CN117094674A - Resource management method, device and system for vehicle project and computing equipment - Google Patents

Resource management method, device and system for vehicle project and computing equipment Download PDF

Info

Publication number
CN117094674A
CN117094674A CN202311029629.4A CN202311029629A CN117094674A CN 117094674 A CN117094674 A CN 117094674A CN 202311029629 A CN202311029629 A CN 202311029629A CN 117094674 A CN117094674 A CN 117094674A
Authority
CN
China
Prior art keywords
information
node
vehicle
resource
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311029629.4A
Other languages
Chinese (zh)
Inventor
赵志丹
赵大晶
韩籼芃
杨帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BMW Brilliance Automotive Ltd
Original Assignee
BMW Brilliance Automotive Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BMW Brilliance Automotive Ltd filed Critical BMW Brilliance Automotive Ltd
Priority to CN202311029629.4A priority Critical patent/CN117094674A/en
Publication of CN117094674A publication Critical patent/CN117094674A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/177Editing, e.g. inserting or deleting of tables; using ruled lines
    • G06F40/18Editing, e.g. inserting or deleting of tables; using ruled lines of spreadsheets
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/186Templates

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Audiology, Speech & Language Pathology (AREA)
  • General Engineering & Computer Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Computational Linguistics (AREA)
  • Artificial Intelligence (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Data Mining & Analysis (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the specification provides a resource management method, device and system for a vehicle project and computing equipment; the method comprises the following steps: acquiring resource information of a first node in a vehicle project through information input equipment, wherein the first node is any node in the vehicle project; processing the resource information of the first node based on the association of the first node and a second node in the vehicle project to obtain the resource information of the second node; responding to a viewing request of information display equipment for the vehicle item, and sending resource information of each node in the vehicle item to the information display equipment; wherein each node comprises the first node and the second node; the method can improve the execution efficiency of the vehicle project.

Description

Resource management method, device and system for vehicle project and computing equipment
Technical Field
The present disclosure relates to the field of computer technologies, and in particular, to a method for resource management of a vehicle project. The present specification also relates to a resource management apparatus of a vehicle item, a resource management system of a vehicle item, a computing device, and a computer-readable storage medium.
Background
With the development of computer technology, there is an increasing demand for convenience in processing events in work and life.
For an item in an enterprise, the duration of the process from the beginning of the item to the end of the item is typically long. In the process, various links generate a lot of data, and the execution of the project requires the coordination of staff of various departments to carry out a lot of communication.
Therefore, the execution efficiency of the current project is low.
Disclosure of Invention
In view of this, the present specification provides a resource management method of a vehicle item, which can improve the execution efficiency of the vehicle item. The present specification also relates to a resource management apparatus of a vehicle item, a resource management system of a vehicle item, a computing device, and a computer-readable storage medium.
According to an aspect of the embodiments of the present specification, there is provided a resource management method of a vehicle item, including:
acquiring resource information of a first node in a vehicle project through information input equipment, wherein the first node is any node in the vehicle project;
processing the resource information of the first node based on the association of the first node and a second node in the vehicle project to obtain the resource information of the second node;
Responding to a viewing request of information display equipment for the vehicle item, and sending resource information of each node in the vehicle item to the information display equipment; wherein each node comprises the first node and the second node.
Optionally, the acquiring, by the information input device, the resource information of the first node in the vehicle item includes:
invoking a data storage system through the information input device;
and acquiring the resource information of the first node from the data storage system.
Optionally, the acquiring, by the information input device, the resource information of the first node in the vehicle item includes:
identifying communication information in the information input equipment;
and acquiring the resource information of the first node based on the communication information under the condition that the communication information is identified as the related information of the first node.
Optionally, the acquiring, by the information input device, the resource information of the first node of the vehicle item includes:
acquiring budget information of a budget submitting node in a production budget planning project of the vehicle through the information input equipment;
processing the resource information of the first node based on the association of the first node and the second node in the vehicle project to obtain the resource information of the second node, including:
And based on the association of the budget submitting node and the budget checking node, summarizing the budget information according to the category to obtain a budget report of the budget checking node.
Optionally, after obtaining the budget report of the budget check node, the method further comprises:
sending a project planning page to the information display equipment, wherein the project planning page at least comprises a report management module;
and under the condition that a trigger instruction of the information display equipment aiming at the report management module is acquired, sending the budget report to the information display equipment.
Optionally, the acquiring, by the information input device, the resource information of the first node in the vehicle item includes:
sending a project planning page to the information input equipment, wherein the project planning page at least comprises a data management module;
responding to a trigger instruction of the information input device for the data management module, and sending an information input page to the information input device; wherein the information input page comprises a plurality of information types related to the first node;
acquiring resource information of the first node input by the information input device based on the information input page; wherein the resource information of the first node includes information of at least one information type of the plurality of information types.
Optionally, before the resource information of each node of the vehicle item is sent to the information presentation device in response to the viewing request of the information presentation device for the vehicle item, the method further includes:
sending a project planning page to the information display equipment, wherein the project planning page at least comprises a planning management module;
and under the condition that a trigger instruction of the information display equipment for the plan management module is acquired, determining that the viewing request is received.
Optionally, the method further comprises:
sending a project planning page to information management equipment, wherein the project planning page at least comprises a system management module;
transmitting authority information of the vehicle item to the information management device under the condition that a trigger instruction of the information management device for the system management module is acquired;
and changing the authority of the vehicle item in response to a change request of the information management device for the authority information.
Optionally, the method further comprises:
acquiring resource information of historical vehicle projects;
evaluating the resource condition of the vehicle project to be handled based on the resource information of the historical vehicle project; wherein the similarity of the to-be-handled vehicle item and the historical vehicle item is higher than a target threshold.
Optionally, the acquiring, by the information input device, the resource information of the first node in the vehicle item includes:
acquiring resource information of the first node based on a user account logged in by the information input equipment;
the response to the viewing request of the information display device for the vehicle item, the resource information of each node in the vehicle item is sent to the information display device, and the method comprises the following steps:
responding to the view request sent by the information display equipment based on the logged-in user account, and sending resource information of each node in the vehicle project to the information display equipment;
the method further comprises the steps of:
counting operations that have been performed on a per user account basis; wherein the operations include: acquiring at least one of resource information and transmission resource information;
and determining the carbon emission reduction amount corresponding to each user account based on the executed operation according to the corresponding relation between the operation and the carbon emission reduction amount.
According to another aspect of the embodiments of the present specification, there is provided a resource management device of a vehicle item, the resource management device of a vehicle item including:
the first acquisition module is used for acquiring resource information of a first node in a vehicle project through information input equipment, wherein the first node is any node in the vehicle project;
The processing module is used for processing the resource information of the first node based on the association between the first node and the second node in the vehicle project to obtain the resource information of the second node;
the first sending module is used for responding to a viewing request of the information display equipment for the vehicle item and sending resource information of each node in the vehicle item to the information display equipment; wherein each node comprises the first node and the second node.
According to yet another aspect of embodiments of the present specification, there is provided a computing device comprising: the system comprises a processor and a memory, wherein the memory stores program instructions, and the processor is used for executing the program instructions to execute the steps in the method.
According to a further aspect of embodiments of the present description, there is provided a computer readable storage medium having stored therein program instructions which, when executed by a processor, are adapted to carry out the steps of the above-mentioned method.
According to still another aspect of the embodiments of the present specification, there is provided a resource management system of a vehicle item, the resource management system including a target device, an information input device, and an information presentation device, the target device being the above-described resource management apparatus or the above-described computing device.
In an embodiment of the present disclosure, resource information of any node in a vehicle item may be obtained through an information input device, resource information of other nodes may be obtained based on association between the node and the other nodes, and resource information of each node in the vehicle item may be sent to an information display device, so as to be displayed by the information display device. Therefore, the users of the information input devices can upload the resource information of the first node in the vehicle project respectively, and the users of the information display devices can directly check the resource information of the second node and can also check the information of the whole life cycle of the vehicle project. Each user does not need to communicate and report the resource information of the first node in sequence and then collect the resource information, the user does not need to analyze the collected resource information by himself, and the complete information about the vehicle project can be directly obtained. Therefore, the user has higher efficiency of acquiring the resource information of each node in the vehicle project, reduces the time waste caused by acquiring the resource information in the project execution process, and further can improve the execution efficiency of the vehicle project.
Drawings
FIG. 1 is a schematic illustration of a resource management system for a vehicle item according to one embodiment of the present disclosure;
FIG. 2 is a flow chart of a method for resource management of a vehicle item according to one embodiment of the present disclosure;
FIG. 3 is a flow chart of another method of resource management of a vehicle item provided in an embodiment of the present disclosure;
FIG. 4 is a schematic diagram of a project plan page according to one embodiment of the present disclosure;
FIG. 5 is a schematic diagram of an information input page according to an embodiment of the present disclosure;
FIG. 6 is a schematic diagram of a display interface according to an embodiment of the present disclosure;
FIG. 7 is a block diagram of a project planning platform according to one embodiment of the present disclosure;
FIG. 8 is a block diagram of a resource management system according to an embodiment of the present disclosure;
FIG. 9 is a simplified flow diagram of a resource management method for budget planning projects according to one embodiment of the present disclosure;
fig. 10 is a schematic structural view of a resource management device for a vehicle item according to an embodiment of the present disclosure;
FIG. 11 is a block diagram of a computing device according to one embodiment of the present disclosure.
Detailed Description
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present description. This description may be embodied in many other forms than described herein and similarly generalized by those skilled in the art to whom this disclosure pertains without departing from the spirit of the disclosure and, therefore, this disclosure is not limited by the specific implementations disclosed below.
The terminology used in the one or more embodiments of the specification is for the purpose of describing particular embodiments only and is not intended to be limiting of the one or more embodiments of the specification. As used in this specification, one or more embodiments and the appended claims, the singular forms "a," "an," and "the" are intended to include the plural forms as well, unless the context clearly indicates otherwise. It should also be understood that the term "and/or" as used in one or more embodiments of the present specification refers to and encompasses any or all possible combinations of one or more of the associated listed items. The term "at least one" in one or more embodiments of the present specification refers to "one or more" and "a plurality" refers to "two or more". The term "comprising" is an open description and should be understood as "including but not limited to" and may include other content in addition to what has been described.
It should be understood that although the terms "first," "second," and the like may be used in one or more embodiments of the present description to describe various information, these information should not be limited to these terms. These terms are only used to distinguish one type of information from another. For example, "first" may also be referred to as "second" and, similarly, "second" may also be referred to as "first" without departing from the scope of one or more embodiments of the present description. The word "if" as used herein may be interpreted as "at … …" or "at … …" or "responsive to a determination", depending on the context.
For an item to be executed, it is generally necessary to collect information (such as budget information) about the item from each business department, and then analyze the collected information from different dimensions and provide the analyzed information to an item manager. The project manager can make a specific project execution plan based on the analyzed information, and subsequent departments can execute the project based on the plan.
For various information of an item, a spreadsheet is generally used for collection, and a plurality of people are required to fill in the spreadsheet in sequence at the time of collection. The user may also use paper to record certain information during the collection process. If the project is updated for the vehicle, the updating information for different vehicle types needs to be collected. Because different vehicle types may be responsible by different business personnel, the business personnel are required to fill in information in sequence, so the information collection process takes longer time. And the business personnel also can need to provide the same information for different managers, and in the process, the business personnel need to copy, paste and template adjustment operations of information for a plurality of times, and the process also consumes more labor cost. And, if a problem occurs in a plan created based on the collected project information, the project manager needs to communicate with each business department offline to find the reason. Therefore, the labor cost required for collecting the information of the project is high at present, repeated collection of more information can be carried out, and the communication cost of personnel is high.
In addition, an item may be part of an overall item for which only certain information gathering and planning is currently performed. The user cannot acquire the relevance between the information of the item and the whole item, the consistency of the item and the whole item is difficult to ensure, and the accuracy of an execution plan formulated for the item is difficult to ensure.
The specification provides a resource management method for a vehicle project, which can collect resource information of the vehicle project more simply, reduce the difficulty of a user in acquiring the required resource information, improve the execution efficiency of the vehicle project, and improve the execution accuracy of the vehicle project. The present specification also relates to a resource management apparatus, a resource management system, a computing device, and a computer-readable storage medium of a vehicle item.
Fig. 1 is a schematic structural diagram of a resource management system of a vehicle item according to an embodiment of the present disclosure. As shown in fig. 1, the resource management system includes a resource management apparatus 101, an information input device 102, and an information presentation device 103. Optionally, the resource management system may also include an information management device 104. The information input device 102, the information presentation device 103, and the information management device 104 are all communicatively connected to the resource management apparatus 101. The resource management device 101 may be a device for providing a resource management function of a vehicle item in a cloud platform, and the information input apparatus 102, the information presentation apparatus 103, and the information management apparatus 104 may access the cloud platform.
Alternatively, the resource management apparatus 101 is a computing device, and may be used to perform processing of resource information. The resource management device 101 may be a computer or a server. The information input device 102, the information display device 103, and the information management device 104 may be a terminal, such as a smart phone, a notebook computer, a tablet computer, or a desktop computer.
The number of information input devices 102, information presentation devices 103, and information management devices 104 in the resource management system may be one or more, and fig. 1 illustrates only one information input device 102, one information presentation device 103, and one information management device 104. One terminal may also serve as at least two of the information input device 102, the information presentation device 103, and the information management device 104 at the same time.
In the resource management system of the embodiment of the present specification, communication connection between each device (i.e., the information input device 102, the information presentation device 103, and the information management device 104) and the resource management apparatus 101 may be realized through a project planning platform. The resource management device 101 may be a background device for supporting services that can be provided by the project planning platform. The project planning platform is presented in the form of an application or web page. By way of example, each device may access the project planning platform by running the application or accessing the web page, thereby obtaining various services that the project planning platform can provide.
For example, a plurality of users can access the project planning platform through the corresponding information input devices 102, and then synchronously send the information of the vehicle project to the resource management device 101. Multiple users may each access the project planning platform via the information presentation device 103, thereby sharing information for the vehicle project. Different users can access the project planning platform through different information management devices 104, and further manage the vehicle projects in the project planning platform. Alternatively, as shown in fig. 1, the information input device 102, the information presentation device 103, and the information management device 104 may display the same or similar pages when accessing the project plan platform.
Fig. 2 is a flowchart of a method for resource management of a vehicle item according to an embodiment of the present disclosure, which may be used in the resource management system shown in fig. 1, such as the resource management device 101 used in the resource management system. As shown in fig. 2, the method includes:
step 201, obtaining resource information of a first node in a vehicle project through an information input device, wherein the first node is any node in the vehicle project.
In the present embodiment, the vehicle item refers to an item related to a vehicle. Such as vehicle items may include design items, production items, assembly items, or vending items for the vehicle, etc. Alternatively, the vehicle project may include the entire process of designing the vehicle to completion of production.
Multiple nodes exist in the execution process of the project, for example, the production project of the vehicle can comprise a budget planning node, a purchasing node, a receiving node, a goods using node and the like. Each node will have corresponding resource information. The resource information of the budget plan node can comprise total budget information, sub-budget information of each execution stage in the project, sub-budget information corresponding to different types of cost in the project, and the like. The resource information, such as the purchasing node, may include total budget information for purchasing, item information for desired purchasing, item information that has been purchased, and remaining budget information for purchasing, among others.
Some nodes in the project may also include multiple child nodes, and each child node may have corresponding resource information. The nodes in the vehicle items described in the embodiments of the present specification may refer to child nodes, and may also refer to nodes to which a plurality of child nodes belong. For any node in the vehicle project, the corresponding staff can input the resource information of the node through the information input equipment, so that the resource management device can manage the vehicle project based on the resource information.
And 203, processing the resource information of the first node based on the association of the first node and the second node in the vehicle project to obtain the resource information of the second node.
The second node refers to a node which is associated with the first node in the vehicle project, and the resource information of the second node needs to be obtained based on the resource information of the first node. The second node may be a node located after the first node in the execution flow of the vehicle item, such as a next node of the first node. Alternatively, the second node may be a node executed in parallel with the first node in the execution flow of the project, which is not limited in the embodiment of the present disclosure.
After the resource management device of the vehicle project acquires the resource information of the first node, the resource information of the second node can be determined based on the resource information, and a worker does not need to analyze the resource information by itself, so that the working process of the worker can be simplified.
Step 205, responding to a viewing request of the information display equipment for the vehicle project, and sending resource information of each node in the vehicle project to the information display equipment; wherein each node includes a first node and a second node.
The user may send a view request for the vehicle item to the resource management device through the information presentation apparatus, and the resource management device may send corresponding resource information to the information presentation apparatus in response to the view request.
For example, the view request may be used only to request to view resource information of a part of nodes in the vehicle item, and the resource management device may send the resource information of the part of nodes to the information presentation apparatus. The viewing request may also be used to request to view resource information of the entire vehicle item, and the resource management device may send resource information of all nodes of the vehicle item to the information display apparatus, where the resource information of all nodes may also be referred to as information of a full life cycle of the vehicle item.
In summary, in the resource management method for a vehicle item provided in the embodiments of the present disclosure, resource information of any node in a vehicle item may be obtained through an information input device, resource information of other nodes may be obtained based on association between the node and the other nodes, and resource information of each node in the vehicle item may be sent to an information display device for display by the information display device. Therefore, the users of the information input devices can upload the resource information of the first node in the vehicle project respectively, and the users of the information display devices can directly check the resource information of the second node and can also check the information of the whole life cycle of the vehicle project. Each user does not need to communicate and report the resource information of the first node in sequence and then collect the resource information, the user does not need to analyze the collected resource information by himself, and the complete information about the vehicle project can be directly obtained. Therefore, the user has higher efficiency of acquiring the resource information of each node in the vehicle project, reduces the time waste caused by acquiring the resource information in the project execution process, and further can improve the execution efficiency of the vehicle project.
FIG. 3 is a flow chart of another method for resource management of a vehicle item, which may be used in the resource management system shown in FIG. 1, in accordance with an embodiment of the present disclosure. As shown in fig. 3, the method includes:
step 301, the resource management device sends a project planning page to the information input device.
Step 303, the information input device displays the project planning page.
For example, for steps 301 and 303 described above, the user may trigger the information input device to access the project plan web page, and the information input device may send an access request to the resource management apparatus. The resource management device may send information of the project plan page to the information input apparatus in response to the access request, and the information input apparatus may display the project plan page based on the information.
The content in the project plan page sent by the resource management apparatus may be different for different information input devices. For example, when the user triggers the information input device to access the project planning webpage, the user also needs to log in a corresponding user account in the project planning webpage, and then the resource management device sends the project planning webpage containing corresponding content based on the authority information item information input device of the user account. An icon of the user account can be displayed in the project planning page, and the user can trigger the icon to change the logged-in user account, check the information of the user account, or log out the current user account. FIG. 4 is a schematic diagram of a project plan page according to one embodiment of the present disclosure. As shown in fig. 4, the project plan page may include an identification icon Y for the user account.
With continued reference to fig. 4, the project plan page of the present embodiment is exemplified by a plan management module, a data management module, a report management module, and a system management module. The module identifiers corresponding to the four modules respectively can be displayed in the project planning page, and any module identifier can be triggered to request the service corresponding to the module from the resource management device. Optionally, the project plan page may also include some of the four modules. The project plan page may also display introductory information to the project plan platform.
The service corresponding to the plan management module comprises query and display of the whole execution plan of each project. Alternatively, the plan management module may include a plurality of sub-modules, each sub-module corresponding to a different type of item.
The service corresponding to the data management module includes acquiring data before the project is executed, such as receiving starting main data of the project. The start master data may include resource information for each node in the project, such as information including an identity of the project, a Loan base Rate (LPR), and a date.
The service corresponding to the report management module comprises a report corresponding to each node in the presentation project, such as an analysis report of the state of the guidance plan. The report management module may include a plurality of sub-modules that respectively correspond to a plurality of different report types, such as a guideline report, a comparison report, an order status report, a version output report, an auxiliary system report, an output absolute principle report, and an output variable report, etc.
The service corresponding to the system management module is a service for managing the authority of the project. The method comprises the steps of authorizing each user account, setting items which can be checked by the user account, setting item nodes which are responsible for processing by each user, freezing data and the like.
Optionally, the project planning platform in the embodiments of the present description supports single sign-on. The project planning platform is bound with an auxiliary system, and a user can log in synchronously in the project planning platform after logging in the auxiliary system, for example, the auxiliary system comprises an internal system of an enterprise. The project planning platform may also directly obtain the data in the auxiliary system, for example, the resource management device may directly obtain the data in the auxiliary system.
Optionally, the project planning platform may also be connected to or integrated with a data storage system to obtain data in the data storage system. Such as the Data storage system includes an enterprise management solution system (System Applications and Products, SAP), a business planning and integration (BPC) system, and a big Data platform (Cloud Data Hub, CDH).
Step 305, the information input device sends a trigger instruction for the data management module to the resource management device.
The user may operate the information input device to click on any module identifier in the project plan page shown in fig. 4. If the user clicks on the module identifier of the data management module, the information input device may generate a trigger instruction for the data management module. The information input device may send the trigger instruction to the resource management device, so that the resource management device provides corresponding information based on the trigger instruction.
In step 307, the resource management device transmits the information input page to the information input device in response to the trigger instruction.
Step 309, the information input device displays the information input page.
The resource management device may send information of the information input page to the information input apparatus in response to the trigger instruction, and the information input apparatus may display the information page based on the information. Optionally, the information input device may also display other pages before displaying the information input page, such as redisplaying the information input page by user triggering on the other pages.
Fig. 5 is a schematic diagram of an information input page according to an embodiment of the present disclosure. When the user clicks on the module identification of the data management module in the project plan page of fig. 4, the information input apparatus may display the information input page shown in fig. 5. For example, the information input page may include a plurality of information types related to a first node of the project, which may be any node in the project. Alternatively, the first node may be a fixed node, for example, the first node is a budget submission node, and the first node may be a first start node of the project. Such as the plurality of information types may include labor cost budget, machine cost budget, business trip budget, and the like.
Alternatively, steps 303 to 309 may be performed by the information input device. When the information input device detects the triggering operation of the user on the data management module, the corresponding triggering instruction can be directly generated and the information input page can be displayed based on the triggering instruction, or the information input page can be directly displayed without generating the triggering instruction.
Step 311, the information input device sends the resource information of the first node in the vehicle item acquired in the information input page to the resource management device.
The resource information of the first node may include information of at least one information type, which is at least one of a plurality of information types in the information input page. Alternatively, the information input device may send the resource information of the first node to the resource management apparatus based on the logged-in user account.
After the information input device displays the information input page, the user can input corresponding information in the input box corresponding to each information type in the information input page. The information input device may combine the basic information set for each information type and the information input by the user to obtain the resource information of the first node. After the input is finished, the user can confirm and submit, and the information input equipment can send the acquired information input by the user to the resource management device.
The above description is presented taking the resource information of the first node as an example of the user input. In another alternative implementation, the information input device may invoke the data storage system to obtain the resource information of the first node stored in the data storage system, and further send the resource information of the first node obtained from the data storage system to the resource management device. For the data storage system, please refer to the description of step 303, and the description is omitted here. Optionally, an invocation option may be included in the information entry page. The user may cause the information input device to invoke the data storage system when the user triggers the option.
In yet another alternative implementation, the resource management device may further monitor and identify the communication information in the information input device through the project planning platform. And acquiring the resource information of the first node based on the communication information under the condition that the communication information is identified as the related information of the first node. For example, the resource management device can use PRA technology to monitor and identify the communication information. Alternatively, identifying the communication may be used to obtain start-up data for the item.
The communication information may include, for example, mail received and sent by the information input device. The monitoring and identifying actions may be performed by an information input device. If the information input device receives a mail containing the total budget information of the production item of a certain automobile, the total budget information can be automatically determined to be one resource information of the budget submitting node corresponding to the item based on the mail. When the user needs to input the resource information of the budget submitting node, the information input device can prompt the total budget information for the user to select. Optionally, the information input device may also automatically send information of the total budget to the resource management arrangement.
Alternatively, an acquisition period may be set for acquisition of resource information of the ground node. The resource management apparatus may receive resource information of the first node transmitted by the plurality of information input devices during the acquisition period. The users of the information input devices do not need to consider the information uploading condition of other users, and only need to upload the information of the users in the acquisition time period.
Alternatively, in the acquisition period of the resource information of a certain node, the resource management device may also receive the resource information of other nodes sent by the information input device at the same time. The resource management method provided by the embodiment of the specification can improve the flexibility of collecting the resource information of the nodes.
Step 313, the resource management device determines a second node associated with the first node in the vehicle item based on the execution flow of the vehicle item.
The second node is a node associated with the first node, and the resource information is needed to be obtained based on the resource information of the first node.
The vehicle project can have a default execution flow, or a worker can correspondingly change the default execution flow for a certain vehicle project, or the worker can also formulate a corresponding execution flow for the vehicle project. The resource management device may determine each node in the vehicle project based on the execution flow of the vehicle project, and may determine a relationship between each node, and a sequence may exist between each node. Alternatively, the various nodes may include executed nodes, executing nodes, and unexecuted nodes.
Illustratively, the second node in the embodiments of the present specification may be a node subsequent to the first node. The resource management device may determine only one second node for the first node, or may determine a plurality of second nodes. If a plurality of second nodes are determined, for each second node, reference is made to the subsequent description about the second node.
Step 315, the resource management device processes the resource information of the first node based on the association between the first node and the second node, to obtain the resource information of the second node.
Illustratively, the first node is a budget submission node of the vehicle item, the second node is a budget check node of the vehicle item, and the budget check node is a next node of the budget submission node. The resource management device can summarize the budget information according to the category based on the association of the budget submitting node and the budget checking node to obtain a budget report of the budget checking node. The budget report is the resource information belonging to the budget check node.
According to the method, all nodes in the vehicle project can be processed, so that the resource information of all the nodes in the vehicle project can be obtained conveniently and rapidly. It should be noted that, as the vehicle item advances, the resource information of each node in the vehicle item may change accordingly. The resource information of each node in the vehicle project can be obtained and processed, and can be continuously updated in the execution process of the vehicle project.
For example, the user may send an update instruction for the execution state of the item to the resource management device through the information input device. The resource management device may update the resource information of the current node in the vehicle item in response to the update instruction.
Step 317, the resource management device sends the project planning page to the information display device.
And 319, displaying the project planning page by the information display equipment.
Step 317 and step 319 can be described with reference to step 301 and step 303, and the description of the embodiment is omitted here. Optionally, the user account logged in the information display device and the information input device may be different, and the authority corresponding to the user account may be different. Alternatively, the rights of the two user accounts may be the same, such as having both input rights for the resource information of the first node and viewing rights for the resource information of each node of the vehicle item. Alternatively, the information presentation device and the information input device may be the same device, or may be different devices.
And 321, the information display equipment transmits a viewing request for the vehicle project to the resource management device based on the project planning page.
Alternatively, the information presentation apparatus may send the viewing request to the resource management device based on the logged-in user account.
Optionally, the user may operate on a module in the project plan page, triggering the information presentation device to send a view request for information of the vehicle project to the resource management apparatus to view the information of the vehicle project. The user can request to view the information of the whole life cycle of the vehicle project through the viewing request, or can request to view the resource information of only part of nodes in the vehicle project.
In a first alternative example, the information presentation apparatus may send a trigger instruction for the plan management module to the resource management device in a case where a trigger operation of the user for the plan management module is detected, and the resource management device may determine the trigger instruction as a view request for the vehicle item. The viewing request may not carry an identification of a specific vehicle item, and the resource management device may determine all existing vehicle items as vehicle items that the information display apparatus requests to view. Alternatively, the view request may carry an identification of a particular vehicle item, at which point the resource management device may determine that the information presentation device requests information for the vehicle item.
Alternatively, the trigger instruction may be directly acquired and sent based on a selection operation for the option identifier corresponding to the trigger plan management module. Or after the user selects the option identifier corresponding to the plan management module, the information display device further displays a plurality of sub-options corresponding to different types of vehicle items, and when the user selects any sub-option, the information display device acquires and sends the trigger instruction. At this time, the triggering instruction carries the vehicle item type corresponding to the sub-option.
In a second alternative example, when the user clicks on the identity of the report management module in the project plan page, the information presentation apparatus may obtain a trigger instruction for the report management module and send the trigger instruction to the resource management device. The resource management device may determine the trigger instruction as a view request for resource information of a target node in the vehicle item. The target node includes a node in the vehicle project that is involved in report viewing, e.g., the target node may include: budget check nodes, purchasing nodes, and the like.
Optionally, after the user clicks on the identifier of the report management module, the identifier of the specific vehicle item may be input, and the identifier of the specific target node in the vehicle item may also be input. Furthermore, the information presentation device may send a trigger instruction carrying the identification of the specific vehicle item and the identification of the target node to the resource management device.
In response to the view request, the resource management device transmits resource information of the target node in the vehicle item to the information presentation apparatus, step 323.
The resource management device may send information that it requests to view to the information presentation device, such as sending resource information of a target node in the vehicle item to the information presentation device, based on the view request.
For the viewing request in the first alternative example, the resource management device may determine all the nodes in the vehicle item as the target nodes, and further send information of all the nodes in the vehicle item to the information presentation device. For a node in the vehicle project that does not execute or acquire resource information, known information such as the time to be executed of the node may be sent to the information display device.
For the case that the viewing request does not carry the identification of the specific vehicle item, the resource management device may first send the information presentation apparatus brief information of all the existing vehicle items, so that the information presentation apparatus further determines the specific vehicle item requested to be viewed based on the brief information. When receiving a viewing request carrying the identification of a specific vehicle item, the resource management device sends resource information of each node of the vehicle item to the information display device.
For the view request in the second alternative example described above, the user may enter the identity of the budget check node in the target vehicle item after clicking on the identity of the report management module. Further, the information presentation apparatus may transmit a budget report of the budget collation node to the resource management device.
And 325, displaying the resource information of the target node in the vehicle project by the information display equipment.
Optionally, during the process that the information display device displays the resource information of the budget check node in the vehicle project, the user may further operate the information display device to trigger freezing or thawing of the resource information of the budget submission node. After freezing, the resource information of the budget submitting node can be forbidden to be updated, so that the situation that the resource information of the budget checking node is not matched with the resource information of the budget submitting node is avoided. After thawing, a user can be supported to update the resource information of the budget submitting node so as to update the resource information of the budget checking node.
For example, report checkers may freeze the resource information of the budget submission node during viewing of the budget report. And under the condition that the data in the report is confirmed to be wrong, the report checking personnel unfreeze the resource information of the budget submitting node, so that the business personnel correct the wrong information.
Step 327, the resource management device sends the project plan page to the information management device.
Step 329, the information management device displays the project planning page.
Step 327 and step 329 are described with reference to step 301 and step 303, and the description of the embodiments is omitted herein. Optionally, the user account logged in by the information management device and the information input device and the information display device may be different, and the authority corresponding to the user account may be different. Or, the authority of the three user accounts may be the same, for example, the authority has the input authority of the resource information of the first node, the authority has the viewing authority of the resource information of each node of the vehicle project, and the authority has the management authority of the vehicle project. Alternatively, at least one of the information presentation device and the information input device may be the same device as the information management device, or may be a different device.
Step 331, the information management apparatus transmits a system management request to the resource management device.
Optionally, the user may operate on a module in the project plan page, triggering the information presentation device to send a system management request to the resource management device to manage the rights of the vehicle project. If the information display device detects the triggering operation of the user on the system management module, the triggering instruction for the system management module can be sent to the resource management device, and the resource management device can determine the triggering instruction as a system management request.
Step 333, the resource management device transmits the authority information of the vehicle item to the information management apparatus in response to the system management request.
Step 335, the information management device displays the rights information.
The information management device may first send authority information of the current vehicle item to the information management device based on the received system management request, so that a user of the information management device may view and determine how to manage the authority. The authority information may include, for example, information of a user who has authority to view for each of the vehicle items, information of whether or not information of each of the vehicle items is editable, information of setting conditions of each of the roles, and the like.
Step 337, the information management apparatus transmits a request for changing the authority information to the resource management device.
The user may perform certain operations (such as adding information, deleting information, modifying information, etc.) on the rights information displayed by the information management device, so as to trigger the information management device to send a request for changing the rights information to the resource management device. The change request carries operation information of the user on the authority information so as to trigger the resource management device to change the authority of the vehicle item based on the operation information.
In response to the change request, the resource management device changes the authority of the vehicle item in step 331.
The resource management device may change the authority of the vehicle item, such as changing the resource information of the vehicle item, changing the viewable information range of different users, changing the editable authority of the information of the vehicle item, and the like. After the resource management device changes the authority of the vehicle item, the follow-up user needs to follow the changed authority for checking and operating the information of the vehicle item. For example, the change request may be an information freeze request for a target node of the vehicle item, and the resource management device may prohibit a subsequent user from making an information change for the target node.
Optionally, the resource management device may further acquire resource information of the historical vehicle project, and further evaluate a resource condition of the vehicle project to be handled based on the resource information of the historical vehicle project. Wherein the similarity of the to-be-handled vehicle item and the historical vehicle item is higher than a target threshold.
For example, the historical vehicle project is a production budget plan for a type a vehicle, the to-do vehicle project is a production budget plan for a type B vehicle, and only the frame styles of the type a vehicle and the type B vehicle are different. Under the condition, the similarity of the A-type vehicle and the B-type vehicle is higher, and the production budget conditions are smaller, so that the production budget planning of the A-type vehicle can be directly utilized to predict the production budget conditions of the B-type vehicle, and guidance is provided for a budget manager to control project budget.
Optionally, the resource management device in the embodiment of the present specification may further use kafka to enhance the expandability of the project planning platform, so as to support user access of different channels. The resource management device may also use redis to guarantee high performance of the project planning platform, even to support the project planning platform to provide huge data.
In the embodiment of the specification, each user can upload resource information in the project planning platform through the information input equipment, the users do not need to fill in information for many times, and the users do not need to communicate frequently, so that the accuracy, the consistency and the efficiency of information acquisition are high. In addition, the starting data of the project can be analyzed aiming at the information input equipment, the resource information of the project can be automatically updated, and the information acquisition efficiency is further improved. The project planning platform can be integrated with an SAP system and a CDH, and can ensure that acquired data is accurate and transparent.
Moreover, the user can check the resource information (such as control data, purchase data, financial data and human resource data) of each node of the vehicle project, so that the project can be monitored from the target agreement stage to the production end, the project budget can be comprehensively known, and the budget can be better controlled and guided.
In the resource management method provided by the embodiment of the specification, since the information recording is not required to be performed by adopting paper, the use of paper can be reduced; and because the collection efficiency of the resource information of the project is improved, and the planning efficiency of the project is improved, the using time of a computer can be reduced, and the electricity consumption is reduced. Therefore, the project planning platform of the embodiment of the specification can realize the effect of reducing the carbon emission, and provides a certain support for the sustainable development policy.
Optionally, the project planning platform in the embodiment of the present disclosure may further have a statistical function of carbon emission reduction, for determining a contribution of the user corresponding to each user account to the reduction of carbon emission. Each operation performed by the user based on the project planning platform (e.g., referred to as a user operation) may correspond to a certain reduction in carbon emissions. For example, the user operation may include at least one of uploading the resource information of the vehicle item (e.g., the resource information of the first node), viewing the resource information of the vehicle item (e.g., the resource information of the target node), deriving the resource information of the vehicle item, creating an execution plan of the vehicle item, modifying the execution plan of the vehicle item, running a project planning procedure, and downloading a user manual.
In the present embodiment, the carbon emission reduction amount corresponding to each operation may be determined according to the standards established by the international energy agency (International Energy Agency, IEA) and the chinese nuclear energy industry association (China Nuclear Energy Association, CNEA). If IEA specifies that 1 kilowatt hour (KWH) corresponds to 5 hours of laptop use power consumption, this corresponds to 997 grams of carbon dioxide emissions. CNEA specifies that the use of one A4 sheet of paper corresponds to A4 gram carbon dioxide emission.
For example, with respect to the related art, by the project planning platform in the embodiment of the present specification, the use of a 10-minute notebook computer can be reduced by creating an execution plan of a vehicle project, which is equivalent to reducing the emission of 33 g of carbon dioxide, so the carbon emission reduction amount corresponding to the operation of creating the execution plan of a vehicle project can be 33 g. The operation of modifying the execution plan of one vehicle item may reduce the use of a 5-minute notebook computer, which is equivalent to reducing the emission of 17 grams of carbon dioxide, so the carbon emission reduction amount corresponding to the operation of modifying the execution plan of the vehicle item may be 17 grams. Deriving the resource information for one vehicle item may reduce the use of a 20 minute notebook computer, which may correspond to reducing the emission of 66 grams of carbon dioxide, so the carbon emission reduction corresponding to the operation of deriving the resource information for the vehicle item may be 66 grams. Downloading the user manual may reduce the use of 4 sheets of A4 paper, which corresponds to reducing the emission of 16 grams of carbon dioxide, so the reduction in carbon emissions corresponding to the operation of downloading the user manual may be 16 grams. The planning procedure for running the project once can reduce the use of 2 sheets of A4 paper, which is equivalent to reducing the emission of 8 grams of carbon dioxide, so the carbon emission reduction corresponding to the operation of the planning procedure for running the project can be 8 grams. The embodiment of the present disclosure only exemplifies the five user operations, and the carbon emission reduction amount corresponding to each user operation may be other values, which is not limited in the embodiment of the present disclosure.
Each user operation may trigger the resource management device to perform a certain operation, and accordingly, each operation performed by the resource management device based on the user operation may correspond to a certain carbon emission reduction amount. The carbon emission reduction amount corresponding to the operation of the resource management device may be determined based on the carbon emission reduction amount corresponding to the user operation that triggers the operation, e.g., the carbon emission reduction amount corresponding to the operation of the resource management device is equal to the carbon emission reduction amount corresponding to the respective user operation. Uploading the resource information of the vehicle project can trigger the resource management device to acquire the resource information, and checking the resource information of the target node can trigger the resource management device to transmit the resource information.
The resource management device may count operations that have been performed on a per-user account basis, and determine a corresponding carbon emission reduction amount for each user account based on the performed operations. The operations that the resource management device has performed based on one user account include: on the device logging into the user account, all user operations by the user trigger operations performed by the resource management means. The resource management device may determine, according to the correspondence between the operation and the carbon emission reduction, a total carbon emission reduction corresponding to all the performed operations based on each user account, where the total carbon emission reduction is the carbon emission reduction corresponding to the user account.
For example, with continued reference to fig. 5, after a display device accesses the project planning platform based on a user account, the display device may display an icon of the user account and may also display a carbon emission reduction amount corresponding to the user account. Fig. 5 is an example in which the icon of the user account and the carbon emission reduction amount are both displayed in the upper right corner of the display interface. The carbon emission reduction amount may be replaced by other names as exemplified by the carbon credit in fig. 5. Wherein the number preceding "/" indicates the current carbon credit of the user and the number following "/" indicates the accumulated carbon credit of the user.
Fig. 6 is a schematic diagram of a display interface according to an embodiment of the disclosure. Such as when the user clicks on the carbon credit information displayed at the user identification in fig. 5, the display device may be triggered to display the interface shown in fig. 6 to display the carbon credit-related information for the user account. As shown in fig. 6, the information may include current carbon credits and accumulated carbon credits of the user account, ranking information of the user joining the carbon credits, and accumulated rule information of the carbon credits. The user can operate based on the information to promote the carbon credit of the user; therefore, the functions of the project planning platform can be enriched, and the use enthusiasm of a user on the project planning platform is improved.
In summary, in the resource management method for a vehicle item provided in the embodiments of the present disclosure, resource information of any node in a vehicle item may be obtained through an information input device, resource information of other nodes may be obtained based on association between the node and the other nodes, and resource information of each node in the vehicle item may be sent to an information display device for display by the information display device. Therefore, the users of the information input devices can upload the resource information of the first node in the vehicle project respectively, and the users of the information display devices can directly check the resource information of the second node and can also check the information of the whole life cycle of the vehicle project. Each user does not need to communicate and report the resource information of the first node in sequence and then collect the resource information, the user does not need to analyze the collected resource information by himself, and the complete information about the vehicle project can be directly obtained. Therefore, the user has higher efficiency of acquiring the resource information of each node in the vehicle project, reduces the time waste caused by acquiring the resource information in the project execution process, and further can improve the execution efficiency of the vehicle project.
FIG. 7 is a block diagram of a project planning platform according to one embodiment of the present disclosure. As shown in fig. 7, the project planning platform may include: front end, application layer, middleware and infrastructure. The front end faces the user; the application layer is used for providing basic functions of the project planning platform; the middleware is used for communicating the application layer with the infrastructure and providing a plurality of commonly supported functions; the infrastructure corresponds to the underlying hardware and is used for supporting the whole project planning platform.
The application layer may include an input service, an output service, and a public service. The input service may be used for information acquisition upload. Such as acquisition plan information, labor cost information, information submission instructions, project start information, information save instructions, and the like. The output service may be used to make output presentation of information to the front end. Such as output comparison reports, version information, BPC information, order status information, etc. Optionally, the application may further include a synchronization service for data synchronization, rights management, role management, popup management, dictionary management, user management, and the like.
The middleware can be used for supporting single sign-on of the project planning platform, information caching, information queuing, operation of a log system and the like. The infrastructure may be used to provide databases and containers, and to conduct container orchestration, etc.
Fig. 8 is a block diagram of a resource management system according to an embodiment of the present disclosure. As shown in fig. 8, the resource management system of the embodiment of the present specification is directed to users including planners, instruction planners, controllers, and administrators. The user can access the project planning platform through an internal system or a data link, so that the resource management method provided by the embodiment of the specification is realized. The project planning data generated in the project planning platform can be shared by mail and RPA. The project planning platform can be in butt joint with a cloud platform or a service platform.
FIG. 9 is a simplified flow diagram of a resource management method for a budget planning project according to an embodiment of the present disclosure. As shown in fig. 9, the process of project planning may include a project evaluation phase, a targeting agreement phase, and a project execution phase. The project execution phase may in turn include: update plan, change request, update project status, and project end. The project planning process involves control, business, other departments and projects.
Corresponding to the method embodiment, the present application further provides an embodiment of a resource management device for a vehicle item, and fig. 10 is a schematic structural diagram of a resource management device for a vehicle item according to an embodiment of the present disclosure. As shown in fig. 10, the resource management device 90 of the vehicle project includes:
a first obtaining module 901, configured to obtain, through an information input device, resource information of a first node in a vehicle project, where the first node is any node in the vehicle project;
the processing module 902 is configured to process the resource information of the first node based on the association between the first node and the second node in the vehicle item, to obtain the resource information of the second node;
A first sending module 903, configured to send resource information of each node in the vehicle item to the information display device in response to a request for viewing the vehicle item by the information display device; wherein each node includes a first node and a second node.
Optionally, the first obtaining module 901 is configured to:
calling a data storage system through information input equipment;
resource information of the first node is obtained from the data storage system.
Optionally, the first obtaining module 901 is configured to:
identifying communication information in the information input device;
and acquiring the resource information of the first node based on the communication information under the condition that the communication information is identified as the related information of the first node.
Optionally, the first obtaining module 901 is configured to:
acquiring budget information of a budget submitting node in a production budget planning project of a vehicle through information input equipment;
processing the resource information of the first node based on the association of the first node and the second node in the vehicle project to obtain the resource information of the second node, including:
based on the association of the budget submitting node and the budget checking node, the budget information is summarized according to the category, and a budget report of the budget checking node is obtained.
Optionally, the resource management device 90 further includes:
the second sending module is used for sending a project planning page to the information display equipment after obtaining the budget report of the budget check node, wherein the project planning page at least comprises a report management module;
and the third sending module is used for sending the budget report to the information display equipment under the condition that the triggering instruction of the information display equipment aiming at the report management module is acquired.
Optionally, the first obtaining module 901 is configured to:
sending a project planning page to the information input equipment, wherein the project planning page at least comprises a data management module;
responding to a trigger instruction of the information input device for the data management module, and sending an information input page to the information input device; the information input page comprises a plurality of information types related to the first node;
acquiring resource information of a first node input by information input equipment based on an information input page; wherein the resource information of the first node includes information of at least one of a plurality of information types.
Optionally, the resource management device 90 further includes:
a fourth sending module, configured to send a project planning page to the information display device before sending resource information of each node of the vehicle project to the information display device in response to a request for viewing the vehicle project by the information display device, where the project planning page at least includes a plan management module;
And the first determining module is used for determining that the viewing request is received under the condition that the triggering instruction of the information display equipment aiming at the plan management module is acquired.
Optionally, the resource management device 90 further includes:
a fifth sending module, configured to send a project planning page to the information management device, where the project planning page at least includes a system management module;
a sixth sending module, configured to send authority information of a vehicle item to the information management device when a trigger instruction of the information management device for the system management module is acquired;
and the changing module is used for responding to the changing request of the information management equipment for the authority information and changing the authority of the vehicle item.
Optionally, the resource management device 90 further includes:
the second acquisition module is used for acquiring resource information of historical vehicle projects;
the evaluation module is used for evaluating the resource condition of the vehicle project to be handled based on the resource information of the historical vehicle project; wherein the similarity of the to-be-handled vehicle item and the historical vehicle item is higher than a target threshold.
Optionally, the first obtaining module 901 is configured to: acquiring resource information of a first node based on a user account logged in by information input equipment;
The first sending module 903 is configured to: and responding to a viewing request sent by the information display equipment based on the logged-in user account, and sending resource information of each node in the vehicle project to the information display equipment.
The resource management device 90 may further include:
a statistics module for counting operations that have been performed based on each user account; wherein the operations include: acquiring at least one of resource information and transmission resource information;
and the second determining module is used for determining the carbon emission reduction amount corresponding to each user account based on the executed operation according to the corresponding relation between the operation and the carbon emission reduction amount.
In summary, in the resource management device for a vehicle item provided in the embodiments of the present disclosure, resource information of any node in a vehicle item may be obtained through an information input device, resource information of other nodes may be obtained based on association between the node and the other nodes, and resource information of each node in the vehicle item may be sent to an information display device for display by the information display device. Therefore, the users of the information input devices can upload the resource information of the first node in the vehicle project respectively, and the users of the information display devices can directly check the resource information of the second node and can also check the information of the whole life cycle of the vehicle project. Each user does not need to communicate and report the resource information of the first node in sequence and then collect the resource information, the user does not need to analyze the collected resource information by himself, and the complete information about the vehicle project can be directly obtained. Therefore, the user has higher efficiency of acquiring the resource information of each node in the vehicle project, reduces the time waste caused by acquiring the resource information in the project execution process, and further can improve the execution efficiency of the vehicle project.
The above is an exemplary embodiment of a resource management device of a vehicle item of the present embodiment. It should be noted that, the technical solution of the resource management device of the vehicle item and the technical solution of the resource management device method of the vehicle item belong to the same concept, and details of the technical solution of the resource management device of the vehicle item, which are not described in detail, can be referred to the description of the technical solution of the resource management device method of the vehicle item.
FIG. 11 is a block diagram of a computing device according to one embodiment of the present disclosure. The components of the computing device 400 include, but are not limited to, a memory 410 and a processor 420. Processor 420 is coupled to memory 410 via bus 430 and database 450 is used to hold data. The memory 410 stores program instructions that are executed by the processor 420 to perform the resource management method of the vehicle item described in fig. 2 and 3.
Computing device 400 also includes access device 440, access device 440 enabling computing device 400 to communicate via one or more networks 460. Examples of such networks include public switched telephone networks (PSTN, public Switched Telephone Network), local area networks (LAN, local Area Network), wide area networks (WAN, wide Area Network), personal area networks (PAN, personal Area Network), or combinations of communication networks such as the internet. The access device 440 may include one or more of any type of network interface, wired or wireless, such as a network interface card (NIC, network Interface Controller), such as an IEEE802.11 wireless local area network (WLAN, wireless Local Area Networks) wireless interface, a worldwide interoperability for microwave access (Wi-MAX, worldwide Interoperability for Microwave Access) interface, an ethernet interface, a universal serial bus (USB, universal Serial Bus) interface, a cellular network interface, a bluetooth interface, a near field communication (NFC, near Field Communication) interface, and so forth.
In one embodiment of the application, the above-described components of computing device 400, as well as other components not shown in FIG. 11, may also be connected to each other, such as by a bus. It should be understood that the block diagram of the computing device illustrated in FIG. 11 is for exemplary purposes only and is not intended to limit the scope of the present application. Those skilled in the art may add or replace other components as desired.
Computing device 400 may be any type of stationary or mobile computing device, including a mobile computer or mobile computing device (e.g., tablet, personal digital assistant, laptop, notebook, netbook, etc.), mobile phone (e.g., smart phone), wearable computing device (e.g., smart watch, smart glasses, etc.), or other type of mobile device, or a stationary computing device such as a desktop computer or PC. Computing device 400 may also be a mobile or stationary server.
The foregoing is a schematic illustration of a computing device of this embodiment. It should be noted that, the technical solution of the computing device and the technical solution of the resource management method of the vehicle item belong to the same concept, and details of the technical solution of the computing device, which are not described in detail, can be referred to the description of the technical solution of the resource management method of the vehicle item.
An embodiment of the present application also provides a computer-readable storage medium storing computer instructions that, when executed by a processor, are configured to implement the resource management method of the vehicle item described in fig. 2 and 3.
The above is an exemplary version of a computer-readable storage medium of the present embodiment. It should be noted that, the technical solution of the storage medium and the technical solution of the resource management method of the vehicle item belong to the same concept, and details of the technical solution of the storage medium, which are not described in detail, can be referred to the description of the technical solution of the resource management method of the vehicle item.
The foregoing describes certain embodiments of the present application. Other embodiments are within the scope of the following claims. In some cases, the actions or steps recited in the claims can be performed in a different order than in the embodiments and still achieve desirable results. In addition, the processes depicted in the accompanying figures do not necessarily require the particular order shown, or sequential order, to achieve desirable results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
The computer instructions include computer program code that may be in source code form, object code form, executable file or some intermediate form, etc. The computer readable storage medium may include: any entity or device capable of carrying the computer program code, a recording medium, a U disk, a removable hard disk, a magnetic disk, an optical disk, a computer Memory, a Read-Only Memory (ROM), a random access Memory (RAM, random Access Memory), an electrical carrier signal, a telecommunications signal, a software distribution medium, and so forth.
It should be noted that, for the sake of simplicity of description, the foregoing method embodiments are all expressed as a series of combinations of actions, but it should be understood by those skilled in the art that the present application is not limited by the order of actions described, as some steps may be performed in other order or simultaneously in accordance with the present application. Further, those skilled in the art will appreciate that the embodiments described in the specification are all preferred embodiments, and that the acts and modules referred to are not necessarily all required for the present application.
In the foregoing embodiments, the descriptions of the embodiments are emphasized, and for parts of one embodiment that are not described in detail, reference may be made to the related descriptions of other embodiments.
The preferred embodiments of the application disclosed above are intended only to assist in the explanation of the application. Alternative embodiments are not intended to be exhaustive or to limit the application to the precise form disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the application and the practical application, to thereby enable others skilled in the art to best understand and utilize the application. The application is limited only by the claims and the full scope and equivalents thereof.

Claims (14)

1. A resource management method of a vehicle item, comprising:
acquiring resource information of a first node in a vehicle project through information input equipment, wherein the first node is any node in the vehicle project;
processing the resource information of the first node based on the association of the first node and a second node in the vehicle project to obtain the resource information of the second node;
responding to a viewing request of information display equipment for the vehicle item, and sending resource information of each node in the vehicle item to the information display equipment; wherein each node comprises the first node and the second node.
2. The method according to claim 1, wherein the obtaining, by the information input device, resource information of the first node in the vehicle item includes:
invoking a data storage system through the information input device;
and acquiring the resource information of the first node from the data storage system.
3. The method according to claim 1, wherein the obtaining, by the information input device, resource information of the first node in the vehicle item includes:
identifying communication information in the information input equipment;
and acquiring the resource information of the first node based on the communication information under the condition that the communication information is identified as the related information of the first node.
4. The method of claim 1, wherein the obtaining, via the information input device, resource information of the first node of the vehicle item comprises:
acquiring budget information of a budget submitting node in a production budget planning project of the vehicle through the information input equipment;
processing the resource information of the first node based on the association of the first node and the second node in the vehicle project to obtain the resource information of the second node, including:
And based on the association of the budget submitting node and the budget checking node, summarizing the budget information according to the category to obtain a budget report of the budget checking node.
5. The method of claim 4, wherein after obtaining the budget report for the budget check node, the method further comprises:
sending a project planning page to the information display equipment, wherein the project planning page at least comprises a report management module;
and under the condition that a trigger instruction of the information display equipment aiming at the report management module is acquired, sending the budget report to the information display equipment.
6. The method according to any one of claims 1 to 5, wherein the acquiring, by the information input device, resource information of the first node in the vehicle item includes:
sending a project planning page to the information input equipment, wherein the project planning page at least comprises a data management module;
responding to a trigger instruction of the information input device for the data management module, and sending an information input page to the information input device; wherein the information input page comprises a plurality of information types related to the first node;
Acquiring resource information of the first node input by the information input device based on the information input page; wherein the resource information of the first node includes information of at least one information type of the plurality of information types.
7. The method of any one of claims 1 to 5, wherein prior to the sending the resource information for each node of the vehicle item to the information presentation device in response to a request for viewing the vehicle item by the information presentation device, the method further comprises:
sending a project planning page to the information display equipment, wherein the project planning page at least comprises a planning management module;
and under the condition that a trigger instruction of the information display equipment for the plan management module is acquired, determining that the viewing request is received.
8. The method according to any one of claims 1 to 5, further comprising:
sending a project planning page to information management equipment, wherein the project planning page at least comprises a system management module;
transmitting authority information of the vehicle item to the information management device under the condition that a trigger instruction of the information management device for the system management module is acquired;
And changing the authority of the vehicle item in response to a change request of the information management device for the authority information.
9. The method according to any one of claims 1 to 5, further comprising:
acquiring resource information of historical vehicle projects;
evaluating the resource condition of the vehicle project to be handled based on the resource information of the historical vehicle project; wherein the similarity of the to-be-handled vehicle item and the historical vehicle item is higher than a target threshold.
10. The method according to any one of claims 1 to 5, wherein the acquiring, by the information input device, resource information of the first node in the vehicle item includes:
acquiring resource information of the first node based on a user account logged in by the information input equipment;
the response to the viewing request of the information display device for the vehicle item, the resource information of each node in the vehicle item is sent to the information display device, and the method comprises the following steps:
responding to the view request sent by the information display equipment based on the logged-in user account, and sending resource information of each node in the vehicle project to the information display equipment;
the method further comprises the steps of:
Counting operations that have been performed on a per user account basis; wherein the operations include: acquiring at least one of resource information and transmission resource information;
and determining the carbon emission reduction amount corresponding to each user account based on the executed operation according to the corresponding relation between the operation and the carbon emission reduction amount.
11. A resource management device of a vehicle item, characterized in that the resource management device of a vehicle item includes:
the first acquisition module is used for acquiring resource information of a first node in a vehicle project through information input equipment, wherein the first node is any node in the vehicle project;
the processing module is used for processing the resource information of the first node based on the association between the first node and the second node in the vehicle project to obtain the resource information of the second node;
the first sending module is used for responding to a viewing request of the information display equipment for the vehicle item and sending resource information of each node in the vehicle item to the information display equipment; wherein each node comprises the first node and the second node.
12. A computing device, the computing device comprising: a processor and a memory, the memory having stored therein program instructions for execution of the program instructions to implement the steps of the method of any of claims 1 to 10.
13. A computer readable storage medium, characterized in that it has stored therein program instructions, which when executed by a processor are adapted to carry out the steps of the method of any of claims 1 to 10.
14. A resource management system of a vehicle item, characterized in that the resource management system comprises a target device, an information input device and an information presentation device, the target device being the resource management apparatus of claim 11 or the computing device of claim 12.
CN202311029629.4A 2023-08-15 2023-08-15 Resource management method, device and system for vehicle project and computing equipment Pending CN117094674A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311029629.4A CN117094674A (en) 2023-08-15 2023-08-15 Resource management method, device and system for vehicle project and computing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311029629.4A CN117094674A (en) 2023-08-15 2023-08-15 Resource management method, device and system for vehicle project and computing equipment

Publications (1)

Publication Number Publication Date
CN117094674A true CN117094674A (en) 2023-11-21

Family

ID=88780905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311029629.4A Pending CN117094674A (en) 2023-08-15 2023-08-15 Resource management method, device and system for vehicle project and computing equipment

Country Status (1)

Country Link
CN (1) CN117094674A (en)

Similar Documents

Publication Publication Date Title
US11972272B2 (en) Generation of bots based on observed behavior
CN107341643B (en) Visual process display method and system
US20140172436A1 (en) User Interface for Processing Requests for Approval
US10380528B2 (en) Interactive approach for managing risk and transparency
US20030126001A1 (en) Process for managing requests for work within an organization through a centralized workflow management system
US20190087910A1 (en) Location and social network data predictive analysis system
US20180121236A1 (en) Cloud embedded process tenant system for big data processing
DE202017100386U1 (en) Latency reduction in the feedback-based determination of system performance
CN115344888A (en) Data access method and device, electronic equipment and storage medium
Yang et al. Design of enterprise management system based on edge computing architecture
CN111798196A (en) Agile development management system based on SpringBoot framework
US20150310390A1 (en) Aggregation and workflow engines for managing project information
US20170308974A1 (en) Systems and methods for managing the acquisition and management of sites
CN100412858C (en) Report generating system and method
US20130041712A1 (en) Emerging risk identification process and tool
CN117094674A (en) Resource management method, device and system for vehicle project and computing equipment
US9542171B2 (en) Managing an application modification process
WO2022240539A1 (en) Automated actions based on ranked work events
JP2018060272A (en) Budget management system, budget management method and budget management
CN112862264A (en) Enterprise operation condition analysis method, computer device and computer storage medium
US20200097870A1 (en) Work task commitment manager
US10810640B1 (en) Automated time tracking of events in a calendar and use of the same to generate invoices
JP2017509940A (en) Systems, devices and methods for exchanging and processing data scales and objects
TW200939140A (en) System and method for maintaining and managing facility and equipment using radio frequency identification
US9412083B2 (en) Aggregation and workflow engines for managing project information

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination