CN1331394A - Method for structure duct in ground - Google Patents

Method for structure duct in ground Download PDF

Info

Publication number
CN1331394A
CN1331394A CN00137114A CN00137114A CN1331394A CN 1331394 A CN1331394 A CN 1331394A CN 00137114 A CN00137114 A CN 00137114A CN 00137114 A CN00137114 A CN 00137114A CN 1331394 A CN1331394 A CN 1331394A
Authority
CN
China
Prior art keywords
vertical shaft
jack
last
pipeline
shield machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN00137114A
Other languages
Chinese (zh)
Other versions
CN1174179C (en
Inventor
徐明宇
朴正权
姜王圭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KT Corp
Original Assignee
KT Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KT Corp filed Critical KT Corp
Publication of CN1331394A publication Critical patent/CN1331394A/en
Application granted granted Critical
Publication of CN1174179C publication Critical patent/CN1174179C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/046Directional drilling horizontal drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/125Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/20Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground

Abstract

An semi-shield method comprises a process in which an underground pipe line excavator advances so as to form a pipe line between a start device and an arrival device, a process in which a pipe advances through the pipe line while inserting many intermediate jacks between pipes, a process in which many intermediate devices are formed to recover the buried intermediate jacks, and a process in which many manholes are provided in the start device, the arrival device, and the intermediate devices. The number of intermediate devices is equal to or larger than the number of intermediate jacks positioned between the start device and the arrival device. Construction cost and construction time can be reduced by providing the manholes without carrying out the ground stabilizing construction work by each intermediate device.

Description

Be used for being configured in the method for the pipeline in soil
The present invention relates to be used to be configured in half-shield method of the pipeline in soil; Specifically, the half-shield method that relates to a kind of cost saving and time.
In general, pipeline is among excacation is built into the soil later on, to imbed the communication line such as cable.At the point of branching of communication line, a manhole is installed is branched into a lot of communication line is connected on another or with communication line.
The construction of carrying out underground utility on densely populated zone or busy street can cause traffic congestion or bring inconvenience to the public.In addition, because built different facilities, be difficult in and carry out construction work under the situation of not destroying these facilities underground.
Recently, half-shield method is applied to reduce excacation.In half-shield method, a main jack, i.e. fluid power jack and a reaction force dunnage, i.e. concrete wall are placed and are configured in the first vertical shaft, so that with jack a shield machine and pipeline are pushed in the soil.In the time of among a pipeline is advanced to the soil fully, follows first pipeline another pipeline is advanced among the soil night.Repeat operation, among a plurality of pipelines are advanced to the soil one by one, arrive last vertical shaft, so structure is finished a under ground piping between first vertical shaft and last vertical shaft up to shield machine.After this, last vertical shaft is used as a new first vertical shaft for use in constructing continuous pipeline or manhole being configured on first vertical shaft and the last vertical shaft.Depression in the structure of this half-shield method, occurs, must on first vertical shaft and last vertical shaft, apply on-the-spot the preparation, so increased expenditure of construction and time in order to prevent.
In general, in order to be increased in the distance between first vertical shaft and the tail vertical shaft, jack in the middle of need between pipeline, adding., the diameter of pipeline greater than 2 meters situation under, the use of middle jack can be restricted, because it reclaims difficulty.
Fig. 1 a is the cross section view of explanation tradition half-shield method to Fig. 1 g.
As shown in Figure 1, half-shield method begins to carry out excavation in a pair of precalculated position to form first vertical shaft 1 and last vertical shaft 2, wherein, corresponding to the position of two adjacent manholes that are mounted, determines the position of first vertical shaft 1 and last vertical shaft 2.
After this,, first vertical shaft 1 and last vertical shaft 2 are applied on-the-spot preparation 8 for the depression that prevents to produce owing to the factors such as reaction force that cause by jack, and the operation that basis half-shield method is carried out subsequently, shown in Fig. 1 b.
Then, fluid power jack 3 and shield machine 4 are installed in the first vertical shaft 1 and are positioned at feeding mechanism 5 machineries around the first vertical shaft 1 with one and are electrically connected, shown in Fig. 1 c.Control order and pressure at feeding mechanism 5 assist following fluid power jack 3 and shield machine 4 to carry out work.
After this, will have the shield machine 4 that inserts pipeline 6 by means of fluid power jack 3 and be advanced among the soil, arrive last vertical shaft 2 up to shield machine 4, shown in Fig. 1 d.
So fluid power jack 3 and shield machine 4 disassemble from first vertical shaft 1 and last vertical shaft 2, shown in Fig. 1 e.
After this, by with last vertical shaft 2 as new first vertical shaft 1, repeat Fig. 1 a and go up the step of description, shown in Fig. 1 f to Fig. 1 e.
At last, after in all vertical shafts 1,2 manhole 7 being installed all, with 1,2 backfill of all vertical shafts, shown in Fig. 1 g.
In half above-mentioned-shield method, there are many problems.At first, the position of vertical shaft is determined in the mounting point of needs consideration manhole.That is to say that first vertical shaft and last vertical shaft should be configured in the place that all will install manhole.Therefore, in the urban area that a plurality of manholes need be installed in short distance, the efficient of above-mentioned half-shield method is lower, because need carry out the scene preparation and transport equipment at first vertical shaft and last vertical shaft, for example jack, shield machine and supply equipment are so increased expenditure of construction and time.
In addition, if the size of pipeline is less, for example diameter is less than 2 meters, and the ultimate range between first vertical shaft and last vertical shaft is restricted, and for example 60 meters, reclaims because middle jack can not pass pipeline.
Therefore, the purpose of this invention is to provide a kind of can cost saving and the half-shield method of time.
According to the present invention, a kind of half-shield method is provided, may further comprise the steps: dig the soil to form first vertical shaft and last vertical shaft at a pair of preposition; First vertical shaft and last vertical shaft are applied on-the-spot the preparation; A main jack and shield machine are installed in the first vertical shaft; To have the shield machine that inserts pipeline and middle jack and be advanced among the soil, and arrive last vertical shaft up to shield machine, jack was set on the predetermined neutral position in the middle of the quilt centre was inserted between the pipeline; Main jack, shield machine and middle jack are disassembled from first vertical shaft, last vertical shaft and middle vertical shaft respectively; A plurality of manholes are installed on first vertical shaft, last vertical shaft and the middle vertical shaft; First vertical shaft, last vertical shaft and middle vertical shaft are carried out backfill.
Description of preferred embodiments in conjunction with the drawings, above and other purpose of the present invention and feature will become more obvious, wherein:
Fig. 1 a is the cross section view of explanation tradition half-shield method to Fig. 1 g;
Fig. 2 a is the cross section view of explanation half-shield method of the present invention to Fig. 2 f.
Fig. 2 a is half-shield method of the explanation according to the present invention to Fig. 2 f.
Shown in Fig. 2 a, it is that excavation in a pair of precalculated position is to form first vertical shaft 101 and last vertical shaft 102 that half-shield method begins.First vertical shaft 101 and last vertical shaft 102 will overlap with a manhole 107a and a remote manhole 107e that will install respectively, shown in Fig. 2 f, wherein be provided with a plurality of manhole 107b, 107c, 107d between manhole 107a and manhole 107e.
Get back to Fig. 2 a, prepare 108 for first vertical shaft 101 and last vertical shaft 102 site of deployment, with prevent they with partly-the shield method duration of work is owing to different factors produce depression.
Then, fluid power master jack 103 and shield machine 104 are installed in the first vertical shaft 101 and are positioned at feeding mechanism 105 machineries around the first vertical shaft 101 with one and are electrically connected, shown in Fig. 2 b.Control order and pressure at feeding mechanism 105 are down auxiliary, and fluid power master jack 103 and shield machine 104 carry out work.
After this, will have the shield machine 104 that inserts pipeline 106 and middle jack 111 and be advanced among the soil, arrive last vertical shaft 102 up to shield machine 104, shown in Fig. 2 c.Middle jack 111 is inserted between the pipeline 106 and with feeding mechanism 105 machineries be electrically connected medially, so by means of fluid power master jack 103 and middle jack 111 pipeline is advanced among the soil.It should be noted that by means of jack 111 in the middle of using, can be increased in the distance between first vertical shaft 101 and the last vertical shaft 102.
So,, expose all underground middle jack 111 whereby, shown in Fig. 2 d by middle vertical shaft 110a, 110b, the 110c of digging ground in preposition formation some.The position of middle vertical shaft 110a, 110b, 110c be determined in case comprise underground in the middle of jack 111 and manhole 107b, 107c between first vertical shaft 101 and last vertical shaft 102,107d (shown in Fig. 2 f), wherein in the middle of the quantity of vertical shaft 110a, 110b, 110c be no less than the quantity of the middle jack 111 between first vertical shaft 101 and last vertical shaft 102.Therefore, jack 111 can be recovered and make manhole 107a, 107b, 107c to be installed between first vertical shaft 101 and the last vertical shaft 102 in the middle of the formation of middle vertical shaft 110a, 110b, 110c made.
So fluid power master jack 103, shield machine 104 and middle jack 111 disassemble from first vertical shaft 101, last vertical shaft 102 and middle vertical shaft 110a, 110c respectively, shown in Fig. 2 e.
After this, a plurality of manhole 107a, 107b, 107c and 107d are installed on first vertical shaft 101, last vertical shaft 102 and middle vertical shaft 110a, 110b, the 110c, then with first vertical shaft 101, last vertical shaft 102 and middle vertical shaft 110a, 110b, 110c, 110d backfill, shown in Fig. 2 f.
Compare with aforementioned disclosed half-shield method, half-shield method of the present invention is included in a plurality of middle vertical shaft between first vertical shaft and the last vertical shaft, wherein can manhole be installed not needing vertical shaft in the middle of each applied under the on-the-spot situation about preparing, so reduced the time of the expense of building.
In addition, middle jack can be applied under the situation of pipeline of reduced size, and for example diameter is less than 2 meters pipeline, because they can be recovered by middle vertical shaft, so increased distance between first vertical shaft and last vertical shaft.
Top the present invention is described certain embodiments, and clearly, those skilled in the art can make changes and improvements not breaking away under spirit of the present invention and protection scope of the present invention.

Claims (5)

1. one and half-shield method may further comprise the steps:
Dig the soil to form first vertical shaft and last vertical shaft at a pair of preposition;
First vertical shaft and last vertical shaft are applied on-the-spot the preparation;
A main jack and shield machine are installed in the first vertical shaft;
To have the shield machine that inserts pipeline and middle jack and be advanced among the soil, and arrive last vertical shaft up to shield machine, jack was set on the predetermined neutral position in the middle of the quilt centre was inserted between the pipeline;
Main jack, shield machine and middle jack are disassembled from first vertical shaft, last vertical shaft and middle vertical shaft respectively;
A plurality of manholes are installed on first vertical shaft, last vertical shaft and the middle vertical shaft;
First vertical shaft, last vertical shaft and middle vertical shaft are carried out backfill.
2. one and half-shield method may further comprise the steps:
Advance a shield machine to be passed in soil between first vertical shaft and the last vertical shaft to form a hole;
Advance pipeline to pass this hole, wherein a plurality of middle jack of middle insertion between pipeline;
Form a plurality of middle vertical shafts to be recovered in underground middle jack; And
At first vertical shaft, last vertical shaft and middle vertical shaft a plurality of manholes are installed.
3. method according to claim 2 is characterized in that: comprise first vertical shaft, last vertical shaft are applied the on-the-spot step of preparing.
4. method according to claim 2 is characterized in that: by main jack and middle jack pipeline is advanced and pass this hole.
5. method according to claim 2 is characterized in that: the quantity of a plurality of middle jack continuously is no less than the quantity of the middle jack between first vertical shaft and last vertical shaft.
CNB001371142A 2000-06-27 2000-12-28 Method for structure duct in ground Expired - Fee Related CN1174179C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020000035628A KR100628432B1 (en) 2000-06-27 2000-06-27 Non-open cut pipe installation method
KR35628/2000 2000-06-27

Publications (2)

Publication Number Publication Date
CN1331394A true CN1331394A (en) 2002-01-16
CN1174179C CN1174179C (en) 2004-11-03

Family

ID=19674158

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB001371142A Expired - Fee Related CN1174179C (en) 2000-06-27 2000-12-28 Method for structure duct in ground

Country Status (5)

Country Link
JP (1) JP2002013388A (en)
KR (1) KR100628432B1 (en)
CN (1) CN1174179C (en)
DE (1) DE10063049C2 (en)
HK (1) HK1043821B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100400753C (en) * 2002-07-16 2008-07-09 早川橡胶株式会社 Man hole structure, flexible water joint for man hole structure and construction method for man hole structure
CN101463924B (en) * 2007-12-20 2010-09-29 上海市基础工程有限公司 Heavy caliber pipe-jacking butt joint technique
CN101852311A (en) * 2009-04-03 2010-10-06 中冶成工上海五冶建设有限公司 Pipe-jacking installation method of bypass pipeline
CN102943489A (en) * 2012-11-30 2013-02-27 上海市机械施工有限公司 System for tube push bench to go out of starting well and unkenneling construction method of tube push bench
CN101749024B (en) * 2008-12-22 2013-05-29 上海广联建设发展有限公司 Pipe-pulling construction method of underground buried box culvert
CN101749028B (en) * 2008-12-16 2013-05-29 上海广联建设发展有限公司 Cross-pulling construction method for soft soil zone with high ground water level
CN104089089A (en) * 2014-07-14 2014-10-08 中国水利水电第十工程局有限公司 Pressure backfill type elastic buried pipe construction method
CN106869040A (en) * 2017-04-07 2017-06-20 安徽建筑大学 A kind of Huizhou City traditional settlement street lane water small stream landscape renovation mechanism arrangement
CN108729469A (en) * 2017-04-14 2018-11-02 植村技研工业株式会社 The construction method of underground structure
CN109056806A (en) * 2018-09-04 2018-12-21 深圳市深水水务咨询有限公司 A kind of construction method and its construction for underground type sewage plant

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100442690B1 (en) * 2000-11-10 2004-08-02 유근무 Tunnel Construction Method for using Wave Profile Type Steel Plate
KR100701885B1 (en) * 2006-01-18 2007-03-30 주식회사 엠 Non-open cut pipe installation method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0230889A (en) * 1988-07-19 1990-02-01 Kubota Ltd Mid-pushing of pipe for propulsive excavation
JPH0639876B2 (en) * 1988-08-10 1994-05-25 南野建設株式会社 Middle push propulsion structure
JPH02101293A (en) * 1988-10-08 1990-04-13 Fujita Corp Center push device for propelling underground conduit and construction method
KR970007379B1 (en) * 1991-12-30 1997-05-08 마고도 우에무라 Method and apparatus for open shield
JP2999056B2 (en) * 1992-02-20 2000-01-17 芦森工業株式会社 Water stop method in middle-press method
JP3366241B2 (en) * 1997-12-18 2003-01-14 株式会社扶桑技研 Underground pipe laying method and apparatus
DE19901497C1 (en) * 1999-01-11 2000-02-10 Gildemeister Tief-, Stahlbeton- U. Rohrleitungsbau Gmbh & Co. Kg Driving method for underground pipe line has the butting pipe sections fitted with jointing sleeves to provide flexibility for the line and with a final jointing process to link then pipe sections
KR100360560B1 (en) * 1999-05-03 2002-11-13 주식회사 동양굴착산업 Shield Tunneling Apparatus and Method

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100400753C (en) * 2002-07-16 2008-07-09 早川橡胶株式会社 Man hole structure, flexible water joint for man hole structure and construction method for man hole structure
CN101463924B (en) * 2007-12-20 2010-09-29 上海市基础工程有限公司 Heavy caliber pipe-jacking butt joint technique
CN101749028B (en) * 2008-12-16 2013-05-29 上海广联建设发展有限公司 Cross-pulling construction method for soft soil zone with high ground water level
CN101749024B (en) * 2008-12-22 2013-05-29 上海广联建设发展有限公司 Pipe-pulling construction method of underground buried box culvert
CN101852311A (en) * 2009-04-03 2010-10-06 中冶成工上海五冶建设有限公司 Pipe-jacking installation method of bypass pipeline
CN101852311B (en) * 2009-04-03 2013-05-15 五冶集团上海有限公司 Pipe-jacking installation method of bypass pipeline
CN102943489A (en) * 2012-11-30 2013-02-27 上海市机械施工有限公司 System for tube push bench to go out of starting well and unkenneling construction method of tube push bench
CN102943489B (en) * 2012-11-30 2015-02-04 上海市机械施工集团有限公司 System for tube push bench to go out of starting well and unkenneling construction method of tube push bench
CN104089089A (en) * 2014-07-14 2014-10-08 中国水利水电第十工程局有限公司 Pressure backfill type elastic buried pipe construction method
CN104089089B (en) * 2014-07-14 2016-03-23 中国水利水电第十工程局有限公司 Pressure backfill type elasticity pipe laying method of construction
CN106869040A (en) * 2017-04-07 2017-06-20 安徽建筑大学 A kind of Huizhou City traditional settlement street lane water small stream landscape renovation mechanism arrangement
CN106869040B (en) * 2017-04-07 2020-07-03 安徽建筑大学 Mechanism device for traditional convergence street lane river landscape reconstruction
CN108729469A (en) * 2017-04-14 2018-11-02 植村技研工业株式会社 The construction method of underground structure
CN108729469B (en) * 2017-04-14 2020-10-20 植村技研工业株式会社 Construction method of underground structure
CN109056806A (en) * 2018-09-04 2018-12-21 深圳市深水水务咨询有限公司 A kind of construction method and its construction for underground type sewage plant

Also Published As

Publication number Publication date
HK1043821B (en) 2005-06-24
DE10063049A1 (en) 2002-01-24
CN1174179C (en) 2004-11-03
HK1043821A1 (en) 2002-09-27
JP2002013388A (en) 2002-01-18
KR100628432B1 (en) 2006-09-27
DE10063049C2 (en) 2003-02-06
KR20020001221A (en) 2002-01-09

Similar Documents

Publication Publication Date Title
CN1174179C (en) Method for structure duct in ground
US5605419A (en) Underground duct banks
JP2842855B2 (en) Long-distance propulsion method and equipment in semi-shield method
CN110485468B (en) Permanent circular working well with water-rich stratum preset jacking pipe door opening and construction method thereof
CN111778994A (en) Pipe-jacking working well supporting device for municipal pipeline engineering and construction method
CN215253290U (en) Sewage drainage pipe for municipal works
CN110863512A (en) Prefabricated cable utility tunnel
CN214695953U (en) Domestic sewage drainage pipe that municipal works were used
CN110485465B (en) Circular working well with water-rich stratum with preset pipe jacking door opening and construction method of circular working well
CN211922702U (en) Prefabricated cable utility tunnel
JPH1136296A (en) Pc hollow pile and construction method for underground structure
CN114592892A (en) Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area
CN204098067U (en) Side's culvert formula underground pipe gallery
KR100654327B1 (en) Structure of hanger using pipe
CN113605466A (en) Safety monitoring and early warning method for side slope of deep foundation pit near lake
CN2558133Y (en) Combined man hole trough for communication and power line
JPH03270613A (en) Method for underground wiring of communication wire by using fluid transport pipe
CN2318263Y (en) Assembly combined sinking pipe
CN216894448U (en) Non-excavation of micro-aperture pipeline is pieced together pipe ripple steel welt supporting device
CN215721220U (en) Temporary protection structure suitable for excavation construction of current pipeline
CN218882260U (en) Ultra-deep soil covering ultra-large caliber ultra-long curve pipe jacking hole outlet water stop device
CN218182980U (en) Connection structure of town road is striden to electric circuit
CN219606226U (en) Temporary pipeline support for pipe jacking construction
CN1033529C (en) Method for laying well and pipe line directly on top pipe line
CN220487600U (en) Pipe jacking thick slurry injection device

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20041103

Termination date: 20151228

EXPY Termination of patent right or utility model