CN117328939A - Tunnel construction plan generation method, system, equipment and medium - Google Patents

Tunnel construction plan generation method, system, equipment and medium Download PDF

Info

Publication number
CN117328939A
CN117328939A CN202311265090.2A CN202311265090A CN117328939A CN 117328939 A CN117328939 A CN 117328939A CN 202311265090 A CN202311265090 A CN 202311265090A CN 117328939 A CN117328939 A CN 117328939A
Authority
CN
China
Prior art keywords
construction
specific
tunnel
determining
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311265090.2A
Other languages
Chinese (zh)
Inventor
罗春雨
吴军
康海波
唐勇
陈先国
邓亨长
王红梅
易长清
范仁玉
王华玲
颜柳
黄华
汪龙
魏霞
罗峰
王占军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Highway Tunnel Branch Of Sichuan Highway And Bridge Construction Group Co ltd
Original Assignee
Highway Tunnel Branch Of Sichuan Highway And Bridge Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Highway Tunnel Branch Of Sichuan Highway And Bridge Construction Group Co ltd filed Critical Highway Tunnel Branch Of Sichuan Highway And Bridge Construction Group Co ltd
Priority to CN202311265090.2A priority Critical patent/CN117328939A/en
Publication of CN117328939A publication Critical patent/CN117328939A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/006Ventilation at the working face of galleries or tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F5/00Means or methods for preventing, binding, depositing, or removing dust; Preventing explosions or fires
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Business, Economics & Management (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Architecture (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to a tunnel construction plan generation method, a system, equipment and a medium, which belong to the technical field of tunnel construction, wherein the plan generation method comprises the following steps: obtaining geological condition data of a current face pile number; based on a preset construction method library, determining a corresponding construction method according to the category of surrounding rock; determining corresponding specific construction measures according to the specific geological condition monitoring data and the harmful gas monitoring data; performing procedure operation adjustment on the construction method according to specific construction measures to generate corresponding construction procedures; determining a preset cyclic footage of the face pile number according to the surrounding rock category and the construction method; determining a corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and a preset cyclic footage; and receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining the construction procedure and the construction operation prediction time. The construction planning method and the construction planning device can reasonably coordinate and plan the construction plan according to the actual condition of the construction site, and improve the construction efficiency.

Description

Tunnel construction plan generation method, system, equipment and medium
Technical Field
The present disclosure relates to the field of tunnel construction technologies, and in particular, to a method, a system, an apparatus, and a medium for generating a tunnel construction plan.
Background
Along with the rapid development of national economy and the continuous perfection of traffic infrastructure construction, the tunnel construction technology has significantly advanced. From initial manual excavation to current mechanical and automatic construction, tunnel construction is greatly improved in speed, quality, safety and the like.
The tunnel construction is usually managed according to the construction cycle, and is generally to predict the footage of one week or one month and make a corresponding annual or monthly construction plan, and each month makes a construction plan of the next month according to the completion condition.
At present, tunnel construction plans are mostly formulated in advance according to construction experience of technicians, and due to lack of accuracy and flexibility, when some sudden geological conditions are faced, construction progress delay can be caused by incapability of timely adjusting the construction plans. Therefore, in order to improve the construction efficiency, how to reasonably coordinate and plan the construction plan according to the actual situation of the construction site is a problem to be solved at present.
Disclosure of Invention
In order to reasonably coordinate and plan a construction plan according to actual conditions of a construction site, the application provides a tunnel construction plan generation method, a system, equipment and a medium.
In a first aspect, the present application provides a tunnel construction plan generating method, which adopts the following technical scheme:
a tunnel construction plan generation method, the plan generation method comprising:
obtaining geological condition data of a current face pile number; the geological condition data comprise surrounding rock types, specific geological condition monitoring data and harmful gas monitoring data;
based on a preset construction method library, determining a corresponding construction method according to the surrounding rock category;
determining corresponding specific construction measures according to the specific geological condition monitoring data and the harmful gas monitoring data;
performing procedure operation adjustment on the construction method according to the specific construction measures to generate corresponding construction procedures;
determining a preset circulating footage of the face pile number according to the surrounding rock category and the construction method;
determining corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and the preset cyclic footage;
and receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining the construction procedure and the construction operation prediction time.
By adopting the technical scheme, the geological condition data such as the surrounding rock category of the current face pile number, the specific geological condition monitoring data, the harmful gas monitoring data and the like are obtained from the advanced geological forecast data or the construction design data so as to comprehensively know the geological condition of the construction area, wherein the corresponding standard construction method can be obtained according to the surrounding rock category so as to ensure that the construction method is matched with geological conditions; corresponding specific construction measures can be obtained according to the specific geological condition monitoring data and the harmful gas monitoring data so as to reduce construction risks; and (3) performing procedure adjustment on the construction method according to specific construction measures to ensure smooth construction process, determining a preset cyclic footage of the face pile number and a corresponding construction operation prediction duration according to surrounding rock types and the construction method, and generating a corresponding tunnel construction plan by combining the construction operation prediction duration, construction organization information input by a user and the adjusted construction procedure.
By accurately acquiring the geological condition data, a construction method is flexibly selected according to the actual geological condition of a construction site, specific construction measures are adopted to adjust working procedures, meanwhile, the circulating footage and the predicted duration of construction operation are reasonably determined, and a tunnel construction plan is generated by combining construction organization information, so that the construction efficiency is improved, the construction risk is reduced, and the smooth progress of tunnel construction is ensured.
Optionally, the step of determining the corresponding specific construction measure according to the specific geological condition monitoring data and the harmful gas monitoring data includes:
judging whether a specific geological condition and/or a harmful gas exceeding standard condition exists or not according to the specific geological condition monitoring data and the harmful gas monitoring data;
if yes, determining a corresponding severity level based on a preset construction measure database according to the specific geological condition monitoring data and/or the harmful gas monitoring data;
and determining corresponding specific construction measures according to the severity level of the specific geological condition and/or the harmful gas exceeding condition.
By adopting the technical scheme, the specific geological condition and the harmful gas exceeding condition are divided into different severity levels, and corresponding treatment measures are determined according to the different severity levels, so that proper measures can be adopted in a targeted manner according to specific conditions, and the safety of tunnel construction and the smooth progress of a construction plan are ensured.
Optionally, after generating the corresponding tunnel construction plan, the method further includes:
monitoring specific geological condition monitoring data and harmful gas monitoring data of the face pile number in real time;
judging whether the specific geological condition and/or the harmful gas exceeding condition have changes or not;
if so, determining the changed specific construction measures according to the changed specific geological conditions and/or the harmful gas exceeding conditions;
and carrying out procedure operation adjustment on the construction procedure of the tunnel construction plan according to the changed specific construction measures so as to regenerate the tunnel construction plan.
By adopting the technical scheme, in the process of generating a construction plan and constructing according to the construction plan, the specific geological condition and the harmful gas exceeding condition of the current construction position are monitored in real time, whether the change condition exists when the construction plan is generated last time is judged, the change condition can be timely dealt with by determining the specific construction measure after the change and adjusting the construction plan, the safety and the smoothness of tunnel construction are ensured, so that the construction quality is improved, the risk is reduced, and the construction progress is effectively controlled.
Optionally, the step of determining the corresponding predicted duration of the construction operation according to the surrounding rock category, the construction procedure and the preset cyclic footage includes:
performing data preprocessing on the surrounding rock category, the construction procedure and the preset cyclic footage to obtain a corresponding model input value;
and inputting the model input value into a pre-trained construction operation duration prediction model to obtain the construction operation prediction duration.
By adopting the technical scheme, the prediction of the construction operation time length can be performed in a neural network model prediction mode according to surrounding rock types, construction procedures, preset circulating entering rules and other influencing factors influencing the tunnel construction operation time length.
Optionally, the plan generating method further includes:
receiving the actual duration of the construction operation input by a user;
correcting the predicted construction operation duration according to the actual construction operation duration;
and regenerating the tunnel construction plan according to the corrected construction operation prediction time length.
By adopting the technical scheme, when each construction cycle is completed and the acquired actual duration of the construction operation exceeds or is advanced to the predicted duration, the predicted duration is corrected in real time, the construction plan is regenerated, and the actual construction condition is compared with the construction plan, so that the construction progress and the resource allocation are convenient to adjust and optimize in time, and the accuracy and the operability of the construction plan are improved.
Optionally, after generating the tunnel construction plan, the method further includes:
analyzing to obtain the predicted construction operation duration according to the tunnel construction plan;
judging whether the predicted construction operation duration exceeds a preset construction duration threshold value or not;
if yes, sending a time-out early warning signal of the construction period to the user terminal.
By adopting the technical scheme, the predicted time length of the construction operation is compared with the preset construction time length threshold value, so that related personnel can know the construction progress condition in time, the potential overtime risk of the construction period is early warned, corresponding countermeasures such as adjusting the construction plan, adding resources and the like are adopted, the construction is ensured to be carried out according to the plan, and the delay of the construction period and the increase of the cost are avoided.
In a second aspect, the present application provides a tunnel construction plan generating system, which adopts the following technical scheme:
a tunnel construction plan generation system, the plan generation system comprising:
the geological condition data acquisition module is used for acquiring geological condition data of the current face pile number; the geological condition data comprise surrounding rock types, specific geological condition monitoring data and harmful gas monitoring data;
the construction method determining module is used for determining a corresponding construction method according to the surrounding rock class based on a preset construction method library;
the specific construction measure determining module is used for determining corresponding specific construction measures according to the specific geological condition monitoring data and the harmful gas monitoring data;
the construction procedure generation module is used for performing procedure operation adjustment on the construction method according to the specific construction measures to generate corresponding construction procedures;
the preset circulating footage determining module is used for determining the preset circulating footage of the face pile number according to the surrounding rock category and the construction method;
the construction operation prediction duration determining module is used for determining the corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and the preset cyclic footage;
and the tunnel construction plan generation module is used for receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining the construction procedure and the construction operation prediction duration.
By adopting the technical scheme, the geological condition data are accurately obtained, the construction method is flexibly selected according to the actual geological condition of the construction site, specific construction measures are adopted to adjust the working procedures, meanwhile, the circulating footage and the predicted duration of the construction operation are reasonably determined, and the tunnel construction plan is generated by combining construction organization information, so that the construction efficiency is improved, the construction risk is reduced, and the smooth progress of tunnel construction is ensured.
Optionally, the plan generating system further includes:
the monitoring module is used for monitoring specific geological condition monitoring data and harmful gas monitoring data of the face pile number in real time;
the judging module is used for judging whether the specific geological condition and/or the harmful gas exceeding condition have changes or not; if yes, outputting a change judgment result;
the specific construction measure determining module is also used for determining the changed specific construction measure according to the changed specific geological condition and/or the harmful gas exceeding condition;
and the tunnel construction plan generation module is also used for carrying out procedure operation adjustment on the construction procedure of the tunnel construction plan according to the changed specific construction measures so as to regenerate the tunnel construction plan.
By adopting the technical scheme, in the process of generating a construction plan and constructing according to the construction plan, the specific geological condition and the harmful gas exceeding condition of the current construction position are monitored in real time, whether the change condition exists when the construction plan is generated last time is judged, the change condition can be timely dealt with by determining the specific construction measure after the change and adjusting the construction plan, the safety and the smoothness of tunnel construction are ensured, so that the construction quality is improved, the risk is reduced, and the construction progress is effectively controlled.
In a third aspect, the present application provides a computer device, which adopts the following technical scheme:
a computer device comprising a memory, a processor and a computer program stored on the memory and executable on the processor, the processor implementing the method according to the first aspect when executing the computer program.
In a fourth aspect, the present application provides a computer readable storage medium, which adopts the following technical scheme:
a computer readable storage medium storing a computer program capable of being loaded by a processor and executing any one of the methods of the first aspect.
In summary, the present application includes at least one of the following beneficial technical effects: by accurately acquiring the geological condition data, a construction method is flexibly selected according to the actual geological condition of a construction site, specific construction measures are adopted to adjust working procedures, meanwhile, the circulating footage and the predicted duration of construction operation are reasonably determined, and a tunnel construction plan is generated by combining construction organization information, so that the construction efficiency is improved, the construction risk is reduced, and the smooth progress of tunnel construction is ensured.
Drawings
Fig. 1 is a first flow diagram of a tunnel construction plan generation method according to one embodiment of the present application.
Fig. 2 is a second flow diagram of a tunnel construction plan generation method according to one embodiment of the present application.
Fig. 3 is a third flow diagram of a tunnel construction plan generation method according to one embodiment of the present application.
Fig. 4 is a fourth flowchart of a tunnel construction plan generation method according to one embodiment of the present application.
Fig. 5 is a fifth flowchart of a tunnel construction plan generation method according to one embodiment of the present application.
Detailed Description
In order to make the objects, technical solutions and advantages of the present application more apparent, the present application will be further described in detail with reference to fig. 1 to 5 and the embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the present application.
The embodiment of the application discloses a tunnel construction plan generation method.
Referring to fig. 1, a tunnel construction plan generation method includes:
step S101, geological condition data of a current face pile number are obtained; the geological condition data comprise surrounding rock types, specific geological condition monitoring data and harmful gas monitoring data;
the tunnel face is a construction face which is gradually pushed to the outlet direction from the inlet in the tunnel construction process according to a certain working procedure and a construction method. The location of a face is typically determined by a pile number, which is a numbering system used to identify the location in an engineering such as a tunnel or road. And the constructor determines the current construction position according to the pile number of the face, and accordingly evaluates geological conditions, determines a construction method, controls construction progress and the like.
It should be noted that the pushing and construction of the tunnel face are a cyclic process, and are repeated until the exit position of the tunnel design is reached. On the tunnel face, constructors perform working procedures such as tunneling, supporting, drainage, ventilation and the like, and work is performed according to construction technology and design requirements. Once the current working procedure and operation of the face is completed, the face will advance a certain distance into the next face. By grasping the position and the progress of the tunnel face, the tunnel construction can be effectively managed and controlled, and the smooth progress of the construction quality and the progress is ensured.
The geological condition data can be obtained through advanced geological forecast data or construction design data; in the process of acquiring the geological condition data, if the advanced geological forecast data exists, the advanced geological forecast data is directly acquired, and if the advanced geological forecast data does not exist, the geological condition data in the construction design data is used as the reference. In one embodiment of the present application, the construction design data is the result of geological survey at the time of design, including surrounding rock category of a certain pile number range (start pile number-end pile number), specific geological condition (such as water gushing or not), and harmful gas condition (such as gas, etc.), and these data are gradually replaced by advanced geological forecast data as the tunnel construction is developed.
In some embodiments, advanced geological forecast data refers to data for predicting and evaluating surrounding rock and stratum conditions in front of a tunnel face before construction by using modern geological exploration technology and analysis methods in the tunnel construction process, wherein the data comprises information such as surrounding rock types, geological structures, groundwater conditions, harmful gas conditions, engineering geological conditions and the like, so as to help constructors know and predict possible bad geological disasters, and accordingly, corresponding construction plans and safety guarantee measures are formulated.
Step S102, determining a corresponding construction method according to the category of surrounding rock based on a preset construction method library;
in some embodiments, tunnel surrounding rock categories may be classified into six classes according to rock hardness, integrity, stability, internal construction, etc., as specified in the highway tunnel engineering construction and quality acceptance Specification; wherein, the first-stage surrounding rock is best, basically a whole hard stone, the sixth-stage surrounding rock is worst, and basically broken loose soft soil mass. The construction methods to be used are different according to the types of surrounding rocks, for example, a common construction method is a two-step method, a three-step method, an up-down-step method, a full-section method and the like.
In one embodiment of the present application, a preset construction method library is established by standardizing and standardizing the construction methods corresponding to each surrounding rock category, where the preset construction method library includes preset mapping relations between multiple groups of surrounding rock categories and construction methods, and each surrounding rock category is configured with a corresponding construction method.
Step S103, corresponding specific construction measures are determined according to the specific geological condition monitoring data and the harmful gas monitoring data;
the special geological conditions such as water burst, fault or weak interlayer and the like; in the embodiment of the application, each specific geological condition and the condition that the harmful gas exceeds the standard are correspondingly configured with corresponding specific construction measures, for example, when water gushing occurs, measures such as dewatering and drainage, water blocking curtains, reinforcing supports and the like are needed to be adopted; when faults or weak interlayers and the like occur, measures such as reinforcing support and the like are needed; when detecting that harmful gases such as gas exceeds standard, ventilation, sealing, fire prevention, explosion prevention measures and the like are needed, so that the safety of tunnel construction is ensured.
Step S104, performing procedure operation adjustment on the construction method according to specific construction measures to generate corresponding construction procedures;
it can be appreciated that, since each standardized construction method further includes a plurality of working procedures, for example, a two-step method includes working procedures of upper step excavation, primary support, lower step excavation, two lining, etc., each working procedure is formed by a series of steps, and the steps are operations; after the corresponding specific construction measures are determined, the construction method can be adjusted in terms of the working procedures, for example, the specific working procedures or the working procedures are added or subtracted, so that the adjusted construction working procedures can be generated.
Step S105, determining a preset circulating footage of the face pile number according to the surrounding rock category and the construction method;
the circulating footage refers to the forward pushing distance of the pile number of the face after each blasting or tunneling in the tunnel excavation process;
in some embodiments, a plurality of circulating footage historical data corresponding to the surrounding rock category and the construction method can be obtained according to the historical construction database, and an average value is calculated through the plurality of circulating footage historical data, so that the average value can be used as a preset circulating footage corresponding to the surrounding rock category.
Step S106, determining the corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and the preset cyclic footage;
in some embodiments, according to surrounding rock types, construction procedures, preset cyclic feeding rules and other influencing factors influencing the tunnel construction operation duration, prediction of the construction operation duration can be performed through historical data moving average, neural network model prediction and other modes, so that the predicted operation duration of each operation in the construction procedures can be determined.
Step S107, receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining a construction procedure and a construction operation prediction duration.
The construction organization information includes equipment arrangement information such as division of construction work areas, construction groups of each work area, the number of persons at each post, and the type and number of construction equipment.
In the above embodiment, the geological condition data such as the surrounding rock category of the current face pile number, the specific geological condition monitoring data, the harmful gas monitoring data and the like are obtained from the advanced geological forecast data or the construction design data, so that the geological condition of the construction area can be comprehensively known, wherein the corresponding standard construction method can be obtained according to the surrounding rock category, so as to ensure that the construction method is matched with the geological condition; corresponding specific construction measures can be obtained according to the specific geological condition monitoring data and the harmful gas monitoring data so as to reduce construction risks; and (3) performing procedure adjustment on the construction method according to specific construction measures to ensure smooth construction process, determining a preset cyclic footage of the face pile number and a corresponding construction operation prediction duration according to surrounding rock types and the construction method, and generating a corresponding tunnel construction plan by combining the construction operation prediction duration, construction organization information input by a user and the adjusted construction procedure.
In the method, the geological condition data are accurately acquired, the construction method is flexibly selected according to the actual geological condition of a construction site, specific construction measures are adopted to adjust working procedures, meanwhile, the circulating footage and the predicted duration of construction operation are reasonably determined, and the tunnel construction plan is generated by combining construction organization information, so that the construction efficiency is improved, the construction risk is reduced, and the smooth progress of tunnel construction is ensured.
In the process of generating the tunnel construction plan, the tunnel face pile number needs to be continuously cycled from the entrance pile number of the tunnel design to the tunnel construction plan generating step of the step S101 to the step S107 until reaching the exit pile number of the tunnel design, so as to effectively control the progress period of the whole tunnel construction and improve the accuracy of the construction plan.
Referring to fig. 2, as a further embodiment of the tunnel construction plan generation method, after generating the corresponding tunnel construction plan, it further includes:
step S201, obtaining tunnel design parameters;
the tunnel design parameters can be obtained through construction design data, and the tunnel design parameters can comprise supporting and lining related data: such as the size and number of arches, concrete labels, thickness of supports and lining, etc.;
step S202, calculating the needed quantity of raw materials according to tunnel design parameters, and generating a corresponding production plan;
based on the collected tunnel design parameters, the required quantity of main raw materials such as the required arch centering, concrete and the like is calculated by utilizing a corresponding calculation formula and a specification. For example, the number of arches required can be calculated from the tunnel interface area and the support parameters; according to the support and lining parameters, the required concrete quantity can be calculated.
In some embodiments, depending on the quantity of raw materials required, in combination with the production capacity and supply chain conditions, a production plan for concrete and steel arches may be generated, including determining production time, production lot, and production sequence information to ensure that the required raw materials are supplied on time.
Step S203, generating a corresponding demand plan according to the raw material demand quantity and the production plan;
in some embodiments, the demand planning includes determining information such as raw material procurement time, procurement lot, and procurement quantity to ensure that production requirements are met on time;
step S204, the production plan and the demand plan are included in the tunnel construction plan.
In the above embodiment, by incorporating the production plan into the construction plan, the reasonable arrangement of production and supply is facilitated, and the timely supply of the required raw materials is ensured to support the smooth progress of tunnel construction.
As an embodiment of step S103, the step of determining the corresponding specific construction measure according to the specific geological condition monitoring data and the harmful gas monitoring data includes:
judging whether a specific geological condition and/or a harmful gas exceeding condition exists or not according to the specific geological condition monitoring data and the harmful gas monitoring data;
if yes, determining a corresponding severity level according to specific geological condition monitoring data and/or harmful gas monitoring data based on a preset construction measure database;
the specific geological conditions and the harmful gas exceeding conditions can be classified and evaluated according to the severity, and the preset construction measure database can be pre-configured with specific construction measures corresponding to various severity levels.
And determining corresponding specific construction measures according to the severity level of the specific geological condition and/or the harmful gas exceeding condition.
In some embodiments, the data may be categorized into three levels, light, medium and heavy, according to their severity for a particular geologic condition. For mild cases, simpler handling measures such as enhanced patrol and monitoring can be taken; for medium conditions, some more complex handling measures may need to be taken, such as reinforcing struts and reinforcements; for severe cases, more stringent and comprehensive treatment measures, such as extensive support and treatment, may be required.
In some embodiments, the harmful gas monitoring data may also be classified and evaluated according to its concentration or superscalar severity. For example, for low concentration or slightly out of standard hazardous gases, conventional measures such as ventilation and closed fire protection can be taken; for high concentrations or severe overstocked harmful gases, more stringent ventilation, explosion protection, and personal protection measures may be required.
In the embodiment, the specific geological conditions and the harmful gas exceeding conditions are divided into different severity levels, and corresponding treatment measures are determined according to the different severity levels, so that proper measures can be adopted in a targeted manner according to specific conditions, and the safety of tunnel construction and the smooth progress of a construction plan are ensured.
Referring to fig. 3, as a further embodiment of the tunnel construction plan generation method, after generating the corresponding tunnel construction plan in step S107, further includes:
step S301, monitoring specific geological condition monitoring data and harmful gas monitoring data of a face pile number in real time;
the pile number of the face, namely the current construction position, is convenient to discover and evaluate the change of specific geological conditions and the condition of exceeding the standard of harmful gas in time by knowing the geological conditions and the gas conditions of the current construction area.
Step S302, judging whether the specific geological condition and/or the harmful gas out-of-standard condition have changes or not; if yes, go to step S303; if not, not executing any operation;
step S303, determining a changed specific construction measure according to the changed specific geological condition and/or the harmful gas exceeding condition;
when the specific geological condition and/or the harmful gas exceeding condition changes, appropriate treatment measures are adopted according to the changing condition so as to ensure the safety and the smooth performance of construction;
step S304, the working procedure operation adjustment is carried out on the construction working procedure of the tunnel construction plan according to the changed specific construction measures so as to regenerate the tunnel construction plan.
In the above embodiment, in the process of generating the construction plan and constructing according to the construction plan, the specific geological condition and the harmful gas exceeding condition of the current construction position are monitored in real time, whether the change condition exists when the construction plan is generated last time is judged, the change condition can be timely dealt with by determining the specific construction measure after the change and adjusting the construction plan, the safety and the smoothness of tunnel construction are ensured, and therefore the construction quality is improved, the risk is reduced, and the construction progress is effectively controlled.
As one embodiment of step S106, the step of determining the corresponding predicted duration of the construction operation according to the surrounding rock category, the construction process and the preset cyclic footage includes:
performing data preprocessing on the surrounding rock category, the construction procedure and the preset cyclic footage to obtain a corresponding model input value;
and inputting the model input value into a pre-trained construction operation duration prediction model to obtain the construction operation prediction duration.
The method comprises the steps of firstly, setting a model input value, wherein influence factors influencing the tunnel construction operation time length, such as surrounding rock category, construction procedure, preset circulating scale entering and the like, can be respectively mapped between values of 0-1 by a linear normalization method, so that the corresponding model input value is obtained;
in some embodiments, taking the surrounding rock class as an example: assuming that the surrounding rock class is currently 4a class surrounding rock, the current original value is 4.2; if the surrounding rock class has 2, 5, 4 and 6c, the corresponding original values are 2, 5, 4 and 6.4 respectively, so that the surrounding rock class 4a is calculated according to the mapping formula, and the surrounding rock class 4a is mapped to a value between 0 and 1 = (4.2-2)/(6.4-2) = 0.5; taking cyclic footage as an example: assuming that the cyclic footage is 2m, the minimum value of all cyclic footages in the system is 0.3m, and the maximum value of all cyclic footages is 4m, the cyclic footage of the current 2m is calculated according to a mapping formula, and the cyclic footage mapping between the current 2m and the value of 0-1 is (2-0.3)/(4-0.3) =0.45.
It should be noted that, the influence factors of the predicted construction operation duration are more, including but not limited to factors such as surrounding rock category, construction procedure and preset circulating footage, so that the influence factors when the prediction model is input need to be adjusted according to the actual condition of construction during actual prediction, which is not limited in the embodiment of the present application.
In the above embodiment, according to the influence factors such as the surrounding rock type, the construction procedure, the preset circulating rule, and the like, which influence the tunnel construction operation time, the prediction of the construction operation time can be performed in a neural network model prediction manner, so as to determine the predicted operation time of each operation in the construction procedure.
In some embodiments, for the training process of the construction operation duration prediction model, during training, all input historical data related to surrounding rock types, construction procedures, preset circulating footage and other influencing factors and all output historical data related to tunnel construction operation duration can be used as data sample sets, training sets and test sets are divided, and the neural network model is continuously trained and iterated until preset iteration times or expected model performance is achieved, so that the optimal construction operation duration prediction model can be obtained.
In this embodiment of the present application, taking the process of excavation as an example, the excavation process includes operations such as drilling, charging, blasting, slag removal, measurement, primary support, and the like, and by using methods such as moving average of historical data and prediction of neural network model, it is known that the predicted duration of the drilling operation is 20 minutes, and the predicted duration of the charging operation is 10 minutes, so that the system can approximately plan the construction duration of the whole excavation process and the corresponding tunnel construction plan according to the number of post personnel, the type of construction equipment, the material configuration, and the like preset for each operation.
Referring to fig. 4, as a further embodiment of the tunnel construction plan generation method, the plan generation method further includes:
step S401, receiving the actual duration of the construction operation input by a user;
after the construction of each circulating footage is completed, the actual duration of the construction operation of the circulating footage input by a user can be received;
step S402, correcting the predicted construction operation duration according to the actual construction operation duration;
when the actual duration of the construction operation exceeds or is ahead of the predicted duration, the predicted duration of the previous construction operation is corrected according to the actual duration, so that the construction progress is predicted more accurately, and the construction exceeding or ahead of time caused by prediction deviation is avoided.
Step S403, regenerating a tunnel construction plan according to the corrected construction operation prediction time length.
In the embodiment, when each construction cycle is completed and the acquired actual duration of the construction operation exceeds or is advanced from the predicted duration, the predicted duration is corrected in real time, and the construction plan is regenerated, so that the actual construction condition is compared with the construction plan, the construction progress and the resource allocation are convenient to adjust and optimize in time, and the accuracy and the operability of the construction plan are improved.
In addition, it should be noted that, in the construction process, when unexpected shutdown occurs, for example, when the construction time is prolonged due to shutdown caused by power failure, gas exceeding standard, etc., the tunnel construction plan also needs to be recalculated according to the shutdown time; the construction schedule is continuously adjusted and regenerated, so that the construction progress is effectively controlled, and the accuracy of the construction schedule is improved.
Referring to fig. 5, as a further embodiment of the tunnel construction plan generation method, after the tunnel construction plan is generated in step S107, step S304, or step S403, the method further includes:
step S501, analyzing and obtaining the predicted construction operation duration according to the tunnel construction plan;
step S502, judging whether the predicted construction operation duration exceeds a preset construction duration threshold; if yes, go to step S503; if not, not executing any operation;
the preset construction time threshold value can be preconfigured and adjusted according to actual engineering conditions, and when the construction operation prediction time exceeds the preset construction time threshold value, the condition that the construction period is delayed is indicated.
Step S503, send the overtime early warning signal of the construction period to the user terminal.
The user terminal may be a mobile intelligent terminal of a technician, such as a mobile phone, a tablet computer, or the like, or may be a computer terminal in a management room.
In the above embodiment, the predicted duration of the construction operation is compared with the preset duration threshold value, so as to help related personnel to know the construction progress in time, and early warn the potential overtime risk of the construction period, so that corresponding countermeasures, such as adjusting the construction plan, increasing resources, and the like, are adopted to ensure that the construction is performed according to the plan, and avoid delay of the construction period and increase of the cost.
The embodiment of the application also discloses a tunnel construction plan generation system.
A tunnel construction plan generation system, the plan generation system comprising:
the geological condition data acquisition module is used for acquiring geological condition data of the current face pile number; the geological condition data comprise surrounding rock types, specific geological condition monitoring data and harmful gas monitoring data;
the construction method determining module is used for determining a corresponding construction method according to the category of surrounding rock based on a preset construction method library;
the specific construction measure determining module is used for determining corresponding specific construction measures according to the specific geological condition monitoring data and the harmful gas monitoring data;
the construction procedure generation module is used for performing procedure operation adjustment on the construction method according to specific construction measures to generate corresponding construction procedures;
the preset circulating footage determining module is used for determining the preset circulating footage of the face pile number according to the surrounding rock category and the construction method;
the construction operation prediction duration determining module is used for determining the corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and the preset cyclic footage;
the tunnel construction plan generation module is used for receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining construction procedures and construction operation prediction duration.
In the embodiment, the geological condition data are accurately obtained, the construction method is flexibly selected according to the actual geological condition of the construction site, specific construction measures are adopted to adjust the working procedures, meanwhile, the circulating footage and the predicted construction operation duration are reasonably determined, and the tunnel construction plan is generated by combining construction organization information, so that the construction efficiency is improved, the construction risk is reduced, and the smooth progress of tunnel construction is ensured.
As a further embodiment of the tunnel construction plan generation system, the plan generation system further includes:
the monitoring module is used for monitoring specific geological condition monitoring data and harmful gas monitoring data of the face pile number in real time;
the judging module is used for judging whether the specific geological condition and/or the harmful gas exceeding condition have changes or not; if yes, outputting a change judgment result;
the specific construction measure determining module is also used for determining the changed specific construction measure according to the changed specific geological condition and/or the harmful gas exceeding condition;
the tunnel construction plan generating module is also used for carrying out procedure operation adjustment on the construction procedure of the tunnel construction plan according to the changed specific construction measures so as to regenerate the tunnel construction plan.
In the above embodiment, in the process of generating the construction plan and constructing according to the construction plan, the specific geological condition and the harmful gas exceeding condition of the current construction position are monitored in real time, whether the change condition exists when the construction plan is generated last time is judged, the change condition can be timely dealt with by determining the specific construction measure after the change and adjusting the construction plan, the safety and the smoothness of tunnel construction are ensured, and therefore the construction quality is improved, the risk is reduced, and the construction progress is effectively controlled.
The tunnel construction plan generation system of the embodiment of the application can realize any one of the tunnel construction plan generation methods, and the specific working process of each module in the tunnel construction plan generation system can refer to the corresponding process in the embodiment of the method.
In several embodiments provided herein, it should be understood that the provided methods and systems may be implemented in other ways. For example, the system embodiments described above are merely illustrative; for example, a division of a module is merely a logical function division, and there may be another division manner in actual implementation, for example, multiple modules may be combined or may be integrated into another system, or some features may be omitted or not performed.
The embodiment of the application also discloses a computer device.
Computer apparatus comprising a memory, a processor, and a computer program stored on the memory and executable on the processor, the processor implementing a tunnel construction plan generation method as described above when executing the computer program.
The embodiment of the application also discloses a computer readable storage medium.
A computer-readable storage medium storing a computer program that can be loaded by a processor and that executes any one of the tunnel construction plan generation methods described above.
Wherein a computer readable storage medium may be any tangible medium that can contain, or store a program for use by or in connection with an instruction execution system, apparatus, or device; program code embodied on a computer readable medium may be transmitted using any appropriate medium, including but not limited to wireless, wireline, optical fiber cable, RF, etc., or any suitable combination of the foregoing.
In the foregoing embodiments, the descriptions of the embodiments are focused on, and for those portions of one embodiment that are not described in detail, reference may be made to the related descriptions of other embodiments.
The foregoing description of the preferred embodiments of the present application is not intended to limit the scope of the application, in which any feature disclosed in this specification (including abstract and drawings) may be replaced by alternative features serving the same, equivalent or similar purpose, unless expressly stated otherwise. That is, each feature is one example only of a generic series of equivalent or similar features, unless expressly stated otherwise.

Claims (10)

1. A tunnel construction plan generation method, characterized in that the plan generation method comprises:
obtaining geological condition data of a current face pile number; the geological condition data comprise surrounding rock types, specific geological condition monitoring data and harmful gas monitoring data;
based on a preset construction method library, determining a corresponding construction method according to the surrounding rock category;
determining corresponding specific construction measures according to the specific geological condition monitoring data and the harmful gas monitoring data;
performing procedure operation adjustment on the construction method according to the specific construction measures to generate corresponding construction procedures;
determining a preset circulating footage of the face pile number according to the surrounding rock category and the construction method;
determining corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and the preset cyclic footage;
and receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining the construction procedure and the construction operation prediction time.
2. The tunnel construction plan generation method according to claim 1, wherein: according to the specific geological condition monitoring data and the harmful gas monitoring data, the step of determining the corresponding specific construction measure comprises the following steps:
judging whether a specific geological condition and/or a harmful gas exceeding standard condition exists or not according to the specific geological condition monitoring data and the harmful gas monitoring data;
if yes, determining a corresponding severity level based on a preset construction measure database according to the specific geological condition monitoring data and/or the harmful gas monitoring data;
and determining corresponding specific construction measures according to the severity level of the specific geological condition and/or the harmful gas exceeding condition.
3. The tunnel construction plan generation method according to claim 2, wherein: the method further comprises the following steps after the corresponding tunnel construction plan is generated:
monitoring specific geological condition monitoring data and harmful gas monitoring data of the face pile number in real time;
judging whether the specific geological condition and/or the harmful gas exceeding condition have changes or not;
if so, determining the changed specific construction measures according to the changed specific geological conditions and/or the harmful gas exceeding conditions;
and carrying out procedure operation adjustment on the construction procedure of the tunnel construction plan according to the changed specific construction measures so as to regenerate the tunnel construction plan.
4. The tunnel construction plan generation method according to claim 1, wherein: according to the surrounding rock category, the construction procedure and the preset cyclic footage, the step of determining the corresponding construction operation prediction duration comprises the following steps:
performing data preprocessing on the surrounding rock category, the construction procedure and the preset cyclic footage to obtain a corresponding model input value;
and inputting the model input value into a pre-trained construction operation duration prediction model to obtain the construction operation prediction duration.
5. The tunnel construction plan generation method according to claim 1, characterized in that the plan generation method further comprises:
receiving the actual duration of the construction operation input by a user;
correcting the predicted construction operation duration according to the actual construction operation duration;
and regenerating the tunnel construction plan according to the corrected construction operation prediction time length.
6. A tunnel construction plan generation method according to any one of claims 1 to 5, wherein: after generating the tunnel construction plan, further comprising:
analyzing to obtain the predicted construction operation duration according to the tunnel construction plan;
judging whether the predicted construction operation duration exceeds a preset construction duration threshold value or not;
if yes, sending a time-out early warning signal of the construction period to the user terminal.
7. A tunnel construction plan generation system, the plan generation system comprising:
the geological condition data acquisition module is used for acquiring geological condition data of the current face pile number; the geological condition data comprise surrounding rock types, specific geological condition monitoring data and harmful gas monitoring data;
the construction method determining module is used for determining a corresponding construction method according to the surrounding rock class based on a preset construction method library;
the specific construction measure determining module is used for determining corresponding specific construction measures according to the specific geological condition monitoring data and the harmful gas monitoring data;
the construction procedure generation module is used for performing procedure operation adjustment on the construction method according to the specific construction measures to generate corresponding construction procedures;
the preset circulating footage determining module is used for determining the preset circulating footage of the face pile number according to the surrounding rock category and the construction method;
the construction operation prediction duration determining module is used for determining the corresponding construction operation prediction duration according to the surrounding rock category, the construction procedure and the preset cyclic footage;
and the tunnel construction plan generation module is used for receiving construction organization information input by a user, and generating a corresponding tunnel construction plan by combining the construction procedure and the construction operation prediction duration.
8. The tunnel construction plan generation system of claim 7, wherein the plan generation system further comprises:
the monitoring module is used for monitoring specific geological condition monitoring data and harmful gas monitoring data of the face pile number in real time;
the judging module is used for judging whether the specific geological condition and/or the harmful gas exceeding condition have changes or not; if yes, outputting a change judgment result;
the specific construction measure determining module is also used for determining the changed specific construction measure according to the changed specific geological condition and/or the harmful gas exceeding condition;
and the tunnel construction plan generation module is also used for carrying out procedure operation adjustment on the construction procedure of the tunnel construction plan according to the changed specific construction measures so as to regenerate the tunnel construction plan.
9. A computer device, comprising: memory, a processor and a computer program stored on the memory and executable on the processor, the processor implementing the method according to any one of claims 1 to 6 when the computer program is executed.
10. A computer-readable storage medium, characterized by: a computer program stored which can be loaded by a processor and which performs the method according to any one of claims 1 to 6.
CN202311265090.2A 2023-09-26 2023-09-26 Tunnel construction plan generation method, system, equipment and medium Pending CN117328939A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311265090.2A CN117328939A (en) 2023-09-26 2023-09-26 Tunnel construction plan generation method, system, equipment and medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311265090.2A CN117328939A (en) 2023-09-26 2023-09-26 Tunnel construction plan generation method, system, equipment and medium

Publications (1)

Publication Number Publication Date
CN117328939A true CN117328939A (en) 2024-01-02

Family

ID=89282355

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311265090.2A Pending CN117328939A (en) 2023-09-26 2023-09-26 Tunnel construction plan generation method, system, equipment and medium

Country Status (1)

Country Link
CN (1) CN117328939A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117745247A (en) * 2024-02-21 2024-03-22 中国有色金属工业昆明勘察设计研究院有限公司 Rock-soil construction wisdom building site system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117745247A (en) * 2024-02-21 2024-03-22 中国有色金属工业昆明勘察设计研究院有限公司 Rock-soil construction wisdom building site system
CN117745247B (en) * 2024-02-21 2024-06-11 中国有色金属工业昆明勘察设计研究院有限公司 Rock-soil construction wisdom building site system

Similar Documents

Publication Publication Date Title
Mawdesley et al. Extending the Mathews stability graph for open–stope design
CN110889532B (en) Intelligent selection and optimization method and system for tunnel excavation and support parameters
CN117328939A (en) Tunnel construction plan generation method, system, equipment and medium
CN111197500B (en) Method and system suitable for real-time judgment of surrounding rock grade of TBM tunneling tunnel
Fetz et al. Fuzzy models in geotechnical engineering and construction management
CN114417697A (en) Neural network-based TBM hob abrasion real-time prediction method and system
Wu et al. A dynamic decision approach for risk analysis in complex projects
CN112364422A (en) Shield construction earth surface deformation dynamic prediction method based on MIC-LSTM
CN110705179A (en) Water guide crack belt height accurate prediction method and system based on fusion neural network
Ji et al. Modified Q-index for prediction of rock mass quality around a tunnel excavated with a tunnel boring machine (TBM)
Einstein et al. Decision analysis applied to rock tunnel exploration
CN117556687A (en) Tunnel blasting parameter determination method, system, electronic equipment and medium
CN118171558A (en) Tunnel excavation regulation and control method and system based on multielement constraint and target optimization
CN118094375A (en) Four-in-one mining ground surface subsidence space-time continuous sensing method
CN117634308A (en) Decision system and analysis method for analyzing rail transit engineering data
Cheng et al. A reliability allocation model and application in designing a mine ventilation system
Samadi et al. Developing GEP technique for prediction of EPB-TBM performance in limestone strata
CN115239108B (en) Weak broken surrounding rock sensing method based on TBM real-time broken rock data
Khetwal et al. Introducing uniform discrete event simulation (CSM2020) for modeling the TBM tunneling process
Mishra et al. Combining expert opinion and instrumentation data using Bayesian networks to carry out stope collapse risk assessment
CN113158561B (en) TBM operation parameter optimization method and system suitable for various rock mass conditions
Contreras et al. Geotechnical risk analysis for the closure alternatives of the Chuquicamata open pit
Peixoto et al. Prediction of rockburst based on an accident database
CN117574781B (en) Intelligent prediction method and system for security risk of surrounding rock of underground factory building of pumped storage power station
CN116108587B (en) TBM utilization rate prediction method considering multi-source information uncertainty

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination