CN201040699Y - Lifting device for converter smoke helmet - Google Patents

Lifting device for converter smoke helmet Download PDF

Info

Publication number
CN201040699Y
CN201040699Y CNU200720012175XU CN200720012175U CN201040699Y CN 201040699 Y CN201040699 Y CN 201040699Y CN U200720012175X U CNU200720012175X U CN U200720012175XU CN 200720012175 U CN200720012175 U CN 200720012175U CN 201040699 Y CN201040699 Y CN 201040699Y
Authority
CN
China
Prior art keywords
chain
lifting
converter
hood
water cooling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU200720012175XU
Other languages
Chinese (zh)
Inventor
李继宏
兰勇
刘士平
曹焰
宋明
张禹
孙岩
张春
吴振国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ansteel Engineering Technology Corp Ltd
Original Assignee
Design & Research Institute Of Anshan Iron And Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Design & Research Institute Of Anshan Iron And Steel Group Corp filed Critical Design & Research Institute Of Anshan Iron And Steel Group Corp
Priority to CNU200720012175XU priority Critical patent/CN201040699Y/en
Application granted granted Critical
Publication of CN201040699Y publication Critical patent/CN201040699Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The utility model discloses a converter hood lifting device, comprising four synchronous hydraulic cylinders, a position sensor and a water cooling pull rod. The four synchronous lifting hydraulic cylinders are horizontally placed on a maintenance platform above a hood. A head part of the hydraulic cylinder is connected with its own chain through a joint. The other end of the chain is connected through the joint with the water cooling pull rod which is connected with the converter hood. Four grooved wheels are respectively fixed on the maintenance platform above the four water cooling pull rods. The chain passes the grooved wheel and the grooved wheel changes the moving direction of the chain from horizontal to vertical. The chain and the water cooling pull rod drive the converter hood to ascend and descend steadily to realize the lifting function of the converter hood. The converter hood lifting device overcomes the shortage of using a hoisting device lifting converter hood and a hydraulic cylinder vertical hanging type lifting converter hood device, and has advantages of steady and reliable operation, reasonable utilization of converter system space, safe and reliable repair and maintenance, time and labor saving equipment replacement and no hidden danger.

Description

The revolving furnace fume hood jacking system
Technical field
The utility model belongs to the metal smelt field, particularly a kind of revolving furnace fume hood jacking system.
Background technology
At present, the revolving furnace fume hood jacking system mainly contains two kinds of patterns: a kind of employing winding plant, drive steel rope by the direct motor drive reel, and walk around fixed pulley lifting revolving furnace fume hood.This device transmission is not steady, causes the equipment scratching easily, and is relatively harsher to space requirement.The another kind of employing vertically hung the hydraulic actuating cylinder form, and hydraulic actuating cylinder hangs upside down above revolving furnace fume hood, directly is connected on the petticoat pipe body by the water-cooled pull bar, realizes the lifting of petticoat pipe by the hydraulic actuating cylinder lifting.This mode can be saved the space, but maintenance, safeguards very difficultly, has huge potential safety hazard.
Summary of the invention
The revolving furnace fume hood jacking system that the purpose of this utility model is to provide a kind of and operates steadily, is convenient to safeguard.
For achieving the above object, the revolving furnace fume hood jacking system that the utility model provides is made up of four synchronous hydraulic cylinders, position transduser, water-cooled pull bar, four synchronization lifting hydraulic actuating cylinders are lain in a horizontal plane on the inspection platform of petticoat pipe top, the hydraulic actuating cylinder head is connected with separately rope chain respectively by joint, the rope chain other end is connected with water-cooled pull bar on being connected revolving furnace fume hood by joint, 4 sheaves are separately fixed on the inspection platform of 4 water-cooled pull bar tops, the rope chain is by sheave, and sheave is vertical with rope chain movement direction by level conversion.
Be equipped with band nylon cushion board mount in the jacking system that the utility model provides under the hydraulic actuating cylinder head body.
Revolving furnace fume hood jacking system described in the utility model is compared with existing revolving furnace fume hood jacking system, four synchronization lifting hydraulic actuating cylinders lie in a horizontal plane on the inspection platform, there is the nylon cushion board mount to make this device operate steadily under the hydraulic actuating cylinder head body and reliably also rationally utilizes the converter system space, repair and maintenance is safe and reliable, equipment replacement is time saving and energy saving, does not have potential safety hazard.
Description of drawings
Accompanying drawing 1 is a petticoat pipe jacking system partial schematic diagram.
Accompanying drawing 2 is a petticoat pipe jacking system birds-eye view.
The specific embodiment
Below in conjunction with accompanying drawing the specific embodiment of the present utility model is described in further detail.
In Fig. 1 and Fig. 2, the revolving furnace fume hood lifting is placed on the steel structure inspection platform with hydraulic actuating cylinder 5 levels, and hydraulic actuating cylinder 5 afterbodys are connected with support 7 usefulness bearing pins, this support 7 and the bearing bolt together that is welded on the platform.Below hydraulic actuating cylinder 5 heads, be equipped with the support 6 of band nylon backing plate, avoid friction and protection hydraulic actuating cylinder 5 surfaces between cylinder body and the platform not easy to wear, guarantee that hydraulic actuating cylinder 5 always is horizontal.The flexible position control of hydraulic actuating cylinder level is finished by the position transduser that it carries.The hydraulic actuating cylinder head is connected with separately rope chain 3 respectively by joint, and rope chain 3 other ends are connected with the water-cooled pull bar 4 of direct connection on revolving furnace fume hood by joint, and this regional temperature is than higher, and the water-cooled pull bar substitutes the function of the rope chain 3 of part linear portion.The high-low limit of two limit switch 2 control petticoat pipes.4 sheaves 1 are separately fixed on the inspection platform of 4 water-cooled pull bar 4 tops, and rope chain 3 is by sheave 1, and sheave 1 transfers rope chain 3 sense of motions vertically to by level, and sheave 1 existing location has the function that turns to again.Rope chain 3 can select for use the rope chain also can select leaf chain for use, adopts the bigger leaf chain traction revolving furnace fume hood lifting effect of intensity better.4 lifting hydraulic cylinders 5 synchronization telescope under the control of hydraulic efficiency pressure system drives the steadily lifting together of rope chain 3, water-cooled pull bar 4 and revolving furnace fume hood, thereby realizes the revolving furnace fume hood elevating function.

Claims (2)

1. revolving furnace fume hood jacking system, by four synchronous hydraulic cylinders (5), position transduser, water-cooled pull bar (4) is formed, it is characterized in that: four synchronization lifting hydraulic actuating cylinders (5) are lain in a horizontal plane on the inspection platform of petticoat pipe top, the hydraulic actuating cylinder head is connected with separately rope chain (3) respectively by joint, rope chain (3) other end is connected with water-cooled pull bar (4) on being connected revolving furnace fume hood by joint, 4 sheaves (1) are separately fixed on the inspection platform of 4 water-cooled pull bars (4) top, rope chain (3) is by sheave (1), and sheave (1) is vertical with rope chain (3) sense of motion by level conversion.
2. according to the described revolving furnace fume hood jacking system of claim 1, it is characterized in that: band nylon cushion board mount (6) is arranged under the described hydraulic actuating cylinder head body.
CNU200720012175XU 2007-05-16 2007-05-16 Lifting device for converter smoke helmet Expired - Fee Related CN201040699Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU200720012175XU CN201040699Y (en) 2007-05-16 2007-05-16 Lifting device for converter smoke helmet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU200720012175XU CN201040699Y (en) 2007-05-16 2007-05-16 Lifting device for converter smoke helmet

Publications (1)

Publication Number Publication Date
CN201040699Y true CN201040699Y (en) 2008-03-26

Family

ID=39252406

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU200720012175XU Expired - Fee Related CN201040699Y (en) 2007-05-16 2007-05-16 Lifting device for converter smoke helmet

Country Status (1)

Country Link
CN (1) CN201040699Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101851694B (en) * 2009-03-31 2012-09-05 上海宝冶建设有限公司 Fast change method of large-scale converter movable gas hood
CN113511607A (en) * 2020-04-10 2021-10-19 合肥华凌股份有限公司 Lifting mechanism, lifting device and household appliance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101851694B (en) * 2009-03-31 2012-09-05 上海宝冶建设有限公司 Fast change method of large-scale converter movable gas hood
CN113511607A (en) * 2020-04-10 2021-10-19 合肥华凌股份有限公司 Lifting mechanism, lifting device and household appliance

Similar Documents

Publication Publication Date Title
CN205577896U (en) Novel high -efficient mechatronic workover machine
CN202785364U (en) Movable dual-door-type mast hoisting device
CN201040699Y (en) Lifting device for converter smoke helmet
CN106672819A (en) Remote-controllable small-sized tower type lifting machine
CN201436274U (en) Special assembling suspender of long chain for slab rolling mill engineering steel plate conveying device
CN204661163U (en) A kind of Multifunction transformer sleeve pipe lifting support
CN103663236A (en) Heavy-type cover plate lifting device
CN107235422A (en) It is exclusively used in the crane device of lifting steel pipes and welding
CN204162319U (en) High strength crane-car
CN201890745U (en) Lifting and guiding device for tundish car
CN103539020B (en) Novel hoisting construction method and special hanging device
CN103058072B (en) Large luffing jib tower crane introduction mechanism
CN203715155U (en) Heavy cover plate lifting device
CN203021213U (en) Rotary one-arm crane
CN201635664U (en) Hoisting device hoisted by two cylinders
CN201330124Y (en) Deviation rectification and turning device for sling of crane
CN204162320U (en) Facilitate the crane-car of operation at night
CN204281777U (en) The Handling device of stove refractory brick is built for steel-making converter
CN102699315B (en) Fixed cover placing and taking device for hot metal ladle
CN201619667U (en) Boarding ladder driving device
CN210682985U (en) Three-way hydraulic adjusting device
CN204824948U (en) Petticoat pipe system containing simple and convenient fluid pressure type activity petticoat pipe elevating gear
CN204980889U (en) Mobile phone film tempering furnace is with boat crane device
CN204150973U (en) Crane-car elevator lifting assemblies
CN211219529U (en) A dismouting equipment for bearing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: ANSTEEL ENGINEERING TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: ANGANG GROUP CORPORATION DESIGN + RESEARCH INSTITUTE

CP01 Change in the name or title of a patent holder

Address after: 114021 Tiexi District, Liaoning City, Anshan Iron and steel plant

Patentee after: Ansteel Engineering Technology Corporation Limited

Address before: 114021 Tiexi District, Liaoning City, Anshan Iron and steel plant

Patentee before: Design & Research Institute of Anshan Iron and Steel Group Corp.

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080326

Termination date: 20140516