CN1584263A - Steel-structure truss high-altitude arc sliding installing method - Google Patents

Steel-structure truss high-altitude arc sliding installing method Download PDF

Info

Publication number
CN1584263A
CN1584263A CN 200410024903 CN200410024903A CN1584263A CN 1584263 A CN1584263 A CN 1584263A CN 200410024903 CN200410024903 CN 200410024903 CN 200410024903 A CN200410024903 A CN 200410024903A CN 1584263 A CN1584263 A CN 1584263A
Authority
CN
China
Prior art keywords
truss
slideway
steel
main couple
slippage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200410024903
Other languages
Chinese (zh)
Inventor
黄明鑫
史秋侠
刘中华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BAITE STEEL STRUCTURE DESIGN Co Ltd SHANGHAI
Original Assignee
BAITE STEEL STRUCTURE DESIGN Co Ltd SHANGHAI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BAITE STEEL STRUCTURE DESIGN Co Ltd SHANGHAI filed Critical BAITE STEEL STRUCTURE DESIGN Co Ltd SHANGHAI
Priority to CN 200410024903 priority Critical patent/CN1584263A/en
Publication of CN1584263A publication Critical patent/CN1584263A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a high-level arc-line slide-moving installation method of steel structure truss. In the concrete, on the concentric curved steel beams respectivley positioned on two ends of the truss to be installed the sipways are respectively set, each of two ends of the truss is equipped with slipper respectively. A hydraulic traction equipment can be used for pulling the slipper and making it be moved along the slipway from far end place of two slipways. After the first main truss is hoisted to high level and assembled into one whole body, the slipper can be forwards slide-moved by one truss width, then the second main truss can be assembled and connected with member between trusses, and can be slide-moved by one truss width, so that the above-mentioned steps can be circulated until several truss units are assembled into a whole body unit, then the whole body unit can be slide-moved into the designed plane position.

Description

Steel structure truss high-altitude camber line slide installation method
Technical field
The invention belongs to the steel building technical field of construction, be specifically related to a kind of steel structure truss high-altitude camber line slide installation method.
Background technology
Flourish along with China's economic construction, large-scale public building such as airport, conference and exhibition center, sports palace, assembly hall theater etc. have obtained using widely.These buildings are generally the long-span space steel work, and form of structure has rack, space truss etc.Composite factors such as stressed and construction features according to truss, field condition, on-the-spot construction technology condition and device resource are installed at the scene of steel work, generally can be divided into high altitude bulk method, itemize or piecemeal installation method, high-altitude sliding method, whole hanging method, whole lift method and integral jacking method.The quality of on-the-spot mounting method has very big influence to construction period, comprehensive cost.Every kind of mounting method is all by oneself pluses and minuses.The high altitude bulk method can be installed with general lifting appliance and fastener type steel pipe scaffold, but the scaffold consumption is big, work high above the ground is many, long in time limit, to account in the building field land used many, and technical acquiring a certain degree of difficulty.Itemize or piecemeal are installed method and generally can not be used separately, be used with other mounting methods such as high altitude bulk method, high-altitude sliding method etc.Whole hanging method is higher to the crane performance requirement, and construction condition requires relatively stricter, for example, assembly unit in place place, crane travel etc. be arranged.Whole lift method one is that the requirement truss must be by high-altitude mounting position assembly unit in place on ground, and promptly high-altitude mounting position and installation on ground position must be on same plane of projection, the 2nd, and the rod member that requirement periphery and pillar are collided must be reserved, so limitation is bigger.Integral jacking method construction embodiment at home is less, and difficulty of construction is big, cost is high and the jack-up construction technology is relevant with structure itself, uses less.The high-altitude sliding method by being arranged on rack end or middle part local assembly unit frame (or utilizing the built construction thing) as the installation at high altitude platform and be located at both sides or middle same long slideway, be combined into strip or block unit on ground, winch to and be assembled into sliding element on the platform for lining, design attitude is arrived in the truss slippage with pulling equipment.But it is linear slippage that the sliding construction technology only limits to the slippage route at truss two ends.
Along with expanding economy, novel form of structure is more and more, and for example the girder steel at truss two ends is a camber line shape etc., and span is increasing, and this just needs more reasonable, more economical mount scheme.
Summary of the invention
The objective of the invention is to propose a kind of slippage route the steel structure truss high-altitude slide installation method that is arc.
The steel structure truss high-altitude slide installation method that the present invention proposes is provided with slideway A-A ' and GG ' respectively on the concentric circular arc girder steel in the both sides of truss to be installed, the axis of slideway A-A ' and GG ' also is two concentric circular arc lines; The two ends of main couple to be installed are arranged on the custom-designed piston shoes 15, and piston shoes 15 move at slideway upper edge slideway; The outside at the end of two slideways A ', G ' is provided with two hydraulic traction devices 10 respectively by reaction frame platform 9, two draw-gears 10 are connected with piston shoes 15 by steel strand 7 respectively, two draw-gears, 10 synchronous workings, thus by steel strand 7 pulling two piston shoes 15 with main couple along the slideway synchronization-sliding; If the spacing of adjacent two main couples is the B degree; Concrete installation steps are as follows:
The one Pin main couple is after the assembling of ground, winch to the installation at high altitude support with loop wheel machine, in end regions, be assembled into integral body, two hydraulic traction devices 10 by two slideway far-ends spur synchronously, along both sides slideway pulling B degree, carry out the assembling of the 2nd Pin main couple then, and connect the member 14 between truss, slippage B degree again; Carry out the installation of member between the assembling of the 3rd Pin main couple and truss thereafter; So circulation becomes integral unit until many truss structures unit splicing, and the whole unit slippage is to the design plane position then.Whole slippage installation process comprises accumulation slippage and two stages of integral slipping:
The accumulation slippage stage: Pin main couple lifting, temporary fixed → single truss structure along the circumferential direction between slippage B degree → the 2nd Pin main couple lifting → the first truss structure lifting component → two truss structures together along the circumferential direction lifting component between slippage B degree → the 3rd Pin main couple lifting → the second truss structure → ... → the first to the 5th truss structure is lifting component between → the five truss structure of slippage B degree → the 6th Pin main couple lifting along the circumferential direction together.When the truss accumulation slippage finishes, form after the integral slipping unit beginning integral slipping.The same accumulation slippage of integral slipping hydraulic haulage mode.Draw the integral slipping unit continuously by the hydraulic haulage device, until design attitude.
Both sides slideway length difference, but they lay respectively on two sections isocentric circular arc, the synchronism of the angular velocity by control both sides slide plate slides converts the synchronism of control slide plate linear velocity to, and linear velocity can be regulated by oil pump flow.Whole Hydraulic Synchronizing draw-gear can be by computer control.
When towing point quit work, sliding element produced brake force by the frictional force between slide plate and the slideway.According to momentum identity: F * t=m * v.Wherein, F=N * μ brings identity → N * μ * t=m * v into.Slide plate equals superstructure deadweight m to track normal pressure N, and coefficientoffriction, hauling speed v all equate, so the braking time of each slide plate equates.Be sliding element in braking procedure, each fulcrum keeps synchronously, no additional internal force.Can guarantee stability of structure.
The present invention can solve crane machinery can't lift the difficulty that puts in place, and during truss construction, civil engineering can cross-operation; The assembling support expense is saved than high altitude bulk method, and it is few to take building periphery place, and having on one side, the construction plant gets final product.By the computer Synchronization Control, make steady, safe, the quick slippage of member to assigned address.The construction of employing the method can obtain obvious economic benefit,
Description of drawings
Fig. 1: the member assembling finishes accumulation slippage between one: the first main couple of slip state and first truss structure.
Fig. 2: slip state two: the member assembling finishes accumulation slippage between first and second Pin main couple and first truss structure.
The member assembling finishes accumulation slippage between three: the three Pin main couples of Fig. 3 slip state and second truss structure.
The member assembling finishes accumulation slippage between four: the four Pin main couples of Fig. 4 slip state and the 3rd truss structure.
The member assembling finishes accumulation slippage between four: the four Pin main couples of Fig. 5 slip state and the 3rd truss structure.
Fig. 6 the 6th slip state: the member assembling finishes between the 6th Pin main couple and the 5th truss structure, and integral slipping is in place.
Fig. 7 slideway bearing elevation.
Number in the figure: 1~6 is main couple, and 7 is steel hinge line, and 8 is slideway, and 9 is the reaction frame platform, and 10 is the hydraulic haulage device, and 11 is slide plate, and 12 are the slippage girder steel, and 13 is steel shoe, and 14 is member between truss, and 15 is piston shoes.
The specific embodiment
About 30900 square metres of the building area of certain airport lounge, it is fan-shaped that the plane is, fan-shaped chord length 197m, the following chord length 154m of going up, span 72m, the plane is divided into B and two districts of C, and main structure adopts the del space tube truss, pipe truss plane is Y-shaped, totally 6 Pin, the about 82T of every Pin weight.Rectangular beam with arc between the main couple links to each other with the ray beam.The high-altitude arc sliding construction technology that adopts is installed at the scene of marquis's machine hall steel roof system.Truss two end bearings are on two sections isocentric circular arc, and two slideway length are respectively 127 meters and 206 meters.Slideway is a topmost supporting member in the truss slippage, and slideway plays load-bearing guiding and laterally restriction slide plate horizontal movement in whole horizontally tracting.Slideway is located on the slippage girder steel of A-A axle and G-G axle arc.Utilize the base plate of the upper surface of slippage girder steel as slideway.At girder steel sliding way width both sides weldable steel baffle plate 13 as the slide plate cross spacing.The center line of slideway and the dead in line of slippage girder steel are to reduce the influence of the deadweight of sliding element in the slipping to the slippage girder steel; Tractive force is selected hydraulic traction device 10 and steel strand 7, arranges along traction axis separate unit.Steel strand 7 one ends are fixed on by ground tackle on the piston shoes 15 of the first truss structure slide plate, and the other end is connected on the hydraulic jack on the reaction frame, establish the steel hinge line outlet at an end (steel hinge line Way out) of reaction frame and dredge support, and steel hinge line is emitted along dredging under the support.Reaction frame 9 is fixed near the column cap towage point of distal-most end A ', G ', in order to fixed hydraulic pulling equipment 10, bears the traction counter-force.
Concrete construction sequence such as Fig. 1-shown in Figure 6.Main couple winches to the installation at high altitude bracing frame with large-scale crawler crane after being assembled into three sections on the fetal membrane frame of ground, after assembly unit on the sliding rail is shaped, from the other side slip of a side direction, after the one Pin lifting splicing is finished, the position of beginning slippage to the two Pin, and then promote the 2nd truss structure.After the 2nd truss structure is finished in the lifting splicing, begin to install members such as steel support and dome, make it in time form the spatial stability system, and then carry out slippage.Circulation is carried out said sequence up in place the finishing of whole truss slippages.

Claims (1)

1, a kind of steel structure truss high-altitude camber line slide installation method is characterized in that on the concentric circular arc girder steel in the both sides of truss to be installed slideway A-A ' and GG ' being set respectively; The two ends of main couple to be installed are arranged on the custom-designed piston shoes (15), and piston shoes (15) move at slideway upper edge slideway; The outside at distal portion A ', the G ' of two slideways is provided with two hydraulic traction devices (10) respectively by reaction frame platform (9), two draw-gears (10) are connected with piston shoes (15) by steel strand (7) respectively, two draw-gears (10) synchronous working, by steel strand (7) pullings two piston shoes (15) thereby with main couple along the slideway synchronization-sliding; If the spacing of adjacent two main couples is the B degree; Concrete installation steps are as follows: a Pin main couple is after the assembling of ground, winch to the installation at high altitude support with loop wheel machine, in end regions, be assembled into integral body, two hydraulic haulage devices by two slideway end points places spur synchronously, along both sides slideway pulling radian, carry out the assembling of the 2nd Pin main couple then, and connect the member (14) between truss, slippage B degree again; Carry out the installation of member between the assembling of the 3rd Pin main couple and truss thereafter; So circulation becomes integral unit until many truss structures unit splicing, and the whole unit slippage is to the design plane position then.
CN 200410024903 2004-06-03 2004-06-03 Steel-structure truss high-altitude arc sliding installing method Pending CN1584263A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200410024903 CN1584263A (en) 2004-06-03 2004-06-03 Steel-structure truss high-altitude arc sliding installing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200410024903 CN1584263A (en) 2004-06-03 2004-06-03 Steel-structure truss high-altitude arc sliding installing method

Publications (1)

Publication Number Publication Date
CN1584263A true CN1584263A (en) 2005-02-23

Family

ID=34601038

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200410024903 Pending CN1584263A (en) 2004-06-03 2004-06-03 Steel-structure truss high-altitude arc sliding installing method

Country Status (1)

Country Link
CN (1) CN1584263A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101323418B (en) * 2008-07-25 2010-06-09 北京城建集团有限责任公司 Huge deformed steel member single machine turnover hoisting method
CN101200959B (en) * 2007-11-29 2010-06-16 北京城建集团有限责任公司 Multi-point pushing cumulative-gliding construction method for steel roof truss
CN101284430B (en) * 2008-05-30 2010-06-30 中国二十二冶集团有限公司 Slipping process of large tonnage pressure frame
CN101029520B (en) * 2007-04-04 2010-08-18 中国京冶工程技术有限公司 Non-push integrated sliding construction of steel truss arch stand
CN101177956B (en) * 2007-11-29 2010-11-03 浙江精工钢结构有限公司 Flexible railway separating thrusting slip construction method and equipment thereof
CN101666163B (en) * 2009-09-15 2010-12-01 中冶建工有限公司 High-altitude long-span roofing pipe truss installation method
CN102102444A (en) * 2009-12-18 2011-06-22 上海市机械施工有限公司 Assembling and positioning construction method of large steel casting members
CN101492966B (en) * 2008-01-24 2011-06-29 中建三局建设工程股份有限公司 Construction method of super large steel structure cantalever
CN102953556A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Hoisting method of large-span asymmetric rectangular space twisted pipe truss
CN103061521A (en) * 2013-01-24 2013-04-24 中国水利水电第二工程局有限公司 Torque type mounting method for cantilever steel truss of large stadium
CN103556824A (en) * 2013-11-12 2014-02-05 中国建筑股份有限公司 Synchronous measurement and control system for slippage and translation of engineering random curve based on RTK (Real Time Kinematic) and method
CN103628691A (en) * 2013-12-12 2014-03-12 上海通用金属结构工程有限公司 Large-span cantilever truss construction support process
CN104234201A (en) * 2014-09-28 2014-12-24 中亿丰建设集团股份有限公司 Installation method and installation structure of great-height-difference arc-shaped roof support
CN105003080A (en) * 2015-05-06 2015-10-28 上海绿地建设(集团)有限公司 Construction technique of sector steel-structured building
CN107780661A (en) * 2016-08-24 2018-03-09 中冶天工集团天津有限公司 A kind of towed accumulation slippage Construction of The Grids devices and methods therefor in high-altitude
CN109812024A (en) * 2019-02-16 2019-05-28 中建一局集团第一建筑有限公司 A kind of high-altitude inclination angle across truss greatly is from anchor accumulation slippage construction method

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101029520B (en) * 2007-04-04 2010-08-18 中国京冶工程技术有限公司 Non-push integrated sliding construction of steel truss arch stand
CN101200959B (en) * 2007-11-29 2010-06-16 北京城建集团有限责任公司 Multi-point pushing cumulative-gliding construction method for steel roof truss
CN101177956B (en) * 2007-11-29 2010-11-03 浙江精工钢结构有限公司 Flexible railway separating thrusting slip construction method and equipment thereof
CN101492966B (en) * 2008-01-24 2011-06-29 中建三局建设工程股份有限公司 Construction method of super large steel structure cantalever
CN101284430B (en) * 2008-05-30 2010-06-30 中国二十二冶集团有限公司 Slipping process of large tonnage pressure frame
CN101323418B (en) * 2008-07-25 2010-06-09 北京城建集团有限责任公司 Huge deformed steel member single machine turnover hoisting method
CN101666163B (en) * 2009-09-15 2010-12-01 中冶建工有限公司 High-altitude long-span roofing pipe truss installation method
CN102102444A (en) * 2009-12-18 2011-06-22 上海市机械施工有限公司 Assembling and positioning construction method of large steel casting members
CN102102444B (en) * 2009-12-18 2014-09-03 上海市机械施工集团有限公司 Assembling and positioning construction method of large steel casting members
CN102953556A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Hoisting method of large-span asymmetric rectangular space twisted pipe truss
CN102953556B (en) * 2012-11-14 2016-05-18 中冶天工集团有限公司 Hoisting method of large-span asymmetric rectangular space twisted pipe truss
CN103061521A (en) * 2013-01-24 2013-04-24 中国水利水电第二工程局有限公司 Torque type mounting method for cantilever steel truss of large stadium
CN103061521B (en) * 2013-01-24 2015-08-05 中电建建筑集团有限公司 Coliseum Steel Cantilever Truss torque type mounting method
CN103556824A (en) * 2013-11-12 2014-02-05 中国建筑股份有限公司 Synchronous measurement and control system for slippage and translation of engineering random curve based on RTK (Real Time Kinematic) and method
CN103556824B (en) * 2013-11-12 2018-05-08 中国建筑股份有限公司 The synchronous investigating method of engineering arbitrary curve sliding translation based on RTK
CN103628691A (en) * 2013-12-12 2014-03-12 上海通用金属结构工程有限公司 Large-span cantilever truss construction support process
CN104234201A (en) * 2014-09-28 2014-12-24 中亿丰建设集团股份有限公司 Installation method and installation structure of great-height-difference arc-shaped roof support
CN105003080A (en) * 2015-05-06 2015-10-28 上海绿地建设(集团)有限公司 Construction technique of sector steel-structured building
CN107780661A (en) * 2016-08-24 2018-03-09 中冶天工集团天津有限公司 A kind of towed accumulation slippage Construction of The Grids devices and methods therefor in high-altitude
CN109812024A (en) * 2019-02-16 2019-05-28 中建一局集团第一建筑有限公司 A kind of high-altitude inclination angle across truss greatly is from anchor accumulation slippage construction method

Similar Documents

Publication Publication Date Title
CN1584263A (en) Steel-structure truss high-altitude arc sliding installing method
CN100572713C (en) The large span bidirectional string stretching girders rope accumulation gliding construction method
CN103669211B (en) Hydraulic multi-function cantilever lifting beam machine and steel box girder assembling method
CN104929373B (en) Large span Square Steel Tubes Truss and its accumulation slippage construction method
CN101446068B (en) Method for erecting suspension bridge main girder by segmenting and jacking and adopted device for rolling and moving heavy objects
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN103790234A (en) Large-span truss hydraulic multi-point synchronous lifting construction method
CN114197634B (en) Construction method of high-rise conjoined large steel structure installation monitoring system
CN110258293A (en) Cable-stayed bridge steel truss girder main pylon pier top erection construction method
CN108118622A (en) A kind of steel-concrete composite beam cable-stayed bridge main cable and girder construction cable crane system
CN110409311A (en) It a kind of single beam girder erecting machine and its sets a roof beam in place, via hole, the method for crossing tunnel
CN110397289B (en) All-dimensional beam erecting equipment standing on top of house column and having automatic walking function
CN201195822Y (en) Propel machine of city rail traffic erecting machine of bridge span capable of walking in S shaped line
CN114182647B (en) Construction method for lifting and turning weak arch
CN111719860A (en) Construction process of large-span complex arch truss roof
CN105839550B (en) A kind of compressing walking mechanism and cantilever cradle for cantilever cradle
CN101481903A (en) Method for erecting main truss of suspension bridge in mountain area by reversely assembling cross-cable cranes
CN110468743A (en) A kind of traveling cradle and construction method for the transformation of old pier coping
CN1057973C (en) Four-bar frame self-lifting type door-base crane
CN101725114A (en) Method for hoisting hawser of long-span cable-stayed bridge and equipment thereof
CN205529915U (en) Ladder type masts type hangs pieces together loop wheel machine
CN218145304U (en) Adjustable lifting appliance
CN111395195A (en) Operation hanging basket for bolted connection of steel-concrete composite beam segments based on bridge girder erection machine
CN109205475B (en) Device and method for assembling and disassembling girder type gantry crane in tunnel through connection of trusses
CN108221639B (en) Three tower suspension bridge girder installation construction structures

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication