CN201224884Y - Anchor rod tamping system - Google Patents

Anchor rod tamping system Download PDF

Info

Publication number
CN201224884Y
CN201224884Y CNU2008200231909U CN200820023190U CN201224884Y CN 201224884 Y CN201224884 Y CN 201224884Y CN U2008200231909 U CNU2008200231909 U CN U2008200231909U CN 200820023190 U CN200820023190 U CN 200820023190U CN 201224884 Y CN201224884 Y CN 201224884Y
Authority
CN
China
Prior art keywords
anchor pole
anchor rod
construction
anchor
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008200231909U
Other languages
Chinese (zh)
Inventor
于华
王翔
孙月英
贾丽杰
张宝军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Oilfield Service Corp
Original Assignee
Shengli Engineering Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shengli Engineering Construction Group Co Ltd filed Critical Shengli Engineering Construction Group Co Ltd
Priority to CNU2008200231909U priority Critical patent/CN201224884Y/en
Application granted granted Critical
Publication of CN201224884Y publication Critical patent/CN201224884Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to an anchor rod ramming system used for the building industry, which is suitable for the retaining engineering of the anchor-drawn side slope, especially for the construction in alluvial plain formed by cohesive soil, muddy soil and silt which are quaternary recently deposited as well as in the deep and large foundation trench in the soft soil area, so as to improve the construction speed of the anchor-drawn side slope and ensure the construction quality. The anchor rod ramming system comprises a pneumatic spear, a chiseling device is arranged at the front end of the pneumatic spear, and a connecting sleeve is installed between the chiseling device and an anchor rod; a fixing handle is installed outside the shell of the pneumatic spear, and the fixing handle is connected with an anchor rod steel tube via a fixing strap. The anchor rod ramming system has the advantages of small volume, simple operation of the equipment, a great amount of saved labor force expenses; the anchor rod steel tube in the soil mass of the foundation pit and the side slope is rammed by using the system, the chiseling is continuous, the acting force is even, the construction efficiency is high, and the engineering quality is good; the speed for the anchor rod steel tube to penetrate the soil mass is high, the disturbance to the soil mass is small, and the engineering quality is ensured; and the noise pollution of the equipment is small, and the construction can be carried out in the urban areas at night.

Description

A kind of anchor pole is rammed system
Technical field
The utility model belongs to the construction equipment of prestressed anchor deep foundation pit support in the building trade, particularly a kind of anchor pole is rammed system, be applicable to that anchor draws the support engineering of side slope, be particularly useful for cohesive soil, silt and the alluvial plain of flour sand formation and the construction of similar soft clay area deep big foundation pit of recent deposit in the Quaternary Period, improve anchor and draw the speed of application of side slope, guarantee construction quality.
Background technology
At alluvial plain and similar soft soil layer that the cohesive soil that belongs to recent deposit in the Quaternary Period, silt and flour sand constitute, bury of groundwater generally is no more than 1m, carries out the deep foundation pit support engineering in such area, generally adopts the composite soil nailing wall support form.Be characterized in that cost is low, the duration short, simple and convenient, safe and reliable, the emphasis environmental protection of constructing.But there is certain limitation in composite soil nailing wall, can only be to the foundation pit construction of 6~10 meters of the supporting degree of depth, and for deep big foundation pit more than 10 meters, composite soil nailing wall is inapplicable.The urban land anxiety at the soft clay area of similar rich groundwater, keeps the hole external environment, is not allowing to cheat under the situation of outer precipitation, and the preexisting hole form of construction work of traditional prestressed anchor is difficult to realization, is prone to the hole phenomenon of collapsing.The prestressed anchor construction technology relatively is suitable for the alluvial plain engineering geological condition, but has some defectives.The prestressed anchor slurry injection technique mainly comprises operations such as anchor bolt construction, slip casing by pressure, waist rail construction and tensioning fixation, is a kind of anchoring system that pulling force is delivered to the stable soil body.Prestressed anchor is made up of a steel pipe and a screw-thread steel, and the anchoring section of steel pipe bottom is provided with slurry outlet, allows the cement paste that injects infiltrate body stratum on every side, then screw-thread steel is penetrated, and plays reinforcement effect.Go into to cause in the foundation ditch quicksand phenomenon influence hole external environment in order to control the outer underground swelling in hole, adopt to be driven into the method construction.The construction machinery employing hammer drill of anchor pole steel pipe is rammed in the job site at present, the operation sequence complexity, and volume is big, needs the number people to lift frame and equipment construction, and every complete equipment generally needs 5-7 people operation.Ram in the process greatlyyer to soil disturbance, workmanship is relatively poor, and the duration is longer, and it is low to ram efficient.The hammer drill noise is bigger, is not suitable for the city and carries on construction work at night.How to improve construction machinery, how to improve the technology of ramming, become the technical barrier of being badly in need of solution.
Summary of the invention
The purpose of this utility model provides a kind of anchor pole and rams system, improves cutter and advances machinery, improves construction speed, guarantees construction quality.
The present technique solution can reach above-mentioned purpose: a kind of anchor pole is rammed system and is comprised pneumatic lance, and the front end of pneumatic lance is the moving device of cutter, and adapter sleeve is installed between moving device of cutter and the anchor pole steel pipe; Outside pneumatic lance housing, install and fix handle, fixed handle is connected with the anchor pole steel pipe by restraint zone.
Use the utlity model has following obvious effects:
1, volume is little, and device manipulation is simple: during construction, every complete equipment only needs 2-3 people, saves a large amount of labour's spendings.If do not use handling frame, also can lift and construct, than also light many of hammer drill by two people.
2, equipment accurate positioning: pneumatic lance is supported by handling frame, and adjustable angle can be rammed into by the anchor pole gradient of design exactly.
3, efficiency of construction height, good engineering quality: in the soil body of foundation ditch, side slope, ram the anchor pole steel pipe with the utility model, the afterbody of adapter sleeve is placed in the moving device of cutter, its front end end is stuck in the body of anchor pole steel pipe, add the cooperation of restraint zone, guarantee that tamping force transmits fully, prevent the tamping force loss when pneumatic lance body rebounds, cutter is continuously moving, and active force is even.It is fast that the anchor pole steel pipe penetrates the speed of the soil body, less to soil disturbance, and workmanship is guaranteed.
4, it is simple and easy that equipment is installed connection, good sealing effect, and noise pollution is little, also can construct in city proper and night.
5, the equipment cost of pneumatic lance is low, has strong competitiveness aspect benefit, can create bigger profit margin, has significantly reduced cost of production.
Description of drawings
Fig. 1 is the structural representation of the pneumatic lance of the utility model use.
Fig. 2 is the structural representation of the utility model adapter sleeve.
Fig. 3 is installation of the present utility model, use schematic diagram.
The specific embodiment
Below in conjunction with embodiment the utility model is done further detailed description: referring to Fig. 1 and Fig. 2, a kind of anchor pole is rammed system and is comprised pneumatic lance 1, and the front end of pneumatic lance 1 is the moving device 2 of cutter, and adapter sleeve 3 is installed between moving device 2 of cutter and the anchor pole steel pipe 6.Referring to Fig. 3, outside pneumatic lance 1 housing, install and fix handle 4, by restraint zone 5 fixed handle 4 is connected with anchor pole steel pipe 6.Fixed handle 4 can weld or screwed connection in pneumatic 1 the lower housing portion of giving.Pneumatic lance 1 is supported by handling frame 8.The interior round structure of adapter sleeve 3 conforms to the contour structures of the moving device 2 of cutter, and the front end of adapter sleeve 3 is that column cooperates with the interior circle of anchor pole steel pipe 6.Because adapter sleeve 3 is big with the contact area of anchor pole steel pipe 6, the cutter of 1 pair of anchor pole steel pipe 6 of pneumatic lance is advanced effectively, effective.Handling frame 8 comprises support and channel-section steel 7; The upper surface of channel-section steel 7 is fluted, and channel-section steel 7 is fixed on the support obliquely, and its angle of inclination conforms to the angle of ramming of anchor pole steel pipe 6, and the groove of upper surface gives 1 and cooperates with pneumatic.If do not use handling frame 8, also can lift and construct, than also light many of hammer drill by two people.Body end at anchor pole steel pipe 6 is provided with radial direction through hole, is used to wear restraint zone 5.So with anchor pole steel pipe 6 and adapter sleeve 3 and pneumatic lance 1 by fixed handle 4 and restraint zone 5, connect as a wholely, be convenient to ram and guarantee that tamping force transmits fully.
During on-the-spot the use, move by following operating procedure:
1, smooth place makes work plane keep smooth, to guarantee accurate positioning.
2, the support with handling frame 8 places ground reposefully, adjusts angle, fixes channel-section steel 7.Also can do two supports that height is different, angle with ram angle and conform to, channel-section steel 7 is fixed on it.
3, anchor pole steel pipe 6 and pneumatic lance 1 and adapter sleeve 3 are placed the groove of channel-section steel 7, anchor pole steel pipe 6 front ends place the anchor pole position of having had good positioning.Install adapter sleeve 3, anchor pole steel pipe 6 and fixed handle 4 are connected, adjust and ram angle with restraint zone 5.
4, with air pressure tube air compressor machine, pneumatic lance 1 and oil foglubrication device are connected, start air compressor machine, open the oil foglubrication device, anchor pole steel pipe 6 is rammed in pneumatic lance 1 beginning continuously.
5, till anchor pole steel pipe 6 is driven into the soil body by designing requirement, close the oil foglubrication device, close air compressor machine.Carry out next step operation.

Claims (5)

1, a kind of anchor pole is rammed system, comprises pneumatic lance (1), and the front end of pneumatic lance (1) is the moving device (2) of cutter, it is characterized in that adapter sleeve (3) is installed between moving device (2) of cutter and the anchor pole steel pipe (6); Outside pneumatic lance (1) housing, install and fix handle (4), fixed handle (4) is connected with anchor pole steel pipe (6) by restraint zone (5).
2, a kind of anchor pole according to claim 1 is rammed system, it is characterized in that the interior round structure of adapter sleeve (3) conforms to the contour structures of the moving device (2) of cutter, and the front end of adapter sleeve (3) is that column cooperates with the interior circle of anchor pole steel pipe (6).
3, a kind of anchor pole according to claim 1 is rammed system, it is characterized in that the body end of anchor pole steel pipe (6) is provided with radial direction through hole.
4, a kind of anchor pole according to claim 1 is rammed system, it is characterized in that pneumatic lance (1) is supported by handling frame (8).
5, a kind of anchor pole according to claim 4 is rammed system, it is characterized in that handling frame (8) comprises support and channel-section steel (7); The upper surface of channel-section steel (7) is fluted, is fixed on obliquely on the support, and its angle of inclination conforms to the angle of ramming of anchor pole steel pipe (6), and the groove of upper surface cooperates with pneumatic giving (1).
CNU2008200231909U 2008-05-30 2008-05-30 Anchor rod tamping system Expired - Lifetime CN201224884Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200231909U CN201224884Y (en) 2008-05-30 2008-05-30 Anchor rod tamping system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200231909U CN201224884Y (en) 2008-05-30 2008-05-30 Anchor rod tamping system

Publications (1)

Publication Number Publication Date
CN201224884Y true CN201224884Y (en) 2009-04-22

Family

ID=40597770

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200231909U Expired - Lifetime CN201224884Y (en) 2008-05-30 2008-05-30 Anchor rod tamping system

Country Status (1)

Country Link
CN (1) CN201224884Y (en)

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN101122131B (en) Foundation pit supporting pile using pipe casting pile embedding in rock
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN103132908B (en) Device for drilling rock and embedding rock-socketed prestressed pipe pile by down-hole hammer and construction method of device
CN100455731C (en) Guide pit type manual pot holing pile reinforing and underpinning method for building foundation and composite supporting pile
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN111058443B (en) Precast pile composite foundation construction method for eliminating loess collapsibility
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN104329020B (en) A kind of reinforced long spire embedding rock construction equipment and technique thereof
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN108643214A (en) It is a kind of to backfill miscellaneous native composite foundation structure and its construction method
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN102995647B (en) Underground water control method used for grouting and seepage insulation of pile hole
CN113969581A (en) Construction method for rock-entering pile planting
CN105064334A (en) Construction method for cast-in-situ bored pile
CN101871218A (en) Trenchless construction method of underground station space and arc-shaped freezing pipe construction equipment thereof
CN111270665A (en) Construction method of triaxial mixing pile
CN204225100U (en) The construction equipment of concrete pile
CN103015435A (en) Long auger down hole hammer vibration rotary-jet steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN105840209A (en) Construction method for controlling deformation of anchor piles at barrel segment of tunnel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SINOPEC OILFIELD SERVICE CORPORATION

Free format text: FORMER OWNER: SHENGLI ENGINEERING CONSTRUCTION (GROUP) CORPORATION LTD. OF SHENGLI OIL FIELD

Effective date: 20150106

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 257000 DONGYING, SHANDONG PROVINCE TO: 100029 CHAOYANG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20150106

Address after: 100029 Beijing City, Chaoyang District Hui Street No. six twelfth floor

Patentee after: SINOPEC OILFIELD SERVICE CORPORATION

Address before: 257000 No. two, 755 North Road, Dongying District, Shandong, Dongying