CN1619097A - Method of regulating layered water distribution using pressure wave - Google Patents

Method of regulating layered water distribution using pressure wave Download PDF

Info

Publication number
CN1619097A
CN1619097A CN 200410061228 CN200410061228A CN1619097A CN 1619097 A CN1619097 A CN 1619097A CN 200410061228 CN200410061228 CN 200410061228 CN 200410061228 A CN200410061228 A CN 200410061228A CN 1619097 A CN1619097 A CN 1619097A
Authority
CN
China
Prior art keywords
pressure
injection well
water
flow regulator
downhole flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200410061228
Other languages
Chinese (zh)
Other versions
CN100422504C (en
Inventor
陈琳
吴杰
陈爱民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Huayou Oil Technology Development Co ltd
Daqing Oilfield Co ltd No 1 Oil Production Plant
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2004100612288A priority Critical patent/CN100422504C/en
Publication of CN1619097A publication Critical patent/CN1619097A/en
Application granted granted Critical
Publication of CN100422504C publication Critical patent/CN100422504C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The method for regulating and controlling layer water distribution by using pressure wave relates to layer water distribution operation in water injection well of oil field. Said method is characterized by adopting the following measures: using high-pressure water produced by ground high-pressure pump as pressure source, arranging pressure-controlled water distributors capable of receiving ground pressure signals, coding said pressure signals, making program for receiving and executing these signals, placing water injection pipe into injection well, operating pressure source and valve mounted on the wellhead equipment to produce water-carrying area change.

Description

Method with compression wave regulation and control layering water distribution
Technical field:
The present invention relates to the operation of layering water distribution in the water injection well in oil fields.
Background technology:
The oil-field flooding displacement of reservoir oil exploitation middle and later periods needs at each interval distribution of remaining oil situation each oil layer section to be carried out water distribution, makes each oil layer section be adjusted to suitable degree because of the power that water filling obtains by rational layering water distribution, thereby improves oil well yield.
Displacement of reservoir oil by filling water is to realize by the water injection well that adjacent interval with oil well communicates.Be provided with a water injection string in water injection well, this tubing string is made up of water injection pipe, packer, injection well downhole flow regulator etc., is separated by packer between each interval, and injection well downhole flow regulator is contained on the water injection pipe between the packer, is adorning the water with a certain aperture in the blanking plug on the injection well downhole flow regulator and is chewing.The layering water distribution is exactly to chew by the water of changing different apertures, and water injection rate is changed.
The method of the current layering water distribution of adopting, implement by the pulling operation: operating personnel arrive special tool in the interval that needs replacing water to chew by relevant device to water injection string under well head, blanking plug on this place's injection well downhole flow regulator taken off pull ground out, replacing water is chewed, and renders to this place again and installs.
Because pulling operation technique complexity, difficulty of construction are big, add factors such as well depth and fouling, the repeatedly unsuccessful situation of pulling operation is happened occasionally, and the replacing that each interval water is chewed must be carried out one by one.Thereby layering water distribution task difficulty is big, long construction period.
Summary of the invention:
Purpose of the present invention provides a kind of alternative pulling operation, thereby realizes the method for layering water distribution with each interval injection well downhole flow regulator discharge area, compression wave regulation and control down-hole on ground, reaches both simple and easy, improves water distribution usefulness again.
The method that realizes above-mentioned purpose is:
According to the interval quantity of water injection well needs water distribution, one group of voltage-controlled injection well downhole flow regulator that can receive the ground pressure signal is respectively set the pressure signal coding of position and action, the program that receives and carry out these signals is set;
The water injection pipe that the voltage-controlled injection well downhole flow regulator that possesses above-mentioned setting is housed is lowered in the well, and makes that each injection well downhole flow regulator is positioned at corresponding interval on it;
Make pressure source with the water under high pressure that the ground high-pressure pump produces,, the voltage-controlled injection well downhole flow regulator on the interval of the needs adjustment water yield is sent and the corresponding pressure code signal of its action, make it to produce the variation of discharge area by the valve on operating pressure source and the wellhead assembly.
Voltage-controlled injection well downhole flow regulator of the present invention is made up of pressure sensor 1, control circuit 2, motor 3, gate mechanism 4, sees Fig. 2.Be composed of program in the control circuit, can judge that pressure signal that pressure sensor receives is whether identical with the set pressure signal coding of this injection well downhole flow regulator and send the corresponding action instruction according to the information that coding transmits; Motor just or counter-rotating and the revolution or the angle of changeing regulation, drives the gate mechanism action and the discharge area is increased or dwindles under the control of action command.
Described pressure coding is taked by address code and action code combined.
Described pressure signal is the various pressure waveforms that are made of pressure and time.
The described water injection string that voltage-controlled injection well downhole flow regulator is housed is that the corresponding interval place between the packer on the existing water injection string 5 is provided with voltage-controlled injection well downhole flow regulator P respectively 1, P 2, P 3Constitute, see Fig. 1.
Water under high pressure is connected with wellhead assembly by pipeline during work, and the valve on operate high pressure pump and the wellhead assembly produces pressure to be changed, and forms code signal.
Open the valve on pressure source and the wellhead assembly, pressure signal is sent to the voltage-controlled injection well downhole flow regulator of each interval, and the pressure sensor of each injection well downhole flow regulator enters the information capture program after receiving the signal call.The well head workman produces the code signal of arranging mutually with each voltage-controlled injection well downhole flow regulator of down-hole by the waveform operation of setting that is made of pressure and time.When a certain coding that the signal that receives when voltage-controlled injection well downhole flow regulator is set with oneself was identical, control circuit made motor send instruction by code signal, drove gate mechanism and carried out corresponding actions, perhaps opened greatly or turned down.
During layering water distribution operation, the well head operative employee presses constructure scheme, and the voltage-controlled injection well downhole flow regulator to the interval of needs adjustment sends corresponding pressure code signal respectively, and full well water distribution construction is promptly accused and finished.
Advantage of the present invention:
1. utilize the ground existing equipment to encode, carry out remote control in the face of each water injection rate of interval of down-hole with being implemented in, greatly reduced existing difficulty of carrying out the layering water distribution, reduce operating personnel, simplified implement with the pulling operation by pressure.
2. operate simple and easy, convenient and high efficiency, reliable for effect.
Description of drawings:
Fig. 1 is the schematic diagram that the water injection string of voltage-controlled injection well downhole flow regulator is housed;
Fig. 2 is the structural representation that is contained in the voltage-controlled injection well downhole flow regulator on the water injection string;
Fig. 3 is the water injection well schematic diagram that is provided with the water injection string with voltage-controlled injection well downhole flow regulator;
Fig. 4 is voltage-controlled injection well downhole flow regulator P 1Open the pressure waveform figure of the 1st grade of pairing coding;
Fig. 5 is voltage-controlled injection well downhole flow regulator P 2Open the pressure waveform figure of the 15th grade of pairing coding;
Fig. 6 is voltage-controlled injection well downhole flow regulator P 3Close the pressure waveform figure of pairing coding.
The specific embodiment:
Is that the invention will be further described for example below in conjunction with Fig. 1, Fig. 3, Fig. 4 with the water injection well of three need control intervals.
To the voltage-controlled injection well downhole flow regulator of forming by pressure sensor, control circuit, motor, gate mechanism, by injection well downhole flow regulator interval that will place and the various discharge areas that need to realize, establishment is provided with the program that receives and carry out described coding by address code and the combined coding of action code in control circuit.
This example will be to placing the injection well downhole flow regulator P at Fig. 3 interval 1, interval 2, interval 3 places 1, P 2, P 3The coding that is provided with adopts seven binary system government establishments laws, and front three is an address code, and back four is action code, and a kind of address code and multiple action code are combined, to realize the multiple water grade of crossing of an injection well downhole flow regulator.The action code that this example adopted has 16 kinds, and from 0000~1111, wherein 0000 is the action code of closing, and opens the action code of 15 gears from 0001~1111 for the injection well downhole flow regulator gate.
Set: P 115 gears opening be encoded to 0010001,0010010,0010011,
0011111
P 1The rock sign indicating number of closing is 0010000
P 215 gears opening be encoded to 0100001,0100010,0100011,
0101111
P 2That closes is encoded to 0100000
P 315 gears opening be encoded to 0110001,0110010,0110011,
0111111
P 3That closes is encoded to 0110000
The shared time of each code name is 5 minutes in the coding, and pressure>5MPa is " 1 ", and<5MPa is " 0 ".
In the above-mentioned coding, with P 10010001, P 20101111, P 30110000 be example, draw oscillogram, see Fig. 4, Fig. 5, Fig. 6.
When water injection well is constructed, the voltage-controlled injection well downhole flow regulator P of above-mentioned setting will have been finished 1, P 2, P 3Be installed to as shown in Figure 1 between water injection pipe 6 upper packers 5 according to the interval that respectively sets, be lowered in the water injection well 7, the corresponding corresponding interval of each voltage-controlled injection well downhole flow regulator is referring to Fig. 3.
In the time will carrying out the water distribution operation, utilize the ground high-pressure pump to produce pressure, the water injection rate definite according to constructure scheme, by respective coding waveform operation wellhead assembly valve, signal is sent to each voltage-controlled injection well downhole flow regulator, make its gate be in corresponding position, finish layering water distribution operation.
Below to open voltage-controlled injection well downhole flow regulator P 1The 1st grade of transmission for example explanation pressure coding.
P 1Open the 1st grade be encoded to 0010001, oscillogram is seen Fig. 4.
Before sending each group coding signal, add send out that a force value is that 5MPa is above, the time is 1 minute synchronizing signal, T represents among Fig. 4.
Operation produces the high-pressure pump and the wellhead assembly valve of water under high pressure:
1. the transmission synchronizing signal is added to well head pressure more than the 5MPa, keeps returning after 1 minute dropping to<5MPa pressure.
2. send 0 signal rose under<5MPa pressure and keeps 5 minutes again, voltage-controlled injection well downhole flow regulator P on the 5th minute 1At this moment detected pressure<5MPa receives 0 signal.
3. send 0 signal and kept 5 minutes from the 10th minute with<5MPa pressure, second 0 signal receives.
4. send 1 signal from the 15th minute, be raised to pressure more than the 5MPa and kept the voltage-controlled injection well downhole flow regulator P of down-hole 5 minutes 1Detected pressure signal>5MPa receives 1 signal.
5. send 0 signal pressure to be reduced to<5MPa and kept the voltage-controlled injection well downhole flow regulator P of down-hole 15 minutes from the 20th minute 1Successively three 0 signals are received.
6. be raised to pressure more than the 5MPa from the 35th minute and kept voltage-controlled injection well downhole flow regulator P 5 minutes 11 signal is received.
Open P 1The 1st grade pressure coding 0010001 sends and finishes.
By that analogy, finish the coding transmission of each interval.

Claims (4)

1. regulate and control the method for layering water distribution with compression wave, it is characterized in that: according to the interval quantity of water injection well needs water distribution, one group of voltage-controlled injection well downhole flow regulator that can receive the ground pressure signal is respectively set the pressure signal coding of position and action, the program that receives and carry out these signals is set; The water injection string that the voltage-controlled injection well downhole flow regulator that possesses above-mentioned setting is housed is lowered in the water injection well, and makes that each injection well downhole flow regulator is positioned at corresponding interval on it; Make pressure source with the water under high pressure that high-pressure pump produces,, the voltage-controlled injection well downhole flow regulator on the interval of the needs adjustment water yield is sent and the corresponding pressure code signal of its action, make it to produce the variation of discharge area by the valve on operating pressure source and the wellhead assembly.
2. according to the method with compression wave regulation and control layering water distribution of claim 1, it is characterized in that described pressure signal coding is taked by address code and action code combined.
3. according to the method with compression wave regulation and control layering water distribution of claim 1, it is characterized in that described pressure signal is the various pressure waveforms that are made of pressure and time.
4. according to the method with compression wave regulation and control layering water distribution of claim 1 and 2, it is characterized in that a kind of address code and the combination of multiple action code make the discharge area of voltage-controlled injection well downhole flow regulator produce a plurality of gears.
CNB2004100612288A 2004-11-27 2004-11-27 Method of regulating layered water distribution using pressure wave Expired - Fee Related CN100422504C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004100612288A CN100422504C (en) 2004-11-27 2004-11-27 Method of regulating layered water distribution using pressure wave

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004100612288A CN100422504C (en) 2004-11-27 2004-11-27 Method of regulating layered water distribution using pressure wave

Publications (2)

Publication Number Publication Date
CN1619097A true CN1619097A (en) 2005-05-25
CN100422504C CN100422504C (en) 2008-10-01

Family

ID=34764459

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100612288A Expired - Fee Related CN100422504C (en) 2004-11-27 2004-11-27 Method of regulating layered water distribution using pressure wave

Country Status (1)

Country Link
CN (1) CN100422504C (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101883910A (en) * 2007-10-16 2010-11-10 弗米尔制造公司 The equipment and the method that are used for the power control of horizontal directional drilling
CN102839954A (en) * 2011-06-24 2012-12-26 中国石油化工股份有限公司 Method for achieving separated layer water distribution by pressure pulse
CN102839952A (en) * 2011-06-24 2012-12-26 中国石油化工股份有限公司 Device and method for data transmission during underground integrated communication
CN106761609A (en) * 2015-11-24 2017-05-31 中国石油化工股份有限公司 The underground turbine generation automatically controlled water injection string of pressure transmission signal
CN108121369A (en) * 2017-12-20 2018-06-05 中国石油天然气股份有限公司 A kind of Intelligent water injection remote control apparatus and method
CN108397173A (en) * 2018-02-07 2018-08-14 中国石油天然气股份有限公司 Seperated layer water injection system and layered water injection method
CN109372479A (en) * 2017-11-07 2019-02-22 中国石油化工股份有限公司 Water injection well wireless test and control separate injection tubing string
CN114622879A (en) * 2020-12-10 2022-06-14 中国石油天然气股份有限公司 Layered water injection wireless communication method and wireless two-way communication device
CN115059438A (en) * 2022-05-30 2022-09-16 西安思坦仪器股份有限公司 Water injection allocation method for wave code injection well
CN118065820A (en) * 2024-04-17 2024-05-24 大庆长垣能源科技有限公司 Piezoelectric switch control toe end sliding sleeve based on precoding uniqueness identification

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109854216B (en) * 2019-03-18 2021-04-23 中国石油化工股份有限公司 Layered water injection method for water injection well multilayer separate injection distributed communication

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1279338A (en) * 1999-07-06 2001-01-10 曹平生 Electrically controlled layered injection and schedule of water for water injection wells in oil field
CN2417288Y (en) * 2000-03-18 2001-01-31 大庆油田有限责任公司第二采油厂 Switching and offcenter type lamination water injection equipment
CN1141491C (en) * 2000-12-12 2004-03-10 中国石化胜利油田有限公司采油工艺研究院 Stratum-changing production method and technical pipe column
CN2480545Y (en) * 2001-05-25 2002-03-06 中国石化胜利油田有限公司临盘采油厂 Downhole fixed pressure opened constant flow water-making up apparatus
CN1525041A (en) * 2003-09-16 2004-09-01 贵州航天凯山石油仪器有限公司 Automatic adjustment method for injection allocation quantity of oil field water injection well

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101883910B (en) * 2007-10-16 2013-11-06 弗米尔制造公司 Devices and methods for power control in horizontal directional drilling
CN101883910A (en) * 2007-10-16 2010-11-10 弗米尔制造公司 The equipment and the method that are used for the power control of horizontal directional drilling
CN102839954A (en) * 2011-06-24 2012-12-26 中国石油化工股份有限公司 Method for achieving separated layer water distribution by pressure pulse
CN102839952A (en) * 2011-06-24 2012-12-26 中国石油化工股份有限公司 Device and method for data transmission during underground integrated communication
CN102839954B (en) * 2011-06-24 2015-10-07 中国石油化工股份有限公司 A kind of pressure pulse realizes the method for layering water distribution
CN106761609A (en) * 2015-11-24 2017-05-31 中国石油化工股份有限公司 The underground turbine generation automatically controlled water injection string of pressure transmission signal
CN109372479A (en) * 2017-11-07 2019-02-22 中国石油化工股份有限公司 Water injection well wireless test and control separate injection tubing string
CN108121369A (en) * 2017-12-20 2018-06-05 中国石油天然气股份有限公司 A kind of Intelligent water injection remote control apparatus and method
CN108121369B (en) * 2017-12-20 2023-10-27 中国石油天然气股份有限公司 Intelligent water injection remote control device and method
CN108397173A (en) * 2018-02-07 2018-08-14 中国石油天然气股份有限公司 Seperated layer water injection system and layered water injection method
US10890059B2 (en) 2018-02-07 2021-01-12 Petrochina Company Limited Layered water injection system and layered water injection method
CN114622879A (en) * 2020-12-10 2022-06-14 中国石油天然气股份有限公司 Layered water injection wireless communication method and wireless two-way communication device
CN114622879B (en) * 2020-12-10 2024-04-30 中国石油天然气股份有限公司 Layered water injection wireless communication method and wireless two-way communication device
CN115059438A (en) * 2022-05-30 2022-09-16 西安思坦仪器股份有限公司 Water injection allocation method for wave code injection well
CN118065820A (en) * 2024-04-17 2024-05-24 大庆长垣能源科技有限公司 Piezoelectric switch control toe end sliding sleeve based on precoding uniqueness identification

Also Published As

Publication number Publication date
CN100422504C (en) 2008-10-01

Similar Documents

Publication Publication Date Title
CN1619097A (en) Method of regulating layered water distribution using pressure wave
CN103277079B (en) A kind of tubing string of horizontal well fracturing completion and pressing crack construction method thereof
CN106194131B (en) It is spaced CO between multistage fracturing horizontal well seam2Oil flooding method
CN102839954B (en) A kind of pressure pulse realizes the method for layering water distribution
CN103277078B (en) A kind of hydraulic sliding sleeve
CN103306640B (en) Rodless pump oil extraction system fluid power paraffin removal unit
CN101498211A (en) Method for water distribution by sound wave remote control
CN109025926B (en) Centralized control type intelligent separate-layer water injection string and regulation and control system
CN105756634B (en) It is spaced cyclic water stimulation oil production method between multistage fracturing horizontal well seam
CN202531143U (en) Digital type underground separated layer water injection measurement and adjustment technological tubular column
CN103362486A (en) Digital underground layering water injection testing and adjusting process pipe column and operation method thereof
CN201437719U (en) Intelligent water distributor for water injection well
CN100335741C (en) Assembly for drilling low pressure formation
CN109252836A (en) A kind of layered water filler and process based on underground wireless communication
CN107503720A (en) A kind of device and method for regulating and controlling seperated layer water injection using flow waves
CN106837290A (en) The asynchronous note CO of the different well of packet of symmetrical expression cloth seam2Oil production method
CN112267851B (en) Composite drainage gas production pipe column for draining accumulated liquid in 'lying well' well and method thereof
CN202148890U (en) Device for producing pressure pulse at wellhead of water injection well
CN1303310C (en) Method for water searching and blocking for oil well
CN109931040B (en) Remote intelligent control system and method for separate injection well
CN202132029U (en) Layer mining and testing system for petroleum
CN114482953A (en) Offshore heavy oil layering viscosity reduction cold recovery pipe column and method
US20100051268A1 (en) Oil extraction system and oil extraction supervisory system
CN204266988U (en) A kind of pilot-controlled switch sliding sleeve
CN204716201U (en) A kind of pilot-controlled switch sliding sleeve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: FIRST OIL PRODUCTION PLANT OF DAQING OILFIELD CO.

Free format text: FORMER OWNER: WU JIE; APPLICANT

Effective date: 20070302

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20070302

Address after: 163001, 1, battle street, Saertu District, Heilongjiang, Daqing

Applicant after: Daqing Oilfield Co.,Ltd. No 1 Oil Production Plant

Co-applicant after: Beijing Huayou Oil Technology Development Co.,Ltd.

Address before: 100000 Beijing six laying Kang 14, 1 - 603

Applicant before: Wu Jie

Co-applicant before: Chen Lin

C14 Grant of patent or utility model
GR01 Patent grant
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Chen Aimin

Document name: patent for invention

C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Chen Aimin

Document name: Notification to Pay the Fees

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Chen Aimin

Document name: Notification of Approving Refund

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Beijing Huayou Oil Technology Development Co.,Ltd. Person in charge of patents

Document name: Notice of Termination of Patent Rights

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081001