CN201132955Y - Synchronized static pressure grouting precast pile device - Google Patents

Synchronized static pressure grouting precast pile device Download PDF

Info

Publication number
CN201132955Y
CN201132955Y CNU2007201381913U CN200720138191U CN201132955Y CN 201132955 Y CN201132955 Y CN 201132955Y CN U2007201381913 U CNU2007201381913 U CN U2007201381913U CN 200720138191 U CN200720138191 U CN 200720138191U CN 201132955 Y CN201132955 Y CN 201132955Y
Authority
CN
China
Prior art keywords
pile
grouting
pipe
stake
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007201381913U
Other languages
Chinese (zh)
Inventor
李建军
梁仁旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North University of China
Original Assignee
North University of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North University of China filed Critical North University of China
Priority to CNU2007201381913U priority Critical patent/CN201132955Y/en
Application granted granted Critical
Publication of CN201132955Y publication Critical patent/CN201132955Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a pile-sinking device for a synchronous grouting static precast pile and belongs to the technical field of precast reinforced concrete piles in the field of construction. The pile-sinking device has the main technical characteristics that a definite length is reserved at the lower end of the precast pile, the lower end forms a grouting hole on the pile tip conical wall through a grout-guiding forked pipe 3, the outlet of the grouting hole faces upwards and presents an angle of 20 to 25 degrees with the level plane, the grout-guiding forked pipe is evenly and symmetrically distributed in the pile tip plane and the pile tip cone angle is 60 degrees. The pile-sinking device for a synchronous grouting static precast pile can achieve a continuous grouting to the pile side and the pile tip, the operation is simple and convenient and the grouting hole is hard to block, enabling the grouting to be carried out smoothly in different pile-sinking stages. During the process of pile sinking, the grout can be distributed between the pile tip and the soil around the pile to form a thin slurry film around the pile. When the pile reaches a designed depth, an expanded head wrapping the pile tip is formed at the pile end. The pile-sinking device for a synchronous grouting static precast pile expands the applied range of a static pile, reduces the construction cost and is applicable to loess, hard silty clay, hard silt, powdered fine sand and hardpan layers.

Description

Synchronous grouting Static Pressure Precast Piles device
Technical field
The utility model belongs to building field precast reinforced concrete piles technical field.
Technical background
Precast reinforced concrete piles and silent piling method thereof because of its noiseless, friction, speed of application is fast, pile quality is reliable, in China's soft clay area multistory building and highrise building, be applied comparatively widely, in recent years, along with in northern area is applied, find that static pressed pile is difficult to pass through intermediate gauge layer of sand and the hardpan in the mutual sedimentary facies in lake, river, pile driving pressure hour, stake presses not go down, increase pile driving pressure, pile body fractures easily; Adopt auxiliary pile sinking method such as bath method and soil digging method commonly used at present, reduced the compacted effect of static pressed pile again; When the stake end entered the layer of sand bearing stratum, because of " reinforcement " and " relaxing " effect of layer of sand, pressurization made end resistance very high, and after the unloading, end resistance decreases, and this brings the unstable and wayward two large problems of construction quality of bearing capacity.
In order to overcome an above-mentioned difficult problem, adopted the different sharp structures of stake, improve the pile sinking quality by improving the sharp grouting process of stake.
Publication number be CN1143137A patent disclosure the precast reinforced concrete piles end annotate the oar method, adopt the stake point to have only a downward injected hole, lead the slurry pipe and be positioned at the preformed pile tube wall.Publication number be CN1335434A patent disclosure high-pressure mortar spraying deposition process of prefabricated steel bar reinforced concrete pile, stake point be configured to heavy wall tubulose steel pipe gunite gun, head closed circular taper is opened some gunniting holes on the tube wall.The big grouting pressure of the notes oar pressure that said method adopts, gunniting hole is blocked easily.
The utility model content
The purpose of this utility model provides a kind of synchronous grouting Static Pressure Precast Piles pile sinking device, reduces the pile press tonnage, improves efficiency of construction, thereby has enlarged the range of application of static pressed pile, reduces construction costs.
The utility model is achieved in that synchronous grouting Static Pressure Precast Piles device, the lower end spud pile point 2 of preformed pile 1, grouting pipe 13 is positioned at preformed pile 1, grouting pipe 13 upper ends connect grouting pressure table 9 successively, grouting pump 10, circulating tank 11 and slurries mixer 12, Grouting Pipe 8 is arranged in grouting pipe 13, it is characterized in that: certain length in reserve is arranged in the preformed pile lower end, the lower end forms injected hole by leading slurry bifurcated pipe 3 at stake pointed cone wall, the injected hole outlet is upwards horizontal by 20 °~25 ° angles, lead the slurry bifurcated pipe and distribute symmetrically in stake point plane, stake pointed cone angle is 60 °.
Lead slurry pipe 13 or be positioned at preformed pile tube wall center, or be positioned at the preformed pile tube wall.
The structure of stake point can be that the rectangular pyramid shape is provided with 4 slip casting bifurcated pipes 3, and 4 injected holes 4 are arranged.
The structure of stake point can also be a cone shape, and 3 slip casting bifurcated pipes 3 are set, and 3 injected holes 4 are arranged.
The utility model synchronous grouting Static Pressure Precast Piles device, stake point can be realized a side and the continuous slip casting of stake end for the make progress concrete pile point of injected hole of sidewall band opening, and is simple to operation, and be difficult for blocking injected hole, make slip casting be able to smooth implementation in the pile sinking different phase.In the stake sinking process, slurries can be evenly distributed between stake and all soil of stake, make and can form a mud film week.After stake arrives projected depth, make the stake end can form the enlarged footing of parcel stake point.The utility model has enlarged the range of application of static pressed pile, has reduced construction costs, is fit to loess, hard silty clay, hard silt, and powder fine sand, sandy gravel stratum use.
Description of drawings:
Fig. 1 is a synchronous grouting Static Pressure Precast Piles apparatus structure schematic diagram,
Fig. 2 is the structural representation of another embodiment of synchronous grouting Static Pressure Precast Piles device
Fig. 3 is that the sharp structural representation of slurry stake is led at the center,
Fig. 4 is that slurry rectangular pyramid body stake point A-A sectional structure schematic diagram is led at the center,
Fig. 5 is that slurry cone stake point A-A plan structure schematic diagram is led at the center,
Fig. 6 is that tube wall is led the sharp side-looking structural representation of slurry stake,
Fig. 7 is the vertical view of Fig. 6.
Specific implementation method
Be described further below in conjunction with accompanying drawing.1-preformed pile among the figure, 2-stake point, 3-slip casting bifurcated pipe, 4-injected hole, 5-stirrup, 6-longitudinal reinforcement, 7-stake point slip casting sleeve pipe, 8-Grouting Pipe, 9-grouting pressure table, 10-grouting pump, 11-circulating tank, 12-slurries mixer, 13-grouting pipe.
Embodiment 1:
With reference to accompanying drawing 1, Fig. 3 and Fig. 4, synchronous grouting Static Pressure Precast Piles device is made of preformed pile 1, stake point 2, grouting pipe 13, the sharp slip casting sleeve pipe 7 of stake, slip casting bifurcated pipe 3, injected hole 4, Grouting Pipe 8, grouting pressure table 9, grouting pump 10, circulating tank 11, slurries mixer 12, leads slurry pipe 13 or is positioned at preformed pile tube wall center.
Grouting pipe 13 can adopt steel pipe or withstand voltage pvc pipe, at the preformed pile two ends certain length in reserve is arranged, and the upper end connects grouting pressure table 9, grouting pump 10, circulating tank 11 and slurries mixer 12 successively.The lower end forms injected hole by leading slurry bifurcated pipe 3 at stake pointed cone wall, the injected hole outlet is upwards horizontal by 20 °~25 ° angles, lead the slurry bifurcated pipe and adopt 6 ' steel pipe, in stake point plane, distribute symmetrically, cast in cone angle and be in 60 ° the concrete precast pile point, precast pile tip will be complementary with stake footpath and profile.The structure of stake point is the rectangular pyramid shape, and 4 slip casting bifurcated pipes 3 are set, and 4 injected holes 4 are arranged.
Embodiment 2:
With reference to accompanying drawing 2, Fig. 6 and Fig. 7, grouting pipe 13 is embedded in the tube wall of prefabricated concrete pipe pile, adopts 6 ' steel pipe, can contemporary longitudinal reinforcement for preformed pile.Three grouting pipe are equilateral triangle and arrange in the slip casting tube wall, certain-length is reserved at two ends, three conduits of a side at the stake end meet at a bit to the bending of the tube wall center of circle simultaneously, spot-welded together, then conduit is continued to be bent upwards to offside, the injected hole outlet is upwards horizontal by 20 °~25 ° angles, and it is the precast pile tip at 60 ° of angles that casting concrete forms cone angle.
The structure of stake point is a cone shape, and 3 slip casting bifurcated pipes 3 are set, and 3 injected holes 4 are arranged.

Claims (4)

1, synchronous grouting Static Pressure Precast Piles device, the lower end spud pile point (2) of preformed pile (1), grouting pipe (13) is positioned at preformed pile (1), grouting pipe (13) upper end connects grouting pressure table (9) successively, grouting pump (10), circulating tank (11) and slurries mixer (12), Grouting Pipe (8) is arranged in grouting pipe (13), it is characterized in that: certain length in reserve is arranged in preformed pile (1) lower end, the lower end forms injected hole (4) by leading slurry bifurcated pipe (3) at stake pointed cone wall, injected hole (4) (4) outlet makes progress and 20 °~25 ° angles of horizontal plane, lead slurry bifurcated pipe (3) and distribute symmetrically in stake point plane, stake pointed cone angle is 60 °.
2, according to the described synchronous grouting Static Pressure Precast Piles of claim 1 pile sinking device, it is characterized in that: lead slurry pipe (13) or be positioned at preformed pile tube wall center, or be positioned at the preformed pile tube wall.
3, according to the described synchronous grouting Static Pressure Precast Piles of claim 1 pile sinking device, it is characterized in that: the structure of stake point has 4 injected holes (4) for the rectangular pyramid shape is provided with 4 slip casting bifurcated pipes (3).
4, according to the described synchronous grouting Static Pressure Precast Piles of claim 1 pile sinking device, it is characterized in that: the structure of stake point is a cone shape, and 3 slip casting bifurcated pipes (3) are set, and 3 injected holes (4) are arranged.
CNU2007201381913U 2007-12-05 2007-12-05 Synchronized static pressure grouting precast pile device Expired - Fee Related CN201132955Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201381913U CN201132955Y (en) 2007-12-05 2007-12-05 Synchronized static pressure grouting precast pile device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201381913U CN201132955Y (en) 2007-12-05 2007-12-05 Synchronized static pressure grouting precast pile device

Publications (1)

Publication Number Publication Date
CN201132955Y true CN201132955Y (en) 2008-10-15

Family

ID=40061228

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201381913U Expired - Fee Related CN201132955Y (en) 2007-12-05 2007-12-05 Synchronized static pressure grouting precast pile device

Country Status (1)

Country Link
CN (1) CN201132955Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660946A (en) * 2012-05-31 2012-09-12 福州市第三建筑工程公司 Grouting pile head of tubular pile and application method thereof
CN102888836A (en) * 2012-06-05 2013-01-23 江苏兴厦建筑安装有限公司 Prefabricated reinforced concrete square pile
CN103015423A (en) * 2012-12-21 2013-04-03 广东永基建筑基础有限公司 Static pressure jet flow piling wall forming equipment and static pressure jet flow piling wall forming construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660946A (en) * 2012-05-31 2012-09-12 福州市第三建筑工程公司 Grouting pile head of tubular pile and application method thereof
CN102660946B (en) * 2012-05-31 2015-02-11 福州市第三建筑工程公司 Grouting pile head of tubular pile and application method thereof
CN102888836A (en) * 2012-06-05 2013-01-23 江苏兴厦建筑安装有限公司 Prefabricated reinforced concrete square pile
CN102888836B (en) * 2012-06-05 2013-11-06 江苏兴厦建筑安装有限公司 Prefabricated reinforced concrete square pile
CN103015423A (en) * 2012-12-21 2013-04-03 广东永基建筑基础有限公司 Static pressure jet flow piling wall forming equipment and static pressure jet flow piling wall forming construction method

Similar Documents

Publication Publication Date Title
CN100519953C (en) Pile sinking method of synchronization grouting static pressure precast pile
CN100462507C (en) Construction method for pulling-resistant and pressure-resistant slip casting pipe pile
CN101812843B (en) Centre grouted poured post-grouting pile construction methods, and grouter and grout injector used thereby
CN103184734A (en) Implanted and grouted compound pile and construction method
CN100532733C (en) Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer
CN104141305A (en) Multi-layer spiral blade self-drilling-type soil anchor rod and constructing method thereof
CN113431490B (en) Large-diameter tubular pile construction equipment and method for karst area
CN104314076B (en) A kind of soft foundation recoverable prestressed anchor Cable Structure and construction method
CN105256795A (en) End support type thread core composite pile and construction device and method for end support type thread core composite pile
CN203213101U (en) Embedding grouting combined pile
CN112726574A (en) Open steel pipe pile utilizing soil plug effect and construction method thereof
CN101307599B (en) Prefabricated hollow pile sinking method
CN204174618U (en) Soft foundation recoverable prestressed anchor Cable Structure
CN201132955Y (en) Synchronized static pressure grouting precast pile device
CN101701459B (en) Method for processing soft soil foundation of intertidal belt to form construction working face
CN202187340U (en) Socketed pile with concrete-filled steel tube core column
CN207659986U (en) A kind of building or structures foundation stabilization underpin pier
GB2609841A (en) Monopile foundation using cemented vibroflotation pile to reinforce soft soil foundation for use in offshore wind power generation, and construction method
CN101603311B (en) Jet grouting pile construction method adopting heavy hammer-tamping compaction soil preformed hole
CN201459749U (en) Stable structure for construction platform of deep water steel pipe pile
CN203129143U (en) Static pressure jet flow piling wall forming equipment
CN205062809U (en) End support type screw thread core composite pile
CN203866821U (en) Lead hole implant cloth bag gravel grouting pile
CN201334662Y (en) Integrated long-spiral drilling tool for jet-grouting branch pile
CN208668417U (en) A kind of steel sheet pile inserting piling auxiliary water shovel structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081015

Termination date: 20100105