CN201074823Y - Energetic flue gas pulse sootblowing device - Google Patents

Energetic flue gas pulse sootblowing device Download PDF

Info

Publication number
CN201074823Y
CN201074823Y CNU2007200134393U CN200720013439U CN201074823Y CN 201074823 Y CN201074823 Y CN 201074823Y CN U2007200134393 U CNU2007200134393 U CN U2007200134393U CN 200720013439 U CN200720013439 U CN 200720013439U CN 201074823 Y CN201074823 Y CN 201074823Y
Authority
CN
China
Prior art keywords
gas
chamber
acetylene gas
air
pulse generator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200134393U
Other languages
Chinese (zh)
Inventor
程永明
程强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENG YONGMING CHENG QIANG
Original Assignee
CHENG YONGMING CHENG QIANG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENG YONGMING CHENG QIANG filed Critical CHENG YONGMING CHENG QIANG
Priority to CNU2007200134393U priority Critical patent/CN201074823Y/en
Application granted granted Critical
Publication of CN201074823Y publication Critical patent/CN201074823Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

The utility model relates to a high power sootblower with gas pulse which is used for a boiler and a wet steam generator, which comprises an accelerating pulse generator, acetylene gas and air supply system, wherein the upper portion of the accelerating pulse generator is a gas mixing chamber, the lower portion of the accelerating pulse generator is an exploding burning chamber, the lower end of the exploding burning chamber is welded with a gas mixing conduit, and the front end of the conduit is provided with a pulse nozzle of an accelerator. One lateral of the gas mixing chamber is welded with a mixing igniting pipe, the other end is provided with a high pressure igniting transformer, the lower end of the gas mixing chamber is connected with a gas mixing combustion chamber which is arranged on the one lateral of the exploding burning chamber, and a high press gas igniting gun is arranged in the gas mixing combustion chamber. The utility model has reasonable design, novel structure and reliable operation, the deashing effect of a boiler and a gas filling boiler can be greatly increased by using the utility model, and the utility model is beneficial to energy saving and consumption reducing and the normal effective operation of a boiler.

Description

High-energy Gas Pulse Sootblowers
Technical field:
The utility model relates to a kind of deashing device that is used for boiler and oil field special wet steam generator.
Background technology:
Boiler is in running, and fouling of heating surface, coking are modal phenomenons, influences the heat transference efficiency of heating surface, weakens the heat exchange between flue gas and working medium, and exhaust gas temperature is raise, and boiler thermal output reduces.Boiler operatiopn certainly leads to dust stratification, yet owing to structural reason causes soot blower operation undesired and to blow grey effect bad, is the high principal element of present exhaust gas temperature, is unfavorable for the raising of energy-saving and cost-reducing and economic benefit.
Novel content:
The purpose of this utility model be to provide a kind of ash-removal effect good, can improve boiler and be subjected to the High-energy Gas Pulse Sootblowers of heat carrier efficient, energy savings.
The utility model is to realize like this.This kind soot blower comprises acceleration pulse generator, air and acetylene gas feed system three parts, and wherein the acceleration pulse generator is made up of gas mixer chamber, detonation chamber, gain plate, mist conduit, mixing point fire tube, high-voltage ignition transformer, mist pilot chamber, mist conduit, acceleration pulse nozzle; The acetylene gas feed system is made up of acetylene gas bottle, acetylene gas control valve, acetylene gas motor-driven valve, acetylene gas distributor, tube connector, Pressure gauge; Air supply system is made up of air magnetic valve, through type floating ball valve, air bleeding valve, air hydrops separator, Pressure gauge.Acceleration pulse generator top is gas mixer chamber, and the bottom is the detonation chamber, and the centre is provided with the gain plate, and lower end, detonation chamber is welded with the mist conduit, and catheter proximal end is provided with the accelerator pulse nozzle; Gas mixer chamber one side is welded with the mixing point fire tube by the mist conduit, and the one side is provided with high-voltage ignition transformer, and the lower end is connected with the mist pilot chamber of detonation chamber one side, is provided with the high energy gas burning torch in the mist pilot chamber.Acetylene gas bottle is connected with acetylene gas hydrops jar by tube connector in the acetylene gas feed system, and the acetylene gas flow container is connected with the mixing point fire tube of acceleration pulse generator by the tube connector which is provided with acetylene gas motor-driven valve and control valve.The air supply system inlet connects air blast and comes tracheae, takes over by the tube connector which is provided with air magnetic valve and through type floating ball valve to be connected with the mixing point fire tube of air hydrops separator and acceleration pulse generator respectively.During work, a plurality of these devices are installed in boiler respectively or injection boiler is on the wet steam generator afterbody convection bank heating surface, be connected with the convection bank outer panel, the accelerator pulse nozzle extends in the convection bank side plate, and it is angled with the deflection plate that is arranged in the heat-insulation layer, this device will enter fuel gas (acetylene or the natural gas of acceleration pulse generator from tube connector respectively, liquefied gas) and air mix in the proper ratio, automatically igniting, the moment detonation, produce the shock wave of certain energy, pass through gas explosion, detonation, sound wave, gain, excite, rapping, the baffling impact of air-flow and the acting in conjunction of sound wave heat energy, act on the dust stratification surface repeatedly, dust stratification or black dirt are shot down, thereby strengthen ash-removal effect, reach the purpose that improves boiler and be subjected to heat carrier efficient and save the energy.
The utility model is reasonable in design, novel structure, and reliable operation utilizes it can improve boiler, injection boiler ash-removal effect greatly, helps the operation normally and efficiently of energy-saving and cost-reducing and boiler.
Description of drawings:
Accompanying drawing is a general structure schematic diagram of the present utility model.
The specific embodiment:
Accompanying drawing is embodiments of the invention.
As shown in the figure, the utility model comes tracheae 20, air magnetic valve 21, through type floating ball valve 23, air bleeding valve 24, air hydrops separator 25 to form by acceleration pulse generator 1, gas mixer chamber 2, gain plate 3, detonation chamber 4, mist conduit 5,10, mixing point fire tube 6, high-voltage ignition transformer 7, high energy gas burning torch 8, mist pilot chamber 9, acceleration pulse nozzle 11, deflection plate 12, Pressure gauge 13,26, tube connector 14,22, acetylene gas distributor 15, acetylene gas control valve 16, acetylene gas motor-driven valve 17, acetylene gas bottle 18, air blast; Its connection, assembled relation are as follows: acceleration pulse generator 1 top is gas mixer chamber 2, and the bottom is detonation chamber 4, and the centre is provided with gain plate 3, and 4 lower ends, detonation chamber are welded with mist conduit 10, and conduit 10 front ends are welded with accelerator pulse nozzle 11; Gas mixer chamber 2 one sides are welded with mixing point fire tube 6 by mist conduit 8, and the one side is provided with high-voltage ignition transformer 7, and the lower end is connected with the mist pilot chamber 9 of detonation chamber 4 one sides, is provided with high energy gas burning torch 8 in the mist pilot chamber 9; Acetylene gas bottle 18 is connected with acetylene gas hydrops jar 15 by tube connector, and acetylene gas hydrops hydrops jar 15 is connected with the mixing point fire tube 6 of acceleration pulse generator 1 by the tube connector which is provided with acetylene gas motor-driven valve 17 and control valve; Air blast comes tracheae 20 to be connected with the mixing point pipe 6 of air hydrops separator 25 and acceleration pulse generator respectively by the tube connector which is provided with air magnetic valve 21 and through type floating ball valve 23, and air hydrops separator 25 belows are provided with air bleeding valve 24.Among the figure, label " 19 " is the system program control device, can realize 2~32 nozzle serial or parallel connections by it, realizes the multi-level procedure auto-control of multiple spot bull, finishes the overall process of blowing ash.Label " 12 " is for being arranged on the deflection plate in the boiler convection bank heat-insulation layer, and when this device was installed, the angle between impulse jet nozzle 11 and the deflection plate was 10-30 °.

Claims (1)

1. High-energy Gas Pulse Sootblowers is by acceleration pulse generator (1), gas mixer chamber (2), gain plate (3), detonation chamber (4), mist conduit (5), (10), mixing point fire tube (6), high-voltage ignition transformer (7), high energy gas burning torch (8), mist pilot chamber (9), acceleration pulse nozzle (11), Pressure gauge (13), (26), tube connector (14), (22), acetylene gas distributor (15), acetylene gas control valve (16), acetylene gas motor-driven valve (17), acetylene gas bottle (18), air blast comes tracheae (20), air magnetic valve (21), through type floating ball valve (23), air bleeding valve (24), air hydrops separator (25) is formed; It is characterized in that: acceleration pulse generator (1) top is gas mixer chamber (2), the bottom is detonation chamber (4), the centre is provided with gain plate (3), and lower end, detonation chamber (4) is welded with mist conduit (10), and conduit (10) front end is provided with accelerator pulse nozzle (11); Gas mixer chamber (2) one sides are welded with mixing point fire tube (6) by mist conduit (8), the one side is provided with high-voltage ignition transformer (7), the lower end is connected with the mist pilot chamber (9) of detonation chamber (4) one sides, is provided with high energy gas burning torch (8) in the mist pilot chamber (9); Acetylene gas bottle (18) is connected with acetylene gas hydrops jar (15) by tube connector, and acetylene gas hydrops jar (15) is connected with the mixing point fire tube (6) of acceleration pulse generator (1) by the tube connector which is provided with acetylene gas motor-driven valve (17) and control valve (16); Air blast comes tracheae 20 to be connected with the mixing point fire tube (6) of air hydrops separator (25) and acceleration pulse generator (1) respectively by the tube connector which is provided with air magnetic valve (21) and through type floating ball valve (23).
CNU2007200134393U 2007-07-23 2007-07-23 Energetic flue gas pulse sootblowing device Expired - Fee Related CN201074823Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200134393U CN201074823Y (en) 2007-07-23 2007-07-23 Energetic flue gas pulse sootblowing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200134393U CN201074823Y (en) 2007-07-23 2007-07-23 Energetic flue gas pulse sootblowing device

Publications (1)

Publication Number Publication Date
CN201074823Y true CN201074823Y (en) 2008-06-18

Family

ID=39520084

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200134393U Expired - Fee Related CN201074823Y (en) 2007-07-23 2007-07-23 Energetic flue gas pulse sootblowing device

Country Status (1)

Country Link
CN (1) CN201074823Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882875A (en) * 2019-03-20 2019-06-14 五邑大学 Combustion mechanism
CN109882840A (en) * 2019-03-20 2019-06-14 五邑大学 Combustor
CN110986069A (en) * 2019-11-22 2020-04-10 邱小琼 Efficient gas pulse soot blower and control method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882875A (en) * 2019-03-20 2019-06-14 五邑大学 Combustion mechanism
CN109882840A (en) * 2019-03-20 2019-06-14 五邑大学 Combustor
CN109882875B (en) * 2019-03-20 2024-08-13 五邑大学 Combustion mechanism
CN110986069A (en) * 2019-11-22 2020-04-10 邱小琼 Efficient gas pulse soot blower and control method thereof
CN110986069B (en) * 2019-11-22 2021-07-09 邱小琼 Efficient gas pulse soot blower and control method thereof

Similar Documents

Publication Publication Date Title
CN201072131Y (en) Bow-wave ash blowing system
CN201074823Y (en) Energetic flue gas pulse sootblowing device
CN101900343B (en) Boiler pulse soot-blowing method and device thereof
CN111271980A (en) Cement kiln waste heat power generation system
CN201066195Y (en) Horizontal type reverse-combusting coal-firing boiler
CN203116043U (en) Online shock ash removing device of crumple-type boiler
CN202328287U (en) Mixed ignition pot of soot blower
CN202216258U (en) Gas energy pulse soot blower using compressed gas
CN201531891U (en) Shock-wave boaster
CN203190431U (en) Boiler pulse soot blower
CN102322643A (en) A kind of gas energy impulse soot blower with Compressed Gas
CN202328286U (en) Continuous-shockwave soot blower
CN201715524U (en) Hydrogen explosion powerful shock-wave soot blower of oxyhydrogen machine
CN206739331U (en) Intelligent gas pulse soot blower
CN201237228Y (en) Three-cavity mixed ignition pot
CN201170561Y (en) Boiler sootblower system for input compressed-air and high-efficiency distribution initiation machine
CN206944114U (en) Gas fuel boiler with compound water-cooled furnace
CN206831533U (en) A kind of shock-wave ash blowing air distributing device
CN100470156C (en) Method for preventing two-explosion gas high-energy impulse dusting device
CN219160375U (en) Pulse soot blower's transformation structure
CN2324423Y (en) Device for removing ash and dirt by explosive shock wave
CN202371697U (en) Constant positive pressure nozzle anticorrosive gas pulse generating device
CN2430616Y (en) Ash cleaner by weak explosion wave
CN114543067B (en) Coal gas station with improved air flow passage and improved heat energy utilization rate
CN201170562Y (en) Boiler sootblower system for high-efficiency distribution initiation machine with volution air pump

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Panjin link energy saving equipment Co., Ltd.

Assignor: Cheng Yongming|Cheng Qiang

Contract fulfillment period: 2008.11.18 to 2017.7.22

Contract record no.: 2009210000017

Denomination of utility model: Energetic flue gas pulse sootblowing device

Granted publication date: 20080618

License type: Exclusive license

Record date: 20090318

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2008.11.18 TO 2017.7.22; CHANGE OF CONTRACT

Name of requester: PANJIN HUANBANG ENERGY SAVING EQUIPMENT CO., LTD.

Effective date: 20090318

EE01 Entry into force of recordation of patent licensing contract

Assignee: Panjin link energy saving equipment Co., Ltd.

Assignor: Cheng Yongming|Chengqiang

Contract fulfillment period: 2008.11.18 to 2017.7.22

Contract record no.: 2009210000017

Denomination of utility model: Energetic flue gas pulse sootblowing device

Granted publication date: 20080618

License type: Exclusive license

Record date: 20090318

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2008.11.18 TO 2017.7.22; CHANGE OF CONTRACT

Name of requester: PANJIN HUANBANG ENERGY SAVING EQUIPMENT CO., LTD.

Effective date: 20090318

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080618

Termination date: 20160723