CN201069374Y CN 200720079890 CN200720079890U CN201069374Y CN 201069374 Y CN201069374 Y CN 201069374Y CN 200720079890 CN200720079890 CN 200720079890 CN 200720079890 U CN200720079890 U CN 200720079890U CN 201069374 Y CN201069374 Y CN 201069374Y
Authority
CN
China
Prior art keywords
straight tube
orifice plate
natural gas
utility
expansion joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200720079890
Other languages
Chinese (zh)
Inventor
张建贵
刘春林
骆进
徐英
王春生
张强
王东林
邓乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
West Sichuan Drilling Co of CNPC Chuanqing Drilling Engineering Co Ltd
Original Assignee
Sichuan Petroleum Administration Chuanxi Drilling Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Petroleum Administration Chuanxi Drilling Co filed Critical Sichuan Petroleum Administration Chuanxi Drilling Co
Priority to CN 200720079890 priority Critical patent/CN201069374Y/en
Application granted granted Critical
Publication of CN201069374Y publication Critical patent/CN201069374Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

A natural gas tester is provided for testing the productivity of natural gas, belonging to the technical field of fabrication of test equipment for drilling and completion of natural gas exploration. The utility model comprises a straight tube mechanism and a bypass mechanism. A retractable adapter is arranged inside the straight tube mechanism and connected with a detachable connector via a punctured plate. The bypass mechanism is provided with a bended member connected with T-shaped adapters at the two ends of the straight tube mechanism. The bypass mechanism is connected with a fast-mount adapter. The utility model provides a retractable adapter for implementing a natural gas tester capable of the rapid change of porous plate. The utility model solves the problems of the prior art, such as large consumption of various parts, long assembly time for porous plate exchange, and heavy load of assembly and disassembly. The utility model realizes the connection between the straight tube mechanism and the bypass mechanism by using a bended tube and the retractable adapter; reduces the weight to 1/6 of the prior art, fabrication cost by 50%, installation time by 7/8, and porous plate exchange time to 1/6 of the prior art; reduces the labor intensity for transportation and installation; and reduces the probability of injury to the staff.

Description

The rock gas proving installation
Technical field:
A kind of rock gas proving installation is used for the test to the gasser production capacity, belongs to the manufacturing technology field of rock gas well completing test equipment.
Background technology:
In the prior art, after a bite gasser is finished drilling well, in the process of completion formation testing, in order to determine the gas production of this well, need to adopt special testing apparatus that the flow of rock gas is tested, the equipment that prior art is used to test mainly is the critical velocity flowmeter that adopts perforated plate, in test process in order to survey the output of accurate rock gas, must change the orifice plate of respective aperture on proving installation tests, two kinds of proving installations are arranged at present: a kind of is the proving installation of not being with by-pass pipe, when changing orifice plate, opens emergent open flow igniting flow process, close testing process and change orifice plate, its problem is: adopting this mode to test needs to use 20 in oil pipe, and proving installation need be fixed 14 places, and the replacing orifice plate time needs 30min, and the use accessory is many, and dismounting and the workload of installing are big; Second kind is the proving installation of band by-pass pipe, this prior art is when changing orifice plate, to open by-pass valve earlier, close upper and lower two valves of critical velocity flowmeter then, open orifice plate again and connect the replaceable orifice plate of trip ability in the ninth of the ten Heavenly Stems, its shortcoming is: use this test mode need use 10 in oil pipe, the position that proving installation need be fixed is 7 places, the elbow that connects by-pass pipe is to be made of two joints and a connector, therefore the accessory that needs is various, the built-up time of device needs 4 hours, and dismounting and the workload of installing are big, and the replacing orifice plate time also needs 30min.
Goal of the invention: the purpose of this utility model is the shortcoming at prior art, adopts the mode of simplifying combination, and a kind of collapsible joint that has is provided, and can realize changing fast the rock gas proving installation of orifice plate.
The utility model is achieved in that the utility model comprises straight tube mechanism and bypass mechanism, and straight tube mechanism comprises that the ninth of the ten Heavenly Stems is swum in two valves, expansion joint, orifice plate connection, manage at the upper reaches; Bypass mechanism comprises two bend pipes, a valve and a ready-packaged joint; Two valves in the straight tube mechanism are arranged on the inboard of two bend pipes, and expansion joint is arranged on orifice plate and connects the trip dirty part in the ninth of the ten Heavenly Stems, and the upper reaches pipe is arranged on orifice plate and connects the trip upper reaches part in the ninth of the ten Heavenly Stems; The ninth of the ten Heavenly Stems is swum in upper reaches pipe, orifice plate connection, expansion joint all is arranged between two valves; Two bend pipes of bypass mechanism are connected with the T junction at straight tube mechanism two ends respectively, and a valve and a ready-packaged joint are set between two bend pipes; During use, the upper and lower end interface of this device straight tube mechanism is connected on the relief line, when testing, close the bypass mechanism valve earlier, open two valves of straight tube mechanism, rock gas flow to the open flow lighting-up tuyere by orifice plate in the straight tube mechanism and expansion joint, so just can record the flow of rock gas; When needs are changed orifice plate, open the valve on the bypass mechanism earlier, close two valves in the straight tube mechanism, rock gas just flows to the open flow lighting-up tuyere from bypass mechanism, opens the orifice plate connection then and swims the ninth of the ten Heavenly Stems, take out orifice plate, change required orifice plate, tighten the orifice plate connection and swim the ninth of the ten Heavenly Stems, open the valve at straight tube mechanism two ends again, close the valve on the bypass mechanism, just can recover test job.
Advantage of the present utility model and effect are, the bend pipe that is used to connect straight tube mechanism and bypass mechanism does not need joint, replaced by the expansion joint of activity and to be fixedly coupled pipe and joint, therefore various connection fittings have been reduced greatly, weight drops to 40 kilograms from 240 kilograms of prior art, manufacturing cost has reduced more than 50%, the time of erecting equipment is 1/8 of prior art, the time of changing orifice plate in the test process is original 1/6, has to reduce the worker and remove the feature that peace labour intensity and minimizing personnel injure probability.
Description of drawings:
Fig. 1 is a package assembly synoptic diagram of the present utility model.
Fig. 2 is that tubule 3 is connected the amplification profile synoptic diagram with bassoon 4 among the utility model Fig. 1.
Embodiment:
Provide embodiment of the present utility model below in conjunction with accompanying drawing: the utility model comprises straight tube mechanism and bypass mechanism, straight tube mechanism comprises two valves 2 and 7, expansion joint, orifice plate connects swims the ninth of the ten Heavenly Stems 5, upper reaches pipe 6, two valves 2 and 7 are arranged on the inboard of two T junctions, orifice plate connects trip and is arranged between upper reaches pipe 6 and the expansion joint ninth of the ten Heavenly Stems 5, expansion joint is arranged on orifice plate and connects the trip dirty end in the ninth of the ten Heavenly Stems 5, expansion joint comprises one section tubule 3 and one section bassoon 4, tubule 3 is enclosed within the bassoon 4, be provided with O-ring seal 13 at tubule 3 and bassoon 4 surface of contact, expansion joint and upper reaches pipe 6 are provided with the tensimeter connector; Bypass mechanism comprises that two bend pipes 12 and 9, one valves 10 and 11, two bend pipes 12 of a ready-packaged joint are connected with 7 outer end with straight tube mechanism two valves 2 respectively with 9, are provided with a valve 10 and a ready-packaged joint 11 between two bend pipes 12 and 9; During use, the upper reaches end straight tube 8 and the dirty end straight tube 1 of this device straight tube mechanism are connected on the relief line, when testing, close the valve 10 of bypass mechanism, open two valves 2 and 7 of straight tube mechanism, rock gas just can record the flow of rock gas by being placed on orifice plate and connecting orifice plate in trip ninth of the ten Heavenly Stems 5 and the bassoon 4 and the tubule 3 of expansion joint flowing out from dirty straight tube 1; When need changing orifice plate, open the valve 10 on the bypass mechanism earlier, close two valves 2 and 7 of straight tube mechanism, rock gas just flows to open flow igniting pipeline from bypass mechanism, open the orifice plate connection then and swim the ninth of the ten Heavenly Stems 5, the direction of bassoon 4 to tubule 3 promoted, just can take out orifice plate, change required orifice plate, retract bassoon then, tighten the orifice plate connection and swim the ninth of the ten Heavenly Stems 5, open the valve 2 and 7 at straight tube mechanism two ends, close the valve 10 on the bypass mechanism, just can recover test job.

Claims (3)

1. a rock gas proving installation comprises straight tube mechanism and bypass mechanism, it is characterized in that:
A, straight tube mechanism comprise that the ninth of the ten Heavenly Stems is swum in two valves, expansion joint, orifice plate connection, manage at the upper reaches, two valves are arranged on the inboard of two T junctions, orifice plate connects trip and is arranged between upper reaches pipe and the expansion joint ninth of the ten Heavenly Stems, and expansion joint is arranged on orifice plate and connects the trip dirty end in the ninth of the ten Heavenly Stems;
B, bypass mechanism comprise two bend pipes, and a valve and a ready-packaged joint, two bend pipes are connected with the outer end straight tube of straight tube mechanism two valves respectively, and a valve and a ready-packaged joint are set between two bend pipes.
2. rock gas proving installation according to claim 1 is characterized in that: described expansion joint comprises one section tubule and one section bassoon, and tubule is enclosed within the bassoon, is provided with O-ring seal at tubule and bassoon surface of contact.
3. rock gas proving installation according to claim 1 is characterized in that: described expansion joint and upper reaches pipe are provided with the tensimeter connector.
CN 200720079890 2007-06-11 2007-06-11 Natural gas testing device Expired - Fee Related CN201069374Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200720079890 CN201069374Y (en) 2007-06-11 2007-06-11 Natural gas testing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200720079890 CN201069374Y (en) 2007-06-11 2007-06-11 Natural gas testing device

Publications (1)

Publication Number Publication Date
CN201069374Y true CN201069374Y (en) 2008-06-04

Family

ID=39490763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200720079890 Expired - Fee Related CN201069374Y (en) 2007-06-11 2007-06-11 Natural gas testing device

Country Status (1)

Country Link
CN (1) CN201069374Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101781983A (en) * 2010-03-01 2010-07-21 中国石油集团川庆钻探工程有限公司 Method used for gas drilling drillstem test
CN104653169A (en) * 2013-11-15 2015-05-27 中国石油天然气股份有限公司 Simple mouth metering device and technology method for gas wells

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101781983A (en) * 2010-03-01 2010-07-21 中国石油集团川庆钻探工程有限公司 Method used for gas drilling drillstem test
CN104653169A (en) * 2013-11-15 2015-05-27 中国石油天然气股份有限公司 Simple mouth metering device and technology method for gas wells
CN104653169B (en) * 2013-11-15 2017-10-17 中国石油天然气股份有限公司 A kind of gas well mouth Simple measuring device and process

Similar Documents

Publication Publication Date Title
CN201069374Y (en) Natural gas testing device
CN110425376A (en) A kind of line leakage and emergency leakage blocking device
CN204074654U (en) A kind of detachable receiving ball tube device for oil-gas pipeline cleaning
CN205919873U (en) Two liquid levels interlocking measurement system is got to sled frame structure no. 3
CN216242425U (en) Switching valve type portable pipeline cleaning device sledge
CN205941220U (en) Hose pressure resistance test installation
CN206583582U (en) A kind of complete fast pressure testing device of piping lane pipeline
KR101045111B1 (en) Pipeline's inside cleansing apparatus for water system conversion and water service pipeline changing construction method thereby
CN101871800A (en) Integral machining type Venturi tube and using method thereof
CN106964612A (en) Hydraulic pipeline oil flushing method
CN209892552U (en) Portable hydraulic system fault detection device
CN106168317A (en) A kind of Combined joint
CN205300836U (en) Coal slurry gasifier nozzle pressure differential measuring device
KR100930817B1 (en) Cleaning module for using pig cleaner
CN205009151U (en) Quick connecting device of sounding pipe
CN208719663U (en) A kind of easy water supply and drainage pipe detection device
CN200986486Y (en) Wind pressure measuring pipe quick blowing apparatus
RU2255202C1 (en) Gas well brace
CN219641364U (en) Multi-flow pipeline flowmeter
CN211346612U (en) Portable pipeline misalignment measuring device
CN217003281U (en) Flange for valve connection
CN209689698U (en) A kind of natural gas flowmeter installation fixed structure
CN216692463U (en) Agricultural water conservancy project is with water conservancy pipeline convenient to installation
CN219977643U (en) Pressure sampling device for demister of multifunctional desulfurization absorption tower
CN209541815U (en) A kind of nonpetroleum metering device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20090109

Address after: Engineering and Technology Department of West Sichuan Drilling Company, No. 143, Sichuan, Chengdu, Chenghua District 610051, China

Patentee after: Chuanxi Drilling Co., Ltd. of CNPC Chuanqing Drilling Engineering Co., Ltd.

Address before: No. 143, Hua Tong Road, Chenghua District, Sichuan, Chengdu Province, China: 610051

Patentee before: Sichuan Petroleum Administration Chuanxi Drilling Company

C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: Engineering and Technology Department of West Sichuan Drilling Company, No. 143 Hua Jing Road, Sichuan, Chengdu, 610051, China: Chenghua District

Patentee after: Chuanxi Drilling Co., Ltd. of CNPC Chuanqing Drilling Engineering Co., Ltd.

Address before: Engineering and Technology Department of West Sichuan Drilling Company, No. 143, Sichuan, Chengdu, Chenghua District 610051, China

Patentee before: Chuanxi Drilling Co., Ltd. of CNPC Chuanqing Drilling Engineering Co., Ltd.

ASS Succession or assignment of patent right

Owner name: CHINA PETROLEUM GROUP CHUANQING DRILLING ENGINEERI

Free format text: FORMER OWNER: SICHUAN PETROLEUM ADMINISTRATION CHUANXI DRILLING CO.,LTD.

Effective date: 20090109

C56 Change in the name or address of the patentee

Owner name: CHINA PETROLEUM GROUP CHUANQING DRILLING ENGINEERI

Free format text: NEW ADDRESS: CHENGHUA DISTRICT, CHENGDU CITY, SICHUAN PROVINCE, NO.143 HUAYOU ROAD, WEST SICHUAN DRILLING CO., LTD., ENGINEERING TECHNOLOGY DEPARTMENT, ZIP CODE:610051

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080604