CN117291384B - Project progress adjustment method, device, equipment and medium based on resource allocation - Google Patents

Project progress adjustment method, device, equipment and medium based on resource allocation Download PDF

Info

Publication number
CN117291384B
CN117291384B CN202311278828.9A CN202311278828A CN117291384B CN 117291384 B CN117291384 B CN 117291384B CN 202311278828 A CN202311278828 A CN 202311278828A CN 117291384 B CN117291384 B CN 117291384B
Authority
CN
China
Prior art keywords
project
information
resource
refined
amount information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202311278828.9A
Other languages
Chinese (zh)
Other versions
CN117291384A (en
Inventor
袁绵
王小芹
王立城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Minghui Color Printing Co ltd
Original Assignee
Guangzhou Minghui Color Printing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Minghui Color Printing Co ltd filed Critical Guangzhou Minghui Color Printing Co ltd
Priority to CN202311278828.9A priority Critical patent/CN117291384B/en
Publication of CN117291384A publication Critical patent/CN117291384A/en
Application granted granted Critical
Publication of CN117291384B publication Critical patent/CN117291384B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to a project progress adjusting method, device, equipment and medium based on resource allocation, wherein the method comprises the steps of obtaining project total plan amount information, triggering project refinement instructions and obtaining refined project plan amount information; generating a project progress bar according to the refined project plan amount information; acquiring refined project completion amount information, and comparing the refined project completion amount information with the project progress bar to obtain a project completion amount comparison result; acquiring allocation resource amount information according to the item completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information; generating a comparison project progress bar according to the resource allocation information and the project progress bar; and obtaining the project completion degree information according to the comparison project progress bar. The application provides a project progress adjusting method with high accuracy in combination with resource quantity.

Description

Project progress adjustment method, device, equipment and medium based on resource allocation
Technical Field
The present invention relates to the field of project management technologies, and in particular, to a method, an apparatus, a device, and a medium for adjusting project progress based on resource allocation.
Background
At present, along with the continuous promotion of the industrialization process, the number of various production and construction projects is also increasing, and in order to strengthen the standardization of production and construction, the projects need to be managed so as to ensure the smooth proceeding of the projects regardless of the volume of the projects.
In the related art, a method for managing a project by using a progress bar updates project work progress in real time according to total project workload and combines completed workload, so that a project progress situation can be mastered in real time, and then a project planning progress is adjusted according to the project progress situation.
The related technical scheme has the following defects: the variability exists in the historical completion condition, so that the schedule progress needs to be frequently updated, the production schedule is not conveniently designated according to the schedule progress, and the schedule progress adjusted according to the historical completion condition is reduced in accuracy due to the variability of the historical completion condition, so that the actual project completion amount and the schedule progress are not in line.
Disclosure of Invention
In order to provide a project progress adjusting method with high accuracy in combination with resource quantity, the application provides a project progress adjusting method, device, equipment and medium based on resource allocation.
In a first aspect, the above object of the present application is achieved by the following technical solutions:
A project progress adjustment method based on resource allocation, the project progress adjustment method based on resource allocation comprising:
Acquiring project total plan amount information, triggering project refinement instructions, and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
generating a project progress bar according to the refined project plan amount information;
Obtaining refined project completion amount information, and comparing the refined project completion amount information with the project progress bar to obtain a project completion amount comparison result, wherein the project completion amount comparison result comprises refined project incomplete information and refined project completion information;
Acquiring allocation resource amount information according to the project completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises resource allocation information to be allocated and allocation information of adjustable allocation resources;
generating a comparison project progress bar according to the resource allocation information and the project progress bar;
And obtaining the project completion degree information according to the comparison project progress bar.
By adopting the technical scheme, the project can be different types of projects, including production projects or sales projects, when the project is a project of a production type, the project total plan amount represents the production amount of the project, when the project is a project of a sales type, the project total plan amount represents the sales performance of the project, the refined project plan amount information refers to dividing the total project plan amount into a plurality of small refined project plan amounts, the refined project plan amounts are obtained according to the actual conditions of the project, for example, when the project completion schedule has peak-valley periods, the plan work amounts and the time of different schedules are completed according to the peak-valley period time of the project, the plan work amounts and the time of the different schedules are correspondingly adjusted, so that the generated project schedule is more reasonable, the project work amounts completed at the time node are obtained on the time node represented by the schedule, the schedule is adjusted according to whether the schedule is completed, when the schedule is not completed, the schedule is completed, the subsequent project schedule is adjusted according to the used resource amounts and the resource amounts which can be increased in the schedule, the actual schedule is updated according to the completed schedule, and the actual schedule updating conditions can be more accurately adjusted.
The present application may be further configured in a preferred example to: the step of obtaining project total planning amount information, triggering project refinement instructions and obtaining refined project planning amount information specifically comprises the following steps:
Acquiring project total planning amount information and project type information, and triggering a project refining instruction according to the project total planning amount information and a preset project refining rule corresponding to the project type information;
and obtaining refined project plan amount information based on the project refinement instruction.
By adopting the technical scheme, the preset project refining rules comprise refining rules corresponding to different projects, for example, when the project is produced, the total plan amount of the project is refined by combining the production shifts of users and the production capacities of different shifts, the obtained refined project plan amount information is more accurate, and the completion rate of the progress of each shift after refining is improved.
The present application may be further configured in a preferred example to: generating a project progress bar according to the refined project plan amount information, wherein the project progress bar specifically comprises the following steps:
Acquiring corresponding planning resource amount information according to the refined project planning amount information;
And generating a project progress bar according to the refined project plan amount information and the plan resource amount information, wherein the project progress bar comprises the refined project plan amount information and the corresponding plan resource amount information.
By adopting the technical scheme, after the refined project plan amount is obtained, the resource amount which can be obtained in the refined project plan progress of each node is also required to be obtained, when the plan resource amount cannot be completed or the corresponding refined project plan amount is completed excessively, the refined project plan amount is required to be adjusted according to the resource amount, whether the adjusted refined project plan amount meets the total project plan amount or not is considered, the obtained progress bar comprises the plan progress of each node and the resource amount provided by the plan, so that the resource amount and the completion progress are combined, and the accuracy of the progress bar is improved.
The present application may be further configured in a preferred example to: the method comprises the steps of obtaining refined project completion amount information, comparing the refined project completion amount information with the project progress bar to obtain a project completion amount comparison result, and specifically comprises the following steps:
acquiring corresponding refinement project completion amount information according to the refinement project plan completion time;
obtaining resource usage amount information, comparing the corresponding planning resource amount information in the project progress bar with the resource usage amount information to obtain a resource usage comparison result, and comparing the refined project completion amount information with the corresponding refined project planning workload in the project progress bar to obtain a project completion amount comparison result.
By adopting the technical scheme, the completion amount of the refined project and the used resource amount acquired at the completion time node of each refined project plan amount are input into the project progress bar, and are compared with the corresponding refined project plan work amount and plan resource amount, so that the corresponding relation between the completed progress and the used resource amount is judged, the proportional relation between the resource amount and the work completion amount can be further judged and known according to the corresponding relation, and the adjustment of the progress bar is facilitated.
The present application may be further configured in a preferred example to: the allocating resource amount information comprises project resource amount information to be allocated and project resource amount information which can be allocated for refining projects, the allocating resource amount information is obtained according to the comparison result, and the resource allocation information is obtained according to the allocating resource amount information, and the method specifically comprises the following steps:
According to the project completion amount comparison result, if the project completion amount comparison result is the refined project incomplete information, acquiring project resource amount information to be allocated according to the resource use comparison result;
If the item completion amount comparison result is the refined item completion information, acquiring refined item adjustable resource amount information according to the resource use comparison result;
and obtaining resource allocation information according to the resource allocation information required by the project or the resource allocation information adjustable by the refined project.
By adopting the technical scheme, the comparison result is that the planned resource quantity is used up and the planned resource quantity is not used up when the thinning item is incomplete and the thinning item is completed, each different condition is represented by different project progress conditions, when the thinning item is incomplete and the resource quantity is used up, the resource quantity needs to be allocated to the subsequent thinning item, when the thinning item is incomplete and the resource quantity is not used up, the condition that the staff of the thinning item is completed is not good, but the resource quantity is insufficient, the resource allocation to the thinning item is not needed, when the thinning item is completed and the resource quantity is used up, the condition that the thinning item is completed is good, the resource allocation to the thinning item is not needed, when the thinning item is completed and the resource quantity is not used up, the condition that the thinning item is completed is excellent, the redundant resource quantity can be extracted and allocated to other projects or reserved, therefore, by combining the analysis of the resource quantity and the completion quantity of the thinning item, the accuracy of allocation of the implemented resources is improved, and the condition that the actual allocation of the resources to the projects which do not need resources is avoided.
The present application may be further configured in a preferred example to: the resource allocation information is obtained according to the resource allocation information required by the project or the resource allocation information adjustable by the refinement project, and specifically comprises the following steps:
acquiring information of a planned increase resource amount, and obtaining information of resource allocation to be allocated according to the information of the planned increase resource amount and the information of the resource amount to be allocated of the project;
and obtaining the allocation information of the allocated resources according to the information of the allocated resources of the refinement project.
By adopting the technical scheme, for the situation that the refined project is incomplete and the resource quantity is used up, the project increasing resource quantity information is not only required to complement the progress of the project, but also required to consider the supply capability of the project, so when the project increasing resource quantity can complement the progress of the project, the resource quantity required by the refined project is allocated to the refined project of the next node, when the project increasing resource quantity can not complement the progress of the project, all the project increasing resource quantity is allocated to the refined project of the next node, when the refined project is completed and the resource quantity is not used up, the redundant resources are extracted, and the redundant resources are allocated according to the situation, and the allocation information of the allocable resources is two different information aiming at different situations, so the resource quantity is reasonably allocated and utilized for different situations, and the project progress bar is more reasonable.
The present application may be further configured in a preferred example to: generating a comparison project progress bar according to the resource allocation information and the project progress bar, wherein the comparison project progress bar specifically comprises the following steps:
Acquiring updated and refined project plan amount information according to the resource allocation information to be allocated;
Generating an updated project progress bar according to the updated refined project plan amount information;
and associating the updated project progress bar with the project progress bar to obtain a comparison project progress bar.
By adopting the technical scheme, the progress increment of the refined project of the next node is judged according to the resource increment of the refined project of the next node, which is represented by the allocation information of the resources to be allocated, the updated project progress bar is generated, the project progress bar is compared, the project progress bar comprises two different project progress bars, one is the original project progress bar, the updated progress bar is judged according to the allocation information of the resources to be allocated, and the progress of the project is conveniently and intuitively known through the comparison of the different project progress bars, so that the dynamic condition of the project progress can be mastered after the project is ended.
In a second aspect, the above object of the present application is achieved by the following technical solutions:
A project progress adjustment device based on resource allocation, the project progress adjustment device based on resource allocation comprising:
The refined project plan amount information acquisition module is used for acquiring project total plan amount information, triggering project refining instructions and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
The project progress bar generation module is used for generating a project progress bar according to the refined project plan amount information;
The completion quantity comparison module is used for obtaining refined project completion quantity information, comparing the refined project completion quantity information with the project progress bar to obtain a project completion quantity comparison result, wherein the project completion quantity comparison result comprises refined project incomplete information and refined project completion information;
the resource allocation information acquisition module is used for acquiring allocation resource amount information according to the project completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises project allocation resource allocation information required to be allocated and project allocation information capable of being allocated for refining projects;
The comparison project progress bar generation module is used for generating a comparison project progress bar according to the resource allocation information and the project progress bar;
and the project completion degree information acquisition module is used for acquiring project completion degree information according to the comparison project progress bar.
In a third aspect, the above object of the present application is achieved by the following technical solutions:
A computer device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, the processor implementing the steps of the resource allocation based project schedule adjustment method described above when the computer program is executed.
In a fourth aspect, the above object of the present application is achieved by the following technical solutions:
a computer-readable storage medium storing a computer program which, when executed by a processor, implements the steps of the project progress adjustment method based on resource allocation described above.
In summary, the present application includes at least one of the following beneficial technical effects:
1. when the peak-valley period exists in the project completion progress, the planning workload and time for planning to complete different progress are correspondingly adjusted according to the peak-valley period time of the project, so that the progress bar of the generated project is more reasonable, and under the condition that the completed progress, the resource amount used by the incomplete planning progress and the resource amount increased by the plan are considered, the correspondingly obtained progress adjustment mode is more fit with the actual, and the accuracy of adjusting the updated planning progress is improved;
2. The comparison result is that the planned resource amount is used up and the planned resource amount is not used up when the refined project is not completed and the refined project is completed, and each different condition represents different project progress conditions, so that the accuracy of implementing resource allocation is improved by combining the analysis of the resource amount and the refined project completion amount, and the condition of actually allocating resources to projects without resources is avoided;
3. The project progress bars are compared, wherein the project progress bars comprise two different project progress bars, one project progress bar is an original project progress bar, the other project progress bar is a progress bar which is updated according to allocation information of resources to be allocated, and the project progress is conveniently and intuitively known through comparison of the different project progress bars, so that the dynamic condition of project progress is mastered after the project is finished.
Drawings
FIG. 1 is a flowchart of an implementation of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 2 is a flowchart of an implementation of S10 of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 3 is a flowchart of an implementation of S20 of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 4 is a flowchart of an implementation of S30 of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 5 is a flowchart of an implementation of S40 of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 6 is a flowchart of an implementation of S43 of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 7 is a flowchart of an implementation of S50 of a project progress adjustment method based on resource allocation in an embodiment of the application;
FIG. 8 is a schematic block diagram of a project progress adjusting device based on resource allocation in an embodiment of the application;
FIG. 9 is a diagram illustrating an internal structure of a project schedule adjustment computer device based on resource allocation in accordance with an embodiment of the present application
Detailed Description
The application is described in further detail below with reference to fig. 1-9.
In an embodiment, as shown in fig. 1, the application discloses a project progress adjustment method based on resource allocation, which specifically comprises the following steps:
S10: and acquiring project total plan amount information, triggering project refinement instructions, and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time.
In the present embodiment, the project total plan amount information refers to demand plan amount information of the entire project. The item refinement instruction refers to instruction information of a refined item that divides the item into a plurality of nodes. The refined project plan amount information refers to demand plan amount information of the refined project. The refinement project plan workload refers to a job plan amount of a refinement project. The project refinement plan completion time refers to the plan completion time of the refinement project.
Specifically, the item may be a different type of item including a production item or a sales item, and in this embodiment, when the item is a production type item, thus, overall demand plan amount information of the item, that is, an item total plan amount indicating a plan throughput and production time of the item is acquired, and after the item total plan amount is acquired, the item is divided into a plurality of nodes of a refinement item, that is, a trigger item refinement instruction, demand plan amount information of the refinement item, that is, refinement item plan amount information including refinement item plan amount information indicating a production plan amount and a plan completion time of the refinement item, and refinement item plan completion time is obtained.
S20: and generating a project progress bar according to the refined project plan amount information.
In the present embodiment, the project progress bar indicates a progress bar of the whole project and the completion of the thinned project.
Specifically, according to the plan amount of the thinned item indicated by the thinned item plan amount information, the thinned items are arranged in time sequence of thinned item plan completion time to form a progress bar indicating the entirety of the item and the completion of the thinned item, i.e., a project progress bar including time nodes indicated at each thinned item plan completion time and thinned item plan amount information within each thinned item plan completion time.
S30: and obtaining refined project completion amount information, and comparing the refined project completion amount information with a project progress bar to obtain a project completion amount comparison result, wherein the project completion amount comparison result comprises refined project incomplete information and refined project completion information.
In the present embodiment, the refinement project completion amount information refers to actual completion amount information of the refinement project. The project completion amount comparison results refer to comparison results of actual throughput versus planned amount of the refined project. The detailed item incomplete information is information indicating that the actual throughput of the detailed item has not reached the planned amount. The detailed item completion information is information indicating that the actual production volume of the detailed item reaches the planned amount.
Specifically, at a time node represented by a project plan completion time, actual completion amount information of a project, i.e., project completion amount information, is acquired, the project completion amount information is compared with a corresponding project plan amount in a project progress bar, a project completion amount comparison result representing a comparison result of an actual throughput of the project with the plan amount is obtained, and the project completion amount comparison result includes project incomplete information representing that the actual throughput of the project does not reach the plan amount, and project completion information representing that the actual throughput of the project reaches or exceeds the plan amount.
S40: and acquiring allocation resource amount information according to the item completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises item allocation resource allocation information required to be allocated and item allocation information capable of being allocated in a refinement mode.
In this embodiment, the allocated resource amount information refers to an allocated production resource amount. The resource allocation information refers to the amount of production resources that can be actually allocated to the project. The project allocation information refers to the amount of production resources actually allocated to the project. Refinement project allotment resource allocation information refers to the amount of production resources extracted from a refinement project and allocated to other projects.
Specifically, according to different conditions represented by the item completion amount comparison result, when the item completion amount comparison result represents that the actual production amount of the refined item does not reach the planned amount, the resource amount to be allocated to the item, namely allocation resource amount information, is obtained according to the production resource demand amount of the item represented by the comparison result, when the item completion amount comparison result represents that the actual production amount of the refined item reaches the planned amount, the redundant production resource amount which can be extracted by the item is obtained according to the redundant production resource amount of the item represented by the comparison result on the premise of completing the planned amount, namely allocation resource amount information, wherein the allocation resource amount information comprises allocation resource amount information of two different conditions, and according to the allocation resource amount information representing the resource amount required to be allocated to the item, the production resource amount which can be actually allocated to the item, namely allocation resource allocation information is obtained in combination with the production resource amount which can be provided actually, and the allocation resource amount information representing the redundant production resource amount which can be extracted by the item is taken as allocation resource allocation information of the refined item.
S50: and generating a comparison project progress bar according to the resource allocation information and the project progress bar.
In the present embodiment, the comparative project progress bar refers to a progress bar for comparison with the project progress bar.
Specifically, according to the resource allocation information, the plan workload of the subsequent refined project is judged and adjusted, a new project progress bar is generated, and the new project progress bar is associated with the original project progress bar, so that a progress bar for comparison with the project progress bar, namely a comparison progress bar, is obtained.
Further, when the finishing amount information of the refined project is obtained later, the finishing amount information of the refined project is compared with the progress bar of the comparison project.
S60: and obtaining the project completion degree information according to the comparison project progress bar.
In the present embodiment, the item completion degree information refers to the ratio information of the completion amount of the item to the planned amount.
Specifically, after the whole project is finished, the proportional relation between the actual completion amount and the planned amount of the project, namely project completion degree information, is obtained according to a comparison project progress bar, wherein the project completion degree information represents the completion rate of the project and the relation between the actual completion condition of the project and the adjustment process of the planned amount of the project.
In one embodiment, as shown in fig. 2, in step S10, the project total plan amount information is acquired, and a project refinement instruction is triggered to obtain refined project plan amount information, which specifically includes:
S11: and acquiring project total planning amount information and project type information, and triggering a project refining instruction according to the project total planning amount information and a preset project refining rule corresponding to the project type information.
In the present embodiment, the item type information refers to information indicating the type of the item.
Specifically, the total project plan amount is acquired, and information indicating the type of the project, namely project type information including production projects and sales projects, in this embodiment, the project type information is used for producing the projects, and the project thinning instruction is triggered to divide the projects into thinned projects according to a preset project thinning rule of the corresponding production projects, wherein the project thinning rule includes production shifts combined with users and production capacities in different shifts, and then combined with the total production plan amount and the plan production time indicated by the total project plan amount information.
S12: based on the project refinement instruction, refined project plan amount information is obtained.
In this embodiment, after the project thinning instruction is triggered, i.e., after dividing the project into thinned projects, thinned project plan amount information indicating the production plan amount and the planned production time of the thinned project is obtained.
In one embodiment, as shown in fig. 3, in step S20, generating a project progress bar according to the refined project plan amount information specifically includes:
s21: and acquiring corresponding planning resource amount information according to the refined project planning amount information.
In the present embodiment, the planned resource amount information is the amount of production resources that are planned to be put into the thinned project.
Specifically, the planned input production resource amount, i.e., the planned resource amount information, corresponding to each of the thinned projects is acquired from the planned input production amount and the planned production time of the thinned projects indicated by the thinned project plan amount information, and the planned input production resource amount for the entire project.
S22: and generating a project progress bar according to the refined project plan amount information and the plan resource amount information, wherein the project progress bar comprises the refined project plan amount information and the corresponding plan resource amount information.
Specifically, according to the project plan amount information and the plan resource amount information, a project progress bar is produced, and the project progress bar is mainly composed of the plan throughput and the plan completion time of the project indicated by the project plan amount information, and the project plan amount information is hung down with the corresponding plan resource amount information.
In one embodiment, as shown in fig. 4, in step S30, refined project completion amount information is obtained, and the refined project completion amount information is compared with a project progress bar to obtain a project completion amount comparison result, which specifically includes:
S31: and obtaining corresponding refinement project completion amount information according to the refinement project plan completion time.
Specifically, a time node after the end of the refinement project represented by the refinement project plan completion time, at which refinement project completion amount information of the corresponding refinement project is acquired.
S32: the method comprises the steps of obtaining resource usage information, comparing the corresponding planning resource amount information in a project progress bar with the resource usage information to obtain a resource usage comparison result, and comparing the refined project completion amount information with the corresponding refined project planning workload in the project progress bar to obtain a project completion amount comparison result.
In the present embodiment, the resource usage amount information refers to the amount of production resources used for the refinement project. The resource usage comparison result refers to the comparison result of the actually used production resource and the production resource planned to be put into.
Specifically, resource usage amount information corresponding to the refined project completion amount information and representing the amount of production resources used by the refined project is obtained, the resource usage amount information is compared with corresponding plan resource amount information in the project progress bar, a resource usage comparison result representing the comparison condition of actually used production resources and production resources planned to be input is obtained, and the refined project completion amount information is compared with corresponding refined project plan workload in the project progress bar, so that a project completion amount comparison result is obtained.
In one embodiment, the allocation resource amount information includes project allocation resource amount information to be allocated and project allocation resource amount information capable of being allocated for refining projects, as shown in fig. 5, in step S40, allocation resource amount information is obtained according to a project completion amount comparison result, and resource allocation information is obtained according to allocation resource amount information, which specifically includes:
S41: and according to the project completion quantity comparison result, if the project completion quantity comparison result is the refined project incomplete information, acquiring the project resource quantity information to be allocated according to the resource use comparison result.
In this embodiment, the project allocation resource amount information refers to the amount of production resources to be allocated to the refinement project.
Specifically, according to the item completion amount comparison result, if the item completion amount comparison result is the refined item incomplete information, the actual completion amount of the refined item is indicated to not reach the production plan amount, then according to the resource usage comparison result, the resource usage comparison result is indicated to not fully use the production resource or to fully use the production resource, when the resource usage comparison result is indicated to not fully use the production resource, the operator completion condition of the refined item is indicated to be poor, but not the production resource amount is indicated to be insufficient, the production resource is not required to be allocated to the refined item, when the resource usage comparison result is indicated to fully use the production resource, the production resource amount is indicated to be insufficient to support the production plan amount of the finished refined item, the production resource amount is required to be allocated to be increased for the follow-up refined item, and the corresponding production resource amount required to be allocated to the follow-up refined item is obtained according to the difference between the actual completion amount indicated by the item completion amount comparison result and the production plan amount.
S42: and if the item completion amount comparison result is the refined item completion information, acquiring the adjustable resource amount information of the refined item according to the resource use comparison result.
In this embodiment, the refinement project-adjustable resource amount information refers to an excess production resource amount of the refinement project.
Specifically, if the item completion amount comparison result is refinement item completion information, the actual completion amount of the refinement item reaches the production plan amount, and when the resource usage comparison result indicates that the resource is completely used, the refinement item completion condition is good, no resource allocation is needed for the refinement item, and when the resource usage comparison result indicates that the resource is not completely used, the refinement item completion condition is excellent, the redundant resource amount can be extracted and distributed to other items or reserved, so that the redundant production resource amount of the refinement item, namely the information of the configurable resource amount of the refinement item, is obtained.
S43: and obtaining the resource allocation information according to the resource allocation information required by the project or the resource allocation information adjustable by the refinement project.
Specifically, according to project allocation resource amount information or project allocation resource amount information, resource allocation information which indicates production resources which need to be allocated into projects and allocation resource allocation information which indicates unnecessary production resources which are allocated into other projects are extracted from the projects are obtained.
In one embodiment, as shown in fig. 6, in step S43, resource allocation information is obtained according to resource allocation information required by a project or resource allocation information capable of being allocated by a refinement project, which specifically includes:
S431: and acquiring the information of the planned increased resource quantity, and obtaining the information of the resource allocation to be allocated according to the information of the planned increased resource quantity and the information of the resource allocation to be allocated of the project.
In the present embodiment, the schedule-increase-resource-amount information refers to an amount of production resources scheduled to increase investment for a project.
Specifically, the production resource amount reserved by the project and used for increasing input when the refined project does not meet the requirement, namely the project increasing resource amount information is obtained, the project increasing resource amount information and the project resource amount information to be allocated are obtained according to the project increasing resource amount information, when the project increasing resource amount information is larger than or equal to the project resource amount information to be allocated, the project resource amount information to be allocated is used as the resource allocation information to be allocated, and when the project increasing resource amount information is smaller than the project resource amount information to be allocated, the project increasing resource amount information is used as the resource allocation information to be allocated.
S432: and obtaining the allocation information of the adjustable resources according to the allocation information of the adjustable resources of the refinement project.
Specifically, the refinement project allotment resource amount information represents the redundant production resource amount of the refinement project, and can be directly extracted and allocated to other projects or reserved, so that the refinement project allotment resource amount information is used as the allotment resource allotment information according to the refinement project allotment resource amount information.
In one embodiment, as shown in fig. 7, in step S50, a comparison project progress bar is generated according to the resource allocation information and the project progress bar, and specifically includes:
s51: and acquiring updated and refined project plan amount information according to the allocation information of the resources to be allocated.
In the present embodiment, updating the plan amount information of the thinned item refers to the adjusted plan amount of the thinned item.
Specifically, according to the amount of production resources added and represented by the allocation information of the resources to be allocated, determining the increment of the planned workload of the refinement project of the next node, namely the increment of the progress of the project progress bar, and adaptively adjusting the subsequent rest of the refinement projects to ensure that the total progress of the projects is within a reasonable range, so as to obtain the planned workload of the refinement project and the corresponding planned completion time of the refinement project after adjustment, namely the planned amount information of the refinement project is updated
S52: and generating an updated project progress bar according to the updated refined project plan amount information.
In this embodiment, the updated project progress bar refers to the adjusted project progress bar.
Specifically, according to updated refined project plan amount information representing the plan amount of the adjusted refined project, a project progress bar is correspondingly adjusted to obtain an updated project progress bar.
S53: and associating the updated project progress bar with the project progress bar to obtain a comparison project progress bar.
Specifically, the updated project progress bar is associated with the project progress bar, and a comparison project progress bar capable of comparing different original project progress bars with the adjusted project progress bar is obtained.
It should be understood that the sequence number of each step in the foregoing embodiment does not mean that the execution sequence of each process should be determined by the function and the internal logic, and should not limit the implementation process of the embodiment of the present application.
In an embodiment, a project schedule adjustment device based on resource allocation is provided, where the project schedule adjustment device based on resource allocation corresponds to the project schedule adjustment method based on resource allocation in the above embodiment one by one. As shown in fig. 8, the project progress adjusting device based on resource allocation includes a refined project plan amount information obtaining module, a project progress bar generating module, a completion amount comparing module, a resource allocation information obtaining module, a comparing project progress bar generating module and a project completion degree information obtaining module. The functional modules are described in detail as follows:
The refined project plan amount information acquisition module is used for acquiring project total plan amount information, triggering project refining instructions, and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
The project progress bar generation module is used for generating a project progress bar according to the refined project plan amount information;
The completion quantity comparison module is used for obtaining refined project completion quantity information, comparing the refined project completion quantity information with a project progress bar to obtain a project completion quantity comparison result, wherein the project completion quantity comparison result comprises refined project incomplete information and refined project completion information;
the resource allocation information acquisition module is used for acquiring allocation resource amount information according to the project completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises project allocation information required to be allocated and project allocation information capable of being allocated for refining projects;
The comparison project progress bar generation module is used for generating a comparison project progress bar according to the resource allocation information and the project progress bar;
And the project completion degree information acquisition module is used for acquiring project completion degree information according to the comparison project progress bar.
Optionally, the refined project plan amount information obtaining module includes:
The project refinement instruction module is used for acquiring project total planning amount information and project type information, and triggering a project refinement instruction according to the project total planning amount information and a preset project refinement rule corresponding to the project type information;
and the refined project plan amount information acquisition sub-module is used for acquiring refined project plan amount information based on the project refining instruction.
Optionally, the project progress bar generating module includes:
the plan resource amount information acquisition sub-module is used for acquiring corresponding plan resource amount information according to the refined project plan amount information;
And the project progress bar generation sub-module is used for generating a project progress bar according to the refined project plan amount information and the plan resource amount information, wherein the project progress bar comprises the refined project plan amount information and the corresponding plan resource amount information.
Optionally, the completion amount comparison module includes:
the refinement project completion amount information acquisition sub-module is used for acquiring corresponding refinement project completion amount information according to the refinement project plan completion time;
The comparison result obtaining sub-module is used for obtaining resource usage amount information, comparing the corresponding planning resource amount information in the project progress bar with the resource usage amount information to obtain a resource usage comparison result, and comparing the refined project completion amount information with the corresponding refined project planning workload in the project progress bar to obtain a project completion amount comparison result.
Optionally, the resource allocation information obtaining module includes:
The project resource quantity information to be allocated is acquired by the project resource quantity information acquisition sub-module according to the project completion quantity comparison result, if the project completion quantity comparison result is the refined project incomplete information, acquiring the project resource quantity information to be allocated according to the resource use comparison result;
the refined project adjustable resource quantity information acquisition sub-module is used for acquiring refined project adjustable resource quantity information according to the resource use comparison result if the project completion quantity comparison result is refined project completion information;
the resource allocation information acquisition sub-module is used for acquiring resource allocation information according to project allocation resource amount information required by projects or project allocation resource amount information capable of being thinned.
Optionally, the resource allocation information obtaining submodule includes:
The resource allocation information to be allocated is used for acquiring the information of the scheduled increase resource quantity, and obtaining the resource allocation information to be allocated according to the information of the scheduled increase resource quantity and the information of the project resource allocation to be allocated;
And the adjustable resource allocation information acquisition unit is used for acquiring the adjustable resource allocation information according to the refined project adjustable resource amount information.
Optionally, the comparison project progress bar generating module includes:
The updated refined project plan amount information acquisition sub-module is used for acquiring updated refined project plan amount information according to the resource allocation information to be allocated;
The updated project progress bar generation sub-module is used for generating an updated project progress bar according to updated refined project plan amount information;
And the comparison project progress bar acquisition sub-module is used for associating the update project progress bar with the project progress bar to obtain the comparison project progress bar.
For specific limitation of the project schedule adjustment apparatus based on resource allocation, reference may be made to the limitation of the project schedule adjustment method based on resource allocation hereinabove, and the description thereof will not be repeated here. The above-mentioned project progress adjusting device based on resource allocation may be implemented in whole or in part by software, hardware and a combination thereof. The above modules may be embedded in hardware or may be independent of a processor in the computer device, or may be stored in software in a memory in the computer device, so that the processor may call and execute operations corresponding to the above modules.
In one embodiment, a computer device is provided, which may be a server, and the internal structure of which may be as shown in fig. 9. The computer device includes a processor, a memory, a network interface, and a database connected by a system bus. Wherein the processor of the computer device is configured to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, computer programs, and a database. The internal memory provides an environment for the operation of the operating system and computer programs in the non-volatile storage media. The database of the computer device is used for storing project progress bars, resource allocation information, comparison project progress bars and the like. The network interface of the computer device is used for communicating with an external terminal through a network connection. The computer program, when executed by a processor, implements a project schedule adjustment method based on resource allocation.
In one embodiment, a computer device is provided comprising a memory, a processor, and a computer program stored on the memory and executable on the processor, the processor implementing the steps of when executing the computer program:
Acquiring project total plan amount information, triggering project refinement instructions, and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
Generating a project progress bar according to the refined project plan amount information;
Obtaining refined project completion amount information, and comparing the refined project completion amount information with a project progress bar to obtain a project completion amount comparison result, wherein the project completion amount comparison result comprises refined project incomplete information and refined project completion information;
acquiring allocation resource amount information according to the item completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises item allocation resource allocation information required to be allocated and item allocation information capable of being allocated in a refinement mode;
generating a comparison project progress bar according to the resource allocation information and the project progress bar;
and obtaining the project completion degree information according to the comparison project progress bar.
In one embodiment, a computer readable storage medium is provided having a computer program stored thereon, which when executed by a processor, performs the steps of:
Acquiring project total plan amount information, triggering project refinement instructions, and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
Generating a project progress bar according to the refined project plan amount information;
Obtaining refined project completion amount information, and comparing the refined project completion amount information with a project progress bar to obtain a project completion amount comparison result, wherein the project completion amount comparison result comprises refined project incomplete information and refined project completion information;
acquiring allocation resource amount information according to the item completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises item allocation resource allocation information required to be allocated and item allocation information capable of being allocated in a refinement mode;
generating a comparison project progress bar according to the resource allocation information and the project progress bar;
and obtaining the project completion degree information according to the comparison project progress bar.
Those skilled in the art will appreciate that implementing all or part of the above described methods may be accomplished by way of a computer program stored on a non-transitory computer readable storage medium, which when executed, may comprise the steps of the embodiments of the methods described above. Any reference to memory, storage, database, or other medium used in embodiments provided herein may include non-volatile and/or volatile memory. The nonvolatile memory can include Read Only Memory (ROM), programmable ROM (PROM), electrically Programmable ROM (EPROM), electrically Erasable Programmable ROM (EEPROM), or flash memory. Volatile memory can include Random Access Memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in a variety of forms such as Static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double Data Rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (SYNCHLINK) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), among others.
It will be apparent to those skilled in the art that, for convenience and brevity of description, only the above-described division of the functional units and modules is illustrated, and in practical application, the above-described functional distribution may be performed by different functional units and modules according to needs, i.e. the internal structure of the apparatus is divided into different functional units or modules to perform all or part of the above-described functions.
The above embodiments are only for illustrating the technical solution of the present application, and not for limiting the same; although the application has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit and scope of the technical solutions of the embodiments of the present application, and are intended to be included in the scope of the present application.

Claims (6)

1. The project progress adjusting method based on resource allocation is characterized by comprising the following steps of:
Acquiring project total plan amount information, triggering project refinement instructions, and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
generating a project progress bar according to the refined project plan amount information;
Obtaining refined project completion amount information, and comparing the refined project completion amount information with the project progress bar to obtain a project completion amount comparison result, wherein the project completion amount comparison result comprises refined project incomplete information and refined project completion information;
Acquiring allocation resource amount information according to the item completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises item allocation resource allocation information required to be allocated and item allocation resource allocation information capable of being allocated for refining the item;
generating a comparison project progress bar according to the resource allocation information and the project progress bar;
obtaining project completion degree information according to the comparison project progress bar;
Generating a project progress bar according to the refined project plan amount information, wherein the project progress bar specifically comprises the following steps:
Acquiring corresponding planning resource amount information according to the refined project planning amount information;
generating a project progress bar according to the refined project plan amount information and the plan resource amount information, wherein the project progress bar comprises the refined project plan amount information and the corresponding plan resource amount information;
The method comprises the steps of obtaining refined project completion amount information, comparing the refined project completion amount information with the project progress bar to obtain a project completion amount comparison result, and specifically comprises the following steps:
acquiring corresponding refinement project completion amount information according to the refinement project plan completion time;
Acquiring resource usage amount information, comparing the corresponding planning resource amount information in the project progress bar with the resource usage amount information to obtain a resource usage comparison result, and comparing the refined project completion amount information with the corresponding refined project planning workload in the project progress bar to obtain a project completion amount comparison result;
the allocation resource amount information comprises project allocation resource amount information to be allocated and project allocation resource amount information capable of being allocated for refining projects, the allocation resource amount information is obtained according to the project completion amount comparison result, and the resource allocation information is obtained according to the allocation resource amount information, and the method specifically comprises the following steps:
According to the project completion amount comparison result, if the project completion amount comparison result is the refined project incomplete information, acquiring project resource amount information to be allocated according to the resource use comparison result;
If the item completion amount comparison result is the refined item completion information, acquiring refined item adjustable resource amount information according to the resource use comparison result;
obtaining resource allocation information according to the resource allocation information required by the project or the resource allocation information adjustable by the refinement project;
The resource allocation information is obtained according to the resource allocation information required by the project or the resource allocation information adjustable by the refinement project, and specifically comprises the following steps:
acquiring information of a planned increase resource amount, and obtaining information of resource allocation to be allocated according to the information of the planned increase resource amount and the information of the resource amount to be allocated of the project;
and obtaining the allocation information of the allocated resources according to the information of the allocated resources of the refinement project.
2. The resource allocation-based project progress adjustment method according to claim 1, wherein the obtaining project total plan amount information triggers a project refinement instruction to obtain refined project plan amount information, and specifically comprises:
Acquiring project total planning amount information and project type information, and triggering a project refining instruction according to the project total planning amount information and a preset project refining rule corresponding to the project type information;
and obtaining refined project plan amount information based on the project refinement instruction.
3. The project progress adjustment method based on resource allocation according to claim 1, wherein the generating a comparison project progress bar according to the resource allocation information and the project progress bar specifically comprises:
Acquiring updated and refined project plan amount information according to the resource allocation information to be allocated;
Generating an updated project progress bar according to the updated refined project plan amount information;
and associating the updated project progress bar with the project progress bar to obtain a comparison project progress bar.
4. The project progress adjusting device based on resource allocation is characterized by comprising:
The refined project plan amount information acquisition module is used for acquiring project total plan amount information, triggering project refining instructions and acquiring refined project plan amount information, wherein the refined project plan amount information comprises refined project plan workload and corresponding refined project plan completion time;
The project progress bar generation module is used for generating a project progress bar according to the refined project plan amount information;
The completion quantity comparison module is used for obtaining refined project completion quantity information, comparing the refined project completion quantity information with the project progress bar to obtain a project completion quantity comparison result, wherein the project completion quantity comparison result comprises refined project incomplete information and refined project completion information;
the resource allocation information acquisition module is used for acquiring allocation resource amount information according to the project completion amount comparison result, and acquiring resource allocation information according to the allocation resource amount information, wherein the resource allocation information comprises project allocation resource allocation information required to be allocated and project allocation information capable of being allocated for refining projects;
The comparison project progress bar generation module is used for generating a comparison project progress bar according to the resource allocation information and the project progress bar;
The project completion degree information acquisition module is used for acquiring project completion degree information according to the comparison project progress bar;
the project progress bar generation module comprises:
the plan resource amount information acquisition sub-module is used for acquiring corresponding plan resource amount information according to the refined project plan amount information;
the project progress bar generation sub-module is used for generating a project progress bar according to the refined project plan amount information and the plan resource amount information, wherein the project progress bar comprises the refined project plan amount information and the corresponding plan resource amount information;
the completion amount comparison module includes:
the refinement project completion amount information acquisition sub-module is used for acquiring corresponding refinement project completion amount information according to the refinement project plan completion time;
the comparison result acquisition sub-module is used for acquiring resource usage amount information, comparing the corresponding planning resource amount information in the project progress bar with the resource usage amount information to obtain a resource usage comparison result, and comparing the refined project completion amount information with the corresponding refined project planning workload in the project progress bar to obtain a project completion amount comparison result;
the resource allocation information acquisition module includes:
The project resource quantity information to be allocated is acquired by the project resource quantity information acquisition sub-module according to the project completion quantity comparison result, if the project completion quantity comparison result is the refined project incomplete information, acquiring the project resource quantity information to be allocated according to the resource use comparison result;
the refined project adjustable resource quantity information acquisition sub-module is used for acquiring refined project adjustable resource quantity information according to the resource use comparison result if the project completion quantity comparison result is refined project completion information;
The resource allocation information acquisition sub-module is used for acquiring resource allocation information according to project allocation resource amount information required by projects or project allocation resource amount information capable of being thinned;
the resource allocation information acquisition submodule comprises:
The resource allocation information to be allocated is used for acquiring the information of the scheduled increase resource quantity, and obtaining the resource allocation information to be allocated according to the information of the scheduled increase resource quantity and the information of the project resource allocation to be allocated;
And the adjustable resource allocation information acquisition unit is used for acquiring the adjustable resource allocation information according to the refined project adjustable resource amount information.
5. A computer device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, characterized in that the processor implements the steps of the resource allocation based project progress adjustment method according to any of claims 1to 3 when the computer program is executed.
6. A computer readable storage medium storing a computer program, wherein the computer program when executed by a processor implements the steps of the resource allocation based project progress adjustment method of any of claims 1 to 3.
CN202311278828.9A 2023-09-28 2023-09-28 Project progress adjustment method, device, equipment and medium based on resource allocation Active CN117291384B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311278828.9A CN117291384B (en) 2023-09-28 2023-09-28 Project progress adjustment method, device, equipment and medium based on resource allocation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311278828.9A CN117291384B (en) 2023-09-28 2023-09-28 Project progress adjustment method, device, equipment and medium based on resource allocation

Publications (2)

Publication Number Publication Date
CN117291384A CN117291384A (en) 2023-12-26
CN117291384B true CN117291384B (en) 2024-05-31

Family

ID=89240559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311278828.9A Active CN117291384B (en) 2023-09-28 2023-09-28 Project progress adjustment method, device, equipment and medium based on resource allocation

Country Status (1)

Country Link
CN (1) CN117291384B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106651309A (en) * 2016-12-23 2017-05-10 国网山东省电力公司 Project schedule tracking adjustment method and system based on PERT
CN206549927U (en) * 2017-02-08 2017-10-13 广州市明辉彩印有限公司 A kind of paper wrapper high-performance automatic double surface gluer
CN110599125A (en) * 2019-09-05 2019-12-20 广东牵引信息科技有限公司 Dynamic list generation system and method for project management
CN112967025A (en) * 2020-07-09 2021-06-15 北京中百信信息技术股份有限公司 Information engineering supervision project image progress management system
CN113537941A (en) * 2021-07-22 2021-10-22 重庆电子工程职业学院 Real-time dynamic progress control method and device for engineering management
CN114648309A (en) * 2022-03-28 2022-06-21 陕西清水川能源股份有限公司 Project node control method, device, equipment, storage medium and program product
CN116502877A (en) * 2023-06-29 2023-07-28 北京康特瑞科统计科技有限责任公司 Project progress monitoring method and device, electronic equipment and readable storage medium

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20200327467A1 (en) * 2019-04-11 2020-10-15 Tim Davies Method and system for automated project management workflow and monitoring
CN113467907A (en) * 2021-06-21 2021-10-01 北京达佳互联信息技术有限公司 Task processing method and device, electronic equipment and storage medium

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106651309A (en) * 2016-12-23 2017-05-10 国网山东省电力公司 Project schedule tracking adjustment method and system based on PERT
CN206549927U (en) * 2017-02-08 2017-10-13 广州市明辉彩印有限公司 A kind of paper wrapper high-performance automatic double surface gluer
CN110599125A (en) * 2019-09-05 2019-12-20 广东牵引信息科技有限公司 Dynamic list generation system and method for project management
CN112967025A (en) * 2020-07-09 2021-06-15 北京中百信信息技术股份有限公司 Information engineering supervision project image progress management system
CN113537941A (en) * 2021-07-22 2021-10-22 重庆电子工程职业学院 Real-time dynamic progress control method and device for engineering management
CN114648309A (en) * 2022-03-28 2022-06-21 陕西清水川能源股份有限公司 Project node control method, device, equipment, storage medium and program product
CN116502877A (en) * 2023-06-29 2023-07-28 北京康特瑞科统计科技有限责任公司 Project progress monitoring method and device, electronic equipment and readable storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
工程项目信息化管理主要模块的应用及解决要点;吴常明;;陕西建筑;20101115(第11期);第123-125页 *

Also Published As

Publication number Publication date
CN117291384A (en) 2023-12-26

Similar Documents

Publication Publication Date Title
CN114625507B (en) Task scheduling method, system, equipment and storage medium based on directed acyclic graph
CN109284289B (en) Data set processing method and device, computer equipment and storage medium
CN114239951A (en) Satellite measurement and control task scheduling method, device and equipment based on hierarchical optimization
CN110968647A (en) Data storage method and device, computer equipment and storage medium
WO2022127122A1 (en) Dynamic configuration method and apparatus for node permissions in blockchain network
CN110633306A (en) Service data processing method and device, computer equipment and storage medium
CN112101584A (en) Nuclear power station spare part systematic maintenance method, device, equipment and storage medium
CN114968739A (en) Operation and maintenance task management method, operation and maintenance method, device, equipment and medium
CN112288400A (en) Multi-system data interaction method and device, computer equipment and storage medium
CN110084476B (en) Case adjustment method, device, computer equipment and storage medium
CN111260253A (en) Information sending method and device, computer equipment and storage medium
CN117291384B (en) Project progress adjustment method, device, equipment and medium based on resource allocation
CN108629050B (en) Service data adjustment method, device, computer equipment and storage medium
CN110298549B (en) Project task processing method, device, equipment and medium for airport construction engineering
CN111125097B (en) Report scheduling method and device
CN111506400A (en) Computing resource allocation system, method, device and computer equipment
CN112101848A (en) Nuclear power plant strategic material receiving method, device, equipment and medium for combined reserve
CN113419672B (en) Storage capacity management method, system and storage medium
CN112000660B (en) Multi-report data processing method and device, computer equipment and storage medium
CN109525675B (en) Northbound server file downloading method and device, computer equipment and storage medium
CN114841661A (en) Discrete processing management method and system
CN110532533B (en) Form precision collocation method, device, computer equipment and storage medium
CN113988804A (en) Digital management method, device, equipment and storage medium for whole engineering construction process
CN113159657A (en) Execution resource allocation method, device and storage medium for procedures
Zola et al. Energy efficient virtual machine consolidation under uncertain input parameters for green data centers

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant