CN117200363A - Control method for AC/DC coordinated interaction micro-grid group - Google Patents
Control method for AC/DC coordinated interaction micro-grid group Download PDFInfo
- Publication number
- CN117200363A CN117200363A CN202311045113.9A CN202311045113A CN117200363A CN 117200363 A CN117200363 A CN 117200363A CN 202311045113 A CN202311045113 A CN 202311045113A CN 117200363 A CN117200363 A CN 117200363A
- Authority
- CN
- China
- Prior art keywords
- micro
- station
- grid
- area
- power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
技术领域Technical field
本发明涉及电力系统运行与控制领域,具体是一种交直流协调互动微电网群的控制方法。The invention relates to the field of power system operation and control, specifically a control method for AC and DC coordinated interactive microgrid groups.
背景技术Background technique
未来配电网将呈现出以下基础特征:分布式电源(DG)的规模化接入、储能系统的规模化接入、充电站和充电桩的大量建设应用、柔性交直流混联的逐步应用等。传统配电网是一种基于“电网(网)-负荷(荷)”的二元结构,简单来说就是电网供电和用户用电之间的单向的电力分配网络。伴随着未来配电网的新形态,传统配电网这种二元结构将逐渐过渡到“源-网-荷-储”的四元结构,也为微电网的发展提供了有力的基础。微电网依靠分布式新能源发电,能够独立组网运行,其电源是分散的,负荷也是分散的,以就地消纳电能为主。随着电力电子技的发展,多个微电网可依托柔性互联装置组成具备交直流协调互动功能的微电网群,实现分布式电源的最大化就地消纳,并对于大电网无法到达的地区,解决当地用户的灵活稳定用电问题。The future distribution network will show the following basic characteristics: large-scale access to distributed power sources (DG), large-scale access to energy storage systems, a large number of construction and application of charging stations and charging piles, and the gradual application of flexible AC and DC hybrid connections. wait. The traditional distribution network is a binary structure based on "grid (network) - load (load)". Simply put, it is a one-way power distribution network between the power supply of the grid and the power consumption of users. With the new form of distribution network in the future, the binary structure of traditional distribution network will gradually transition to the four-element structure of "source-grid-load-storage", which also provides a strong foundation for the development of microgrids. Microgrids rely on distributed new energy power generation and can operate independently. Their power sources are dispersed and their loads are also dispersed. They mainly consume electric energy locally. With the development of power electronics technology, multiple microgrids can rely on flexible interconnection devices to form a microgrid group with AC and DC coordination and interaction functions, maximizing on-site consumption of distributed power sources, and for areas that cannot be reached by large power grids. Solve the problem of flexible and stable electricity consumption for local users.
现阶段,源网荷储在微电网群的互动应用仍有几个问题亟需解决:At this stage, there are still several issues that need to be resolved in the interactive application of source-grid-load-storage in microgrid groups:
一是分布式电源的消纳能力仍需提高。投运的分布式电源系统在节假日等局部区域负载较低的情况下会抬升配电线路电压甚至超越警戒线。配电网缺乏灵活调节手段,只能粗暴的限制功率或切机,拉长了分布式电源的建设回收期,损害了用户的建设收益。First, the accommodation capacity of distributed power sources still needs to be improved. When the distributed power system is put into operation and the load in local areas is low, such as holidays, the voltage of the distribution line will rise or even exceed the warning line. The distribution network lacks flexible adjustment methods and can only roughly limit power or shut down machines, which lengthens the construction payback period of distributed power sources and damages users' construction benefits.
二是储能装置应用功能单一,储能系统各自独立运行,设备利用率仍需提高。已建设的储能装置大多只针对单一问题进行配置和应用,未有效满足用户电能质量提升、用电成本降低的需求,没有充分发挥储能装置优势。Second, the application function of energy storage devices is single, energy storage systems operate independently, and equipment utilization still needs to be improved. Most of the energy storage devices that have been built are only configured and applied for a single problem. They do not effectively meet the needs of users for improving power quality and reducing electricity costs, and do not give full play to the advantages of energy storage devices.
三是电动汽车等随机性负荷的有序化管理和控制仍需提高。电动汽车的快充时间越来越短,充电功率越来越大,规模化的充电站对电网的负荷波动影响越来越大。对区域配电网内的大量充电站进行系统层面的分析管理将可以有效改善用户充电行为对配电网的影响。Third, the orderly management and control of random loads such as electric vehicles still need to be improved. The fast charging time of electric vehicles is getting shorter and shorter, the charging power is getting larger and larger, and large-scale charging stations have an increasing impact on the load fluctuation of the power grid. System-level analysis and management of a large number of charging stations within the regional distribution network will effectively improve the impact of user charging behavior on the distribution network.
四是源网荷储间缺乏配电网层面的相互协调。现阶段源网荷储在微电网层面相互协调体现的较为充分,在配电网层面的相互协调互动还很弱,源荷储基本分别以各自的目标进行独立运行控制或与电网互动,还没有形成整体性的有效协调和配合,即源荷储灵活调控潜力并未被充分利用。Fourth, there is a lack of mutual coordination at the distribution network level between the source, grid, load and storage. At this stage, the mutual coordination between source, grid, load and storage is relatively sufficient at the microgrid level, but the mutual coordination and interaction at the distribution network level is still very weak. Source, load and storage basically carry out independent operation control or interact with the power grid according to their own goals. There is no To form an overall effective coordination and cooperation, that is, the potential of flexible regulation of source, load and reservoir has not been fully utilized.
综上所述,亟需发明一种适用于微电网群的控制方法,实现分布式能源的最大化消纳,充分发挥储能及电动汽车等柔性负荷的调控潜力,实现源网荷储协调控制效果最优。In summary, there is an urgent need to invent a control method suitable for microgrid groups to maximize the consumption of distributed energy, give full play to the regulation potential of flexible loads such as energy storage and electric vehicles, and achieve coordinated control of source, grid, load and storage. Best results.
发明内容Contents of the invention
针对现有源网荷储在微电网群的互动应用中存在的分布式能源消纳能力不足、柔性资源调控潜力缺乏充分挖掘、协调互动能力不足等问题,本发明提供一种交直流协调互动微电网群的控制方法。In order to solve the problems existing in the interactive application of source, grid, load and storage in microgrid groups, such as insufficient distributed energy consumption capacity, lack of full exploration of flexible resource regulation potential, and insufficient coordination and interaction capabilities, the present invention provides an AC-DC coordinated interactive micro-system. Control methods for power grid groups.
一种交直流协调互动微电网群的控制方法,应用于多个低压台区间进行柔性互联组成微电网群的场景,所述微电网群具备交直流协调互动功能,所述微电网群采用一体化三层协同控制架构和三层信息交互架构,在线控制模式、离线控制模式、计划检修模式和电网故障模式四种主要运行模式下采用不同的控制策略。A control method for an AC and DC coordinated interactive microgrid group, which is applied to a scenario where multiple low-voltage stations are flexibly interconnected to form a microgrid group. The microgrid group has an AC and DC coordinated and interactive function, and the microgrid group adopts an integrated Three-layer collaborative control architecture and three-layer information interaction architecture adopt different control strategies in four main operating modes: online control mode, offline control mode, planned maintenance mode and power grid failure mode.
进一步的,所述微电网群微由10kV中压交流线路中的多个低压台区组成,多个低压交流台区通过柔性互联装置在直流侧组成柔性互联,且各个台区均具备微电网自治能力;每个台区均配备有一个微电网控制器,向下对台区内的可调资源下发控制指令,并采集台区内资源信息,向上接收云主站下发的控制指令;所有台区的微网控制器与一个共同的云主站建立通讯,接受云主站的统一协调调配;台区内包含普通的交、直流负荷以及光、储、充柔性负荷。Further, the microgrid group consists of multiple low-voltage stations in the 10kV medium-voltage AC line. The multiple low-voltage AC stations form a flexible interconnection on the DC side through flexible interconnection devices, and each station has microgrid autonomy. Capability; Each station area is equipped with a microgrid controller, which sends control instructions downward to the adjustable resources in the station area, collects resource information in the station area, and receives control instructions issued by the cloud master station upwards; all The microgrid controller in the Taiwan area establishes communication with a common cloud master station and accepts the unified coordination and deployment of the cloud master station; the Taiwan area includes ordinary AC and DC loads as well as optical, storage and charging flexible loads.
进一步的,所述三层协同控制架构包括:设备级控制层、台区自治控制层、主站协调控制层;Further, the three-layer collaborative control architecture includes: equipment-level control layer, station area autonomous control layer, and master station coordination control layer;
其中设备级控制层包含:柔性互联装置及其直流输出端口连接的可调资源、台区内其它可调资源;The equipment-level control layer includes: adjustable resources connected to the flexible interconnection device and its DC output port, and other adjustable resources in the station area;
台区自制控制层由微电网控制器接收主站指令和控制模式或自治策略形成控制指令,下发到可调资源;The self-made control layer in the Taiwan area consists of the microgrid controller receiving the master station instructions and control mode or autonomous strategy to form control instructions and issuing them to adjustable resources;
主站协调控制层依托实时发用电数据,依托优化模型形成下发调控指令或接收台区的需求,按照需求形成控制指令下发。The master station coordination control layer relies on real-time power consumption data and optimization models to formulate and issue control instructions or receive the needs of the station area, and form and issue control instructions according to the needs.
进一步的,所述三层信息交互架构为云-边-端一体化三层信息交互架构;Further, the three-layer information interaction architecture is a cloud-edge-end integrated three-layer information interaction architecture;
其中,所述端包括:柔性互联装置、一二次标准接口柜、储能车,其中柔性互联装置负责采集本体基本信息及本台区内所连接的直流设备信息;一二次标准接口柜负责采集接入储能车信息及接入开关信息;Among them, the end includes: a flexible interconnection device, a primary and secondary standard interface cabinet, and an energy storage vehicle. The flexible interconnection device is responsible for collecting the basic information of the body and the DC equipment information connected in the station area; the primary and secondary standard interface cabinet is responsible for collecting Collect access energy storage vehicle information and access switch information;
所述边包括每个台区配置的微电网控制器,负责收集端设备信息,完成台区内自治协调控制功能,并将台区内所有端设备信息和状态传送给主站,同时接收主站的调控指令,形成下发控制指令;The side includes the microgrid controller configured in each station area, which is responsible for collecting end device information, completing the autonomous coordination control function in the station area, transmitting all end device information and status in the station area to the main station, and receiving the information from the main station at the same time. control instructions to form and issue control instructions;
所述云包括微电网群的云主站,云主站负责台区信息的监测和台区间的协调控制,给微电网控制器下发调控指令。The cloud includes a cloud master station of the microgrid group. The cloud master station is responsible for monitoring station area information and coordinating control between stations, and issuing regulatory instructions to the microgrid controller.
进一步的,所述在线控制模式定义为:电网正常运行,台区与云主站间通讯正常,可以进行正常的信息交互、控制指令下发、接收与执行,在云主站的统一协调调配下,实现各台区间的经济最优运行、分布式资源最大化消纳、供电质量优化治理功能。Further, the online control mode is defined as: the power grid is operating normally, the communication between the station area and the cloud master station is normal, normal information interaction, control instruction issuance, reception and execution can be carried out, under the unified coordination and deployment of the cloud master station , to realize the optimal economic operation of each station, the maximum consumption of distributed resources, and the optimization and management of power supply quality.
进一步的,所述离线控制模式定义为:电网正常运行,主站和微电网控制器间的通讯异常,主站15分钟内无法接收到微电网控制的信息,离线台区依靠本台区的微网控制器,完成台区内的微电网自治,实现本地光伏最大化消纳。Further, the offline control mode is defined as: the power grid is operating normally, the communication between the main station and the microgrid controller is abnormal, the main station cannot receive microgrid control information within 15 minutes, and the offline station area relies on the microgrid control of the station area. The network controller completes the microgrid autonomy in the Taiwan area and maximizes local photovoltaic consumption.
进一步的,所述计划检修模式定义为:主站对单个台区提前下达检修指令,其余操作由微电网控制器和就地接口柜完成,利用柔性互联装置转移功率,支撑起检修台区本地负荷的方式,实现台区的零停电检修。Further, the planned maintenance mode is defined as: the main station issues maintenance instructions to a single station area in advance, and the rest of the operations are completed by the microgrid controller and local interface cabinets, using flexible interconnection devices to transfer power to support the local load of the maintenance station area. way to achieve zero power outage maintenance in the Taiwan area.
进一步的,所述电网侧故障模式定义为:中压侧线路发生故障,云主站控制微网控制器及时切除故障区段内相关台区,并通过柔性互联装置完成功率互济,支撑起台区内负荷,实现被切除的台区最短时间停电。Furthermore, the grid-side fault mode is defined as: when the medium-voltage side line fails, the cloud master station controls the microgrid controller to promptly remove the relevant station area in the fault section, and completes power mutual assistance through the flexible interconnection device to support the station. load within the area to achieve the shortest possible power outage in the removed station area.
进一步的,所述控制策略的约定和约束为:Further, the conventions and constraints of the control strategy are:
1)当台区不需要外部支援时,按照台区自治运行,当需要外部支撑时,台区微电网控制器向主站发出请求,主站形成控制指令下发;1) When the Taiwan area does not need external support, it operates autonomously according to the Taiwan area. When external support is needed, the Taiwan microgrid controller sends a request to the main station, and the main station forms a control command and issues it;
2)台区自治运行包括以下运行模式:a)经济运行:台区线损优化;b)低碳运行:优先消纳台区清洁能源;c)供电质量优化:治理低电压、谐波等电能质量,提升供电质量水平;2) Autonomous operation in the Taiwan District includes the following operating modes: a) Economic operation: Line loss optimization in the Taiwan District; b) Low-carbon operation: Prioritize the consumption of clean energy in the Taiwan District; c) Power supply quality optimization: Control of low voltage, harmonics and other electric energy Quality, improve the quality level of power supply;
3)台区间功率互济包括:a)重载转供模式,实现某台区重载时,另一台区可以通过柔性互联转供互济;b)零停电检修模式,实现检修台区的零停电;c)跨台区低碳运行模式,实现光伏大发情况下,分布式光伏的跨台区消纳。3) Power mutual assistance between stations includes: a) heavy load transfer mode, which realizes that when one station area is heavily loaded, another station area can transfer power supply and mutual assistance through flexible interconnection; b) zero power outage maintenance mode, realizes the maintenance of station area Zero power outage; c) Cross-region low-carbon operation mode to realize the cross-region consumption of distributed photovoltaics under the situation of large-scale photovoltaic development.
进一步的,所述微电网群初始运行条件、指令发送及功率匹配原则为:Further, the initial operating conditions, command sending and power matching principles of the microgrid group are:
1)一次设备方面,台区交流、直流均并网,电力电子变压器为VF节点,其余为PQ节点;1) In terms of primary equipment, both AC and DC in the Taiwan area are connected to the grid, the power electronic transformer is the VF node, and the rest are PQ nodes;
2)二次设备方面,有n个微电网控制在线,其中1≤n≤5;2) In terms of secondary equipment, there are n microgrids controlled online, where 1≤n≤5;
3)主站下发各台区节点电压范围,各台区节点电压范围来源于潮流计算与状态估计结果、或电压合格率范围+7%~-10%、或人工设定范围;3) The master station issues the node voltage range of each station area. The node voltage range of each station area comes from the power flow calculation and state estimation results, or the voltage qualification rate range +7% to -10%, or the manually set range;
4)微电网控制器上送:15min上送本台区功率需求、交直流电源分级供给情况、负荷分级供给情况,其中交直流电源分级供给情况按照供给稳定性分级,在TTU中预定义,交流主网功率为1级、储能为2级、光伏为3级、V2G为4级,负荷分级供给情况按照负荷重要性分级,重要负荷为1级、一般负荷为2级、可中断负荷为3级;4) Microgrid controller uploads: 15 minutes to upload the power demand, AC and DC power supply situation, and load classification supply situation of the station area in 15 minutes. Among them, the AC and DC power supply situation is classified according to the supply stability, which is predefined in TTU. Main network power is level 1, energy storage is level 2, photovoltaic is level 3, and V2G is level 4. The load classification supply situation is graded according to load importance, with important load being level 1, general load being level 2, and interruptible load being level 3. class;
5)台区间功率匹配的原则为:优先单个台区满足、优先选对侧10kV线路台区、优先电源-负荷稳定性满足;5) The principles of power matching between stations are: priority for a single station area, priority for the opposite 10kV line station area, and priority for power supply-load stability;
6)主站对功率匹配执行的方式为:下发至A台区TTU,A台区向直流母线发出某kW功率;下发至B台区TTU,B台区从直流母线吸收某kW功率;由参与匹配的各台区TTU控制柔性互联装置执行;6) The main station performs power matching in the following manner: it is sent to the TTU of station A, and station A sends a certain kW power to the DC bus; it is sent to the TTU of station B, and station B absorbs a certain kW power from the DC bus; The flexible interconnection device is controlled by the TTU of each station participating in the matching;
7)主站对台区控制模式的切换:在线、离线控制模式;7) The master station switches the control mode of the station area: online and offline control mode;
8)针对柔性互联装置故障,预制一个VF节点切换顺序的表,并在电力电子变压器上送故障时,按照顺序切换在线的柔性互联装置。8) In response to the failure of the flexible interconnection device, pre-make a table of the VF node switching sequence, and when the power electronic transformer fails, switch the online flexible interconnection device in sequence.
本发明主要应用于具备交直流协调互动功能的微电网群,基于云-边-端一体化三层协同控制架构,实现包括在线控制模式、离线控制模式、计划检修模式和电网故障模式四种主要运行模式下的微电网群控制;实现了设备级控制层、台区自治控制层、主站协调控制层的策略最优化分解,实现了不依赖就地侧横向通信的分层协同调控,充分挖掘了柔性资源调控潜能,提升了分布式资源消纳能力与源网荷储协同互动能力,具有规模可拓展性强、功能可复用性好的推广优势。This invention is mainly applied to microgrid groups with AC and DC coordination and interaction functions. Based on the three-layer collaborative control architecture of cloud-edge-end integration, it realizes four main modes including online control mode, offline control mode, planned maintenance mode and power grid failure mode. Microgrid group control in operation mode; realizes the optimal decomposition of strategies at the equipment level control layer, station area autonomous control layer, and master station coordination control layer, realizes hierarchical collaborative regulation that does not rely on local side lateral communication, and fully exploits It improves the potential of flexible resource regulation, improves distributed resource consumption capabilities and source network load storage collaborative interaction capabilities, and has the promotion advantages of strong scale scalability and good function reusability.
附图说明Description of the drawings
图1为本发明实施例云-边-端一体化三层信息交互架构图;Figure 1 is a three-layer information interaction architecture diagram of cloud-edge-device integration according to the embodiment of the present invention;
图2为某地交直流协调互动微电网群示范工程整体拓扑图;Figure 2 is the overall topology diagram of the AC-DC coordinated interactive microgrid group demonstration project in a certain place;
图3为在线控制模式控制策略流程图;Figure 3 is the control strategy flow chart of online control mode;
图4为离线控制模式控制策略流程图;Figure 4 is a flow chart of the offline control mode control strategy;
图5为本发明实施例以T5台区为例的计划检修模式控制策略流程图;Figure 5 is a flow chart of the planned maintenance mode control strategy taking the T5 station area as an example according to the embodiment of the present invention;
图6为本发明实施例以T5台区为例的电网侧故障模式控制策略流程图;Figure 6 is a flow chart of the grid-side fault mode control strategy taking the T5 station area as an example according to the embodiment of the present invention;
图7为T5台区仿真验证结果图;Figure 7 shows the simulation verification results of T5 station area;
图8为T4台区仿真验证结果图。Figure 8 shows the simulation verification results of the T4 station area.
具体实施方式Detailed ways
为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本发明保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments These are some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without any creative work fall within the scope of protection of the present invention.
本发明以某处交直流协调互动微电网群示范工程为实施例进行说明。The present invention is explained by taking a certain AC-DC coordinated interactive microgrid group demonstration project as an example.
该微电网群在5个台区低压侧建设柔性低压直流互联装置,同时部署1台有载调容调压变压器替代现有台变,1台电力电子变压器,并以柔性低压直流互联装置为核心,建设一定规模的直流配电台区,打造切换灵活、功率互济的有源配电网。具体拓扑结构如图2所示。T4和T5台区分别从10kV柳611线路的第122#和124#杆塔引出,T1、T2、T3及非互联台区从10kV东14线路的74#杆塔引出,4个台区通过一个分支开关相连。T1、T2、T3台区通过环网柜相连。10kV柳611线路的第124#杆塔与10kV东14线路的74#杆塔通过联络开关连接。T1、T2、T3、T4、T5台区通过一条直流母线组成柔性互联。每个台区的光伏、储能、充电桩、柔性互联装置的配置详见图2,其中储能车通过一二次标准接口柜接入。该微电网群采用三层协同控制架构,包括设备级控制层、台区自治控制层、主站协调控制层;该微电网群采用三层信息交互架构,为云-边-端一体化三层信息交互架构,如图1所示。This microgrid group builds flexible low-voltage DC interconnection devices on the low-voltage side of five Taiwan areas. It also deploys an on-load capacity-adjusting and voltage-regulating transformer to replace the existing transformer and a power electronics transformer, with the flexible low-voltage DC interconnection device as the core. , build a DC distribution station area of a certain scale and create an active distribution network with flexible switching and mutual power support. The specific topology is shown in Figure 2. The T4 and T5 station areas are led from the 122# and 124# towers of the 10kV Liu 611 line respectively. The T1, T2, T3 and non-interconnected station areas are led from the 74# tower of the 10kV East 14 line. The 4 station areas pass a branch switch connected. T1, T2, and T3 stations are connected through ring main units. The No. 124 tower of the 10kV Liu 611 line is connected to the No. 74 tower of the 10kV East 14 line through a contact switch. T1, T2, T3, T4, and T5 stations form a flexible interconnection through a DC bus. The configuration of photovoltaics, energy storage, charging piles, and flexible interconnection devices in each station area is detailed in Figure 2. The energy storage vehicles are connected through primary and secondary standard interface cabinets. The microgrid group adopts a three-layer collaborative control architecture, including a device-level control layer, a station autonomous control layer, and a master station coordination control layer. The microgrid group adopts a three-layer information interaction architecture, which is a three-layer cloud-edge-end integration. Information interaction architecture is shown in Figure 1.
下面将详细介绍本实施例中各类控制模式的控制策略。The control strategies of various control modes in this embodiment will be introduced in detail below.
1、在线控制模式1. Online control mode
步骤1:主站首先下发各个台区正常运行时的电压范围指令。Step 1: The master station first issues the voltage range instructions for each station area during normal operation.
步骤2:各台区微电网控制器计算台区内光伏输出功率、储能、充电桩以及负荷功率。Step 2: The microgrid controller of each station calculates the photovoltaic output power, energy storage, charging pile and load power in the station.
判断1:判断台区电压是否越限,若是则进入步骤3,若否则进入判断3。Judgment 1: Determine whether the voltage in the station area exceeds the limit. If so, go to step 3. If not, go to judgment 3.
步骤3:微网控制器计算该台区无功功率补充或谐波补充指令值.Step 3: The microgrid controller calculates the reactive power supplement or harmonic supplement command value of the station area.
判断2:导线上连接的柔性互联装置及其它可调变流器是否有多余容量,若否则举手向主站求助转移功率,柔性互联装置释放容量,参与节点电压调节,若是则进入步骤4。Judgment 2: Whether the flexible interconnection device and other adjustable converters connected to the wire have excess capacity. If not, raise your hand and ask the main station for help to transfer power. The flexible interconnection device releases capacity and participates in node voltage regulation. If so, proceed to step 4.
步骤4:微电网控制器下发无功功率补偿或谐波补偿指令值。Step 4: The microgrid controller issues reactive power compensation or harmonic compensation command values.
判断3:判断光伏出力Ppv是否大于负载负荷需求Pload,若是则进入判断4,否则进入判断9。Judgment 3: Determine whether the photovoltaic output Ppv is greater than the load demand Pload. If so, enter judgment 4, otherwise enter judgment 9.
判断4:判断储能是否具备充电条件,若是则储能充电,否则进入步骤5.Judgment 4: Determine whether the energy storage meets the charging conditions. If so, charge the energy storage, otherwise go to step 5.
步骤5:微网控制器举手告知云主站需要主动转移功率,云主站寻找功率缺额台区,下一步进入判断5.Step 5: The microgrid controller raises his hand to inform the cloud master station that it needs to actively transfer power. The cloud master station looks for the power shortage station area. The next step is to enter judgment 5.
判断5:判断非同10kV供电台区是否有功率缺额,若是则进入判断6,否则进入判断7。Judgment 5: Determine whether there is a power shortage in the non-identical 10kV power supply station area. If so, go to Judgment 6, otherwise go to Judgment 7.
判断6:判断是否具备转供条件,若是则云主站下发被转供指令给被转供台区微网控制器,微网控制器控制柔性互联装置接收功率,完成重载转供。若否则进入判断7。Judgment 6: Determine whether the transfer conditions are met. If so, the cloud master station issues a transferred instruction to the microgrid controller of the transferred station. The microgrid controller controls the received power of the flexible interconnection device to complete the overload transfer. If not, go to judgment 7.
判断7:同10kV供电台区是否有功率缺额,是则进入判断8,否则无法完成重载转供。Judgment 7: Check whether there is a power shortage in the same 10kV power supply station area. If so, enter Judgment 8, otherwise the overload transfer cannot be completed.
判断8:判断是否具备转供条件,是则云主站下发被转供指令给被转供台区微网控制器,微网控制器控制柔性互联装置接收功率,完成重载转供。若否则无法完成重载转供。Judgment 8: Determine whether the transfer conditions are met. If so, the cloud master station issues the transferred instruction to the microgrid controller of the transferred station. The microgrid controller controls the received power of the flexible interconnection device to complete the overload transfer. Otherwise, the reload transfer cannot be completed.
判断9:储能是否具备放电条件?若是则储能放电、充电桩停止充电。若否则进入步骤6。Judgment 9: Does the energy storage meet the conditions for discharge? If so, the energy storage is discharged and the charging pile stops charging. If not, go to step 6.
步骤6:微网控制器举手告知云主站请求其它台区功率互济,云主站寻找功率盈余台区。下一步进入判断10。Step 6: The microgrid controller raises its hand to inform the cloud master station to request power mutual assistance from other stations, and the cloud master station looks for power surplus stations. The next step is to enter judgment 10.
判断10:判断非同10kV供电台区是否有功率盈余,若是则进入判断11,否则进入判断12。Judgment 10: Determine whether there is power surplus in the non-identical 10kV power supply station area. If so, enter judgment 11, otherwise enter judgment 12.
判断11:判断是否具备转供条件。若是则云主站下发转出功率指令给功率转出台区微网控制器,微网控制器控制柔性互联装置转出功率,完成重载转供。若否则进入判断12。Judgment 11: Determine whether the conditions for transfer are met. If so, the cloud master station issues a power transfer instruction to the power transfer area microgrid controller, and the microgrid controller controls the flexible interconnection device to transfer power to complete heavy load transfer. If not, go to judgment 12.
判断12:判断同10kV供电台区是否有功率盈余,若是则进入判断13,否则无法完成重载转供。Judgment 12: Determine whether there is power surplus in the same 10kV power supply station area. If so, proceed to Judgment 13, otherwise the overload transfer cannot be completed.
判断13:判断是否具备转供条件。若是则云主站下发转出功率指令给功率转出台区微网控制器,微网控制器控制柔性互联装置转出功率,完成重载转供。若否则无法完成重载转供。Judgment 13: Determine whether the conditions for transfer are met. If so, the cloud master station issues a power transfer instruction to the power transfer area microgrid controller, and the microgrid controller controls the flexible interconnection device to transfer power to complete heavy load transfer. Otherwise, the reload transfer cannot be completed.
具体控制策略逻辑图见图3。The specific control strategy logic diagram is shown in Figure 3.
2、离线控制模式2. Offline control mode
以T5台区为例Take T5 Taiwan District as an example
步骤1:T5台区微网控制器计算光伏输出功率和负荷功率。下一步进入判断1。Step 1: The T5 microgrid controller calculates the photovoltaic output power and load power. The next step is to enter judgment 1.
判断1:判断台区光伏出力是否为0,若是则光伏不出力,下一步进入判断4,否则进入判断2。Judgment 1: Determine whether the photovoltaic output in the Taiwan area is 0. If so, the photovoltaic output will not be output. The next step will be judgment 4. Otherwise, judgment 2 will be entered.
判断2:判断光伏出力是否大于负荷功率需求。若是则进入步骤2;若否则进入判断4。Judgment 2: Determine whether the photovoltaic output is greater than the load power demand. If yes, go to step 2; if not, go to judgment 4.
步骤2:光伏出力至T5台区,并引导充电车充电。下一步进入判断3。Step 2: The photovoltaic output is sent to the T5 station area and the charging vehicle is guided to charge. The next step is to enter judgment 3.
判断3:判断储能是否充满电。若是则光伏对储能充电;若否则光伏反向送电至10kV电网,待通讯正常后,微电网控制器举手向主站发出功率输出请求。Judgment 3: Determine whether the energy storage is fully charged. If it is, the photovoltaic will charge the energy storage; if not, the photovoltaic will send power to the 10kV power grid in reverse direction. After the communication is normal, the microgrid controller will raise its hand and send a power output request to the main station.
判断4:判断储能是否放电。若是则进入判断5;若否则储能停止放电。Judgment 4: Determine whether the energy storage is discharged. If so, enter judgment 5; if not, the energy storage stops discharging.
判断5:判断储能支撑负荷的电压是否合格。若是则进入判断6,若否则进入储能停止放电。Judgment 5: Determine whether the voltage of the energy storage supporting the load is qualified. If so, enter judgment 6, if not, enter energy storage and stop discharging.
判断6:判断储能支撑负荷的频率是否合格。若是则储能放电至5号台区,否则储能停止放电。Judgment 6: Determine whether the frequency of energy storage supporting load is qualified. If so, the energy storage is discharged to station area 5, otherwise the energy storage stops discharging.
具体控制策略逻辑图见图4。The specific control strategy logic diagram is shown in Figure 4.
3、计划检修模式3. Planned maintenance mode
1)以T5台区检修为例1) Take the maintenance of T5 station area as an example
步骤1:主站提前下发计划检修指令。Step 1: The master station issues planned maintenance instructions in advance.
步骤2:T5台区微网控制器计算台区内光伏功率Ppv5及充电桩功率Pv2g5及直流负载功率Pload5,并将计算结果上报给主站。下一步进入判断1。Step 2: The T5 station area microgrid controller calculates the photovoltaic power Ppv5, charging pile power Pv2g5 and DC load power Pload5 in the station area, and reports the calculation results to the main station. The next step is to enter judgment 1.
判断1:判断Ppv5是否大于Pv2g5+Pload5?若否则进入步骤3,若是则进入步骤6。Judgment 1: Determine whether Ppv5 is greater than Pv2g5+Pload5? If not, go to step 3, if so, go to step 6.
步骤3:T5台区微网控制器向主站请求台区功率互济。Step 3: The T5 station area microgrid controller requests the station area power mutual assistance from the main station.
步骤4:T5台区微网控制器计算出本台区功率缺额Pc5=Ppv5-Pv2g5-Pload5并上报给主站。Step 4: The microgrid controller of T5 station area calculates the power deficit Pc5=Ppv5-Pv2g5-Pload5 of this station area and reports it to the main station.
步骤5:主站下发指令给参与功能互济的台区微网控制器,利用柔性互联装置转移Pc5功率给其它台区。下一步进入步骤8。Step 5: The master station issues instructions to the microgrid controllers of the stations participating in the mutual assistance of functions, and uses the flexible interconnection device to transfer PC5 power to other stations. Next go to step 8.
步骤6:T5台区微网控制器控制台区内光伏主动支撑台区内直流负载及充电桩,下一步进入判断2。Step 6: The photovoltaics in the control area of the microgrid controller in the T5 station area actively support the DC loads and charging piles in the station area. The next step is to enter judgment 2.
判断2:判断储能能否充电?若是则储能充电,若否则进入步骤7。Judgment 2: Determine whether the energy storage can be charged? If so, store energy and charge, if not, go to step 7.
步骤7:T5台区微网控制器举手向云主站请求支援,将T5台区内冗余光伏转移至其它台区。Step 7: The microgrid controller of the T5 station area raises its hand to request support from the cloud master station to transfer the redundant PV in the T5 station area to other station areas.
步骤8:T5台区微网控制器监测变压器进线侧电流Iac5,下一步进入判断3。Step 8: The T5 microgrid controller monitors the transformer incoming side current Iac5, and the next step is to enter judgment 3.
判断3:判断Iac5是否小于可开断值I0。若是则进入步骤9,否则进入步骤8。Judgment 3: Determine whether Iac5 is less than the breakable value I0. If yes, go to step 9, otherwise go to step 8.
步骤9:微网控制器下发模式切换指令给柔性互联装置,柔性互联装置切换为V/F控制模式。Step 9: The microgrid controller issues a mode switching instruction to the flexible interconnection device, and the flexible interconnection device switches to the V/F control mode.
步骤10:微网控制器发断开变压器出线开关指令给一二次接口柜,一二次接口柜控制断开变压器出线开关。Step 10: The microgrid controller sends a command to disconnect the transformer outlet switch to the primary and secondary interface cabinets, and the primary and secondary interface cabinet controls to disconnect the transformer outlet switch.
步骤11:进入计划检修。下一步进入判断4。Step 11: Enter planned maintenance. The next step is to enter judgment 4.
判断4:判断检修是否完成。若是则进入步骤12;若否则进入步骤11。Judgment 4: Determine whether the maintenance is completed. If yes, go to step 12; if not, go to step 11.
步骤12:微网控制器向主站发送请求告知已经检修完成。Step 12: The microgrid controller sends a request to the main station to inform that the maintenance has been completed.
步骤13:主站下发恢复为正常状态指令至微网控制器,微网控制器发合闸变压器出线开关指令给一二次接口,一二次接口转发指令检同期合闸变压器出线开关。Step 13: The master station issues a command to restore the normal state to the microgrid controller. The microgrid controller sends a command to close the transformer outlet switch to the primary and secondary interfaces. The primary and secondary interfaces forward the command to check the synchronous closing transformer outlet switch.
步骤14:低压柔性互联装置切换为P/Q模式,并恢复为主站控制状态。检修结束,系统恢复。Step 14: The low-voltage flexible interconnection device switches to P/Q mode and returns to the main station control state. The maintenance is completed and the system is restored.
具体控制策略逻辑图见图5。The specific control strategy logic diagram is shown in Figure 5.
T4及其它台区检修均与T5台区控制策略类似(如图6所示),遵循的原则均为由其它台区支撑其本地负荷功率,再断开交流侧供电,实现零停电检修,此处不再赘述,但控制策略均为该专利保护范围。The maintenance of T4 and other station areas is similar to the control strategy of T5 station area (as shown in Figure 6). The principle followed is that other station areas support their local load power, and then disconnect the AC side power supply to achieve zero power outage maintenance. This No further details will be given here, but the control strategies are within the scope of patent protection.
4、电网侧故障模式4. Grid side failure mode
以T5台区交流10kV侧故障为例Take the AC 10kV side fault in T5 Taiwan area as an example
步骤1:电网中压侧发生相间短路故障,T5台区光伏防孤岛保护动作,立即断开光伏交流并网开关。Step 1: A phase-to-phase short circuit fault occurs on the medium-voltage side of the power grid. The photovoltaic anti-islanding protection in the T5 station area is activated and the photovoltaic AC grid connection switch is immediately disconnected.
步骤2:柔性互联装置有功调节指令置零。Step 2: Set the active power adjustment command of the flexible interconnection device to zero.
步骤3:T5台区微网控制器通过一二次标准接口柜断开本台区变压器低压侧断路器及直流母线开关。Step 3: The T5 station microgrid controller disconnects the low-voltage side circuit breaker and DC bus switch of the transformer in this station through the primary and secondary standard interface cabinet.
步骤4:T5台区微网控制器通过一二次标准接口柜切换储能车进入V/F工作模式,支撑台区电压,并放电支撑台区内交流负荷。Step 4: The T5 station area microgrid controller switches the energy storage vehicle into the V/F working mode through the primary and secondary standard interface cabinets, supports the station area voltage, and discharges to support the AC load in the station area.
步骤5:T5台区微网控制器控制光伏交流并网开关合闸并网,光伏参与支撑该台区负荷。Step 5: The microgrid controller of the T5 station controls the photovoltaic AC grid-connected switch to close and connect to the grid, and the photovoltaic participates in supporting the load of the station.
判断1:判断储能车出力+光伏出力是否大于台区负荷。若是则进入步骤9,否则进入步骤6.。Judgment 1: Determine whether the energy storage vehicle output + photovoltaic output is greater than the station load. If so, go to step 9, otherwise go to step 6.
步骤6:T5台区微网控制器控制柔性互联装置切换为V/F模式,同时闭合直流母线开关,并向主站请求功率互济。云主站寻找功率盈余台区。下一步进入判断2。Step 6: The T5 microgrid controller controls the flexible interconnection device to switch to V/F mode, closes the DC bus switch at the same time, and requests power mutual assistance from the master station. The cloud master station looks for power surplus station areas. The next step is to enter judgment 2.
判断2:非同10kV供电台区是否有功率盈余。若是则进入判断3,否则进入判断4。Judgment 2: Whether there is power surplus in the non-identical 10kV power supply station area. If so, go to judgment 3, otherwise go to judgment 4.
判断3:判断是否具备转供条件,若是则云主站下发转出功率指令给功率转出台区微网控制器,微网控制器控制柔性互联装置转出功率,并进入步骤7。若否则进入判断4。Judgment 3: Determine whether the transfer conditions are met. If so, the cloud master station issues a transfer power instruction to the power transfer area microgrid controller. The microgrid controller controls the flexible interconnection device to transfer power and enters step 7. If not, go to judgment 4.
判断4:同10kV供电台区是否有功率盈余。若是则进入判断5,否则无法完成功率互济。Judgment 4: Whether there is power surplus in the same 10kV power supply station area. If so, enter judgment 5, otherwise power mutual assistance cannot be completed.
判断5:判断是否具备转供条件。若是则云主站下发转出功率指令给功率转出台区微网控制器,微网控制器控制柔性互联装置转出功率,并进入步骤7。若否则无法完成功率互济。Judgment 5: Determine whether the conditions for transfer are met. If so, the cloud master station issues a power transfer instruction to the power transfer area microgrid controller, and the microgrid controller controls the flexible interconnection device to transfer power, and enters step 7. Otherwise, power mutual aid cannot be completed.
步骤7:等待电网故障清除。Step 7: Wait for the grid fault to clear.
判断6:判断电网故障是否清除。若是则进入步骤8,否则进入步骤7。Judgment 6: Determine whether the power grid fault has been cleared. If yes, go to step 8, otherwise go to step 7.
步骤8:T5台区微网控制器控制低压柔性互联装置切换为P/Q模式,T5台区微网控制器通过一二次标准接口柜检同期合闸本台区变压器低压出线断路器,故障恢复完成。Step 8: The T5 station area microgrid controller controls the low-voltage flexible interconnection device to switch to P/Q mode. The T5 station area microgrid controller passes the first and second standard interface cabinet inspection and closes the low-voltage outlet circuit breaker of the station area transformer at the same time. Failure Recovery complete.
步骤9:T5台区微网控制器控制柔性互联装置切换为V/F模式,向云主站举手示意,申请转出光伏盈余功率,同时闭合直流母线开关。云主站寻找功率缺额台区。下一步进入判断7。Step 9: The T5 microgrid controller controls the flexible interconnection device to switch to V/F mode, raises hands to the cloud master station, applies to transfer the photovoltaic surplus power, and closes the DC bus switch at the same time. The cloud master station looks for power shortage stations. The next step is to enter judgment 7.
判断7:判断非同10kV供电台区是否有功率缺额?若是则进入判断8,否则进入判断9。Judgment 7: Determine whether there is a power shortage in the non-identical 10kV power supply station area? If so, go to judgment 8, otherwise go to judgment 9.
判断8:是否具备转供条件。若是则进入步骤10,否则进入判断9。Judgment 8: Whether the conditions for transfer are met. If yes, go to step 10, otherwise go to judgment 9.
判断9:判断同10kV供电台区是否有功率缺额?若是则进入判断10,否则无法完成光伏盈余功率转供。Judgment 9: Determine whether there is a power shortage in the same 10kV power supply station area? If so, proceed to judgment 10, otherwise the photovoltaic surplus power transfer cannot be completed.
判断10:判断是否具备转供条件。若是则进入步骤10;否则无法完成光伏盈余功率转供。Judgment 10: Determine whether the conditions for transfer are met. If so, proceed to step 10; otherwise, the photovoltaic surplus power transfer cannot be completed.
步骤10:云主站下发被转供指令给被转供台区微网控制器,微网控制器控制柔性互联装置完成T5台区光伏盈余功率转供。恢复完成。具体控制策略逻辑图见图6。Step 10: The cloud master station issues the transferred instruction to the microgrid controller of the transferred station area, and the microgrid controller controls the flexible interconnection device to complete the transfer of photovoltaic surplus power in the T5 station area. Recovery complete. The specific control strategy logic diagram is shown in Figure 6.
仿真验证Simulation
为有效验证具体实施效果,依照具体实施方式中的包含具备交直流协调互动微电网的中低压有源配电网,依托RT-LAB实时仿真系统,构建离散化仿真模型,全面验证故障和检修两种场景下的控制策略。In order to effectively verify the specific implementation effect, according to the specific implementation method, a medium and low-voltage active distribution network with AC and DC coordinated interactive microgrids is relied on, relying on the RT-LAB real-time simulation system, to build a discrete simulation model to comprehensively verify both fault and maintenance. control strategy in this scenario.
(1)电网故障模式(1)Power grid failure mode
仿真中台区T4、T5的10kV电网故障发生在0.438s,该场景下,当台区T4、台区T5的电网侧出现故障时,电网侧开关断开,进入离网运行,台区T4柔性互联装置由恒功率模式转为交流电压模式供给台区内交流负荷,台区T4电力电子变压器停止运行。台区T1由恒功率模式转为恒电压模式控制总直流母线电压维持在稳定的750V,台区T4、T5的直流负荷均由总直流母线提供功率。台区T2、T3仍运行在恒功率模式。In the simulation, the 10kV power grid fault of Taiwan District T4 and T5 occurred at 0.438s. In this scenario, when the grid side of Taiwan District T4 and Taiwan District T5 failed, the switch on the grid side was disconnected and entered off-grid operation. The flexibility of Taiwan District T4 The interconnection device changed from constant power mode to AC voltage mode to supply AC loads in the Taiwan area, and the T4 power electronic transformer in the Taiwan area stopped operating. The station area T1 changes from constant power mode to constant voltage mode to control the total DC bus voltage to maintain a stable 750V. The DC loads of station areas T4 and T5 are all powered by the main DC bus. Station area T2 and T3 are still running in constant power mode.
在台区T4、T5电网故障恢复后,台区T4电力电子变压器恢复运行,台区T1柔性互联装置由恒电压模式转换为恒交流功率模式,台区T5由交流电压模式转换为恒功率模式,跟踪电网电压,控制其交流输出电压与电网电压幅值、频率、相位一致后闭合台区交流侧开关,台区T5由离网转并网整体系统将恢复正常运行。仿真中10kV电网故障恢复于0.76s,台区T5准备并网,0.789s台区T5柔性互联装置完成离并网转换。仿真结果以台区T5的相关波形进行展示,具体见图7所示,与预期结果相符,证明了实施方式的正确性。After the power grid faults in Taiwan District T4 and T5 were restored, the power electronic transformer in Taiwan District T4 resumed operation, the flexible interconnection device in Taiwan District T1 was converted from constant voltage mode to constant AC power mode, and Taiwan District T5 was converted from AC voltage mode to constant power mode. Track the grid voltage, control its AC output voltage to be consistent with the grid voltage amplitude, frequency, and phase, and then close the AC side switch of the station area. The overall system of T5 in the station area will switch from off-grid to grid-connected and the overall system will resume normal operation. In the simulation, the 10kV power grid fault recovered at 0.76s, the station area T5 was ready to connect to the grid, and the station area T5 flexible interconnection device completed the off-grid connection transition at 0.789s. The simulation results are displayed with the relevant waveforms of station area T5, as shown in Figure 7. They are consistent with the expected results, proving the correctness of the implementation method.
(2)检修模式(2) Maintenance mode
仿真中,于0.832s由主站下发检修控制指令,台区T4电力电子变压器停止运行,其余台区各柔性互联装置自主控制其功率流动大小和方向,使各自电网侧功率及电流逐渐降低至0,在电网侧端口功率满足要求后,分别断开电网侧开关,并且由恒交流功率模式转换为交流电压模式进入离网状态,此时各个台区的直流母线由储能或者光伏进行支撑。In the simulation, the main station issued a maintenance control command at 0.832s, and the T4 power electronic transformer in the Taiwan area stopped running. The flexible interconnection devices in the other Taiwan areas independently controlled the magnitude and direction of their power flow, so that the power and current on their respective grid sides gradually reduced to 0. After the grid-side port power meets the requirements, the grid-side switches are turned off respectively, and the constant AC power mode is converted to the AC voltage mode to enter the off-grid state. At this time, the DC bus of each station area is supported by energy storage or photovoltaics.
仿真中,于0.957s检修结束,当电网检修完成后,主站下发控制命令,台区T4电力电子变压器投入运行,支撑总直流母线电压,所有柔性互联装置跟踪电网电压,控制其电网侧输出电压与电网电压同步后,分别闭合其电网侧开关,且由交流电压模式转换为恒功率模式,转入并网运行,系统恢复正常运行。仿真结果以台区T4的相关波形进行展示,具体见附图8所示,与预期结果相符,证明了实施方式的正确性。In the simulation, the maintenance ended at 0.957s. When the power grid maintenance was completed, the master station issued a control command, and the Taiwan District T4 power electronic transformer was put into operation to support the total DC bus voltage. All flexible interconnection devices tracked the grid voltage and controlled its grid-side output. After the voltage is synchronized with the grid voltage, the grid-side switches are closed respectively, and the AC voltage mode is converted to the constant power mode, and then transferred to grid-connected operation, and the system returns to normal operation. The simulation results are displayed with the relevant waveforms of station area T4, as shown in Figure 8. They are consistent with the expected results, proving the correctness of the implementation method.
本发明具有以下优势:The invention has the following advantages:
1、本发明实现了设备级控制层、台区自治控制层、主站协调控制层的策略最优化分解,实现了不依赖就地侧横向通信的分层协同调控,充分挖掘了柔性资源调控潜能,提升了分布式资源消纳能力与源网荷储协同互动能力。1. The present invention realizes the policy optimization and decomposition of the equipment level control layer, the station autonomous control layer, and the master station coordination control layer, realizes hierarchical collaborative regulation that does not rely on local side lateral communication, and fully taps the potential of flexible resource regulation. , which improves distributed resource consumption capabilities and source network load storage collaborative interaction capabilities.
2、基于上述实施例分析可得,本发明的控制方法具有普适性和合理性,可在具备交直流协调互动功能的微电网群中进行应用,具有规模可拓展性强、功能可复用性好的推广优势。2. Based on the analysis of the above embodiments, it can be concluded that the control method of the present invention is universal and rational, can be applied in microgrid groups with AC and DC coordination and interaction functions, has strong scalability and reusable functions. Good promotion advantages.
以上所述,仅为本发明的具体实施方式,但本发明的保护范围并不局限于此,任何属于本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到的变化或替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应该以权利要求的保护范围为准。The above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed in the present invention. All are covered by the protection scope of the present invention. Therefore, the protection scope of the present invention should be subject to the protection scope of the claims.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202311045113.9A CN117200363A (en) | 2023-08-17 | 2023-08-17 | Control method for AC/DC coordinated interaction micro-grid group |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202311045113.9A CN117200363A (en) | 2023-08-17 | 2023-08-17 | Control method for AC/DC coordinated interaction micro-grid group |
Publications (1)
Publication Number | Publication Date |
---|---|
CN117200363A true CN117200363A (en) | 2023-12-08 |
Family
ID=89002548
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202311045113.9A Pending CN117200363A (en) | 2023-08-17 | 2023-08-17 | Control method for AC/DC coordinated interaction micro-grid group |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN117200363A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117762043A (en) * | 2024-02-22 | 2024-03-26 | 国网上海能源互联网研究院有限公司 | A flexible-direct interconnection hardware-in-the-loop simulation system and testing method |
-
2023
- 2023-08-17 CN CN202311045113.9A patent/CN117200363A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117762043A (en) * | 2024-02-22 | 2024-03-26 | 国网上海能源互联网研究院有限公司 | A flexible-direct interconnection hardware-in-the-loop simulation system and testing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102931653B (en) | Comprehensive coordination control method of wind-solar direct current micro-grid | |
CN104281977B (en) | A kind of mixed type micro-capacitance sensor application platform and its control method | |
CN102510089B (en) | Wind-solar storage micro-grid system | |
CN205429725U (en) | Many generating lines residential block power supply system based on little electric wire netting of direct current | |
CN106505603B (en) | A Hierarchical Energy Storage Microgrid Containing Multiple Energy Storage Units | |
CN105811458A (en) | Microgrid energy storage system and energy management method thereof | |
CN207753466U (en) | A kind of Ac/dc Power Systems based on dual redundant electric power electric transformer | |
CN110601248A (en) | Multi-mode coordination control method of annular alternating current-direct current hybrid micro-grid system | |
CN104269847B (en) | A kind of flexible ring network control system runs and tide optimization method | |
CN204168208U (en) | A kind of photovoltaic micro networking | |
CN105262135A (en) | Wind, light and diesel storage microgrid system containing composite energy storage and coordinated control method during grid connection | |
CN103683272A (en) | Independent direct-current micro-grid system and energy balance control method thereof | |
CN112117767A (en) | Power supply and distribution system based on multi-station integration | |
Kumar et al. | A review on microgrids with distributed energy resources | |
CN108879728A (en) | A kind of multi-source micro-capacitance sensor frequency control method for coordinating | |
CN107681700B (en) | Method for converting operation modes of alternating current-direct current hybrid micro-grid | |
CN209913508U (en) | Micro-grid layered coordination control device | |
CN109842139A (en) | A kind of micro-capacitance sensor Expansion Planning method containing mobile energy storage | |
CN112072697A (en) | Modular direct-current microgrid structure reconstruction method and operation control method | |
CN111293777A (en) | Uninterrupted power supply system and method for multi-station fusion in power operation | |
CN103280844A (en) | Alternating/direct current hybrid multi-level micro grid system | |
CN114465267A (en) | A charging station system with an integrated energy router for light storage and charging | |
CN117200363A (en) | Control method for AC/DC coordinated interaction micro-grid group | |
CN110718933B (en) | A multi-level coordinated power balance control strategy for wind-storage isolated grid system | |
Sayed et al. | Supervisory control of a resilient DC microgrid for commercial buildings |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |