CN117905050A - Karst area bored pile foundation construction method - Google Patents
Karst area bored pile foundation construction method Download PDFInfo
- Publication number
- CN117905050A CN117905050A CN202410320807.7A CN202410320807A CN117905050A CN 117905050 A CN117905050 A CN 117905050A CN 202410320807 A CN202410320807 A CN 202410320807A CN 117905050 A CN117905050 A CN 117905050A
- Authority
- CN
- China
- Prior art keywords
- hole
- drilling
- karst
- pile foundation
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 40
- 238000005553 drilling Methods 0.000 claims abstract description 85
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 77
- 239000010959 steel Substances 0.000 claims abstract description 77
- 230000002787 reinforcement Effects 0.000 claims abstract description 10
- 238000004519 manufacturing process Methods 0.000 claims abstract description 8
- 238000004140 cleaning Methods 0.000 claims description 30
- 238000000034 method Methods 0.000 claims description 27
- 239000013049 sediment Substances 0.000 claims description 16
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 12
- 238000013461 design Methods 0.000 claims description 9
- 239000011435 rock Substances 0.000 claims description 7
- 230000015572 biosynthetic process Effects 0.000 claims description 6
- 239000002002 slurry Substances 0.000 claims description 6
- 238000007689 inspection Methods 0.000 claims description 5
- 239000004576 sand Substances 0.000 claims description 5
- 239000002689 soil Substances 0.000 claims description 5
- 238000009826 distribution Methods 0.000 claims description 3
- 239000004033 plastic Substances 0.000 claims description 3
- 230000003068 static effect Effects 0.000 claims description 3
- 239000004575 stone Substances 0.000 claims description 3
- 230000000903 blocking effect Effects 0.000 claims description 2
- 238000001514 detection method Methods 0.000 claims description 2
- 238000005755 formation reaction Methods 0.000 claims 1
- 238000005096 rolling process Methods 0.000 claims 1
- 238000010408 sweeping Methods 0.000 claims 1
- 239000010410 layer Substances 0.000 description 10
- 239000000243 solution Substances 0.000 description 10
- 238000005259 measurement Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 5
- 238000004062 sedimentation Methods 0.000 description 4
- 239000004927 clay Substances 0.000 description 3
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 230000035515 penetration Effects 0.000 description 3
- 239000003351 stiffener Substances 0.000 description 3
- 238000003860 storage Methods 0.000 description 3
- 238000012360 testing method Methods 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 101001121408 Homo sapiens L-amino-acid oxidase Proteins 0.000 description 2
- 241000755266 Kathetostoma giganteum Species 0.000 description 2
- 102100026388 L-amino-acid oxidase Human genes 0.000 description 2
- CDBYLPFSWZWCQE-UHFFFAOYSA-L Sodium Carbonate Chemical compound [Na+].[Na+].[O-]C([O-])=O CDBYLPFSWZWCQE-UHFFFAOYSA-L 0.000 description 2
- 238000005520 cutting process Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 101100233916 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) KAR5 gene Proteins 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- 229910000278 bentonite Inorganic materials 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002985 plastic film Substances 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000011241 protective layer Substances 0.000 description 1
- 238000000746 purification Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 229910000029 sodium carbonate Inorganic materials 0.000 description 1
- 235000017550 sodium carbonate Nutrition 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/68—Mould-pipes or other moulds for making bulkheads or elements thereof
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域Technical Field
本申请涉及钻孔灌桩的技术领域,尤其涉及一种岩溶地区钻孔桩基础施工方法。The present application relates to the technical field of bored piles, and in particular to a bored pile foundation construction method in karst areas.
背景技术Background technique
钻孔灌注桩是目前应用比较广泛的桩基类型,它机械化程度高,单桩承载大,桩身刚度强。Bored cast-in-place piles are currently the most widely used type of pile foundation, with a high degree of mechanization, large single pile bearing capacity and strong pile body rigidity.
在钻孔施工过程中遇到溶洞时,常常会向溶洞内抛填片石、混凝土、粘土等,与岩溶填充物共同形成良好的护壁。但是,该方法仍然存在以下问题:When encountering a karst cave during drilling construction, stone flakes, concrete, clay, etc. are often thrown into the cave to form a good protective wall together with the karst filling. However, this method still has the following problems:
岩溶地区钻孔桩基础施工中无法判断溶洞大小而导致混凝土超灌量难以控制,成桩质量差,对自然环境影响大,绿色建造水平低。In the construction of bored pile foundations in karst areas, it is impossible to judge the size of the cave, which makes it difficult to control the over-injection of concrete, resulting in poor pile quality, a great impact on the natural environment, and a low level of green construction.
发明内容Summary of the invention
本申请提供一种岩溶地区钻孔桩基础施工方法,高效地解决了因桩基中无法判断溶洞大小而导致混凝土超灌量难以控制的问题,成桩质量高,对自然环境影响小,绿色建造水平高,施工周期大大缩短。The present application provides a bored pile foundation construction method in karst areas, which effectively solves the problem of difficulty in controlling the over-injection of concrete due to the inability to determine the size of the karst cave in the pile foundation. The pile quality is high, the impact on the natural environment is small, the green construction level is high, and the construction period is greatly shortened.
本申请提供一种岩溶地区钻孔桩基础施工方法,包括:S1、测量放样,采用仪器精确定位桩孔的位置,根据桩定位点拉十字线钉放四个控制桩,以四个所述控制桩为基准控制钢护筒的埋设位置和钻机的准确就位;S2、钢护筒制作及埋设,采用钢板卷制成型所述钢护筒,使所述钢护筒的内径比设计桩径大0.2~0.4m;所述钢护筒埋设完毕后,控制所述钢护筒的顶部高于原地面0.3m,用于钻头定位及保护桩孔;S3、钻机就位,钻机就位时,事先检查钻机的性能状态是否良好,保证钻机工作正常;通过测设的桩位准确地确定钻机的位置,并保证钻机稳定,通过手动粗略调平以保证钻杆基本竖直后, 利用自动控制系统调整钻杆保持竖直状态;S4、钻机钻进成孔,现场设置泥浆池,随后,进行钻孔作业;S5、溶洞定位、测量,根据地勘报告溶洞位置结合钻进深度进行初步定位,并阻断地面泥浆流入孔内;钻至溶洞具体位置时,孔内泥浆面会迅速下降,此时孔深位置可近似侧壁溶洞顶部标高,根据泥浆面下降高度,测算出溶洞最小容量;再根据地勘报告显示的溶洞底标高结合钻孔岩样判定溶洞近似底标高,近似确定孔侧壁溶洞断面尺寸;S6、钻机钻进至终孔;S7、清孔及验收,湿孔清孔采用换浆法清孔,清孔时需要注意保持孔内水位;干孔沉渣采用沉淀后用平头钻头进行清理;S8、钢筋笼制作运输及安装,若溶洞深度超过4m或者无法判断溶洞体积大小,则在钢筋笼对应溶洞侧壁的外侧固定包裹快易收口网,所述快易收口网的尺寸大于溶洞的洞口尺寸;S9、下导管,导管安装时逐节量取导管实际长度并按序编号,做好记录,检查每段导管两头丝扣无破丝现象;S10、二次清孔,导管下放到位后,立即进行桩基础底部沉渣检测,若沉渣厚度不满足设计要求,采用气举反循环二次清孔,清孔结束检验合格后,立即拆除吸泥弯头;S11、水下混凝土灌注。The present application provides a bored pile foundation construction method in karst areas, comprising: S1, surveying and setting out, using instruments to accurately locate the position of the pile hole, pulling cross-line nails according to the pile positioning points to place four control piles, and using the four control piles as a reference to control the buried position of the steel casing and the accurate positioning of the drilling rig; S2, steel casing production and burying, using steel plates to roll and shape the steel casing, so that the inner diameter of the steel casing is 0.2 to 0.4 m larger than the designed pile diameter; after the steel casing is buried, the top of the steel casing is controlled to be 0.3 m higher than the original ground for drill bit positioning and pile hole protection; S3, drilling rig positioning, when the drilling rig is in place, check in advance whether the performance status of the drilling rig is good to ensure that the drilling rig works normally; accurately determine the position of the drilling rig through the measured pile position, and ensure that the drilling rig is stable, and manually roughly level the drill rod to ensure that it is basically vertical, Use the automatic control system to adjust the drill rod to keep it in a vertical state; S4, the drill rig drills a hole, sets up a mud pool on site, and then carries out drilling operations; S5, cave positioning and measurement, preliminary positioning is carried out according to the location of the cave in the geological survey report and the drilling depth, and the ground mud is blocked from flowing into the hole; when drilling to the specific location of the cave, the mud surface in the hole will drop rapidly. At this time, the hole depth position can be approximated to the top elevation of the side wall cave. According to the height of the mud surface drop, the minimum capacity of the cave is calculated; then, according to the elevation of the cave bottom shown in the geological survey report and the drilled rock sample, the approximate bottom elevation of the cave is determined, and the cross-sectional size of the cave on the side wall of the hole is approximately determined; S6, the drill rig drills to the final hole; S7, hole cleaning and acceptance, wet hole cleaning adopts the slurry replacement method to clean the hole, and it is necessary to pay attention to keeping the hole when cleaning the hole Internal water level; the dry hole sediment is cleaned with a flat-head drill bit after settling; S8, production, transportation and installation of steel cage. If the depth of the cave exceeds 4m or the volume of the cave cannot be determined, a quick-closing net is fixed on the outer side of the steel cage corresponding to the cave side wall. The size of the quick-closing net is larger than the size of the cave entrance; S9, lowering the guide tube. When installing the guide tube, measure the actual length of the guide tube section by section and number them in sequence, keep records, and check that there is no broken thread at both ends of each section of the guide tube; S10, secondary hole cleaning. After the guide tube is lowered into place, the sediment at the bottom of the pile foundation is immediately detected. If the sediment thickness does not meet the design requirements, air lift reverse circulation is used for secondary hole cleaning. After the hole cleaning is completed and the inspection is qualified, the mud suction elbow is immediately removed; S11, underwater concrete pouring.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S2中,在所述钢护筒的顶部、底部端口外围均焊接加劲环。In the optional technical solution of the above-mentioned bored pile foundation construction method in karst areas, in step S2, stiffening rings are welded to the periphery of the top and bottom ports of the steel casing.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S3中,采用旋挖钻机进行钻孔。In the above optional technical solution of the bored pile foundation construction method in karst areas, in step S3, a rotary drilling rig is used for drilling.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S4中,对于黏结性良好的岩土层,采用干式或清水钻进工艺,不使用泥浆护壁,对孔口0.5m范围内的碎石泥土进行清理干净;对于松散易坍塌地层或有地下水分布的底层,采用静态泥浆护壁钻进工艺。In the above-mentioned optional technical scheme of the bored pile foundation construction method in karst areas, in step S4, for rock and soil layers with good adhesion, a dry or clean water drilling process is adopted without using mud wall protection, and the gravel and soil within 0.5m of the hole mouth are cleaned; for loose and easily collapsed strata or the bottom layer with groundwater distribution, a static mud wall drilling process is adopted.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S4中,钻孔过程中根据地质情况控制进尺速度:由硬地层钻到软地层时,适当加快钻进速度;当软地层变为硬地层时,减速慢进;在易缩径的地层中,适当增加扫孔次数,防止缩径;对硬塑层采用快转速钻进,以提高钻进效率;对于砂层,采用慢转速慢钻进并适当增加泥浆比重和粘度。In the above-mentioned optional technical solution of the bored pile foundation construction method in karst areas, in step S4, the penetration speed is controlled according to the geological conditions during the drilling process: when drilling from a hard stratum to a soft stratum, the drilling speed is appropriately accelerated; when the soft stratum becomes a hard stratum, the penetration speed is slowed down; in strata that are prone to shrinkage, the number of hole sweeps is appropriately increased to prevent shrinkage; high-speed drilling is used for hard plastic layers to improve drilling efficiency; for sand layers, slow drilling is used with a slow speed and the mud density and viscosity are appropriately increased.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S7中,清孔分两次进行,第一次清孔在钻孔深度达到设计深度后进行,待钢筋笼安装到位后下放导管前再进行第二次清孔。In the above-mentioned optional technical solution of the bored pile foundation construction method in karst areas, in step S7, the hole cleaning is performed twice. The first hole cleaning is performed after the drilling depth reaches the designed depth, and the second hole cleaning is performed after the steel cage is installed in place and before the guide tube is lowered.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S8中,为防止运输和吊装时钢筋笼变形,对吊点位进行加强处理,对加劲筋进行加密。In the optional technical solution of the bored pile foundation construction method in karst areas described above, in step S8, in order to prevent the steel cage from being deformed during transportation and hoisting, the hoisting points are reinforced and the stiffening bars are encrypted.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S8中,使用顶部、底部具有折边的快易收口网,钢筋笼下放至孔内后,使所述折边紧贴孔壁;使用顶部、底部大于侧壁溶洞尺寸至少50cm的快易收口网;使用U型钢筋绑扎快易收口网,并加密所述U型钢筋,沿着快易收口网均匀布设所述U型钢筋。In the above-mentioned optional technical solution of the bored pile foundation construction method in karst areas, in step S8, a quick-closing net with folded edges at the top and bottom is used, and after the steel cage is lowered into the hole, the folded edges are made close to the hole wall; a quick-closing net with a top and bottom at least 50 cm larger than the size of the side wall cave is used; the quick-closing net is tied with U-shaped steel bars, and the U-shaped steel bars are denser, and the U-shaped steel bars are evenly arranged along the quick-closing net.
在上述一种岩溶地区钻孔桩基础施工方法的可选技术方案中,在步骤S11中,灌注混凝土前对混凝土输送管路及容器洒水润湿。In the above-mentioned optional technical solution of the bored pile foundation construction method in karst areas, in step S11, the concrete delivery pipeline and container are sprinkled with water to moisten them before pouring concrete.
本申请提供的一种岩溶地区钻孔桩基础施工方法,步骤S8为关键步骤,通过在钢筋笼对应溶洞侧壁的外侧固定包裹快易收口网,快易收口网的尺寸大于溶洞的洞口尺寸,高效地解决了因桩基中无法判断溶洞大小而导致混凝土超灌量难以控制的问题,成桩质量高,对自然环境影响小,绿色建造水平高,施工周期大大缩短。The present application provides a method for constructing bored pile foundations in karst areas, wherein step S8 is a key step. A quick-closing net is fixedly wrapped around the outer side of a steel cage corresponding to a side wall of a karst cave, wherein the size of the quick-closing net is larger than the size of the cave opening. This effectively solves the problem of difficulty in controlling the amount of over-pouring of concrete due to the inability to judge the size of the cave in the pile foundation. The piles are of high quality, have little impact on the natural environment, have a high level of green construction, and greatly shorten the construction period.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
此处的附图被并入说明书中并构成本说明书的一部分,示出了符合本申请的实施例,并与说明书一起用于解释本申请的原理。The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
图1为本申请实施例提供的一种岩溶地区钻孔桩基础施工方法的流程图;FIG1 is a flow chart of a bored pile foundation construction method in a karst area provided by an embodiment of the present application;
图2为溶洞位置尺寸判断步骤图;Figure 2 is a diagram showing the steps for determining the location and size of a cave;
图3为带有快易收口网的钢筋笼的安装示意图;FIG3 is a schematic diagram of the installation of a steel cage with a quick-closing mesh;
图4为混凝土灌注过程示意图。FIG. 4 is a schematic diagram of the concrete pouring process.
通过上述附图,已示出本申请明确的实施例,后文中将有更详细的描述。这些附图和文字描述并不是为了通过任何方式限制本申请构思的范围,而是通过参考特定实施例为本领域技术人员说明本申请的概念。The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments.
具体实施方式Detailed ways
这里将详细地对示例性实施例进行说明,其示例表示在附图中。下面的描述涉及附图时,除非另有表示,不同附图中的相同数字表示相同或相似的要素。以下示例性实施例中所描述的实施方式并不代表与本申请相一致的所有实施方式。相反,它们仅是与如所附权利要求书中所详述的、本申请的一些方面相一致的装置和方法的例子。Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The implementations described in the following exemplary embodiments do not represent all implementations consistent with the present application. Instead, they are merely examples of devices and methods consistent with some aspects of the present application as detailed in the appended claims.
正如背景技术所述,钻孔灌注桩是目前应用比较广泛的桩基类型,它机械化程度高,单桩承载大,桩身刚度强。As described in the background art, bored piles are currently the most widely used type of pile foundation, which has a high degree of mechanization, a large single pile bearing capacity, and a strong pile body rigidity.
在钻孔施工过程中遇到溶洞时,常常会向溶洞内抛填片石、混凝土、粘土等,与岩溶填充物共同形成良好的护壁。但是,该方法仍然存在以下问题:When encountering a karst cave during drilling construction, stone flakes, concrete, clay, etc. are often thrown into the cave to form a good protective wall together with the karst filling. However, this method still has the following problems:
岩溶地区钻孔桩基础施工中无法判断溶洞大小而导致混凝土超灌量难以控制,成桩质量差,对自然环境影响大,绿色建造水平低。In the construction of bored pile foundations in karst areas, it is impossible to judge the size of the cave, which makes it difficult to control the over-injection of concrete, resulting in poor pile quality, a great impact on the natural environment, and a low level of green construction.
针对上述技术问题,本申请实施例提供一种岩溶地区钻孔桩基础施工方法,通过在钢筋笼对应溶洞侧壁的外侧固定包裹快易收口网,从而可以封堵溶洞的泄漏口,从而解决了岩溶地区钻孔桩基础施工中无法判断溶洞大小而导致混凝土超灌量难以控制,成桩质量差,对自然环境影响大,绿色建造水平低的技术问题。In response to the above-mentioned technical problems, an embodiment of the present application provides a method for constructing bored pile foundations in karst areas, by fixing and wrapping a quick-closing net on the outer side of the steel cage corresponding to the side wall of the cave, thereby blocking the leakage of the cave, thereby solving the technical problems that the size of the cave cannot be judged during the construction of bored pile foundations in karst areas, resulting in difficulty in controlling the over-pouring of concrete, poor pile quality, great impact on the natural environment, and low level of green construction.
下面以具体地实施例对本申请的技术方案以及本申请的技术方案如何解决上述技术问题进行详细说明。下面这几个具体的实施例可以相互结合,对于相同或相似的概念或过程可能在某些实施例中不再赘述。下面将结合附图1-4,对本申请的实施例进行描述。The technical solution of the present application and how the technical solution of the present application solves the above-mentioned technical problems are described in detail below with specific embodiments. The following specific embodiments can be combined with each other, and the same or similar concepts or processes may not be repeated in some embodiments. The embodiments of the present application will be described below in conjunction with Figures 1-4.
本申请实施例提供一种岩溶地区钻孔桩基础施工方法,包括以下步骤:The present application provides a method for constructing a bored pile foundation in a karst area, comprising the following steps:
S1、测量放样,请参照图1,采用仪器精确定位桩孔的位置,本实施例可以采用全站仪,根据桩定位点拉十字线钉放四个控制桩,以四个控制桩为基准控制钢护筒的埋设位置和钻机的准确就位,控制桩需要做到良好的保护工作,防止施工过程中被扰动。S1. Measurement and layout. Please refer to FIG1. Use an instrument to accurately locate the position of the pile hole. In this embodiment, a total station can be used. Pull crosshairs and place four control piles according to the pile positioning points. The four control piles are used as a reference to control the buried position of the steel casing and the accurate positioning of the drilling rig. The control piles need to be well protected to prevent them from being disturbed during the construction process.
S2、钢护筒制作及埋设,请参照图1,采用钢板卷制成型钢护筒,具体而言,钢护筒可以采用6mm钢板卷制成型,使钢护筒的内径比设计桩径大0.2m~0.4m;在钢护筒的顶部、底部端口外围均焊接加劲环;钢护筒安装时,钻机操作手利用扩孔器将桩孔扩大,之后通过大扭矩钻头将钢护筒压入设计标高。护筒压入前及压入后,通过靠在钢护筒上的精确水平仪调整钢护筒的垂直位置;钢护筒埋设完毕后,控制钢护筒的顶部高于原地面0.3m,用于钻头定位及保护桩孔。S2. Steel casing production and burial, please refer to Figure 1, steel casing is made of rolled steel plate. Specifically, the steel casing can be made of 6mm steel plate, so that the inner diameter of the steel casing is 0.2m~0.4m larger than the designed pile diameter; stiffening rings are welded on the outer periphery of the top and bottom ports of the steel casing; when installing the steel casing, the drill operator uses the reamer to expand the pile hole, and then presses the steel casing into the designed elevation with a high-torque drill bit. Before and after the casing is pressed in, the vertical position of the steel casing is adjusted by a precise level against the steel casing; after the steel casing is buried, the top of the steel casing is controlled to be 0.3m higher than the original ground for drill bit positioning and pile hole protection.
S3、钻机就位,请参照图1,具体而言,本实施例可以采用旋挖钻机进行钻孔;钻机就位时,事先检查钻机的性能状态是否良好,保证钻机工作正常;通过测设的桩位准确地确定钻机的位置,并保证钻机稳定,通过手动粗略调平以保证钻杆基本竖直后, 利用自动控制系统调整钻杆保持竖直状态。S3. The drilling rig is in place. Please refer to FIG. 1 . Specifically, in this embodiment, a rotary drilling rig can be used for drilling. When the drilling rig is in place, check in advance whether the performance of the drilling rig is good to ensure that the drilling rig works normally. The position of the drilling rig is accurately determined by measuring the pile position, and the drilling rig is ensured to be stable. After roughly leveling manually to ensure that the drill rod is basically vertical, the automatic control system is used to adjust the drill rod to maintain a vertical state.
S4、钻机钻进成孔,请参照图1,现场设置泥浆池,随后,进行钻孔作业。S4. The drilling rig drills into a hole. Please refer to Figure 1. A mud pool is set up on site, and then the drilling operation is carried out.
①泥浆制备① Mud preparation
对于黏结性良好的岩土层,采用干式或清水钻进工艺,不使用泥浆护壁,对孔口0.5m范围内的碎石泥土进行清理干净;对于松散易坍塌地层或有地下水分布的底层,采用静态泥浆护壁钻进工艺。For rock and soil layers with good adhesion, dry or clean water drilling technology is adopted without mud wall protection, and the gravel and soil within 0.5m of the hole mouth are cleaned up; for loose and easily collapsed strata or the bottom layer with groundwater distribution, static mud wall drilling technology is adopted.
泥浆池包含回浆用沉淀池及泥浆储备池,一般为钻孔容积的1.5~2.0倍,泥浆池的底部和四周要铺设塑料布或采取其它封闭措施,防止泥浆外流。The mud pool includes a sedimentation tank for slurry return and a mud storage tank, which is generally 1.5 to 2.0 times the volume of the borehole. Plastic sheets should be laid on the bottom and around the mud pool or other sealing measures should be taken to prevent the mud from flowing out.
具体而言,制备泥浆的设备有两种:泥浆搅拌机、水力搅拌器。使用粘土粉造浆时优先使用水力搅拌器;使用膨润土造浆时优先使用泥浆搅拌机。Specifically, there are two types of equipment for preparing mud: mud mixer and hydraulic mixer. When using clay powder to make mud, hydraulic mixer is preferred; when using bentonite to make mud, mud mixer is preferred.
造浆后试验全部性能指标,钻孔过程中随时检验泥浆比重和含砂率,并填写泥浆试验记录表,并随时注意地质变化,根据地质情况的变化随时调整泥浆的性能指标,保证泥浆的各项指标符合规范要求。After slurry making, all performance indicators are tested. During the drilling process, the mud density and sand content are checked at any time, and the mud test record form is filled in. Attention is paid to geological changes at any time, and the mud performance indicators are adjusted at any time according to the changes in geological conditions to ensure that all indicators of the mud meet the specifications.
钻孔施工现场设置回收泥浆池用作回收护壁泥浆使用,泥浆经沉淀净化后,输送到储浆池中,在储浆池中进一步处理(加入适量纯碱和CMC改善泥浆性能)经测试合格后重复使用。A recovery mud pool is set up at the drilling construction site to recycle the wall protection mud. After sedimentation and purification, the mud is transported to the slurry storage pool, where it is further processed (adding appropriate amount of soda ash and CMC to improve mud properties) and reused after passing the test.
②钻孔作业②Drilling operation
开孔时,以钻斗自重并加压作为钻进动力,一次进尺短条形柱显示当前钻头的钻孔深度,长条形柱动态显示钻头的运动位置,孔深的数字显示此孔的总深度。当钻斗被挤压充满钻渣后,将其提出地表,操作回转操作手柄使机器转到土方运输车方向的位置,用装载机将钻渣装入土方车,清运至适当地点进行弃方处理。When drilling, the weight and pressure of the drill bucket are used as the drilling power. The short bar column of the one-time footage shows the current drilling depth of the drill bit, the long bar column dynamically shows the movement position of the drill bit, and the number of the hole depth shows the total depth of the hole. When the drill bucket is squeezed and filled with drill cuttings, it is lifted out of the ground, and the rotary operating handle is operated to turn the machine to the position in the direction of the earthwork transport vehicle. The loader is used to load the drill cuttings into the earthwork vehicle and transport them to an appropriate location for disposal.
钻孔过程中根据地质情况控制进尺速度:由硬地层钻到软地层时,适当加快钻进速度;当软地层变为硬地层时,减速慢进;在易缩径的地层中,适当增加扫孔次数,防止缩径;对硬塑层采用快转速钻进,以提高钻进效率;对于砂层,采用慢转速慢钻进并适当增加泥浆比重和粘度。During the drilling process, the penetration speed is controlled according to the geological conditions: when drilling from a hard formation to a soft formation, the drilling speed should be appropriately increased; when the soft formation becomes a hard formation, the drilling speed should be reduced; in the formation that is easy to shrink, the number of hole sweeps should be appropriately increased to prevent shrinkage; for the hard plastic layer, high-speed drilling is used to improve the drilling efficiency; for the sand layer, slow drilling is used and the mud density and viscosity should be appropriately increased.
随着钻进的进行,泥浆不断流入桩孔内,确保桩孔内水位与钢护筒外水位一致。As drilling progresses, mud continuously flows into the pile hole, ensuring that the water level in the pile hole is consistent with the water level outside the steel casing.
S5、溶洞定位、测量,请参照图1和图2,根据地勘报告溶洞位置结合钻进深度进行初步定位,并阻断地面泥浆流入孔内;钻至溶洞具体位置时,孔内泥浆面会迅速下降,此时孔深位置可近似侧壁溶洞顶部标高,根据泥浆面下降高度,测算出溶洞最小容量;再根据地勘报告显示的溶洞底标高结合钻孔岩样判定溶洞近似底标高,近似确定孔侧壁溶洞断面尺寸。S5. Cave positioning and measurement. Please refer to Figures 1 and 2. Preliminary positioning is carried out based on the location of the cave in the geological survey report and the drilling depth, and the mud on the ground is blocked from flowing into the hole. When drilling to the specific location of the cave, the mud surface in the hole will drop rapidly. At this time, the hole depth can be approximated to the top elevation of the side wall cave. According to the height of the mud surface drop, the minimum capacity of the cave is calculated. Then, the approximate bottom elevation of the cave is determined based on the elevation of the cave bottom shown in the geological survey report and the drilled rock samples, and the cross-sectional size of the cave on the side wall of the hole is approximately determined.
S6、钻机钻进至终孔,请参照图1,钻孔达到设计深度后,核实地质情况。通过钻渣与地质柱状图对照结合首桩验收封样的岩样比对,以验证地质情况是否满足设计要求;如与勘测设计资料不符,及时进行确认处理;如满足设计要求,立即对孔深、孔径、孔型进行检查。S6. After the drilling rig has drilled to the final hole, refer to Figure 1. After the hole has reached the designed depth, verify the geological conditions. Compare the drill slag with the geological columnar diagram and the rock sample of the first pile acceptance seal to verify whether the geological conditions meet the design requirements; if they do not match the survey and design data, confirm and deal with them in time; if they meet the design requirements, immediately check the hole depth, hole diameter, and hole shape.
对于孔径、孔壁、垂直度等检测项目采用测孔仪进行检测。A hole gauge is used to test the hole diameter, hole wall, verticality and other inspection items.
孔深及沉渣厚度检测:成孔后,根据旋挖钻显示界面的钻孔深度L1,利用测绳测量孔深L2,两者对比,如果L2小于L1,更换清底钻头,进行清底,并重新测定孔深。Hole depth and sediment thickness detection: After the hole is formed, use a measuring rope to measure the hole depth L2 according to the drilling depth L1 displayed on the rotary drill interface. Compare the two. If L2 is less than L1, replace the bottom cleaning drill bit, clean the bottom, and re-measure the hole depth.
确认满足设计和验标要求后,进行验收,验收合格后,立即进行清孔。After confirming that the design and verification requirements are met, acceptance is carried out. After passing the acceptance, the hole is cleaned immediately.
S7、清孔及验收,请参照图1,湿孔清孔采用换浆法清孔,清孔时需要注意保持孔内水位;干孔沉渣采用沉淀后用平头钻头进行清理。清孔的目的是清除钻渣和沉淀层,减少桩基础底部沉淀厚度,防止桩底存留过厚沉渣而降低桩的承载力。S7. Hole cleaning and acceptance, please refer to Figure 1. Wet hole cleaning adopts slurry replacement method to clean the hole. When cleaning the hole, it is necessary to pay attention to maintaining the water level in the hole; dry hole sediment is cleaned with a flat-head drill bit after sedimentation. The purpose of hole cleaning is to remove drilling debris and sedimentation layer, reduce the sediment thickness at the bottom of the pile foundation, and prevent excessive sediment from remaining at the bottom of the pile to reduce the bearing capacity of the pile.
清孔分两次进行,第一次清孔在钻孔深度达到设计深度后进行,第一次清孔应满足规范要求,否则不下放钢筋笼。The hole cleaning is carried out in two times. The first hole cleaning is carried out after the drilling depth reaches the designed depth. The first hole cleaning should meet the requirements of the specifications, otherwise the steel cage will not be lowered.
待钢筋笼安装到位后下放导管前再进行第二次清孔,灌注混凝土前清孔必须达到以下标准:孔内排出或抽出的泥浆手摸无颗粒感觉,泥浆比重>1.03,含砂率<2%,粘度17~20s;浇筑水下混凝土前桩基础底部沉渣厚度不大于5cm。After the steel cage is installed in place, the hole will be cleaned for the second time before the guide tube is lowered. The hole cleaning before pouring concrete must meet the following standards: the mud discharged or extracted from the hole has no granular feeling when touched, the mud specific gravity is greater than 1.03, the sand content is less than 2%, and the viscosity is 17 to 20s; the thickness of the sediment at the bottom of the pile foundation before pouring underwater concrete is not more than 5cm.
桩基础底部沉渣的测量:采用前端悬挂平砣的测绳在孔壁周围测量孔深,测点不少于4个,两者底标高之差为沉渣厚度,每次测量前采用钢尺对测量绳进行校核。Measurement of sediment at the bottom of pile foundation: Use a measuring rope with a flat weight suspended at the front end to measure the hole depth around the hole wall. There should be no less than 4 measuring points. The difference between the two bottom elevations is the sediment thickness. Use a steel ruler to calibrate the measuring rope before each measurement.
S8、钢筋笼制作运输及安装,请参照图1和图3,根据配筋图制作钢筋笼,按桩孔深度分两段制作,第一节为定长钢筋笼(结合吊机的起吊高度),第二节由桩实际深度确定制作长度。确保钢筋的位置、间距及根数符合图纸的规定和规范要求;主筋焊接相互错开,使35d(d为钢筋直径)范围内的接头数不超过钢筋总数的一半。S8. For the production, transportation and installation of the steel cage, please refer to Figures 1 and 3. The steel cage is produced according to the reinforcement diagram and divided into two sections according to the depth of the pile hole. The first section is a fixed-length steel cage (combined with the lifting height of the crane), and the second section is determined by the actual depth of the pile. Ensure that the position, spacing and number of steel bars meet the requirements of the drawings and specifications; the main bars are welded staggered so that the number of joints within 35d (d is the diameter of the steel bar) does not exceed half of the total number of steel bars.
钢筋笼的螺旋箍筋或加劲筋的接头采用焊接,加劲筋与主筋连接采用点焊,螺旋箍与主筋连接采用绑扎。为防止运输和吊装时钢筋笼变形,对吊点位进行加强处理,对加劲筋进行加密。The joints of the spiral hoops or stiffeners of the steel cage are welded, the connection between the stiffeners and the main bars is spot welding, and the connection between the spiral hoops and the main bars is tied. In order to prevent the steel cage from deforming during transportation and hoisting, the lifting points are strengthened and the stiffeners are encrypted.
若溶洞深度超过4m或者无法判断溶洞体积大小,则在钢筋笼对应溶洞侧壁的外侧固定包裹快易收口网,快易收口网的尺寸大于溶洞的洞口尺寸;使用顶部、底部具有折边的快易收口网,钢筋笼下放至孔内后,使所述折边紧贴孔壁;使用顶部、底部大于侧壁溶洞尺寸至少50cm的快易收口网;使用U型钢筋绑扎快易收口网,并加密所述U型钢筋,沿着快易收口网均匀布设所述U型钢筋。If the depth of the cave exceeds 4m or the size of the cave cannot be determined, a quick-closing net is fixedly wrapped on the outside of the side wall of the cave corresponding to the steel cage, and the size of the quick-closing net is larger than the size of the cave entrance; a quick-closing net with folded edges on the top and bottom is used, and after the steel cage is lowered into the hole, the folded edges are made close to the hole wall; a quick-closing net with a top and bottom that is at least 50cm larger than the size of the side wall cave is used; U-shaped steel bars are used to tie the quick-closing net, and the U-shaped steel bars are denser, and the U-shaped steel bars are evenly arranged along the quick-closing net.
为保证钢筋笼的保护层厚度,在钢筋笼外侧事先焊接U型筋支撑,沿桩长的间距为2m,横向圆周不少于4处。In order to ensure the thickness of the protective layer of the steel cage, U-shaped reinforcement supports are welded in advance on the outside of the steel cage, with a spacing of 2m along the length of the pile and no less than 4 locations on the horizontal circumference.
在加工现场分段制作完成并验收合格后的钢筋笼,运至孔口吊放入孔内,两段钢筋笼连接时采用单面焊,焊接长度为10d(d为钢筋直径)。搬运和吊装时,需要防止变形,安放要对准孔位,避免碰撞孔壁,钢筋笼顶达到设计标高后立即固定,以免浇注混凝土时钢筋笼上浮。整根钢筋笼制作完成后,在钢筋加工场内分段运送至工地。钢筋笼安装前清除粘附的泥土和油渍,保证钢筋与混凝土紧密黏结。After the steel cage is manufactured in sections and accepted at the processing site, it is transported to the hole mouth and hoisted into the hole. The two sections of the steel cage are connected by single-sided welding, and the welding length is 10d (d is the diameter of the steel bar). During transportation and hoisting, it is necessary to prevent deformation, and the placement must be aligned with the hole position to avoid collision with the hole wall. The steel cage top must be fixed immediately after reaching the design elevation to prevent the steel cage from floating when pouring concrete. After the entire steel cage is manufactured, it is transported to the construction site in sections in the steel processing yard. Before installing the steel cage, remove the adhering dirt and oil stains to ensure that the steel bars and concrete are tightly bonded.
S9、下导管,请参照图1和图4,导管安装时逐节量取导管实际长度并按序编号,做好记录以便砼灌注过程中控制埋管深度,需要注意橡皮圈是否安置,检查每段导管两头丝扣无破丝现象,以免灌注过程中出现导管进水的现象。S9. For lowering the conduit, please refer to Figures 1 and 4. When installing the conduit, measure the actual length of each section and number them in sequence. Keep records to control the depth of the buried pipe during concrete pouring. Pay attention to whether the rubber ring is installed and check whether there are any broken threads at both ends of each section of the conduit to avoid water entering the conduit during the pouring process.
S10、二次清孔,请参照图1,导管下放到位后,立即进行桩基础底部沉渣检测,若沉渣厚度不满足设计要求,采用气举反循环二次清孔,循环时注意保持泥浆水头并补充优质泥浆防止塌空,清孔结束检验合格后,立即拆除吸泥弯头。S10. Secondary hole cleaning. Please refer to Figure 1. After the guide tube is lowered into place, immediately check the sediment at the bottom of the pile foundation. If the sediment thickness does not meet the design requirements, use air lift reverse circulation for secondary hole cleaning. During the circulation, pay attention to maintaining the mud head and adding high-quality mud to prevent collapse. After the hole cleaning is completed and the inspection is qualified, immediately remove the mud suction elbow.
S11、水下混凝土灌注,请参照图1和图4,灌注混凝土前对混凝土输送管路及容器洒水润湿,然后在填充导管内安装隔水设施,待储料斗储满混凝土后,开始灌注水下混凝土。S11, underwater concrete pouring, please refer to Figure 1 and Figure 4, before pouring concrete, sprinkle water on the concrete delivery pipeline and container to moisten it, then install water-proof facilities in the filling duct, and after the storage hopper is full of concrete, start pouring underwater concrete.
首批灌注混凝土的数量要能满足导管首次埋置深度至少为1m和填充导管底部高度的需要,封底时导管埋入混凝土中的深度至少为1m,首批混凝土方量是根据桩径和导管埋深及导管内混凝土的方量而定,拌制好的混凝土用砼运输车运至桩基口处,注入钻机提升的料斗内,车内砼方量约8m³,由一人统一指挥,双方都准备好后将隔水栓和阀门同时打开进行封底,隔离栓采用钢板,钢板用细钢丝绳牵引,由塔吊或汽车吊起吊。The quantity of the first batch of poured concrete must be able to meet the needs of the initial buried depth of the conduit of at least 1m and the height of the bottom of the filling conduit. When sealing the bottom, the depth of the conduit buried in the concrete is at least 1m. The volume of the first batch of concrete is determined according to the pile diameter, the buried depth of the conduit and the volume of concrete in the conduit. The mixed concrete is transported to the pile foundation mouth by a concrete transport vehicle and injected into the hopper lifted by the drilling rig. The volume of concrete in the vehicle is about 8m³, which is commanded by one person. After both parties are ready, the watertight plug and the valve are opened at the same time to seal the bottom. The isolation plug is made of steel plate, which is pulled by fine steel wire rope and lifted by a tower crane or a car crane.
①首批混凝土下落后,混凝土连续灌注。在灌注过程中,导管埋置深度控制在2~6m。① After the first batch of concrete falls, the concrete is poured continuously. During the pouring process, the buried depth of the conduit is controlled at 2 to 6 meters.
②灌注混凝土过程中采用重量不小于4kg测锤经常量测孔内混凝土面的上升高度,导管到达一定埋深后,逐级快速拆卸导管,并在每次起升导管前,探测一次孔内混凝土面高度。测量用的测绳在每根桩灌注前后用钢尺校核各一次,避免发生错误。②During the process of pouring concrete, use a hammer with a weight of not less than 4kg to frequently measure the height of the concrete surface in the hole. After the guide tube reaches a certain buried depth, quickly dismantle the guide tube step by step, and detect the height of the concrete surface in the hole before lifting the guide tube each time. The measuring rope used for measurement should be checked with a steel ruler once before and after each pile pouring to avoid errors.
③控制灌注的桩顶标高比设计标高要高出0.3m以上,保证混凝土强度,多余部分桩头进行凿除,确保桩头无松散层。③ The top elevation of the pile to be poured should be controlled to be at least 0.3m higher than the design elevation to ensure the strength of the concrete. The excess part of the pile head should be chiseled off to ensure that there is no loose layer on the pile head.
④灌注完混凝土后,及时将导管、漏斗等进行清理和检查,以备下一孔使用。④ After pouring concrete, clean and inspect the conduit, funnel, etc. in time for use in the next hole.
⑤在灌注水下混凝土前,应填写检查钻孔桩和钢筋笼情况的“相关检测表格”,在浇注水下混凝土的过程中,应填写“水下混凝土浇筑记录”。⑤ Before pouring underwater concrete, the "Related Inspection Form" for checking the conditions of bored piles and steel cages should be filled in, and during the process of pouring underwater concrete, the "Underwater Concrete Pouring Record" should be filled in.
本领域技术人员在考虑说明书及实践这里公开的技术方案后,将容易想到本申请的其它实施方案。本申请旨在涵盖本申请的任何变型、用途或者适应性变化,这些变型、用途或者适应性变化遵循本申请的一般性原理并包括本申请未公开的本技术领域中的公知常识或惯用技术手段。说明书和实施例仅被视为示例性的,本申请的真正范围和精神由权利要求书指出。Those skilled in the art will readily come up with other embodiments of the present application after considering the specification and practicing the technical solutions disclosed herein. The present application is intended to cover any variations, uses or adaptations of the present application, which follow the general principles of the present application and include common knowledge or customary technical means in the art that are not disclosed in the present application. The specification and examples are intended to be exemplary only, and the true scope and spirit of the present application are indicated by the claims.
应当理解的是,本申请并不局限于上面已经描述并在附图中示出的精确结构,并且可以在不脱离其范围进行各种修改和改变。本申请的范围仅由所附的权利要求书来限制。It should be understood that the present application is not limited to the precise structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present application is limited only by the appended claims.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202410320807.7A CN117905050A (en) | 2024-03-20 | 2024-03-20 | Karst area bored pile foundation construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202410320807.7A CN117905050A (en) | 2024-03-20 | 2024-03-20 | Karst area bored pile foundation construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN117905050A true CN117905050A (en) | 2024-04-19 |
Family
ID=90682406
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202410320807.7A Pending CN117905050A (en) | 2024-03-20 | 2024-03-20 | Karst area bored pile foundation construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN117905050A (en) |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109056706A (en) * | 2018-08-03 | 2018-12-21 | 上海宝冶集团有限公司 | A kind of Karst Geological Landscape poured pile base construction method |
| CN113152438A (en) * | 2021-03-30 | 2021-07-23 | 上海建工四建集团有限公司 | Method for constructing pile foundation in karst cave geological environment and pile hole integrated retaining wall |
| CN113981958A (en) * | 2021-11-26 | 2022-01-28 | 中铁十六局集团第四工程有限公司 | Method for plugging karst cave of mechanical pore-forming cast-in-place pile |
| CN116988456A (en) * | 2023-08-28 | 2023-11-03 | 中冶武勘工程技术有限公司 | Anti-overcharging structure for cast-in-place pile in karst area and construction method |
| CN117026943A (en) * | 2023-08-11 | 2023-11-10 | 中冶天工集团有限公司 | Pile-forming method for cast-in-place pile for karst cave stratum |
| CN117626947A (en) * | 2023-12-15 | 2024-03-01 | 中交一公局集团有限公司 | Construction method of bored piles with rotary drill |
-
2024
- 2024-03-20 CN CN202410320807.7A patent/CN117905050A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109056706A (en) * | 2018-08-03 | 2018-12-21 | 上海宝冶集团有限公司 | A kind of Karst Geological Landscape poured pile base construction method |
| CN113152438A (en) * | 2021-03-30 | 2021-07-23 | 上海建工四建集团有限公司 | Method for constructing pile foundation in karst cave geological environment and pile hole integrated retaining wall |
| CN113981958A (en) * | 2021-11-26 | 2022-01-28 | 中铁十六局集团第四工程有限公司 | Method for plugging karst cave of mechanical pore-forming cast-in-place pile |
| CN117026943A (en) * | 2023-08-11 | 2023-11-10 | 中冶天工集团有限公司 | Pile-forming method for cast-in-place pile for karst cave stratum |
| CN116988456A (en) * | 2023-08-28 | 2023-11-03 | 中冶武勘工程技术有限公司 | Anti-overcharging structure for cast-in-place pile in karst area and construction method |
| CN117626947A (en) * | 2023-12-15 | 2024-03-01 | 中交一公局集团有限公司 | Construction method of bored piles with rotary drill |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2022096024A1 (en) | Construction method for super-long small-diameter hole bored pile | |
| CN108894214B (en) | Karst cave geological environment cast-in-place pile and pile-forming construction method thereof | |
| CN112502139A (en) | Construction method for excavation of deep pit by three-axis stirring pile curtain water stop and rotary digging cast-in-place pile support | |
| CN112482395A (en) | Construction method of cast-in-situ bored pile and inner support supporting structure of rail transit station | |
| CN110984221A (en) | Construction method for reinforcing end socket at initial end of air shaft and guide wall structure | |
| CN115217098A (en) | A cast-in-place pile construction technology | |
| CN111395322A (en) | Construction method for rotary digging cast-in-place pile under karst landform | |
| CN110805029A (en) | Subway underground-excavated station drilling and grouting fender post construction method | |
| CN117626947A (en) | Construction method of bored piles with rotary drill | |
| CN113981958A (en) | Method for plugging karst cave of mechanical pore-forming cast-in-place pile | |
| CN107246007A (en) | A kind of construction method CFG | |
| CN105649010A (en) | Grouting pile construction technology | |
| CN116220027A (en) | BIM auxiliary reinforced pile and non-reinforced pile engaged pile construction method | |
| CN115110520A (en) | A construction method of bridge pile foundation on highway | |
| CN109403316A (en) | A kind of manually digging hole combines the pile base construction method of realization with mechanical hole building | |
| CN113914304A (en) | CFG pile long spiral drill hole core pipe pumping mixture pouring pile-forming construction method | |
| CN113404042A (en) | Bridge pile position construction method | |
| CN118704502A (en) | A method for dewatering a deep foundation pit pipe well in a quicksand layer adjacent to an existing building | |
| CN119800957A (en) | A deformation control method for a double-line shield tunnel passing through an existing railway soft soil embankment | |
| CN118774155A (en) | Construction method of dewatering deep foundation pit in pressurized water | |
| CN205224019U (en) | Stake of reinforcing bar fiber cement soil | |
| CN117905050A (en) | Karst area bored pile foundation construction method | |
| CN118375434A (en) | Method for reinforcing earth surface of shield machine section | |
| CN116804324A (en) | Soft soil foundation reinforcing method based on plain concrete piles | |
| CN115110561A (en) | Small-diameter pile foundation construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20240419 |
|
| WD01 | Invention patent application deemed withdrawn after publication |