CN201087402Y - 高承载力灌注桩 - Google Patents

高承载力灌注桩 Download PDF

Info

Publication number
CN201087402Y
CN201087402Y CNU2007200148875U CN200720014887U CN201087402Y CN 201087402 Y CN201087402 Y CN 201087402Y CN U2007200148875 U CNU2007200148875 U CN U2007200148875U CN 200720014887 U CN200720014887 U CN 200720014887U CN 201087402 Y CN201087402 Y CN 201087402Y
Authority
CN
China
Prior art keywords
cast
pile body
pile
hypomere
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200148875U
Other languages
English (en)
Inventor
郑新俊
吴伟林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2007200148875U priority Critical patent/CN201087402Y/zh
Application granted granted Critical
Publication of CN201087402Y publication Critical patent/CN201087402Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本实用新型涉及一种建筑基础中使用的高承载力灌注桩。其结构为:上段设置为钢管,钢管内部设有混凝土,下段现浇桩身内设有下段桩身上插筋和下段桩身下插筋,下段桩身下插筋穿过现浇底座钉入硬土层,上现浇砼底座将上段钢管和下段现浇桩身连成一体,下段现浇桩身的下端设有现浇砼底座。它提高了单桩的承载力、抗冲击力和材料强度的利用率,同时适用范围广,降低了成本。

Description

高承载力灌注桩
技术领域
本实用新型涉及一种建筑基础中使用的扩底桩,特别是涉及一种适合高层建筑用的高承载力灌注桩。
背景技术
目前在地基的桩基工程中,通常采用沉管灌注桩、预制桩和大直径钻孔灌注桩三种。其中大直径钻孔灌注桩承载力最高,但其造价昂贵、工效低,而且施工时污染严重,所以只用于高层建筑及承载力要求高的建筑。预制桩的质量好、承载力也较高,但其造价也高,一般用于安全等级较高的建筑。按承受力情况分类所述的三种桩均属摩擦桩。其中应用最为广泛的是灌注桩,约占各类桩总数量的50%,但是由于地壳形成的土质年代不同,软土地基随地壳层深度的增加通常软、硬土层呈交替状态,在连续打桩施工时,在后的施桩会对土层产生挤压,就会影响到在先灌注而尚未完全凝固的桩,尤其在软土层与硬土层的交界处尤其严重,往往出现断桩、缩颈现象,从而导致沉管灌注桩的质量达不到要求,致使下桩密布,引起土体严重变形,甚至危及桩身的质量;该桩的另一个缺点是承载力低,为增大承载力,一般采用在灌砼浇注桩身后加压扩底的办法,但因其利用加压扩底方式使其形状大小不确定和规范,使其应用受到局限。同时,现有技术中的桩身在使用过程中存在着承载力和抗冲击力较弱的问题,操作使用繁琐,成本高。
实用新型内容
本实用新型针对现有技术存在的问题,提供一种适用范围广通用性强,可明显提高材料强度利用率,单桩承载力高的高承载力灌注桩,解决了桩身在使用过程中承载力和抗冲击力较弱的问题,而且操作使用方便,降低了成本。
本实用新型解决技术问题所采用的技术方案是:上段设置为钢管,钢管内部设置混凝土,下段现浇桩身内设有下段桩身上插筋和下段桩身下插筋,下段桩身下插筋穿过现浇底座钉入硬土层,上现浇砼底座将上段钢管和下段现浇桩身连成一体,下段现浇桩身的下端设有现浇砼底座。
所述的现浇砼底座和上现浇砼底座的中心与上段钢管和下段现浇桩身的中心在同一轴线上。
本实用新型与现有技术相比,提高了单桩的承载力、抗冲击力和材料强度的利用率,容易达到设计的预期效果,更好地满足建筑工程的需要,同时适用范围广。
附图说明
图1是本实用新型高承载力灌注桩的结构示意图。
图中:1、现浇砼底座;2、上现浇砼底座;3、下段现浇桩身;4、上段钢管;5、下段桩身下插筋;7、下段桩身上插筋;8、混凝土。
具体实施方式
本实用新型的实施例结合附图加以详细描述,但本实用新型的保护范围不受实施例所限。
如图1所示的是本实用新型结构示意图,上段设置为钢管4,钢管4内部设有混凝土8,下段现浇桩身3内设有下段桩身上插筋7和下段桩身下插筋5,下段桩身下插筋5穿过现浇底座1钉入硬土层,上现浇砼底座2将上段钢管4和下段现浇桩身3连成一体,下段现浇桩身3的下端设有现浇砼底座1。现浇砼底座1和上现浇砼底座2的中心与上段钢管4和下段现浇桩身3的中心在同一轴线上。本实施例的施工方法可以按照常规工艺进行施工。

Claims (2)

1.一种高承载力灌注桩,其特征在于结构如下:上段设置为钢管(4),钢管(4)内部设有混凝土(8),下段现浇桩身(3)内设有下段桩身上插筋(7)和下段桩身下插筋(5),下段桩身下插筋(5)穿过现浇底座(1)钉入硬土层,上现浇砼底座(2)将上段钢管(4)和下段现浇桩身(3)连成一体,下段现浇桩身(3)的下端设有现浇砼底座(1)。
2.根据权利要求1所述的高承载力灌注桩,其特征在于所述的现浇砼底座(1)和上现浇砼底座(2)的中心与上段钢管(4)和下段现浇桩身(3)的中心在同一轴线上。
CNU2007200148875U 2007-09-29 2007-09-29 高承载力灌注桩 Expired - Fee Related CN201087402Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200148875U CN201087402Y (zh) 2007-09-29 2007-09-29 高承载力灌注桩

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200148875U CN201087402Y (zh) 2007-09-29 2007-09-29 高承载力灌注桩

Publications (1)

Publication Number Publication Date
CN201087402Y true CN201087402Y (zh) 2008-07-16

Family

ID=39634996

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200148875U Expired - Fee Related CN201087402Y (zh) 2007-09-29 2007-09-29 高承载力灌注桩

Country Status (1)

Country Link
CN (1) CN201087402Y (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10100486B2 (en) 2014-03-28 2018-10-16 Public Joint Stock Company “Transneft” Method for installing overhead transmission line supports on permafrost soils
US10443207B2 (en) 2014-03-28 2019-10-15 Public Joint Stock Company “Transneft” Pile foundations for supporting power transmission towers

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10100486B2 (en) 2014-03-28 2018-10-16 Public Joint Stock Company “Transneft” Method for installing overhead transmission line supports on permafrost soils
US10443207B2 (en) 2014-03-28 2019-10-15 Public Joint Stock Company “Transneft” Pile foundations for supporting power transmission towers

Similar Documents

Publication Publication Date Title
CN201087402Y (zh) 高承载力灌注桩
CN201137068Y (zh) 高层建筑用抗冲击力沉管灌注桩
CN200955146Y (zh) 多级沉管灌注桩
CN201087401Y (zh) 抗冲击力建筑基础灌注桩
CN201137072Y (zh) 高承载力灌注桩
CN201137064Y (zh) 抗冲击力建筑基础灌注桩
CN201087357Y (zh) 高承载力灌注桩
CN201087413Y (zh) 灌注桩
CN201087414Y (zh) 高层建筑沉管灌注桩
CN201137066Y (zh) 高承载力灌注桩
CN200955147Y (zh) 高层建筑沉管灌注桩
CN201087354Y (zh) 抗冲击力沉管灌注桩
CN201137067Y (zh) 高承载力多级沉管灌注桩
CN201087358Y (zh) 高层建筑用抗冲击力沉管灌注桩
CN201087356Y (zh) 抗冲击力建筑基础灌注桩
CN201087352Y (zh) 高承载力多级沉管灌注桩
CN201137085Y (zh) 多级沉管灌注桩
CN201137073Y (zh) 抗冲击力建筑基础灌注桩
CN201087355Y (zh) 沉管灌注桩
CN201087380Y (zh) 建筑基础灌注桩
CN201137099Y (zh) 抗冲击力沉管灌注桩
CN201089902Y (zh) 沉管灌注扩底桩
CN201137098Y (zh) 灌注桩
CN201137100Y (zh) 高层建筑沉管灌注桩
CN201087353Y (zh) 多级沉管灌注桩

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee