CN117610111A - Construction progress intelligent monitoring method, data integration platform, device and storage medium - Google Patents

Construction progress intelligent monitoring method, data integration platform, device and storage medium Download PDF

Info

Publication number
CN117610111A
CN117610111A CN202311373240.1A CN202311373240A CN117610111A CN 117610111 A CN117610111 A CN 117610111A CN 202311373240 A CN202311373240 A CN 202311373240A CN 117610111 A CN117610111 A CN 117610111A
Authority
CN
China
Prior art keywords
construction
information
building
building module
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311373240.1A
Other languages
Chinese (zh)
Inventor
余涛
李小勇
翟水生
申伟
宋熙
周强
彭智鹏
吴绍远
陈乾名
钟川
黄烨
岳刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Original Assignee
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRCC Harbour and Channel Engineering Bureau Group Co Ltd filed Critical CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Priority to CN202311373240.1A priority Critical patent/CN117610111A/en
Publication of CN117610111A publication Critical patent/CN117610111A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Abstract

The application relates to the technical field of engineering construction, in particular to an intelligent construction progress monitoring method, a data integration platform, a device and a storage medium. The intelligent construction progress monitoring method is applied to a data integration platform and comprises the steps of obtaining a building BIM drawing, wherein the building BIM drawing comprises a plurality of building module information of an engineering building; carrying out construction numbering on the plurality of building module information according to the construction sequence, wherein each construction number represents a specific construction area; generating a bill of materials based on the information of each building module and the corresponding construction number, wherein the bill of materials contains various material information; and acquiring the state information of the material corresponding to the material information, and carrying out color marking on the building module corresponding to the building module information according to the state information, wherein the building module after color marking is shown, so that convenience of checking the construction progress of staff is improved.

Description

Construction progress intelligent monitoring method, data integration platform, device and storage medium
Technical Field
The application relates to the technical field of engineering construction, in particular to an intelligent construction progress monitoring method, a data integration platform, a device and a storage medium.
Background
In engineering construction, it is often necessary to monitor the progress of the construction.
In the related art, the manner of monitoring the progress of construction includes the following three types. The method comprises the steps of monitoring by adopting manpower, printing out a two-dimensional drawing of an engineering building by a worker, periodically obtaining the working procedure completion or material use condition, analyzing the construction progress according to the working procedure completion or material use condition, and finally marking on the two-dimensional drawing. And secondly, the electronic table is adopted for monitoring, and workers directly record the process completion or material use condition in the electronic table. Thirdly, an informatization system such as ERP (Enterprise Resource Planning ), SCM (Software configuration management, software configuration management), PLM (Product Lifetime Management, product life cycle management system) and the like is adopted to automatically collect data and monitor construction progress.
For the above related art, the inventors consider that the first mode is purely manual monitoring, which is low in efficiency. The second way is manual entry, which is prone to error. The third mode can reduce the error probability while ensuring the efficiency, but the data are shown in the form of characters no matter ERP, SCM or PLM, so that workers need to check each module in the engineering building respectively, and the construction progress is difficult to intuitively see. Therefore, convenience of checking the construction progress by the staff is still to be improved.
Disclosure of Invention
In order to help to improve convenience of checking construction progress of staff, the application provides a construction progress intelligent monitoring method, a data integration platform, a device and a storage medium.
In a first aspect, the application provides a construction progress intelligent monitoring method, which adopts the following technical scheme:
the construction progress intelligent monitoring method is applied to a data integration platform, and comprises the following steps:
acquiring a building BIM drawing, wherein the building BIM drawing comprises a plurality of building module information of an engineering building;
carrying out construction numbering on a plurality of building module information according to a construction sequence, wherein each construction number represents a specific construction area;
generating a bill of materials based on the building module information and the corresponding construction numbers, wherein the bill of materials comprises various material information;
and acquiring state information of the materials corresponding to the material information, and carrying out color marking on the building module corresponding to the building module information according to the state information to show the building module after color marking.
Through adopting above-mentioned technical scheme, when being under construction, the data integration platform at first acquires building BIM drawing, and building BIM drawing is three-dimensional drawing, generally by the diagrammer, contains a plurality of building module information of engineering construction in the building BIM drawing. And the data integration platform carries out construction numbering on the plurality of building module information according to the construction sequence, obtains the corresponding building module information by obtaining each construction numbering opportunity, and then analyzes the building module information to generate a bill of materials containing various material information. After acquiring the bill of materials, the data integration platform acquires the state information of the materials corresponding to the material information, the building condition of the building module corresponding to the material information can be determined, then the data integration platform can carry out color marking on the building module corresponding to the building module information according to the state information, and finally the data integration platform shows the building module after the color marking, so that the building modules with different construction progress are distinguished through colors, and convenience of checking the construction progress by workers is improved.
Optionally, before the building module is color-labeled according to the state information, the method further includes:
and clearing the color information of the building BIM drawing, wherein the color information is information for distinguishing the colors of the building modules when a drafter makes the building BIM drawing.
By adopting the technical scheme, when a diagrammer draws, different building modules are often distinguished by adopting different colors, and the color information of the different building modules can influence the color marking of the data integration platform on the building modules, so that the sight of the staff can be disturbed. Therefore, the data integration platform removes the original color information on the building BIM drawing, and can effectively reduce the interference of the color information on the sight of staff during drawing.
Optionally, the generating a plurality of bill of materials based on each building module information and each corresponding construction number includes:
acquiring the construction number;
reading the building module information based on the construction number, wherein the building module information comprises at least one piece of material information;
and adding the construction number and the material information to the bill of materials.
Through adopting above-mentioned technical scheme, after data integration platform obtains the construction number, can obtain the building module information that corresponds with the number, then data integration platform can read the material information in the building module information, later can add construction number and corresponding material information in the bill of materials to realize the acquisition to the bill of materials.
Optionally, the obtaining the state information of the material corresponding to the material information includes:
generating a milestone standardized design table based on the bill of materials, wherein the milestone standardized design table comprises at least two kinds of state information in purchasing, warehousing, transporting, receiving, installing, testing and checking and accepting;
in any construction step, obtaining a graphic code or chip information on the material, wherein the graphic code or the chip information contains the material information;
based on the graphical code or the chip information, the status information in the milestone standardized design form is dynamically updated.
By adopting the technical scheme, after the bill of materials is obtained by the data integration platform, the milestone standardized design table can be generated, wherein the transverse table head of the milestone standardized design table comprises at least two kinds of state information in purchasing, warehousing, transportation, receiving, installing, testing and checking and receiving, and the longitudinal table head of the milestone standardized design table is the material information in the bill of materials. In any construction step, the data integration platform can acquire the graphic codes on the materials scanned by the code scanning gun, then the state information of the corresponding materials can be determined according to the graphic codes, and then the milestone standardized design table can be updated according to dynamics.
Optionally, any one of the state information of the building modules corresponds to a labeling color, and the color labeling of the building module corresponding to the building module information according to the state information includes:
acquiring the state information in the milestone standardized design table;
and dynamically updating the color label of the building module based on the construction number and the state information.
By adopting the technical scheme, in the process of dynamically updating the milestone standardized design table by the data integration platform, the data integration platform can dynamically update the color marking of the building module according to the state information in the table and the construction number corresponding to the material information, thereby marking different colors of the building modules with different construction progress.
Optionally, the construction progress intelligent monitoring method further comprises the following steps:
acquiring a construction schedule, wherein the construction schedule comprises planning construction completion time planned by each material; acquiring the actual construction completion time of the material based on the state information;
and if the actual construction completion time is later than the planned construction completion time, displaying progress hysteresis prompt information.
By adopting the technical scheme, the actual construction completion time of the material can be obtained according to the state information in the process of dynamically updating the milestone standardized design table. Before construction begins, a construction progress planning table is provided, the data integration platform can acquire the construction planning table, so that planning construction completion time planned by each material is acquired, then the data integration platform compares the planning construction completion time with actual construction completion time, whether the progress is lagged or not can be determined, and if the actual construction completion time is later than the planning construction completion time, the data integration platform can show prompt information after the progress.
Optionally, the construction progress intelligent monitoring method further comprises the following steps:
constructing a construction progress monitoring directory tree, wherein the construction progress monitoring directory tree comprises at least one system directory, at least one batch directory under the system directory and a plurality of component directories under the batch directory;
the building module information is added to the component catalog based on the status information and the construction number.
By adopting the technical scheme, the data integration platform can monitor the directory tree for the construction progress of the system directory, the batch directory and the component directory by the component structure, and then add the building module information to the component directory according to the state information and the construction number, so that workers can check the specific conditions of the building module information in a classified manner.
In a second aspect, the present application provides a data integration platform, which adopts the following technical scheme:
a data integration platform, the data integration platform comprising:
the system comprises an acquisition module, a storage module and a storage module, wherein the acquisition module is used for acquiring a building BIM drawing, and the building BIM drawing contains a plurality of building module information of an engineering building; the method is also used for acquiring state information of the materials corresponding to the material information;
the processing module is used for numbering the construction of a plurality of building module information according to the construction sequence, and each construction number represents a specific construction area;
the generating module is used for generating a bill of materials based on the building module information and the corresponding construction numbers, wherein the bill of materials contains various material information;
the color labeling module is used for color labeling of the building module corresponding to the building module information according to the state information; and the display module is used for showing the building module after color marking.
Through adopting above-mentioned technical scheme, at the in-process that data integration platform carries out the color mark to the building module, at first acquire the building BIM drawing that the module can acquire a plurality of building module information that contain engineering construction, then processing module can carry out construction serial number with a plurality of building module information according to the construction order, later generate module according to building module information and corresponding construction serial number and generate the bill of materials that contains multiple material information, later acquire the state information of the material that corresponds with the material information again. And the color marking module marks the colors of the building modules corresponding to the building module information according to the state information, and finally the display module shows the building modules after the colors are marked, so that the building modules can present different colors according to the construction progress, and convenience of checking the construction progress by workers can be improved.
In a third aspect, the present application provides a computer apparatus, which adopts the following technical scheme:
the computer device comprises a processor, a memory and a computer program which is stored in the memory and can run on the processor, wherein the processor realizes the intelligent monitoring method of the construction progress when executing the computer program.
By adopting the technical scheme, the computer device capable of implementing the intelligent monitoring method for the construction progress is provided.
In a fourth aspect, the present application provides a computer readable storage medium, which adopts the following technical scheme:
a computer-readable storage medium storing a computer program; the computer program realizes the intelligent monitoring method of the construction progress when being executed by the processor.
By adopting the technical scheme, the carrier of the computer program of the intelligent monitoring method for the construction progress is provided.
In summary, the application has the following beneficial technical effects: when constructing, the data integration platform can carry out the color mark to the building module that building module information corresponds according to state information to can distinguish the building module of different construction progress through the colour, and then can help promoting the staff and look over the convenience of construction progress.
Drawings
FIG. 1 is a block flow diagram of a construction progress intelligent monitoring method in an embodiment of the application;
FIG. 2 is a flow chart of yet another intelligent monitoring method for construction progress in an embodiment of the present application;
fig. 3 is a schematic diagram of a data integration platform according to an embodiment of the present application.
Reference numerals illustrate:
1. an acquisition module; 2. a processing module; 3. a generating module; 4. a color labeling module; 5. and a display module.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application will be further described in detail with reference to fig. 1 to 3 and the embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the present application.
The embodiment of the application discloses an intelligent construction progress monitoring method which is applied to a data integration platform.
Referring to fig. 1, the construction progress intelligent monitoring method includes the steps of:
s102, acquiring a building BIM drawing.
Before construction, a drafter of a building design house or other drafter can drafte according to the actual conditions of the engineering building, so that a building BIM drawing is prepared, and the building BIM drawing contains a plurality of building module information of the engineering building. The drafter can upload the building BIM drawing to the data integration platform through the desktop computer, and the acquisition module 1 can acquire the building BIM drawing.
The desktop computer in the embodiment of the application can also be used as a tablet personal computer, a mobile phone, a mobile wearable device and other communication devices.
S104: and numbering the construction modules according to the construction sequence.
In one project, a construction schedule is planned before construction, and the construction schedule comprises planned construction completion time planned by each material. The staff can upload the construction schedule through the desktop computer, and the acquisition module 1 can acquire the construction schedule.
And then the processing module 2 analyzes the construction schedule to obtain the construction sequence of the engineering building. The processing module 2 can then perform construction numbering on the plurality of building module information according to the construction sequence, wherein the building module information corresponding to each construction number corresponds to a specific construction area.
The conventional construction schedule is usually a Gantt chart, wherein the transverse gauge heads are time gauge heads, and the longitudinal gauge heads are material gauge heads. In the process of the processing module 2 performing construction numbering on the building module information, since each material has a start construction time and an end construction time, the processing module 2 can determine the construction sequence by acquiring the start construction time of the material.
In one possible embodiment, the materials in the construction schedule include a first layer of body, a second layer of body, a third layer of body, a first layer of door and window, a second layer of door and window, and a third layer of door and window. In another possible embodiment, the materials in the construction schedule include a one-layer glass curtain wall, a two-layer glass curtain wall, and a three-layer glass curtain wall. In yet another possible embodiment, the materials in the construction schedule plan include zone a steel pipe pile, zone B steel pipe pile, zone C steel pipe pile, zone a body steel structure, zone B body steel structure, zone C body steel structure, zone a load carrying platform, zone B load carrying platform, zone C load carrying platform.
S106: and generating a bill of materials based on the building module information and the corresponding construction number.
After the acquiring module 1 acquires the building module information and the processing module 2 acquires the construction number, the acquiring module 1 can acquire the construction number, and then can determine the corresponding building module information according to the construction number, and since the building module information is materials such as a cross beam, a longitudinal beam, a glass curtain wall, a door, a window and the like, the generating module 3 can add each building module information and each construction number corresponding to the building module information to the bill of materials, so that the bill of materials can contain a plurality of pieces of material information corresponding to each building module information.
S108: and acquiring state information of the material corresponding to the material information.
After the generating module 3 generates the bill of materials, the milestone standardized design table can be generated according to the bill of materials. The milestone standardized design table is a state table of each material, and comprises state information of purchase, warehouse entry, transportation, receiving, installation, test, acceptance and the like of the materials. Of course, the status information in the milestone standardized design form can be adjusted according to the actual construction needs.
In one possible implementation, during construction of an engineering building, a worker can post an RFID (Radio Frequency Identification ) chip on a material and input material information in the RFID chip. Then in any construction step, the data integration platform can identify the RFID chip on the material through the control chip identification equipment, namely the identification time, the material information and the step where the material is located can be obtained, so that the state information of the material can be obtained based on the chip information, and the generation module 3 can dynamically update the corresponding state information of the material in the milestone standardized design table.
In another possible embodiment, during the construction of the engineering building, the staff can post graphic codes on the materials and input material information in the graphic codes. Then in any construction step, the data integration platform can identify the graphic code on the material by controlling the code scanning equipment, namely the identification time, the material information and the step where the material is located can be obtained, so that the state information of the material can be obtained based on the graphic code, and the generation module 3 can dynamically update the corresponding state information of the material in the milestone standardized design table.
In the embodiment of the present application, the graphic Code is a QR Code (Quick response Code). In other embodiments, the graphic code may be a DM code (daatrix two-dimensional code), PDF417 two-dimensional code, maxiCode two-dimensional code, or a han-xin code.
Specifically, in one possible implementation, if the materials in the milestone standardized design table include glass curtain walls, steel structures, doors and windows, and the state information of the glass curtain walls is transportation, the state information of the steel structures is acceptance, the state information of the doors is installation, and the state information of the windows is installation, the milestone standardized design table is as follows in table 1:
type(s) Purchasing Warehouse entry Transportation of Receiving goods Mounting Testing Acceptance check
Glass curtain wall
Steel structure
Door
Window
TABLE 1
S110: and carrying out color marking on the building module corresponding to the building module information according to the state information.
In the data integration platform, any one of the state information of the building module corresponds to one of the labeling colors. Therefore, after the milestone standardized design table is dynamically updated, the acquisition module 1 can acquire the updated milestone standardized design table, and then the color marking module 4 can dynamically update the color marking of the building module according to the corresponding construction number and state information.
In one possible implementation, the status information of the material is red for the building module during purchase, orange for the building module during warehouse entry, yellow for the building module during transportation, green for the building module during receiving, cyan for the building module during installation, blue for the building module during testing, and purple for the building module during acceptance. Of course, the staff can set the labeling color and state information by himself.
S112: showing the color-coded building block.
The display module 5 directly shows the building module marked with colors through a display screen.
In an alternative embodiment of the present application, referring to fig. 2, the construction progress intelligent monitoring method further includes the following steps:
s202: and (5) clearing the color information of the building BIM drawing.
When a diagrammer draws a drawing, in order to display the position relation of each module in the building BIM drawing, the diagrammer may make color labeling on each building module, and meanwhile, the distinction of different building modules is realized. This portion of the color information may cause line-of-sight interference with the color labeling of the building module by the data integration platform.
Therefore, it can be understood that the processing of the color information can be further included before the color labeling of the building module according to the state information, and the color information of the building BIM drawing is only required to be cleared through the processing module 2, so that the interference of the color information on the building module after the color labeling is reduced.
S204: and constructing a construction progress monitoring directory tree, and adding building module information into the component directory.
Firstly, a worker enters the data integration platform through a desktop computer, and then clicks a corresponding interface in the data integration platform through a mouse, so that the worker can enter a designated editing interface. And then, a new directory tree is established in the appointed editing interface, and the new directory tree is named, so that a plurality of system directories, a plurality of batch directories under the system directories and a plurality of component directories under the batch directories are formed.
All building module information of a single engineering building can be displayed in each system catalog, and workers can add the engineering building information to the component catalog according to batches. Wherein, the staff can add according to the state information and the construction number of material, can understand that when the staff issues the interpolation instruction, handle by processing module 2, and the staff only need the input construction number can accomplish corresponding interpolation.
S206: and when the actual construction completion time is later than the planned construction completion time, the progress delay prompt information is shown.
After the obtaining module 1 obtains the construction schedule, the planned construction completion time planned by each material included in the construction schedule can be obtained.
Likewise, in the dynamic updating process of the milestone standardized design table, the actual construction completion time of the material can be known as long as the state information of the material is acceptance.
And the processing module 2 can compare the actual construction completion time with the planned construction completion time, and if the actual construction completion time is later than the planned construction completion time, the display module 5 can show progress delay prompt information so as to remind workers of construction progress delay.
Based on the same design concept, the embodiment also discloses a data integration platform.
Referring to fig. 3, the data integration platform is configured to execute each step and corresponding technical effects in the construction progress intelligent monitoring method shown in the foregoing embodiments and possible implementation manners. The data integration platform comprises an acquisition module 1, a processing module 2, a generation module 3, a color labeling module 4 and a display module 5.
The acquisition module 1 is used for acquiring a building BIM drawing, wherein the building BIM drawing comprises a plurality of building module information of an engineering building; and the method is also used for acquiring the state information of the material corresponding to the material information.
And a processing module 2 for numbering the construction modules according to the construction sequence, wherein each construction number represents a specific construction area.
And the generating module 3 is used for generating a bill of materials based on the information of each building module and the corresponding construction numbers, wherein the bill of materials contains various material information.
And the color marking module 4 is used for marking the colors of the building modules corresponding to the building module information according to the state information.
And the display module 5 is used for showing the building module after color marking.
The present application also provides a computer readable storage medium storing instructions that when loaded and executed by a processor perform the above steps.
The computer-readable storage medium includes, for example: a U-disk, a removable hard disk, a Read-Only Memory (ROM), a random access Memory (Random Access Memory, RAM), a magnetic disk, or an optical disk, or other various media capable of storing program codes.
Based on the same inventive concept, embodiments of the present application provide a computer apparatus comprising a memory and a processor, the memory having stored thereon a computer program that can be loaded by the processor and perform the above method.
It will be apparent to those skilled in the art that, for convenience and brevity of description, only the above-described division of the functional modules is illustrated, and in practical application, the above-described functional allocation may be performed by different functional modules according to needs, i.e. the internal structure of the apparatus is divided into different functional modules to perform all or part of the functions described above. The specific working processes of the above-described systems, devices and units may refer to the corresponding processes in the foregoing method embodiments, which are not described herein.
In the several embodiments provided in this application, it should be understood that the disclosed systems, apparatuses, and methods may be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative, e.g., the division of the modules or units is merely a logical functional division, and there may be additional divisions when actually implemented, e.g., multiple units or components may be combined or integrated into another system, or some features may be omitted, or not performed. Alternatively, the coupling or direct coupling or communication connection shown or discussed with each other may be an indirect coupling or communication connection via some interfaces, devices or units, which may be in electrical, mechanical or other form.
The units described as separate units may or may not be physically separate, and units shown as units may or may not be physical units, may be located in one place, or may be distributed on a plurality of network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
In addition, each functional unit in each embodiment of the present application may be integrated in one processing unit, or each unit may exist alone physically, or two or more units may be integrated in one unit. The integrated units may be implemented in hardware or in software functional units.
The integrated units, if implemented in the form of software functional units and sold or used as stand-alone products, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present application may be embodied in essence or a part contributing to the prior art or all or part of the technical solution, in the form of a software product stored in a storage medium, including several instructions to cause a computer device (which may be a personal computer, a server, or a network device, etc.) or a processor (processor) to perform all or part of the steps of the methods described in the embodiments of the present application. And the aforementioned storage medium includes: various media capable of storing program codes, such as a U disk, a mobile hard disk, a read-only memory, a random access memory, a magnetic disk or an optical disk.
The foregoing embodiments are only used for describing the technical solution of the present application in detail, but the descriptions of the foregoing embodiments are only used for helping to understand the method and the core idea of the present application, and should not be construed as limiting the present application. Variations or alternatives that are readily contemplated by those skilled in the art within the scope of the present disclosure are intended to be encompassed within the scope of the present disclosure.

Claims (10)

1. The construction progress intelligent monitoring method is characterized by being applied to a data integration platform, and comprises the following steps:
acquiring a building BIM drawing, wherein the building BIM drawing comprises a plurality of building module information of an engineering building;
carrying out construction numbering on a plurality of building module information according to a construction sequence, wherein each construction number represents a specific construction area;
generating a bill of materials based on the building module information and the corresponding construction numbers, wherein the bill of materials comprises various material information;
and acquiring state information of the materials corresponding to the material information, and carrying out color marking on the building module corresponding to the building module information according to the state information to show the building module after color marking.
2. The construction progress intelligent monitoring method of claim 1, further comprising, before color marking the building module according to the status information:
and clearing the color information of the building BIM drawing, wherein the color information is information for distinguishing the colors of the building modules when a drafter makes the building BIM drawing.
3. The method of claim 1, wherein generating a plurality of bill of materials based on each of the building module information and each of the corresponding construction numbers comprises:
acquiring the construction number;
reading the building module information based on the construction number, wherein the building module information comprises at least one piece of material information;
and adding the construction number and the material information to the bill of materials.
4. The construction progress intelligent monitoring method according to claim 3, wherein the obtaining the state information of the material corresponding to the material information includes:
generating a milestone standardized design table based on the bill of materials, wherein the milestone standardized design table comprises at least two kinds of state information in purchasing, warehousing, transporting, receiving, installing, testing and checking and accepting;
in any construction step, obtaining a graphic code or chip information on the material, wherein the graphic code or the chip information contains the material information;
based on the graphical code or the chip information, the status information in the milestone standardized design form is dynamically updated.
5. The intelligent monitoring method for construction progress according to claim 4, wherein any one of the status information of the building modules corresponds to a labeling color, and the color labeling of the building module corresponding to the building module information according to the status information comprises:
acquiring the state information in the milestone standardized design table;
and dynamically updating the color label of the building module based on the construction number and the state information.
6. The construction progress intelligent monitoring method of claim 1, further comprising:
acquiring a construction schedule, wherein the construction schedule comprises planning construction completion time planned by each material;
acquiring the actual construction completion time of the material based on the state information;
and if the actual construction completion time is later than the planned construction completion time, displaying progress hysteresis prompt information.
7. The construction progress intelligent monitoring method of claim 1, further comprising:
constructing a construction progress monitoring directory tree, wherein the construction progress monitoring directory tree comprises at least one system directory, at least one batch directory under the system directory and a plurality of component directories under the batch directory;
the building module information is added to the component catalog based on the status information and the construction number.
8. A data integration platform, the data integration platform comprising:
the system comprises an acquisition module (1) for acquiring a building BIM drawing, wherein the building BIM drawing comprises a plurality of building module information of an engineering building; the method is also used for acquiring state information of the materials corresponding to the material information;
the processing module (2) is used for numbering the construction of a plurality of building module information according to the construction sequence, and each construction number represents a specific construction area;
the generating module (3) is used for generating a bill of materials based on the building module information and the corresponding construction numbers, wherein the bill of materials contains various material information;
the color marking module (4) is used for marking the colors of the building modules corresponding to the building module information according to the state information;
and the display module (5) is used for showing the building module after color marking.
9. Computer device, characterized in that it comprises a processor, a memory and a computer program stored in the memory and executable on the processor, the processor implementing the construction progress intelligent monitoring method according to any one of claims 1-7 when executing the computer program.
10. A computer-readable storage medium, wherein the computer storage medium stores a computer program; the computer program, when executed by a processor, implements the construction progress intelligent monitoring method according to any one of claims 1 to 7.
CN202311373240.1A 2023-10-20 2023-10-20 Construction progress intelligent monitoring method, data integration platform, device and storage medium Pending CN117610111A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311373240.1A CN117610111A (en) 2023-10-20 2023-10-20 Construction progress intelligent monitoring method, data integration platform, device and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311373240.1A CN117610111A (en) 2023-10-20 2023-10-20 Construction progress intelligent monitoring method, data integration platform, device and storage medium

Publications (1)

Publication Number Publication Date
CN117610111A true CN117610111A (en) 2024-02-27

Family

ID=89946945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311373240.1A Pending CN117610111A (en) 2023-10-20 2023-10-20 Construction progress intelligent monitoring method, data integration platform, device and storage medium

Country Status (1)

Country Link
CN (1) CN117610111A (en)

Similar Documents

Publication Publication Date Title
Motamedi et al. Lifecycle management of facilities components using radio frequency identification and building information model
Dutta et al. Managing a big data project: the case of ramco cements limited
Brintrup et al. RFID opportunity analysis for leaner manufacturing
Chow et al. Design of a RFID case-based resource management system for warehouse operations
US7378969B2 (en) Systems and methods for visualizing auto-id data
US8839132B2 (en) Method and system for providing visual instructions to warehouse operators
US7707064B2 (en) RFID receiving process for use with enterprise resource planning systems
US9262741B1 (en) Continuous barcode tape based inventory location tracking
US8269606B2 (en) Methods and systems for RFID tag read verification
US6615096B1 (en) Method using statistically analyzed product test data to control component manufacturing process
CN104392297A (en) Method and system for realizing non-business process irregularity detection in large data environment
CN113807651A (en) Big data based component whole process management system, terminal equipment and management method
KR102255695B1 (en) Expandable manufacturing Execution System
Kabadurmus et al. Design of pull production control systems using axiomatic design principles
CN109117962A (en) A kind of outgoing upkeep operation tool management system and computer readable storage medium
CN117610111A (en) Construction progress intelligent monitoring method, data integration platform, device and storage medium
CN104616128A (en) Method and system for optimizing dispatching based on RFID (Radio Frequency Identification Device)
Lao et al. An RFRS that combines RFID and CBR technologies
CA2723355C (en) Method and system for providing visual instructions to warehouse operators
Kafi et al. Essential of RFID technology in supply chain management: A review on digital perspective
CN114781027A (en) BIM-based digital steel structure building construction method and system
CN106021624A (en) ETL (extract-transform-load) model generation method and device
US10685313B2 (en) Systems and/or methods for path finding on model structures
Dighero et al. RFID: The Real and Integrated Story.
Cudzilo et al. Improving the efficiency of planning and execution of deliveries with the use of a location register based on GLN identifiers

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination