CN1227296A - Power switch device and controller for washing machine - Google Patents

Power switch device and controller for washing machine Download PDF

Info

Publication number
CN1227296A
CN1227296A CN98123088.1A CN98123088A CN1227296A CN 1227296 A CN1227296 A CN 1227296A CN 98123088 A CN98123088 A CN 98123088A CN 1227296 A CN1227296 A CN 1227296A
Authority
CN
China
Prior art keywords
power
switch
switch device
power supply
state
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN98123088.1A
Other languages
Chinese (zh)
Other versions
CN1109152C (en
Inventor
梅谷重雄
玉江贞之
木内光幸
麻田和彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Holdings Corp
Original Assignee
Matsushita Electric Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Electric Industrial Co Ltd filed Critical Matsushita Electric Industrial Co Ltd
Publication of CN1227296A publication Critical patent/CN1227296A/en
Application granted granted Critical
Publication of CN1109152C publication Critical patent/CN1109152C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • DTEXTILES; PAPER
    • D06TREATMENT OF TEXTILES OR THE LIKE; LAUNDERING; FLEXIBLE MATERIALS NOT OTHERWISE PROVIDED FOR
    • D06FLAUNDERING, DRYING, IRONING, PRESSING OR FOLDING TEXTILE ARTICLES
    • D06F34/00Details of control systems for washing machines, washer-dryers or laundry dryers
    • D06F34/10Power supply arrangements, e.g. stand-by circuits
    • DTEXTILES; PAPER
    • D06TREATMENT OF TEXTILES OR THE LIKE; LAUNDERING; FLEXIBLE MATERIALS NOT OTHERWISE PROVIDED FOR
    • D06FLAUNDERING, DRYING, IRONING, PRESSING OR FOLDING TEXTILE ARTICLES
    • D06F37/00Details specific to washing machines covered by groups D06F21/00 - D06F25/00
    • D06F37/42Safety arrangements, e.g. for stopping rotation of the receptacle upon opening of the casing door
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B40/00Technologies aiming at improving the efficiency of home appliances, e.g. induction cooking or efficient technologies for refrigerators, freezers or dish washers

Landscapes

  • Engineering & Computer Science (AREA)
  • Textile Engineering (AREA)
  • Control Of Washing Machine And Dryer (AREA)
  • Stand-By Power Supply Arrangements (AREA)
  • Detail Structures Of Washing Machines And Dryers (AREA)
  • Direct Current Feeding And Distribution (AREA)

Abstract

power source switching means for washer comprising a control means performing action during DC power supplying period. A control means 17 puts the power source switching means 13 in a closed state by electric power supplied from the DC power source 11 while turning on the power source closing switch 15, and puts the power source switching means 13 in an opening state when turning on a power source cutoff switch 16 to input cutoff the power source after starting operation.When the switch is open, that is, a load unoperated state,it enable input of the switch in a standby electric power nonexistent state without carrying an electric current to a DC power source in a power source cutoff state, so that shorten an operation stroke of a switch, to enbale input in the light touch, and to improve operability/waterproof performance.

Description

The power switch device of washing machine etc. and control device
The present invention relates to possess the power switch device and the control device of washing machine that the control device that moves is arranged etc. during providing electric power by dc source.
In the past, the formation that possesses the washing machine that this power switch device is arranged as shown in figure 14.Below, its formation is described.
As shown in the figure, load 1 is made of motor 2, water-supply valve 3, draining valve 4 etc., controls by the power switch device 6 that is made of amphicheirality's controllable silicon etc. with control device 5, and each program of corresponding washing, rinsing, dehydration is moved successively.Load is connected the AC power 8 of loading on 1 with power switch device 7 switches.Operation display device 9 is that the running of input washing, rinsing, dehydration etc. is set, the running beginning, stop etc. temporarily, and show the device of its content etc. in operating condition with when unusual, has switch 10, this switch 10 is the normal off open forms that are used to import the break-make of power supply, only becomes on-state during pressing.
Dc source 11 is connected on the AC power, provides power supply to control device 5.Condensate tank of dehumidifier 12 detects the water level in the double dehydration barrel (not shown) of laundry, and its output is input to control device 5, can feed water to the water level of regulation.
In the above-described configuration, if the action when carrying out the break-make of switch 10 of washing machine according to the process description of Figure 15, then under the state that connects AC power 8, dc source 11 is switched on all the time, control device 5 monitors the switch 10 that is arranged in the operation display device 9 all the time, if in step 141, press switch 10, then in step 142 according to present state judge the input of switch 10 be logical be disconnected.
Connecting under the situation of power supply, in step 143, showing the initial holding state of the setting of accepting running etc. by operation display device 9, in step 144, will load be set to closure state with power switch device 7 after, and move to next stroke.When in step 142 when disconnecting, judge in step 145 whether load 1 moves, under the situation of load 1 action, break load 1 in step 146, in step 147, establish T time delay.When load 1 when not moving, enter step 148 and will load and be set to off-state with power switch device 7, in step 149, extinguish the demonstration of operation display device 9, become the input wait of switch 10 once more.
But, in above-mentioned formation in the past, even do not make under the state of washing machine running, 1 the power supply of promptly loading is under the state that disconnects, owing to need make control device 5 actions in order to make switch 10 be in the input wait state, so on dc source 11, connecting AC power 8 always.Therefore consume often and prepare electric power,, wish to propose to reduce the countermeasure of this consumption from saving the viewpoint of the energy.
In addition, because dc source 11 always is in conducting state, so constitute the component heating of dc source 11, do not use washing machine, the problem of operation part heating though exist.
Have again, the washing machine in past also has such example, promptly be arranged to the formation of power switch device and power switch dual-purpose, by use to keep built-in power supply disconnect the such power switch of on/off state of the solenoidal hand of usefulness, in the on/off of under the situation of dc source energising, not carrying out power supply, only make the action of power switch disconnection by control device, but, in this formation, the complex structure of power switch, water proofing property is also poor, and the operational stroke during owing to on/off increases, and therefore has the problem of operability difference.
The present invention proposes in order to solve above-mentioned problem in the past, and its 1st purpose is to provide a kind of switch control run short, can import with simple touch manner, and can improve the power switch device of the washing machine etc. of operability and water proofing property.
In addition, when stating the 1st purpose in realization, even its 2nd purpose is to provide the control device of the washing machine that a kind of generation instantaneous power failure also can return to the state before instantaneous power failure takes place etc.
The power switch device of washing machine of the present invention etc., in order to realize above-mentioned the 1st purpose, it constitutes by the power switch device switch and is connected AC power on the dc source, the power connection switch in parallel that to carry out the power connection input is connected on the power switch device, so constitute control device, make and during the power connection switch is switched on, be set to on-state by the electric power power switch device that provides by dc source, be switched on if carry out the power supply cut-off switch of power supply disconnection input after the action beginning, then power switch device is set to off-state.
Thus, at the state of power supply disconnection, promptly when the state that load does not move, can not switch on, and do not having the input of carrying out switch under the state of preparing electric power, make the switching manipulation stroke short to dc source, can import with simple touch manner, can improve operability and water proofing property.
In addition, the control device of washing machine of the present invention etc., in order to realize above-mentioned the 2nd purpose, it constitutes, possesses above-mentioned power switch device, detect the instantaneous power failure checkout gear of the generation of instantaneous power failure, the power supply holding device that constitutes by electrolytic capacitor, the power supply that is made of timer is drive unit again, so constitute control device, detect instantaneous power failure then make power supply drive unit action and power switch device are set to off-state again if make, if power supply drive unit again detects and passed through the stipulated time, then power switch device is set to on-state.
Thus, even taking place, instantaneous power failure also can return to the preceding state of instantaneous power failure generation.
The formation of the invention of technical scheme 1 of the present invention is, possesses dc source, the control device that during providing electric power, moves by above-mentioned dc source, switch is connected the power switch device of the AC power on the above-mentioned dc source, be connected in parallel with above-mentioned power switch device and carry out the power connection switch of power connection input, carry out power supply and disconnect the power supply cut-off switch of importing, so constitute above-mentioned control device, make above-mentioned power connection switch be switched on during use the above-mentioned power switch device of the electric power that provides by dc source to be set to closure state, if the above-mentioned power supply cut-off switch in action beginning back is switched on, then above-mentioned power switch device is set to off-state, like this, in power-off state, when promptly loading the state that does not move, power switch device is set to off-state, can be to dc source energising, prepare electric power and be to carry out under zero the state action of switch connection.
The invention of technical scheme 2, be in the invention of technique scheme 1, to be connected in series by anti-locking apparatus of the dash current that resistance constitutes and the power connection switch that carries out the power connection input, the dash current that flows through when the power connection switch is switched on can be suppressed at, thereby the damage of component can be prevented.
The invention of technical scheme 3, be in the invention of technique scheme 1, possesses the load power switching device that switch is connected the AC power on the load, constituting of power switch device is connected switch AC power supply on the dc source, can in power switch device, use the element of low capacity thus, thereby the action when power supply is inserted is more stable.
The invention of technical scheme 4, the power switch device that possesses technical scheme 1, detect the instantaneous power failure checkout gear that instantaneous power failure takes place, the power supply holding device that constitutes by electrolytic capacitor, the power supply that is made of timer is drive unit again, so constitute control device, detect instantaneous power failure then make the drive unit action and power switch device is arranged to off-state again of above-mentioned power supply if make, when above-mentioned power supply again drive unit detect when having passed through the stipulated time, above-mentioned power switch device is set to on-state, like this, even taking place, instantaneous power failure also can return to the preceding state of instantaneous power failure generation.
Fig. 1 is the block diagram of the power switch device of washing machine of embodiments of the invention 1 etc.
Fig. 2 is the circuit diagram of the power switch device of same washing machine etc.
Fig. 3 is the flow chart of the action when showing the power connection input of power switch device of same washing machine etc.
Fig. 4 is the flow chart of the power supply of showing the power switch device of same washing machine etc. the action when disconnecting input.
Fig. 5 is the block diagram of the power switch device of washing machine of embodiments of the invention 2 etc.
Fig. 6 is the circuit diagram of the power switch device of same washing machine etc.
Fig. 7 is the block diagram of the power switch device of washing machine of embodiments of the invention 3 etc.
Fig. 8 is the circuit diagram of the power switch device of same washing machine etc.
Fig. 9 is the flow chart of the action when showing the power connection input of power switch device of same washing machine etc.
Figure 10 shows the flow chart of the action the when power supply of the power switch device of same washing machine etc. disconnects input.
Figure 11 is the block diagram of the power switch device of washing machine of embodiments of the invention 4 etc.
Figure 12 is the circuit diagram of the power switch device of same washing machine etc.
Figure 13 is the flow chart of the instantaneous power failure of showing the control device of the same washing machine action when taking place.
Figure 14 is the block diagram that possesses the washing machine of power switch device in the past.
Figure 15 is the flow chart of the action when showing the power supply on/off input of same supply unit.
Below, with reference to the description of drawings embodiments of the invention.Be endowed prosign and omit explanation with routine same structure in the past.
(embodiment 1)
As shown in Figure 1, power switch device 13, the AC power 8 that switch is connected with load 1 and dc source 11.The state of the on/off of power supply status display unit 14 display power supplies.Power connection switch 15 and power supply cut-off switch 16 are the switches that switch on and off input that carry out power supply respectively, are the normal off open forms, only become on-state during pressing switch.During power connection switch 15 was pressed, AC power 8 and dc source 11 were connected, and dc source 11 is to control device 17 power supplies.
Control device 17, by the power conversion device 6 that constitutes by bidirectional triode thyristor etc., the load 1 that control is made of motor 2, water-supply valve 3, draining valve 4 etc. is washing one by one, in each order of rinsing, dehydration, power switch device 13 is being set to on-state and keeps this state.In addition, if press power supply cut-off switch 16 in action beginning back then power switch device 13 be set to off-state.
Concrete circuit constitutes as shown in Figure 2, and dc source 11 is made of transformer 18, bridge diode 19, voltage-stabilized power supply circuit 20, provides dc source to control device 17 at power switch device 13 during for on-state.Power connection switch 15 is connected in parallel on the power switch device 13, even make when power switch device 13 is in off-state, also provides dc source to control device 17 when pressing power connection switch 15.
Control device 17, have lead-out terminal OUT and input terminal IN, wherein lead-out terminal OUT connects, disconnects by make transistor Q1 via resistance R 1, and the coil 13a of field power supply switching device 13 comes Switching Power Supply switching device 13, and input terminal IN accepts the input of power supply cut-off switch 16.
In the above-described configuration, carry out action under the connection situation of switch according to the process description of Fig. 3.If in step 51, press power connection switch 15, then in step 52, provide power supply to control device 17 from dc source 11, begin action.In step 53, lead-out terminal OUT is set to high level state, makes transistor Q1 conducting.Then, in step 54, by 13 coil 13a of field power supply switching device, power switch device 13 becomes on-state and keeps this state.In step 55, connect the demonstration of power supply status display unit 14, be set to the state of power connection, and enter the next line journey.
Then, carry out action under the disconnection of switch according to the process description of Fig. 4.If input terminal IN accepts the power supply disconnection indication of power supply cut-off switch device 16 in step 61, then control device 17 judges in step 62 whether load 1 moves, under the situation of load 1 action, the action of load 1 is stopped, T ' time delay is set in step 64, inserts step 65 then.
Under the situation that load 1 does not move, enter step 56, turn off power supply status display unit 14, lead-out terminal OUT is set to low level state in step 66, by transistor Q1 being ended cut off energising to power switch device 13, power switch device 13 is set to off-state, cut-out is to the energising of dc source 11, the action that end switch is cut off.
(embodiment 2)
As Fig. 5 and shown in Figure 6, resistance 21 and power connection switch 15 are connected in series, thereby prevent the dash current that when power connection switch 15 is switched on, flows through.Other formation is identical with the foregoing description 1.
In the above-described configuration, for the action under the connection of carrying out switch, the disconnection, carry out with step 51 from Fig. 3 of the foregoing description 1 to the step 53, and a series of action identical action of the step 61 from Fig. 4 to the step 66.
Thereby, the dash current that flows through when power connection switch 15 is switched on can be suppressed at, thereby the damage of component can be prevented.
(embodiment 3)
As shown in Figure 7, load is controlled by the output of control device 23 with power switch device 22, and switch is connected the AC power 8 on the load 1.The switch that constitutes of power switch device 24 is connected AC power 8 on the dc source 11.Other formation is identical with the foregoing description 1.
Concrete circuit constitutes as shown in Figure 8, and dc source 11 provides dc source to control device 23 when power switch device 24 is in the state of connection.Power connection switch 15 is connected in parallel on the power switch device 24, even when power switch device 24 is in off-state, also provides dc source to control device 23 if press power connection switch 15.
Control device 23 possesses: input terminal IN, the input that its power supply of accepting power supply cut-off switch 16 disconnects; Lead-out terminal OUT1, it is used for by make transistor Q1 connect, disconnect via resistance R 1, and the coil 24a of field power supply switching device 24 comes Switching Power Supply switching device 24; Lead-out terminal OUT2, it is used for making transistor Q2 connect, disconnect via resistance R 3, switch load power switch device 22.
In the above-described configuration, carry out action under the connection situation of switch according to the process description of Fig. 9.If in step 71, press power connection switch 15, then in step 72, provide power supply to control device 23 from dc source 11, begin action.In step 73, lead-out terminal OUT1 is set to high level state, makes transistor Q1 conducting.Then, by the coil 24a of field power supply switching device 24, power switch device 24 becomes on-state and keeps this state in step 74.In step 75, connect the demonstration of power supply status display unit 14, control device 23 lead-out terminal OUT2 are set to high level state in step 77, are set to on-state and enter the next line journey with power switch device 22 by transistor Q2 conducting will be loaded.
Then, carry out action under the situation of disconnection of switch with reference to the process description of Figure 10.Disconnect indication if in step 81, receive the power supply of power supply cut-off switch device 16, then control device 23 judges in step 82 whether load 1 moves, under load 1 situation of moving, the action of load 1 is stopped, T ' time delay is set in step 84, and enters step 85.
Under the situation that load 1 does not move, enter step 85, lead-out terminal OUT2 is set to low level state, by making transistor Q2 be set to off-state with power switch device 22 by loading, in step 86, turn off power supply status display unit 14, lead-out terminal OUT1 is set to low level state in step 87, by making transistor Q1, cut off power supply, and enter the next line journey to dc source 11 by power switch device 24 is set to off-state.
Thereby, power switch device 24, because only switch is to the power supply of dc source 11, so can use the element of low capacity in power switch device 24, the action when power supply is inserted is more stable.
As shown in figure 11, instantaneous power failure checkout gear 25 is the devices of generation that detect the instantaneous power failure of AC power 8, by reducing the voltage of AC power, the synchronous signal of supervision and AC power detects the generation of instantaneous power failure, meanwhile the generation of exporting instantaneous power failures to control device 26.Voltage is drive unit 27 again, and being instrumentation begins to the device of the stipulated time of recovering from instantaneous power failure, if from the generation of control device 26 input instantaneous power failures, then the instrumentation stipulated time, reached the stipulated time to control device 26 outputs.Voltage retaining device 28 is when instantaneous power failure begins to recover, and is used for the power supply of driving voltage switching device 13 again.Other formation is identical with the foregoing description 1.
The formation of physical circuit as shown in figure 12, control device 26, portion possesses within it: lead-out terminal OUT, it is by making transistor Q1 conducting, ending via resistance R 1, the coil 13a of field power supply switching device 13 comes Switching Power Supply switching device 13; Input terminal IN1, it accepts the input of power supply cut-off switch 16; Input terminal IN2, it detects the input from instantaneous power failure checkout gear 25; Timer is a power supply drive unit again.
Action during in the above-described configuration, according to the process description generation instantaneous power failure of Figure 13.If in step 91, detect the generation instantaneous power failure, then in step 92, make as the power supply timer startup of drive unit 27 again, judge in step 93 whether load 1 moves, 1 moving, the action of load 1 is stopped if loading.After being set, T ' time delay enters step 96 in step 95.
Under the situation that load 1 does not move, in step 96, turn off power supply status display unit 14.Then, lead-out terminal OUT is set to low level state in step 97, and transistor Q1 is ended, and cuts off the path to power switch device 13, in step 98 power switch device 13 is set to off-state.
If in step 99 power supply again drive unit reach stipulated time t, then lead-out terminal OUT is set to high level state in step 100, makes transistor Q1 conducting, to power switch device 13 energising.After power switch device in step 101 13 is connected, in step 102, connect power supply status display unit 14, enter next stroke.So-called next stroke is meant state or the initial holding state before instantaneous power failure takes place.
Thereby, even taking place, instantaneous power failure also can return to the preceding state of instantaneous power failure generation.
In the above-described embodiments, be illustrated, but except washing machine, for example, also can similarly realize for power switch device by the machine of the control device control program of dryer, dishwashing detergent drying machine etc. for washing machine.
If adopt the invention of technical scheme 1 of the present invention as mentioned above, because its formation is, possesses dc source, the control device that during providing electric power, moves by above-mentioned dc source, switch is connected the power switch device of the AC power on the above-mentioned dc source, be connected in parallel with above-mentioned power switch device and carry out the power connection switch of power connection input, carry out power supply and disconnect the power supply cut-off switch of importing, above-mentioned control device, during being switched on, above-mentioned power connection switch is set to on-state according to the above-mentioned power switch device of electric power that provides by dc source, if be switched on then above-mentioned power switch device is set to off-state at the above-mentioned power supply cut-off switch in action beginning back, so can be at the state of power supply disconnection, when promptly loading the state that does not move, power switch device is set to off-state, can not switch on to dc source, and do not make under the situation of control device action, carry out the input of switch, can remove preparation electric power.In addition, owing under the state that switch disconnects, do not switch on, the component that constitutes dc source is not generated heat, thereby make operation part not hot to dc source.Have again,, therefore can make the simple in structure of switch owing to be arranged to be provided with respectively the structure of switch and power switch device, thereby can improve operability, water proofing property, and then, by the connection switch and the cut-off switch of power supply are set respectively, it is simple that circuit is constituted, and realizes low-cost.
In addition, if adopt the invention of technical scheme 2, because can be connected in series the anti-locking apparatus of the dash current that constitutes by resistance with the power connection switch that carries out the power connection input, so can be suppressed at the dash current that flows through when the power connection switch is switched on, thereby can prevent the damage of component.
Have again, if adopt the invention of technical scheme 3, then be because of its formation, possesses the load power switch device that switch is connected the AC power on the load, power switch device is connected switch AC power supply on the AC power, so can in power switch device, use the element of low capacity, thereby the action when power supply is inserted is more stable.
And then; if adopt the invention of technical scheme 4; then because possess the instantaneous power failure checkout gear of the generation that detects instantaneous power failure; the apparatus for protecting power supply that constitutes by electrolytic capacitor; the power supply that is made of timer is drive unit again; if detecting instantaneous power failure, control device make above-mentioned power supply be set to off-state in drive unit action and power switch device; if above-mentioned power supply drive unit again detects and has passed through the stipulated time; then above-mentioned power switch device is set to on-state, so also can return to the preceding state of instantaneous power failure generation even instantaneous power failure takes place.

Claims (4)

1. the power switch device of washing machine etc., possess, dc source, the gauge tap that moves during by above-mentioned DC power supply, switch is connected the power switch device of the AC power on the above-mentioned dc source, be connected in parallel with above-mentioned power switch device and carry out the power connection switch of power connection input, and the power supply cut-off switch that carries out power supply disconnection input, above-mentioned control device is during above-mentioned power connection switch is switched on, use the electric power that provides by dc source to make above-mentioned power switch device become on-state, if above-mentioned power cut-out switch is switched in action beginning back, then make above-mentioned power switch device become off-state.
2. the described power switch device of claim 1 is characterized in that and carry out that the power connection switch that power connection is imported in series is connected with the anti-locking apparatus of the dash current that is made of resistance.
3. the power switch device of described washing machine of claim 1 etc. it is characterized in that possessing the load power switch device that switch is connected the AC power on the load, and power switch device is connected switch AC power supply on the dc source.
4. the control device of washing machine etc., it is characterized in that, possess, the described power switch device of claim 1, detect the instantaneous power failure checkout gear of the generation of instantaneous power failure, the power supply holding device that constitutes by electrolytic capacitor and the power supply that constitutes by timer drive unit again,, control device makes the drive unit action and make power switch device become off-state again of above-mentioned power supply if detecting instantaneous power failure, if above-mentioned power supply drive unit again detects and passed through the stipulated time, then make above-mentioned power switch device become on-state.
CN98123088A 1998-02-26 1998-12-09 Power switch device and controller for washing machine Expired - Lifetime CN1109152C (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP44966/98 1998-02-26
JP10044966A JPH11239690A (en) 1998-02-26 1998-02-26 Power source switching device of washing machine and control device
JP44966/1998 1998-02-26

Publications (2)

Publication Number Publication Date
CN1227296A true CN1227296A (en) 1999-09-01
CN1109152C CN1109152C (en) 2003-05-21

Family

ID=12706232

Family Applications (2)

Application Number Title Priority Date Filing Date
CN98249470.XU Expired - Lifetime CN2387125Y (en) 1998-02-26 1998-12-09 Power source switch of washing machine
CN98123088A Expired - Lifetime CN1109152C (en) 1998-02-26 1998-12-09 Power switch device and controller for washing machine

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN98249470.XU Expired - Lifetime CN2387125Y (en) 1998-02-26 1998-12-09 Power source switch of washing machine

Country Status (4)

Country Link
JP (1) JPH11239690A (en)
KR (1) KR100657063B1 (en)
CN (2) CN2387125Y (en)
TW (1) TW435481U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877263A (en) * 2008-06-25 2013-01-16 株式会社东芝 Washing machine
CN102995352A (en) * 2011-09-13 2013-03-27 株式会社东芝 Load driving apparatus and washing machine
CN105229539A (en) * 2013-07-24 2016-01-06 松下知识产权经营株式会社 Electricity equipment

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101677612B1 (en) * 2009-10-29 2016-11-18 엘지전자 주식회사 Swiching mode power supply and controlling method thereof
JP5624944B2 (en) * 2011-05-31 2014-11-12 日立アプライアンス株式会社 Washing machines and electrical equipment

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR890006903A (en) * 1987-10-22 1989-06-16 다니이 아끼오 Power switch control device such as washing machine
CN87200051U (en) * 1987-01-02 1988-11-30 郭少智 Program controller for washer
CN2036315U (en) * 1988-06-22 1989-04-19 曾广华 Telecontrol electric power source plug board
JPH06284605A (en) * 1993-03-30 1994-10-07 Sharp Corp Power supply
KR950003220A (en) * 1993-07-12 1995-02-16 김동학 Manufacturing method of apatite molded sintered body
US5686767A (en) * 1994-12-29 1997-11-11 Thomson Consumer Electronics, Inc. Apportioning minimal standby power
KR970024441A (en) * 1995-10-11 1997-05-30 구자홍 Power consumption reduction device using optical energy

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102877263A (en) * 2008-06-25 2013-01-16 株式会社东芝 Washing machine
CN102877263B (en) * 2008-06-25 2015-08-19 株式会社东芝 Rinsing maching
CN102995352A (en) * 2011-09-13 2013-03-27 株式会社东芝 Load driving apparatus and washing machine
CN102995352B (en) * 2011-09-13 2015-04-01 株式会社东芝 Load driving apparatus and washing machine
CN105229539A (en) * 2013-07-24 2016-01-06 松下知识产权经营株式会社 Electricity equipment
CN105229539B (en) * 2013-07-24 2017-05-31 松下知识产权经营株式会社 Electric equipment
CN107245837A (en) * 2013-07-24 2017-10-13 松下知识产权经营株式会社 Electric equipment
CN107245837B (en) * 2013-07-24 2019-01-08 松下知识产权经营株式会社 Electric equipment

Also Published As

Publication number Publication date
JPH11239690A (en) 1999-09-07
KR19990071460A (en) 1999-09-27
KR100657063B1 (en) 2007-04-25
CN2387125Y (en) 2000-07-12
CN1109152C (en) 2003-05-21
TW435481U (en) 2001-05-16

Similar Documents

Publication Publication Date Title
CN201341018Y (en) Air conditioner phase-sequence controller with automatic phase change function
CN107086547B (en) A kind of combined high-voltage dc circuit breaker and its self energizing method with self energizing ability
CN1109152C (en) Power switch device and controller for washing machine
CN103210563A (en) Electronic control device and method for reducing stand-by state energy consumption of an electric household appliance
CN1920705A (en) Electronic equipment with state detecting and memorizing functions
CN101897093B (en) Circuit configuration for operating a household appliance
CN102870060A (en) Household appliance circuit arrangement
CN102570580B (en) Zero-standby power consumption power supply circuit, power supply device and household appliance
CN1722565A (en) Uninterruptible power supply
CN106130165B (en) The control circuit of automatic transfer switching electric appliance
CN2720596Y (en) Three-phase ac. dynamic switch
CN101824730B (en) Control method and control device of washing machine
CN2859596Y (en) Power shifter for household appliance
CN201083814Y (en) Stepper motor detection device
CN1369961A (en) Driving gear and driving method of a.c motor
CN104246053B (en) Electromotor control circuit for brushless washing machine motor
CN201290087Y (en) Standby soft starter device for motor
CN106575128B (en) For switching switching device, home appliances and corresponding method to the energy resource supply of electronic control unit
CN211908690U (en) Integrated control panel and control system of household appliance
CN213990491U (en) Starting control circuit of power supply system
CN1252904C (en) AC voltage control unit
CN217037078U (en) Double-shaft motor emergency stop circuit, double-shaft motor driver and double-shaft motor driving system
CN204530229U (en) A kind of washing machine based on super capacitor
CN217362943U (en) Double-voltage switching circuit
CN101565888B (en) Method for controlling clothes washing of washing machine

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20030521

CX01 Expiry of patent term