CN117669081A - A design method for arch dam foundation excavation - Google Patents

A design method for arch dam foundation excavation Download PDF

Info

Publication number
CN117669081A
CN117669081A CN202311645493.XA CN202311645493A CN117669081A CN 117669081 A CN117669081 A CN 117669081A CN 202311645493 A CN202311645493 A CN 202311645493A CN 117669081 A CN117669081 A CN 117669081A
Authority
CN
China
Prior art keywords
excavation
dam
layer
layered
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311645493.XA
Other languages
Chinese (zh)
Inventor
毛拥政
付登辉
陈平平
谭迪平
王栋
薛一峰
任耀文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Institute Of Water Conservancy And Electricity Survey And Design
Original Assignee
Shaanxi Institute Of Water Conservancy And Electricity Survey And Design
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Institute Of Water Conservancy And Electricity Survey And Design filed Critical Shaanxi Institute Of Water Conservancy And Electricity Survey And Design
Priority to CN202311645493.XA priority Critical patent/CN117669081A/en
Publication of CN117669081A publication Critical patent/CN117669081A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/17Mechanical parametric or variational design
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/27Design optimisation, verification or simulation using machine learning, e.g. artificial intelligence, neural networks, support vector machines [SVM] or training a model
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/02CAD in a network environment, e.g. collaborative CAD or distributed simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Medical Informatics (AREA)
  • Software Systems (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Artificial Intelligence (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses an arch dam foundation excavation design method, belongs to the technical field of water conservancy and hydropower engineering, and can solve the problems that the existing arch dam excavation design is long in time and difficult to control in excavation slope ratio. The method comprises the following steps: s1, creating an excavation surface at the upper part of a dam top on a terrain geological model of an arch dam site area according to a three-dimensional model of an arch dam body; s2, constructing a layered excavation datum line from the elevation of the bottom surface of the dam body to the elevation of the top surface of the dam body on the terrain geological model, and creating a dam body excavation surface according to the layered excavation datum line; s3, creating a dam foundation excavation model according to the upper excavation surface of the dam top and the dam body excavation surface. The method is used for designing the arch dam foundation excavation model.

Description

一种拱坝基础开挖设计方法A design method for arch dam foundation excavation

技术领域Technical field

本发明涉及一种拱坝基础开挖设计方法,属于水利水电工程技术领域。The invention relates to an arch dam foundation excavation design method and belongs to the technical field of water conservancy and hydropower engineering.

背景技术Background technique

拱坝作为一种水电工程常用坝型,广泛应用于各种水利水电工程,为国民经济发展起到了巨大作用。拱坝一般建于高山峡谷中,河岸边坡陡峻,地形地质条件复杂,拱坝本身体型复杂,基础开挖一直是拱坝设计的重点、难点。As a commonly used dam type in hydropower projects, arch dams are widely used in various water conservancy and hydropower projects and play a huge role in the development of the national economy. Arch dams are generally built in mountain canyons with steep river bank slopes, complex topographic and geological conditions, and complex body shapes of the arch dams. Foundation excavation has always been the focus and difficulty of arch dam design.

现有技术通常利用三维软件建模或利用CAD软件进行开挖设计,存在以下不足:1、拱坝基础采用径向断面法进行开挖,开挖断面需要根据拱坝体型确定地质条件,绘制地质剖面后才能进行开挖设计。当拱坝体型发生变化时需要重新绘制地质剖面,然后再进行开挖设计,这样需要设计者与地质专家多次协调配合,设计工作的时间会明显增加。2、采用径向断面开挖方法,不方便控制开挖坡比,断面开挖图中的边坡和设计边坡不一致,不是边坡开挖设计的开挖方向。3、传统的开挖方法不能从整体上协调开挖边坡,开挖边坡的协调和控制不直观。The existing technology usually uses three-dimensional software modeling or CAD software for excavation design, which has the following shortcomings: 1. The arch dam foundation is excavated using the radial section method. The excavation section needs to determine the geological conditions according to the arch dam shape and draw it. Excavation design can only be carried out after the geological profile is obtained. When the shape of the arch dam changes, the geological profile needs to be redrawn and then the excavation design is carried out. This requires multiple coordination between the designer and geological experts, and the design work time will be significantly increased. 2. The radial cross-section excavation method is inconvenient to control the excavation slope ratio. The slope in the cross-section excavation diagram is inconsistent with the designed slope and is not the excavation direction designed for slope excavation. 3. Traditional excavation methods cannot coordinate the excavation slope as a whole, and the coordination and control of the excavation slope are not intuitive.

发明内容Contents of the invention

本发明提供了一种拱坝基础开挖设计方法,能够解决现有拱坝开挖设计所需时间较长、开挖坡比难以控制的问题。The invention provides an arch dam foundation excavation design method, which can solve the problems that the existing arch dam excavation design requires a long time and the excavation slope ratio is difficult to control.

本发明提供了一种拱坝基础开挖设计方法,所述方法包括:The invention provides an arch dam foundation excavation design method, which method includes:

S1、根据拱坝坝体三维模型,在拱坝坝址区的地形地质模型上创建坝顶上部开挖面;S1. Based on the three-dimensional model of the arch dam body, create an excavation surface for the upper part of the dam crest on the topographic and geological model of the arch dam site area;

S2、在所述地形地质模型上构建从坝体底面高程至坝体顶面高程的分层开挖基准线,并根据所述分层开挖基准线创建坝体开挖面;S2. Construct a layered excavation baseline from the bottom elevation of the dam to the top elevation of the dam on the topographic geological model, and create a dam excavation surface based on the layered excavation baseline;

S3、根据所述坝顶上部开挖面和所述坝体开挖面创建坝基开挖模型。S3. Create a dam foundation excavation model based on the upper excavation surface of the dam crest and the dam body excavation surface.

可选的,在所述S3之后,所述方法还包括:Optionally, after S3, the method further includes:

根据所述地形地质模型调整所述坝基开挖模型中的开挖坡比,得到更新后的坝基开挖模型。The excavation slope ratio in the dam foundation excavation model is adjusted according to the topographic geological model to obtain an updated dam foundation excavation model.

可选的,在所述S1之前,所述方法还包括:Optionally, before S1, the method further includes:

根据拱坝设计参数绘制坝体三维模型,并根据坝址区地质资料绘制拱坝坝址区的地形地质模型。Draw a three-dimensional model of the dam body based on the design parameters of the arch dam, and draw a topographic and geological model of the arch dam site area based on the geological data of the dam site area.

可选的,所述S1具体为:Optional, the S1 is specifically:

根据坝体三维模型和坝址区地质资料,在拱坝坝址区的地形地质模型上采用断面法创建坝顶上部开挖面。Based on the three-dimensional model of the dam body and the geological data of the dam site area, the cross-section method was used to create the upper excavation surface of the dam crest on the topographic geological model of the arch dam site area.

可选的,所述S2中的在所述地形地质模型上构建从坝体底面高程至坝体顶面高程的分层开挖基准线,具体为:Optionally, in S2, a layered excavation baseline from the bottom elevation of the dam to the top elevation of the dam is constructed on the topographic geological model, specifically:

确定坝体底面高程上的坝体开挖轮廓,以及分层开挖的开挖层高和开挖坡比;Determine the excavation profile of the dam body on the elevation of the dam bottom surface, as well as the excavation layer height and excavation slope ratio of layered excavation;

根据所述坝体开挖轮廓以及分层开挖的开挖层高和开挖坡比,确定每层开挖面的分层开挖基准线。According to the excavation contour of the dam body and the excavation layer height and excavation slope ratio of the layered excavation, the layered excavation baseline of each layer of excavation surface is determined.

可选的,根据所述坝体开挖轮廓以及分层开挖的开挖层高和开挖坡比,确定每层开挖面的分层开挖基准线,具体为:Optionally, according to the excavation contour of the dam body and the excavation layer height and excavation slope ratio of the layered excavation, determine the layered excavation baseline of each layer of excavation surface, specifically as follows:

将所述坝体开挖轮廓作为底层开挖基准线,并根据所述底层开挖基准线以及上一层开挖面的开挖层高和开挖坡比确定上一层开挖面的开挖边线;The excavation contour of the dam body is used as the base line of the bottom excavation, and the excavation level of the upper layer of excavation surface is determined based on the base line of the bottom layer of excavation and the excavation layer height and excavation slope ratio of the upper layer of excavation surface. dig edge;

根据所述开挖边线和预留马道宽度,形成上一层开挖面的分层开挖基准线,并将所述分层开挖基准线作为底层开挖基准线,依次逐层确定每层开挖面的分层开挖基准线。According to the excavation edge line and the reserved horse road width, a layered excavation datum line for the upper layer of excavation surface is formed, and the layered excavation datum line is used as the bottom layer excavation datum line, and each layer is determined layer by layer in turn. The layered excavation datum line for the excavation face.

可选的,所述S2中的根据所述分层开挖基准线创建坝体开挖面,具体包括:Optionally, in S2, creating a dam excavation surface based on the hierarchical excavation baseline includes:

将每层开挖面的开挖边线上的转折点和与其对应的底层开挖基准线上的转折点对应相连,形成每层开挖面的引导线;Correspondingly connect the turning points on the excavation edge line of each layer of excavation surface with the turning points on the corresponding bottom excavation baseline to form the guide line of each layer of excavation surface;

根据所述分层开挖基准线和所述引导线创建坝体开挖面。Create a dam excavation surface based on the layered excavation baseline and the guide line.

可选的,根据所述分层开挖基准线和所述引导线创建坝体开挖面,具体包括:Optionally, create a dam excavation surface based on the layered excavation baseline and the guide line, specifically including:

根据所述分层开挖基准线和所述引导线形成开挖边坡面;Form an excavation slope surface according to the layered excavation baseline and the guide line;

以填充方式形成马道面,并将所述马道面与所述开挖边坡面接合形成坝体开挖面。The horse track surface is formed by filling, and the horse track surface is joined with the excavation side slope surface to form the dam body excavation surface.

可选的,根据所述地形地质模型调整所述坝基开挖模型中的开挖坡比,得到更新后的坝基开挖模型,具体为:Optionally, adjust the excavation slope ratio in the dam foundation excavation model according to the topographic geological model to obtain an updated dam foundation excavation model, specifically:

根据所述地形地质模型切割后的开挖面调整所述坝基开挖模型中的分层开挖基准线,得到更新后的坝基开挖模型。The layered excavation baseline in the dam foundation excavation model is adjusted according to the excavation surface cut by the topographic geological model to obtain an updated dam foundation excavation model.

可选的,所述地形地质模型的岩层风化类型分为由上至下的强风化层、弱风化层和微风化层。Optionally, the rock layer weathering types of the topographic geological model are divided into strongly weathered layer, weak weathered layer and lightly weathered layer from top to bottom.

本发明能产生的有益效果包括:The beneficial effects produced by this invention include:

(1)本发明提供的拱坝基础开挖设计方法,通过平面分层的方式构建坝体底面至顶面的分层开挖基准线,以创建坝体开挖面。本发明改变了传统拱坝采用径向断面设计拱坝坝基开挖的传统方法,可以结合拱坝坝址区地质二维平切图和三维地质风化模型设计开挖面。另外,对于拱坝来说,开挖边坡纵向和水平向都会发生变化,且相互关联,因此本发明通过参数化设计分层开挖基准线,方便总体调整开挖面,而且可以快速形成开挖面,查看调整后的整体效果,这样大大提高设计质量和效益。(1) The arch dam foundation excavation design method provided by the present invention constructs a layered excavation datum line from the bottom surface of the dam body to the top surface through plane layering to create the dam body excavation surface. The present invention changes the traditional method of using radial sections to design arch dam foundation excavation, and can design the excavation surface by combining the geological two-dimensional plan view of the arch dam site area and the three-dimensional geological weathering model. In addition, for arch dams, both the longitudinal and horizontal excavation slopes will change and are related to each other. Therefore, the present invention facilitates the overall adjustment of the excavation surface through parametric design of the hierarchical excavation baseline, and can quickly form an excavation surface. Dig in and see the overall effect after adjustment, which greatly improves design quality and efficiency.

(2)本发明提供的拱坝基础开挖设计方法,通过建立水平的分层开挖基准线,方便施工放线和控制开挖坡比,设计图纸和施工更好结合,从而加快施工进度。同时,本发明采用三维实体分类开挖可以从开挖面的颜色直接查看边坡设计的合理性,方便边坡设计的调整。(2) The arch dam foundation excavation design method provided by the present invention establishes a horizontal layered excavation reference line to facilitate construction setting out and control the excavation slope ratio, and better integrates design drawings and construction, thereby accelerating the construction progress. At the same time, the present invention uses three-dimensional entity classification for excavation to directly check the rationality of the slope design from the color of the excavation surface, thereby facilitating the adjustment of the slope design.

附图说明Description of drawings

图1为本发明实施例提供的基于CATIA平台的拱坝基础开挖设计方法流程图;Figure 1 is a flow chart of the arch dam foundation excavation design method based on the CATIA platform provided by the embodiment of the present invention;

图2为本发明实施例提供的三维地形地质模型示意图;Figure 2 is a schematic diagram of a three-dimensional terrain geological model provided by an embodiment of the present invention;

图3为本发明实施例提供的坝体三维模型示意图;Figure 3 is a schematic diagram of a three-dimensional model of a dam provided by an embodiment of the present invention;

图4为本发明实施例提供的坝顶坝肩边坡开挖面创建示意图;Figure 4 is a schematic diagram of the excavation surface creation of the dam crest and abutment slope provided by the embodiment of the present invention;

图5为本发明实施例提供的分层开挖基准线及引导线示意图;Figure 5 is a schematic diagram of the layered excavation baseline and guide lines provided by the embodiment of the present invention;

图6为本发明实施例提供的坝顶上部开挖面及坝体开挖面示意图;Figure 6 is a schematic diagram of the excavation surface of the upper part of the dam crest and the excavation surface of the dam body provided by the embodiment of the present invention;

图7为本发明实施例提供的开挖调整示意图;Figure 7 is a schematic diagram of excavation adjustment provided by the embodiment of the present invention;

图8为本发明实施例提供的开挖完成后的整体效果示意图。Figure 8 is a schematic diagram of the overall effect after excavation is completed according to the embodiment of the present invention.

部件和附图标记列表:Parts and reference number list:

1、地质钻孔点;2、地形面;3、强风化下限曲面;4、弱风化下限曲面;5、强风化层;6、弱风化层;7、微风化层;8、坝体三维模型;9、拱坝坝顶;10、拱坝底面;11、右坝肩顶;12、左坝肩顶;13、边坡开挖基线;14、开挖断面法向轮廓;15、坝顶上部开挖面;16、拱坝模型底部基线;17、坝体底面高程基准面;18、坝体开挖轮廓;19、第一层马道高程基准面;20、第一层开挖边线;21、引导线;22、第一层开挖基准线;23、左坝肩顶部开挖面;24、右坝肩顶部开挖面;25、坝体开挖面;26、分层开挖基准线;27、调整前后基准线投影距离;28、坝基开挖结果面;29、左坝肩开挖结果面;30、右坝肩开挖结果面;31、马道开挖结果面;32、微风化开挖坡面;33、弱风化开挖坡面;34、强风化开挖坡面。1. Geological drilling points; 2. Topographic surface; 3. Strong weathering lower limit surface; 4. Weak weathering lower limit surface; 5. Strong weathering layer; 6. Weak weathering layer; 7. Slightly weathered layer; 8. Three-dimensional model of dam body ; 9. Top of arch dam; 10. Bottom of arch dam; 11. Top of right dam abutment; 12. Top of left dam abutment; 13. Baseline of slope excavation; 14. Normal profile of excavation section; 15. Upper part of dam crest Excavation surface; 16. Baseline of the bottom of the arch dam model; 17. Dam base elevation datum; 18. Dam excavation outline; 19. First layer of horse track elevation datum; 20. First layer excavation edge line; 21. Guide line; 22. First layer excavation datum line; 23. Excavation surface at the top of the left abutment; 24. Excavation surface at the top of the right abutment; 25. Dam body excavation surface; 26. Layered excavation datum line; 27. Adjust the projection distance of the front and rear baselines; 28. Dam foundation excavation result surface; 29. Left dam abutment excavation result surface; 30. Right dam abutment excavation result surface; 31. Horse road excavation result surface; 32. Breeze excavation Excavation slope; 33. Excavation slope with weak weathering; 34. Excavation slope with strong weathering.

具体实施方式Detailed ways

下面结合实施例详述本发明,但本发明并不局限于这些实施例。The present invention will be described in detail below with reference to examples, but the present invention is not limited to these examples.

本发明实施例提供了一种拱坝基础开挖设计方法,如图1至图8所示,所述方法包括:An embodiment of the present invention provides an arch dam foundation excavation design method, as shown in Figures 1 to 8. The method includes:

S1、根据拱坝坝体三维模型8,在拱坝坝址区的地形地质模型上创建坝顶上部开挖面15。S1. Based on the three-dimensional model 8 of the arch dam body, create an excavation surface 15 for the upper part of the dam crest on the topographic and geological model of the arch dam site area.

在S1之前,所述方法还包括:Before S1, the method further includes:

根据拱坝设计参数绘制坝体三维模型8,并根据坝址区地质资料创建拱坝坝址区的地形地质模型。其中,地形地质模型以岩层风化类型进行创建,分为由上至下的强风化层5、弱风化层6和微风化层7。Draw a three-dimensional model of the dam body based on the design parameters of the arch dam8, and create a topographic and geological model of the arch dam site area based on the geological data of the dam site area. Among them, the terrain geological model is created based on the rock layer weathering type, which is divided into strongly weathered layer 5, weak weathered layer 6 and lightly weathered layer 7 from top to bottom.

通过地形曲面和结合前期地质勘察成果建立的坝基三维地质风化曲面共同创建坝址区域所在的地形地质模型。利用CATIA样条曲线分层形成拱坝基线并形成坝体三维模型8。The topographic and geological model of the dam site area is jointly created through the terrain surface and the three-dimensional geological weathering surface of the dam foundation established based on the previous geological survey results. CATIA spline curves are used to form the arch dam baseline in layers and form a three-dimensional model of the dam body8.

图2为本发明实施例提供的三维地形地质模型示意图,参考图2所示,地质钻孔点1为地质勘查所提供的资料;地形面2为用点云在CATIA平台生成的曲面;强风化下限曲面3和弱风化下限曲面4为根据地质勘测孔实测资料,利用GOCAD软件拟合形成点云成果,再用CATIA平台生成的曲面;强风化层5为地形面2和强风化下限曲面3中间的岩体;弱风化层6为强风化下限曲面3和弱风化下限曲面4中间的岩体;微风化层7为弱风化下限曲面4以下的部分岩体。Figure 2 is a schematic diagram of a three-dimensional terrain geological model provided by an embodiment of the present invention. As shown in Figure 2, the geological drilling point 1 is the data provided by geological exploration; the terrain surface 2 is a curved surface generated using point clouds on the CATIA platform; strong weathering The lower limit surface 3 and the weakly weathered lower limit surface 4 are surfaces generated by using the GOCAD software to fit the point cloud results based on the measured data of the geological survey holes, and then using the CATIA platform; the strongly weathered layer 5 is the middle surface between the terrain surface 2 and the strong weathering lower limit surface 3 The weakly weathered layer 6 is the rock mass between the strong weathering lower limit curved surface 3 and the weakly weathered lower limit curved surface 4; the slightly weathered layer 7 is the part of the rock mass below the weakly weathered lower limit curved surface 4.

图3为本发明实施例提供的坝体三维模型8的示意图。参考图3所示,拱坝坝顶9为坝体三维模型8最高处所在平面;拱坝底面10为坝体三维模型8最低处所在平面;右坝肩顶11为拱坝坝顶9在顺水流方向右端部位;左坝肩顶12为拱坝坝顶9在顺水流方向左端部位。Figure 3 is a schematic diagram of the three-dimensional model 8 of the dam body provided by the embodiment of the present invention. As shown in Figure 3, the top 9 of the arch dam is the plane where the highest point of the three-dimensional model 8 of the dam body is; the bottom surface 10 of the arch dam is the plane where the lowest point of the three-dimensional model 8 of the dam body is; the top 11 of the right abutment is the plane where the top 9 of the arch dam is. The right end position of the water flow direction; the left dam abutment 12 is the left end position of the arch dam crest 9 along the flow direction.

S1具体为:S1 is specifically:

根据坝体三维模型8和坝址区地质现状,在拱坝坝址区的地形地质模型上采用断面法创建坝顶上部开挖面15。According to the three-dimensional model of the dam body8 and the current geological conditions of the dam site area, the cross-section method was used to create the excavation surface of the upper part of the dam crest15 on the topographic geological model of the arch dam site area.

获取拱坝坝址区的地形地质模型,以及拱坝坝体三维模型8,坝顶以上开挖设计应与道路布置结合,依据地质条件,按照相关设计规范要求,确定边坡开挖设计参数,采用断面法创建坝顶上部开挖面15。Obtain the topographic and geological model of the arch dam site area and the three-dimensional model of the arch dam body8. The excavation design above the dam crest should be combined with the road layout, and the slope excavation design parameters should be determined according to the geological conditions and relevant design specifications. The section method is used to create the excavation surface 15 on the upper part of the dam crest.

图4为本发明实施例提供的坝顶坝肩边坡开挖面创建示意图。参考图4所示,边坡开挖基线13为根据工程实际布置情况,所设计的边坡开挖基准线,作为形成开挖曲面的引导线;开挖断面法向轮廓14为开挖部位设计断面,包含边坡开挖坡高、坡度、马道等相关设计参数;坝顶上部开挖面15为利用CATIA中的扫掠命令,以开挖断面法向轮廓14为断面草图和以边坡开挖基线13为引导线生成的曲面。Figure 4 is a schematic diagram of the excavation surface creation of the dam crest and abutment slope provided by the embodiment of the present invention. As shown in Figure 4, the slope excavation baseline 13 is the slope excavation baseline designed based on the actual layout of the project, and is used as a guide line to form the excavation surface; the excavation section normal profile 14 is the design of the excavation site Section, including slope excavation slope height, slope, horse path and other related design parameters; the excavation surface 15 on the upper part of the dam top is made by using the sweep command in CATIA, using the excavation section normal profile 14 as the section sketch and the side slope excavation Digging baseline 13 is the surface generated by the guide line.

S2、在地形地质模型上构建从坝体底面高程至坝体顶面高程的分层开挖基准线26,并根据分层开挖基准线26创建坝体开挖面25。S2. Construct a layered excavation baseline 26 from the bottom elevation of the dam to the top elevation of the dam on the topographic geological model, and create the dam excavation surface 25 based on the layered excavation baseline 26.

根据开挖规划从坝体底面高程开始按平面分层法建立拱坝开挖基准线(即分层开挖基准线26),基于分层开挖基准线26以多截面命令创建坝体开挖面25。According to the excavation plan, starting from the elevation of the dam bottom surface, the arch dam excavation baseline (i.e., the layered excavation baseline 26) is established according to the plane layering method. Based on the layered excavation baseline 26, the dam body excavation is created with a multi-section command. Side 25.

具体包括:Specifically include:

(1)确定坝体底面高程上的坝体开挖轮廓18,以及分层开挖的开挖层高和开挖坡比。(1) Determine the dam excavation profile 18 on the dam bottom elevation, as well as the excavation layer height and excavation slope ratio for layered excavation.

(2)根据坝体开挖轮廓18以及分层开挖的开挖层高和开挖坡比,确定每层开挖面的分层开挖基准线26。其中,坝体开挖轮廓18以及分层开挖的开挖层高和开挖坡比,需满足相关规范及施工条件要求。(2) According to the excavation contour 18 of the dam body and the excavation layer height and excavation slope ratio of the layered excavation, determine the layered excavation baseline 26 of each layer of excavation surface. Among them, the dam excavation profile 18 and the excavation layer height and excavation slope ratio of layered excavation must meet relevant specifications and construction condition requirements.

具体为:Specifically:

将坝体开挖轮廓18作为底层开挖基准线,并根据底层开挖基准线以及上一层开挖面的开挖层高和开挖坡比确定上一层开挖面的开挖边线。The dam body excavation contour 18 is used as the bottom excavation datum line, and the excavation edge line of the upper layer excavation surface is determined based on the bottom excavation datum line and the excavation layer height and excavation slope ratio of the upper layer excavation surface.

根据开挖边线和预留马道宽度,形成上一层开挖面的分层开挖基准线26,并将分层开挖基准线26作为底层开挖基准线,依次逐层确定每层开挖面的分层开挖基准线26。According to the excavation edge line and the width of the reserved horse road, a layered excavation datum line 26 of the upper layer of excavation surface is formed, and the layered excavation datum line 26 is used as the bottom layer excavation datum line, and each layer of excavation is determined layer by layer. The layered excavation datum line 26 on the surface.

在实际应用中,先确定最低一层坝体开挖轮廓18,然后初步根据坝肩地形和地质的风化情况确定开挖层高和坡比,以折线方式形成上一层的开挖边线,在此基础上留马道,形成下一层的底层开挖基准线,以此类推完成拱坝坝基的分层开挖基准线26。In practical applications, the excavation outline of the lowest layer of the dam is first determined18, and then the excavation layer height and slope ratio are initially determined based on the topography of the dam abutment and geological weathering conditions, and the excavation edge line of the upper layer is formed in a broken line. On this basis, a horse track is left to form the base excavation baseline of the next layer, and so on to complete the layered excavation baseline 26 of the arch dam foundation.

(3)将每层开挖面的开挖边线上的转折点和与其对应的底层开挖基准线上的转折点对应相连,形成每层开挖面的引导线21。(3) Correspondingly connect the turning points on the excavation edge line of each layer of excavation surface with the turning points on the corresponding bottom layer excavation baseline to form the guide line 21 of each layer of excavation surface.

先从拱坝底面10确定开挖边界的基准线(使用折线),然后根据开挖平台高度在第一层马道高程基准面19建立该高程的开挖边界的基准线,即第一层开挖边线20,此开挖边线的距离按地质风化类型确定开挖坡比换算为水平距离,确定该层开挖边界基准线的位置。完成开挖基准线后,以此为基础根据设计马道宽度完成马道的开挖边界基准线,作为下一层开挖的底层开挖基准线,以此类推完成坝顶以下的分层开挖基准线26的确定,最后根据开挖边界基准线的设计,将折线的转折点上下两点对应相连作为开挖形成开挖面的引导线21,根据各引导线的方向,进一步控制开挖有效坡比,并方便后期开挖优化设计。First determine the base line of the excavation boundary from the bottom surface 10 of the arch dam (using a polyline), and then establish the base line of the excavation boundary at that elevation at the first layer of horse road elevation datum 19 based on the height of the excavation platform, that is, the first layer of excavation. Side line 20, the distance of this excavation side line is determined according to the geological weathering type and converted into a horizontal distance according to the excavation slope ratio to determine the position of the excavation boundary baseline of this layer. After the excavation datum line is completed, use this as a basis to complete the excavation boundary datum line of the bridleway according to the designed bridleway width, which will be used as the bottom excavation datum line for the next layer of excavation, and so on to complete the layered excavation datum below the dam top. To determine the line 26, finally based on the design of the excavation boundary baseline, the upper and lower points of the turning point of the polyline are connected correspondingly as the guide line 21 for the excavation to form the excavation surface. According to the direction of each guide line, the effective slope ratio of the excavation is further controlled. , and facilitate later excavation optimization design.

(4)根据分层开挖基准线26和引导线21创建坝体开挖面25。(4) Create the dam excavation surface 25 based on the layered excavation reference line 26 and the guide line 21.

具体包括:首先根据分层开挖基准线26和引导线21形成开挖边坡面;然后以填充方式形成马道面,并将马道面与开挖边坡面接合形成坝体开挖面25。Specifically, it includes: first forming the excavation slope surface according to the layered excavation reference line 26 and the guide line 21; then forming the horse track surface by filling, and joining the horse track surface and the excavation side slope surface to form the dam body excavation surface 25.

图5为本发明实施例提供的分层开挖基准线26及引导线21的示意图。参考图5所示,拱坝模型底部基线16为拱坝底面10的轮廓线;坝体底面高程基准面17为拱坝底面10所在的高程面,用来定位开挖草图的位置;坝体开挖轮廓18为根据拱坝模型底部基线16所设计的开挖边界线,一般拱坝模型底部基线16范围小于坝体开挖轮廓18所包含的范围,坝体开挖轮廓18以及上述基准线均为折线状,以适应不同的空间关系;第一层马道高程基准面19为根据地质情况和设计布置所确定的从坝体底面高程基准面17开始的第一级马道所在高程面;第一层开挖边线20为根据坝体开挖轮廓18之间的投影关系所设计的开挖基准线,第一层开挖边线20与坝体开挖轮廓18通过开挖边界的引导线21形成第一层开挖曲面;开挖边界的引导线21为坝体开挖轮廓18和第一层开挖边线20的折线相应位置折点处点的连线,用来控制开挖坡比;Figure 5 is a schematic diagram of the layered excavation reference line 26 and the guide line 21 provided by the embodiment of the present invention. Referring to Figure 5, the base line 16 at the bottom of the arch dam model is the outline of the arch dam bottom surface 10; the elevation datum plane 17 of the dam bottom surface is the elevation surface where the arch dam bottom surface 10 is located, which is used to locate the excavation sketch; The excavation outline 18 is the excavation boundary line designed based on the bottom baseline 16 of the arch dam model. Generally, the range of the arch dam model bottom baseline 16 is smaller than the range included in the dam excavation outline 18. The dam excavation outline 18 and the above-mentioned baseline are both It is in the shape of a broken line to adapt to different spatial relationships; the elevation datum 19 of the first-level horse track is the elevation plane where the first-level horse track is located starting from the elevation datum 17 of the bottom of the dam determined according to the geological conditions and design layout; The excavation edge line 20 is an excavation datum line designed based on the projection relationship between the dam body excavation contours 18. The first layer excavation edge line 20 and the dam body excavation contour 18 form the first layer of excavation through the guide line 21 of the excavation boundary. layer excavation curved surface; the guide line 21 of the excavation boundary is the connection line between the corresponding points of the excavation contour 18 of the dam body and the polyline of the first layer excavation edge line 20, which is used to control the excavation slope ratio;

第一层开挖基准线22为根据第一层开挖边线20偏移一定距离(马道设计宽度)所设计的边界基准线,与第一层开挖边线20形成马道平台,以此类推,第一层开挖基准线22作为下一个开挖曲面的基线,依次完成坝顶以下的开挖基准线的创建和曲面生成;依据分层开挖基准线26,按照CATIA的多截面命令创建分层开挖面,利用引导线21控制开挖方向,依次形成开挖坡面,然后利用曲面填充命令形成马道面,最后利用接合命令粘接为一个曲面,形成坝顶以下的坝体开挖面25。The first layer of excavation datum line 22 is a boundary datum line designed based on a certain distance offset from the first layer of excavation edge line 20 (the design width of the horse track), and forms a horse path platform with the first layer of excavation edge line 20, and so on. The one-layer excavation baseline 22 serves as the baseline for the next excavation surface, and the creation and surface generation of the excavation baseline below the dam top are completed in sequence; based on the layered excavation baseline 26, layers are created according to CATIA's multi-section command For the excavation surface, use the guide line 21 to control the direction of the excavation, and form the excavation slope in sequence. Then use the curved surface filling command to form the road surface, and finally use the joint command to bond it into a curved surface to form the excavation surface 25 of the dam body below the dam top. .

图6为本发明实施例提供的坝顶上部开挖面15及坝体开挖面25的示意图。参考图6所示,左坝肩顶部开挖面23为左坝肩顶12所在高程以上部分的开挖曲面,用来切割拱坝坝顶9左侧部分岩体;右坝肩顶部开挖面24为右坝肩顶11所在高程以上部分的开挖曲面,用来切割拱坝坝顶9右侧部分岩体;坝体开挖面25为拱坝坝顶9与拱坝底面10中间部分的开挖曲面,用来切割拱坝坝顶9和拱坝底面10中间部分的岩体,最终完成拱坝的基础开挖。Figure 6 is a schematic diagram of the upper excavation surface 15 of the dam crest and the excavation surface 25 of the dam body provided by the embodiment of the present invention. As shown in Figure 6, the excavation surface 23 at the top of the left dam abutment is the excavation curved surface above the elevation of the left dam abutment 12, and is used to cut the rock mass on the left side of the arch dam crest 9; the excavation surface at the top of the right dam abutment 24 is the excavation curved surface of the part above the elevation of the right dam abutment 11, which is used to cut the rock mass on the right side of the arch dam crest 9; the dam body excavation surface 25 is the middle part of the arch dam crest 9 and the arch dam bottom surface 10 The excavation curved surface is used to cut the rock mass in the middle part of the arch dam crest 9 and the arch dam bottom 10, and finally complete the foundation excavation of the arch dam.

S3、根据坝顶上部开挖面15和坝体开挖面25创建坝基开挖模型。S3. Create a dam foundation excavation model based on the upper excavation surface 15 of the dam crest and the dam body excavation surface 25.

进一步的,在S3之后,所述方法还包括:Further, after S3, the method also includes:

根据地形地质模型进一步调整优化坝基开挖模型中的开挖坡比,得到更新后的坝基开挖模型。The excavation slope ratio in the dam foundation excavation model was further adjusted and optimized based on the terrain geological model to obtain an updated dam foundation excavation model.

具体为:根据初步切割后的地形地质模型的开挖形象图,结合岩体风化情况进一步调整坝基开挖模型中的分层开挖基准线26和引导线21的方向,得到更新后的坝基开挖模型。Specifically, according to the excavation image of the preliminary cut terrain geological model, combined with the weathering conditions of the rock mass, the directions of the layered excavation baseline 26 and the guide line 21 in the dam foundation excavation model are further adjusted to obtain the updated dam foundation excavation. Dig the model.

根据地质情况调整开挖面,按风化类别进行开挖。图7为本发明实施例提供的开挖调整示意图。参考图7所示,分层开挖基准线26即为包含坝体开挖轮廓18、第一层开挖边线20、第一层开挖基准线22在内的各层设计基准线;调整前后基准线投影距离27即为各层开挖曲面基线投影之间的距离,与开挖边界的引导线21共同控制开挖坡比。图7中示出了调整前该层开挖曲面基线投影距离为10,调整开挖基准线后,该层开挖曲面基线投影距离变为12.5。The excavation surface is adjusted according to the geological conditions and the excavation is carried out according to the weathering category. Figure 7 is a schematic diagram of excavation adjustment provided by the embodiment of the present invention. Referring to Figure 7, the layered excavation datum line 26 is the design datum line of each layer including the dam excavation outline 18, the first layer excavation edge line 20, and the first layer excavation datum line 22; before and after adjustment The baseline projection distance 27 is the distance between the baseline projections of the excavation surfaces at each layer, and controls the excavation slope ratio together with the guide line 21 of the excavation boundary. Figure 7 shows that before adjustment, the baseline projection distance of the excavation surface of this layer was 10. After adjusting the excavation baseline, the baseline projection distance of the excavation surface of this layer became 12.5.

根据步骤S3形成的坝基开挖模型,以及开挖面揭示的风化类别,从下向上、从坝肩到河道中间,根据需要不断调整水平开挖基线(即分层开挖基准线26)的位置和引导线21的方向,直到每层开挖边坡和地质条件相符合理。相符合理的标准是:边坡衔接平顺,分段开挖坡比和风化地质条件,地形条件相适应。According to the dam foundation excavation model formed in step S3 and the weathering categories revealed on the excavation surface, the position of the horizontal excavation baseline (i.e., the layered excavation baseline 26) is continuously adjusted from bottom to top, from the dam abutment to the middle of the river channel as needed. and the direction of the guide line 21 until the excavation slope of each layer is consistent with the geological conditions. The standards that are consistent and reasonable are: the slope connection is smooth, the slope ratio of the segmented excavation is compatible with the weathered geological conditions, and the terrain conditions are suitable.

确定最终的开挖面后,通过刷新完成拱坝坝基的开挖更新,能够有效节省设计修改时间,提高设计工作效率和产品质量,然后根据实际需要分类别统计开挖量。After the final excavation surface is determined, the excavation update of the arch dam foundation is completed through refreshing, which can effectively save design modification time, improve design work efficiency and product quality, and then count the excavation volume according to actual needs.

图8为本发明实施例提供的开挖完成后的整体效果示意图。图8示出了坝基开挖结果面28、左坝肩开挖结果面29、右坝肩开挖结果面30、马道开挖结果面31、微风化开挖坡面32、弱风化开挖坡面33、强风化开挖坡面34,开挖结果可用来进行出图和计算工程量等工作。其中,开挖坡面的坡度由陡到缓应该为微风化开挖坡面32的坡度<弱风化开挖坡面33的坡度<强风化开挖坡面34的坡度。Figure 8 is a schematic diagram of the overall effect after excavation is completed according to the embodiment of the present invention. Figure 8 shows the dam foundation excavation result surface 28, the left dam abutment excavation result surface 29, the right dam abutment excavation result surface 30, the horse road excavation result surface 31, the lightly weathered excavation slope surface 32, and the weakly weathered excavation slope surface. Surface 33 and strongly weathered excavation slope 34, the excavation results can be used to draw drawings and calculate engineering quantities. Among them, the slope of the excavation slope from steep to gentle should be the slope of the lightly weathered excavation slope 32 < the slope of the weakly weathered excavation slope 33 < the slope of the strongly weathered excavation slope 34.

先利用坝顶上部开挖面15按风化类别完成坝顶以上开挖,然后根据坝体开挖面25利用CATIA切割命令完成不同风化类别的开挖实体。根据开挖完成的情况,从整体复核开挖是否满足整体设计的要求,需要调整可以从下往上通过调整分层开挖引导线的位置调整开挖面,并通过CATIA的刷新命令完成开挖面调整,直至满足设计要求。最后利用CATIA的测量命令完成分类工程量统计。First, use the excavation surface 15 on the upper part of the dam crest to complete the excavation above the dam crest according to the weathering category, and then use the CATIA cutting command to complete the excavation entities of different weathering categories according to the excavation surface 25 of the dam body. Based on the completion of the excavation, review the overall excavation to see if it meets the overall design requirements. If adjustments are needed, you can adjust the excavation surface from bottom to top by adjusting the position of the layered excavation guide line, and complete the excavation through the refresh command of CATIA Make adjustments until the design requirements are met. Finally, the measurement commands of CATIA are used to complete the classification engineering quantity statistics.

本发明通过平面分层的方式构建坝体底面至顶面的分层开挖基准线26,以创建坝体开挖面25。本发明改变了传统拱坝采用径向断面设计拱坝坝基开挖的传统方法,可以结合拱坝坝址区地质二维平切图和三维地质风化模型设计开挖面。另外,对于拱坝来说,开挖边坡纵向和水平向都会发生变化,且相互关联,因此本发明通过参数化设计分层开挖基准线26,方便总体调整开挖面,而且可以快速形成开挖面,查看调整后的整体效果,这样大大提高设计质量和效益。The present invention constructs the layered excavation reference line 26 from the bottom surface to the top surface of the dam body in a plane layering manner to create the dam body excavation surface 25. The present invention changes the traditional method of using radial sections to design arch dam foundation excavation, and can design the excavation surface by combining the geological two-dimensional plan view of the arch dam site area and the three-dimensional geological weathering model. In addition, for arch dams, both the longitudinal and horizontal directions of the excavation slope will change and are related to each other. Therefore, the present invention facilitates the overall adjustment of the excavation surface through parametric design of the hierarchical excavation baseline 26, and can quickly form Excavate the surface and check the overall effect after adjustment, which greatly improves the design quality and efficiency.

本发明通过建立水平的分层开挖基准线26,方便施工放线和控制开挖坡比,设计图纸和施工更好结合,从而加快施工进度。同时,本发明采用三维实体分类开挖可以从开挖面的颜色直接查看边坡设计的合理性,方便边坡设计的调整。By establishing a horizontal layered excavation reference line 26, the present invention facilitates construction setting out and control of excavation slope ratio, and better integrates design drawings and construction, thereby accelerating construction progress. At the same time, the present invention uses three-dimensional entity classification for excavation to directly check the rationality of the slope design from the color of the excavation surface, thereby facilitating the adjustment of the slope design.

以上所述,仅是本申请的几个实施例,并非对本申请做任何形式的限制,虽然本申请以较佳实施例揭示如上,然而并非用以限制本申请,任何熟悉本专业的技术人员,在不脱离本申请技术方案的范围内,利用上述揭示的技术内容做出些许的变动或修饰均等同于等效实施案例,均属于技术方案范围内。The above are only a few embodiments of the present application, and are not intended to limit the present application in any way. Although the present application is disclosed as above with preferred embodiments, they are not intended to limit the present application. Any skilled person familiar with this field, Without departing from the scope of the technical solution of this application, slight changes or modifications made using the technical content disclosed above are equivalent to equivalent implementation examples and fall within the scope of the technical solution.

Claims (10)

1.一种拱坝基础开挖设计方法,其特征在于,所述方法包括:1. An arch dam foundation excavation design method, characterized in that the method includes: S1、根据拱坝坝体三维模型,在拱坝坝址区的地形地质模型上创建坝顶上部开挖面;S1. Based on the three-dimensional model of the arch dam body, create an excavation surface for the upper part of the dam crest on the topographic and geological model of the arch dam site area; S2、在所述地形地质模型上构建从坝体底面高程至坝体顶面高程的分层开挖基准线,并根据所述分层开挖基准线创建坝体开挖面;S2. Construct a layered excavation baseline from the dam bottom elevation to the dam top elevation on the topographic geological model, and create a dam excavation surface based on the layered excavation baseline; S3、根据所述坝顶上部开挖面和所述坝体开挖面创建坝基开挖模型。S3. Create a dam foundation excavation model based on the upper excavation surface of the dam crest and the dam body excavation surface. 2.根据权利要求1所述的方法,其特征在于,在所述S3之后,所述方法还包括:2. The method according to claim 1, characterized in that, after the S3, the method further includes: 根据所述地形地质模型调整所述坝基开挖模型中的开挖坡比,得到更新后的坝基开挖模型。The excavation slope ratio in the dam foundation excavation model is adjusted according to the topographic geological model to obtain an updated dam foundation excavation model. 3.根据权利要求1所述的方法,其特征在于,在所述S1之前,所述方法还包括:3. The method according to claim 1, characterized in that, before the S1, the method further includes: 根据拱坝设计参数绘制坝体三维模型,并根据坝址区地质资料绘制拱坝坝址区的地形地质模型。Draw a three-dimensional model of the dam body based on the design parameters of the arch dam, and draw a topographic and geological model of the arch dam site area based on the geological data of the dam site area. 4.根据权利要求1所述的方法,其特征在于,所述S1具体为:4. The method according to claim 1, characterized in that, the S1 is specifically: 根据坝体三维模型和坝址区地质资料,在拱坝坝址区的地形地质模型上采用断面法创建坝顶上部开挖面。Based on the three-dimensional model of the dam body and the geological data of the dam site area, the cross-section method was used to create the upper excavation surface of the dam crest on the topographic geological model of the arch dam site area. 5.根据权利要求1所述的方法,其特征在于,所述S2中的在所述地形地质模型上构建从坝体底面高程至坝体顶面高程的分层开挖基准线,具体为:5. The method according to claim 1, characterized in that in S2, a layered excavation baseline from the bottom elevation of the dam body to the elevation of the dam top surface is constructed on the topographic geological model, specifically: 确定坝体底面高程上的坝体开挖轮廓,以及分层开挖的开挖层高和开挖坡比;Determine the excavation profile of the dam body on the elevation of the dam bottom surface, as well as the excavation layer height and excavation slope ratio of layered excavation; 根据所述坝体开挖轮廓以及分层开挖的开挖层高和开挖坡比,确定每层开挖面的分层开挖基准线。According to the excavation contour of the dam body and the excavation layer height and excavation slope ratio of the layered excavation, the layered excavation baseline of each layer of excavation surface is determined. 6.根据权利要求5所述的方法,其特征在于,根据所述坝体开挖轮廓以及分层开挖的开挖层高和开挖坡比,确定每层开挖面的分层开挖基准线,具体为:6. The method according to claim 5, characterized in that the layered excavation of each layer of excavation surface is determined according to the excavation profile of the dam body and the excavation layer height and excavation slope ratio of the layered excavation. Baseline, specifically: 将所述坝体开挖轮廓作为底层开挖基准线,并根据所述底层开挖基准线以及上一层开挖面的开挖层高和开挖坡比确定上一层开挖面的开挖边线;The excavation contour of the dam body is used as the base line of the bottom excavation, and the excavation level of the upper layer of excavation surface is determined based on the base line of the bottom layer of excavation and the excavation layer height and excavation slope ratio of the upper layer of excavation surface. dig edge; 根据所述开挖边线和预留马道宽度,形成上一层开挖面的分层开挖基准线,并将所述分层开挖基准线作为底层开挖基准线,依次逐层确定每层开挖面的分层开挖基准线。According to the excavation edge line and the reserved horse road width, a layered excavation datum line for the upper layer of excavation surface is formed, and the layered excavation datum line is used as the bottom layer excavation datum line, and each layer is determined layer by layer in turn. The layered excavation datum line for the excavation face. 7.根据权利要求6所述的方法,其特征在于,所述S2中的根据所述分层开挖基准线创建坝体开挖面,具体包括:7. The method according to claim 6, characterized in that, in S2, creating a dam excavation surface based on the hierarchical excavation baseline specifically includes: 将每层开挖面的开挖边线上的转折点和与其对应的底层开挖基准线上的转折点对应相连,形成每层开挖面的引导线;Correspondingly connect the turning points on the excavation edge line of each layer of excavation surface with the turning points on the corresponding bottom excavation baseline to form the guide line of each layer of excavation surface; 根据所述分层开挖基准线和所述引导线创建坝体开挖面。Create a dam excavation surface based on the layered excavation baseline and the guide line. 8.根据权利要求7所述的方法,其特征在于,根据所述分层开挖基准线和所述引导线创建坝体开挖面,具体包括:8. The method according to claim 7, characterized in that creating a dam excavation surface based on the layered excavation baseline and the guide line specifically includes: 根据所述分层开挖基准线和所述引导线形成开挖边坡面;Form an excavation slope surface according to the layered excavation baseline and the guide line; 以填充方式形成马道面,并将所述马道面与所述开挖边坡面接合形成坝体开挖面。The horse track surface is formed by filling, and the horse track surface is joined with the excavation side slope surface to form the dam body excavation surface. 9.根据权利要求2所述的方法,其特征在于,根据所述地形地质模型调整所述坝基开挖模型中的开挖坡比,得到更新后的坝基开挖模型,具体为:9. The method according to claim 2, characterized in that the excavation slope ratio in the dam foundation excavation model is adjusted according to the topographic geological model to obtain an updated dam foundation excavation model, specifically: 根据所述地形地质模型切割后的开挖面调整所述坝基开挖模型中的分层开挖基准线,得到更新后的坝基开挖模型。The layered excavation baseline in the dam foundation excavation model is adjusted according to the excavation surface cut by the topographic geological model to obtain an updated dam foundation excavation model. 10.根据权利要求1所述的方法,其特征在于,所述地形地质模型的岩层风化类型分为由上至下的强风化层、弱风化层和微风化层。10. The method according to claim 1, characterized in that the rock formation weathering types of the topographic geological model are divided into strongly weathered layer, weak weathered layer and lightly weathered layer from top to bottom.
CN202311645493.XA 2023-12-04 2023-12-04 A design method for arch dam foundation excavation Pending CN117669081A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311645493.XA CN117669081A (en) 2023-12-04 2023-12-04 A design method for arch dam foundation excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311645493.XA CN117669081A (en) 2023-12-04 2023-12-04 A design method for arch dam foundation excavation

Publications (1)

Publication Number Publication Date
CN117669081A true CN117669081A (en) 2024-03-08

Family

ID=90082098

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311645493.XA Pending CN117669081A (en) 2023-12-04 2023-12-04 A design method for arch dam foundation excavation

Country Status (1)

Country Link
CN (1) CN117669081A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002081008A (en) * 2000-09-11 2002-03-22 Kokusai Kogyo Co Ltd Earthwork design support system using digital map data
WO2014180101A1 (en) * 2013-05-10 2014-11-13 武汉大学 Cushion blasting method combining hole bottom damage control and fast excavation
CN105654550A (en) * 2015-09-24 2016-06-08 中国电建集团昆明勘测设计研究院有限公司 Three-dimensional geological display method for hydropower engineering side slope
CN106971422A (en) * 2017-03-31 2017-07-21 中国电建集团贵阳勘测设计研究院有限公司 Method for compiling stability analysis model of arch dam abutment based on CATIA
CN113051641A (en) * 2021-03-10 2021-06-29 长江勘测规划设计研究有限责任公司 Three-dimensional parametric modeling method applied to arch dam slope excavation
CN114021240A (en) * 2021-11-16 2022-02-08 中国电建集团成都勘测设计研究院有限公司 Modeling method for arch dam foundation surface excavation slope model based on 3DEXPERIENCE platform
CN114708414A (en) * 2022-04-19 2022-07-05 中铁二院工程集团有限责任公司 Engineering three-dimensional terrain data cutting and fusing method and system
CN116226970A (en) * 2023-01-03 2023-06-06 中国电建集团成都勘测设计研究院有限公司 Method for establishing slope BIM model based on 3DEXPERIENCE platform
CN116244802A (en) * 2023-02-27 2023-06-09 广西更维科技研发有限公司 BIM-based earth-rock dam engineering integral model integration method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002081008A (en) * 2000-09-11 2002-03-22 Kokusai Kogyo Co Ltd Earthwork design support system using digital map data
WO2014180101A1 (en) * 2013-05-10 2014-11-13 武汉大学 Cushion blasting method combining hole bottom damage control and fast excavation
CN105654550A (en) * 2015-09-24 2016-06-08 中国电建集团昆明勘测设计研究院有限公司 Three-dimensional geological display method for hydropower engineering side slope
CN106971422A (en) * 2017-03-31 2017-07-21 中国电建集团贵阳勘测设计研究院有限公司 Method for compiling stability analysis model of arch dam abutment based on CATIA
CN113051641A (en) * 2021-03-10 2021-06-29 长江勘测规划设计研究有限责任公司 Three-dimensional parametric modeling method applied to arch dam slope excavation
CN114021240A (en) * 2021-11-16 2022-02-08 中国电建集团成都勘测设计研究院有限公司 Modeling method for arch dam foundation surface excavation slope model based on 3DEXPERIENCE platform
CN114708414A (en) * 2022-04-19 2022-07-05 中铁二院工程集团有限责任公司 Engineering three-dimensional terrain data cutting and fusing method and system
CN116226970A (en) * 2023-01-03 2023-06-06 中国电建集团成都勘测设计研究院有限公司 Method for establishing slope BIM model based on 3DEXPERIENCE platform
CN116244802A (en) * 2023-02-27 2023-06-09 广西更维科技研发有限公司 BIM-based earth-rock dam engineering integral model integration method

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
冯海青;李贺林;: "高陡地形拱坝坝肩窑洞式开挖设计与施工", 云南水力发电, no. 04, 15 August 2013 (2013-08-15), pages 49 - 51 *
富安 等主编: "中国水利学会勘测专业委员会2021年年会暨学术交流会论文集 复杂条件下水利工程勘察与创新", 30 September 2021, 武汉:中国地质大学出版社, pages: 173 - 177 *
张万奎;徐典政;: "黄登水电站坝基开挖面三维地质展示的创新应用", 水力发电, no. 06, 12 June 2019 (2019-06-12), pages 35 - 38 *
潘家铮主编: "中国大坝50年", 30 September 2000, 北京:中国水利水电出版社, pages: 885 *
王超;黎满林;刘翔;: "大岗山水电站拱坝建基面开挖与基础处理设计", 人民长江, no. 22, 28 November 2012 (2012-11-28), pages 42 - 46 *

Similar Documents

Publication Publication Date Title
CN105138788B (en) A kind of road threedimensional model Full Parameterized method for building up
CN106097450B (en) A kind of contour lines creation method and device
CN109191566B (en) Three-dimensional terrace modeling method based on TIN
CN107679337A (en) A kind of method that irregular earthwork calculates in engineering survey
CN109472866B (en) A kind of modeling method of big geology Building Information Model
CN105184867A (en) Three-dimensional stratum modeling method based on regular grids and corner-point grid technology
CN101872376A (en) True three-dimensional road intelligent design method and system
CN107330140A (en) The method that transformer station is quickly vertically arranged is realized based on BIM technology
CN110750864A (en) Dam break flood demonstration early warning method and platform based on BIM technology
CN110189409B (en) PLAXIS-based rapid true three-dimensional geological modeling method and system
CN111986325B (en) An Implicit Sectioning Method for 3D Geological Model
CN110163965A (en) A kind of solid threedimensional model building method of monoclinal strate tectonic landform
CN111595403B (en) Engineering earthwork measuring method based on point cloud measuring technology
CN104200528B (en) Three-dimensional modeling method based on vector closure
CN113946980B (en) Step earth and stone volume calculation method and system for large strip mine excavation engineering
CN109657290A (en) Core wall dam design method based on CATIA and Excel
CN104732026A (en) Method for designing ore storage yard and earth-disposing site on gold mine
CN115099092B (en) Tailing pond seepage calculation method based on three-dimensional modeling
CN106023311B (en) Improve the method that dimensional topography generates precision
CN116778097A (en) Site design method based on unmanned aerial vehicle oblique photography technology and BIM technology
CN114549774A (en) A 3D stratigraphic modeling method based on borehole data
CN103871101A (en) Foundation pit and geologic body model seamless integration method based on three-dimensional Boolean operation
CN116401742A (en) Method for establishing panel dam toe board parameterized model by CATIA three-dimensional software
CN117669081A (en) A design method for arch dam foundation excavation
CN106814392B (en) The velocity modeling method in three-dimensional secondary closely plast fusion face

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Country or region after: China

Address after: 710001 No.57, East Street, Beilin District, Xi'an City, Shaanxi Province

Applicant after: Shaanxi Provincial Water Resources and Electric Power Survey and Design Institute (Group) Co.,Ltd.

Address before: 710001 No.57, East Street, Beilin District, Xi'an City, Shaanxi Province

Applicant before: Shaanxi Institute of Water Conservancy and Electricity Survey and Design

Country or region before: China