CN117252654B - Engineering cost calculation system and method based on Revit model - Google Patents

Engineering cost calculation system and method based on Revit model Download PDF

Info

Publication number
CN117252654B
CN117252654B CN202311548232.6A CN202311548232A CN117252654B CN 117252654 B CN117252654 B CN 117252654B CN 202311548232 A CN202311548232 A CN 202311548232A CN 117252654 B CN117252654 B CN 117252654B
Authority
CN
China
Prior art keywords
cost
building
module
equipment
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202311548232.6A
Other languages
Chinese (zh)
Other versions
CN117252654A (en
Inventor
李平
沈琦俊
王小波
朱静
季鑫桃
何超
王晓觅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jianke Engineering Consulting Co ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Jiangsu Jianke Engineering Consulting Co ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jianke Engineering Consulting Co ltd, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical Jiangsu Jianke Engineering Consulting Co ltd
Priority to CN202311548232.6A priority Critical patent/CN117252654B/en
Publication of CN117252654A publication Critical patent/CN117252654A/en
Application granted granted Critical
Publication of CN117252654B publication Critical patent/CN117252654B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0283Price estimation or determination
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0481Interaction techniques based on graphical user interfaces [GUI] based on specific properties of the displayed interaction object or a metaphor-based environment, e.g. interaction with desktop elements like windows or icons, or assisted by a cursor's changing behaviour or appearance
    • G06F3/0482Interaction with lists of selectable items, e.g. menus
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0484Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range
    • G06F3/04845Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range for image manipulation, e.g. dragging, rotation, expansion or change of colour
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/10Constructive solid geometry [CSG] using solid primitives, e.g. cylinders, cubes
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T19/00Manipulating 3D models or images for computer graphics
    • G06T19/20Editing of 3D images, e.g. changing shapes or colours, aligning objects or positioning parts
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

The invention discloses a project cost calculation system and a project cost calculation method based on a Revit model, wherein the calculation method adopts a cost calculation system to work, the system comprises a Revit model generation module, a cost estimation module and a recommendation ordering module, the Revit model generation module is used for generating a three-dimensional model of a building in a three-dimensional coordinate system, the cost calculation module is used for calculating the total cost and the real-time cost of the design scheme, the recommendation ordering module is used for ordering materials and equipment in an alternative column according to budgets and recommendation weights, the Revit model generation module comprises a parameter establishment module, a model retrieval module, a big data fitting module, a three-dimensional coordinate system establishment module and a model library, the parameter establishment module is used for inputting the type, layout, area and height parameters of the building, and the model retrieval module is used for retrieving the building model required by the load according to the input parameters.

Description

Engineering cost calculation system and method based on Revit model
Technical Field
The invention relates to the technical field of engineering cost, in particular to an engineering cost calculation system and method based on a Revit model.
Background
The Revit model includes various data of the three-dimensional geometry of the building, component properties, material information, equipment and system components, and the like. The Revit model can provide visual effect graphs and animation presentations for building projects, so that customers can better understand and evaluate building design schemes.
The existing construction engineering cost calculation mode is to design first, price according to the design result, and often the situation that the budget is exceeded occurs, at this time, the designer needs to plan and adjust again, and real-time cost evaluation and material selection recommendation cannot be carried out on the design. Therefore, it is necessary to design a construction cost computing system and method based on a Revit model for real-time evaluation.
Disclosure of Invention
The invention aims to provide a project cost calculation system and method based on a Revit model, which are used for solving the problems in the background technology.
In order to solve the technical problems, the invention provides the following technical scheme: the project cost calculating method based on the Revit model adopts a cost calculating system to work, the system comprises a Revit model generating module, a cost estimating module and a recommended sorting module, the Revit model generating module is used for generating a three-dimensional model of a building in a three-dimensional coordinate system, the cost calculating module is used for calculating the total cost and the real-time cost of the design scheme, and the recommended sorting module is used for sorting materials and equipment in an alternative column according to budgets and recommended weights.
According to the technical scheme, the Revit model generation module comprises a parameter establishment module, a model retrieval module, a big data fitting module, a three-dimensional coordinate system establishment module and a model library, wherein the parameter establishment module is used for inputting the type, layout, area and height parameters of a building, the model retrieval module is used for retrieving a building model required by a load according to the input parameters, the big data fitting module is used for carrying out big data-based close fitting on the building model conforming to the model library, the three-dimensional coordinate system establishment module is used for establishing a meshed three-dimensional model for placing the building model, and the model library is used for storing the designed building model;
the manufacturing cost estimation module comprises a type distinguishing module, a volume calculation module, a material equipment determination module and a unit cost measurement module, wherein the type distinguishing module is used for establishing a specific type of a current design building, the volume calculation module is used for calculating the occupied space of a building model, the material equipment determination module is used for selecting all materials and equipment types of the current building model, and the unit cost measurement module is used for calculating the material cost of a unit area and the equipment cost of a unit volume;
the recommendation ordering module comprises an alternative display module, an ordering establishment module and a weight adjustment module, wherein the alternative display module is used for selecting and displaying alternative materials and equipment in a current design area for a designer to select, the ordering establishment module is used for ordering the manufacturing cost of various materials and equipment and establishing the ordering of recommended materials and equipment manufacturing cost, and the weight adjustment module is used for adjusting the recommendation weight according to the evaluation of the designer and a building owner;
the weight adjustment module comprises a timing module, an evaluation module and a selection frequency calculation module, wherein the timing module is used for counting the service life of a certain building design, the evaluation module is used for carrying out return visit evaluation on a building owner, and the selection frequency calculation module is used for calculating the frequency of adopting a certain material or equipment by a designer.
According to the technical scheme, the method comprises the following main steps:
s1, a designer generates a preliminary three-dimensional model by using a Revit model according to the requirements and planning of the building engineering design, wherein the model content is the main structure and appearance characteristics of the building;
s2, estimating according to the average cost in the model library, and primarily estimating the cost of the design scheme according to the building type and combining the average cost data in the model library;
s3, determining the type recommended range of materials and equipment according to the cost budget of the design scheme;
s4, combining historical evaluation and market feedback, and arranging alternative materials and equipment;
s5, calculating the current cost in real time, and when the type selection is carried out, calculating in real time according to the current cost, and adjusting the type recommended subsequently, so that the design scheme is economically feasible;
s6, after the final type selection is determined, determining the engineering cost of the design.
According to the above technical solution, in the step S1, a method for generating a preliminary three-dimensional model is as follows: after the type, layout, area and height parameters of the building are determined, the Revit model software can search a model library, select finished products in the model library which are the same in type and layout and similar in area and height parameters, fit a rough building model shape, place the building model in a grid-shaped three-dimensional coordinate system, drag lines at the edges of the model by a mouse for fine adjustment of a designer, and automatically attach the lines on grids of the nearest three-dimensional coordinate system.
According to the above technical scheme, in the step S2, the method for performing preliminary estimation on the manufacturing cost is as follows: naming building types of each component in the three-dimensional model, selecting unit volume cost of all the building types in the model library to average, and finally calculating total preliminary cost Wherein->Cost per unit material for a certain building type in the model base,/-, for>Cost per unit equipment for a certain building type in model base,/->For the number of building types>Is the volume of a certain building type in the present design.
According to the technical scheme, in the step S3, all suitable alternative materials and equipment of the current building type are firstly ordered according to the price, and then the cost budget according to the current design scheme isAnd total preliminary costIs recommended for materials and equipment according to the cost sequence and extends upwards and downwards by a certain proportion +.>Alternatively, specifically:
the average cost of the materials and equipment used by the current building type is that the cost of all the materials and equipment suitable for the current building type is ordered as beforeEach material and equipment has independent ordering, and the materials and equipment recommended by the design are ordered before the manufacturing cost of all materials and equipment suitable for the current building type is increased>The formula is:
cost budget for this designThe higher the recommended materials and equipment cost ordering the earlier, the recommended range of alternative materials and equipment is: />
According to the above technical solution, in the step S4, the specific method for arranging the alternative materials and devices is as follows:
the recommendation weight is introduced, materials and equipment with higher recommendation weight are displayed at more prominent positions in the candidate bar, each material and equipment has a respective evaluation system, the evaluation system is divided into designer favor and building owner satisfaction, and the recommendation weight is calculated according to the evaluation systemThe method comprises the following steps: />Wherein->Average favour for designers of a certain material, equipment,/->For average satisfaction of building owners of a certain material and equipment, when the certain material and equipment are in the alternative columns and selected by designers, the favorability is improved, when the certain material and equipment are in the alternative columns and are not selected, the favorability is reduced, the favorability is unchanged in the alternative columns, the building owners are revisited every fixed period when the satisfaction is investigated, and when the certain material and equipment are given poor feedback by the building owners, the satisfaction of the building owners is reduced>,/>、/>Respectively mean by the designerWeight coefficients for favorability and average satisfaction of building owners.
According to the above technical solution, in the above step S5, when a designer uses a certain material or equipment, firstly, a model pattern using the material or equipment is generated on the Revit model software, and is brought into the three-dimensional coordinate system to obtain the coverage area of the material, and the model and size of the equipment, the cost is calculated by combining the cost of the material and the equipment, and if the cost budget remaining in the design is exceeded, the cost ordering of the subsequent non-design area is reducedIf the remaining cost budget of the design scheme is not reached, the cost ordering of the subsequent non-design area is improved>Become newThe method specifically comprises the following steps: />=/>
In the method, in the process of the invention,in order to achieve the cost, i.e. the total cost calculated for the materials and equipment that have been selected by the designer,setting the cost for the standard, i.e. the total material is according to +.>The total cost achieved when designing the cost ordering of (c).
Compared with the prior art, the invention has the following beneficial effects: the invention firstly generates a rough three-dimensional model before building design, then estimates the cost of the design according to the average cost in a model library, and when the type is specifically selected, arranges and recommends alternative types according to historical evaluation, simultaneously calculates the current cost in real time and adjusts the type recommended subsequently.
Drawings
The accompanying drawings are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate the invention and together with the embodiments of the invention, serve to explain the invention. In the drawings:
fig. 1 is a schematic view of the overall module structure of the present invention.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1, the present invention provides the following technical solutions: the project cost calculating method based on the Revit model adopts a cost calculating system to work, the system comprises a Revit model generating module, a cost estimating module and a recommended sorting module, the Revit model generating module is used for generating a three-dimensional model of a building in a three-dimensional coordinate system, the cost calculating module is used for calculating the total cost and the real-time cost of the design scheme, and the recommended sorting module is used for sorting materials and equipment in an alternative column according to budgets and recommended weights;
the Revit model generation module comprises a parameter establishment module, a model retrieval module, a big data fitting module, a three-dimensional coordinate system establishment module and a model library, wherein the parameter establishment module is used for inputting the type, layout, area and height parameters of a building, the model retrieval module is used for retrieving a building model required by a load according to the input parameters, the big data fitting module is used for carrying out big data-based close fitting on the building model conforming to the model library, the three-dimensional coordinate system establishment module is used for establishing a gridded three-dimensional model for placing the building model, and the model library is used for storing the designed building model;
the manufacturing cost estimation module comprises a type distinguishing module, a volume calculation module, a material equipment determination module and a unit cost measurement module, wherein the type distinguishing module is used for establishing a specific type of a current design building, the volume calculation module is used for calculating the occupied space of the building model, the material equipment determination module is used for selecting all materials and equipment types of the current building model, and the unit cost measurement module is used for calculating the material cost of a unit area and the equipment cost of the unit volume;
the recommendation ordering module comprises an alternative display module, an ordering establishment module and a weight adjustment module, wherein the alternative display module is used for selecting and displaying alternative materials and equipment in a current design area for a designer to select, the ordering establishment module is used for ordering the manufacturing cost of various materials and equipment and establishing the ordering of recommended materials and equipment manufacturing cost, and the weight adjustment module is used for adjusting the recommendation weight according to the evaluation of the designer and a building owner;
the weight adjustment module comprises a timing module, an evaluation module and a frequency selection calculation module, wherein the timing module is used for counting the service life of a certain building design, the evaluation module is used for carrying out return visit evaluation on a building owner, and the frequency selection calculation module is used for calculating the frequency of adopting a certain material or equipment by a designer;
the method comprises the following main steps:
s1, a designer generates a preliminary three-dimensional model by using a Revit model according to the requirements and planning of the building engineering design, wherein the model content is the main structure and appearance characteristics of the building;
s2, estimating according to the average cost in the model library, and primarily estimating the cost of the design scheme according to the building type and combining the average cost data in the model library;
s3, determining the type recommended range of materials and equipment according to the cost budget of the design scheme;
s4, combining historical evaluation and market feedback, and arranging alternative materials and equipment;
s5, calculating the current cost in real time, and when the type selection is carried out, calculating in real time according to the current cost, and adjusting the type recommended subsequently, so that the design scheme is economically feasible;
s6, after determining the final type selection, determining the engineering cost of the design;
in the step S1, a preliminary three-dimensional model is generated by: after the type, layout, area and height parameters of the building are determined, the Revit model software can search a model library, select finished products in the model library which are the same in type and layout and similar in area and height parameters, fit a rough building model shape, place the building model in a grid-shaped three-dimensional coordinate system, drag lines at the edge of the model by a mouse for fine adjustment of a designer, and automatically attach the lines on grids of the nearest three-dimensional coordinate system;
in the step S2, the method for performing preliminary estimation on the cost includes: naming building types of each component in the three-dimensional model, selecting unit volume cost of all the building types in the model library to average, and finally calculating total preliminary costWherein->Cost per unit material for a certain building type in the model base,/-, for>Cost per unit equipment for a certain building type in model base,/->For the number of building types>In the design ofThe volume of a certain building type;
in the step S3, all suitable alternative materials and equipment of the current building type are firstly ordered according to the price, and then the cost budget according to the design scheme isAnd total preliminary cost->Is recommended for materials and equipment according to the cost sequence and extends upwards and downwards by a certain proportion +.>Alternatively, specifically:
the average cost of the materials and equipment used by the current building type is that the cost of all the materials and equipment suitable for the current building type is ordered as beforeEach material and equipment has independent ordering, and the materials and equipment recommended by the design are ordered before the manufacturing cost of all materials and equipment suitable for the current building type is increased>The formula is: />
Cost budget for this designThe higher the recommended materials and equipment cost ordering the earlier, the recommended range of alternative materials and equipment is: />
In the step S4, the specific method for arranging the alternative materials and devices is as follows:
introducing a recommendation weight, the higher the recommendation weight, the material andthe equipment can be displayed in a more prominent position in the alternative column, each material and equipment has a respective evaluation system, the evaluation system is divided into a designer favor degree and a building owner satisfaction degree, and the recommendation weights are used for recommendationThe method comprises the following steps: />Wherein->Average favour for designers of a certain material, equipment,/->For average satisfaction of building owners of a certain material and equipment, when the certain material and equipment are in the alternative columns and selected by designers, the favorability is improved, when the certain material and equipment are in the alternative columns and are not selected, the favorability is reduced, the favorability is unchanged in the alternative columns, the building owners are revisited every fixed period when the satisfaction is investigated, and when the certain material and equipment are given poor feedback by the building owners, the satisfaction of the building owners is reduced>,/>、/>Respectively the average degree of favour of the designer and the average degree of satisfaction of the building owners;
in the above step S5, when a designer uses a certain material or equipment, firstly, a model pattern using the material or equipment is generated on the Revit model software, and is brought into a three-dimensional coordinate system to obtain the coverage area of the material, and the model and size of the equipment, the cost is calculated by combining the cost of the material and the equipment, and if the remaining cost budget of the design scheme is exceeded, the subsequent un-design is reducedCost ordering of regionsIf the remaining cost budget of the design scheme is not reached, the cost ordering of the subsequent non-design area is improved>Become new->The method specifically comprises the following steps:
=/>
in the method, in the process of the invention,in order to achieve the cost, i.e. the total cost calculated for the materials and equipment that have been selected by the designer,setting the cost for the standard, i.e. the total material is according to +.>The total cost achieved when designing the cost ordering of (c).
In the above step S2, the building types are classified into residential building, commercial building, industrial building, educational building, medical building, cultural building, sports building, and the division in advance is helpful for more accurate cost calculation due to the great difference in materials and structures of the building with different functions.
The building type is further subdivided into functional types such as meeting rooms, kitchens, terraces and the like, and is a large type of vertical subdivision small type.
The alternative materials in the step S4 include wall materials, roof materials, door and window materials and floor materials,
the equipment includes heating equipment, ventilation equipment, power equipment, water supply equipment and the like.
In the above-mentioned step S4,and->Adjustment according to the age of the material or device, < > or->And->The adjustment method of (2) is that, in the early stage of the use of the material or the equipment on the building, the satisfaction of the building owners is +.>All will be deficient and high, thus decreasing satisfaction->To increase the weight of the design person to favor the degree +.>Because of the sufficient experience of the designer, the more favored solution should be more prominently presented, reducing the screening cost of the subsequent designs, and as the service life is prolonged, problems with materials or equipment will develop, and many building owners will feed back materials or equipment that have a low life or are in problem during use, thereby improving satisfaction>To correspondingly reduce the weight of the design person>The specific formula is as follows:
wherein the method comprises the steps ofFor the service life of the current material or device in the building, < >>The critical period for which problems easily occur is set according to actual conditions.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Finally, it should be noted that: the foregoing description is only a preferred embodiment of the present invention, and the present invention is not limited thereto, but it is to be understood that modifications and equivalents of some of the technical features described in the foregoing embodiments may be made by those skilled in the art, although the present invention has been described in detail with reference to the foregoing embodiments. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (1)

1. The engineering cost calculation system based on the Revit model is characterized in that: the system comprises a Revit model generation module, a cost estimation module and a recommendation ordering module, wherein the Revit model generation module is used for generating a three-dimensional model of a building in a three-dimensional coordinate system, the cost estimation module is used for calculating the total cost and the real-time cost of the design scheme, and the recommendation ordering module is used for ordering materials and equipment in an alternative column according to budget and recommendation weight;
the Revit model generation module comprises a parameter establishment module, a model retrieval module, a big data fitting module, a three-dimensional coordinate system establishment module and a model library, wherein the parameter establishment module is used for inputting the type, layout, area and height parameters of a building, the model retrieval module is used for retrieving a building model required by a load according to the input parameters, the big data fitting module is used for carrying out big data-based close fitting on the building model conforming to the model library, the three-dimensional coordinate system establishment module is used for establishing a gridded three-dimensional model for placing the building model, and the model library is used for storing the designed building model;
the manufacturing cost estimation module comprises a type distinguishing module, a volume calculation module, a material equipment determination module and a unit cost measurement module, wherein the type distinguishing module is used for establishing a specific type of a current design building, the volume calculation module is used for calculating the occupied space of a building model, the material equipment determination module is used for selecting all materials and equipment types of the current building model, and the unit cost measurement module is used for calculating the material cost of a unit area and the equipment cost of a unit volume;
the recommendation ordering module comprises an alternative display module, an ordering establishment module and a weight adjustment module, wherein the alternative display module is used for selecting and displaying alternative materials and equipment in a current design area for a designer to select, the ordering establishment module is used for ordering the manufacturing cost of various materials and equipment and establishing the ordering of recommended materials and equipment manufacturing cost, and the weight adjustment module is used for adjusting the recommendation weight according to the evaluation of the designer and a building owner;
the weight adjustment module comprises a timing module, an evaluation module and a selected frequency calculation module, wherein the timing module is used for counting the service life of a certain building design, the evaluation module is used for carrying out return visit evaluation on a building owner, and the selected frequency calculation module is used for calculating the frequency of adopting a certain material or equipment by a designer;
the method comprises the following main steps:
s1, a designer generates a preliminary three-dimensional model by using a Revit model according to the requirements and planning of the building engineering design, wherein the model content is the main structure and appearance characteristics of the building;
s2, estimating according to the average cost in the model library, and primarily estimating the cost of the design scheme according to the building type and combining the average cost data in the model library;
s3, determining the type recommended range of materials and equipment according to the cost budget of the design scheme;
s4, combining historical evaluation and market feedback, and arranging alternative materials and equipment;
s5, calculating the current cost in real time, and when the type selection is carried out, calculating in real time according to the current cost, and adjusting the type recommended subsequently, so that the design scheme is economically feasible;
s6, after determining the final type selection, determining the engineering cost of the design;
in the step S1, a preliminary three-dimensional model is generated by: after the type, layout, area and height parameters of the building are determined, the Revit model software can search a model library, select finished products in the model library which are the same in type and layout and similar in area and height parameters, fit a rough building model shape, place the building model in a grid-shaped three-dimensional coordinate system, drag lines at the edge of the model by a mouse for fine adjustment of a designer, and automatically attach the lines on grids of the nearest three-dimensional coordinate system;
in the step S2, the method for performing preliminary estimation on the cost includes: naming building types of each component in the three-dimensional model, selecting unit volume cost of all the building types in the model library to average, and finally calculating total preliminary cost W 0 ,W 0 =(A 1 +B 1 )v 1 +(A 2 +B 2 )v 2 +...+(A n +B n )v n Wherein A is the unit material cost of a certain building type in the model library, B is the unit equipment cost of a certain building type in the model library, n is the number of building types, and v isThe volume of a certain building type in the design;
in the step S3, all suitable alternative materials and equipment of the current building type are firstly ordered according to the price, and then the cost budget according to the current design scheme is W 1 And total preliminary cost W 0 Materials and equipment are recommended according to the cost sequence, and a certain proportion m% extends upwards and downwards as an alternative, specifically:
the average cost of materials and equipment used by the current building type is X% before the cost of all materials and equipment suitable for the current building type, each material and equipment has independent sequencing, the cost of materials and equipment recommended by the design is Y% before the cost of all materials and equipment suitable for the current building type is sequenced, and the formula is:
cost budget W for this design 1 The higher the recommended materials and equipment cost ordering the earlier, the recommended range of alternative materials and equipment is: [ X% -m%, X% +m ]];
In the step S4, the specific method for arranging the alternative materials and devices is as follows:
the recommendation weight is introduced, materials and equipment with higher recommendation weight are displayed at more prominent positions in the candidate bar, each material and equipment has a respective evaluation system, the evaluation system is divided into a designer favor degree and a building owner satisfaction degree, and the recommendation weight H is specifically as follows: h=μd+τf, where D is the average designer preference of a material, device, F is the average satisfaction of the building owners of a material, device, and when a material, device appears in the candidate bar and is selected by the designer, the preference is increased, when a material, device appears in the candidate bar and is not selected, the preference is decreased, when a material, device does not appear in the candidate bar, the preference is unchanged, the building owners are revisited every fixed period when satisfaction is investigated, when a material, device is given poor feedback by the building owners, the satisfaction F of the building owners is decreased, μ, τ are the weight coefficients of the average designer preference and the average satisfaction of the building owners, respectively;
in the step S4, μ and τ are adjusted according to the service life of the material or the equipment, and the adjustment method of μ and τ is that, in the early stage of the use of the material or the equipment on the building, since the building owners will not find problems quickly, the satisfaction degree F of the building owners will be high, so the weight of the satisfaction degree F is reduced, the weight of the designer favoring the degree D is increased, the more favored scheme of the designer should be displayed more prominently, the screening cost of the subsequent design is reduced, the problem of the material or the equipment will develop gradually when the service life is prolonged, and many building owners will feed back the material or the equipment with problems in the service life or the use process, so the weight of the satisfaction degree F is increased to correspondingly reduce the weight of the designer favoring the degree D, and the specific formula is as follows:
wherein t is the service life of the current material or equipment on the building, t 0 Setting a critical period for easily causing problems according to actual conditions;
in the above step S5, when a designer uses a certain material or equipment, firstly, a model pattern using the material or equipment is generated on the Revit model software, and the model pattern is brought into a three-dimensional coordinate system to obtain the coverage area of the material, and the model and size of the equipment, the cost is calculated in combination with the cost of the material and the equipment, if the cost budget remaining in the design scheme is exceeded, the cost ordering Y% of the subsequent non-design area is reduced, and if the cost budget remaining in the design scheme is not reached, the cost ordering Y% of the subsequent non-design area is increased, and the new Y is changed 1 The specific steps are as follows:
in which W is 2 For the cost realized, i.e. the total cost calculated for the materials and equipment already selected by the designer, W 3 The cost is set for the standard, i.e. the total cost achieved when all materials are designed according to a cost order of Y%.
CN202311548232.6A 2023-11-20 2023-11-20 Engineering cost calculation system and method based on Revit model Active CN117252654B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311548232.6A CN117252654B (en) 2023-11-20 2023-11-20 Engineering cost calculation system and method based on Revit model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311548232.6A CN117252654B (en) 2023-11-20 2023-11-20 Engineering cost calculation system and method based on Revit model

Publications (2)

Publication Number Publication Date
CN117252654A CN117252654A (en) 2023-12-19
CN117252654B true CN117252654B (en) 2024-02-27

Family

ID=89135490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311548232.6A Active CN117252654B (en) 2023-11-20 2023-11-20 Engineering cost calculation system and method based on Revit model

Country Status (1)

Country Link
CN (1) CN117252654B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110704929A (en) * 2019-09-29 2020-01-17 中铁二院工程集团有限责任公司 Green building auxiliary optimization system based on BIM + GIS and case reasoning
CN111259480A (en) * 2020-01-20 2020-06-09 中冠工程管理咨询有限公司 Engineering cost consultation management method, system and computer storage medium
CN112581093A (en) * 2020-12-23 2021-03-30 无锡航吴科技有限公司 Project review process method under online fusion line
CN115907675A (en) * 2022-12-13 2023-04-04 中国人民解放军军事科学院国防工程研究院 Intelligent management system for engineering cost evaluation and analysis based on cloud computing and big data
CN116090046A (en) * 2022-12-13 2023-05-09 中国人民解放军军事科学院国防工程研究院 Project cost calculation method based on Revit model
CN116579795A (en) * 2023-05-10 2023-08-11 河南建匠勘测设计研究院有限公司 Municipal construction engineering cost evaluation system based on big data

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110704929A (en) * 2019-09-29 2020-01-17 中铁二院工程集团有限责任公司 Green building auxiliary optimization system based on BIM + GIS and case reasoning
CN111259480A (en) * 2020-01-20 2020-06-09 中冠工程管理咨询有限公司 Engineering cost consultation management method, system and computer storage medium
CN112581093A (en) * 2020-12-23 2021-03-30 无锡航吴科技有限公司 Project review process method under online fusion line
CN115907675A (en) * 2022-12-13 2023-04-04 中国人民解放军军事科学院国防工程研究院 Intelligent management system for engineering cost evaluation and analysis based on cloud computing and big data
CN116090046A (en) * 2022-12-13 2023-05-09 中国人民解放军军事科学院国防工程研究院 Project cost calculation method based on Revit model
CN116579795A (en) * 2023-05-10 2023-08-11 河南建匠勘测设计研究院有限公司 Municipal construction engineering cost evaluation system based on big data

Also Published As

Publication number Publication date
CN117252654A (en) 2023-12-19

Similar Documents

Publication Publication Date Title
US8260581B2 (en) Joining and disjoining individual rooms in a floor plan
US8117558B2 (en) Converting web content into two-dimensional CAD drawings and three-dimensional CAD models
US9019266B2 (en) Systems, methods, and computer program products for home and landscape design
US20080126020A1 (en) Visual bookmarks for home and landscape design
US20080126023A1 (en) Searching and Matching Related objects, Drawings and Models For Home and Landscape Design
CN107657551B (en) The implementation method of total solution is lived by family based on information-based business model
US20080126021A1 (en) Converting web content into texture mapping objects
US20210019455A1 (en) Method and system for calculating a space planning and generating design solutions assisted by artificial intelligence
CN102663830B (en) Data processing method of interior decoration model
US6816819B1 (en) Graphical method and system for modeling and estimating construction parameters
CN112883476B (en) Layout method and device of building space and electronic equipment
WO2008067191A2 (en) Systems, methods, and computer program products for home and landscape design
US20140222608A1 (en) Method and apparatus for estimating home remodeling costs
US8909501B2 (en) Method and apparatus for optimization of floor covering and system for user configuration and real time pricing information
CN105976434A (en) Interior decoration intelligent design method
CN110930178A (en) Decoration expense budget system based on household model
CN113850646A (en) Household article customized design cloud service platform
JP2003150655A (en) Building plan proposing system, proposing method for building plan and building plan proposing device
CN113869979B (en) Household article decoration and design scheme customization service platform
WO2007138560A2 (en) Design facilitation
CN117252654B (en) Engineering cost calculation system and method based on Revit model
JP2003044115A (en) Method and device for designing manufacture line, and process designing method
CN113850647A (en) Intelligent system for customizing household articles
CN110727974A (en) Data processing method and device, computer equipment and readable storage medium
KR20220006166A (en) User-centered Construction Electronic Bidding System and the methods toprovide services

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant