CN1183324A - Method for mfg. long stailess steel fibre - Google Patents

Method for mfg. long stailess steel fibre Download PDF

Info

Publication number
CN1183324A
CN1183324A CN 97121887 CN97121887A CN1183324A CN 1183324 A CN1183324 A CN 1183324A CN 97121887 CN97121887 CN 97121887 CN 97121887 A CN97121887 A CN 97121887A CN 1183324 A CN1183324 A CN 1183324A
Authority
CN
China
Prior art keywords
stainless steel
copper
complex
cold working
heat treatment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 97121887
Other languages
Chinese (zh)
Other versions
CN1060103C (en
Inventor
吴晓祖
杨照玲
云咏
李亚录
李建平
李成仁
王天成
王忠俊
奚正平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an Filter Metal Materials Co., Ltd.
Original Assignee
Northwest Institute for Non Ferrous Metal Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northwest Institute for Non Ferrous Metal Research filed Critical Northwest Institute for Non Ferrous Metal Research
Priority to CN97121887A priority Critical patent/CN1060103C/en
Publication of CN1183324A publication Critical patent/CN1183324A/en
Application granted granted Critical
Publication of CN1060103C publication Critical patent/CN1060103C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

A process for preparing long fibres of stainless steel is a bunched drawing one, which features that after heat treatment to soften, cold treatment is performed, during which the 20-90% of cold processed quantity is completed at the temp lower than 0 deg. C. By changing temp condition and controlling processed quantity, the conversion of austenite to martensite is promoted, so improving the tension strength of stainless steel fibres.

Description

The long stapled preparation method of a kind of stainless steel
The long stapled preparation method of a kind of stainless steel relates to a kind of employing boundling hubbing and prepares the long stapled method of stainless steel.
The flexibility of existingization of stainless steel fibre pricker, synthetic fibers and goods thereof, the good electric conductivity, corrosion resistance, the heat-resisting quantity that have metal itself to have again, thereby have purposes widely.At present, stainless steel fibre is mainly used in the production of the conductive fabric (as screening clothing, heat-resisting fabric) in the textile industry, and conduction conductive plastics preparation and sound-absorbing material, electromagnetic shielding material, anti-static material, the false proof coupon of bank etc. in the plastic cement industry.The stainless steel fibre felt of making of stainless steel fibre is the state-of-the-art high efficiency filter material of the eighties, be widely used in that high-viscosity melt in petrochemical industry, chemical fibre chemical industry, the textile industry filters and aerospace industry in the oil filter.
At present, the production method of stainless steel fibre has three kinds: hubbing, cutting method and take out molten method.Cutting method and take out molten method and be mainly used in the preparation stainless steel short fiber, and mostly adopt the boundling hubbing for widely used stainless steel long fibre.This method is with in the integrated a branch of and round jacket of packing into of tens even wires up to ten thousand rod, compresses tube reducing again.Inter-adhesive in order to prevent between the work metal line, need before the boundling at metal wire surface applied separation layer, peel off overcoat when pulling to required core filament diameter and remove separation layer, obtain fibre bundle.
Austenitic stainless steel has better heat-resisting performance, decay resistance and good processing properties, being most widely used of its fiber.Application form mainly contains yarn fabric, porous material (fibrofelt) and fibre reinforced composites.Because this class alloy of austenitic stainless steel can not undergo phase transition when heat treatment, makes them not improve its mechanical performance by heat-treating methods.Can only produce distortion martensite by cold working mode and improve mechanical performance.High-nickel austenite stainless steel particularly, because nickel has strengthened austenitic stability, thereby austenite is difficult to change to Ma Shiti when carrying out cold deformation at ambient temperature.And traditional boundling hubbing normally at room temperature carries out drawing, has influenced the performance of stainless steel fibre.The diameter of Sheng Chaning is 12 microns a 316L stainless steel fibre in this way, and its stretching resistance has only about 10g, so that reduced the yield rate in its use.
The objective of the invention is to overcome the powerful low shortcoming of stainless steel fibre tension that traditional boundling hubbing production exists, a kind of a kind of new long stapled preparation method of stainless steel that can effectively improve stainless steel long fibre mechanical performance is provided.
A kind of preparation method of stainless steel fibre, its process comprises: a. electroplating copper generates separation layer at stainless steel wire surface electrical plating copper; B. boundling with the stainless steel wire after the many plating, in the copper pipe of packing into, is formed steel/copper complex; C. once-combined body processing is carried out a cold working with steel/copper complex and is drawn into once-combined line; D. secondary boundling is once-combinedly traditional thread bindingly gone in the copper pipe many, forms steel/copper secondary complex; E. secondary complex processing is carried out drawing with complex, is processed into the secondary recombination line; F. work hardening heat treatment is eliminated in heat treatment; G. separation layer and copper overcoat are removed in pickling; It is characterized in that: after eliminating work hardening heat treatment, when carrying out final cold working, it is to carry out under the temperature temperature is 0 ℃~-100 ℃ condition that 20%~90% final cold working amount is arranged.
Because at a certain temperature, be out of shape formula body difficult to understand martensite transfor mation will take place, martensite is many more, and the tension brute force is high more.Method of the present invention is exactly by to the temperature of drawing process part process and to the control of working modulus, makes deformed austenite to martensite transfor mation, to improve the tension brute force of stainless steel fibre.This method has overcome traditional boundling hubbing drawing at room temperature effectively, and the shortcoming of the stainless steel fibre mechanicalness difference of production has improved the yield rate of stainless steel fibre shop felt, is a kind of preparation method of desirable stainless steel fibre.
Below in conjunction with example method of the present invention is described further.
A kind of preparation method of stainless steel fibre, its process is: a. electroplating copper generates separation layer at stainless steel wire surface electrical plating copper; B. boundling with the stainless steel wire after the many plating, in the copper pipe of packing into, is formed steel/copper complex, requires the mutual keeping parallelism of wire rod, and is regularly arranged; C. the complex time processing pulls to steel/copper complex cold working certain size, is processed into once-combined line.In this process, can produce work hardening, plasticity is reduced, recover plasticity, so that further processing so will prepare suitable annealing process.D. the secondary boundling reinstalls many once-combined lines in the copper pipe, forms the secondary complex; E. secondary complex processing pulls to certain size with complex, is processed into secondary steel/copper composite wire; F. heat treatment, g all eliminates work hardening heat treatment in first and second complex process; After eliminating work hardening heat treatment, carry out in final cold working, to effectively control processing temperature and processing ratio at a certain temperature, 20%~90% of its processing capacity will carry out under temperature is 0 ℃~-100 ℃ condition, h. copper overcoat and separation layer are removed in pickling, obtain stainless fiber beam.
Final cold working temperature is to carry out under 0~-100 ℃ of condition, is that final working modulus is controlled at 20%~90% because austenite is transformed into martensitic process and can carries out smoothly at low temperatures, be for the hardening constituent that guarantees sufficient amount be martensitic formation.The means of acquisition low temperature of the present invention can be by adopting modes such as refrigerating chamber, freezing liquid, frozen water mixed liquor and liquid nitrogen.Adopt the method for liquid nitrogen frozen, though can reach very low temperature, but process will inevitably produce a large amount of low temperature losses, so the possible actual minimum of process is greatly about about-100 ℃, cross the effect that low temperature may produce, but consider that from the cost of practical operation adopting temperature conditions of the present invention still is both economical practicality.
Embodiment 1
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out the cold working drawing, after certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 5.86mm through re-compounded 6655 its recombination lines of core 316L/ copper, after carrying out last heat treatment, recombination line is stretched to 3.9mm by Φ 5.86mm at ambient temperature, it is freezing then multiple line to be put into freezing liquid, its temperature is under-100 ℃~-50 ℃ conditions, then recombination line is stretched to Φ 2.76mm from Φ 3.9mm, obtains 20 microns stainless fiber beam after copper overcoat and separation layer are removed in last pickling.Its tension brute force reaches 38.2g after testing, and the fiber of processing than whole drawings has at room temperature improved 25%.
Embodiment 2
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out cold working pull to certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 5.86mm through re-compounded 3751 its recombination lines of core 316L/ copper, after carrying out last heat treatment, recombination line is stretched to 1.92mm by Φ 5.86mm at ambient temperature, it is freezing then multiple line to be put into freezing liquid, its temperature is under-30 ℃~-20 ℃ conditions, again recombination line is stretched to Φ 1.36mm from Φ 1.92mm, obtains 12 microns stainless fiber beam after copper overcoat and separation layer are removed in last pickling.Its tension brute force reaches 16.95g after testing.
Embodiment 3
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out a cold working pull to certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 5.86mm through re-compounded 3651 its recombination lines of core 316L/ copper, after carrying out last heat treatment, recombination line is stretched to 2.29mm by Φ 5.86mm at ambient temperature, then multiple line being put into the frozen water mixed liquor lowers the temperature, in its temperature is under 0 ℃ of condition, again recombination line is stretched to Φ 1.62mm from Φ 2.29mm, pickling obtains 12 microns stainless fiber beam after removing copper overcoat and separation layer then.
Embodiment 4
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out a cold working pull to certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 5.86mm through re-compounded 3751 its recombination lines of core 316L/ copper, after carrying out last heat treatment, recombination line is stretched to 2.04mm by Φ 5.86mm at ambient temperature, then multiple line being put into the frozen water mixed liquor lowers the temperature, in its temperature is under 0 ℃ of condition, again recombination line is stretched to Φ 1.44mm from Φ 2.04mm, obtains 12 microns stainless fiber beam after copper overcoat and separation layer are removed in last pickling.Its tension brute force reaches 20.85g after testing.
Embodiment 5
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out a cold working pull to certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 11.6mm through re-compounded its recombination line of 13255 cores, 316/ bronze medal, after carrying out last heat treatment, recombination line is stretched to 2.85mm by Φ 11.6mm at ambient temperature, then multiple line being put into freezing liquid lowers the temperature, in its temperature is under-70~-50 ℃ of conditions, again recombination line is stretched to Φ 2.39mm from Φ 2.85mm, obtains 12 microns stainless fiber beam after copper overcoat and separation layer are removed in last pickling.
Embodiment 6
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out a cold working pull to certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 11.6mm through re-compounded 13255 its recombination lines of core 316L/ copper, after carrying out last heat treatment, recombination line is stretched to 3.4mm by Φ 11.6mm at ambient temperature, then multiple line being put into liquid nitrogen frozen liquid lowers the temperature, in its temperature is under-70~-50 ℃ of conditions, again recombination line is stretched to Φ 2.39mm from Φ 3.4mm, pickling obtains 12 microns stainless fiber beam after removing copper overcoat and separation layer then.
Embodiment 7
By generating separation layer,, in the copper pipe of packing into, form steel/copper complex with the stainless steel wire after the many plating at stainless steel wire surface electrical plating copper; Steel/copper complex is carried out a cold working pull to certain specification, many once-combined lines are reinstalled in the copper pipe, it is compound to carry out secondary, be machined to Φ 11.6mm through re-compounded its recombination line of 13255 cores, 316/ bronze medal, after carrying out last heat treatment, again the recombination line recombination line is stretched to 3.8mm by Φ 11.6mm at ambient temperature, it is freezing then multiple line to be put into freezing liquid, its temperature is under-70 ℃~-50 ℃ conditions, be stretched to Φ 2.39mm from Φ 3.8mm, pickling obtains 12 microns stainless fiber beam after removing place to go cover and separation layer then.

Claims (1)

1. long stapled preparation side of stainless steel comprises:
A. generate separation layer at stainless steel wire surface electrical plating copper;
B. boundling with the stainless steel wire after the many plating, in the copper pipe of packing into, is formed steel/copper complex;
C. once-combined body processing is carried out a cold working drawing with steel/copper complex, is processed into once-combined line;
D. the secondary boundling reinstalls many once-combined lines in the copper pipe, forms the secondary complex;
E. secondary complex cold working is carried out drawing with complex, is processed into the secondary recombination line;
F. eliminate work hardening heat treatment;
G. stainless steel layer and overcoat are removed in pickling;
It is characterized in that: after eliminating work hardening heat treatment, when carrying out final cold working, it is to carry out under temperature is 0 ℃~-100 ℃ condition that 20%~90% processing capacity is arranged in the final cold working amount.
CN97121887A 1997-12-11 1997-12-11 Method for mfg. long stailess steel fibre Expired - Lifetime CN1060103C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN97121887A CN1060103C (en) 1997-12-11 1997-12-11 Method for mfg. long stailess steel fibre

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN97121887A CN1060103C (en) 1997-12-11 1997-12-11 Method for mfg. long stailess steel fibre

Publications (2)

Publication Number Publication Date
CN1183324A true CN1183324A (en) 1998-06-03
CN1060103C CN1060103C (en) 2001-01-03

Family

ID=5176515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN97121887A Expired - Lifetime CN1060103C (en) 1997-12-11 1997-12-11 Method for mfg. long stailess steel fibre

Country Status (1)

Country Link
CN (1) CN1060103C (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100427659C (en) * 2002-05-13 2008-10-22 贝卡尔特股份有限公司 Electrically conductive yarn
CN102477577A (en) * 2010-11-22 2012-05-30 湖南汇博金属材料有限责任公司 Preparation process for metal fibers
CN102825096A (en) * 2012-03-23 2012-12-19 常州市武进恒通金属钢丝有限公司 New process for producing micron-order stainless steel fiber
CN103215529A (en) * 2013-04-18 2013-07-24 沈阳理工大学 Steel/stainless steel fiber reinforced composite copper foil and manufacturing method thereof
CN103233254A (en) * 2013-04-11 2013-08-07 西安菲尔特金属过滤材料有限公司 Preparation method of corrosion resistant alloy fiber
CN103418995A (en) * 2013-07-29 2013-12-04 朱建军 Method of manufacturing micron-sized superfine aluminum fiber
CN104275362A (en) * 2014-09-19 2015-01-14 中山市鸿程科研技术服务有限公司 Preparation method of iron-chromium-aluminum metal fibers
CN104368622A (en) * 2014-09-29 2015-02-25 石家庄德安旺金属科技有限公司 Metal fiber production technology
CN105386105A (en) * 2015-11-25 2016-03-09 西安菲尔特金属过滤材料有限公司 Manufacturing method of nickel base alloy fibers
CN105945084A (en) * 2016-05-17 2016-09-21 湖南汇博金属材料有限责任公司 Stainless steel fiber containing copper in surface and preparation method of stainless steel fiber

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3379000A (en) * 1965-09-15 1968-04-23 Roehr Prod Co Inc Metal filaments suitable for textiles
BE1001539A3 (en) * 1988-03-17 1989-11-21 Bekaert Sa Nv Metal fibers obtained by bundled PULLING.

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100427659C (en) * 2002-05-13 2008-10-22 贝卡尔特股份有限公司 Electrically conductive yarn
CN102477577A (en) * 2010-11-22 2012-05-30 湖南汇博金属材料有限责任公司 Preparation process for metal fibers
CN102825096A (en) * 2012-03-23 2012-12-19 常州市武进恒通金属钢丝有限公司 New process for producing micron-order stainless steel fiber
CN103233254A (en) * 2013-04-11 2013-08-07 西安菲尔特金属过滤材料有限公司 Preparation method of corrosion resistant alloy fiber
CN103233254B (en) * 2013-04-11 2015-05-13 西安菲尔特金属过滤材料有限公司 Preparation method of corrosion resistant alloy fiber
CN103215529A (en) * 2013-04-18 2013-07-24 沈阳理工大学 Steel/stainless steel fiber reinforced composite copper foil and manufacturing method thereof
CN103418995A (en) * 2013-07-29 2013-12-04 朱建军 Method of manufacturing micron-sized superfine aluminum fiber
CN103418995B (en) * 2013-07-29 2016-01-27 朱建军 A kind of processing method of micron-class superfine aluminum fiber
CN104275362A (en) * 2014-09-19 2015-01-14 中山市鸿程科研技术服务有限公司 Preparation method of iron-chromium-aluminum metal fibers
CN104368622A (en) * 2014-09-29 2015-02-25 石家庄德安旺金属科技有限公司 Metal fiber production technology
CN105386105A (en) * 2015-11-25 2016-03-09 西安菲尔特金属过滤材料有限公司 Manufacturing method of nickel base alloy fibers
CN105945084A (en) * 2016-05-17 2016-09-21 湖南汇博金属材料有限责任公司 Stainless steel fiber containing copper in surface and preparation method of stainless steel fiber

Also Published As

Publication number Publication date
CN1060103C (en) 2001-01-03

Similar Documents

Publication Publication Date Title
CN1060103C (en) Method for mfg. long stailess steel fibre
US3379000A (en) Metal filaments suitable for textiles
Manocha et al. Effect of carbon fiber surface-treatment on mechanical properties of C/C composites
US6497029B1 (en) Process for making fine and ultra fine metallic fibers
CN112246894A (en) Production process of titanium fiber
CN110391048A (en) A kind of Nb3The preparation method of Sn presoma wire rod
CN112439799B (en) Production method of ultra-fine and ultra-high-strength synchronous belt steel cord
US6325875B2 (en) Titanium fiber and method of producing the same
KR930005075B1 (en) Super high strength super fine wire
CN101752032A (en) Contact cable taking alloy material to wrap carbon fiber core
CN114457602A (en) Method for manufacturing galvanized steel wire rope for high-altitude operation hanging basket
EP0057492A2 (en) Process for the surface modification of carbon fibres
WO2002068148A1 (en) Process for making fine metallic mesh
CN1357449A (en) Bimetallic composite wire of stainless steel coated carbon steel and its production process
Levitt et al. Fabrication and properties of graphite fiber reinforced magnesium
CN201465629U (en) Contact cable formed by packing carbon fiber core with alloy material
Veit Metal fibers
Nishi et al. Nb3Sn superconducting strand development in Japan for ITER
KR100369377B1 (en) Method for preparing steel cords
EP0431237A1 (en) Direct deposition of gold on carbon fiber
JPH10128428A (en) Manufacture of alloy fine wire, alloy fine wire assembly, alloy fine wire strand, alloy fine wire textile, alloy fine wire knit fabric, alloy fine wire web and alloy fine wire felt
Dobránszky et al. A New Method for Determining the Pullability of Composite Reinforcing Ceramic Fibres
Ismojo et al. Effect of time alkali treatment on chemical composition and tensile strength properties of kenaf single fibers
CN116759154B (en) Preparation method of superconducting wire with short production period and ultra-low copper ratio
CN220149947U (en) Carbon fiber nano surface modification device

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: WEST METAL MATERIAL CO., LTD.

Free format text: FORMER OWNER: XIBEI INST. OF NON-FERROUS METALS

Effective date: 20060512

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20060512

Address after: 710065 No. 56, science and technology road, hi tech Zone, Shaanxi, Xi'an

Patentee after: Xibu Metal Material Co., Ltd.

Address before: 710016 box 51, Xi'an, Shaanxi

Patentee before: Xibei Non-ferrous Metals Research Inst.

ASS Succession or assignment of patent right

Owner name: XI'AN FEIERTE METAL FILTER MATERIAL CO., LTD.

Free format text: FORMER OWNER: WEST METAL MATERIAL CO., LTD.

Effective date: 20070202

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20070202

Address after: 710016 Shaanxi city of Xi'an Province dragon Northwest Institute two western part of North Feierte company

Patentee after: Xi'an Filter Metal Materials Co., Ltd.

Address before: 710065 No. 56, science and technology road, hi tech Zone, Shaanxi, Xi'an

Patentee before: Xibu Metal Material Co., Ltd.

CX01 Expiry of patent term

Granted publication date: 20010103

CX01 Expiry of patent term