CN117895376A - Operation method for transferring rod wire under uninterrupted power supply - Google Patents

Operation method for transferring rod wire under uninterrupted power supply Download PDF

Info

Publication number
CN117895376A
CN117895376A CN202410028935.4A CN202410028935A CN117895376A CN 117895376 A CN117895376 A CN 117895376A CN 202410028935 A CN202410028935 A CN 202410028935A CN 117895376 A CN117895376 A CN 117895376A
Authority
CN
China
Prior art keywords
tower
line
pole
pole tower
voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202410028935.4A
Other languages
Chinese (zh)
Inventor
徐勇
周明杰
汪明轩
戴军
施震华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Training Center of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Training Center of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd, Training Center of State Grid Zhejiang Electric Power Co Ltd filed Critical Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority to CN202410028935.4A priority Critical patent/CN117895376A/en
Publication of CN117895376A publication Critical patent/CN117895376A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • H02G1/04Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开了一种不间断供电下迁移杆线的作业方法,包括以下步骤:S100、在迁移线路旁架设与迁移线路同等数量的杆塔,在首杆塔上安装开关,并在首杆塔、末杆塔和第一支线杆塔的导线下方均安装分支横担和直线绝缘子,用以固定从新杆塔延伸过来的导线;S200、判断杆塔是否为耐张杆塔,如果是则跳过本步骤,如果否,则将杆塔改为耐张杆塔;S300、开展带电转移负荷:S500、拆除旧线路。本发明的优点是:不影响分支线路供电,并保障低压线路正常运行,线路迁改完成与迁移线路上杆塔上的装置基本保持不变,装置符合标准。

The present invention discloses a method for relocating poles and lines under uninterrupted power supply, comprising the following steps: S100, erecting the same number of pole towers as the relocated line beside the relocated line, installing switches on the first pole tower, and installing branch cross arms and straight insulators under the conductors of the first pole tower, the last pole tower and the first branch line pole tower to fix the conductors extending from the new pole tower; S200, judging whether the pole tower is a tension pole tower, if yes, skipping this step, if not, changing the pole tower to a tension pole tower; S300, carrying out live load transfer; S500, dismantling the old line. The advantages of the present invention are: it does not affect the power supply of the branch line, and ensures the normal operation of the low-voltage line, the line relocation is completed and the devices on the pole towers on the relocated line remain basically unchanged, and the devices meet the standards.

Description

一种不间断供电下迁移杆线的作业方法A method for migrating poles under uninterrupted power supply

技术领域Technical Field

本发明涉及配电网中线路迁移的方法,具体涉及一种不间断供电下迁移杆线的作业方法。The invention relates to a method for line migration in a distribution network, and in particular to an operation method for migrating pole lines under uninterrupted power supply.

背景技术Background technique

在城市发展、电网建设过程中,时常需要对现有架空线路进行迁改,特别是在杆塔线路因道路施工、市政规划等因素需要小范围迁移杆塔位置和线路路径时,10kV配电线路、杆塔下部0.4kV低压线路不停电情况下完成杆塔移位和线路迁改作业,目前无论是培训教材还是规范制度都未涉及该项作业。In the process of urban development and power grid construction, it is often necessary to relocate existing overhead lines. In particular, when the pole tower position and line path need to be relocated in a small area due to road construction, municipal planning and other factors, the 10kV distribution line and the 0.4kV low-voltage line under the pole tower must be relocated and the line relocation must be completed without power outage. Currently, neither the training materials nor the standard system cover this operation.

发明内容Summary of the invention

本发明的目的在于提供一种不间断供电下迁移杆线的作业方法,能够可有效避免因作业方法不正确、安全措施不到位而造成安全事故,适用于现场各类工况,通过使用绝缘紧线器、移动箱变车和旁路电缆等工具装备有效分隔档距内带电线路和停电线路,确保带电施工与停电施工存在明晰安全界面,以便现场安全有序开展检修施工作业。The purpose of the present invention is to provide an operation method for relocating poles under uninterrupted power supply, which can effectively avoid safety accidents caused by incorrect operation methods and inadequate safety measures. It is applicable to various working conditions on site, and effectively separates the energized lines and the power-off lines within the span by using tools and equipment such as insulated tensioners, mobile box transformers and bypass cables, ensuring a clear and safe interface between energized construction and power-off construction, so that maintenance and construction work can be carried out safely and orderly on site.

为了解决上述技术问题,本发明是通过以下技术方案实现的:In order to solve the above technical problems, the present invention is achieved through the following technical solutions:

一种不间断供电下迁移杆线的作业方法,迁移线路上包括位于头部的首杆塔和位于尾部的末杆塔,迁移线路上还连有支线,支线上与迁移线路最近的杆塔为第一支线杆塔,不间断供电下迁移杆线的作业方法包括以下步骤:A method for relocating a pole line under uninterruptible power supply, wherein the relocation line includes a first pole tower at the head and a last pole tower at the tail, and the relocation line is also connected to a branch line, wherein the pole tower on the branch line closest to the relocation line is a first branch line pole tower, and the method for relocating a pole line under uninterruptible power supply includes the following steps:

S100、在迁移线路旁架设与迁移线路同等数量的杆塔,在首杆塔上安装开关,并在首杆塔、末杆塔和第一支线杆塔的导线下方均安装分支横担和直线绝缘子,用以固定从新杆塔延伸过来的导线;S100. Erect the same number of pole towers as the relocated line beside the relocated line, install switches on the first pole tower, and install branch cross arms and straight insulators under the conductors of the first pole tower, the last pole tower and the first branch line tower to fix the conductors extending from the new pole tower;

S200、判断杆塔是否为耐张杆塔,如果是则跳过本步骤,如果否,则将杆塔改为耐张杆塔;S200, determining whether the pole tower is a tension pole tower, if yes, skipping this step, if no, changing the pole tower to a tension pole tower;

S300、开展带电转移负荷:S300, carry out live load transfer:

S310、使用引线作为耐张杆跳线带电搭接末杆塔新架导线与大号侧导线;S310, use the lead wire as the tension pole jumper to connect the new wire of the end tower with the large side wire;

S320、使用引线作为耐张杆跳线带电搭接第一支线杆塔新架导线与大号侧导线,在新架线路与第一支线杆塔连接的杆塔的跌落式熔断器上下桩头处核对相位是否正确,正确则合上跌落式熔断器;S320, use the lead wire as a tension pole jumper to connect the new wire of the first branch line tower with the large side wire under power, and check whether the phase is correct at the upper and lower piles of the drop-out fuse of the tower connecting the new line and the first branch line tower. If it is correct, close the drop-out fuse;

S330、在首杆塔开关处核对相位是否正确,确认正确后合上开关,并在首杆塔、第一支线杆塔两个点测量新线路和旧线路电流分流情况是否正常;S330, check whether the phase is correct at the switch of the first tower, close the switch after confirming that it is correct, and measure whether the current shunting of the new line and the old line is normal at two points of the first tower and the first branch line tower;

S500、拆除旧线路。S500, dismantle the old line.

优选的,所述步骤S100中首杆塔上开关安装在导线下方2米处。Preferably, in step S100, the switch on the first tower is installed 2 meters below the conductor.

优选的,步骤S200中将杆塔改为耐张杆塔具体步骤为:Preferably, the specific steps of changing the pole tower into a tension pole tower in step S200 are:

S210、在杆塔两侧同时安装绝缘紧线器和卡线器,同时收紧杆塔两侧导线后,使用绝缘引流线连接杆塔大号侧和小号侧,开断导线并将小号侧的尾线固定在新装的耐张绝缘子串耐张线夹内;杆塔大号侧与绝缘紧线器、卡线器连接的绝缘绳套放长0.5~1.5m;杆塔大号侧绝缘紧线器卡线器在安装时与后续新架导线保持足够安装距离,同时卡线器内侧的旧导线可以截断至0.4~0.6m,确保带电导线不会挤压作业空间;S210. Install insulated tensioners and wire clamps on both sides of the tower at the same time. After tightening the conductors on both sides of the tower at the same time, use insulated drain wires to connect the large and small sides of the tower, disconnect the conductors and fix the tail wires on the small side in the tension clamps of the newly installed tension insulator string; lengthen the insulated rope loops connected to the insulated tensioners and wire clamps on the large side of the tower by 0.5 to 1.5 meters; keep the insulated tensioners and wire clamps on the large side of the tower at a sufficient installation distance from the subsequent new wires during installation, and the old wires inside the wire clamps can be cut to 0.4 to 0.6 meters to ensure that the live wires do not squeeze the working space;

S220、在杆塔的分支横担上导线从横担绝缘子上拆除,安装在大号侧主横担耐张绝缘子耐张线夹内,并通过绝缘紧线器工具收紧导线控制弧垂,避免新架导线和原导线交叉,此时新架导线在原导线下方位置,应在做好六根导线绝缘遮蔽基础上保持足够距离;S220. Remove the conductor from the cross-arm insulator on the branch cross-arm of the tower and install it in the tension wire clamp of the large side main cross-arm tension insulator. Use the insulated wire tightener tool to tighten the conductor to control the sag to avoid the new conductor from crossing the original conductor. At this time, the new conductor is located below the original conductor and should be kept at a sufficient distance on the basis of good insulation shielding of the six conductors.

S230、拆除杆塔上的分支横担,在开关两侧安装引线并将引线分别搭接在杆塔小号侧导线和大号侧新架导线上。S230. Remove the branch crossarm on the pole tower, install lead wires on both sides of the switch and connect the lead wires to the conductors on the small side of the pole tower and the newly installed conductors on the large side.

优选的,步骤S220中,杆塔大号侧绝缘紧线器卡线器在安装时需保证紧线器绝缘扁带长度,以便与后续新架导线保持足够安全距离,同时卡线器内侧的旧导线截断至0.5m,用以确保带电导线不会挤压作业空间。Preferably, in step S220, the length of the insulating flat belt of the insulated tensioner on the large side of the tower needs to be ensured during installation so as to maintain a sufficiently safe distance from the subsequent newly installed wires. At the same time, the old wires on the inside of the tensioner are cut off to 0.5m to ensure that the live wires will not squeeze the working space.

优选的,步骤S500拆除旧线路的具体步骤为:Preferably, the specific steps of removing the old line in step S500 are:

S510、拉开迁移线路上与第一支线杆塔对应杆塔上的跌落式熔断器,拆除第一支线杆塔处小号侧绝缘引流线、紧线器和原线路;S510, pull out the drop-out fuse on the pole tower corresponding to the first branch line pole tower on the migration line, and remove the small-side insulated drain wire, tensioner and original line at the first branch line pole tower;

S520、带电拆除末杆塔小号侧绝缘引流线、紧线器和原线路;S520, live removal of the insulated drain wire, tensioner and original line on the small side of the last tower;

S530、带电拆除首杆塔大号侧绝缘引流线、紧线器和原线路。S530, remove the insulated drain wire, tensioner and original line on the large side of the first tower under power.

S540、以上步骤完成后可在不带电状态下拆除迁移线路上其他旧杆塔和线路。S540. After completing the above steps, other old poles and lines on the migration line can be dismantled in a de-energized state.

优选的,如果在迁移线路上有杆塔上安装有变压器,则在步骤S300后增加步骤S400低压线迁移,具体步骤为:Preferably, if a transformer is installed on a tower on the migration line, step S400 of low-voltage line migration is added after step S300, and the specific steps are:

S410、在新架线路上安装低压架空线,并采用带电作业手段与原有低压架空线带电连接,并将原有低压架空线出线用户逐个转移至新架低压架空线上,带电断开与旧低压线路的连接;S410, install low-voltage overhead lines on the new lines, and use live working methods to connect them to the original low-voltage overhead lines, and transfer the original low-voltage overhead line users one by one to the new low-voltage overhead lines, and disconnect them from the old low-voltage lines;

S420、使用移动箱变车临时取电,高压电缆连接至新架导线上,低压电缆连接至新架低压线上,确认移动箱变车低压出线开关处具备同期并网条件后合上低压开关,此时低压负荷同时由4#杆变压器和移动箱变车供给;S420, use a mobile box transformer to temporarily draw power, connect the high-voltage cable to the new rack conductor, and connect the low-voltage cable to the new rack low-voltage line. After confirming that the low-voltage outlet switch of the mobile box transformer meets the synchronous grid connection conditions, close the low-voltage switch. At this time, the low-voltage load is supplied by the 4# pole transformer and the mobile box transformer at the same time;

S430、带电拆除杆塔上变压器高低压侧出线,并将变压器转移至新线路上对应的杆塔上,搭接变压器高低压侧出线至高低压新架线路,并核对变压器低压开关处相位并合闸;S430, remove the high and low voltage outgoing wires on the tower of the transformer under power, and transfer the transformer to the corresponding tower on the new line, connect the high and low voltage outgoing wires on the transformer to the new high and low voltage lines, and check the phase of the low voltage switch of the transformer and close it;

S440、依次拉开移动箱变车低压侧开关、高压侧开关,并带电拆除高低压电缆,该步骤工作完成。S440, pull open the low-voltage side switch and high-voltage side switch of the mobile box transformer in sequence, and remove the high and low voltage cables under power. This step is completed.

与现有技术相比,本发明的优点是:Compared with the prior art, the advantages of the present invention are:

一是可以安全有效区分带电设备和停电设备,确保在停电状态下完成新杆线安装,通过带电作业完成新杆线投入运行和旧杆线退出运行,同样在停电状态下完成旧杆线拆除。同时不影响分支线路供电,并保障低压线路正常运行。First, it can safely and effectively distinguish between live equipment and power-off equipment, ensure that new poles and lines are installed in a power-off state, put new poles and lines into operation and old poles and lines out of operation through live work, and also dismantle old poles and lines in a power-off state. At the same time, it does not affect the power supply of branch lines and ensures the normal operation of low-voltage lines.

二是该方法不同于常规旁路作业需要敷设大量旁路电缆等设备,采用就地取材新架空线路作为“旁路系统”完成新旧杆线的负荷转移工作,同时采用卡线器临时固定导线的方式保障了新架线路与旧线路的距离,避免发生相间短路事故发生,使得线路迁改完成与迁移线路上杆塔上的装置基本保持不变,装置符合标准。Secondly, this method is different from conventional bypass operations that require the laying of a large number of bypass cables and other equipment. It uses new overhead lines made from local materials as a "bypass system" to complete the load transfer between the old and new poles. At the same time, it uses wire clamps to temporarily fix the conductors to ensure the distance between the new and old lines, avoiding phase-to-phase short-circuit accidents. As a result, the line relocation is completed and the devices on the poles and towers on the relocated lines remain basically unchanged, and the devices meet the standards.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本发明的流程图。FIG. 1 is a flow chart of the present invention.

具体实施方式Detailed ways

下面详细描述本发明的实施例,所述实施例的示例在附图中示出。下面通过参考附图描述的实施例是示例性的,旨在用于解释本发明,而不能理解为对本发明的限制。Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括至少一个该特征。在本发明的描述中,“多个”的含义是至少两个,例如两个,三个等,除非另有明确具体的限定。In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接或彼此可通讯;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系,除非另有明确的限定。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

参阅图1为本发明一种不间断供电下迁移杆线的作业方法的实施例,迁移线路上包括位于头部的首杆塔和位于尾部的末杆塔,迁移线路上还连有支线,支线上与迁移线路最近的杆塔为第一支线杆塔,不间断供电下迁移杆线的作业方法包括以下步骤:Referring to FIG. 1, an embodiment of a method for relocating a pole line under uninterruptible power supply of the present invention is shown. The relocation line includes a first pole tower at the head and a last pole tower at the tail. The relocation line is also connected to a branch line. The pole tower on the branch line closest to the relocation line is the first branch line pole tower. The method for relocating a pole line under uninterruptible power supply includes the following steps:

S100、在迁移线路旁架设与迁移线路同等数量的杆塔,不带电的情况下先立杆塔并安装柱上设备,新立杆塔上的设备与待迁移线路上对应杆塔上设备一致;在首杆塔上安装开关,首杆塔上开关安装在导线下方2米处,并在首杆塔、末杆塔和第一支线杆塔的导线下方1.5m处均安装分支横担和直线绝缘子,用以固定从新杆塔延伸过来的导线;S100. Erect the same number of poles and towers as the relocated line. First erect the poles and install the pole-mounted equipment without power. The equipment on the newly erected poles and towers should be consistent with the equipment on the corresponding poles and towers on the line to be relocated. Install switches on the first pole and the switch on the first pole should be installed 2 meters below the conductor. Install branch cross arms and straight insulators 1.5 meters below the conductor on the first pole, the last pole and the first branch pole to fix the conductor extending from the new pole.

S200、判断杆塔是否为耐张杆塔,如果是则跳过本步骤,如果否,则将杆塔改为耐张杆塔;S200, determining whether the pole tower is a tension pole tower, if yes, skipping this step, if no, changing the pole tower to a tension pole tower;

S210、在杆塔两侧同时安装绝缘紧线器和卡线器,同时收紧杆塔两侧导线后,使用绝缘引流线连接杆塔大号侧和小号侧,(如果是绝缘导线则需要剥除绝缘层),开断导线并将小号侧的尾线固定在新装的耐张绝缘子串耐张线夹内;杆塔大号侧与绝缘紧线器、卡线器连接的绝缘绳套放长0.5~1.5m;杆塔大号侧绝缘紧线器卡线器在安装时尽量靠外,以便与后续新架导线保持足够安装距离,同时卡线器内侧的旧导线可以截断至0.4~0.6m,这样可以确保带电导线不会挤压作业空间;S210. Install insulated tensioners and wire clamps on both sides of the tower at the same time. After tightening the wires on both sides of the tower at the same time, use an insulated drain wire to connect the large and small sides of the tower (if it is an insulated wire, the insulation layer needs to be stripped off), disconnect the wire and fix the tail wire on the small side in the newly installed tension insulator string tension clamp; the insulated rope loop connected to the insulated tensioner and wire clamp on the large side of the tower is lengthened by 0.5 to 1.5 meters; the insulated tensioner and wire clamp on the large side of the tower should be installed as far out as possible to keep a sufficient installation distance from the subsequent new wires. At the same time, the old wire inside the wire clamp can be cut off to 0.4 to 0.6 meters, so as to ensure that the live wire will not squeeze the working space;

S220、在杆塔的分支横担上导线从横担绝缘子上拆除,安装在大号侧主横担耐张绝缘子耐张线夹内,并通过绝缘紧线器工具收紧导线控制弧垂,避免新架导线和原导线交叉,此时新架导线在原导线下方位置,应在做好六根导线绝缘遮蔽基础上保持足够距离;S220. Remove the conductor from the cross-arm insulator on the branch cross-arm of the tower and install it in the tension wire clamp of the large side main cross-arm tension insulator. Use the insulated wire tightener tool to tighten the conductor to control the sag to avoid the new conductor from crossing the original conductor. At this time, the new conductor is located below the original conductor and should be kept at a sufficient distance on the basis of good insulation shielding of the six conductors.

S230、拆除杆塔上的分支横担,在开关两侧安装引线并将引线分别搭接在杆塔小号侧导线和大号侧新架导线上;S230, remove the branch crossarm on the tower, install the lead wires on both sides of the switch and connect the lead wires to the small side conductor and the large side new frame conductor of the tower respectively;

S300、开展带电转移负荷;S300, carry out live load transfer;

S310、使用引线作为耐张杆跳线带电搭接末杆塔新架导线与大号侧导线;S310, use the lead wire as the tension pole jumper to connect the new wire of the end tower with the large side wire;

S320、使用引线作为耐张杆跳线带电搭接第一支线杆塔新架导线与大号侧导线,在新架线路与第一支线杆塔连接的杆塔的跌落式熔断器上下桩头处核对相位是否正确,正确则合上跌落式熔断器;S320, use the lead wire as a tension pole jumper to connect the new wire of the first branch line tower with the large side wire under power, and check whether the phase is correct at the upper and lower piles of the drop-out fuse of the tower connecting the new line and the first branch line tower. If it is correct, close the drop-out fuse;

S330、在首杆塔开关处核对相位是否正确,确认正确后合上开关,并在首杆塔、第一支线杆塔两个点测量新线路和旧线路电流分流情况是否正常,占总电流1/4~3/4;S330, check whether the phase is correct at the switch of the first tower, close the switch after confirming that it is correct, and measure whether the current shunting of the new line and the old line is normal at two points of the first tower and the first branch line tower, accounting for 1/4 to 3/4 of the total current;

S500、拆除旧线路:S500, dismantling old lines:

S510、拉开迁移线路上与第一支线杆塔对应杆塔上的跌落式熔断器,拆除第一支线杆塔处小号侧绝缘引流线、紧线器和原线路;S510, pull out the drop-out fuse on the pole tower corresponding to the first branch line pole tower on the migration line, and remove the small-side insulated drain wire, tensioner and original line at the first branch line pole tower;

S520、带电拆除末杆塔小号侧绝缘引流线、紧线器和原线路;S520, live removal of the insulated drain wire, tensioner and original line on the small side of the last tower;

S530、带电拆除首杆塔大号侧绝缘引流线、紧线器和原线路。S530, remove the insulated drain wire, tensioner and original line on the large side of the first tower under power.

S540、以上步骤完成后可在不带电状态下拆除迁移线路上其他旧杆塔和线路。S540. After completing the above steps, other old poles and lines on the migration line can be dismantled in a de-energized state.

如果在迁移线路上有杆塔上安装有变压器,则在步骤S300后增加步骤S400低压线迁移,具体步骤为:If there is a transformer installed on a tower on the migration line, step S400 of low-voltage line migration is added after step S300. The specific steps are as follows:

S410、在新架线路上安装低压架空线,并采用带电作业手段与原有低压架空线带电连接,并将原有低压架空线出线用户逐个转移至新架低压架空线上,带电断开与旧低压线路的连接;S410, install low-voltage overhead lines on the new lines, and use live working methods to connect them to the original low-voltage overhead lines, and transfer the original low-voltage overhead line users one by one to the new low-voltage overhead lines, and disconnect them from the old low-voltage lines;

S420、使用移动箱变车临时取电,高压电缆连接至新架导线上,低压电缆连接至新架低压线上,确认移动箱变车低压出线开关处具备同期并网条件后合上低压开关,此时低压负荷同时由4#杆变压器和移动箱变车供给;S420, use a mobile box transformer to temporarily draw power, connect the high-voltage cable to the new rack conductor, and connect the low-voltage cable to the new rack low-voltage line. After confirming that the low-voltage outlet switch of the mobile box transformer meets the synchronous grid connection conditions, close the low-voltage switch. At this time, the low-voltage load is supplied by the 4# pole transformer and the mobile box transformer at the same time;

S430、带电拆除杆塔上变压器高低压侧出线,并将变压器转移至新线路上对应的杆塔上,搭接变压器高低压侧出线至高低压新架线路,并核对变压器低压开关处相位并合闸;S430, remove the high and low voltage outgoing wires on the tower of the transformer under power, and transfer the transformer to the corresponding tower on the new line, connect the high and low voltage outgoing wires on the transformer to the new high and low voltage lines, and check the phase of the low voltage switch of the transformer and close it;

S440、依次拉开移动箱变车低压侧开关、高压侧开关,并带电拆除高低压电缆,该步骤工作完成。S440, pull open the low-voltage side switch and high-voltage side switch of the mobile box transformer in sequence, and remove the high and low voltage cables under power. This step is completed.

采用上述方案进行不间断供电下迁移杆线的作业可以安全有效区分带电设备和停电设备,确保在停电状态下完成新杆线安装,通过带电作业完成新杆线投入运行和旧杆线退出运行,同样在停电状态下完成旧杆线拆除。同时不影响分支线路供电,并保障低压线路正常运行。该方法不同于常规旁路作业需要敷设大量旁路电缆等设备,采用就地取材新架空线路作为“旁路系统”完成新旧杆线的负荷转移工作,同时采用卡线器临时固定导线的方式保障了新架线路与旧线路的距离,避免发生相间短路事故发生,使得线路迁改完成与迁移线路上杆塔上的装置基本保持不变,装置符合标准。The above scheme can be used to relocate poles and lines under uninterrupted power supply to safely and effectively distinguish between live equipment and power-off equipment, ensure that new poles and lines are installed under power outage conditions, put new poles and lines into operation and old poles and lines out of operation through live operations, and also remove old poles and lines under power outage conditions. At the same time, it does not affect the power supply of branch lines and ensures the normal operation of low-voltage lines. This method is different from conventional bypass operations that require the laying of a large number of bypass cables and other equipment. It uses local materials to lay new overhead lines as a "bypass system" to complete the load transfer work between the new and old poles and lines. At the same time, the wire clamp is used to temporarily fix the conductor to ensure the distance between the new line and the old line, avoiding phase-to-phase short circuit accidents, so that the line relocation is completed and the devices on the pole towers on the relocated line remain basically unchanged, and the devices meet the standards.

以上所述仅为本发明的具体实施例,但本发明的技术特征并不局限于此,任何本领域的技术人员在本发明的领域内,所作的变化或修饰皆涵盖在本发明的专利范围之中。The above description is only a specific embodiment of the present invention, but the technical features of the present invention are not limited thereto. Any changes or modifications made by any technician in the field of the present invention are included in the patent scope of the present invention.

Claims (6)

1.一种不间断供电下迁移杆线的作业方法,迁移线路上包括位于头部的首杆塔和位于尾部的末杆塔,迁移线路上还连有支线,支线上与迁移线路最近的杆塔为第一支线杆塔,其特征在于,不间断供电下迁移杆线的作业方法包括以下步骤:1. A method for relocating a pole line under uninterruptible power supply, wherein the relocation line includes a first pole tower at the head and a last pole tower at the tail, and the relocation line is also connected to a branch line, and the pole tower on the branch line closest to the relocation line is a first branch line pole tower, characterized in that the method for relocating a pole line under uninterruptible power supply includes the following steps: S100、在迁移线路旁架设与迁移线路同等数量的杆塔,在首杆塔上安装开关,并在首杆塔、末杆塔和第一支线杆塔的导线下方均安装分支横担和直线绝缘子,用以固定从新杆塔延伸过来的导线;S100. Erect the same number of pole towers as the relocated line, install switches on the first pole tower, and install branch cross arms and straight insulators under the conductors of the first pole tower, the last pole tower and the first branch line tower to fix the conductors extending from the new pole tower; S200、判断杆塔是否为耐张杆塔,如果是则跳过本步骤,如果否,则将杆塔改为耐张杆塔;S200, determining whether the pole tower is a tension pole tower, if yes, skipping this step, if no, changing the pole tower to a tension pole tower; S300、开展带电转移负荷:S300, carry out live load transfer: S310、使用引线作为耐张杆跳线带电搭接末杆塔新架导线与大号侧导线;S320、使用引线作为耐张杆跳线带电搭接第一支线杆塔新架导线与大号侧导线,在新架线路与第一支线杆塔连接的杆塔的跌落式熔断器上下桩头处核对相位是否正确,正确则合上跌落式熔断器;S310, use the lead wire as a tension pole jumper to connect the new wire of the end tower with the large side wire; S320, use the lead wire as a tension pole jumper to connect the new wire of the first branch line tower with the large side wire, and check whether the phase is correct at the upper and lower piles of the drop-out fuse of the tower connecting the new line and the first branch line tower. If it is correct, close the drop-out fuse; S330、在首杆塔开关处核对相位是否正确,确认正确后合上开关,并在首杆塔、第一支线杆塔两个点测量新线路和旧线路电流分流情况是否正常;S330, check whether the phase is correct at the switch of the first tower, close the switch after confirming that it is correct, and measure whether the current shunting of the new line and the old line is normal at two points of the first tower and the first branch line tower; S500、拆除旧线路。S500, dismantle the old line. 2.如权利要求1所述的一种不间断供电下迁移杆线的作业方法,其特征在于,所述步骤S100中首杆塔上开关安装在导线下方2米处。2. A method for relocating poles and lines under uninterruptible power supply as described in claim 1, characterized in that in step S100, the switch on the first pole tower is installed 2 meters below the conductor. 3.如权利要求1所述的一种不间断供电下迁移杆线的作业方法,其特征在于,步骤S200中将杆塔改为耐张杆塔具体步骤为:3. The method for relocating poles under uninterruptible power supply as claimed in claim 1, characterized in that the specific steps of changing the pole tower into a tension pole tower in step S200 are: S210、在杆塔两侧同时安装绝缘紧线器和卡线器,同时收紧杆塔两侧导线后,使用绝缘引流线连接杆塔大号侧和小号侧,开断导线并将小号侧的尾线固定在新装的耐张绝缘子串耐张线夹内;杆塔大号侧与绝缘紧线器、卡线器连接的绝缘绳套放长0.5~1.5m;杆塔大号侧绝缘紧线器卡线器在安装时与后续新架导线保持足够安装距离,同时卡线器内侧的旧导线可以截断至0.4~0.6m,确保带电导线不会挤压作业空间;S210. Install insulated tensioners and wire clamps on both sides of the tower at the same time. After tightening the conductors on both sides of the tower at the same time, use insulated drain wires to connect the large and small sides of the tower, disconnect the conductors and fix the tail wires on the small side in the tension clamps of the newly installed tension insulator string; lengthen the insulated rope loops connected to the insulated tensioners and wire clamps on the large side of the tower by 0.5 to 1.5 meters; keep the insulated tensioners and wire clamps on the large side of the tower at a sufficient installation distance from the subsequent new wires during installation, and the old wires inside the wire clamps can be cut to 0.4 to 0.6 meters to ensure that the live wires do not squeeze the working space; S220、在杆塔的分支横担上导线从横担绝缘子上拆除,安装在大号侧主横担耐张绝缘子耐张线夹内,并通过绝缘紧线器工具收紧导线控制弧垂,避免新架导线和原导线交叉,此时新架导线在原导线下方位置,在做好六根导线绝缘遮蔽基础上保持足够距离;S220. Remove the conductor from the cross-arm insulator on the branch cross-arm of the tower and install it in the tension wire clamp of the large side main cross-arm tension insulator. Use the insulation tensioner tool to tighten the conductor to control the sag to avoid the new conductor from crossing the original conductor. At this time, the new conductor is located below the original conductor and maintains a sufficient distance on the basis of insulation shielding of the six conductors. S230、拆除杆塔上的分支横担,在开关两侧安装引线并将引线分别搭接在杆塔小号侧导线和大号侧新架导线上。S230. Remove the branch crossarm on the pole tower, install lead wires on both sides of the switch and connect the lead wires to the conductors on the small side of the pole tower and the newly installed conductors on the large side. 4.如权利要求3所述的一种不间断供电下迁移杆线的作业方法,其特征在于,步骤S220中,杆塔大号侧绝缘紧线器卡线器在安装时需保证紧线器绝缘扁带长度,以便与后续新架导线保持足够安全距离,同时卡线器内侧的旧导线截断至0.5m,用以确保带电导线不会挤压作业空间。4. A method for relocating poles and lines under uninterrupted power supply as described in claim 3, characterized in that in step S220, the length of the insulating flat belt of the wire tensioner on the large side of the pole tower must be ensured during installation so as to maintain a sufficiently safe distance from the subsequent newly installed wires, and at the same time, the old wires on the inner side of the wire gripper are cut off to 0.5m to ensure that the live wires will not squeeze the working space. 5.如权利要求1所述的一种不间断供电下迁移杆线的作业方法,其特征在于,步骤S500拆除旧线路的具体步骤为:5. The method for relocating poles and lines under uninterrupted power supply as claimed in claim 1, wherein the specific steps of removing the old line in step S500 are: S510、拉开迁移线路上与第一支线杆塔对应杆塔上的跌落式熔断器,拆除第一支线杆塔处小号侧绝缘引流线、紧线器和原线路;S510, pull out the drop-out fuse on the pole tower corresponding to the first branch line pole tower on the migration line, and remove the small-side insulated drain wire, tensioner and original line at the first branch line pole tower; S520、带电拆除末杆塔小号侧绝缘引流线、紧线器和原线路;S520, live removal of the insulated drain wire, tensioner and original line on the small side of the last tower; S530、带电拆除首杆塔大号侧绝缘引流线、紧线器和原线路。S530, remove the insulated drain wire, tensioner and original line on the large side of the first tower under power. S540、以上步骤完成后可在不带电状态下拆除迁移线路上其他旧杆塔和线路。S540. After completing the above steps, other old poles and lines on the migration line can be dismantled in a de-energized state. 6.如权利要求1所述的一种不间断供电下迁移杆线的作业方法,其特征在于,如果在迁移线路上有杆塔上安装有变压器,则在步骤S300后增加步骤S400低压线迁移,具体步骤为:6. A method for relocating poles and lines under uninterruptible power supply as claimed in claim 1, characterized in that if a transformer is installed on a pole tower on the relocation route, a step S400 of low-voltage line relocation is added after step S300, and the specific steps are: S410、在新架线路上安装低压架空线,并采用带电作业手段与原有低压架空线带电连接,并将原有低压架空线出线用户逐个转移至新架低压架空线上,带电断开与旧低压线路的连接;S410, install low-voltage overhead lines on the new lines, and use live working methods to connect them to the original low-voltage overhead lines, and transfer the original low-voltage overhead line users one by one to the new low-voltage overhead lines, and disconnect them from the old low-voltage lines; S420、使用移动箱变车临时取电,高压电缆连接至新架导线上,低压电缆连接至新架低压线上,确认移动箱变车低压出线开关处具备同期并网条件后合上低压开关,此时低压负荷同时由4#杆变压器和移动箱变车供给;S430、带电拆除杆塔上变压器高低压侧出线,并将变压器转移至新线路上对应的杆塔上,搭接变压器高低压侧出线至高低压新架线路,并核对变压器低压开关处相位并合闸;S420, use a mobile box transformer to temporarily draw power, connect the high-voltage cable to the new wire, and the low-voltage cable to the new low-voltage line. After confirming that the low-voltage outlet switch of the mobile box transformer has the conditions for synchronous grid connection, close the low-voltage switch. At this time, the low-voltage load is supplied by the 4# pole transformer and the mobile box transformer at the same time; S430, remove the high- and low-voltage side outlets of the transformer on the pole tower under power, and transfer the transformer to the corresponding pole tower on the new line, connect the high- and low-voltage side outlets of the transformer to the high- and low-voltage new lines, and check the phase at the low-voltage switch of the transformer and close the switch; S440、依次拉开移动箱变车低压侧开关、高压侧开关,并带电拆除高低压电缆,该步骤工作完成。S440, pull open the low-voltage side switch and high-voltage side switch of the mobile box transformer in sequence, and remove the high and low voltage cables under power. This step is completed.
CN202410028935.4A 2024-01-08 2024-01-08 Operation method for transferring rod wire under uninterrupted power supply Withdrawn CN117895376A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410028935.4A CN117895376A (en) 2024-01-08 2024-01-08 Operation method for transferring rod wire under uninterrupted power supply

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410028935.4A CN117895376A (en) 2024-01-08 2024-01-08 Operation method for transferring rod wire under uninterrupted power supply

Publications (1)

Publication Number Publication Date
CN117895376A true CN117895376A (en) 2024-04-16

Family

ID=90643972

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410028935.4A Withdrawn CN117895376A (en) 2024-01-08 2024-01-08 Operation method for transferring rod wire under uninterrupted power supply

Country Status (1)

Country Link
CN (1) CN117895376A (en)

Similar Documents

Publication Publication Date Title
KR101103553B1 (en) Uninterrupted Bypass Method for Distribution Lines Using Insulating Guiders for Space Maintenance
KR101777080B1 (en) Uninterrupted power distribution method in which wires are separated in de-energized power lines state by using insulated live wire grip and bypass jumper cables
CN101888073A (en) On-load opened and segmented operating method of 10kV line
CN203734209U (en) Live working device for cable bypass
US20170338633A1 (en) Quick connect and disconnect cable junction box
CN105298201A (en) Electric-transmission-line cable-terminal three-dimensional downwards-leading device
CN208078525U (en) Three-phase conducting wire for distribution network live line work upright bar struts insulating frame
CN105445567B (en) The nuclear-phase method of totally enclosed type generalized information system
CN202535016U (en) OPGW pull-in optical cable safety grounding fixing assembly
CN110380340B (en) Substation power distribution device
CN117895376A (en) Operation method for transferring rod wire under uninterrupted power supply
CN114362041B (en) Method for changing straight line rod into tension rod and hardware fitting for changing straight line rod into tension rod
CN117673966A (en) Long-distance large-section single-core cable laying construction method
US20210362613A1 (en) Electric vehicle charging station for connecting to high or extra high voltage transmission line and operation method thereof
KR20230124873A (en) Line construction method
CN210779513U (en) Power distribution device of transformer substation
CN115377862A (en) A bypass cable fixing operation method
CN114614399B (en) Operating method for on-load migration tension rod
CN107386771A (en) Cable type double back steel pipe rod-type terminal tower before and after a kind of 110kV overhead transmission lines
Hagh et al. Design and installation of first 20 kV spacer cable in Iran
JP5788033B2 (en) Overhead power transmission line support structure
CN111817288A (en) A site layout method and structure applied to a true-type test platform for distribution network
CN220628851U (en) Wire and cable's wiring device
CN104577928B (en) Three-phase aerial condutor
CN2864716Y (en) Terminal joint case for optical fiber composite phase wire

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20240416

WW01 Invention patent application withdrawn after publication