CN201199034Y - Smoke canal heat preservation structure with reinforcing rib - Google Patents

Smoke canal heat preservation structure with reinforcing rib Download PDF

Info

Publication number
CN201199034Y
CN201199034Y CNU2008200935292U CN200820093529U CN201199034Y CN 201199034 Y CN201199034 Y CN 201199034Y CN U2008200935292 U CNU2008200935292 U CN U2008200935292U CN 200820093529 U CN200820093529 U CN 200820093529U CN 201199034 Y CN201199034 Y CN 201199034Y
Authority
CN
China
Prior art keywords
flue
reinforcing rib
insulation
heat
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008200935292U
Other languages
Chinese (zh)
Inventor
吴迅海
王韶锋
郑君国
刘现卓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Universtar Science and Technology Shenzhen Co Ltd
Original Assignee
Universtar Science and Technology Shenzhen Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Universtar Science and Technology Shenzhen Co Ltd filed Critical Universtar Science and Technology Shenzhen Co Ltd
Priority to CNU2008200935292U priority Critical patent/CN201199034Y/en
Application granted granted Critical
Publication of CN201199034Y publication Critical patent/CN201199034Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a flue heat-preservation structure with reinforcing ribs, which includes a flue shell and a rock-wool panel coated with a wire netting; the rock-wool panel is fixed on the flue shell through a self-locking board; wherein, a transverse reinforcing rib is arranged on the flue shell; an external heat-preservation layer is arranged outside the transverse reinforcing rib; and a dope with a lower emissivity is coated on the external heat-preservation layer. Compared with the prior art, the transverse reinforcing rib is arranged on the flue shell and a layer of polyurethane is coated on the outermost protection layer, thereby achieving the goals of protecting the metal protection layer of the flue from being eroded by the outside environment and preventing the heat inside the flue from radiating to the outside.

Description

A kind of flue insulation construction with reinforcing rib
Technical field:
The utility model relates to a kind of flue insulation construction, is specially a kind of flue insulation construction with reinforcing rib.
Background technology:
At present adopt traditional heat preserving mode for the insulation of flue in the engineering, promptly at the outside of pipeline parcel one deck rock wool or mineral wool as heat-insulation layer, the shape that again aluminium skin or iron sheet is pressed into pipeline is wrapped in the outside of heat-insulation layer as protective layer.The construction of this technology is simple, use also very general, but heat insulation effect usually falls flat, the development trend that incompatibility is present.
This insulation construction also exists a big defective in addition; because the protective layer of its outside is a metal level; its thermal conductivity factor is big; rapid with the heat exchange in the environment, the environment that scatters and disappears soon for the heat of coming, form thermal balance with external environment from heat-insulation layer conduction; particularly higher for flue temperature; this heat conduction is inevitable, and at cold district, this situation is just more outstanding.Metallic insulation also is vulnerable to the acid rain, ultraviolet radiation in the environment etc. and destroys and produce corrosion, and the heat conduction and the etching problem that therefore solve external protection become particularly important.
Summary of the invention:
For heat conduction and the etching problem that solves owing to the flue external protection makes heat insulation effect not reach the problem of expection, the purpose of this utility model is to provide the insulation construction of flue in a kind of flue gas desulfurization technique.
For achieving the above object, the utility model adopts following technical scheme:
A kind of flue insulation construction with reinforcing rib, comprise flue housing and the rock cotton board that is enclosed with wire netting, described rock cotton board is fixed on the flue housing by the self-locking plate, wherein the flue housing is provided with horizontal reinforcement ribs, described horizontal reinforcement ribs is outside equipped with external thermal insulation, scribbles the coating of low-launch-rate on the described external thermal insulation.
Described coating is preferably polyurethane coating.
Described external thermal insulation is a metallic insulation.
The described external thermal insulation top water gradient of setting up defences.
The utility model is on the basis of existing insulation construction; be provided with horizontal reinforcement ribs on the flue housing and brushing one deck polyurethane on the outermost layer protective layer; thereby the coat of metal that reaches the protection flue is avoided the erosion of external environment, the purpose that the heat of prevention flue inside is outwards dispersed.
Description of drawings:
Fig. 1 is the generalized section of the utility model flue structure.
Identifier declaration among the figure: flue housing 1, wire netting 2, rock cotton board 3, bar for line 4, self-locking plate 5, horizontal reinforcement ribs 6, external thermal insulation 7, coating 8.
The specific embodiment:
Core concept of the present utility model is: lay rock cotton board on the flue housing, with wire netting rock cotton board is wrapped up then, and be fixed on the flue housing, as heat-insulation layer by self-locking plate and bar for line.And then outside heat-insulation layer, lay outside the metal and protect, and pass through the polyurethane coating of spraying or brushing low-launch-rate on outside metal, protecting, thus reach the erosion that the coat of metal of protecting flue is avoided external environment, the purpose that the heat of prevention flue inside is outwards dispersed.
For setting forth thought of the present utility model and purpose, the utility model is described further below in conjunction with the drawings and specific embodiments.
See also shown in Figure 1, the utility model is the insulation construction of flue in a kind of flue gas desulfurization technique, the rock cotton board 3 that it mainly comprises flue housing 1 and is enclosed with wire netting 2, described rock cotton board 3 is fixedly mounted on the flue housing 1 by self-locking plate 5 and bar for line 4, wherein flue housing 1 is provided with horizontal reinforcement ribs 6, described horizontal reinforcement ribs 6 is outside equipped with outer metallic insulation 7, scribbles the polyurethane coating 8 of low-launch-rate on the described outer metallic insulation.
In addition, in order to prevent to form ponding on the outer metallic insulation 7, the top of outside metal, the protecting water gradient of also setting up defences.
The utility model is that brushing one deck polyurethane on the outermost layer protective layer, this coating both can protect the coat of metal of flue to avoid the erosion of external environment on the basis of existing insulation construction, can stop inner heat outwards to be dispersed again.
More than a kind of flue insulation construction with reinforcing rib provided by the utility model is described in detail, used specific case herein principle of the present utility model and embodiment are set forth, the explanation of above embodiment just is used for helping to understand method of the present utility model and core concept thereof; Simultaneously, for one of ordinary skill in the art, according to thought of the present utility model, the part that all can change in specific embodiments and applications, in sum, this description should not be construed as restriction of the present utility model.

Claims (4)

1. flue insulation construction with reinforcing rib, comprise flue housing (1) and be enclosed with the rock cotton board (3) of wire netting (2), described rock cotton board (3) is fixed on the flue housing (1) by self-locking plate (5), it is characterized in that: flue housing (1) is provided with horizontal reinforcement ribs (6), described horizontal reinforcement ribs (6) is outside equipped with external thermal insulation (7), scribbles the coating (8) of low-launch-rate on the described external thermal insulation (7).
2. the flue insulation construction of band reinforcing rib according to claim 1 is characterized in that: described coating (8) is preferably polyurethane coating.
3. the flue insulation construction of band reinforcing rib according to claim 1 is characterized in that: described external thermal insulation (7) is a metallic insulation.
4. the flue insulation construction of band reinforcing rib according to claim 1 is characterized in that: described external thermal insulation (7) the top water gradient of setting up defences.
CNU2008200935292U 2008-04-22 2008-04-22 Smoke canal heat preservation structure with reinforcing rib Expired - Lifetime CN201199034Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200935292U CN201199034Y (en) 2008-04-22 2008-04-22 Smoke canal heat preservation structure with reinforcing rib

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200935292U CN201199034Y (en) 2008-04-22 2008-04-22 Smoke canal heat preservation structure with reinforcing rib

Publications (1)

Publication Number Publication Date
CN201199034Y true CN201199034Y (en) 2009-02-25

Family

ID=40450190

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200935292U Expired - Lifetime CN201199034Y (en) 2008-04-22 2008-04-22 Smoke canal heat preservation structure with reinforcing rib

Country Status (1)

Country Link
CN (1) CN201199034Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102042753A (en) * 2010-12-22 2011-05-04 本钢板材股份有限公司 Tunnel furnace flue and making method thereof
CN102784558A (en) * 2012-08-17 2012-11-21 中国大唐集团环境技术有限公司 Denitrating reactor with shell of dual-layer steel plate structure
CN107965624A (en) * 2017-11-22 2018-04-27 广州正德工业工程技术有限公司 Lithium battery film applicator air hose prepares and mounting process

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102042753A (en) * 2010-12-22 2011-05-04 本钢板材股份有限公司 Tunnel furnace flue and making method thereof
CN102784558A (en) * 2012-08-17 2012-11-21 中国大唐集团环境技术有限公司 Denitrating reactor with shell of dual-layer steel plate structure
CN102784558B (en) * 2012-08-17 2014-10-01 中国大唐集团环境技术有限公司 Denitrating reactor with shell of dual-layer steel plate structure
CN107965624A (en) * 2017-11-22 2018-04-27 广州正德工业工程技术有限公司 Lithium battery film applicator air hose prepares and mounting process

Similar Documents

Publication Publication Date Title
CN202327524U (en) Overhead steam conveying pipeline
CN201199034Y (en) Smoke canal heat preservation structure with reinforcing rib
CN202327525U (en) Overhead steam conveying pipeline
CN204507741U (en) The attemperator of salt storage tank
CN205037030U (en) Pipeline insulation construction
CN204717239U (en) A kind of modified phenolic foam thermal insulation pipe
CN207893322U (en) A kind of heat insualtion structure for heat power pipe net
CN102865433A (en) Composite type polyurethane heat preservation pipe
CN215721396U (en) Corrosion-resistant rubber pipe
CN203336149U (en) Pipeline flange heat preservation structure
CN105715910A (en) Method for controlling corrosion of pipeline under insulating layer
CN201866408U (en) Groove type fireproof cable bridge
CN112373140A (en) Novel high-flame-retardant heat-insulating material
CN209180577U (en) A kind of Multifunctional cover steel pipe heat-insulation support structure
CN203115397U (en) Direct-buried steam conveying pipeline
CN209744973U (en) Heat preservation structure of rotary kiln cooling system manger plate cover
CN206626330U (en) A kind of direct built-in rainhat
CN208396058U (en) A kind of external wall that high intensity is freeze proof
CN202852213U (en) Light environment-friendly type insulating glass cotton pipe
CN213333102U (en) Heat insulation structure suitable for FBT series rare earth composite heat insulation material
CN218020547U (en) Pipeline heat insulation protective sleeve
JP6448771B2 (en) Twisted tube heat exchanger
CN109140060A (en) A kind of polyurethane thermal pipe
CN213117809U (en) Heat supply pipeline with safety protection
CN220286742U (en) Corrosion-resistant natural gas conveying device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20090225