CN117823173A - Shell discarding process and machine head for shell discarding process - Google Patents

Shell discarding process and machine head for shell discarding process Download PDF

Info

Publication number
CN117823173A
CN117823173A CN202310660822.1A CN202310660822A CN117823173A CN 117823173 A CN117823173 A CN 117823173A CN 202310660822 A CN202310660822 A CN 202310660822A CN 117823173 A CN117823173 A CN 117823173A
Authority
CN
China
Prior art keywords
shell
machine head
discarding process
pipe joint
driving device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310660822.1A
Other languages
Chinese (zh)
Inventor
张志勇
王建平
王中兵
闪耀
林成峰
张志刚
舒鹏
杨谊儒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Juding Engineering Technology Co ltd
Original Assignee
Shanghai Juding Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Juding Engineering Technology Co ltd filed Critical Shanghai Juding Engineering Technology Co ltd
Priority to CN202310660822.1A priority Critical patent/CN117823173A/en
Publication of CN117823173A publication Critical patent/CN117823173A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The application relates to the technical field of pipe jacking engineering, and particularly discloses a shell discarding process and a machine head for the shell discarding process. The shell discarding process comprises the following steps: step one: the concrete prefabricated pipe joint is used for replacing part or all of the machine head steel plate structure, and the cutter head driving device and related components in the machine head are arranged on the machine head through the embedded part; step two: carrying out pipe jacking construction; step three: and removing and recycling the cutterhead and the driving mechanism. A head for the above described shell discarding process, comprising: prefabricating a pipe joint by using concrete; the cutterhead driving device and the machine head assembly mounting frame are arranged at the end part of the concrete prefabricated pipe joint and are detachably connected with the concrete prefabricated pipe joint; the cutter head assembly is arranged at the ends of the cutter head driving device and the machine head assembly mounting frame; and the driving assembly is arranged on the cutterhead driving device and the machine head assembly mounting frame and is used for driving the cutterhead assembly to work. The shell discarding process is simple in construction process, convenient to realize, high in construction efficiency, and capable of reducing waste of machine head steel, reducing construction cost and being beneficial to improving structural compactness and supportability of machine head pipe joints.

Description

Shell discarding process and machine head for shell discarding process
Technical Field
The invention relates to the technical field of pipe jacking engineering, in particular to a shell discarding process and a machine head for the shell discarding process.
Background
A pipe jacking engineering is a sub-subject in non-excavation engineering or a non-excavation engineering construction technology, which is a technology for constructing pipelines through auxiliary equipment by adopting non-excavation surface layers and being capable of penetrating roads, railways, river, ground buildings, underground structures, various underground pipelines and the like. The common process has an initial working well and a receiving well, but some special working conditions have no receiving well, so the shell discarding process is utilized to meet the engineering requirements. The machine head shell is used as an outer mold for secondary reinforced concrete lining pouring, but firstly, the machine parts, the cutter head and the driving system in the machine head are removed, then the steel components in the machine shell are treated, and after the process is finished, the structural construction procedures such as steel bar binding, formwork erection, concrete pouring and tamping are carried out.
After the working machine head is jacked into the design mileage and requirements, the driving system, the hinging system, the power disc and the electrical cabinet of the machine head are dismantled, the front chest plate is dismantled, the rib plates in the machine shell are cut off according to the design after the dismantled workpieces are cleared, the binding condition of the reinforcing steel bars is met, the outer shell of the machine is utilized as an outer mold of the structure, the whole process construction of the structure of the box culvert in the machine shell section is complicated, the working procedures are more, the local compactness of concrete is insufficient due to the limitation of the process conditions, the structure quality is influenced, and the whole construction period is longer.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the invention provides a shell discarding process and a machine head for the shell discarding process, which have the advantage of reducing cost, and solve the problems that the whole process construction is complicated, the working procedures are more, the local compactness of concrete is insufficient due to the limitation of process conditions, the structure quality is influenced, the waste of materials (shell steel plates) is caused, and the whole construction period is longer.
(II) technical scheme
In order to achieve the above purpose, the present invention provides the following technical solutions:
in a first aspect, the present application discloses a shell discarding process comprising the steps of:
step one: the concrete prefabricated pipe joint is used for replacing part or all of the machine head steel plate structure, and the cutter head, the driving device and related components in the machine head are arranged on the machine head through the embedded part;
step two: carrying out pipe jacking construction;
step three: and removing and recycling the cutterhead and the driving mechanism.
Optionally, the shell discarding process further comprises the steps of reinforcing and waterproofing the peripheral soil body.
Optionally, the peripheral soil body is reinforced and waterproof by adopting a freezing method.
Optionally, the well point water-reducing method is adopted to strengthen the surrounding soil body and waterproof construction.
Optionally, the peripheral soil body is reinforced and waterproof by adopting a high-pressure jet grouting pile method.
Optionally, the peripheral soil body is reinforced and waterproof by adopting a compaction grouting method.
Optionally, several combinations of freezing method, well point dewatering method, high-pressure jet grouting pile and compaction grouting method are adopted to strengthen and waterproof the surrounding land.
Optionally, the shell discarding process further comprises the steps of monitoring, measuring and rectifying the position of the machine head in the jacking process of the machine head.
Optionally, the step one further includes: and measuring the structural size of the head steel plate, and preparing the concrete prefabricated pipe joint according to the size of the head, wherein in the preparation process, an embedded part is arranged in advance so as to facilitate the installation of a follow-up cutter head.
Optionally, the jacking pipe construction in the second step includes, but is not limited to, the following steps:
1) Forming a foundation pit (a working well);
2) Measuring and positioning;
3) And (3) equipment installation:
back mounting: forming a back wall, and vertically placing a back steel plate in front of the back wall on the ground;
and (3) guide rail installation: the two guide rails are laid below the pipe jacking path in parallel to limit the jacking direction of the pipeline;
mounting a hydraulic jack bracket: a driving device is arranged on the foundation pit and is used for driving the hydraulic jack bracket; connecting a hydraulic jack bracket with the driving device by adopting a high-pressure oil pipe, and placing the jack bracket between two guide rails for fixing;
4) The heading machine is in place: placing the heading machine on a guide rail in a foundation pit;
5) And (3) positioning the push bench: the rear end of the push bench is propped against the front side of the back steel plate;
6) Pipeline (pipe joint) installation:
hoisting the pipeline (pipe joint) by using a hanging strip, and slowly hoisting the pipeline (pipe joint) to a working platform at the bottom of the foundation pit;
7) Jacking construction:
the pipe jacking tunneling machine is used for tunneling, the tunneling machine cuts and discharges earth and stones in front of the pipe, the pipe is pushed forward along with the tunneling machine, the jacking system of the pipe jacking machine is retracted when the pipe is pushed to a set position, and meanwhile, the tunneling machine stops acting and is used for pipe joint discharging;
8) Repeating the steps 6) and 7) until all the pipelines are jacked in place.
Optionally, the shell discarding process further comprises a process of constructing corrosion resistance and waterproof protection at the joint of the two connected concrete pipe joints.
Optionally, the waterproof material of the joint seam of the pipe joint is an anti-corrosion and anti-aging EPDM elastic rubber sealing strip.
Optionally, the shell discarding process further comprises a process of constructing corrosion-resistant and waterproof protection on the connecting piece holes between the connected beam concrete pipe joints.
Optionally, the waterproof material of the connecting piece hole is an anti-corrosion, anti-aging and water-swelling rubber sealing ring.
In a second aspect, the present application discloses a hand piece for use in the shell discarding process of the first aspect, comprising:
prefabricating a pipe joint by using concrete;
the cutterhead driving device and the machine head assembly mounting frame are arranged at the end part of the concrete prefabricated pipe joint and are detachably connected with the concrete prefabricated pipe joint;
the cutter head assembly is arranged at the ends of the cutter head driving device and the machine head assembly mounting frame; and
and the driving assembly is arranged on the cutterhead driving device and the machine head assembly mounting frame and used for driving the cutterhead assembly to work.
Optionally, the prefabricated tube coupling tip of concrete is provided with the built-in fitting, the prefabricated tube coupling of concrete passes through built-in fitting is connected with blade disc drive arrangement and aircraft nose subassembly mounting bracket can be dismantled.
Optionally, the embedded part is an embedded bolt.
(III) beneficial effects
Compared with the prior art, the invention provides a shell discarding process, which has the following beneficial effects:
1. according to the shell discarding process, the concrete prefabricated pipe joint is used for replacing part or all of the head steel plate structure, so that the manufacturing materials (steel plates) of the shell are saved, and the cost is reduced;
2. according to the shell discarding process, a part or all of the head steel plate structure is replaced by the precast concrete pipe joint, so that the concrete pouring process after pipe jacking construction is omitted, the construction efficiency is improved, and the construction period is shortened;
3. according to the shell discarding process, the prefabricated concrete pipe joint is prepared and formed before construction, so that the compactness of concrete is high, and the structural quality is effectively improved.
Drawings
Fig. 1 is a schematic diagram of the overall structure of a handpiece for a shell discarding process in a second embodiment of the present application.
Description of the drawings: 1. prefabricating a pipe joint by using concrete; 2. cutter driving device and machine head assembly mounting frame; 3. a cutterhead assembly; 4. a drive assembly; 5. and (5) embedding the parts.
Detailed Description
The technical solutions of the embodiments of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention, and it is apparent that the described embodiments are only some embodiments of the present invention, not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Embodiment one: shell discarding process
The shell discarding process comprises the following steps:
step one: the concrete prefabricated pipe joint is used for replacing part or all of the machine head steel plate structure, and the cutter head is arranged at the end part of the machine head through the embedded part;
step two: carrying out pipe jacking construction;
step three: and removing and recycling the cutterhead and the driving mechanism.
Furthermore, the shell discarding process further comprises the steps of reinforcing and waterproofing the peripheral soil body.
In a first embodiment, the surrounding soil is reinforced and waterproof by freezing.
In a second specific embodiment, the well point water-reducing method is adopted to strengthen and waterproof the surrounding soil body.
In a third specific embodiment, the high-pressure jet grouting pile method is adopted for reinforcing and waterproofing the peripheral soil body.
In a fourth embodiment, the compaction grouting method is used for reinforcing and waterproofing the peripheral soil body.
In other embodiments, the surrounding land is reinforced and waterproof by a combination of freezing, well point dewatering, high pressure jet grouting, and compaction grouting.
Further, the shell discarding process further comprises the steps of monitoring, measuring and rectifying the position of the machine head in the jacking process of the machine head.
Further, the first step further includes: and measuring the structural size of the head steel plate, and preparing the concrete prefabricated pipe joint according to the size of the head, wherein in the preparation process, an embedded part is arranged in advance so as to facilitate the installation of a follow-up cutter head.
Further, the pipe jacking construction in the second step includes, but is not limited to, the following steps:
1) Forming a foundation pit (a working well);
2) Measuring and positioning;
3) And (3) equipment installation:
back mounting: forming a back wall, and vertically placing a back steel plate in front of the back wall on the ground;
and (3) guide rail installation: the two guide rails are laid below the pipe jacking path in parallel to limit the jacking direction of the pipeline;
mounting a hydraulic jack bracket: a driving device is arranged on the foundation pit and is used for driving the hydraulic jack bracket; connecting a hydraulic jack bracket with the driving device by adopting a high-pressure oil pipe, and placing the jack bracket between two guide rails for fixing;
4) The heading machine is in place: placing the heading machine on a guide rail in a foundation pit;
5) And (3) positioning the push bench: the rear end of the push bench is propped against the front side of the back steel plate;
6) Pipeline (pipe joint) installation:
hoisting the pipeline (pipe joint) by using a hanging strip, and slowly hoisting the pipeline (pipe joint) to a working platform at the bottom of the foundation pit;
7) Jacking construction:
the pipe jacking tunneling machine is used for tunneling, the tunneling machine cuts and discharges earth and stones in front of the pipe, the pipe is pushed forward along with the tunneling machine, the jacking system of the pipe jacking machine is retracted when the pipe is pushed to a set position, and meanwhile, the tunneling machine stops acting and is used for pipe joint discharging;
8) Repeating the steps 6) and 7) until all the pipelines are jacked in place.
Furthermore, the shell discarding process further comprises the process of constructing corrosion resistance and waterproof protection at the joint of the two connected concrete pipe joints.
Further, the waterproof material of the joint seam of the pipe joint is an anti-corrosion and anti-aging EPDM elastic rubber sealing strip.
Further, the shell discarding process further comprises the process of constructing corrosion resistance and waterproof protection on the connecting piece holes between the connected beam concrete pipe joints.
Furthermore, the waterproof material of the connecting piece hole is an anti-corrosion and anti-aging water-swelling rubber sealing ring.
The beneficial effects of the invention are as follows: 1. according to the shell discarding process, the concrete prefabricated pipe joint is used for replacing part or all of the head steel plate structure, so that the manufacturing materials (steel plates) of the shell are saved, and the cost is reduced; according to the shell discarding process, a part or all of the head steel plate structure is replaced by the precast concrete pipe joint, so that the concrete pouring process after pipe jacking construction is omitted, and the construction efficiency is improved; according to the shell discarding process, the prefabricated concrete pipe joint is prepared and formed before construction, so that the compactness of concrete is high, and the structural quality is effectively improved.
Embodiment two: handpiece for shell discarding process of embodiment one
A handpiece, comprising:
a concrete prefabricated pipe joint 1;
the cutterhead driving device and the machine head assembly mounting frame 2 are arranged at the end part of the concrete prefabricated pipe joint 1 and are detachably connected with the concrete prefabricated pipe joint 1;
the cutter head assembly 3 is arranged at the end parts of the cutter head driving device and the machine head assembly mounting frame 2; and
and the driving assembly 4 is arranged on the cutterhead driving device and the machine head assembly mounting frame 2 and is used for driving the cutterhead assembly 3 to work.
Further, an embedded part 5 is arranged at the end part of the concrete prefabricated pipe joint 1, and the concrete prefabricated pipe joint 1 is detachably connected with the cutterhead driving device and the machine head assembly mounting frame 2 through the embedded part 5.
Further, the embedded part 5 is an embedded bolt.
Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The shell discarding process is characterized by comprising the following steps of:
step one: the concrete prefabricated pipe joint is used for replacing part or all of the machine head steel plate structure, and the cutter head driving device and related components in the machine head are arranged on the machine head through the embedded part;
step two: carrying out pipe jacking construction;
step three: and removing and recycling the cutterhead and the driving mechanism.
2. The shell discarding process according to claim 1, further comprising the step of reinforcing and waterproofing the surrounding soil mass.
3. The shell discarding process according to claim 2, wherein the surrounding land is reinforced and waterproof by one or more of freezing, well point dewatering, high pressure jet grouting, and compaction grouting.
4. The shell discarding process according to claim 1, further comprising the step of monitoring, measuring, and correcting the position of the head during its jacking.
5. A head for use in the shell discarding process according to any one of claims 1 to 4, comprising:
prefabricating a pipe joint by using concrete;
the cutterhead driving device and the machine head assembly mounting frame are arranged at the end part of the concrete prefabricated pipe joint and are detachably connected with the concrete prefabricated pipe joint;
the cutter head assembly is arranged at the ends of the cutter head driving device and the machine head assembly mounting frame; and
and the driving assembly is arranged on the cutterhead driving device and the machine head assembly mounting frame and used for driving the cutterhead assembly to work.
6. The machine head according to claim 5, wherein an embedded part is arranged at the end part of the concrete prefabricated pipe joint, and the concrete prefabricated pipe joint is detachably connected with the cutter head driving device and the machine head assembly mounting frame through the embedded part.
7. The head of claim 6, wherein the embedment is an embedment bolt.
CN202310660822.1A 2023-06-06 2023-06-06 Shell discarding process and machine head for shell discarding process Pending CN117823173A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310660822.1A CN117823173A (en) 2023-06-06 2023-06-06 Shell discarding process and machine head for shell discarding process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310660822.1A CN117823173A (en) 2023-06-06 2023-06-06 Shell discarding process and machine head for shell discarding process

Publications (1)

Publication Number Publication Date
CN117823173A true CN117823173A (en) 2024-04-05

Family

ID=90519826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310660822.1A Pending CN117823173A (en) 2023-06-06 2023-06-06 Shell discarding process and machine head for shell discarding process

Country Status (1)

Country Link
CN (1) CN117823173A (en)

Similar Documents

Publication Publication Date Title
CN109723065B (en) Reinforcing device and deep foundation pit local freezing reinforcing construction method in water-rich gravel stratum
CN110485470B (en) Rectangular working well with pre-arranged jacking pipe door opening and sliding type rear wall in water-rich stratum and construction method of rectangular working well
CN101761083B (en) Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN109356596B (en) Method for launching and receiving shield tunneling machine by utilizing recyclable underground continuous wall and steel sleeve
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN111335902B (en) Construction method for shield tunneling ground connection wall underpass operation subway station
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN110485468B (en) Permanent circular working well with water-rich stratum preset jacking pipe door opening and construction method thereof
CN110924961B (en) Construction method for starting shield tunneling machine to pass through existing station
CN111577334B (en) Operating tunnel inverted arch repairing method
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN109356183B (en) Open caisson reserved hole plugging structure and construction method thereof
CN111503368A (en) Pipe jacking construction method under sandy gravel geological condition
CN114164823B (en) Pile foundation construction method in high-fill foundation
CN113638448B (en) Working well and construction method thereof, underground pipeline working well device and construction method thereof
CN110205988A (en) It is a kind of to be discharged the dual water-stopping system and its construction technology that box culvert is connect with new and old
CN204533812U (en) A kind of slurry-water balance type jacking construction system
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
CN113047858A (en) Chest-closed TBM construction system for water-containing soft rock stratum of crack and construction method thereof
CN111733853A (en) Tongue-and-groove type prefabricated underground continuous wall structure
CN116516845A (en) Maintenance and reinforcement method for underwater pier of bridge in tidal zone
CN117823173A (en) Shell discarding process and machine head for shell discarding process
CN115681613A (en) Pipe jacking construction method for silt silty clay layer construction
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN111946358B (en) Correction tool for treating shield tail deformation in water-rich sand layer and construction process of correction tool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication