CN1354863A - System and method of scheduling manufacturing resources - Google Patents

System and method of scheduling manufacturing resources Download PDF

Info

Publication number
CN1354863A
CN1354863A CN00808266A CN00808266A CN1354863A CN 1354863 A CN1354863 A CN 1354863A CN 00808266 A CN00808266 A CN 00808266A CN 00808266 A CN00808266 A CN 00808266A CN 1354863 A CN1354863 A CN 1354863A
Authority
CN
China
Prior art keywords
resources
order
product
production
demand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN00808266A
Other languages
Chinese (zh)
Inventor
D·B·格莱迪奇
G·J·斯赫雷涅梅克斯
S·A·詹姆士
B·L·库尔贝克
R·E·博纳卢米
V·A·科隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Trane International Inc
Original Assignee
American Standard International Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from US09/285,288 external-priority patent/US6397118B1/en
Priority claimed from US09/285,314 external-priority patent/US6393332B1/en
Priority claimed from US09/285,289 external-priority patent/US6415195B1/en
Priority claimed from US09/285,286 external-priority patent/US6415194B1/en
Application filed by American Standard International Inc filed Critical American Standard International Inc
Publication of CN1354863A publication Critical patent/CN1354863A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling

Abstract

A system and method of scheduling demand for a manufacturing resource in response to a customer order for a product is provided. The system and method includes device for tracking scheduled finished goods orders, existing finished goods inventory, past due finished goods orders, unallocated customer orders and marketing orders, and the manufacturing lead time for the product, among other manufacturing process parameters. The customer order amount and the date requested for the order are entered, and depending on whether the date requested is inside, equal to or outside the manufacturing lead time, manufacturing resources are consumed from one or more of the scheduled finished goods orders, existing finished goods inventory, available to promise amounts, past due finished goods orders, unallocated customer orders, marketing orders, and high flex amounts.

Description

The system and method for scheduling manufacturing resources
Related application
The application is in this U. S. application 09/285,286,09/285,288 that requires the inventor to submit on April 2nd, 1999,09/284,289 and 09/285,314 right of priority.
Invention field
The present invention relates to be applied to the computer system and method for resources of production scheduling, and be specifically related to determine starting material in the production run and other resources of production day expense computer system and method.Calculate (prediction) or the actual order and some preset parameter relevant that daily demand amout is based on a certain product expection by computer system and method for the present invention with the resources of production.The result of this computer system and method, that is, the plan of resources of production demand when being applied to arrangement and distributing the resources of production, provides the resources of production of enough utilizations to produce the product demand of not expecting to satisfy.
Background of invention
In producing or factory is provided with, need within a certain period of time (for example, before the shipping date of making a promise) to handle and produce order client to disparity items.For the every kind of order that does not have in those finished product inventories,, must produce this kind goods product in order to enrich customer order.For this reason, some resources of production that need use in scheduled event sequence (production procedure) lining (starting material for example, machine or production line time, workman's time and other were similar in shifts).In order effectively to utilize the resources of production of workshop and factory, and finally satisfy the diversity of customer order, the producer preferably uses a kind of system and method to dispatch the required different resource of different date and times.Scheduling of resource allows the planned resource that makes full use of of the producer.
In traditional product lot quantity production method, ordered starting material in advance and left these starting material in warehouse as raw material store.This production method is typical uses arranged the techniques of mass production, wherein based on weekly or every month plan generate arranged product.Usually based on weekly or every month finished product demand these products are produced subassembly or parts earlier.Then, these subassemblies are assembled into final finished to satisfy actual customer order, perhaps put into finished goods inventory.
To produce accessory in case dispatch, just generate work order, and based on planned production Start Date and lot-size need for the various parts of producing this accessory obtaining from the warehouse.Subassembly is the same with the production method of final finished usually.Like this, after production, these subassemblies are stored up to needs its final assembling.Because the time span of each flow process usually needs a large amount of stock's parts and finished product to satisfy customer demand unexpected or fluctuation.Thereby the production procedure of scheduling needs a large amount of spaces to store starting material, subassembly stock and finished goods inventory.And, store a large amount of like this stocks and cause the fringe cost that causes because of the out-of-date loss of starting material, subassembly and finished product and damage.
Develop computer software programs and effectively finished in the production company material planning clerk for scheduling with follow the tracks of raw materials inventory in the batch production systems, many calculating of subassembly in batches.Typically, such computer software can be based on the planned dispatching input of planner input, calculates and determines, and even can generate the starting material quantity of purchase order with the expection that need to obtain.Except the scheduling starting material, these computer softwares also can have in scheduling manufacturing resources, for example dispatch product line and in shifts the workman organize.
Also develop other dispatching methods and helped to obtain to utilize required material collection plan in the outer production run of bulk production process.The computer scheduling system of using these dispatching methods refers generally to materials demand amount plan (MRP) system.Typically, the machine that MRP dispatching system supposition is endless, workman's time and similarly, and MRP system in shifts for have certain prediction or true order-known workshop must in time determine raw-material quantity and type in specified date.
Manufacturing resource planning (MRP II) system, it is the improvement to traditional MRP system, also can be applicable to scheduling and distributes the various resources of production.MRP II system generally also uses customer order and market forecast to determine the producing predetermined required resources of production quantity of product of customer order in preset time.In MRP II system, produce a kind of product and be called as from the fate that begins to produce assembly or subassembly at first and spent and produce delivery time or production line to the final finished shipment.Owing to the long delivery cycle that the subassembly production run causes, be difficult to be reacted to as early as possible the customer order of not expecting.The queuing of each tediously long subassembly of long production delivery cycle, and get resource to the warehouse frequently come and go the long delay that will cause between production stage, so also caused in client's order and finished and loaded and transported long time period between the goods.
One of prior problem of these MRP II systems is the fine in advance production scheduling that generated, and is not easy to change.In addition, these computer software programs of using in the process generally lack the ability of adjusting scheduling when condition changing easily.If it is more flexible that production run becomes, the computer software programs that then are used to dispatch also should become more flexible.Yet in typical MRP II system, product quantity perhaps to the aggregate demand of resource, is to be provided with by master scheduling is manual, and can not adjusts easily.
Thereby, the dispatching system of having developed likely, if receive the order of some, it can it can identify when and where to run counter to resource quantity or regularly restriction, these abnormalities will be solved before their actual generations like this.Yet, relevant with product and flow process and the relation and the constraint should in these systems, accurately set up the future event that model indicates any precision.Model can comprise flow process output and probability factor, but can not indicate random occurrence, and parts, perhaps bad weather are omitted in for example equipment failure.But, must take in and preplan random occurrence, like this can excessive resource and storage capacity prevent bottleneck.Use another kind of resource instead and also can prevent bottleneck.In arbitrary situation, in time discern and respond (that is, scheduling near) for safeguarding that productive capacity is necessary.
In any production environment, timely and accurate resource planning and scheduling usually are the key factors of a success.Can determine materials demand amount in the future and comprise the potential shortage amount that the customer demand of not expecting causes because of condition changing and not expectation incident in order to the materials demand amount planning system that above-mentioned consideration strengthens.The result of success realization system reduces tank farm stock and material damage is minimized.Even yet this materials demand amount planning system also just in certain and demand plan (promptly, produce number rather than the actual customer order of product in the production system with satisfied forecast) middle performance is well, and design variation (thereby, the change of production procedure and/or raw-material type and quantity) be infrequent.
In addition, the production dirigibility of increase is particularly being produced the more than a kind of factory of product, has produced product based on productive capacity and expection and has mixed requirement to long-term MRP strategy.Dispatching method that can applications similar is controlled other commercial operations, comprises productive capacity, sells plant maintenance and factory floor scheduling.Scheduling had frequent adjustment, because will cause bigger change to many different resource demands in the little change of demand, situation, product, flow process or to their restriction.
Clearly, need a kind of system and method for improved to calculate the total daily demand amout of expection of the resources of production automatically and energy is resource-based have related parameter to adjust automatically, to adapt to user's order of not expecting or other changes (comprising the change of starting material availability) of production procedure.Also need such system, it can distribute and scheduling manufacturing resources, and the customer order of producing maximum quantity minimizes overhead simultaneously and safeguards that excessive resources bank deposits cost related.The present invention has satisfied the requirement of these and other.
Summary of the invention
Usually according to the present invention, provide to pre-determine in the production system improving one's methods and system to the daily demand amout of the resources of production.More specifically, method and system of the present invention provides resources of production demand scheme in time based on one or many actual customer orders, the prediction of following customer order, the historical data of client's shipment in the past, current finished goods inventory quantity with the preset parameter relevant with the resources of production.
The method and system can be according to whenever filling in the customer order requirement, then calculate starting material or other resources of production that when will need some, and this system and method can determine additionally that the producer need buy or produce starting material, fill-in and similar date of (based on known supplier or produce the delivery time) thus, can also plan out to satisfy other resources that the time of shipment of promising to undertake in the customer order will be used in time producing goods.Thereby management material of the present invention is with other resources and can confirm system's centralized production resource planning with order.
And, this method and system can minimize the stand-by period of being made part, the production that increases machine is used (promptly, reduce waste residue machine time) and the maximum machine dirigibility to support the method for many different product demands, distribute and scheduling manufacturing resources, for example machine time or production line utilization.For example, in the heating steps of factory flow, place the part of maximum when it is desirable to use kiln in stove at every turn.System and method of the present invention allows once by using (consumption) kiln resource more than a product.Thereby the invention provides effective manufacturing resource planning, it has supported the demand of client to many products.
This system comprise one be used to store preset parameter, about the database of customer order information and historical data.An input equipment is provided, and it allows Systems Operator's input parameter and other information.On the other hand, this input equipment can link to each other with the output of different control gears in process of production.Provide a kind of output device to generate the detailed report that resource planning distributes.When the production for scheduling distributed raw-material situation, output device can generate purchase order.On the other hand, this output device can also link to each other with the input of different control gears in the production run, perhaps even with supplier or client's order system links to each other.
It is an improved method and system that above-mentioned aspect of the present invention and other aspects are finished, and it has determined the resources of production aggregate demand of every day in several time periods of being determined by system user.For example, in very first time section, the time durations from current date (being today) to demand (that is, producing the delivery time), aggregate demand can change, even begun the product of production some.The too much product that system of the present invention utilization is minimum and maximum finished goods inventory target has been produced with supply additional product or consumption.And, have the product that postpones sign, that is, general finished product order can be before this product becomes unique step, exchange mutually in the Related product of general finished product order.
Exceeding in several cycles of requirement time durations, be called as the elasticity period, the aggregate demand of every day can determine that a number percent or fixed number increase and number percent or fixed number reduce (this number percent or several can be the same or different) and change by each product user.Can there be a different number percent in each cycle, and for example, can there be different fates every period of one-period, however in one-period all days all use the same elasticity number percent that this should the cycle.This number percent or fixed number are represented to make the plussage of these resources spendable in order to satisfy client's product order of a predetermined level is exceeded to every kind of plan.Generated available volume of resources during the elasticity, this capacity is ordered the trend direction along continuous client and is moved, and it is by comprising one or more current turnout, and the weight factor that following order is predicted and the client loaded and transported history is in the past determined in interior numeral.
In case determined the amount during elasticity, system generate a plan order starting material and scheduling enough foundation add other resources of production of total expectation demand of demand during the elasticity.System has set up the dirigibility of the customer order that can satisfy elastic region upper limit quantification like this.
Exceed the order of required amount time durations if receive portion, and this order is bigger than the demand and the additional flexibility demand (being called the high resiliency amount) on this date of total prediction, native system and method will calculate once more above the demand time durations and before this orders the date aggregate demand of all fates, attempt is filled up the necessary aggregate demand amount of order with what is called smoothing process.In the resources of production demand of measuring during calculating reaches elasticity, system uses a kind of algorithm, and it comes adjustment amount to prevent arbitrary day aggregate demand above this day plan available raw materials amount and other mode.Thereby, by the smoothing of fate in early stage, even only flexible excessive stock number of the producer and quantity of material also can satisfy in client's order of ordering the high resiliency amount of not expecting day that surpasses.
Also provide the difference during production line that customer status and finished product are replenished the intermediate report of ordering at improvement system and method for the present invention.If problem has taken place, can recognize at once and report, system can take action and deal with problems like this, such as passing through from other deposits, for example from noncommittal customer order or market order, promise to undertake and can utilize number, finished goods inventory or finished product to replenish order, come the consumption of natural resource demand.
Method and system of the present invention has also solved various resource management problem.The resource that can manage comprises starting material, machine or production line time, man-hour, other labours, space, the energy or any other limitations affect are accepted the amount of deliver goods and Service Order ability in shifts.
For example, in building industry, the scheduling utilization of resource can include the build labourer of general or special expertise, various individual event tasks or multipurpose plant and materials demand amount; In forwarding business, effectively utilize the motor vehicle of conveying people, material and facility between special or general a plurality of positions; In health care, can dispatch and use sick bed, operating room, general or special office worker and fixing or mobile device.Other use of system and method for the present invention, for those can understand specific embodiment described here people will and easily see.
Accordingly, a purpose of this invention provides a kind of system and method, be used for plan, scheduling is used for satisfying the customer order of not expecting with the distribution resources of production with maximization production dirigibility and minimizes the relevant expense of keeping the excessive ability of this type of resource with other of inventory cost simultaneously.
Another target of the present invention provides a kind of system and method, and it can distribute the resources of production based on whether having enough, in time produces customer order and generate order approval scheme before the target date of customer requirement.
Another target provides a kind of system and method, and when calculating needed the resources of production, how many starting material the producer need buy, the workman in shifts of plan machine time and allotment operation production line.
Another target provides a kind of system and method, and it considers the ability of each machine and plant personnel.At last, distribute a manageable workload for every kind of resources of production, and can not surpass this assignment.In a similar manner, the reasonable amount and the timely capacity that keeps being convenient to provide sufficient that have calculated raw materials inventory and subassembly satisfy the demand of not expecting, minimize trucking costs and this stock damage or risk of missing simultaneously.
Another target of the present invention provides a kind of system and method, and it provides detailed resource analysis information and plan for company's amount of being subjected to.
Another target of the present invention provides a kind of system and method, can revise order approval and resource planning scheme when importing fresh information at every turn.
Other targets of the present invention and advantage part will will be more obvious by following detailed description.
The present invention is corresponding to comprise many steps, mutual relationship between one or more step and the system architecture that adapts with these steps, and the concrete feature of element combinations and component configuration, and scope of the present invention will be pointed out in claims.
The accompanying drawing summary
In order more comprehensively to understand the present invention, must be following about the description of the drawings, wherein with the accompanying drawing reference:
Fig. 1 describes the synoptic diagram according to the daily demand amout administrative model of the specific embodiment of the invention;
Fig. 2 describes the algorithm steps synoptic diagram that uses in the forecast consumption strategy according to the specific embodiment of the invention when requiring the target date in the demand time durations;
Fig. 3 describes the algorithm steps synoptic diagram that uses in the forecast consumption strategy according to the specific embodiment of the invention when requiring the target date to surpass the demand time durations;
Fig. 4 has described the algorithm steps synoptic diagram that uses in the predicting strategy according to the specific embodiment of the invention when requiring the target date in the demand time durations;
Fig. 5 has described the algorithm steps synoptic diagram that uses in the predicting strategy according to the specific embodiment of the invention when requiring the target date to surpass the demand time durations;
Fig. 6 has described the algorithm steps synoptic diagram that is applied to the actual subscription strategy according to the specific embodiment of the invention;
Fig. 7 a-7e describes the process flow diagram according to the algorithm steps that uses of the specific embodiment of the invention; With
Fig. 8 a-8v describes according to the present invention, when the producer runs into the spreadsheet of the result of algorithm when not expecting customer order.
The preferred embodiment explanation
Can well understand different specific embodiment of the present invention and example and their advantage referring to figs. 1 to Fig. 8 v, similar numeral is used to represent similar and corresponding part among the different figure.Following explanation is providing the present invention in the announcement General Principle of the present invention to be described also in detail.
The next example of system and method for the present invention is the daily demand amout administrative model.Fig. 1 has described schematically showing according to of the present invention day administrative model.The production run delivery time, i.e. streamline 100 expressions are assembled to the customer order time necessary amount of producing from starting material.Distal point at streamline 100 is the demand time durations, DTF102.The product that only can be used for production line 100 by the resources of production amount of DTF102.In general, scheduling is gone forward side by side into the resources of production amount or the aggregate demand 103 of streamline 100 by DTF102, will equate with bigger that in premeasuring 104 or the actual every day customer order 105.Every day, rate 107 was in the resources of production, consumption rate, and rate every day of establishing the DTF102 place equals aggregate demand 103.Difference between premeasuring 104 and actual customer order 105 is the admissible off-the-shelf amount ATP114 that can be used for filling other customer orders.
In order to ensure satisfying premeasuring 104 and/or the resources of production of the actual customer order 105 that fluctuates, accumulated the deposit 108 of the resources of production.Deposit 108 should be to be enough to provide premeasuring 104 and actual customer order 105, and should make the trucking costs of excess on hand and other resources of production minimum.A kind of technology of known plan deposit 108 comprises and is provided with during the elasticity, and expression surpasses and is lower than rate 107 the number percent or amount every day that can satisfy customer order during the elasticity.
The method of this known plan elasticity quantity depends in rate current every day of demand time durations, has seen that this can cause the acutely fluctuation up and down between the sky, and fluctuation has unfavorable result for the planned production resource utilization.The actual subscription rate of any specific products is very important, and random variation one monthly average and the season of nature on average are predictable, but mean value was very different therewith in arbitrary day.In system and method for the present invention, during the elasticity be one based on composite number it have pair streamline, client order premeasuring and shipment in the past historical every day rate one or more average every day rate weighting factor.Thereby the direction that elastic region connects the continuous trend of demand moves, and is not random variation or unusual every day.Be easy to adjust to time-current production, prediction in the future, in the past historical-or wherein one or more groups the most relevant synthetic top-priority that.
Typically, used three flex time sections, wherein each time period is illustrated in some days above DTF102, and elasticity quantity all increased every period.As shown in Figure 1, flex time section 1109 prolongs six days 5% amount of elasticity.Flex time section 2110 prolongs eight days 10% amount of elasticity.Flex time section 3111 has prolonged ten days 20% amount of elasticity.But thereby can be in six days of DTF102 order scheduling and surpass current every day of rate 107 5% the available resources of production to satisfy the client.Equally, can the fortnight of DTF102 in, can dispatch and surpass current every day of rate 107 10% the available resources of production.At last, can in two fortnights of DTF102, can dispatch and surpass current every day of rate 107 20% the available resources of production.
Thereby, calculate the aggregate demand 103 of every day to certain given living resources by time period during the program user input flexibility 109,110 and 111 backs.At current date, today 115, between DTF102, general aggregate demand can not change, because by this turnout production and will finish production in certain fate.During during the elasticity 109,110 and 111, the aggregate demand 103 of every day can become, for example the number percent of determining because of product user.Different number percent is arranged during each elasticity, and during each elasticity different fates can be arranged, however all days in during elasticity the elasticity number percent in generally all using during this.
In case determined during elasticity the amount in 109,110 and 111, native system produces the starting material plan and other resources of production is generated to be enough to set up and adds that amount is at the daily demand amout of interior expectation demand during the elasticity.If receive order above the DTF102 date, and this order is bigger than the proof resilience demand of that day, and native system will recomputate DTF102 tries hard to scheduling and can utilize the resources of production to produce to smooth demand process with what is called and fill up the necessary aggregate demand of order to ordering before the date aggregate demand of these days later on.。
Also there is another problem at known system and method during utilizing elasticity.If it is improper to be provided with during the elasticity, may produce undesired finished goods inventory.For addressing this problem,, replenish and order considerably beyond conservative finished goods inventory producing finished product if the order rate of certain given product is lower than rate every day.Say again, if the order rate height of certain given product has no idea to satisfy order finished goods inventory in streamline in known one-tenth system and method.
System and method of the present invention has utilized the smoothing process, this process comprise a computing machine and with a kind of algorithm of software programming to the resources of production demand of a kind of product smoothing to the time.The smoothing process variable receives customer order from typical order management system, and can distribute and dispatch the required resources of production demand of production customer order.Different order strategies also promptly consumes strategy, needs different algorithm steps to determine the finishing date of product and the product volume that can finish on any given date.
With the very big customer in response demand of forecast consumption strategy, the minimum stock who keeps the resources of production simultaneously.As described in Figure 1, with 109,110 and 111 providing starting material deposit 108 during the outer elasticity of DTF102 to satisfy the demand bigger than prediction.Because this consumes strategy, replenish order for the target of production minimum finished goods inventory has generated finished product, and this finished goods inventory is used for arriving demand time durations 102 at customer order the situation of (that is, in less than this finished product institute spended time of production).
With reference to figure 2 algorithm steps of forecast consumption strategy has been described, has wherein required in DTF102, to set up the client and set up and produce target date RBCD200.In the first step 21, finished product replenishes order FGO101 115 (from right to left) from RBCD200 to today will be consumed in 100 li on streamline continuously, and it may cause finished goods inventory maximum target FGI Max 201 to be exceeded.That is, calculate current finished goods inventory, FGI202 adds that FGO101 in the streamline and consumption cause that FGI202 adds FGO101's and greater than the FGO101 of FGI Max 201.Next step 22, then consumed the FGI202 that surpasses FGI Max 201.Next step 23, continuous consumption (from right to left) from RBCD200 to today 115 in streamline remaining FGO101.Next step 24, consumed deserved in the past FGO203.Next step 25, the market order 207 of the unappropriated customer order 206 of 115 (from right to left) continuous consumption and any scheduling from RBCD200 to today.Next step 26, consumed remaining FGI202.
If also the amount of satisfying the demands has not generated RBCD and run counter to, then tell to make the user can not in promise date, satisfy customer order.System can select from left to right to move the order date of promising to undertake, and the unappropriated customer order of continuous consumption and market order are up to satisfying whole demand.System is to the user report order target date then.
Fig. 3 has shown the algorithm steps of RBCD200 outside requiring time durations 102.In the first step 31,115 (from right to left) continuous consumption will cause the FGO101 in the streamline 100 that FGI Max 201 is exceeded from RBCD200 to today.That is, calculating current FGI202 adds FGO101 and consumes and will cause FGI202 and FGO101's and greater than the FGO101 of FGI Max 201.Next step 32, then consume the FGI202 that surpasses FGIMax 201.Next step 33, (from right to left) continuous consumption ATP114 from RBCD200 to DTF102.Next step 34,115 (from right to left) continuous consumption will cause the FGO101 of the streamline 100 of FGI Min 204 in being exceeded from RBCD200 to today.Next step 35, consume deserved in the past FGO203.Next step 36, from RBCD200 to today the unappropriated client of 115 (from right to left) continuous consumption order 206 and the market of any scheduling order 207.Next step 37, consume to surpass the FGI202 of FGIMin 204.
If the amount of satisfying the demands not also, in step 38, from RBCD200 to demand time durations 102 (from right to left) continuous consumption available high resiliency amount.Available high resiliency amount is the maximum of planned production resource.As described in reference to figure 1, they by any given elasticity during amount of elasticity determine.Next step 39,100 li remaining FGO101 of 115 (from right to left) continuous consumption streamline from DTF102 to today.Next step 40, consume remaining FGI202.
If also the amount of satisfying the demands has not generated RBCD and run counter to, then tell the user can not in promise date, satisfy customer order.In step 41, system can from left to right move the order date of promising to undertake, and the unappropriated customer order 206 of continuous consumption, market order 207, ATP114 and high resiliency amount are up to satisfying whole demand.The order target date to the user report revision is followed by system.
Usually the sales forecast of determining in season with predicting strategy substantially exceeds in the production plant of productive capacity, handles seasonal straight line and rises.When in the demand time durations, receiving a large amount of order, also use this strategy.In these situations, outside DTF102, do not use during the elasticity, so only planned the resources of production of enough production forecast amounts 104.And, generate the FGO101 that satisfies minimum FGI target 204.
With reference to the algorithm steps of figure 4 explanation RBCD200 in requiring time durations 102.In the first step 42,115 (from right to left) continuous consumption will cause the FGO101 of the streamline 100 that FGI Max 201 is exceeded from RBCD200 to today.That is, calculating current FGI202 adds the FGO101 in the streamline and consumes and will cause FGI202 and FGO101's and greater than the FGO101 of FGI Max 201.Next step 43, consume to surpass the FGI202 of FGI Max 201.Next step 44, continuous consumption is 115 (from right to left) remaining FGO101 in streamline from RBCD200 to today.Next step 45, consume deserved in the past FGO203.Next step 46, the unappropriated client of 115 (from being shifted to the right to a left side) continuous consumption orders and the market order of any scheduling from RBCD200 to today.Next step 47, consumed remaining FGI202.
If also the amount of satisfying the demands has not been run counter to RBCD, then tell to make the user can not in promise date, satisfy customer order.In step 48, system can from left to right move the order date of promising to undertake, and the unappropriated customer order of continuous consumption and market order are up to satisfying whole demand.System is then to the user report order target date.
Fig. 5 has shown the algorithm steps of RBCD200 outside requiring time durations 102.In the first step 51,115 (from right to left) continuous consumption will cause the FGO101 of the streamline 100 that FGI Max 201 is exceeded from RBCD 200 to today.That is, calculating current FGI202 adds the FGO101 in the streamline and consumes and will cause FGI202 and FGO101's and greater than the FGO101 of FGI Max 201.Next step 52, then consume the FGI202 that surpasses FGI Max 201.Next step 53, from RBCD200 to demand time durations 102 (from right to left) continuous consumption ATP114.Next step 54, the FGO101 of 100 li on 115 (from right to left) continuous consumption streamline from RBCD200 to today.Next step 55, consume deserved in the past FGO203.Next step 56, from RBCD200 to today the unappropriated client of 115 (from right to left) continuous consumption order 206 and the market of any scheduling order 207.Next step 57, consumed remaining FGI202.
If also the amount of satisfying the demands has not been run counter to RBCD, then tell the user can not in promise date, satisfy customer order.In step 58, system can from left to right move the order date of promising to undertake, and the unappropriated customer order 206 of continuous consumption, market order 207 and ATP114 are up to satisfying whole demand.The order target date to the user report revision is followed by system.
The actual subscription application of policies is in a small amount of product of fragmentary demand.In the case, premeasuring 104 can not be suitable for.Outside DTF102, do not exist during the elasticity.Do not plan the FGO101 and the FG1202 of 100 li on streamline; Only place an order (in the situation of FGO101) and if then they just exist when cancelling this order in (in the situation of FGI202) in the DTF102 as the client.
Algorithm steps with reference to figure 6 explanation actual subscription strategies.In the first step 61, if there is FGI202 just to be consumed.Next step 62, the FGO101 of 115 (from right to left) continuous consumption streamline 100 from DTF102 to today.Next step 63, from RBCD200 to today the client of 115 (from right to left) continuous consumption unallocated (i.e. cancellation) order 206 and any market order 207.
If the amount of satisfying the demands not, and RBCD is less than producing the delivery time MLT205, the required time of other resources of production of production customer order that perhaps accumulates all raw material and scheduling usefulness, run counter to RBCD, then told user person's order before promise date, not satisfy.In step 64, system can from left to right move the order date of promising to undertake, and the unappropriated customer order of continuous consumption and market order are up to satisfying whole demand or up to having crossed MLT205.System is then to the user report order target date.
Narrated the option of several enhancing smoothing processes.It allows system and method for the present invention to adapt to the various conditions that may occur in any given production run.These modifications comprise promise can utilize series, package quantity, smoothing time left side boundary, fixing and general finished product order series.
Be used for promising to undertake series: this part belongs to one " ATP series " and can share each other premeasuring.It provides a kind of dirigibility of production customer demand, and this demand is not predicted specific products corresponding to another product consumption requirements from ATP series.Like this, can reduce the starting material amount that is retained in for any independent product on hand.Here it is the present invention is based on the administrative model of demand, shows as the reduction of measuring during product elasticity in the ATP series.Typically, algorithm will be revised as the ATP that at first consumes institute's order and then other part consumption sharing A TP on the same day in the ATP series.
Packing Unit: some customer requirement orders are with many times of amount shipments of certain parcel loading amount.Like this, revised the consumption rule of this algorithm.Consumption in given certain day any classification is the multiple of this Packing Unit like this.
Smoothing time left side boundary: the ordering products that smoothing time left side boundary prevents to have RBCD is near will be away from the FGO101 and the ATP114 that consume 100 li of FGI202, streamline in the time period of DTF102.Smoothing time left side boundary length is to determine on the date that after this smoothing takes place from the target date skew of customer requirement.If left side boundary date smoothing time outside DTF102, does not then then consume to whatever between the DTF102 on the left side on left side boundary date smoothing time.If left side boundary date smoothing time then adapts to the normal consumption rule in DTF102.
Limit: limit permission production discrete cell and be imparted to the particular customer order.A kind of hard closed indent will have a specific ID unit (may be a physical tags, mark or other diacritic features) to each parts; The association of unit is hard and binding.When producing smoothing, these parts can not be assigned to any other customer order.This will obviously reduce the amount of the available resources of production outside DTF102.Can specify soft closed indent, and limit for any soft qualification customer order again.Soft fixedly order meets the smoothing rule of logic.
General finished product order series: on the just left side of DTF102 one time window is arranged, wherein allow the general FGO101 that considers several finished products.These products are tradable in DTF102, up to certain special process, and for example punching press or spraying.This new time durations, perhaps general window of opportunity is general finished product order time boundary.In case FGO101 leaves this window, just disappeared from the chance of other finished product consumption requirements amounts.Yet in during the general finished product order time, any finished product that general finished product is ordered series can consume this finished product.
In addition, when reference requirement amount event horizon and elastic region one day time durations at interval is discussed, system and method for the present invention allows to use slightly little or big slightly time durations interval.Like this, for example, can be divided into class Three every day, and be the separately consumption and the distribution of the means of production of each class.
To choose enhancing wantonly together with above-mentioned can be used as below, provide an example of system and method for the present invention.With reference to figure 7a, the first according to the process flow diagram of the method step of the algorithm that uses of the specific embodiment of the invention has been described.When the new customer order that receives a kind of product, the method starts from 300.In the quantity of square frame 302 places inputs order and set up demand to the various resources of production.The product of ordering in this situation can be the finished product that the client orders, or must be by ordering the subassembly that the client produces finished product.At square frame 302 input product quantities can be that the user directly imports at workstation 304, perhaps can determine that the order endorsement system 306 of many different product quantity of given customer order receives in enterprise.
The method is then retrieved the order strategy of this product in the step 332 of input order strategy.The user person of system orders strategy and is stored in system database 320 for each product is provided with.Another kind, the user can select a kind of order strategy and at workstation 304 directly with its input.Whether the method then uses the forecast consumption strategy at 308 decision products.Do not use the forecast consumption strategy as fruit product, whether the method uses predicting strategy at 310 decision products.Do not use predicting strategy as fruit product, whether the method uses actual order strategy at 312 decision products.Do not use actual order strategy as fruit product, then this product does not use any available admitted order strategy and at step 314 reporting errors.Certainly will recognize that the method can carry out determining step 308,310 and 312 and at another embodiment with any order, use which order strategy such as the judgement product that uses the CASE statement.
If this product uses actual order strategy, the method is transferred to 316 A.Perhaps, if this product uses predicting strategy, the method is transferred to 318 B.Otherwise if do not report any mistake, then this product uses the forecast consumption strategy, and the method is transferred to the RBCD at square frame 322 input orders.RBCD is the date of product order entry system, and generally it is set to than the product bigger fate of (that is, producing) fate of can delivering in production line flowing water 100.For example, if the customer requirement product was delivered in 20 days, and produce this product and will spend 4 days (streamline 100 equals 4 days), RBCD is set to 16 days.This date can be by the user in workstation 304 inputs, and perhaps preferable obtains from order endorsement system 306.
The method is then retrieved the DTF of this product in the step of input DTF330.For each product is provided with DTF and stores this DTF in database 320.Another kind, the user can determine DTF and directly import at workstation 304.The method then at 324 decision RBCD whether in DTF.If RBCD not in DTF, RBCD outside DTF then the method transfer to 326 C.Otherwise RBCD is in DTF and the method is then replenished the step of order and finished goods inventory maximum target (FGImax) at the current finished product of square frame 327 input current finished goods inventories (FGI), streamline (FGOpipe) lining.What the method was preferable retrieves these information from database 320, and native system can keep the renewal to 320 li information of database.
The method then determines whether to exist the excessive FGO in streamline that will cause FGImax to be exceeded in process 328.Process 328 comprise calculate FGI add FGOpipe and with FGImax relatively:
FGI+FGOpipe>FGImax
Once more, be preferably in 320 li values of safeguarding FGI and FGOpipe of database.Another kind, the user directly imports these data at workstation 304.The method is estimated the excessive FGO that whether has from process 328 334.If have, consume these excessive FGO and the method at square frame 336 and determine 338 whether resources of production demands have satisfied and finish customer order.If can satisfy then the method is finished 340 and finished.
If the amount of satisfying the demands does not perhaps have excessive FGO from 334, then the method determines whether to have excessive FGI in process 342.Process 342 comprises the comparison of FGI and FGImax:
FGI>FGImax
Value at square frame 327 retrieval FGI and FGImax.Whether the method evaluation has excessive FGI 344.If have, determine 348 whether resources of production demands satisfy customer order at square frame 346 these excessive FGO of consumption and the method.If satisfy, then the method finishes 340.
If do not satisfy, perhaps in 344, there is not excessive FGO, the method is at the D that transfers to 350.Shown in 352 D among Fig. 7 b.The method then determines 354 li whether remaining FGOpipe is arranged in process.Value at square frame 327 retrieval FGOpipe.The method evaluation is at the 356 residual FGOpipe that whether have from process 354.If have, determining 360 to determine whether resources of production demands satisfy customer order at square frame 358 these excessive FGOpipe of consumption and the method.If satisfy, the method finishes 340.
If do not satisfy, if perhaps do not have residual F GOpipe from 356, the method is then carried out the input current orders of finished product in the past (FGOpast) at square frame 362.Preferable in 320 li values of safeguarding FGOpast of database.The method has then determined whether excessive FGOpast in process 364.The method is estimated the residual FGOpast that whether has from process 364 366.If have, determining 370 to determine whether resources of production demands have satisfied customer order at square frame 368 these residual FGOpast of consumption and the method.If satisfy, the method finishes 340.
If the amount of satisfying the demands not, if perhaps not from determining 366 residual FGOpast, the method is then carried out the step of the market order (MO) of input unallocated customer orders (uCO) and any planning at square frame 372.Preferable in 320 li values of safeguarding uCO and MO of database.The method has then determined whether excessive uCO and MO in process 374.The method is determining whether 376 assessments have uCO and the MO from process 374.If have, consume those uCO and MO and the method at square frame 378 and determining 380 to determine whether to satisfy and finish the required resources of production demand of customer order.If satisfied this demand, the method is finishing 340 end.
If demand does not satisfy, if perhaps do not have uCO and MO from 376, the method then determines 382 li whether remaining FGI is arranged in process.The value of square frame 327 retrieval FGI in Fig. 7 a.Whether the method evaluation has FGI 384.If have, determine 388 whether resources of production demands satisfy customer order at square frame 386 these FGI of consumption and the method.If satisfied this demand, the method is transferred to 402 F, and F404 finishes 340.
If the amount of satisfying the demands not, if perhaps do not have FGI from 384, the method generates RBCD and runs counter to 390, and the demand of the resources of production of announcement can not satisfy customer order.This system and method for the present invention is had the ability to determine to have at which day and is satisfied the required available resources of production demand of customer order.So which can fill up user's order at (i.e. best date) at.In the case, each product records a best date switch, if when this switch is opened, tells system and method for the present invention to determine to fill up first date of customer order.
The method is retrieved best date on off states at the best date switch square frame 392 of input, and determines the state of these switches in process 394.Whether the method is being opened at the best date switches of 396 assessments, and if do not open, the method is transferred to 406 F and part F and is finished 340.If opening at 396 best date switches, the method was the back mobile RBCD of square frame 398 one day.Square frame 398 increases RBCD one day.The method is then transferred to 400 E.E shows in Fig. 7 a, and the E control of shifting the method gets back to 324 to determine that RBCD is whether in DTF.
In the RBCD situation in DTF not, the method is from 326 C that transfer to 408 in Fig. 7 c.Then the method is carried out input FGI, FGOpipe, FGImax and finished goods inventory minimum target (FGImin) at square frame 410.What the method was preferable retrieves these information from database 320.
The method then determines whether to exist the excessive FGO that will cause in the streamline that FGImax is exceeded in process 412.Process 412 comprise calculate FGI add FGOpipe and will with FGImax relatively:
FGI+FGOpipe>FGImax
The method is estimated the excessive FGO that whether has from process 412 414.If have, determine 418 whether resources of production demands satisfy customer order at square frame 416 these excessive FGO of consumption and the method.If satisfy, the method finishes 340.
If the amount of satisfying the demands not, if perhaps do not have excessive FGO from 414, then the method determines whether there is excessive FGI in process 420.Process 420 comprises the comparison of FGI and FGImax:
FGI>FGImax
Retrieved the value of FGI and FGImax at square frame 410.Whether the method evaluation has excessive FGI 422.If have, determine 426 whether resources of production demands satisfy customer order at square frame 424 these excessive FGI of consumption and the method.If satisfied, the method finishes 340.
If the amount of satisfying the demands not, if perhaps do not have excessive FGI from 422, then the method is then carried out input premeasuring and customer orders at square frame 428.What the method was preferable retrieves these information from database 320.
The method has then determined whether excessive ATP in process 430.Process 430 comprises the calculating premeasuring and deducts client's quantity ordered:
Pre-quantitation-client's lot-size
The method evaluation is at the 432 excessive ATP that whether have from process 430.If have, determine 436 whether resources of production demands satisfy customer order at square frame 434 these excessive ATP of consumption and the method.If satisfy, the method is transferred to 438 G and part G440 and is finished 340.
If the amount of satisfying the demands not, if perhaps do not have excessive ATP 432, then the method determines whether there is excessive FGOpipe in process 442.Retrieved the value of FGOpipe at square frame 410.Whether the method is evaluated at process 442 444 remaining FGOpipe.If have, determine 448 whether resources of production demands have satisfied customer order at square frame 446 these excessive FGI of consumption and the method.If satisfy, the method is transferred to 438 G and part G440 and is finished 340.
If the amount of satisfying the demands not, if perhaps not from 444 residual F GOpipe, the method is then carried out the step of input FGOpast at square frame 450.Be preferably the value (not showing) of safeguarding FGOpast 320 li of databases.The method has then determined whether excessive FGOpast in process 452.The method is estimated the residual F GOpast that whether has from process 452 454.If have, determining 458 to determine whether resources of production demands satisfy customer order at square frame 456 consumption this residual F GOpast and the method.If satisfy, the method finishes 340 at the G and the G440 that transfer to 438.
If the amount of satisfying the demands not, if perhaps not from 454 residual F GOpast, the method is then carried out input uCO and MO at square frame 460.Be preferably the value (not showing) of safeguarding uCO and MO 320 li of databases.The method has then determined whether excessive uCO and MO in process 462.The method is assessed uCO and the MO that whether has from process 462 464.If have, consume those uCO and MO and the method at square frame 466 and determine 468 whether resources of production demand has satisfied customer order.If satisfy, the method is transferred to 438 part G and G440 and is finished 340.
If the amount of satisfying the demands is arranged, if perhaps do not have uCO and MO from 464, the method has then determined whether greater than FGImin residual F GI 470 li of processes.Retrieved the value of FGI and FGImin at square frame 410.The method is assessed the FGI that whether has greater than FGImin 472.If have, whether FGI and the method for consuming greater than FGImin at square frame 474 satisfy customer order in 476 definite resources of production demands.If satisfy, the method is transferred to 478 F, and F404 finishes 340.
If the amount of satisfying the demands not, if perhaps from 472 not greater than the FGI of FGImin, the method is then transferred to 480 H and section H 482 and is shifted the elastomeric value of square frames 484 inputs.Be preferably 320 li of databases and safeguard elastomeric values (not showing) or can be by the user in workstation 340 (not showing) input.The method then determines whether excessive high resiliency in process 486.The method is assessed the high resiliency that whether has from process 486 488.If have, determine 492 whether resources of production demands satisfy customer order at this residue high resiliency of square frame 490 consumption and the method.If satisfy, the method is transferred to 494 G and part G440 and is finished 340.
If the amount of satisfying the demands not, if perhaps there is not high resiliency in 488, the method has then determined whether remaining FGOpipe for 496 li in process.Retrieved the value of FGOpipe at square frame 410.The method evaluation is at the 498 residual F GOpipe that whether have from process 496.If have, determine 502 whether resources of production demands satisfy customer order at square frame 500 these excessive FGOpipe of consumption and the method.If satisfy, the method is transferred to 504 G and G440 and is finished 340.
If the amount of satisfying the demands not, if perhaps there is not FGOpipe in 498, the method is transferred to 506 I.Shown I508 in Fig. 7 b, I rotates back into process 382 with control and determines residual F GI and continuation therefrom.
When the order strategy from Fig. 7 a square frame 332 is the situation of predicting strategy, 318 508Bs that transfer in Fig. 7 d of the method from Fig. 7 a.Then the method can equal 0 and then 512 J514 that transfer among Fig. 7 a from Fig. 7 d during square frame 510 is provided with elasticity.J514 rotates back into square frame 322 with control, input RBCD and continuation therefrom.
When the order strategy from the square frame 332 of Fig. 7 a is the situation of actual order strategy, 316 A516s that transfer in Fig. 7 e of the method from Fig. 7 a.Then the method can during square frame 518 is provided with elasticity, equal 0 and premeasuring equal 0 and then the transferase 45 20 from Fig. 7 e transfer to J514 among Fig. 7 a.J514 rotates back into square frame 322 with control, input RBCD and continuation therefrom.
Certainly, should be noted that the accurate order that resources of production demand is consumed can change in not departing from scope of the present invention.For example, do not have the product of enough shelf lifes, or during other products that rot easily, expectation replenishes order and preferentially consumes any finished goods inventory that surpasses the finished goods inventory minimum target prior to finished product in streamline in the manufacturing.With reference to figure 3, can direct execution in step 37 after step 32 and before the step 34.This will make system and method tendency of the present invention keep the finished goods inventory minimum target.Thereby the goods that rots often can be retained on stock's shelf easily.
Should also be noted that the situation that belongs to ATP series in specific features, can revise the method, be convenient to before square frame 434 and process 442, to consume the miscellaneous part consumption ATP from ATP series after any excessive ATP (if there is) in the process 430 of Fig. 7 c.And the method consumes after any excessive high resiliency (if there is) before can also being modified in square frame 490 and process 442, the available high resiliency of sharing from the consumption of ATP series miscellaneous part in the process 486 of Fig. 7 c.
Rate is several days a mathematical mean because system and method for the present invention is determined synthetic every day, and it comprises prediction and historical element in the future in the past, can suppress the upper and lower big ups and downs of actual every day of rate and can eliminate the artificial interference of rate every day.Elasticity volume is only with demand trend, historical pattern, perhaps some impulsions of changing of prediction and changing.Extra elasticity volume is only with demand trend, and historical pattern predicts that perhaps some impulsion amounts that change are just available.Thereby supplier has seen it not being the less changeableness of an actual demand amount trend part and the direction that the actual demand amount is provided that there is the reliable reflection of more predictabilitys in system.Which the material planning person can determine more important by the weighting of the mean value of adjusting composition, streamline rate, pre-quantitation or historical data.And the observation of time frame can be arranged to have nothing in common with each other in every month.
To Fig. 8 v, shown an example of the arithmetic result that is applied to not expect customer order according to a particular embodiment of the invention with reference to figure 8a.Fig. 8 a has described and has worked as precondition, before the extra client order of today and reception product.
So shown in the example, producing the delivery time is six days, and has during three each elasticity of three days by a definite date, and 10%, 20% and 30% amount of elasticity is arranged respectively during each.The product of 20 units and 10 FGOpast836 of unit of finished product order are in the past arranged in finished goods inventory FGI834.Rate every day of today 802 832 is 100.That is, will produce the product of 100 units today.In these 100 units, 90 distribute to customer order 838 and remaining 10 units to be current finished products in the streamline replenish order FGOpipe840.
Shown in whole during the prediction of (15 days) be 100 unit products every day.At the actual customer order 838 that has shown product every day in the works.In this example, actual customer order is lower than pre-quantitation, so rate every day in the streamline 832 is set to premeasuring 100.Surpass those days of pre-quantitation in client's quantity ordered, will every day rate 832 be set to client's lot-size.
The demand of current planning, demand 844 in during the elasticity, also is set to the big person between actual client's lot-size 838 and the pre-quantitation.The quantity available that allows, ATP842 is the poor of demand 844 and actual client's lot-size 838.
The finished product of having produced and not distributed to customer order replenishes order and can distribute to finished goods inventory except that satisfying new customer order.
Now, at the new order of 100 unit products of shipment in the 9th day with to 50 unit products of shipment in the 4th day.This algorithm is checked the request the earliest of setting up the target date, the 4th day, at first, determines whether to satisfy this requirement of product.This algorithm at first consumes 10 FGOpipe of unit of the 4th day 808 and forwards them to client's lot-size 838.With reference to figure 8b.
Then, this algorithm consumes 10 units of FGOpast836, and 10 FGOpipe of unit (this also may be thought of as FGOpipe in this context) that consume today 802 and can use and transfer them to client's lot-size 838, with reference to figure 8c, for satisfy the 4th day order also needs produce 20 units.
Then, this algorithm consumes the FGOpipe (from right to left) of next day among the available FGOpipe, in this example, with the FGOpipe of 20 units of the 3rd day 806, stays 10 units, is client's lot-size 838, satisfies the 4th day demand.With reference to figure 8d.
Algorithm assigns is at the customer order of 100 units of the 9th day now.Algorithm at first consumes 30 unit products from the 9th day 818 ATP842.With reference to figure 8e.
Then, the ATP842 that this algorithm moves up into a day (from right to left) and consumes at 20 units of the 8th day 816, then algorithm shift-in one day and consume 10 ATP842 of unit again at the 7th day 814.With reference to figure 8f.Also need to distribute 40 unit product demands.
Then, this algorithm is shift-in several days again, crosses the demand time durations, and DTF102 is up to finding stupefied available FGOpipe840.In this example, consume 40 unit products from the 5th day 810 FGOpipe840, stay 10 a units product, and satisfy the product demand of the 9th day customer order.With reference to figure 8g.
Now, 100 unit new orders will be shipment in the 9th day.Do not stay ATP842 between the 9th day 818 and the DTF102.Thereby 40 FGOpipe of unit that this algorithm is checked FGOpipe and consumed the 2nd day 804, the 3 days 806 and the 5th days 810 also will distribute 60 units with reference to figure 8h.
This algorithm then consumes the FGI834 that surpasses the finished goods inventory minimum target, in this example, is 0 to have consumed 20 all FGI834 of unit so minimize Target Setting.With reference to figure 8i.
Algorithm then consumes high resiliency 846, shifts to DTF102 since the 9th day 818.Like this, client's lot-size 838 of the 7th day 814, the 8 days 816 and the 9th days 818 is increased to 110.With reference to figure 8j.Notice that the demand of these days is increased to 100, reflecting to increase resource requirement.
Also need to distribute the finished product demand of 10 units.Yet available never again resource satisfies this demand under current plan.If the best date switch of this product cuts out, then system runs counter to user report RBCD.On the other hand, if the best date switch of this product is being opened, then this algorithm checks that next available ATP842 (from left to right) consumes 10 ATP842 of unit of the 10th day 820 in this example.With reference to figure 8k.Because this order demand satisfies now, can report the best date, the 10th day, and change in the prompting customer order.
For this example, suppose that best date switch opening.Received 250 unit new orders at the 14th day.At first, consume the ATP842 of 80 units of the 14th day.Shift to DTF102, consumed the ATP842 of 70 units from the 13rd day 826, consumed the ATP842 of 60 units from the 12nd day 824 and consumed the ATP842 of 40 units from the 11st day 822, stayed 10 ATP842 of unit at the 11st day 822 and satisfied the 14th day new order demand.With reference to Figure 81.
Notice that system and method for the present invention has satisfied customer order near RBCD, has stayed ATP and FGOpipe near today as much as possible.Thereby early customer order can also satisfy.
In next day, became today on the 2nd day.Because demand 844 was increased to 110 in the 7th day 814, every day rate 832 to be set at the 6th day 812 now be 110.With reference to figure 8m.Other day from right to left, and new had be added in this plan in the 15th day 830 of 0 customer order.
Notice that be based on the every day rate to whole streamline and prediction in the future and historical data average in the past because with target rate every day amount of elasticity is set, typical amount is change not.Yet if whole streamline rate every day has been increased, amount of elasticity also will increase.Like this, amount of elasticity is not a flip-flop, but only corresponding on the rise.
Continue to come order.Now, receive order at 125 units of the 15th day.At first consume 100 ATP842 of unit at the 15th day 830.With reference to figure 8n.Also need 25 units.
Then, consume the ATP842 of next 25 units of the 14th day 828 that enter.With reference to figure 8o.The 15th day order demand has satisfied.
In next day, became today on the 2nd day.With reference to figure 8p.Continuing order has.Equally, all dates move from right to left and have increased new the 15th day 830.Now, receive order at 125 units of the 15th day.At first, at first consume 100 ATP842 of unit of the 15th day 830.Also need 25 units.Then, consuming the ATP842 of 25 units in the next sky that available ATP is arranged that enters, is the 13rd day 826 in this example.With reference to figure 8q.The 15th day order demand has satisfied.
In next day, became today on the 2nd day.With reference to figure 8r.Order continues to arrive.Now, receive order at 125 units of the 15th day.At first, consume 100 ATP842 of unit at the 15th day 830.Also need 25 units.Then, consuming the ATP842 of 25 units in the next sky that available ATP arranged, is the 12nd day 824 in this example.With reference to figure 8s.The 15th day order demand has satisfied.
In next day, became today on the 2nd day.With reference to figure 8t.Notice that owing to crossed DTF in the 7th day 814, actual order measures 848 during being less than low elasticity.Replenish order so produce the finished product of schedulable 20 units.With the method, the resources of production amount that is used for production run is not to change significantly and the actual least resource amount of using plan.
Order continues to arrive.Now, receive order at 125 units of the 15th day.The ATP842 of 100 units of the 15th day 830 of Xiao Haoing at first.Also stay the demand of 50 units.Then, consume the ATP842 in the next sky that available ATP is arranged that enters, in this example, 15 units of the 11st day 824 and 10 units of the 7th day 814.With reference to figure 8u.Also stay the demand of 25 units.
Because DTF102 do not have ATP842 outward again, and do not have available FGOpast836 and FGI834 yet, this algorithm shift-in (from right to left) is up to there being first day of available FGOpipe840, in this example in, having first day of available FGOpipe840 is the 6th day 812.Consume those 20 units and transfer it to client's lot-size 838.Also stay the demand of 5 units.Thereby this algorithm shifts out (from left to right) up to first day that available amount of elasticity is arranged, and in this example, having first day of available amount of elasticity is the 7th day 814.Client's lot-size 838 of the 7th day 814 is increased to 105 units.With reference to figure 8v.The 15th day demand has satisfied.
Thereby system and method for the present invention goes for not expecting customer order, does not temporarily need during the artificial lifting elasticity above premeasuring.In this example, relatively stable 100 units every day that remain of aggregate demand in whole plan.Yet, if the customer order of receiving surpasses prediction, aggregate demand will begin to go up and elasticity during measure and also will go up.If this trend continues, system will send the signal of adjusting prediction to market department.
To see that above-mentioned instructions makes the object of illustrating clearly, and has effectively reached above-mentioned target.Change as long as in carrying out said method, can carry out some without departing from the spirit and scope of the present invention, expect that all the elements that above-mentioned instructions and accompanying drawing show are construed as illustrative and should limit to some extent the present invention.
Should be appreciated that also following claim expectation covers the statement of all general and the special characteristic and the scope of the invention of the present invention described here, because linguistic relation should drop in the claim.

Claims (50)

  1. One kind in the production schedule according to the customer order of product, the method of scheduling manufacturing resources demand, the wherein said production schedule comprises during delivery time of producing described product, at least one elasticity outside the described delivery time and at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, it is characterized in that described method comprises following step:
    Input shows the product customer order of resources of production demand;
    The target date that described customer order requires is produced in input;
    Retrieval is produced the delivery time of described product and at least to the finished product order that is scheduled, finished goods inventory, promise available resources, in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource retrieved the current available resource amount in the past from the production schedule;
    Determine describedly to require whether the target date is in the described delivery time, equal the described delivery time, in outside the described delivery time one;
    If described to require the target date be in the described delivery time and equal in the described delivery time one, then at least in one the described available volume of resources from the described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and described market order, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production;
    If the target date of described requirement is outside the described delivery time, then at least in one the described available volume of resources from the described finished product order that is scheduled, described finished goods inventory, described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and described high resiliency resource, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production; And
    In the described production schedule that wherein consumes described demand, upgrading each described available volume of resources.
  2. 2. the method for claim 1 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And described method also comprises following steps, prediction quantity ordered and the historical quantity ordered of retrieval during during average every day of described delivery time quantity ordered, described elasticity in the described production schedule, and, determine described high resiliency resource and described low elasticity resource during during the described elasticity based on compound every day of the rate numeral that comprises at least from one weighting factor in described average every day quantity ordered, described prediction quantity ordered and the described historical quantity ordered.
  3. 3. method as claimed in claim 2 is characterized in that, the described production schedule also comprises the relevant renewable available volume of resources of promise available series of the promise available resources of sharing with Related product; And described method also comprises step: the current available resource amount of retrieving the promise available series of described product, if and describedly require the target date outside the described delivery time, then the described promise available resources that described Related product is shared in described promise available series, the described demand that consumes the described resources of production.
  4. 4. method as claimed in claim 2 is characterized in that, the described production schedule also is included in the described smoothing time left side boundary fate that required before the target date; And described method also comprises following steps: the smoothing time left side boundary of retrieving described finished product; And if describedly required the target date outside the described delivery time, then the consumption step with the described demand of the described resources of production would be restricted to described smoothing time left side boundary.
  5. 5. method as claimed in claim 2 is characterized in that, the described production schedule also comprises the relevant renewable available volume of resources of general finished product series of the finished product order of sharing with Related product that is scheduled when described product is indistinction with described Related product; And comprise step: the current available resource amount of retrieving the general series of described product, if and described to require the target date be in the described delivery time and equal in the described delivery time one, then with described general finished product series in described Related product described being conditioned in the finished product order of sharing, the described demand that consumes the described resources of production.
  6. 6. method as claimed in claim 2 is characterized in that the described production schedule also comprises the maximum target of described finished goods inventory; Also comprise step: retrieve the maximum target of the described finished goods inventory of described product, and the described finished product order and surpass the described demand that consumes the described resources of production among the described finished goods inventory of described maximum target one of being scheduled from surpassing described maximum target with described finished goods inventory addition at least.
  7. 7. method as claimed in claim 6 is characterized in that the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise, retrieve the minimum target of the described finished goods inventory of described product, and from surpass the described finished goods inventory of described minimum target, consume the described demand of the described resources of production.
  8. One kind in the production schedule according to the product customer order, the system of scheduling manufacturing resources demand, the wherein said production schedule comprises the delivery time of producing described product, during at least one elasticity outside the described delivery time with at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, it is characterized in that described system comprises:
    Be used to import the input equipment of the product customer order that shows resources of production demand;
    Be used to import the device of producing the described customer order requirement target date;
    A database stores the delivery time of the described product of production in the production schedule and is be scheduled finished product order, finished goods inventory, promise available resources, a current available resource amount in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past at least;
    Determine that described whether require the target date be in the described delivery time, equal the described delivery time, one device in outside the described delivery time;
    To require the target date be in the described delivery time and equal in the described delivery time one when described, at least from the described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and described market order one described available volume of resources in, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production;
    When the target date of described requirement is outside the described delivery time, be used for from one described available volume of resources of the described finished product order that is scheduled, described finished goods inventory, described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and described high resiliency resource, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production; With
    Be used to upgrade the device of each the described available volume of resources in the described production schedule that therefrom consumes described demand.
  9. 9. system as claimed in claim 8 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And described system also comprises and is used in described production schedule retrieval at average every day of described delivery time quantity ordered, prediction quantity ordered during during the described elasticity and the device of historical quantity ordered, with based on compound every day of the rate number that comprises at least from one weighting factor in described average every day quantity ordered, described prediction quantity ordered and the described historical quantity ordered, determine the described high resiliency resource during during the described elasticity and the device of described low elasticity resource.
  10. 10. system as claimed in claim 9 is characterized in that, the described production schedule also comprises the promise of the promise available resources of sharing with Related product can utilize the relevant renewable available volume of resources of series; Also comprise the promise of retrieving described product and can utilize the device of the current available resource amount of series, with when target date of described requirement outside the described delivery time, can utilize the described promise available resources that described Related product is shared in the series from described promise, consume the device of the described demand of the described resources of production.
  11. 11. system as claimed in claim 9 is characterized in that, the described production schedule also is included in the described smoothing time left side boundary fate that required before the target date; And described system also comprises the device of the smoothing time left side boundary of retrieving described finished product; With ought describedly require the target date outside the described delivery time, the described step that consumes the described demand of the described resources of production is limited to the device of described smoothing time left side boundary.
  12. 12. system as claimed in claim 9 is characterized in that, the described production schedule also comprises when described product and described Related product are indistinction, shares the relevant renewable available volume of resources of general finished product series of the finished product order that is scheduled with Related product; And described system also comprises the device of the current available resource amount of the general finished product series that is used to retrieve described product, with be used for when the target date of described requirement is in the described delivery time and equals of described delivery time, then the described finished product order that is scheduled that described Related product is shared in described general finished product series, consume the device of the described demand of the described resources of production.
  13. 13. system as claimed in claim 9 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; Described system also comprises the device of the maximum target of the described finished goods inventory of retrieving described product, the described finished product order and surpassing among the described finished goods inventory of described maximum target one of being scheduled that may surpass described maximum target at least from described finished goods inventory addition the time consumes the device of the described demand of the described resources of production.
  14. 14. system as claimed in claim 13 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise, retrieve the minimum target of the described finished goods inventory of described product, and the step that from surpass the described finished goods inventory of described minimum target, consumes the described demand of the described resources of production.
  15. 15. one kind in the production schedule corresponding to the product customer order, the method of scheduling manufacturing resources demand, the wherein said production schedule comprises the delivery time of producing described product, during at least one elasticity outside the described delivery time with at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, it is characterized in that described method comprises step:
    Input shows the product customer order of resources of production demand;
    The target date that described customer order requires is produced in input;
    Retrieval is produced the delivery time of described product and at least to the finished product order that is scheduled, finished goods inventory, promise available resources, in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource retrieved its current available resource amount in the past from the production schedule;
    Whether the target date of determining described requirement be in the described delivery time, equal the described delivery time, in outside the described delivery time one;
    Retrieval can utilize the relevant renewable available volume of resources of series with the promise of the promise available resources that Related product is shared;
    If the target date of described requirement is in the described delivery time and equals in the described delivery time one, at least in one the described available volume of resources in the described finished product order that is scheduled that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and described market order, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production;
    If the target date of described requirement is outside the described delivery time, at least from the described promise available resources of the described finished product order that is scheduled, described finished goods inventory, described product, can utilize in one the described available volume of resources described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and the described high resiliency resource that described Related product is shared in the series with described promise, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production; And
    Can utilize each described available volume of resources of renewal in the series in the described production schedule that therefrom consumes described demand and described promise.
  16. 16. method as claimed in claim 15 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And comprise, retrieval is in average every day of described delivery time quantity ordered, prediction quantity ordered and historical quantity ordered during during the described elasticity the described production schedule, and, determine the described high resiliency resource during during the described elasticity and the step of described low elasticity resource based on compound every day of the rate number that comprises at least from one weighting factor in described average every day quantity ordered, described prediction quantity ordered and the described historical quantity ordered.
  17. 17. method as claimed in claim 15 is characterized in that, the described production schedule also is included in the described smoothing time left side boundary fate that required before the target date; And comprise step: the smoothing time left side boundary of retrieving described finished product; And if describedly required the target date outside the described delivery time, then will be to the consumption step limit of the described demand of the described resources of production in described smoothing time left side boundary.
  18. 18. method as claimed in claim 15 is characterized in that, the described production schedule also comprises when described product and described Related product are indistinction, the relevant renewable available volume of resources of general finished product series of the finished product order of sharing with Related product that is scheduled; And comprise step: the current available resource amount of retrieving the general finished product series of described product, if and the target date of described requirement is in the described delivery time and equals in the described delivery time one, the described demand that the described finished product order that is scheduled that described Related product is shared in the described general finished product series consumes the described resources of production.
  19. 19. method as claimed in claim 15 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; Also comprise step: the maximum target of retrieving the described finished goods inventory of described product, and the described finished product order and surpassing among the described finished goods inventory of described maximum target one of being scheduled from surpassing described maximum target with described finished goods inventory addition consumes described resources of production demand at least.
  20. 20. method as claimed in claim 19 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise, retrieve the minimum target of the described finished goods inventory of described product, and from surpass the described finished goods inventory of described minimum target, consume the step of the described demand of the described resources of production.
  21. 21. system that in the production schedule, plans resources of production demand corresponding to the product customer order, the wherein said production schedule comprises the delivery time of producing described product, during at least one elasticity outside the described delivery time with at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, one relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, it is characterized in that described system comprises:
    Be used to import the input equipment of the product customer order that shows resources of production demand;
    Be used to import the device of the target date of producing described customer order requirement;
    A database stores the delivery time of the described product of production in the production schedule and is at least the finished product order that is scheduled, finished goods inventory, promise available resources, one current available resource amount in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past;
    Whether the target date that is used for determining described requirement is in the described delivery time, equals described delivery time, one device outside the described delivery time;
    The promise of the promise available resources of sharing with Related product can be utilized the relevant renewable available volume of resources of series;
    Be in the described delivery time and equal in the described delivery time one when the target date of described requirement, at least in one the described available volume of resources from the described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and described market order, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production;
    When the target date of described requirement is outside the described delivery time, be used for from the described finished product order that is scheduled, described finished goods inventory, described promise available resources, can utilize one the described available volume of resources of described Related product is shared in the series described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and described high resiliency resource with described promise, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production; With
    Can utilize the device that upgrades each described available volume of resources in the series in the described production schedule that has therefrom consumed described demand and described promise.
  22. 22. system as claimed in claim 21 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And comprise and be used in described production schedule retrieval at average every day of described delivery time quantity ordered, prediction quantity ordered during during the described elasticity and the device of historical quantity ordered, with based on compound every day of the rate number that comprises at least from one weighting factor in described average every day quantity ordered, described prediction quantity ordered and the described historical quantity ordered, determine the described high resiliency resource during during the described elasticity and the device of described low elasticity resource.
  23. 23. system as claimed in claim 21 is characterized in that, the described production schedule also is included in the described smoothing time left side boundary fate that required before the target date; And comprise the device of the smoothing time left side boundary of retrieving described finished product; With ought describedly require the target date outside the described delivery time, the described consumption step that limits the described demand of the described resources of production is the device of described smoothing time left side boundary.
  24. 24. system as claimed in claim 21 is characterized in that, the described production schedule also comprises the relevant renewable available volume of resources of general finished product series of the finished product order of sharing with Related product that is scheduled when described product is indistinction with described Related product; And comprise the device of the current available resource amount of the general finished product series that is used to retrieve described product, with to be used for target date when described requirement be in the described delivery time and equal of described delivery time, the described finished product order that is scheduled that described Related product is shared in the described general finished product series consumes the device of the described demand of the described resources of production.
  25. 25. system as claimed in claim 21 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; The device that also comprises the maximum target of the described finished goods inventory that is used to retrieve described product, at least will consume the device of the described demand of the described resources of production above be scheduled finished product order and surpassing among the described finished goods inventory of described maximum target one of described maximum target described from described finished goods inventory addition the time.
  26. 26. system as claimed in claim 25 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise, retrieve the minimum target of the described finished goods inventory of described product, and the step that from surpass the described finished goods inventory of described minimum target, consumes the described demand of the described resources of production.
  27. 27. method of in the production schedule, planning resources of production demand corresponding to the product customer order, comprise the delivery time of producing described product, with at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, described method comprises step during at least one elasticity outside the described delivery time:
    Input shows the product customer order of resources of production demand;
    The target date that described customer order requires is produced in input;
    Retrieval is produced the delivery time of described product and at least from the finished product order that is scheduled, finished goods inventory, promise available resources, in the past among finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource, retrieve the current available resource amount from the production schedule;
    Whether the target date of determining described requirement be in the described delivery time, equal the described delivery time, in outside the described delivery time one;
    Retrieve the smoothing time left side boundary fate of described product before requiring the target date;
    If the target date of described requirement is in the described delivery time and when equaling in the described delivery time one, at least in one the described available volume of resources from the described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and described market order, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production;
    If the target date of described requirement is outside the described delivery time, at least in the described available volume of resources from the described finished product order that is scheduled, described finished goods inventory, described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and described high resiliency resource, in in described smoothing time left side boundary, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production; And
    Therefrom consuming each described available volume of resources of renewal in the described production schedule of described demand.
  28. 28. method as claimed in claim 27 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And comprise step: retrieval is in average every day of described delivery time quantity ordered, prediction quantity ordered and historical quantity ordered during during the described elasticity the described production schedule, and, determine the described high resiliency resource during during the described elasticity and the step of described low elasticity resource based on compound every day of the rate number that comprises at least from one weighting factor in described average every day quantity ordered, described prediction quantity ordered and the described historical quantity ordered.
  29. 29. method as claimed in claim 27 is characterized in that, the described production schedule also comprises the promise of the promise available resources of sharing with certain Related product can utilize the relevant renewable available volume of resources of series; Also comprise step: the promise of retrieving described product can be utilized the current available resource amount of series, if and the target date of described requirement is outside the described delivery time, then, consume described from utilizing the described promise available resources that described Related product is shared in the series with described promise
    The step of the described demand of the resources of production.
  30. 30. method as claimed in claim 27 is characterized in that, the described production schedule also comprises when described product and described Related product are indistinction, the renewable available volume of resources of general finished product series of the finished product order of sharing with Related product that is scheduled; And comprise step: the current available resource amount of retrieving the general finished product series of described product, if and the target date of described requirement is in the described delivery time and equals in the described delivery time one, the described demand that the described finished product order that is scheduled that described Related product is shared in the described general finished product series consumes the described resources of production.
  31. 31. method as claimed in claim 27 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; Also comprise step: retrieve the maximum target of the described finished goods inventory of described product, and at least from when with described finished goods inventory addition, may surpass described maximum target described be scheduled the finished product order and surpass the described finished goods inventory of described maximum target at least one consume described resources of production demand.
  32. 32. method as claimed in claim 31 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise step: retrieve the minimum target of the described finished goods inventory of described product, and from surpass the described finished goods inventory of described minimum target, consume described resources of production demand.
  33. 33. system that in the production schedule, plans resources of production demand corresponding to the product customer order, comprise the delivery time of producing described product, with at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, described system comprises during at least one elasticity outside the described delivery time:
    Be used to import the input equipment of the product customer order that shows resources of production demand;
    Be used to import the device of the target date of producing described customer order requirement;
    A database, it has stored the delivery time of the described product of production in the production schedule and has been at least the finished product order that is scheduled, finished goods inventory, promise available resources, one current available resource amount in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past;
    Whether the target date that is used for determining described requirement is in the described delivery time, equals described delivery time, one device outside the described delivery time;
    At described described product smoothing time left side boundary fate before requiring the target date;
    Be in the described delivery time and equal in the described delivery time one when the target date of described requirement, be used for from one described available volume of resources of the described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and described market order, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production;
    When the target date of described requirement is outside the described delivery time, be used for from one described available volume of resources of the described finished product order that is scheduled, described finished goods inventory, described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and described high resiliency resource, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production; With
    Therefrom consuming the device that upgrades each described available volume of resources in the described production schedule of described demand.
  34. 34. system as claimed in claim 33 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And described system also comprises and is used in described production schedule retrieval at average every day of described delivery time quantity ordered, prediction quantity ordered during during the described elasticity and the device of historical quantity ordered, with be used for based on compound every day of the rate number of one weighting factor that comprises from described average every day quantity ordered, described prediction quantity ordered and described historical quantity ordered, determine the described high resiliency resource during during the described elasticity and the device of described low elasticity resource.
  35. 35. system as claimed in claim 33 is characterized in that, the described production schedule also comprises the promise of the promise available resources of sharing with certain Related product can utilize the relevant renewable available volume of resources of series; Described system also comprises the device that the promise that is used to retrieve described product can be utilized the current available resource amount of series, work as the target date of described requirement outside the described delivery time with being used for, can utilize the described promise available resources that described Related product is shared in the series from described promise, consume the device of the described demand of the described resources of production.
  36. 36. system as claimed in claim 33, it is characterized in that, the described production schedule also comprises when described product and described Related product are indistinction, the relevant renewable available volume of resources of general finished product series of the finished product order of sharing with certain Related product that is scheduled; And described system also comprises the device of the current available resource amount of the general finished product series that is used to retrieve described product, with be used for when the target date of described requirement is in the described delivery time and equals of described delivery time, the described finished product order that is scheduled that described Related product is shared in described general finished product series, consume the device of the described demand of the described resources of production.
  37. 37. system as claimed in claim 33 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; Described system also comprises the device of the maximum target of the described finished goods inventory that is used to retrieve described product, at least perhaps will consume the device of the described demand of the described resources of production from described finished goods inventory addition the time above be scheduled finished product order and surpassing in the described finished goods inventory of described maximum target at least one of described maximum target described.
  38. 38. system as claimed in claim 37 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise step: retrieve the minimum target of the described finished goods inventory of described product, and from surpass the described finished goods inventory of described minimum target, consume the step of described resources of production demand.
  39. 39. method of in the production schedule, planning resources of production demand corresponding to the product customer order, comprise the delivery time of producing described product, during at least one elasticity outside the described delivery time with at least with the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, described method comprises step:
    Input shows the product customer order of resources of production demand;
    The target date that described customer order requires is produced in input;
    Retrieval is produced the delivery time of described product and is at least the finished product order that is scheduled, finished goods inventory, promise available resources, one current available resource amount in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past from the production schedule;
    Whether the target date of determining described requirement be in the described delivery time, equal the described delivery time, in outside the described delivery time one;
    When described product and described Related product are indistinction, the serial relevant renewable available volume of resources of general finished product of the finished product order that is scheduled that retrieval and Related product are shared;
    If the target date of described requirement is in the described delivery time and equals in the described delivery time one, at least from the described finished product order that is scheduled, with described general finished product series in one the described available volume of resources described the Related product described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and the described market order shared, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production;
    If the target date of described requirement is outside the described delivery time, at least from the described finished product order that is scheduled, with described general finished product series in one the described available volume of resources described the Related product described finished product order that is scheduled, described finished goods inventory, described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and the described high resiliency resource shared, consume the described demand of the described resources of production, up to the described demand that is dispatched to the described resources of production; And
    Therefrom consuming each described available volume of resources of upgrading in the described production schedule of described demand.
  40. 40. method as claimed in claim 39 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And comprise step: retrieval is in average every day of described delivery time quantity ordered, prediction quantity ordered and historical quantity ordered during during the described elasticity the described production schedule, and, determine the described high resiliency resource during during the described elasticity and the step of described low elasticity resource based on compound every day of the rate number that comprises at least one weighting factor from described average every day quantity ordered, described prediction quantity ordered and described historical quantity ordered.
  41. 41. method as claimed in claim 39 is characterized in that, the described production schedule also comprises the promise of the promise available resources of sharing with Related product can utilize the relevant renewable available volume of resources of series; Also comprise step: the promise of retrieving described product can be utilized the current available resource amount of series, if and the target date of described requirement is outside the described delivery time, can utilize the described promise available resources that described Related product is shared in the series from described promise, consume the step of the described demand of the described resources of production.
  42. 42. method as claimed in claim 39 is characterized in that, the described production schedule also is included in the described smoothing time left side boundary fate that required before the target date; And comprise step: the smoothing time left side boundary of retrieving described finished product; And if describedly required the target date outside the described delivery time, the consumption step of described demand that then limits the described resources of production would be to the left side boundary of described smoothing time.
  43. 43. method as claimed in claim 39 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; Also comprise step: the maximum target of retrieving the described finished goods inventory of described product, and the described finished product order and surpass the described finished goods inventory of described maximum target one of being scheduled from may surpass described maximum target when with described finished goods inventory addition consumes the described source demand of described production money.
  44. 44. method as claimed in claim 43 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise step: retrieve the minimum target of the described finished goods inventory of described product, and from surpass the described finished goods inventory of described minimum target, consume the described demand of the described resources of production.
  45. 45. one kind in the production schedule corresponding to the system of product customer order scheduling manufacturing resources demand, comprise the delivery time of producing described product, with at least one and the finished product order that is scheduled, finished goods inventory, promise available resources, a relevant renewable available volume of resources in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past, described system comprises during at least one elasticity outside the described delivery time:
    Be used to import the input equipment of the product customer order that shows resources of production demand;
    Be used to import the device of the target date of producing described customer order requirement;
    A database, it has stored the delivery time of the described product of production in the production schedule and has been be scheduled finished product order, finished goods inventory, promise available resources, one current available resource amount in finished product order, unallocated customer order, market order, high resiliency resource and the low elasticity resource in the past at least;
    Whether the target date that is used for determining described requirement is in the described delivery time, equals described delivery time, which the device outside the described delivery time;
    About when described product and described Related product are indistinction, the relevant renewable available volume of resources of general finished product series of the finished product order of sharing with Related product that is scheduled;
    When the target date of described requirement is in the described delivery time and equals in the described delivery time one, be used for from the described finished product order that is scheduled, with described general finished product series in one the described available volume of resources of described the Related product described finished product order that is scheduled, described finished goods inventory, the described order of finished product in the past, described unallocated customer order and the described market order shared, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production;
    When the target date of described requirement is outside the described delivery time, be used for from the described finished product order that is scheduled, with described general finished product series in one the described available volume of resources of described the Related product described finished product order that is scheduled, described finished goods inventory, described promise available resources, the described order of finished product in the past, described unallocated customer order, described market order and the described high resiliency resource shared, consume the described demand of the described resources of production, up to the device of the described demand that is dispatched to the described resources of production; With
    In the described production schedule that therefrom consumes described demand and described general finished product series, upgrade the device of each described available volume of resources.
  46. 46. system as claimed in claim 45 is characterized in that, the described production schedule also comprises average every day of quantity ordered, prediction quantity ordered and historical quantity ordered; And described system also comprises in described production schedule retrieval at average every day of described delivery time quantity ordered, prediction quantity ordered during during the described elasticity and the device of historical quantity ordered, with based on compound every day of the rate number that comprises one weighting factor from described average every day quantity ordered, described prediction quantity ordered and described historical quantity ordered at least, determine the described high resiliency resource during during the described elasticity and the device of described low elasticity resource.
  47. 47. system as claimed in claim 45 is characterized in that, the described production schedule also comprises the promise of the promise available resources of sharing with Related product can utilize the relevant renewable available volume of resources of series; Described system also comprises the device that the promise that is used to retrieve described product can be utilized the current available resource amount of series, work as the target date of described requirement outside the described delivery time with being used for, can utilize the described promise available resources that described Related product is shared in the series from described promise, consume the device of the described demand of the described resources of production.
  48. 48. system as claimed in claim 45 is characterized in that, the described production schedule also is included in the described smoothing time left side boundary fate that required before the target date; And described system also comprises the device of the smoothing time left side boundary that is used to retrieve described finished product; Ought describedly require the target date outside the described delivery time with being used for, the consumption step of the described demand of the described resources of production is limited to the device of described smoothing time left side boundary.
  49. 49. system as claimed in claim 45 is characterized in that, the described production schedule also comprises the maximum target of described finished goods inventory; Described system also comprises the device of the maximum target of the described finished goods inventory that is used to retrieve described product, the described finished product order and surpassing among the described finished goods inventory of described maximum target one of being scheduled with surpassing described maximum target from described finished goods inventory addition the time consumes the device of the described demand of the described resources of production.
  50. 50. system as claimed in claim 49 is characterized in that, the described production schedule also comprises the minimum target of described finished goods inventory; Also comprise step: retrieve the minimum target of the described finished goods inventory of described product, and from surpass the described finished goods inventory of described minimum target, consume the described demand of the described resources of production.
CN00808266A 1999-04-02 2000-03-30 System and method of scheduling manufacturing resources Pending CN1354863A (en)

Applications Claiming Priority (8)

Application Number Priority Date Filing Date Title
US09/285,314 1999-04-02
US09/285,288 US6397118B1 (en) 1999-04-02 1999-04-02 Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US09/285,314 US6393332B1 (en) 1999-04-02 1999-04-02 Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US09/285,289 US6415195B1 (en) 1999-04-02 1999-04-02 Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US09/285,286 US6415194B1 (en) 1999-04-02 1999-04-02 Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US09/285,289 1999-04-02
US09/285,286 1999-04-02
US09/285,288 1999-04-02

Publications (1)

Publication Number Publication Date
CN1354863A true CN1354863A (en) 2002-06-19

Family

ID=27501390

Family Applications (1)

Application Number Title Priority Date Filing Date
CN00808266A Pending CN1354863A (en) 1999-04-02 2000-03-30 System and method of scheduling manufacturing resources

Country Status (8)

Country Link
EP (1) EP1192578A4 (en)
JP (1) JP2002541564A (en)
CN (1) CN1354863A (en)
AU (1) AU769097B2 (en)
CA (1) CA2368929A1 (en)
MX (1) MXPA01009958A (en)
TW (1) TW548570B (en)
WO (1) WO2000060523A1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100386702C (en) * 2005-06-10 2008-05-07 同济大学 Dynamic scheduling method based on pheromone for semiconductor production line
CN104346654A (en) * 2013-07-26 2015-02-11 三星Sds株式会社 Demand forecast segmentation method, apparatus and method for adjusting demand forecast
CN105243442A (en) * 2015-09-29 2016-01-13 武汉宝钢华中贸易有限公司 Inventory optimization management information model based on capacity supply chain
CN105550835A (en) * 2015-11-03 2016-05-04 武汉宝钢华中贸易有限公司 Product processing and delivery automatic management system model based on internet plus technology
CN105550836A (en) * 2015-11-03 2016-05-04 武汉宝钢华中贸易有限公司 Automatic production scheduling optimization management information model based on big data analysis and processing technology
CN105631543A (en) * 2015-12-23 2016-06-01 武汉宝钢华中贸易有限公司 Automatic volume matching management information model based on customer data analysis and processing technology
CN107169660A (en) * 2017-05-18 2017-09-15 株洲汇隆实业发展有限公司 A kind of balanced production method of planning of extending type
CN108604092A (en) * 2016-02-05 2018-09-28 三菱电机株式会社 Load human-hour estimating device, load human-hour estimating method and program
CN108604325A (en) * 2016-02-12 2018-09-28 本田技研工业株式会社 Investment of production equipment plans auxiliary system and commodity production system
CN110363567A (en) * 2019-05-31 2019-10-22 浙江口碑网络技术有限公司 The determination method, device and equipment of food product production information
CN112926909A (en) * 2019-12-05 2021-06-08 株式会社日立大厦系统 Demand amount planning system and demand amount planning method

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7225040B2 (en) 2001-11-14 2007-05-29 Exxon Mobil Oil Corporation Method and system for reducing lead-time in the packaging industry
CN1287243C (en) * 2000-12-05 2006-11-29 埃克森美孚石油公司 A method and system for reducing leadtime in the packaging industry
JP4648013B2 (en) * 2005-01-20 2011-03-09 花王株式会社 Production scheduling system
CN112766857B (en) * 2021-01-25 2022-07-12 海尔数字科技(青岛)有限公司 Intelligent warehouse management platform, system and method

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4807108B1 (en) * 1987-08-10 1995-03-28 Bell Telephone Labor Inc Product realization method
US5233533A (en) * 1989-12-19 1993-08-03 Symmetrix, Inc. Scheduling method and apparatus
US5369570A (en) * 1991-11-14 1994-11-29 Parad; Harvey A. Method and system for continuous integrated resource management
US5440480A (en) * 1992-05-15 1995-08-08 Jit Institute Of Technology, Inc. Method for determining flexible demand in a manufacturing process
US5596502A (en) * 1994-11-14 1997-01-21 Sunoptech, Ltd. Computer system including means for decision support scheduling
KR970066969A (en) * 1996-03-19 1997-10-13 모리시다 요이치 Manufacturing plan drafting method and manufacturing plan drafting device
US5819232A (en) * 1996-03-22 1998-10-06 E. I. Du Pont De Nemours And Company Method and apparatus for inventory control of a manufacturing or distribution process
JPH09282374A (en) * 1996-04-16 1997-10-31 Matsushita Electric Ind Co Ltd Mounting factory management support system
US5983195A (en) * 1997-06-06 1999-11-09 Electronic Data Systems Corporation Method and system for scheduling product orders in a manufacturing facility

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100386702C (en) * 2005-06-10 2008-05-07 同济大学 Dynamic scheduling method based on pheromone for semiconductor production line
CN104346654A (en) * 2013-07-26 2015-02-11 三星Sds株式会社 Demand forecast segmentation method, apparatus and method for adjusting demand forecast
CN104346654B (en) * 2013-07-26 2018-06-01 三星Sds株式会社 Requirement forecasting amount thinning method, requirement forecasting quantity regulating device and method
CN105243442A (en) * 2015-09-29 2016-01-13 武汉宝钢华中贸易有限公司 Inventory optimization management information model based on capacity supply chain
CN105550835A (en) * 2015-11-03 2016-05-04 武汉宝钢华中贸易有限公司 Product processing and delivery automatic management system model based on internet plus technology
CN105550836A (en) * 2015-11-03 2016-05-04 武汉宝钢华中贸易有限公司 Automatic production scheduling optimization management information model based on big data analysis and processing technology
CN105631543A (en) * 2015-12-23 2016-06-01 武汉宝钢华中贸易有限公司 Automatic volume matching management information model based on customer data analysis and processing technology
CN108604092A (en) * 2016-02-05 2018-09-28 三菱电机株式会社 Load human-hour estimating device, load human-hour estimating method and program
CN108604325A (en) * 2016-02-12 2018-09-28 本田技研工业株式会社 Investment of production equipment plans auxiliary system and commodity production system
CN107169660A (en) * 2017-05-18 2017-09-15 株洲汇隆实业发展有限公司 A kind of balanced production method of planning of extending type
CN110363567A (en) * 2019-05-31 2019-10-22 浙江口碑网络技术有限公司 The determination method, device and equipment of food product production information
CN110363567B (en) * 2019-05-31 2022-04-15 浙江口碑网络技术有限公司 Method, device and equipment for determining food production information
CN112926909A (en) * 2019-12-05 2021-06-08 株式会社日立大厦系统 Demand amount planning system and demand amount planning method

Also Published As

Publication number Publication date
CA2368929A1 (en) 2000-10-12
AU769097B2 (en) 2004-01-15
MXPA01009958A (en) 2002-07-30
AU4183800A (en) 2000-10-23
EP1192578A4 (en) 2005-08-17
WO2000060523A1 (en) 2000-10-12
EP1192578A1 (en) 2002-04-03
TW548570B (en) 2003-08-21
JP2002541564A (en) 2002-12-03

Similar Documents

Publication Publication Date Title
US6415195B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US6393332B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
CN1354863A (en) System and method of scheduling manufacturing resources
Manavizadeh et al. A Simulated Annealing algorithm for a mixed model assembly U-line balancing type-I problem considering human efficiency and Just-In-Time approach
US6560501B1 (en) System and method for collaborative batch aggregation and scheduling
US6463345B1 (en) Regenerative available to promise
De et al. A multi-periods production–inventory model with capacity constraints for multi-manufacturers–A global optimality in intuitionistic fuzzy environment
Singh et al. Meta-hierarchical-heuristic-mathematical-model of loading problems in flexible manufacturing system for development of an intelligent approach
CN115136164A (en) Computer-implemented method for production planning and/or control of a production system and production planning and/or production control system with production optimization
US6415194B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
Leong et al. Improved hierarchical production planning
CN1629863A (en) System and method for pull-in order planning and control
US6397118B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US20060009989A1 (en) Method, apparatus, data structure and system for scheduling work consistent with an entity's strategic objectives
Paolucci et al. An Agent-based system for sales and operations planning in manufacturing supply chains
CN115151925A (en) Computer-implemented method for production planning and/or control of a production system and production planning and/or control system
Lee et al. Implementing distribution requirement planning and scheduling system for lens manufacturing company
Mula et al. Fuzzy material requirement planning
Prakash et al. Modelling manufacturing system effectiveness: an integration of analytical hierarchy process and linear programming
US20220358605A1 (en) System and method for manufacturing a product in a distributed environment
Zanella et al. Sustainable production planning optimization using integer programming
Ryszard et al. Optimization of the Medium-Term Production Planning in the Company-Case Study
Riezebos Design of
Bhattacharya The Fundamentals of Resource Optimization in Construction Projects
Kovács A novel approach to aggregate scheduling in project-oriented manufacturing

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication