CN1566369A - Cooling process for hot-blast stove - Google Patents

Cooling process for hot-blast stove Download PDF

Info

Publication number
CN1566369A
CN1566369A CN 03135155 CN03135155A CN1566369A CN 1566369 A CN1566369 A CN 1566369A CN 03135155 CN03135155 CN 03135155 CN 03135155 A CN03135155 A CN 03135155A CN 1566369 A CN1566369 A CN 1566369A
Authority
CN
China
Prior art keywords
hotblast stove
air duct
furnace
manhole
stove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 03135155
Other languages
Chinese (zh)
Inventor
何天均
高宗来
杨才渝
孙杰锋
吴荣善
易振翔
苏清
余占平
朱爱国
彭将国
彭秋菊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CONSTRUCTION Co Ltd PANGANG GROUP
Original Assignee
CONSTRUCTION Co Ltd PANGANG GROUP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CONSTRUCTION Co Ltd PANGANG GROUP filed Critical CONSTRUCTION Co Ltd PANGANG GROUP
Priority to CN 03135155 priority Critical patent/CN1566369A/en
Publication of CN1566369A publication Critical patent/CN1566369A/en
Pending legal-status Critical Current

Links

Landscapes

  • Air Supply (AREA)

Abstract

The invention discloses a furnace kiln overhauling process, in particular to a furnace cooling process suitable for overhauling a blast furnace hot blast stove in the metallurgical industry. The cooling process of the hot blast stove adopts the technical scheme that: and after the furnace is shut down, the manhole at the upper part and the manhole at the lower part are opened, the cold air pipeline, the flue pipe and the hot air pipeline are sealed, and then the exhaust fan is used for exhausting air at the bottom of the hot air furnace. By adopting the technical process, cold air is forced to be sucked from the manhole of the furnace top and discharged through the lower exhaust fan, the airflow direction in the furnace is changed, the cooling speed in the furnace is improved, in the construction and dismantling process, the cold air enters the checker bricks from the feet of constructors, and the hot air is discharged from the manhole of the lower part, so that the environmental temperature of a construction area is improved, and the dismantling and construction progress is improved.

Description

The hotblast stove cooling equipment process
Affiliated technical field
The present invention relates to stove maintenance technology, particularly be suitable for the descent of temperature technology in blast funnace hot blast stove when maintenance of metallurgy industry.
Background technology
In metallurgy industry, in order to guarantee the stable high yield of blast furnace, guarantee the stable air-supply of hotblast stove, must regularly carry out shutdown maintenance to hotblast stove.In the past need be after blowing out cool stove 15 days, make when temperature is from work in the stove 1300 ℃ drop to 50 ℃ and just can overhaul construction.
At present, in order to shorten the repair time, accelerate speed of furnace cooling, employing is suitably sprinkled water in stove and the drum combustion air is forced to cool off.Adopting above-mentioned strong cooling method after 5 days after the blowing out, the checker brick temperature also remains on 200~300 ℃ in the stove, gas flow temperature is 70~170 ℃, and this moment, the workmen carried out the inside dismounting, must stop to force cooling with the drum combustion air, can only adopt the vacuum fan exhausting, but effect is undesirable, and the construction environment very severe is so must carry out operation by turns, the dismounting cycle in early stage is long, generally needs 19~21 days.Its reason is: owing to all use many hotblast stove air feed simultaneously in smelter, cold wind (200 ℃) in order to prevent other hotblast stoves during maintenance, flue gas and hot blast are scurried in the stove and are hurted sb.'s feelings, need be with cold-air duct, flue tube, disconnections such as smoke valve bottom and hot blast short pipe, when the blower fan exhausting is used in the bottom of hotblast stove, from the cold-air duct gap, form between position such as Flue valve bottom and the blower fan " short circuit ", a large amount of freezing airs is directly discharged by blower fan from above-mentioned position, and there is a spot of freezing air to discharge from furnace roof through checker brick, so stove internal upper part air-flow is not had too big cooling effect, and effect is undesirable.
Goal of the invention
At existing temperature reduction technology weak effect, the long shortcoming of temperature fall time, the invention provides a kind of hotblast stove cooling equipment process that freezing air is discharged by furnace bottom bottom blower fan by back in the stove from furnace roof.
The technical scheme that hotblast stove cooling equipment process of the present invention adopts is: after blowing out top manhole and bottom manhole are opened, with cold air duct, flue tube, hot air duct sealing, carried out exhausting in the bottom of hotblast stove with vacuum fan again.
Adopt technical matters of the present invention, forcing freezing air to suck from the furnace roof manhole discharges through the downdraft machine, changed the gas stream in the stove direction, improved the cooling rate in the stove, in the construction demolishing process, freezing air enters checker brick from workmen's underfooting, and warm air is discharged from the bottom manhole, improved the construction area envrionment temperature, improved and remove and construction speed.
Description of drawings
Fig. 1 is the structure and the fundamental diagram of hotblast stove;
Fig. 2 is the A-A diagrammatic cross-section among Fig. 1;
Fig. 3 be among Fig. 2 the B-B sectional view '
Fig. 4 is a cold air duct sealing synoptic diagram;
Fig. 5 is a hot air duct sealing synoptic diagram;
Fig. 6 is a fume pipe sealing synoptic diagram.
Sequence number explanation in the accompanying drawing: 1-top manhole, 2-bottom manhole, 3-cold air duct, 4-hot air duct, 5-regenerator, 6-combustion chamber, 7-chimney, 8-burner, 9-fume pipe, 10-flue, 11-smoke valve, 12-blind plate, 13-cold blast valve, 14-hot blast valve, 15-hot blast short pipe.
Embodiment
The structure of hotblast stove and fundamental diagram are as shown in Figure 1,6 tops enter regenerator 5 to the waste gas that burner combustion produces through the combustion chamber from burner 8, discharge from chimney 7 by fume pipe 9 and flue 10 again, waste gas is with the heating of the checker brick in the regenerator 5, and hot blast valve 14 on the hot air duct 4 and the cold blast valve 13 on the cold air duct 3 are closed at this moment.After temperature in the regenerator 5 is raised to certain altitude, burner 8 cease combustions, cold blast valve 13 on the unlatching cold air duct 3 and the hot blast valve 14 on the hot air duct 4, after cold wind enters from cold air duct 3, after checker brick in regenerator 5 carry out heat exchange and are heated, send in the blast furnace by combustion chamber 6 and hot air duct 4.So when needs overhaul, because checker brick etc. are also accumulated a large amount of heats are arranged in the stove, make to keep very high temperature in the stove, bring influence to service work.
Hotblast stove cooling equipment process of the present invention is earlier cold air duct, flue tube, hot air duct to be sealed when blowing out, then top manhole and bottom manhole is opened, and carries out exhausting in the bottom of hotblast stove with vacuum fan again.
In order to guarantee the quick decline of temperature in the blowing out stove in early stage, adopt the drum combustion air to force the stove internal cooling in the 3-7 after blowing out days, can effectively reduce temperature in the stove.
Embodiment 1: during the hotblast stove blowing out, with the cold blast valve on the cold air duct 3 13, smoke valve 11 on the fume pipe 9 and the hot blast valve 14 on the hot air duct 4 are closed sealing, and suitably watering and drum combustion air forced cooling method forced cooling after 5 days in the employing stove, top manhole 1 and bottom manhole 2 are opened, vacuum fan is installed at hotblast stove bottom manhole 2 places is again carried out exhausting, force freezing air to suck from furnace roof top manhole 1, after the checker brick heat exchange in stove, forming warm air gets rid of from bottom manhole 2, thereby improved construction environment, can carry out the construction of removing in the stove.
Embodiment 2: in the production in ironworks, generally all be to adopt many hotblast stoves to provide hot blast to blast furnace, after the hotblast stove blowing out that will need to overhaul, in order to prevent damage and inefficacy owing to each valve, in construction process, hurt sb.'s feelings for preventing that hot blast, flue gas and cold wind from scurrying in the stove, earlier fume pipe 9, hot air duct 4 and cold air duct 3 are disconnected, the gap of hot air duct 4 is arranged on the hot blast short pipe 15.And blind plate 12 being set respectively at cold air duct 3, fume pipe 9 gaps and hot blast short pipe 15 gaps, the steel plate of using 1mm again is with the gap sealing between blind plate 12 and the above-mentioned pipeline.The cool stove of forced cooling is after 5 days, though temperature is 97 ℃ in the stove, open top manhole 1 and bottom manhole 2 again, adopt vacuum fan to carry out exhausting at hotblast stove bottom manhole 2 places, but after adopting this temperature reduction technology, improved envrionment temperature immediately, accelerated construction speed, only tearing the stove time open is 6 days, has shortened 13 days.Be discharging and the discharge port that need offer is provided with along with the variation of removing the position when removing, offer again when tearing open to this position.
Owing to all be the dismounting of adopting from top to bottom,, can guarantee effectively that the temperature on top is lower in the construction so adopt the method for downdraft in construction process.And the mode that adopts the bottom to blow, then cooling-down effect is not ideal, but belongs to protection scope of the present invention.

Claims (8)

1,, the hotblast stove cooling equipment process with cold air duct (3), flue tube (9), hot air duct (4) sealing, is characterized in that: top manhole (1) and bottom manhole (2) are opened, carried out exhausting in the bottom of hotblast stove with vacuum fan again when blowing out.
2, hotblast stove cooling equipment process as claimed in claim 1 is characterized in that: adopt the drum combustion air to force stove internal cooling 3-7 days after blowing out, carry out exhausting in the bottom of hotblast stove with vacuum fan again.
3, hotblast stove cooling equipment process as claimed in claim 2 is characterized in that: adopt the drum combustion air to force stove internal cooling 5 days after blowing out, carry out exhausting in the bottom of hotblast stove with vacuum fan again.
4, hotblast stove cooling equipment process as claimed in claim 1, it is characterized in that: after blowing out, earlier fume pipe (9), hot air duct (4) and cold air duct (3) are disconnected, and adopt vacuum fan to carry out exhausting in the bottom of hotblast stove in above-mentioned gap sealing back.
5, hotblast stove cooling equipment process as claimed in claim 4 is characterized in that: be provided with at fume pipe (9), hot air duct (4) and cold air duct (3) gap respectively and adopt blind plate (12), again with the gap sealing between blind plate (12) and the above-mentioned pipeline.
6, as claim 4 or 5 described hotblast stove cooling equipment processes, it is characterized in that: the gap of hot air duct (4) is arranged on the hot blast short pipe (15).
7, hotblast stove cooling equipment process as claimed in claim 1 is characterized in that: vacuum fan is installed in bottom manhole (2) and locates to carry out exhausting.
8, hotblast stove cooling equipment process as claimed in claim 1 is characterized in that: discharge port is along with the variation of removing the position is provided with.
CN 03135155 2003-06-09 2003-06-09 Cooling process for hot-blast stove Pending CN1566369A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 03135155 CN1566369A (en) 2003-06-09 2003-06-09 Cooling process for hot-blast stove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 03135155 CN1566369A (en) 2003-06-09 2003-06-09 Cooling process for hot-blast stove

Publications (1)

Publication Number Publication Date
CN1566369A true CN1566369A (en) 2005-01-19

Family

ID=34470202

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 03135155 Pending CN1566369A (en) 2003-06-09 2003-06-09 Cooling process for hot-blast stove

Country Status (1)

Country Link
CN (1) CN1566369A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101128606B (en) * 2005-02-01 2012-06-20 丹尼利克里斯有限公司 Support assembly for supporting heat regeneration checker work in a hot blast stove, hot blast stove provided with said support assembly, method of producing hot air using said hot blast stove
CN105238901A (en) * 2015-09-30 2016-01-13 北京首钢国际工程技术有限公司 Multipurpose hot blast stove high-temperature preheating system
CN111664713A (en) * 2020-07-28 2020-09-15 广东韶钢松山股份有限公司 Off-line cooling method of hot blast stove
CN111850211A (en) * 2020-07-29 2020-10-30 广东韶钢松山股份有限公司 Off-line drying method of hot blast stove
CN113124255A (en) * 2021-04-16 2021-07-16 广东韶钢松山股份有限公司 Hot air piping system maintenance cooling method
CN114480769A (en) * 2022-01-28 2022-05-13 新疆八一钢铁股份有限公司 Method for treating harmful gas in Ou metallurgical furnace body

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101128606B (en) * 2005-02-01 2012-06-20 丹尼利克里斯有限公司 Support assembly for supporting heat regeneration checker work in a hot blast stove, hot blast stove provided with said support assembly, method of producing hot air using said hot blast stove
CN105238901A (en) * 2015-09-30 2016-01-13 北京首钢国际工程技术有限公司 Multipurpose hot blast stove high-temperature preheating system
CN111664713A (en) * 2020-07-28 2020-09-15 广东韶钢松山股份有限公司 Off-line cooling method of hot blast stove
CN111850211A (en) * 2020-07-29 2020-10-30 广东韶钢松山股份有限公司 Off-line drying method of hot blast stove
CN113124255A (en) * 2021-04-16 2021-07-16 广东韶钢松山股份有限公司 Hot air piping system maintenance cooling method
CN113124255B (en) * 2021-04-16 2022-04-12 广东韶钢松山股份有限公司 Hot air piping system maintenance cooling method
CN114480769A (en) * 2022-01-28 2022-05-13 新疆八一钢铁股份有限公司 Method for treating harmful gas in Ou metallurgical furnace body
CN114480769B (en) * 2022-01-28 2023-02-10 新疆八一钢铁股份有限公司 Method for treating harmful gas in Ou metallurgical furnace body

Similar Documents

Publication Publication Date Title
CN103145328B (en) A kind of method of basalt blast furnace slag in preparation of rock wool board comprehensive utilization
CN101570807A (en) Steelmaking converter gas purification and waste heat recovery system
JP4235651B2 (en) Stoker-type incinerator and operation method thereof
CN200955757Y (en) Furnace slag residual heat recovery device
CN1566369A (en) Cooling process for hot-blast stove
CN103480614B (en) Quick dust removal method for coke oven gas conversion system
CN2205532Y (en) Core furnace speed regulating gravity vertical drier
CN210070552U (en) Reinforced scrap steel preheating device for electric arc furnace
CN105238901B (en) A kind of multiduty hot-blast stove high temperature preheating system
CN201772762U (en) Energy saving cooling system for a roller kiln tail
CN101608869B (en) Method and device for forcibly cooling electrode baking furnaces
CN216404224U (en) Double-chamber kiln channel ventilation device
CN110030841A (en) Dedusting of EAF equipment and dust removal method
CN113941196A (en) Movable electric furnace smelting secondary smoke dust collecting and purifying device for casting
CN209706554U (en) A kind of energy saving and environment friendly Multi-functional smelting furnace
CN206739336U (en) A kind of converter dedusting line flue automatic ash removing device
CN111397385A (en) Automatic ash removal horizontal gas heat exchanger economizer system
CN216295502U (en) Movable electric furnace smelting secondary smoke dust collecting and purifying device for casting
CN201449007U (en) A turn-back flow coal burning hot air furnace
CN206724722U (en) Rotary hearth furnace fume afterheat gradient utilization system
CN1959204A (en) Construction method for burner, air channels, gas flues inside furnace wall of heating furnace in heat storage type
CN2711660Y (en) Hot air cupola
CN215724979U (en) Water-cooling hot-air cupola with long furnace life
CN1296495C (en) High wind temperature obtaining method using pure blast furnace gas combustion
CN220771375U (en) Hot-blast stove

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication