CN1974941A - Bottom reaming piling method - Google Patents

Bottom reaming piling method Download PDF

Info

Publication number
CN1974941A
CN1974941A CN 200610134715 CN200610134715A CN1974941A CN 1974941 A CN1974941 A CN 1974941A CN 200610134715 CN200610134715 CN 200610134715 CN 200610134715 A CN200610134715 A CN 200610134715A CN 1974941 A CN1974941 A CN 1974941A
Authority
CN
China
Prior art keywords
pile
base
immersed tube
concrete
belling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200610134715
Other languages
Chinese (zh)
Inventor
王茂华
王国奋
杨国龙
Original Assignee
王茂华
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王茂华 filed Critical 王茂华
Priority to CN 200610134715 priority Critical patent/CN1974941A/en
Publication of CN1974941A publication Critical patent/CN1974941A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The present invention discloses a construction method of building pile foundation engineering, in particular, it relates to a belling pile-forming method of pipe-sinking belled pile. Said belling pile-forming method includes the following steps: pressing the sinking pipe with metal pile head to the hard soil layer with designed level; taking out metal pile head; utilizing belling equipment to enlarge base and make the base be formed into a base hollow cavity,; using camera to record the image formation in the base hollow cavity; pouring the prepared concrete into the base hollow cavity to form concrete base; downwards placing the prefabricated reinforced concrete pile body and making said prefabricated reinforced concrete pile body and cast-in-situ concrete base be butt-connected together and anchored into one body; drawing out said sinking pipe and pouring cement slurry so as to obtain the invented pile.

Description

At the bottom of a kind of expansion, piling method
Technical field
At the bottom of the present invention relates to the expansion of a kind of construction of building pile foundation engineering, particularly ram-expanded pile, piling method.
Background technology
The quality of building foundation engineering quality will directly influence the quality of building, so each unit in charge of construction not only payes attention to the construction quality of superstructure, and more pay attention to the quality of Foundation Design.And drop into scientific research strength and tap the latent power to pile foundation engineering, make it in the utilization rate of guaranteeing to improve under the prerequisite of workmanship the strength of materials.For the expanded bore pile that improves bearing capacity of single pile, composite foundation stake etc. occur in succession, although this bearing capacity of single pile than traditional foundation pile is significantly improved, but because traditional pile foundation engineering job practices is with manually bit by bit cutting the earth, fetch earth and dig pile body soil, and for prevent that landslide from digging next section of certain depth immersed tube downwards thereupon, when waiting to dig design elevation, the people is sling, expand the end with traditional bottom-expanding equipment again, and be positioned on the hardpan, hang out after the moulding and directly water the concrete pile after bottom-expanding equipment fetches earth.Thereby visible traditional pile foundation expands the end, also there is following defective in piling method: the pile body part soil body is with manually diging up, and working face is too big, and the workload that fetches earth obviously increases, inefficiency, cost height; Bottom-expanding equipment is not owing to there is immersed tube to do support, and the location is inaccurate, and the base expanded-angle is too little, and each parameter that expands in the end process can not guarantee, thereby makes the quality of stake be not easy control, and is difficult to reach designing requirement, causes the bearing capacity of single pile to be had a greatly reduced quality; Have constructor's potential safety hazard, the constructor does not note just being prone to accidents slightly; The scope of application is narrow, not only is not suitable for the minor diameter pile body and expands the end, nor can be used for expanding the end and pile under precast pile and the high complicated geological situation.Based on above-mentioned situation, for improving bearing capacity of single pile, reduce the Foundation Design cost, must be improved.
Summary of the invention
The present invention is directed to the problem that above-mentioned technology exists, all kinds of pile bodies that are applicable to various building safety grades, geological condition are provided, guarantee the pile foundation engineering quality, obviously improve bearing capacity of single pile, improve the strength of materials and utilization rate, raising pile efficient, at the bottom of the expansion of safety, piling method.
In order to solve the problems of the technologies described above, the present invention be achieved in that expand the end, piling method is as follows: the immersed tube that it comprises following processing step: a, will have a metal pile head passes weak soil and is laminated to the design elevation hardpan; B, taking-up metal pile head are thrown away discrete object from the immersed tube mouth, cut the earth with bottom-expanding equipment and expand the bottom application worker, and the vertical earlier expansion end is the level expansion end again, expands the end and cuts the earth till reaching designing requirement base cavity pocket type; C, the surflaes in the base is taken out; D, usefulness have the video camera of light source and check in base cavity pocket whether its quality reaches designing requirement, and record by imaging is filed the correction in time of pinpointing the problems; E, will be in the good concrete of floor manufacture be packed long bucket into, be put into the immersed tube bottom from the immersed tube mouth, when being located at the iron staff contact pan soil of bucket bottom, the bucket bottom door is backed down, concrete in it falls into base cavity pocket and forms cast-in-situ base, is lowered to the precast reinforced concrete pile body and docks anchoring by its bottom joint bar with the Cast-in-place concrete base to be integral; F, extract immersed tube, along the slit grout injection pile of extracting behind the immersed tube.
Advantage of the present invention and effect are as follows:
The present invention compared with prior art, owing to utilized a series of technical measures such as immersed tube, bottom-expanding equipment and precast pile with metal pile head, and the advanced production technology of employing, there is process simply advanced through evidence, expand chamber, end regular geometry, needn't get pile body chamber soil, pile-forming speed is fast, the efficient height, and the ratio range that expands bottom face diameter and pile body cross section is big, effectively improve bearing capacity of single pile, and reach designing requirement, and guarantee the pile foundation engineering quality, reduce building costs, improve strength of materials utilization rate, stake is worked under most economical state; The scope of application is wide simultaneously, adopt the pile body and corresponding base-enlarging method, the plant equipment that are complementary with it to replace manually-operated according to building safety grade and different geological conditions, not only improve operating efficiency, shortened the construction period, but also obviously reduced the earth volume of cutting the earth, improved working security, accident potential appears in minimizing.And adopt video camera to check in base cavity pocket whether its construction quality reaches designing requirement with light source, and record by imaging is filed, pinpoint the problems and in time correct, in time adjusting job practices and material therefor when promptly pinpointing the problems adopts remedial measures, construction quality is guaranteed, and the underground construction situation can be allowed the ground handling personnel in time grasp.
The specific embodiment
The present invention expands the end, piling method: it is to be realized by following activities: a, the immersed tube that will have a metal pile head pass weak soil and are laminated to the design elevation hardpan; B, taking-up metal pile head are thrown away discrete object from the immersed tube mouth, cut the earth with bottom-expanding equipment and expand the bottom application worker, and the vertical earlier expansion end is the level expansion end again, expands the end and cuts the earth till reaching designing requirement base cavity pocket type; C, the surflaes in the base is taken out; D, usefulness have the video camera of light source and check in base cavity pocket whether its quality reaches designing requirement, and record by imaging is filed the correction in time of pinpointing the problems; E, will be in the good concrete of floor manufacture be packed long bucket into, be put into the immersed tube bottom from the immersed tube mouth, when being located at the iron staff contact pan soil of bucket bottom, the bucket bottom door is backed down, concrete in it falls into base cavity pocket and forms cast-in-situ base, is lowered to the precast reinforced concrete pile body and docks anchoring by its bottom joint bar with the Cast-in-place concrete base to be integral; F, extract immersed tube, along the slit grout injection pile of extracting behind the immersed tube.
Method of the present invention can be built according to different safety class, geological condition and adopt pile body and the base-enlarging method that is complementary with it, and the scope of application is wide.

Claims (1)

1, at the bottom of a kind of expansion, piling method, the immersed tube that it comprises following processing step: a, will have a metal pile head passes weak soil and is laminated to the design elevation hardpan; B, taking-up metal pile head are thrown away discrete object from the immersed tube mouth, cut the earth with bottom-expanding equipment and expand the bottom application worker, and the vertical earlier expansion end is the level expansion end again, expands the end and cuts the earth till reaching designing requirement base cavity pocket type; C, the surflaes in the base is taken out; D, usefulness have the video camera of light source and check in base cavity pocket whether its quality reaches designing requirement, and record by imaging is filed the correction in time of pinpointing the problems; E, will be in the good concrete of floor manufacture be packed long bucket into, be put into the immersed tube bottom from the immersed tube mouth, when being located at the iron staff contact pan soil of bucket bottom, the bucket bottom door is backed down, concrete in it falls into base cavity pocket and forms cast-in-situ base, is lowered to the precast reinforced concrete pile body and docks anchoring by its bottom joint bar with the Cast-in-place concrete base to be integral; F, extract immersed tube, along the slit grout injection pile of extracting behind the immersed tube.
CN 200610134715 2006-12-12 2006-12-12 Bottom reaming piling method Pending CN1974941A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200610134715 CN1974941A (en) 2006-12-12 2006-12-12 Bottom reaming piling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200610134715 CN1974941A (en) 2006-12-12 2006-12-12 Bottom reaming piling method

Publications (1)

Publication Number Publication Date
CN1974941A true CN1974941A (en) 2007-06-06

Family

ID=38125272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200610134715 Pending CN1974941A (en) 2006-12-12 2006-12-12 Bottom reaming piling method

Country Status (1)

Country Link
CN (1) CN1974941A (en)

Similar Documents

Publication Publication Date Title
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN105804089B (en) Locally increase deep support system and its construction method after a kind of former deep foundation pit construction
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN112030956A (en) Karst stratum bored pile construction method
CN104329020B (en) A kind of reinforced long spire embedding rock construction equipment and technique thereof
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN104762956B (en) Method for forming pile based on construction waste recycled aggregate
CN201078234Y (en) Integral hydraulic pressure steel sheet piling curtain of vertical shaft construction overflowing sand bed
CN1974939A (en) Construction foundation working method
CN1974941A (en) Bottom reaming piling method
CN1974946A (en) Bottom reaming piling technology
CN1974944A (en) Piling technology
CN1974945A (en) Construction pilling technology
CN1974940A (en) Piling method
CN1974938A (en) Pile foundation construction process
CN1974942A (en) Ground pile foundation driving construction method
CN100549307C (en) A kind of construction foundation working process
CN1320215C (en) Method for making foundation piles in high embankment region
CN1202317C (en) Rammer-expanded composite pile base construction method
CN1974937A (en) Construction foundation piling method
CN218437022U (en) Post-anchor rod construction structure
CN204002575U (en) Broken ground pore-creating device
CN217810998U (en) Construction device for improving bearing capacity of rock-socketed pile by utilizing sediments

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication