CN116954166A - Flow shop production and maintenance joint scheduling method considering plug order disturbance - Google Patents

Flow shop production and maintenance joint scheduling method considering plug order disturbance Download PDF

Info

Publication number
CN116954166A
CN116954166A CN202310641239.6A CN202310641239A CN116954166A CN 116954166 A CN116954166 A CN 116954166A CN 202310641239 A CN202310641239 A CN 202310641239A CN 116954166 A CN116954166 A CN 116954166A
Authority
CN
China
Prior art keywords
maintenance
representing
scheduling
population
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310641239.6A
Other languages
Chinese (zh)
Inventor
李波
张竞一
刘民岷
洪涛
胡家文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of Electronic Science and Technology of China
Original Assignee
University of Electronic Science and Technology of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Electronic Science and Technology of China filed Critical University of Electronic Science and Technology of China
Priority to CN202310641239.6A priority Critical patent/CN116954166A/en
Publication of CN116954166A publication Critical patent/CN116954166A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32252Scheduling production, machining, job shop

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a flow shop production and maintenance joint scheduling method considering plug-in disturbance, and relates to a mixed flow line joint scheduling model optimization solving method and a dynamic scheduling method. According to the invention, disturbance analysis is performed and main disturbance events of a research object are determined aiming at the problem of production scheduling and equipment preventive maintenance integrated optimization in a dynamic scheduling scene, meanwhile, a rolling window technology and rescheduling deviation punishment cost are introduced on the basis of an integrated model to establish a dynamic scheduling basic model, then a rescheduling driving mechanism is formulated, a rescheduling method is determined, and an embedded simulation parallel particle swarm-genetic hybrid algorithm is designed for obtaining a complete rescheduling scheme.

Description

Flow shop production and maintenance joint scheduling method considering plug order disturbance
Technical Field
The invention relates to the field of mixed flow shop preventive maintenance and production joint scheduling, in particular to a mixed flow shop production and preventive maintenance joint dynamic scheduling method considering plug-in disturbance.
Technical Field
The preventive maintenance strategy and the production scheduling strategy of the mixed flow shop are two important factors influencing the production cost, in the traditional production and manufacturing process, production managers usually independently formulate the two strategies and neglect the correlation between the two strategies, so that higher production cost is caused, meanwhile, with the rising of production modes such as customization, multiple varieties, small batches and the like, the disturbance caused by the change of demands in the production process is more and more, such as order withdrawal, emergency bill insertion, change of delivery date and the like, and the static scheduling which only takes a production plan as input is more and more unsuitable for the production environment at present. When the static scheduling scheme is executed, dynamic disturbance occurs, so that the original production and processing plan and the actual production process come in and go out, and if a reasonable disturbance processing strategy is not formulated, the production cost is greatly increased. Therefore, the method has important practical significance for the production and preventive maintenance combined dynamic scheduling research of the mixed flow shop.
At present, the related research of the dynamic scheduling problem is concentrated in the field of pure production scheduling, and the dynamic scheduling research aiming at the production workshop production and preventive maintenance combined scheduling is very rare; meanwhile, the existing dynamic scheduling problem only considers the influence of disturbance on a production scheduling scheme, and neglects the influence on a maintenance plan; in addition, the existing dynamic scheduling strategy usually only formulates a single rescheduling driving mechanism and rescheduling method, thereby resulting in higher dynamic scheduling deviation cost.
Disclosure of Invention
Aiming at the problem of production scheduling and equipment preventive maintenance integrated optimization in a dynamic scheduling scene, the invention provides a mixed flow production line maintenance and production combined dynamic scheduling method considering plug-in disturbance. The method takes the minimum equipment maintenance cost, the total workpiece early and late penalty cost and the dynamic scheduling deviation penalty cost as optimization targets, establishes a mathematical model, and optimizes and solves to obtain a rescheduling scheme after the insertion order disturbance occurs, thereby realizing the maintenance and production combined dynamic scheduling management of the mixed flow shop.
The technical scheme of the invention is a flow shop production and maintenance joint scheduling method considering plug-in disturbance, which comprises the following steps:
step 1: establishing a combined dynamic scheduling basic model of a mixed flow shop;
step 1.1: determining constraint conditions of a combined dynamic scheduling basic model;
step 1.2: performing preventive maintenance modeling, and updating an initial scheduling sequence;
step 1.2.1: let the machine failure rate function obey two-parameter weibull distribution:the machine reliability function is: r (t) =e- (t/η) φ T is 0.ltoreq.t, where t denotes the service life of the plant, provided that +.>In the case of a certain process, i.e. at the time of completion of a certain process, there is +.>The system performs a j-th maintenance shutdown at which point beta j,xy =1,T j =t,n s =n s +1, performing opportunistic maintenance judgment on other devices:
device state factor beta j,xy Indicating equipment E during the jth shutdown maintenance of the system xy Whether maintenance activities are performed or not, wherein 1 represents that maintenance is performed, and 0 represents that maintenance is not performed;
wherein ,represent arbitrary values, phi represents the shape parameter in the Weibull distribution, phi>0, η represents the size parameter in the weibull distribution, η>0,R xy (t) represents the apparatus E xy Reliability function of C xy[l] Represents O xy[l] End time of the process, R pt Representing a preventive maintenance threshold, T j Represents the jth preventive maintenance time of the system, E xy The first step of the process xy stage apparatus, n s Indicating the total shutdown times of the system, wherein the initial value is 0, < ->The working life of the y-th station apparatus in the process x at the time t is represented by R ot Representing a device opportunity maintenance threshold;
step 1.2.2: modeling maintenance effects using virtual service life models, and after the jth shutdown maintenance of the system, based on the equipment status factor beta j,xy After updating the jth maintenance, i.e. t=t j +T m Virtual working years of each equipment at moment, T m Representing the average maintenance time of the device:
①β j,xy =0, i.e. the j-th system maintenance time, equipment E xy No maintenance is performed:
②β j,xy =1, i.e. the j-th system maintenance, equipment E xy And (3) maintaining:
ε x for improving factor of service life, the method is used for describing the reliability change condition of equipment after imperfect maintenance, and the equipment epsilon in the same process x The same and constant value is 0 < epsilon x <1,The y-th station apparatus indicating process x is at T j Service life at moment;
step 1.2.3: after adding the preventive maintenance strategy to the original production schedule, the process start time S is set after each system shutdown maintenance xy[l] And working procedure finishing time C xy[l] Updating:
step 1.2.4: calculating the equipment E in the whole production scheduling period xy Expected number of times of unexpected failure n xy
wherein Representing machine E xy At C mk Age of moment lambda x (t) represents a failure rate function of step x;
step 1.3: constructing a joint dynamic scheduling basic model objective function;
(1) Computing device maintenance Total cost C m
C m =C dm +C pm
wherein ,
wherein ,cus Representing equipment repair costs by considering post-fault repair emergency dispatch costs c s C, representing the preventive maintenance cost of the equipment, taking the preventive maintenance scheduling cost into consideration dm Representing the total cost of post-hoc repair, C pm Represents the total cost of preventive maintenance, m represents the total number of processes, n x Representing the total number of devices, n xy The expected number of unexpected failures of the y-th equipment in the process x is represented, the initial value is 0,representing the equipment overhaul cost of process x, c s Representing a single maintenance schedule charge,/->Indicating the equipment maintenance cost of the process x;
(2) Calculating the total early and late punishment cost C of workpieces ta
wherein ,representing the workpiece J i Is>Representing the workpiece J i Unit stall penalty cost,/->Representing the workpiece J i Unit advance penalty cost, x ixy[l] Representing the workpiece J i Processing the first position of the y-th stage equipment in the process x to be 1, otherwise, processing the first position to be 0;
(3) Calculating a dynamic scheduling deviation punishment cost:
cost of machine offset penalty C ed Refers to the product of the quantity change of the workpiece processed by a rescheduling scheme and an initial scheduling scheme of a certain device and a penalty factor:
equipment maintenance departure penalty cost C md Refers to the product of the preventive maintenance time change and penalty factor of rescheduling scheme and initial scheduling scheme arrangement of a certain device:
thus, the overall weight of the production system deviates from penalty cost C d The method comprises the following steps:
wherein ,machine deviation penalty factor, ED, representing process x xy Representing device E xy The number of changes in the work piece after rescheduling, +.>Maintenance deviation penalty factor representing process x, MD xy Representing device E xy The number of maintenance times changes after rescheduling;
(4) The objective function F is;
F=min(C ta +C m +C d );
step 2: formulating a combined dynamic scheduling strategy of the mixed flow shop;
step 2.1: initializing the length of a scheduling processing window and rescheduling period;
step 2.2: acquiring workpiece processing information;
step 2.3: updating a scheduling processing window;
step 2.4: solving the objective function obtained in the step 1 by adopting a parallel particle swarm-genetic hybrid method;
step 2.5: generating a static scheduling scheme;
step 2.6: executing a dispatch plan;
step 2.7: determine if a rescheduling period is reached? If yes, turning to the step 2.8, and if not, turning to the step 2.9;
step 2.8: determining whether the fitness difference reaches a threshold? If yes, turning to the step 2.3, otherwise, returning to the step 2.7;
step 2.9: determine whether a disturbance has occurred? If yes, performing tail insertion rescheduling, then turning to step 2.8, and if not, turning to step 2.10;
step 2.10: determining whether all work pieces are finished? If yes, the technology is scheduled, and if not, the step 2.6 is performed.
Further, the detailed method of the step 2.4 is as follows:
step 2.4.1: the method adopts a double-chromosome form to represent the feasible solution coding, and divides the population into two sub-populations according to the self-adaptive population distribution factors, wherein one sub-population is updated by using a particle swarm algorithm, one sub-population is updated by using a genetic algorithm, and the self-adaptive population distribution factors have the following calculation formula:
wherein ,di Represents the Euclidean distance of the ith individual, K represents the adaptive population distribution factor, f i ·、 f j represents the fitness value of the ith individual, the fitness value of the jth individual, d avg Represents the average Euclidean distance of the population, d min Representing the minimum value of Euclidean distance in the population, d max Representing the maximum value of Euclidean distance in the population; when the population quantity is N, KN individual components in the population form a sub-population 1 to enter a particle swarm algorithm for updating, and the rest individual components form a sub-population 2 to enter a genetic algorithm for updating;
step 2.4.2: constructing an improved particle swarm algorithm to optimize the sub population 1 in the step 3.1;
step 2.4.3: constructing an improved genetic algorithm to optimize the sub population 2 in the step 3.1;
step 2.4.4: combining the sub population 1 with the sub population 2;
step 2.4.5: judging whether the current population reaches the maximum iteration times, if so, executing the step 3.6, otherwise, continuing the step 3.1;
step 2.4.6: and obtaining the combined rescheduling scheme of the mixed flow shop after the single-plug disturbance.
Further, the detailed method of the step 2.4.2 is as follows:
a1: according to the maintenance threshold combination, calculating the fitness of each particle through the preventive maintenance model simulation established in the step 1.2, and updating the processing starting time and the processing finishing time of each workpiece obtained by decoding;
a2: updating self-adaptive weights;
a3: particle velocity update and position update.
Further, the detailed method of the step 2.4.3 is as follows:
b1: according to the maintenance threshold combination, calculating the fitness of each chromosome through the preventive maintenance model simulation established in the step 1.2, and updating the processing starting time and the processing finishing time of each decoded workpiece;
b2: chromosome selection operations are performed by using a random competition selection mode, and elite retention strategies are introduced;
b3: performing cross operation by using a single-point cross mode;
b4: chromosome mutation operation.
The invention provides a method for joint dynamic scheduling of preventive opportunity maintenance and production in a mixed flow shop taking account of plug-in disturbance, which uses a rolling window technology to statically process a dynamic scheduling process, constructs a mixed rescheduling driving mechanism combining a period and an event, formulates a combined rescheduling method combining complete rescheduling and tail plug-in rescheduling, and designs an embedded simulated parallel type self-adaptive particle swarm-genetic hybrid algorithm for model solving according to model characteristics to realize joint dynamic scheduling of the mixed flow shop.
Drawings
FIG. 1 is a diagram of an example scrolling window division;
FIG. 2 is a flow chart of a hybrid rescheduling driving mechanism;
FIG. 3 is a flow chart of a combined rescheduling method;
FIG. 4 is a flow chart of a hybrid flow shop joint dynamic scheduling;
FIG. 5 is a flow chart of a particle swarm-genetic algorithm of an embedded simulation;
FIG. 6 is a flow chart of a simulation algorithm;
FIG. 7 is a flow chart of a specific embodiment of the method of the present invention.
Detailed Description
The following describes the implementation routine of the present invention in detail (fig. 6), and the implementation routine is implemented on the premise of the technical solution of the present invention, and a detailed implementation and a specific operation procedure are given, but the scope of protection of the present invention is not limited to the implementation routine described below.
The implementation routine can be mainly divided into the following steps:
step 1: model constraints are determined.
(1) In any process, each workpiece can only occupy one machining position of one machine;
wherein ,xixy[l] Representing the workpiece J i Processing the first position of the y-th stage equipment in the process x to be 1, otherwise, processing the first position to be 0, and taking the first position as a decision variable;
(2) In any process, only one workpiece can be processed at any position of any machine;
(3) Standard machining time of the workpiece process corresponding to the first machining position of the y-th machine in the process x;
wherein ,Pxy[l] Represents O xy[l] Standard processing time of the procedure;
(4) The start time of a workpiece in a certain process is not earlier than the finish time of the process immediately before the equipment;
(5) The end time of the workpiece process corresponding to the first processing position of the y-th machine in the process x;
(6) The start time of a workpiece in a certain process is not earlier than the finish time of the workpiece in a previous process;
C xy[l] ≥S xy[l] +p xy[l]
(7) Machine preventative maintenance threshold and opportunity maintenance threshold constraints;
0≤R pt ,R ot ≤1
R pt <R ot
(8) Maximum system completion time;
C mk =max{C my[l] }
(9) Disturbance occurs in the process of production scheduling execution;
wherein ,to Representing the occurrence time of the disturbance;
(10) Process start time constraints when a disturbance occurs. When the workpiece J i When the disturbance occurs during the processing in the x working procedure, the starting time of the next working procedure of the workpiece is not earlier than the maximum value of the ending time of the workpiece on the working procedure and the disturbance occurrence time;
(11) Equipment processing time constraint when disturbance occurs; when equipment E xy When the first task is processed, disturbance occurs, and the starting time of the next processing task of the equipment is not earlier than the maximum value of the finishing time of the current task of the equipment and the disturbance occurrence time;
step 2: when a plug-in disturbance event occurs, the initial scheduling scheme is windowed using a rolling window technique (FIG. 1). And (3) processing the plug-in single disturbance by using a tail plug-in rescheduling method, judging a threshold value of the disturbance degree, if the disturbance degree is smaller than or equal to the threshold value, not processing, and if the disturbance degree is larger than the threshold value, entering a step (4), and performing complete rescheduling on the workpieces in the scheduling processing window in the step (2).
Step 2.1: determining the plug-in disturbance as the main dynamic disturbance of the plug-in disturbance:
disturbance of the production process is generally divided into external factors and internal factors according to sources of the disturbance, wherein the external factors can be divided into two aspects of inherent factors and market factors, and the internal factors can be divided into environment factors, equipment factors and personnel factors;
step 2.2: introducing a rolling window technology, and statically processing the dynamic scheduling problem (figure 1):
first, the process needs to be classified according to its state: a set of processed processes, a set of in-process processes, a set of unprocessed processes, and a set of waiting for scheduling processes; three static scheduling windows are then defined for storing these process sets:
(1) A finishing window for storing a finished set of processes;
(2) A scheduling processing window for storing the processing procedure set and the unprocessed procedure set;
(3) A waiting window for storing a waiting scheduling procedure set;
the initialization of the length of the dispatching processing window can be set according to the production capacity of a processing workshop, the delivery period of the workpiece, the experience of a manager and the like by taking the workpiece or the procedure as a unit; when the scheduling starts, the scheduling processing window firstly takes out the workpiece sets with the number equal to the window set length from the waiting window according to a certain rule, performs static scheduling, and starts to execute the scheduling plan. When the set period is reached or rescheduling is needed due to disturbance, firstly, part of working procedures which are finished in the scheduling processing window are put into the finishing window, then, a part of workpieces are selected from the waiting window according to a certain rule and added into the scheduling processing window, and finally, the working procedures in the scheduling processing window are rescheduled according to a static scheduling method, so that disturbance events occurring in the whole production process can be dynamically absorbed; dynamic scheduling based on a rolling window technology is to repeat the process until all workpieces finish processing;
in order to illustrate the specific use of the rolling window technology, assuming that the production system is disturbed and needs to be rescheduled, dividing an initial scheduling scheme into three static windows according to the principle of the rolling window technology, wherein the window division is shown in fig. 1;
according to the above, the process can be divided into four sets according to the production state of each process at the rescheduling moment, and the specific division is as follows;
(1) Set of processed procedures: {1.1,2.1,3.1,4.1,5.1,6.1 (1),4.2 (1) }
(2) The working procedure is assembled: {6.1 (2),4.2 (2) }
(3) Waiting for a set of scheduling procedures: {7.1,7.2,8.1}
(4) Raw process set: all procedures except the above set
Wherein "1.1" represents the first process of the workpiece 1, and the rest are the same; at the rescheduling time, splitting the finished part and the unfinished part of the working procedure in processing into 2 independent working procedures for scheduling, wherein '4.2 (1)' in the set represents the finished part of the second working procedure of the workpiece 4 at the rescheduling time, and '4.2 (2)' represents the unfinished part in processing, and the rest is the same;
when rescheduling is carried out, firstly, the finished working procedure in the scheduling processing window is put into the finishing window, and then the workpiece is filled in the waiting window and scheduling is carried out;
step 2.3: constructing a hybrid driving mechanism based on disturbance degree threshold judgment (figure 2):
considering that rescheduling is based on a production and maintenance integrated model, and simultaneously relates to two dimensions of production scheduling and equipment maintenance, when a disturbance event occurs in the production process, the production scheduling and the equipment preventive maintenance are interfered, so that a quantitative index of disturbance degree should represent two aspects of influence on the production scheduling and influence on the equipment preventive maintenance at the same time; the influence of disturbance on production scheduling is finally reflected as the change of the delivery time of the workpiece, and the influence on equipment maintenance is finally reflected as the change of the equipment maintenance times and the expected times of unexpected faults, so that the sum of the total early and late punishment cost of the workpiece and the equipment maintenance cost is used as a quantitative index of the disturbance degree; as can be seen from fig. 2, when the set rescheduling period arrives or a dynamic disturbance event occurs, firstly, calculating the difference between the adaptability of the scheduling scheme and the original scheduling scheme, namely the disturbance degree, and comparing the calculated difference with a preset disturbance degree threshold value, if the difference exceeds the threshold value, it indicates that the current system needs rescheduling, and if the difference does not exceed the threshold value, it does not need rescheduling;
step 2.4: a combined rescheduling method (fig. 3) is established in which the full rescheduling method is combined with the tail-inserted rescheduling method:
a combined rescheduling method is designed by using a complete rescheduling method and a tail-inserted rescheduling method. In combination with the hybrid rescheduling driving mechanism based on the disturbance degree threshold judgment proposed in step 2.3, the workflow of the combined rescheduling method designed by the invention is shown in fig. 3.
As can be seen from fig. 3, when a disturbance event occurs, the disturbance is processed by a tail-inserted rescheduling method, then the difference between the adaptation degree before and after rescheduling is calculated and compared with a preset threshold value, if the difference between the adaptation degree is greater than the threshold value, the complete rescheduling is performed, otherwise, a tail-inserted rescheduling scheme is used as a rescheduling result; when the rescheduling period arrives, calculating the final fitness according to the execution condition of the current scheduling scheme, comparing the difference value between the final fitness and the fitness of the last complete rescheduling scheme with a threshold value, and if the final fitness is larger than the threshold value, performing complete rescheduling, otherwise, not performing rescheduling operation;
step 2.5: combining the step 2.3 with the step 2.4 to obtain a combined dynamic scheduling overall flow of the mixed flow shop; (fig. 4) step 3: and constructing an embedded simulated parallel particle swarm-genetic algorithm optimization solution (figure 5).
Step 3.1: initializing a maintenance threshold combination according to the model constraint determined in the step 1;
step 3.2: initializing a scheduling scheme population according to the model constraint determined in the step 1;
step 3.3: dividing a population into two sub-populations, wherein one sub-population is updated by using a particle swarm algorithm, one sub-population is updated by using a genetic algorithm, and in order to improve the local searching capability of the algorithm when the populations are scattered and the global searching capability of the algorithm when the populations are concentrated, the self-adaptive allocation factors are adopted for carrying out population division:
when the population quantity is N, KN individuals in the population enter a particle swarm algorithm for updating, and the rest individuals enter a genetic algorithm for updating.
Step 3.4: iterative sub-population 1 using an improved particle swarm algorithm;
step 3.4.1: calculating fitness of each particle by simulation (fig. 6);
(1) When (when)There is->The system performs the j-th maintenance shutdown and recordsT j =t,n s =n s +1, performing opportunistic maintenance judgment on other devices:
device state factor beta j,xy Indicating equipment E during the jth shutdown maintenance of the system xy Whether maintenance activities are performed.
(2) After the jth shutdown maintenance is carried out on the system, the system is controlled according to the equipment state factor beta j,xy Update jth post-maintenance t=t+t m Service life of the time equipment:
①β j,xy =0, i.e. the j-th system maintenance time, equipment E xy No maintenance is performed:
②β j,xy =1, i.e. the j-th system maintenance, equipment E xy And (3) maintaining:
ε x for improving factor of service life, the method is used for describing the reliability change condition of equipment after imperfect maintenance, and the equipment epsilon in the same process x The same and constant value is 0 < epsilon x <1。
(3) Start machining time S xy[l] And finishing time C xy[l] Updating:
(4) Equipment E xy Unexpected failure occursDesired number of times:
wherein Representing machine E xy At C mk Age of moment.
(5) Calculating a total cost of maintenance of the machine C m
C m =C dm +C pm
wherein :
(6) Calculating the total early and late punishment cost C of workpieces ta
wherein :
(7) Calculating dynamic scheduling deviation penalty cost C d
The machine deviation punishment cost refers to the product of the quantity change of the workpiece processed by a rescheduling scheme and an initial scheduling scheme of a certain equipment and a punishment factor:
the equipment maintenance deviation penalty cost refers to the product of the preventative maintenance frequency change and penalty factor of a certain equipment rescheduling scheme and an initial scheduling scheme arrangement:
thus, the total weight adjustment deviation penalty cost of the production system can be expressed as:
wherein ,machine deviation penalty factor, ED, representing process x xy Representing device E xy The number of changes in the work piece after rescheduling, +.>Maintenance deviation penalty factor representing process x, MD xy Representing device E xy The number of maintenance times changes after rescheduling;
(8) Calculating the fitness f:
f=C ta +C m +C d
step 3.4.2: updating omega by adopting a nonlinear dynamic inertia weight coefficient formula:
step 3.4.3: particle velocity update, position update:
x id (t+1)=x id (t)+v id (t+1)
step 4.4.4: because the particle swarm algorithm aims at continuous variables, real numbers are generated in the searching process, and illegal solutions are often brought at the same time, updated particles need to be adjusted after the primary optimizing operation is finished so as to correct the illegal solutions:
(1) Rounding down each code
(2) Removing still illegal solutions in coding
(3) Randomly generating chromosomes according to coding rules to complement the solutions removed in (2)
Step 3.5: iterative sub-population 2 using an improved genetic algorithm;
step 3.5.1: the fitness of each chromosome is calculated through simulation, and the calculation method is the same as that of the step 4.4.1;
step 3.5.2: selecting by using a random competition selection mode, so that the probability of reserving chromosomes with larger fitness is larger, randomly selecting a certain number of chromosomes as new father, and simultaneously introducing elite reservation strategy to enable a certain number of high-quality solutions to directly enter the next generation so as to accelerate the convergence rate of the algorithm;
step 3.5.3: the interleaving is performed using a single point interleaving approach, as the encoding herein requires certain constraints to be maintained: the first dimension code indicates that the value of each element required to be met by the processing equipment code selected by the workpiece in each process is not more than the number of the process equipment where the element is located, and the second dimension code indicates that the value of each element required to be met by the processing sequence code of the workpiece in each process has uniqueness in the column where the element is located. Therefore, the first dimension code randomly selects a longitudinal crossing mode and a transverse crossing mode to perform single-point crossing operation, and the second dimension code performs single-point crossing operation in the longitudinal crossing mode;
step 3.5.4: two gene exchange sequences were randomly selected to achieve the effect of variation. The constraint condition of the codes can prove that the first dimension codes can only carry out line genetic variation, and the second dimension codes can carry out variation in rows and columns;
step 3.6: fusing the population 1 with the population 2, judging whether the current population meets the termination condition, if not, continuing the step 4.3, otherwise, stopping iteration;
step 3.7: the full rescheduling scheme is output.

Claims (4)

1. A flow shop production and maintenance joint scheduling method considering insertion order disturbance comprises the following steps:
step 1: establishing a combined dynamic scheduling basic model of a mixed flow shop;
step 1.1: determining constraint conditions of a combined dynamic scheduling basic model;
step 1.2: performing preventive maintenance modeling, and updating an initial scheduling sequence;
step 1.2.1: let the machine failure rate function obey two-parameter weibull distribution:the machine reliability function is: />T is 0.ltoreq.t, where t denotes the service life of the plant, provided that +.>In the case of a certain process, i.e. at the time of completion of a certain process, there is +.>The system performs a j-th maintenance shutdown at which point beta j,xy =1,T j =t,n s =n s +1, performing opportunistic maintenance judgment on other devices:
device state factor beta j,xy Indicating equipment E during the jth shutdown maintenance of the system xy Whether maintenance activities are performed or not, wherein 1 represents that maintenance is performed, and 0 represents that maintenance is not performed;
wherein ,represent arbitrary values, phi represents the shape parameter in the Weibull distribution, phi>0, η represents the size parameter in the weibull distribution, η>0,R xy (t) represents the apparatus E xy Reliability function of C xy[l] Represents O xy[l] End time of the process, R pt Representing a preventive maintenance threshold, T j Represents the jth preventive maintenance time of the system, E xy Y-th stage apparatus for indicating process x, n s Indicating the total shutdown times of the system, wherein the initial value is 0, < ->The working life of the y-th station apparatus in the process x at the time t is represented by R ot Representing a device opportunity maintenance threshold;
step 1.2.2: modeling maintenance effects using virtual service life models, and after the jth shutdown maintenance of the system, based on the equipment status factor beta j,xy After updating the jth maintenance, i.e. t=t j +T m Virtual working years of each equipment at moment, T m Representing the average maintenance time of the device:
①β j,xy =0, i.e. the j-th system maintenance time, equipment E xy No maintenance is performed:
②β j,xy =1, i.e. the j-th system maintenance, equipment E xy And (3) maintaining:
ε x for improving factor of service life, the method is used for describing the reliability change condition of equipment after imperfect maintenance, and the equipment epsilon in the same process x The same and constant value is 0 < epsilon x <1,The y-th station apparatus indicating process x is at T j Service life at moment;
step 1.2.3: after adding the preventive maintenance strategy to the original production schedule, the process start time S is set after each system shutdown maintenance xy[l] And working procedure finishing time C xy[l] Updating:
step 1.2.4: calculating the equipment E in the whole production scheduling period xy Expected number of times of unexpected failure n xy
wherein Representing machine E xy At C mk Age of moment lambda x (t) represents a failure rate function of step x;
step 1.3: constructing a joint dynamic scheduling basic model objective function;
(1) Computing device maintenance Total cost C m
C m =C dm +C pm
wherein ,
wherein ,cus Representing equipment repair costs by considering post-fault repair emergency dispatch costs c s C, representing the preventive maintenance cost of the equipment, taking the preventive maintenance scheduling cost into consideration dm Representing the total cost of post-hoc repair, C pm Represents the total cost of preventive maintenance, m represents the total number of processes, n x Representing the total number of devices, n xy The expected number of unexpected failures of the y-th equipment in the process x is represented, the initial value is 0,representing the equipment overhaul cost of process x, c s Representing a single maintenance schedule charge,/->Indicating the equipment maintenance cost of the process x;
(2) Calculating the total early and late punishment cost C of workpieces ta
wherein ,representing the workpiece J i Is>Representing the workpiece J i Unit stall penalty cost,/->Representing the workpiece J i Unit advance penalty cost, x ixy[l] Representing the workpiece J i Processing the first position of the y-th stage equipment in the process x to be 1, otherwise, processing the first position to be 0;
(3) Calculating a dynamic scheduling deviation punishment cost:
cost of machine offset penalty C ed Refers to the product of the quantity change of the workpiece processed by a rescheduling scheme and an initial scheduling scheme of a certain device and a penalty factor:
equipment maintenance departure penalty cost C md Refers to the product of the preventive maintenance time change and penalty factor of rescheduling scheme and initial scheduling scheme arrangement of a certain device:
thus, the overall weight of the production system deviates from penalty cost C d The method comprises the following steps:
wherein ,machine deviation penalty factor, ED, representing process x xy Representing device E xy The number of changes in the work piece after rescheduling, +.>Maintenance deviation penalty factor representing process x, MD xy Representing device E xy The number of maintenance times changes after rescheduling;
(4) The objective function F is;
F=min(C ta +C m +C d );
step 2: formulating a combined dynamic scheduling strategy of the mixed flow shop;
step 2.1: initializing the length of a scheduling processing window and rescheduling period;
step 2.2: acquiring workpiece processing information;
step 2.3: updating a scheduling processing window;
step 2.4: solving the objective function obtained in the step 1 by adopting a parallel particle swarm-genetic hybrid method;
step 2.5: generating a static scheduling scheme;
step 2.6: executing a dispatch plan;
step 2.7: determine if a rescheduling period is reached? If yes, turning to the step 2.8, and if not, turning to the step 2.9;
step 2.8: determining whether the fitness difference reaches a threshold? If yes, turning to the step 2.3, otherwise, returning to the step 2.7;
step 2.9: determine whether a disturbance has occurred? If yes, performing tail insertion rescheduling, then turning to step 2.8, and if not, turning to step 2.10;
step 2.10: determining whether all work pieces are finished? If yes, the technology is scheduled, and if not, the step 2.6 is performed.
2. The flow shop production and maintenance joint scheduling method considering plug-in disturbance according to claim 1, wherein the detailed method of step 2.4 is as follows:
step 2.4.1: the method adopts a double-chromosome form to represent the feasible solution coding, and divides the population into two sub-populations according to the self-adaptive population distribution factors, wherein one sub-population is updated by using a particle swarm algorithm, one sub-population is updated by using a genetic algorithm, and the self-adaptive population distribution factors have the following calculation formula:
wherein ,di Represents the Euclidean distance of the ith individual, K represents the adaptive population distribution factor, f i 、f j Indicating the fitness value of the ith individual, the fitness value of the jth individual, d avg Represents the average Euclidean distance of the population, d min Representing the minimum value of Euclidean distance in the population, d max Representing the maximum value of Euclidean distance in the population; when the population quantity is N, KN individual components in the population form a sub-population 1 to enter a particle swarm algorithm for updating, and the rest individual components form a sub-population 2 to enter a genetic algorithm for updating;
step 2.4.2: constructing an improved particle swarm algorithm to optimize the sub population 1 in the step 3.1;
step 2.4.3: constructing an improved genetic algorithm to optimize the sub population 2 in the step 3.1;
step 2.4.4: combining the sub population 1 with the sub population 2;
step 2.4.5: judging whether the current population reaches the maximum iteration times, if so, executing the step 3.6, otherwise, continuing the step 3.1;
step 2.4.6: and obtaining the combined rescheduling scheme of the mixed flow shop after the single-plug disturbance.
3. The flow shop production and maintenance joint scheduling method considering the insert disturbance according to claim 2, wherein the detailed method of step 2.4.2 is as follows:
a1: according to the maintenance threshold combination, calculating the fitness of each particle through the preventive maintenance model simulation established in the step 1.2, and updating the processing starting time and the processing finishing time of each workpiece obtained by decoding;
a2: updating self-adaptive weights;
a3: particle velocity update and position update.
4. The flow shop production and maintenance joint scheduling method considering plug-in disturbance according to claim 2, wherein the detailed method of step 2.4.3 is as follows:
b1: according to the maintenance threshold combination, calculating the fitness of each chromosome through the preventive maintenance model simulation established in the step 1.2, and updating the processing starting time and the processing finishing time of each decoded workpiece;
b2: chromosome selection operations are performed by using a random competition selection mode, and elite retention strategies are introduced;
b3: performing cross operation by using a single-point cross mode;
b4: chromosome mutation operation.
CN202310641239.6A 2023-06-01 2023-06-01 Flow shop production and maintenance joint scheduling method considering plug order disturbance Pending CN116954166A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310641239.6A CN116954166A (en) 2023-06-01 2023-06-01 Flow shop production and maintenance joint scheduling method considering plug order disturbance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310641239.6A CN116954166A (en) 2023-06-01 2023-06-01 Flow shop production and maintenance joint scheduling method considering plug order disturbance

Publications (1)

Publication Number Publication Date
CN116954166A true CN116954166A (en) 2023-10-27

Family

ID=88451838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310641239.6A Pending CN116954166A (en) 2023-06-01 2023-06-01 Flow shop production and maintenance joint scheduling method considering plug order disturbance

Country Status (1)

Country Link
CN (1) CN116954166A (en)

Similar Documents

Publication Publication Date Title
CN109359884B (en) Aviation complex equipment structural member workshop operation planning and rescheduling method
CN109636011B (en) Multi-shift planning and scheduling method based on improved variable neighborhood genetic algorithm
CN110221585B (en) Energy-saving scheduling control method for mixed flow shop considering equipment maintenance
CN112001618B (en) Method for integrating and optimizing construction period assignment, order acceptance and production scheduling
CN111966049B (en) Scheduling control method for production equipment of mixed flow shop
CN104268722A (en) Dynamic flexible job-shop scheduling method based on multi-objective evolutionary algorithm
CN115600774B (en) Multi-target production scheduling optimization method for assembly type building component production line
CN111144710B (en) Construction and dynamic scheduling method of sustainable hybrid flow shop
CN110956371A (en) Green scheduling optimization method for intelligent manufacturing workshop facing complex man-machine coupling
CN113592319A (en) INSGA-II-based flexible job shop scheduling method and device under complex constraint
Lei Scheduling fuzzy job shop with preventive maintenance through swarm-based neighborhood search
CN114881504B (en) Electronic precision part full-automatic flexible production line scheduling method based on order selection
CN111210125B (en) Multi-target workpiece batch scheduling method and device based on historical information guidance
CN111814359B (en) Discrete manufacturing-oriented integrated workshop scheduling and assembly sequence planning method
Lü et al. Multiproduct and multistage integrated production planning model and algorithm based on an available production capacity network
CN111985841B (en) Injection workshop scheduling method and system based on improved genetic algorithm
CN110705844B (en) Robust optimization method for job shop scheduling scheme based on non-forced idle time
CN116954166A (en) Flow shop production and maintenance joint scheduling method considering plug order disturbance
CN115310832A (en) Multi-population optimization algorithm double-resource constraint flexible job shop scheduling method and device
Bouddou et al. Solving Bid-Based Dynamic Economic Dispatch in Competitive Electricity Market Using Improved Simulated Annealing Algorithm.
Esquivel et al. Parameter settings and representations in Pareto-based optimization for job shop scheduling
CN114676987A (en) Intelligent flexible job shop active scheduling method based on hyper-heuristic algorithm
CN115456268A (en) Guide roller manufacturing resource optimal allocation method, device, equipment and medium
CN115204619A (en) Flexible workshop scheduling method, device and system based on improved genetic algorithm decoding
Jain et al. An approach for optimisation of flexible flow shop group scheduling with sequence dependent set-up time and preventive maintenance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination