CN1858405A - Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel - Google Patents
Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel Download PDFInfo
- Publication number
- CN1858405A CN1858405A CN 200610012790 CN200610012790A CN1858405A CN 1858405 A CN1858405 A CN 1858405A CN 200610012790 CN200610012790 CN 200610012790 CN 200610012790 A CN200610012790 A CN 200610012790A CN 1858405 A CN1858405 A CN 1858405A
- Authority
- CN
- China
- Prior art keywords
- wall
- stones
- building
- leiyin
- laying bricks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 56
- 239000003245 coal Substances 0.000 title claims abstract description 15
- 238000000034 method Methods 0.000 title claims abstract description 15
- 238000001363 water suppression through gradient tailored excitation Methods 0.000 title 1
- 239000011435 rock Substances 0.000 claims abstract description 30
- 239000000463 material Substances 0.000 claims abstract description 11
- 239000000126 substance Substances 0.000 claims abstract description 9
- 239000004575 stone Substances 0.000 claims description 48
- 239000011449 brick Substances 0.000 claims description 21
- 230000003014 reinforcing effect Effects 0.000 claims description 18
- 239000000853 adhesive Substances 0.000 claims description 12
- 230000001070 adhesive effect Effects 0.000 claims description 12
- 239000007767 bonding agent Substances 0.000 claims description 9
- 239000004927 clay Substances 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000006260 foam Substances 0.000 claims description 6
- 239000011347 resin Substances 0.000 claims description 6
- 229920005989 resin Polymers 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 5
- 238000005187 foaming Methods 0.000 claims description 3
- 239000004570 mortar (masonry) Substances 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 4
- 239000007787 solid Substances 0.000 abstract 1
- 239000004568 cement Substances 0.000 description 7
- 239000004567 concrete Substances 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 2
- 239000002002 slurry Substances 0.000 description 2
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000004945 emulsification Methods 0.000 description 1
- 239000003063 flame retardant Substances 0.000 description 1
- 238000007429 general method Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 229920000620 organic polymer Polymers 0.000 description 1
- 229910052760 oxygen Inorganic materials 0.000 description 1
- 239000001301 oxygen Substances 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 210000002966 serum Anatomy 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
Claims (1)
- The method of constructing floodgate wall fast under 1 one kinds of soft coal opening water gushing out with high pressure conditions, it is characterized in that: it can be undertaken by following five steps:A, construct temporary water dash wall (1), at first pre-buried aqueduct (6) in the clay bag of then clay being packed into, is built with clay bag vertical transport lane and to be built temporary water dash wall (1), in the aqueduct (6) that big portion water burst is forced place;B, construct one entity temporary water dash wall (2), at first build work stone wall (10) by laying bricks or stones in its front end vertical transport lane, between work stone wall (10) and temporary water dash wall (1), with the Bo Leiyin that do not foam make bonding agent, building stones are built one entity temporary water dash wall (2) by laying bricks or stones as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor (9) at least before the building wall, the pre-buried Grouting Pipe (7) that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;C, construct filling section (3), at first build work stone wall (11) by laying bricks or stones at its front end vertical transport inter-road, between work stone wall (11) and entity temporary water dash wall (2), use instead the foaming Bo Leiyin make bonding agent, spoil/building stones are built filling section (3) by laying bricks or stones as aggregate, the pre-buried Grouting Pipe (7) that goes up is built the back by laying bricks or stones and by Grouting Pipe its roadway surrounding rock is carried out grouting and reinforcing in building by laying bricks or stones;D, construct main body floodgate wall (4), at first build work stone wall (12) by laying bricks or stones at the vertical headentry of its front end, between work stone wall (12) and filling section (3), again with the Bo Leiyin that do not foam make bonding agent, building stones are constructed main body floodgate wall (4) as aggregate, roadway surrounding rock is provided with row's screw-thread steel resin anchor (9) at least before the building wall, the pre-buried Grouting Pipe (7) that goes up is carried out grouting and reinforcing by Grouting Pipe to its roadway surrounding rock behind the building wall in the building wall;3~5 meters of e, the interior sprayed mortars in the outer tunnel of main body floodgate wall (4) (5), and the grouting and reinforcing hole (8) that is at least a row is set, use the hole packer sealing of hole, carry out grouting and reinforcing with Bo Leiyin chemical water shutoff and reinforcement material;Described temporary water dash wall (1), entity temporary water dash wall (2), filling section (3), the every segment length of main body floodgate wall (4), press the adhesive strength of Bo Leiyin and aggregate and the adhesive strength and the water burst hydraulic pressure designing and calculating of both sides, tunnel country rock and determine that the adhesive strength of Bo Leiyin and aggregate and both sides, tunnel country rock should be greater than water burst hydraulic pressure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100127900A CN100494630C (en) | 2006-06-06 | 2006-06-06 | Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100127900A CN100494630C (en) | 2006-06-06 | 2006-06-06 | Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1858405A true CN1858405A (en) | 2006-11-08 |
CN100494630C CN100494630C (en) | 2009-06-03 |
Family
ID=37297352
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2006100127900A Active CN100494630C (en) | 2006-06-06 | 2006-06-06 | Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100494630C (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102121388A (en) * | 2011-01-11 | 2011-07-13 | 河北同成矿业科技有限公司 | Method for quickly constructing water gate wall |
CN103422469A (en) * | 2013-08-14 | 2013-12-04 | 中国神华能源股份有限公司 | Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks |
CN110307015A (en) * | 2019-07-26 | 2019-10-08 | 安徽马钢矿业资源集团有限公司 | A kind of packaged type tunnel waterproofing device and method |
CN112627893A (en) * | 2020-12-22 | 2021-04-09 | 河南理工大学 | 3D printing water gate wall and assembling method thereof |
CN114704322A (en) * | 2022-03-16 | 2022-07-05 | 中国矿业大学 | Catchment prevention and control method for goaf without coal pillars |
-
2006
- 2006-06-06 CN CNB2006100127900A patent/CN100494630C/en active Active
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102121388A (en) * | 2011-01-11 | 2011-07-13 | 河北同成矿业科技有限公司 | Method for quickly constructing water gate wall |
CN102121388B (en) * | 2011-01-11 | 2013-07-10 | 河北同成科技股份有限公司 | Method for quickly constructing water gate wall |
CN103422469A (en) * | 2013-08-14 | 2013-12-04 | 中国神华能源股份有限公司 | Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks |
CN103422469B (en) * | 2013-08-14 | 2014-09-10 | 中国神华能源股份有限公司 | Artificial retaining dam for coal mine underground reservoir and connecting method of artificial retaining dam and coal pillar dam bodies as well as surrounding rocks |
RU2606790C1 (en) * | 2013-08-14 | 2017-01-10 | Чайна Шэньхуа Энерджи Компани Лимитед | Coal mine underground reservoir artificial retaining dam and safety coal pillar, surrounding rock and retaining dam connection method |
CN110307015A (en) * | 2019-07-26 | 2019-10-08 | 安徽马钢矿业资源集团有限公司 | A kind of packaged type tunnel waterproofing device and method |
CN112627893A (en) * | 2020-12-22 | 2021-04-09 | 河南理工大学 | 3D printing water gate wall and assembling method thereof |
CN114704322A (en) * | 2022-03-16 | 2022-07-05 | 中国矿业大学 | Catchment prevention and control method for goaf without coal pillars |
Also Published As
Publication number | Publication date |
---|---|
CN100494630C (en) | 2009-06-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20140314497A1 (en) | Polymer grouting method for constructing gravel pile | |
CN103184734B (en) | A kind of construction method implanting slip casting compound pile | |
CN104612134A (en) | Cast-in place pile post-grouting construction method for pouring construction | |
CN107725056A (en) | One kind passes through silly stratum tunnel loopful quick grouting construction method in advance | |
CN101130991A (en) | Caisson cofferdam based on prepacked foundation bed | |
CN100494630C (en) | Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel | |
WO2020098033A1 (en) | Supporting structural body for local goaf filling under hard roof conditions and construction method therefor | |
CN103603379A (en) | Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system | |
CN102121388B (en) | Method for quickly constructing water gate wall | |
CN1760455A (en) | Method for treating collapsed road surface around inspection-pit for underground lines | |
CN1067453C (en) | Foundation pit slope flat anchor spray net supporting method | |
CN104879149A (en) | Bolt-grouting support method for roadway in three-soft high-stress region | |
CN106837382A (en) | A kind of subway tunnel country rock pre grouting from the surface reinforcement process | |
KR101542078B1 (en) | Soil retaining wall structure and Method for constructinging the same | |
CN101705788B (en) | Construction method using blowout plug to shield oblique drilling hole | |
CN102535518B (en) | Plugging method of large seam of underground diaphragm wall | |
CN203613568U (en) | Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system | |
CN113445516A (en) | Drilling and pouring type cement soil pile and construction method thereof | |
CN1461857A (en) | Construction method and its use | |
Shimada et al. | Performance of mortar and chemical grout injection into surrounding soil when slurry pipe-jacking method is used | |
CN113914874A (en) | Large-scale geological abnormal fault zone roadway surrounding rock ultra-long distance pre-reinforcement method | |
Tung et al. | Application of pile bottom post-grouting technology to increase the bearing capacity of bored piles in Vietnam | |
CN1144916C (en) | Continuous wall constructing method including drilling holes and late grouting | |
CN112963119A (en) | Induced splitting grouting reinforcement method suitable for silt silty soil stratum | |
Peng et al. | Property prediction methods of granular soil penetration grouting reinforced body based on fractal theory and Mori-Tanaka method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Assignee: Hebei Tongcheng Mining Technology Co., Ltd. Assignor: Song Yanbo Contract record no.: 2011130000018 Denomination of invention: Method for quick constructing water gate wall under high pressure surging water in soft coal tunnel Granted publication date: 20090603 License type: Exclusive License Open date: 20061108 Record date: 20110228 |
|
ASS | Succession or assignment of patent right |
Owner name: HEBEI TONGCHENG MINING TECHNOLOGY CO., LTD. Free format text: FORMER OWNER: SONG YANBO Effective date: 20120614 |
|
C41 | Transfer of patent application or patent right or utility model | ||
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 054000 XINGTAI, HEBEI PROVINCE TO: 054001 XINGTAI, HEBEI PROVINCE |
|
TR01 | Transfer of patent right |
Effective date of registration: 20120614 Address after: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China Patentee after: Hebei Tongcheng Mining Technology Co., Ltd. Address before: Xingtai City, Hebei province 054000 GuoShouJing Road No. 386 Patentee before: Song Yanbo |
|
C56 | Change in the name or address of the patentee |
Owner name: HEBEI TONGCHENG TECHNOLOGY CO., LTD. Free format text: FORMER NAME: HEBEI TONGCHENG MINING TECHNOLOGY CO., LTD. |
|
CP01 | Change in the name or title of a patent holder |
Address after: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China Patentee after: Hebei Tongcheng Technology Co., Ltd. Address before: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China Patentee before: Hebei Tongcheng Mining Technology Co., Ltd. |
|
C56 | Change in the name or address of the patentee | ||
CP02 | Change in the address of a patent holder |
Address after: 054001 No. 1666, main street, Xingtai Economic Development Zone, Hebei Patentee after: Hebei Tongcheng Technology Co., Ltd. Address before: Three Jiangdong Road, Xingtai Development Zone, Hebei 054001, China Patentee before: Hebei Tongcheng Technology Co., Ltd. |