CN201008968Y - Internal lining construction of torpedo pot - Google Patents

Internal lining construction of torpedo pot Download PDF

Info

Publication number
CN201008968Y
CN201008968Y CNU2007200899431U CN200720089943U CN201008968Y CN 201008968 Y CN201008968 Y CN 201008968Y CN U2007200899431 U CNU2007200899431 U CN U2007200899431U CN 200720089943 U CN200720089943 U CN 200720089943U CN 201008968 Y CN201008968 Y CN 201008968Y
Authority
CN
China
Prior art keywords
brick
section
torpedo
unit
stones
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007200899431U
Other languages
Chinese (zh)
Inventor
校松波
赵永安
李树森
张晓雷
李明欢
张灿星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUNAI SCI-TECH DEVELOPMENT Co Ltd GONGYI
Original Assignee
WUNAI SCI-TECH DEVELOPMENT Co Ltd GONGYI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUNAI SCI-TECH DEVELOPMENT Co Ltd GONGYI filed Critical WUNAI SCI-TECH DEVELOPMENT Co Ltd GONGYI
Priority to CNU2007200899431U priority Critical patent/CN201008968Y/en
Application granted granted Critical
Publication of CN201008968Y publication Critical patent/CN201008968Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model relates to a fish torpedo tank lining structure, which comprises a spray finishing material (2) positioned at the inner side wall of the tank, a tank opening (1) positioned in the middle of the tank and a firebrick working layer positioned on the inner side of the spray finishing material (2), wherein, an impact zone (I) is arranged on the right downside of the tank opening (1) which is built by laying a fish torpedo tank special brick ''A''(3). One vertical section of the brick is a rectangular, while the other section of the brick is an isosceles trapezoid. A non-impact zone (II) is built by laying two fish torpedo tank special bricks ''B'' (4 and 5), wherein, one vertical section is a rectangular, while the other section is an isosceles trapezoid. A sectional awl shell lining masonry segment (III) is built by laying three fish torpedo tank special bricks ''C'' (6, 7 and 8), wherein, one vertical section of the brick is a right angle trapezoid, while the other vertical section is an isosceles trapezoid. An end wall lining masonry segment (IV) is built by laying a fish torpedo tank special brick ''D'' (9). The brick is a cuboid. The fish torpedo tank lining structure adopts the least brick types to facilitate brick matching and masonry, thereby effectively avoiding phenomenon of brick falling, dregs hanging and iron pasting and saving material. The brick type structure becomes simple. The masonry hardness is reduced to be beneficial for popularization and implementation.

Description

Torpedo tank lining structure therewith
One, technical field:
The utility model relates to the torpedo tank car that a kind of Ferrous Metallurgy field shipment molten iron is used, particularly a kind of torpedo tank lining structure therewith.
Two, background technology:
The torpedo jar is that the Ferrous Metallurgy casting field is used to load and transport blast-melted a kind of device, tank body is combined with the symmetrical truncated cone shell section that is connected in two ends and the sealing cambered surface section of each truncated cone shell section end by the cylindrical shell section of centre, profile is similar to torpedo, so be called the torpedo jar.Torpedo tank car just is employed in the industrial country of prosperities such as Europe, the United States, day in early days, and along with the continuous development of the big-and-middle-sized iron and steel enterprise of China, the torpedo jar is progressively applied in recent years.Torpedo jar madial wall must be built by laying bricks or stones to play insulation and to prevent that high-temperature molten metal or slag from corroding tank body with torpedo jar special brick.
Yet the employed refractory brick of present torpedo jar working lining both domestic and external is of a great variety, generally all at 15~30 kinds, in addition more, and brick type complexity, build by laying bricks or stones very difficult.
Three, utility model content:
The utility model is to overcome the deficiency that prior art exists, and designs and produce a kind of torpedo tank lining structure therewith.
Technical scheme:
A kind of torpedo tank lining structure therewith, the spray paint (2) that contains the tank body madial wall, jar mouthful (1) in the middle of the tank body, the refractory brick work layer that spray paint (2) is inboard, this refractory brick work layer comprises cylindrical shell inside lining building section (I, II), truncated cone shell inside lining building section (III) and headwall inside lining building section (IV), wherein cylindrical shell inside lining building section comprises impact zone (I) and the non-impact zone (II) under jar mouthful (1), described impact zone (I) is built by laying bricks or stones by torpedo jar special brick first (3) and is formed, a longitudinal cross-section of this brick is a rectangle, and another longitudinal cross-section is an isosceles trapezoid; Non-impact zone (II) is built by laying bricks or stones by torpedo jar special brick second (4,5) and is formed, and longitudinal cross-section of this brick is a rectangle, and another longitudinal cross-section is an isosceles trapezoid, and wherein the height of unit Zhuan Jia (3) is greater than the height of unit brick second (4,5); Truncated cone shell inside lining building section (III) is built by laying bricks or stones by torpedo jar special brick third (6,7,8) and is formed, and a longitudinal cross-section of this brick is a right-angled trapezium, and another longitudinal cross-section is an isosceles trapezoid; Headwall inside lining building section (IV) is built by laying bricks or stones by torpedo jar special brick fourth (9) and is formed, and this brick is a cuboid.
Be provided with one section cambered surface end liner and build layer (V) by laying bricks or stones between the bottom of described cylindrical shell inside lining building section (I, II) and spray paint (2), this end liner is built layer (V) by laying bricks or stones and is built by laying bricks or stones by torpedo jar special brick penta (10) and form; Perhaps described cylindrical shell inside lining building section (I, II) directly contacts with spray paint (2), does not establish end liner in the middle of it and builds layer by laying bricks or stones.
Described torpedo jar special brick brick second (4,5) comprises two (5) of one of unit brick second (4) and unit brick second; Two (5) isosceles trapezoid cross section of one of this unit brick second (4) and unit brick second, the waist of its isosceles trapezoid is different with the base corner dimension, waist of one of unit brick second (4) and end angle (α 1) less than two (5) waist and the end angle of cut (α of unit brick second 2).
One of torpedo jar special brick second (4) for regulating brick, this brick is built by laying bricks or stones at impact zone (I) center or non-impact zone (II) center as required.
Described torpedo jar special brick third (6,7,8) comprise one of unit brick third (6), unit brick third two (7), unit brick third three (8); One of this unit brick third (6), unit brick third two (7), three (8) isosceles trapezoid cross section of unit brick third, the waist of its isosceles trapezoid is different with the base corner dimension, waist of one of unit brick third (6) and end angle (β 1) greater than two (7) waist and end angle (β of unit brick third 2), two (7) waist and end angle (β of unit brick third 2) greater than three (8) waist and end angle (β of unit brick third 3).
In the big end section of described truncated cone shell inside lining building section (III) based on one of torpedo jar special brick third (6), torpedo jar special brick third two (7) for regulating brick; In the stage casing of truncated cone shell inside lining building section (III) based on two (7) of torpedo jar special brick third, torpedo jar special brick third three (8) for regulating brick; In the small end section of truncated cone shell inside lining building section (III) based on three (8) of torpedo jar special brick third.
The right-angled trapezium cross section of brick third (6,7,8) is built in the torpedo jar special use of described truncated cone shell inside lining building section (III) by laying bricks or stones, and the right angle waist of this right-angled trapezium is built by laying bricks or stones in torpedo jar inboard, and the inclination waist contacts with spray paint (2) and builds by laying bricks or stones.
The beneficial effects of the utility model:
1, torpedo tank lining structure therewith of the present utility model adopts minimum brick type as far as possible, conveniently joins brick and builds by laying bricks or stones, reduces the brick envelope simultaneously, effectively avoids phenomenons such as brick, dross, sticking iron.
2, torpedo tank lining structure therewith of the present utility model, prolong service life, and repairing and replacement are more prone to, and suitably reduce molten iron erosional layer area, economize on material.
3, torpedo tank lining structure therewith of the present utility model, brick type structure becomes simply, builds difficulty by laying bricks or stones and reduces, and has also reduced cost, is beneficial to very much promotion and implementation.
Four, description of drawings:
Fig. 1 is one of torpedo tank liner cross-sectional view;
Fig. 2 is the A-A cross-sectional view of Fig. 1;
Fig. 3 is the B-B cross-sectional view of Fig. 1;
Fig. 4 is the C-C cross-sectional view of Fig. 1;
Fig. 5-1 faces structural representation for torpedo jar special brick first;
Fig. 5-2 is a torpedo jar special brick first left side TV structure schematic diagram;
Fig. 6-1 faces structural representation for one of torpedo jar special brick second;
Fig. 6-2 is one of a torpedo jar special brick second left TV structure schematic diagram;
Fig. 6-3 faces structural representation for two of torpedo jar special brick second;
Fig. 6-4 is two left TV structure schematic diagrames of torpedo jar special brick second;
Fig. 7-1 faces structural representation for one of torpedo jar special brick third;
Fig. 7-2 is the left TV structure schematic diagram of one of torpedo jar special brick third;
Fig. 7-3 faces structural representation for two of torpedo jar special brick third;
Fig. 7-4 is two left TV structure schematic diagrames of torpedo jar special brick third;
Fig. 7-5 faces structural representation for three of torpedo jar special brick third;
Fig. 7-6 is three left TV structure schematic diagrames of torpedo jar special brick third;
Fig. 8-1 faces structural representation for torpedo jar special brick fourth;
Fig. 8-2 is a torpedo jar special brick fourth left side TV structure schematic diagram;
Fig. 9-1 faces structural representation for torpedo jar special brick penta;
Fig. 9-2 is torpedo jar special brick penta a left TV structure schematic diagram;
Figure 10 is two of a torpedo tank liner cross-sectional view.
Five, specific embodiments:
Embodiment one: referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, a kind of torpedo tank lining structure therewith, the spray paint 2 that contains the tank body madial wall, jar mouth 1 in the middle of the tank body, the refractory brick work layer of spray paint 2 inboards, this refractory brick work layer comprises cylindrical shell inside lining building section I, II, truncated cone shell inside lining building section III and headwall inside lining building section IV, and wherein cylindrical shell inside lining building section comprises jar impact zone I and the non-impact zone II under mouthful 1; Described impact zone I is built by laying bricks or stones by torpedo jar special brick first 3 and forms, and a longitudinal cross-section of this brick is a rectangle, and another longitudinal cross-section is an isosceles trapezoid; Non-impact zone II is built by laying bricks or stones by torpedo jar special brick second 4,5 and forms, and longitudinal cross-section of this brick is a rectangle, and another longitudinal cross-section is an isosceles trapezoid, and wherein the height of unit brick first 3 is greater than the height of unit brick second 4,5; Truncated cone shell inside lining building section III is built by laying bricks or stones by torpedo jar special brick the third 6,7,8 and forms, and a longitudinal cross-section of this brick is a right-angled trapezium, and another longitudinal cross-section is an isosceles trapezoid; Headwall inside lining building section IV is built by laying bricks or stones by torpedo jar special brick fourth 9 and forms, and this brick is a cuboid.
Be provided with one section cambered surface end liner and build a layer V by laying bricks or stones between the bottom of described cylindrical shell inside lining building section I, II and spray paint 2, this end liner is built layer V by laying bricks or stones and is built by laying bricks or stones by torpedo jar special brick penta 10 and form.
Described torpedo jar special brick brick second 4,5 comprises 25 of one of unit brick second 4 and unit brick second; 25 isosceles trapezoid cross section of one of this unit brick second 4 and unit brick second, the waist of its isosceles trapezoid is different with the base corner dimension, waist of one of unit brick second 4 and end angle α 125 waist and end angle of cut α less than unit brick second 2One of torpedo jar special brick second 4 is for regulating brick, and this brick is built by laying bricks or stones at impact zone I center or non-impact zone II center as required.
Described torpedo jar special brick the third 6,7,8 comprise one of unit brick third 6, unit brick third 27, unit brick third 38; One of this unit brick third 6, unit brick third 27,38 isosceles trapezoid cross section of unit brick third, the waist of its isosceles trapezoid is different with the base corner dimension, waist of one of unit brick third 6 and end angle β 127 waist and end angle β greater than unit brick third 2, 27 waist and end angle β of unit brick third 238 waist and end angle β greater than unit brick third 3In the big end section of described truncated cone shell inside lining building section III based on one of torpedo jar special brick third 6, torpedo jar special brick third 27 for regulating brick; In the stage casing of truncated cone shell inside lining building section III based on 27 of torpedo jar special brick third, torpedo jar special brick third 38 for regulating brick; In the small end section of truncated cone shell inside lining building section III based on 38 of torpedo jar special brick third.
The right-angled trapezium cross section of brick the third 6,7,8 is built in the torpedo jar special use of described truncated cone shell inside lining building section III by laying bricks or stones, and the right angle waist of this right-angled trapezium is built by laying bricks or stones in torpedo jar inboard, and the inclination waist contacts with spray paint 2 and builds by laying bricks or stones.
Embodiment two: referring to Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, Figure 10, number identically with embodiment one, meaning is identical, does not repeat, different is: cylindrical shell inside lining building section I, II with directly contact with spray paint 2, do not establish end liner in the middle of it to build layer by laying bricks or stones.

Claims (7)

1. torpedo tank lining structure therewith, the spray paint (2) that contains the tank body madial wall, jar mouthful (1) in the middle of the tank body, the refractory brick work layer that spray paint (2) is inboard, this refractory brick work layer comprises cylindrical shell inside lining building section (I, II), truncated cone shell inside lining building section (III) and headwall inside lining building section (IV), wherein cylindrical shell inside lining building section comprises impact zone (I) and the non-impact zone (II) under jar mouthful (1), it is characterized in that: described impact zone (I) is built by laying bricks or stones by torpedo jar special brick first (3) and is formed, a longitudinal cross-section of this brick is a rectangle, and another longitudinal cross-section is an isosceles trapezoid; Non-impact zone (II) is built by laying bricks or stones by torpedo jar special brick second (4,5) and is formed, and longitudinal cross-section of this brick is a rectangle, and another longitudinal cross-section is an isosceles trapezoid, and wherein the height of unit Zhuan Jia (3) is greater than the height of unit brick second (4,5); Truncated cone shell inside lining building section (III) is built by laying bricks or stones by torpedo jar special brick third (6,7,8) and is formed, and a longitudinal cross-section of this brick is a right-angled trapezium, and another longitudinal cross-section is an isosceles trapezoid; Headwall inside lining building section (IV) is built by laying bricks or stones by torpedo jar special brick fourth (9) and is formed, and this brick is a cuboid.
2. torpedo tank lining structure therewith according to claim 1, it is characterized in that: be provided with one section cambered surface end liner and build layer (V) by laying bricks or stones between the bottom of described cylindrical shell inside lining building section (I, II) and spray paint (2), this end liner is built layer (V) by laying bricks or stones and is built by laying bricks or stones by torpedo jar special brick penta (10) and form; Perhaps described cylindrical shell inside lining building section (I, II) directly contacts with spray paint (2), does not establish end liner in the middle of it and builds layer by laying bricks or stones.
3. torpedo tank lining structure therewith according to claim 1 is characterized in that: described torpedo jar special brick brick second (4,5) comprises two (5) of one of unit brick second (4) and unit brick second; Two (5) isosceles trapezoid cross section of one of this unit brick second (4) and unit brick second, the waist of its isosceles trapezoid is different with the base corner dimension, waist of one of unit brick second (4) and end angle (α 1) less than two (5) waist and the end angle of cut (α of unit brick second 2).
4. according to claim 1 or the described torpedo tank lining structure therewith of 3 arbitrary claims, it is characterized in that: one of torpedo jar special brick second (4) is for regulating brick, and this brick is built by laying bricks or stones at impact zone (I) center or non-impact zone (II) center as required.
5. torpedo tank lining structure therewith according to claim 1 is characterized in that: described torpedo jar special brick third (6,7,8) comprise one of unit brick third (6), unit brick third two (7), unit brick third three (8); One of this unit brick third (6), unit brick third two (7), three (8) isosceles trapezoid cross section of unit brick third, the waist of its isosceles trapezoid is different with the base corner dimension, waist of one of unit brick third (6) and end angle (β 1) greater than two (7) waist and end angle (β of unit brick third 2), two (7) waist and end angle (β of unit brick third 2) greater than three (8) waist and end angle (β of unit brick third 3).
6. according to claim 1 or the described torpedo tank lining structure therewith of 5 arbitrary claims, it is characterized in that: in the big end section of described truncated cone shell inside lining building section (III) based on one of torpedo jar special brick third (6), torpedo jar special brick third two (7) for regulating brick; In the stage casing of truncated cone shell inside lining building section (III) based on two (7) of torpedo jar special brick third, torpedo jar special brick third three (8) for regulating brick; In the small end section of truncated cone shell inside lining building section (III) based on three (8) of torpedo jar special brick third.
7. torpedo tank lining structure therewith according to claim 1, it is characterized in that: the right-angled trapezium cross section of brick third (6,7,8) is built in the torpedo jar special use of described truncated cone shell inside lining building section (III) by laying bricks or stones, the right angle waist of this right-angled trapezium is built by laying bricks or stones in torpedo jar inboard, and the inclination waist contacts with spray paint (2) and builds by laying bricks or stones.
CNU2007200899431U 2007-04-09 2007-04-09 Internal lining construction of torpedo pot Expired - Fee Related CN201008968Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007200899431U CN201008968Y (en) 2007-04-09 2007-04-09 Internal lining construction of torpedo pot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007200899431U CN201008968Y (en) 2007-04-09 2007-04-09 Internal lining construction of torpedo pot

Publications (1)

Publication Number Publication Date
CN201008968Y true CN201008968Y (en) 2008-01-23

Family

ID=39043901

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007200899431U Expired - Fee Related CN201008968Y (en) 2007-04-09 2007-04-09 Internal lining construction of torpedo pot

Country Status (1)

Country Link
CN (1) CN201008968Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103350221A (en) * 2013-07-24 2013-10-16 武汉钢铁(集团)公司 Method for maintaining and building 320-ton torpedo ladle cone working layer
CN110487076A (en) * 2019-09-05 2019-11-22 首钢集团有限公司 A kind of torpedo tank liner repairing method
CN111848193A (en) * 2020-08-10 2020-10-30 河南自力耐火材料股份有限公司 Torpedo tank lining structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103350221A (en) * 2013-07-24 2013-10-16 武汉钢铁(集团)公司 Method for maintaining and building 320-ton torpedo ladle cone working layer
CN103350221B (en) * 2013-07-24 2015-06-10 武汉钢铁(集团)公司 Method for maintaining and building 320-ton torpedo ladle cone working layer
CN110487076A (en) * 2019-09-05 2019-11-22 首钢集团有限公司 A kind of torpedo tank liner repairing method
CN111848193A (en) * 2020-08-10 2020-10-30 河南自力耐火材料股份有限公司 Torpedo tank lining structure

Similar Documents

Publication Publication Date Title
CN201008968Y (en) Internal lining construction of torpedo pot
CN104529485B (en) Two-layer compound refractory material and two-layer compound refractory material ditch cover and its manufacture method and application
CN201225826Y (en) Fireproof brick anchoring piece for rotary kiln wall lining
CN207487414U (en) A kind of easily combination refractory brick
CN203401073U (en) Steel ladle bottom-covering work layer masonry construction
CN206440121U (en) A kind of brick and tile tunnel kiln car
CN202845770U (en) Lining structure of molten iron tank opening
CN211866588U (en) Steel ladle with stepped ladle bottom
CN202595182U (en) Layout structure of bottom blowing air bricks of small-scale top and bottom combined blown converter
CN207435322U (en) The energy-saving shaft furnace kiln of calcium industry
CN2516294Y (en) Continuous casting tundish impact groove
CN203269958U (en) Blast-furnace tapping channel
CN203405085U (en) Aluminum-magnesia carbon brick for steel ladle
CN201020527Y (en) Torpedo tank liner structure
CN208430207U (en) High-efficiency cleaning structure for metal smelt
CN203437605U (en) Impact cup with slag blocking and flow stabilization integrated
CN206768167U (en) A kind of masonry construction of RH refining furnaces lower channel
CN111560486A (en) Blast furnace bottom building method for guiding furnace bottom to be in shape of boiler bottom
CN2539741Y (en) Multiple output melting pool glass furnace
CN203695939U (en) Special-shaped magnesia carbon brick
CN2747529Y (en) Structure of liner for limestone kiln
CN204359118U (en) Tower molten aluminium stove melting chamber hearth structure
CN219546999U (en) Converter structure for iron and steel smelting
CN221505651U (en) Prefabricated member furnace top melting furnace capable of improving overhaul maintenance efficiency and quality
CN201828148U (en) Integrated nose brick

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080123