CN1858405A - Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel - Google Patents

Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel Download PDF

Info

Publication number
CN1858405A
CN1858405A CN 200610012790 CN200610012790A CN1858405A CN 1858405 A CN1858405 A CN 1858405A CN 200610012790 CN200610012790 CN 200610012790 CN 200610012790 A CN200610012790 A CN 200610012790A CN 1858405 A CN1858405 A CN 1858405A
Authority
CN
China
Prior art keywords
wall
stones
building
leiyin
laying bricks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610012790
Other languages
Chinese (zh)
Other versions
CN100494630C (en
Inventor
宋彦波
高京泽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HEBEI TONGCHENG TECHNOLOGY Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2006100127900A priority Critical patent/CN100494630C/en
Publication of CN1858405A publication Critical patent/CN1858405A/en
Application granted granted Critical
Publication of CN100494630C publication Critical patent/CN100494630C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The quick construction process of water retaining wall under high pressure surging condition in soft coal drift includes five steps of: constructing temporary water retaining wall, constructing solid temporary water retaining wall, filling, constructing main water retaining wall, etc. The process includes no carving groove in wall rock, has less engineering work load and raised construction safety, and has chemical material with high adhesion strength to coal rock used in constructing the water retaining wall capable of reaching high pressure strength within minutes.

Description

The method of constructing floodgate wall fast under the soft coal opening water gushing out with high pressure condition
Technical field
The present invention relates to a kind of method of constructing floodgate wall, the method for constructing floodgate wall fast under particularly a kind of soft coal opening water gushing out with high pressure condition.
Background technology
At present, under soft seam especially three soft-conditions during digging laneway generation high-pressure high-flow gushing water, the general method that adopts concrete to construct floodgate wall, cement injection reinforced roadway exterior wall, this methods engineering amount is great, operational difficulty, and speed of application is slow, the per pass operation all will be waited for the intensity length of time of concrete and cement paste, after engineering was all finished, floodgate wall can not come into operation at once, must wait for 28 days the intensity length of time of concrete; In addition, concrete, cement paste can produce in consolidation process and shrink, and the permeability of cement paste is bad, and the cementability of cement and coal body is relatively poor, and adhesive strength is also low, and water leakage was big after often floodgate wall built up, even caused the engineering failure.
Summary of the invention
Technical problem to be solved by this invention is to overcome existing drawback of constructing floodgate wall, usefulness cement grouting and reinforcing roadway surrounding rock method with concrete, and provide the method for constructing floodgate wall fast under a kind of soft coal opening water gushing out with high pressure condition, construct the floodgate wall body of wall with Bo Leiyin chemical water shutoff and reinforcement material, roadway surrounding rock is carried out grouting and reinforcing with Bo Leiyin chemical water shutoff and reinforcement material.
The present invention solves the technical scheme that its technical problem takes: the method for constructing floodgate wall fast under this soft coal opening water gushing out with high pressure condition is characterized in that it can be undertaken by following five steps:
A, construct the temporary water dash wall, at first pre-buried aqueduct in the clay bag of then clay being packed into, is built with clay bag vertical transport lane and to be built the temporary water dash wall, and big portion water burst is forced in the aqueduct that places;
B, construct entity temporary water dash wall one, at first build the work stone wall by laying bricks or stones in its front end vertical transport lane, between work stone wall and temporary water dash wall, with the Bo Leiyin that do not foam make bonding agent, building stones are built entity temporary water dash wall by laying bricks or stones one as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor at least before the building wall, the pre-buried Grouting Pipe that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;
C, construct the filling section, at first build the work stone wall by laying bricks or stones at its front end vertical transport inter-road, between work stone wall and entity temporary water dash wall, use instead the foaming Bo Leiyin make bonding agent, spoil/building stones are built the filling section by laying bricks or stones as aggregate, the pre-buried Grouting Pipe that goes up is built the back by laying bricks or stones and by Grouting Pipe its roadway surrounding rock is carried out grouting and reinforcing in building by laying bricks or stones;
D, construct the main body floodgate wall, at first build the work stone wall by laying bricks or stones at the vertical headentry of its front end, intersegmental at work stone wall and filling, again with the Bo Leiyin that do not foam make bonding agent, building stones are constructed the main body floodgate wall as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor at least before the building wall, the pre-buried Grouting Pipe that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;
Sprayed mortar is 3~5 meters in e, the outer tunnel of main body floodgate wall, and the grouting and reinforcing hole that is at least a row is set, and uses the hole packer sealing of hole, carries out grouting and reinforcing with Bo Leiyin chemical water shutoff and reinforcement material;
Described temporary water dash wall, entity temporary water dash wall, filling section, the every segment length of main body floodgate wall, press the adhesive strength of Bo Leiyin and aggregate and the adhesive strength and the water burst hydraulic pressure designing and calculating of both sides, tunnel country rock and determine that the adhesive strength of Bo Leiyin and aggregate and both sides, tunnel country rock should be greater than water burst hydraulic pressure.
The method of constructing floodgate wall fast under this soft coal opening water gushing out with high pressure condition provided by the present invention, wall construction needn't carry out the roadway surrounding rock slotting, significantly reduced engineering quantity, improved working security, the floodgate wall that the Bo Leiyin chemical material is constructed fast and the adhesive strength of coal and rock are than the high several times of cement, after body of wall was built several minutes, its compressive strength can reach more than the 50Mpa; In addition, the concreting that this method has been cancelled all body of wall end facing waters and backwater end protects the lane, adopt Bo Leiyin chemical material grouting and reinforcing roadway surrounding rock, its intensity and water-resistance obviously improve, save concrete fully and constructed the curing time of floodgate wall, realized the rapid construction of under soft coal opening inner high voltage water burst condition, constructing floodgate wall.
Description of drawings
Fig. 1 is for constructing the method structural representation of floodgate wall fast under the soft coal opening water gushing out with high pressure condition that the embodiment of the invention provided.
The specific embodiment
With reference to accompanying drawing, the method for constructing floodgate wall fast under this soft coal opening water gushing out with high pressure condition that the embodiment of the invention provided, it can be undertaken by following five steps:
A, construct temporary water dash wall 1, at first pre-buried aqueduct 6 in the clay bag of then clay being packed into, is built with clay bag vertical transport lane and to be built temporary water dash wall 1, and big portion water burst is forced in the aqueduct 6 that places;
B, construct entity temporary water dash wall 2 one, at first build work stone wall 10 by laying bricks or stones in its front end vertical transport lane, on 1 on work stone wall 10 and temporary water dash wall, with the Bo Leiyin that do not foam make bonding agent, building stones are built entity temporary water dash wall 2 by laying bricks or stones one as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor 9 at least before the building wall, the pre-buried Grouting Pipe 7 that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;
C, construct filling section 3, at first build work stone wall 11 by laying bricks or stones at its front end vertical transport inter-road, on 2 on work stone wall 11 and entity temporary water dash wall, use instead the foaming Bo Leiyin make bonding agent, spoil/building stones are built filling section 3 by laying bricks or stones as aggregate, the pre-buried Grouting Pipe 7 that goes up is built the back by laying bricks or stones and by Grouting Pipe its roadway surrounding rock is carried out grouting and reinforcing in building by laying bricks or stones;
D, construct main body floodgate wall 4, at first build work stone wall 12 by laying bricks or stones at the vertical headentry of its front end, 3 of work stone wall 12 and filling sections, again with the Bo Leiyin that do not foam make bonding agent, building stones are constructed main body floodgate wall 4 as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor 9 at least before the building wall, the pre-buried Grouting Pipe 7 that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;
Sprayed mortar is 3~5 meters in e, the main body floodgate wall 4 outer tunnels 5, and the grouting and reinforcing hole 8 that is at least a row is set, and uses the hole packer sealing of hole, carries out grouting and reinforcing with Bo Leiyin chemical water shutoff and reinforcement material;
Described temporary water dash wall 1, entity temporary water dash wall 2, filling section 3, main body floodgate wall 4 every segment length, press the adhesive strength of Bo Leiyin and aggregate and the adhesive strength and the water burst hydraulic pressure designing and calculating of both sides, tunnel country rock and determine that the adhesive strength of Bo Leiyin and aggregate and both sides, tunnel country rock should be greater than water burst hydraulic pressure.
Described Bo Leiyin chemical water shutoff material is that effluent north is with the organic polymer dual-liquid slip-casting material that becomes the development of mining industry Science and Technology Ltd., these slurries have higher bonding force and mechanical performance preferably, with the rock stratum affinity is preferably arranged, the flexility of induration bears certain stratum deformation, after material injected the rock stratum, low viscosity mixtures kept several seconds kinds, penetrated into tiny crack and expanded, be applied at present under the coal mine, its Bo Leiyin performance indications are as follows:
1. emulsification times 10~15s
2. time 50~60s does not touch with one's hand
3. induration density 400~1250Kg/m 3
4. compressive strength 30~50Mpa
5. the fire-retardant oxygen index (OI) of fire resistance is greater than 26%
6. adhesive strength 30~50Mpa
7. serum density 1200Kg/m 3
8. slurry viscosity 225~300mpa.s
9. the biliquid mixing ratio is 1: 1
10. expansion multiple 1~3.

Claims (1)

  1. The method of constructing floodgate wall fast under 1 one kinds of soft coal opening water gushing out with high pressure conditions, it is characterized in that: it can be undertaken by following five steps:
    A, construct temporary water dash wall (1), at first pre-buried aqueduct (6) in the clay bag of then clay being packed into, is built with clay bag vertical transport lane and to be built temporary water dash wall (1), in the aqueduct (6) that big portion water burst is forced place;
    B, construct one entity temporary water dash wall (2), at first build work stone wall (10) by laying bricks or stones in its front end vertical transport lane, between work stone wall (10) and temporary water dash wall (1), with the Bo Leiyin that do not foam make bonding agent, building stones are built one entity temporary water dash wall (2) by laying bricks or stones as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor (9) at least before the building wall, the pre-buried Grouting Pipe (7) that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;
    C, construct filling section (3), at first build work stone wall (11) by laying bricks or stones at its front end vertical transport inter-road, between work stone wall (11) and entity temporary water dash wall (2), use instead the foaming Bo Leiyin make bonding agent, spoil/building stones are built filling section (3) by laying bricks or stones as aggregate, the pre-buried Grouting Pipe (7) that goes up is built the back by laying bricks or stones and by Grouting Pipe its roadway surrounding rock is carried out grouting and reinforcing in building by laying bricks or stones;
    D, construct main body floodgate wall (4), at first build work stone wall (12) by laying bricks or stones at the vertical headentry of its front end, between work stone wall (12) and filling section (3), again with the Bo Leiyin that do not foam make bonding agent, building stones are constructed main body floodgate wall (4) as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor (9) at least before the building wall, the pre-buried Grouting Pipe (7) that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;
    3~5 meters of e, the interior sprayed mortars in the outer tunnel of main body floodgate wall (4) (5), and the grouting and reinforcing hole (8) that is at least a row is set, use the hole packer sealing of hole, carry out grouting and reinforcing with Bo Leiyin chemical water shutoff and reinforcement material;
    Described temporary water dash wall (1), entity temporary water dash wall (2), filling section (3), the every segment length of main body floodgate wall (4), press the adhesive strength of Bo Leiyin and aggregate and the adhesive strength and the water burst hydraulic pressure designing and calculating of both sides, tunnel country rock and determine that the adhesive strength of Bo Leiyin and aggregate and both sides, tunnel country rock should be greater than water burst hydraulic pressure.
CNB2006100127900A 2006-06-06 2006-06-06 Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel Active CN100494630C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100127900A CN100494630C (en) 2006-06-06 2006-06-06 Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100127900A CN100494630C (en) 2006-06-06 2006-06-06 Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel

Publications (2)

Publication Number Publication Date
CN1858405A true CN1858405A (en) 2006-11-08
CN100494630C CN100494630C (en) 2009-06-03

Family

ID=37297352

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100127900A Active CN100494630C (en) 2006-06-06 2006-06-06 Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel

Country Status (1)

Country Link
CN (1) CN100494630C (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121388A (en) * 2011-01-11 2011-07-13 河北同成矿业科技有限公司 Method for quickly constructing water gate wall
CN103422469A (en) * 2013-08-14 2013-12-04 中国神华能源股份有限公司 Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks
CN110307015A (en) * 2019-07-26 2019-10-08 安徽马钢矿业资源集团有限公司 A kind of packaged type tunnel waterproofing device and method
CN112627893A (en) * 2020-12-22 2021-04-09 河南理工大学 3D printing water gate wall and assembling method thereof
CN114704322A (en) * 2022-03-16 2022-07-05 中国矿业大学 Catchment prevention and control method for goaf without coal pillars

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121388A (en) * 2011-01-11 2011-07-13 河北同成矿业科技有限公司 Method for quickly constructing water gate wall
CN102121388B (en) * 2011-01-11 2013-07-10 河北同成科技股份有限公司 Method for quickly constructing water gate wall
CN103422469A (en) * 2013-08-14 2013-12-04 中国神华能源股份有限公司 Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks
CN103422469B (en) * 2013-08-14 2014-09-10 中国神华能源股份有限公司 Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks
RU2606790C1 (en) * 2013-08-14 2017-01-10 Чайна Шэньхуа Энерджи Компани Лимитед Coal mine underground reservoir artificial retaining dam and safety coal pillar, surrounding rock and retaining dam connection method
CN110307015A (en) * 2019-07-26 2019-10-08 安徽马钢矿业资源集团有限公司 A kind of packaged type tunnel waterproofing device and method
CN112627893A (en) * 2020-12-22 2021-04-09 河南理工大学 3D printing water gate wall and assembling method thereof
CN114704322A (en) * 2022-03-16 2022-07-05 中国矿业大学 Catchment prevention and control method for goaf without coal pillars

Also Published As

Publication number Publication date
CN100494630C (en) 2009-06-03

Similar Documents

Publication Publication Date Title
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN103184734B (en) A kind of construction method implanting slip casting compound pile
CN104612134A (en) Cast-in place pile post-grouting construction method for pouring construction
CN107725056A (en) One kind passes through silly stratum tunnel loopful quick grouting construction method in advance
CN101130991A (en) Caisson cofferdam based on prepacked foundation bed
CN100494630C (en) Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel
WO2020098033A1 (en) Supporting structural body for local goaf filling under hard roof conditions and construction method therefor
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN102121388B (en) Method for quickly constructing water gate wall
CN1760455A (en) Method for treating collapsed road surface around inspection-pit for underground lines
CN1067453C (en) Foundation pit slope flat anchor spray net supporting method
CN104879149A (en) Bolt-grouting support method for roadway in three-soft high-stress region
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
KR101542078B1 (en) Soil retaining wall structure and Method for constructinging the same
CN101705788B (en) Construction method using blowout plug to shield oblique drilling hole
CN102535518B (en) Plugging method of large seam of underground diaphragm wall
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN113445516A (en) Drilling and pouring type cement soil pile and construction method thereof
CN1461857A (en) Construction method and its use
Shimada et al. Performance of mortar and chemical grout injection into surrounding soil when slurry pipe-jacking method is used
CN113914874A (en) Large-scale geological abnormal fault zone roadway surrounding rock ultra-long distance pre-reinforcement method
Tung et al. Application of pile bottom post-grouting technology to increase the bearing capacity of bored piles in Vietnam
CN1144916C (en) Continuous wall constructing method including drilling holes and late grouting
CN112963119A (en) Induced splitting grouting reinforcement method suitable for silt silty soil stratum
Peng et al. Property prediction methods of granular soil penetration grouting reinforced body based on fractal theory and Mori-Tanaka method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hebei Tongcheng Mining Technology Co., Ltd.

Assignor: Song Yanbo

Contract record no.: 2011130000018

Denomination of invention: Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel

Granted publication date: 20090603

License type: Exclusive License

Open date: 20061108

Record date: 20110228

ASS Succession or assignment of patent right

Owner name: HEBEI TONGCHENG MINING TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: SONG YANBO

Effective date: 20120614

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 054000 XINGTAI, HEBEI PROVINCE TO: 054001 XINGTAI, HEBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120614

Address after: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China

Patentee after: Hebei Tongcheng Mining Technology Co., Ltd.

Address before: Xingtai City, Hebei province 054000 GuoShouJing Road No. 386

Patentee before: Song Yanbo

C56 Change in the name or address of the patentee

Owner name: HEBEI TONGCHENG TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: HEBEI TONGCHENG MINING TECHNOLOGY CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China

Patentee after: Hebei Tongcheng Technology Co., Ltd.

Address before: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China

Patentee before: Hebei Tongcheng Mining Technology Co., Ltd.

C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 054001 No. 1666, main street, Xingtai Economic Development Zone, Hebei

Patentee after: Hebei Tongcheng Technology Co., Ltd.

Address before: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China

Patentee before: Hebei Tongcheng Technology Co., Ltd.