network is LAN (Local Area Network) or internet according to the described system that is used to carry out underground gas ductwork risk fuzzy evaluation of claim 1.
CNU2008200493441U 2008-06-17 2008-06-17 System for fuzzy evaluation of underground gas pipe net risk Expired - Lifetime CN201242769Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200493441U CN201242769Y (en) 2008-06-17 2008-06-17 System for fuzzy evaluation of underground gas pipe net risk

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200493441U CN201242769Y (en) 2008-06-17 2008-06-17 System for fuzzy evaluation of underground gas pipe net risk

Publications (1)

Publication Number Publication Date
CN201242769Y true CN201242769Y (en) 2009-05-20

Family

ID=40716058

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200493441U Expired - Lifetime CN201242769Y (en) 2008-06-17 2008-06-17 System for fuzzy evaluation of underground gas pipe net risk

Country Status (1)

Country Link
CN (1) CN201242769Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101625071B (en) * 2009-08-07 2012-11-28 天津大学 Method for measuring and locating leakage of gas pipelines
CN103606025A (en) * 2013-10-17 2014-02-26 中国石油化工股份有限公司 Risk-based oil refining device corrosion management control method
CN104700161A (en) * 2015-03-06 2015-06-10 深圳市燃气集团股份有限公司 Risk factor identification-based construction site patrol optimization method and system
CN103927604B (en) * 2013-01-10 2017-01-25 中国石油天然气股份有限公司 Oil gas pipeline integrity data technology implementation method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101625071B (en) * 2009-08-07 2012-11-28 天津大学 Method for measuring and locating leakage of gas pipelines
CN103927604B (en) * 2013-01-10 2017-01-25 中国石油天然气股份有限公司 Oil gas pipeline integrity data technology implementation method
CN103606025A (en) * 2013-10-17 2014-02-26 中国石油化工股份有限公司 Risk-based oil refining device corrosion management control method
CN104700161A (en) * 2015-03-06 2015-06-10 深圳市燃气集团股份有限公司 Risk factor identification-based construction site patrol optimization method and system
CN104700161B (en) * 2015-03-06 2019-03-26 深圳市燃气集团股份有限公司 A kind of construction site inspection optimization method and system based on risk factors collection

Similar Documents

Publication Publication Date Title
CN101071483A (en) Underground gas pipe network fuzzy risk evaluating system
Farah et al. Leakage detection using smart water system: Combination of water balance and automated minimum night flow
Guo et al. Risk identification of third-party damage on oil and gas pipelines through the Bayesian network
Zhang et al. A probabilistic approach for safety risk analysis in metro construction
CN101488213A (en) Risk evaluation and security management decision support system for town gas pipe
CN108345976A (en) A kind of long-distance oil & gas pipeline dynamic risk appraisal procedure and device
CN102156413B (en) Emergency scheduling method and system thereof for urban multi-source raw water system
CN104537574A (en) Damage risk assessment method for oil and natural gas pipeline
CN101071098A (en) Underground steel gas pipe network pipeline corrosion prediction system
CN104200319A (en) Oil-gas pipeline construction data monitoring method based on pipeline integrity management technology
CN201242769Y (en) System for fuzzy evaluation of underground gas pipe net risk
Xu et al. Evaluation model for immersed tunnel health state: A case study of Honggu Tunnel, Jiangxi Province, China
JPH0896039A (en) Water pipeline information management device
Xiao et al. Understanding the factors and consequences of pipeline incidents: An analysis of gas transmission pipelines in the US
CN109858747B (en) Third party construction monitoring analysis method for oil and gas pipeline based on LBS and big data
KR20030067305A (en) Method of risk assessment for buried gas pipelines
Allouche Implementing quality control in HDD projects—a North American prospective
CN111861151A (en) Gas pipeline risk management and control method
Baumert et al. Real-time monitoring for quality delivery of directional drilling installations
CN105243472A (en) CAMEO based city natural gas pipe network emergency rescue system
Lopez et al. Pressure-Based Pipe Condition Assessment for Intelligent Water Network Maintenance
Rankin Pipeline integrity information integration
Lijuan et al. Leakage prediction model based on RBF neural network
Epuh et al. Application of GIS to Oil and Gas Pipeline Management (A Case Study of South-South Nigeria)
CN115168976B (en) BIM technology-based foundation pit water level visualization system and method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 510623, room 3, 2301 Linjiang Road, Guangzhou, Guangdong, Tianhe District

Co-patentee after: South China University of Technology

Patentee after: Guangzhou Gas Group Co., Ltd.

Address before: 510060, one of No. 416 East Ring Road, Guangzhou, Guangdong

Co-patentee before: South China University of Technology

Patentee before: Gas Co., Ltd. of Guangzhou City

CP03 Change of name, title or address
TR01 Transfer of patent right

Effective date of registration: 20170619

Address after: 510623, room 3, 2301 Linjiang Road, Guangzhou, Guangdong, Tianhe District

Co-patentee after: South China University of Technology

Patentee after: Guangzhou Gas Group Co., Ltd.

Address before: 510060, one of No. 416 East Ring Road, Guangzhou, Guangdong

Co-patentee before: South China University of Technology

Patentee before: Gas Co., Ltd. of Guangzhou City

TR01 Transfer of patent right
CX01 Expiry of patent term

Granted publication date: 20090520

CX01 Expiry of patent term