CN116796961A - Engineering project management method, equipment and computer readable storage medium - Google Patents

Engineering project management method, equipment and computer readable storage medium Download PDF

Info

Publication number
CN116796961A
CN116796961A CN202310651275.0A CN202310651275A CN116796961A CN 116796961 A CN116796961 A CN 116796961A CN 202310651275 A CN202310651275 A CN 202310651275A CN 116796961 A CN116796961 A CN 116796961A
Authority
CN
China
Prior art keywords
construction
sub
project
time period
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310651275.0A
Other languages
Chinese (zh)
Inventor
谷明静
刘连康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liancheng Technology Hebei Co ltd
Original Assignee
Liancheng Technology Hebei Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liancheng Technology Hebei Co ltd filed Critical Liancheng Technology Hebei Co ltd
Priority to CN202310651275.0A priority Critical patent/CN116796961A/en
Publication of CN116796961A publication Critical patent/CN116796961A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to an engineering project management method, equipment and a computer readable storage medium, belonging to the technical field of computers, wherein the method comprises the following steps: dividing the project construction plan into a plurality of sub-project construction plans arranged in a sub-project node flow according to the project type and a preset construction plan division model; the sub-engineering construction plan comprises a sub-engineering construction time period; acquiring construction condition information and construction influence factors according to a sub-engineering construction time period of a target sub-engineering; calculating a first construction progress deviation of the target sub-project according to construction condition information, construction influence factors, preset construction progress deviation calculation rules and a sub-project construction plan corresponding to the target sub-project, generating a visual progress report according to the first construction progress deviation, and sending the visual progress report to a management terminal corresponding to the project to be managed. The application has the effects of facilitating management personnel to control the engineering progress integrally and reducing the occurrence of engineering delay.

Description

Engineering project management method, equipment and computer readable storage medium
Technical Field
The present application relates to the field of computer technologies, and in particular, to a method and apparatus for engineering project management, and a computer readable storage medium.
Background
The project is a project using project construction as a carrier, and is a one-time project construction task as a managed object. The method takes a building or a structure as a target output, needs to pay a certain cost, is completed in a certain time according to a certain program, and meets the quality requirement.
Along with development of engineering projects, real-time construction period progress of engineering can only be controlled by construction parties, but because different construction parts are generally responsible for different construction parties in engineering, and influence of subjective factors of different construction parts, external environment and the like easily causes influence of engineering delay and the like, management personnel are inconvenient to control the engineering progress integrally.
Disclosure of Invention
In order to facilitate management personnel to control the engineering progress integrally and reduce the occurrence of engineering delay, the application provides an engineering project management method, equipment and a computer readable storage medium.
In a first aspect, the present application provides a method for managing engineering projects, which adopts the following technical scheme:
an engineering project management method, comprising:
acquiring project information of a project to be managed; the project information comprises a project type and a project construction plan;
Dividing the project construction plan into a plurality of sub-project construction plans arranged in a sub-project node flow according to the project type and a preset construction plan division model; the sub-engineering construction plan comprises a sub-engineering construction time period;
acquiring construction condition information according to a sub-engineering construction time period of a target sub-engineering; the target sub-project is a sub-project to be implemented currently; the construction condition information comprises environment information, personnel information and material information;
acquiring construction influence factors of a target sub-project; the construction influence factors are any one or more of environmental factors, personnel factors and material factors;
calculating a first construction progress deviation of a target sub-project according to the construction condition information, the construction influence factors, a preset construction progress deviation calculation rule and a sub-project construction plan corresponding to the target sub-project;
and generating a visual progress report according to the first construction progress deviation, and sending the visual progress report to a management terminal corresponding to the project to be managed.
By adopting the technical scheme, the project to be managed is divided into a plurality of sub-projects, before each sub-project is constructed, construction influence factors of the sub-projects are analyzed, construction progress influence factors of the sub-projects are analyzed, accordingly construction progress deviation of the sub-projects and construction progress in a sub-project construction plan is predicted, the construction time period of the whole project to be managed can be calculated according to the construction progress deviation of the sub-projects, a visual progress report about the construction progress is generated, and the visual progress report is sent to a management terminal, so that management staff can conveniently and timely adjust the project construction plan according to the visual progress report, control over the project progress is achieved, and the condition of project delay is reduced.
Optionally, the obtaining the construction condition information according to the sub-engineering construction time period of the target sub-engineering includes:
determining a first time period according to the sub-engineering construction time period and a preset time period selection rule; the first time period is located before the sub-engineering construction time period;
collecting the environment information of the target sub-engineering in the first time period; the environment information comprises temperature information, humidity information and bad weather day information;
predicting the environmental information of the sub-project construction time period corresponding to the target sub-project based on the environmental information of the first time period, the sub-project construction plan of the target sub-project and the environmental information of the historical year;
before the sub-engineering construction time period, acquiring personnel information and material information uploaded by a responsible person at a management terminal; the personnel information comprises the number of constructors, the age of the constructors and the technical grade of the constructors; the material information is construction material type and corresponding supply time and supply amount of each construction material type.
By adopting the technical scheme, the environment information, the personnel information, the material information and the like are acquired before the sub-engineering construction time period corresponding to the target sub-engineering, the sub-engineering construction progress of the target sub-engineering is analyzed by utilizing the environment information, the personnel information, the material information and the like, and the analyzed target sub-engineering construction progress is compared with the sub-engineering construction progress of the sub-engineering construction plan, so that the construction progress deviation can be predicted in advance, and the target sub-engineering construction plan can be adjusted according to the construction progress deviation.
Optionally, the temperature information includes average temperature and temperature variation trend, and the humidity information includes average humidity and humidity variation trend; the sub-engineering construction plan comprises a construction area; the predicting the environment information of the sub-project corresponding to the sub-project construction time period based on the environment information of the first time period, the sub-project construction plan of the target sub-project and the environment information of the historical year includes:
acquiring temperature information, humidity information and bad weather day information of the history year of the construction area;
taking a time period with the same historical year as the first time period as a node;
searching temperature information of a second time period which is most similar to the temperature information of the first time period in time periods before and after the node according to the length of the first time period;
adding the time period difference value of the first time period and the second time period and the sub-engineering construction time period to obtain a first target time period;
taking the temperature information of the first target time period as the temperature information of the sub-engineering construction time period corresponding to the target sub-engineering;
according to the length of the first time period, searching humidity information of a third time period which is most similar to the humidity information of the first time period in time periods before and after the node;
Adding the time period difference value of the first time period and the third time period and the sub-engineering construction time period to obtain a second target time period;
taking the humidity information of the second target time period as the humidity information of the sub-engineering construction time period corresponding to the target sub-engineering;
searching severe weather day information of a fourth time period which is most similar to the severe weather day information of the first time period in the time period before and after the node according to the length of the first time;
adding the time period difference value of the first time period and the fourth time period and the sub-engineering construction time period to obtain a third target time period;
and taking the bad weather day information of the third target time period as the bad weather day information of the target sub-project corresponding to the sub-project construction time period.
By adopting the technical scheme, the temperature information, the humidity information and the bad weather day information of the target sub-project are predicted by adopting the historical environment information, so that the influence of the environment information on the progress of the target sub-project can be analyzed, a manager can conveniently adjust the sub-project construction target of the sub-project, and the possibility of delay of the whole project to be managed is reduced.
Optionally, the acquiring the environmental information according to the sub-engineering construction time period of the target sub-engineering includes:
inputting the sub-engineering construction time period into a preset environment prediction model, and analyzing the environment information of the sub-engineering construction time period corresponding to the target sub-engineering; the preset environment prediction model is obtained through training of temperature information, humidity information and severe weather day information in the same time period in the historical years.
Through adopting above-mentioned technical scheme, through presetting the machine learning algorithm and training the relation between the two, make the temperature information, humidity information and the bad weather day information of the different time slots of prediction more accurate.
Optionally, the sub-engineering construction plan includes a construction name, and the obtaining the construction influencing factors of the target sub-engineering includes:
and inputting the construction name, the construction area and the sub-engineering construction time period of the target sub-engineering into a preset construction influence factor model to obtain the construction influence factor of the target sub-engineering.
Optionally, the calculating the first construction progress deviation of the target sub-project according to the construction condition information, the construction influencing factor, the preset construction progress deviation calculation rule and the sub-project construction plan corresponding to the target sub-project includes:
Determining condition information to be analyzed in the construction condition information according to the construction influence factors;
if the condition information to be analyzed comprises environmental information, searching a plurality of sub-engineering information similar to the environmental information in a historical database;
determining at least one first sub-engineering information among the plurality of sub-engineering information based on the construction area and the construction name;
if a plurality of first sub-project information exists, taking a first sub-project of which the construction time period is closest to the sub-project construction time period of the target sub-project as a reference sub-project;
taking the environmental influence construction progress deviation of the reference sub-project as a first construction progress deviation of the target sub-project;
if the condition information to be analyzed comprises personnel information, comparing the age of the constructor of the target sub-project with a preset age interval to obtain an age interval corresponding to the constructor;
searching engineering quantities corresponding to the age interval and the technical grade in a preset stored engineering scale according to the age interval and the technical grade corresponding to constructors;
calculating the daily work quantity of the target sub-project according to the engineering quantity corresponding to the age interval and the technical grade and the number of constructors corresponding to each work quantity;
Analyzing a first construction progress deviation of a target sub-project according to the daily work quantity and the sub-project construction plan;
if the condition information to be analyzed comprises material information, judging whether the corresponding supply time and supply quantity of each construction material type are met according to the sub-construction plan;
if the first construction progress deviation is not satisfied, analyzing the first construction progress deviation of the target sub-project according to the difference value of the supply time and the supply quantity.
By adopting the technical scheme, the construction progress influence analysis is carried out on the environmental information, the personnel information and the material information in advance before the target sub-engineering construction, so that reliable data is provided for the subsequent sub-engineering construction progress analysis of the target sub-engineering. Before each sub-engineering is constructed, construction influence factors are analyzed in advance, so that management staff can know the construction conditions of the sub-engineering in advance, and the management staff can adjust construction plans such as staff, materials, progress and the like according to the construction conditions.
Optionally, the generating a visual progress report according to the first construction progress deviation includes:
building a BIM building model of the project to be managed according to the project construction plan;
Marking sub-engineering labels corresponding to the sub-engineering in one-to-one correspondence in the BIM building model according to the construction nodes of the sub-engineering;
updating at least one sub-engineering construction time period of sub-engineering node flow arrangement of an actual work after the target sub-engineering according to the first construction progress deviation;
controlling corresponding positions in the BIM building model according to the sub-engineering labels to display sub-engineering construction time periods of each sub-engineering, updated sub-engineering construction time periods and construction influence factors;
and generating a visual progress report according to the sub-project construction time period of each sub-project, the updated sub-project construction time period and the construction influence factor BIM building model.
By adopting the technical scheme, the information such as the predicted construction condition information, the influence factor information, the sub-engineering construction time period of each sub-engineering, the updated sub-engineering construction time period and the like is displayed in the BIM building model. When the construction progress delay is analyzed according to the first construction progress deviation, a visual progress report is generated according to the updated BIM building model, and the visual progress report is sent to a management terminal used by a manager, so that the manager can conveniently check information such as construction progress change conditions of the project to be managed.
Optionally, in the actual construction process of the target sub-engineering, acquiring construction detection information and sub-engineering plan adjustment information; the construction detection information comprises construction workload; the sub-engineering plan adjustment information is a sub-engineering construction plan adjusted by a manager according to the first construction deviation;
comparing the construction workload with the corresponding construction completion amount in the sub-engineering construction plan to obtain a second construction deviation;
calculating at least one sub-engineering construction time period of the sub-engineering node flow arrangement of the actual work after the target sub-engineering according to the second construction deviation and the first construction deviation, and recording the at least one sub-engineering construction time period as an adjustment time period;
and controlling the corresponding position in the BIM building model to display the sub-project plan adjustment information and the adjustment time period of each sub-project according to the sub-project label.
By adopting the technical scheme, real-time tracking is carried out according to the sub-engineering construction plans corresponding to each sub-engineering in the actual construction process of the sub-engineering, meanwhile, the result progress and the like of the execution stage are periodically collected and recorded into the BIM model, the actual construction progress of the target sub-engineering, sub-engineering plan adjustment information and the adjustment time period for adjusting the follow-up sub-engineering according to the actual construction progress are timely updated, and management staff can be helped to timely master the current situation and the actual construction progress of the engineering construction site.
In a second aspect, the present application provides an electronic device, which adopts the following technical scheme:
an electronic device comprising a memory and a processor, the memory having stored thereon a computer program capable of being loaded by the processor and executing the method for integrated management of engineering projects according to any one of the first aspects.
In a third aspect, the present application provides a computer readable storage medium, which adopts the following technical scheme:
a computer-readable storage medium storing a computer program capable of being loaded by a processor and executing the engineering project management method of any one of the first aspects.
Drawings
FIG. 1 is a flow chart of an integrated project management method according to an embodiment of the present application.
Fig. 2 is a schematic flow chart of steps S31 to S41 according to an embodiment of the application.
Fig. 3 is a schematic flow chart of steps S51 to S61 according to an embodiment of the present application.
Fig. 4 is a block diagram of an electronic device according to an embodiment of the present application.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present application more apparent, the technical solutions of the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present application, and it is apparent that the described embodiments are some embodiments of the present application, but not all embodiments of the present application. All other embodiments, which can be made by those skilled in the art based on the embodiments of the application without making any inventive effort, are intended to be within the scope of the application.
In addition, the term "and/or" herein is merely an association relationship describing an association object, and means that three relationships may exist, for example, a and/or B may mean: a exists alone, A and B exist together, and B exists alone. In this context, unless otherwise specified, the term "/" generally indicates that the associated object is an "or" relationship.
The embodiment of the application provides an engineering project management method, which is executed by electronic equipment, wherein the electronic equipment can be a server or terminal equipment, and the server can be an independent physical server, a server cluster or a distributed system formed by a plurality of physical servers or a cloud server for providing cloud computing service; the terminal device may be, but is not limited to, a smart phone, a tablet computer, a desktop computer, etc.
The following describes the working example of the application in further detail with reference to the accompanying drawings, and as shown in the drawings, the main flow of the method is described as follows (steps S1 to S6):
step S1, acquiring project information of a project to be managed; the project information comprises a project type and a project construction plan;
In one embodiment, the engineering types are classified into industrial construction engineering, civil construction engineering, individual earth and stone engineering, pile foundation engineering and decoration engineering according to engineering categories; according to the size of the scale, the large-scale building engineering is divided into a large-scale building engineering and a large-scale building engineering; the floor is divided into a bottom layer building, a multi-layer building, a middle-high-rise building, a high-rise building and an ultra-high-rise building according to the number of layers. In addition, the engineering types can be divided according to different stages and different layers of engineering construction, and the engineering of the same construction stage or construction level is divided into one engineering type.
The engineering project construction plan is the engineering content required by engineering, namely the type of required mechanical equipment, the type of materials, the manpower condition, the corresponding engineering progress and the like.
S2, dividing the project construction plan into a plurality of sub-project construction plans arranged in a sub-project node flow according to the project type and a preset construction plan division model; the sub-engineering construction plan comprises a sub-engineering construction time period;
in one embodiment, different project types correspond to different sub-project division modes, a corresponding construction plan division model is selected according to the project types, the project to be managed is divided into a plurality of sub-projects according to different construction stages through the construction plan division model, each sub-project corresponds to a sub-project construction plan, and the sub-project construction plan comprises information such as a sub-project construction time period, a construction name, a construction area and the like. The project construction plan is divided into a plurality of sub-project construction plans arranged in a sub-project node flow according to each sub-project construction time period.
In the embodiment of the present application, the construction node is set at the end of each sub-project, that is, the construction node is the end part of one sub-project, and each construction node is provided with a construction name. And a manager can conveniently check the sub-construction plan information of the sub-project.
S3, acquiring construction condition information according to a sub-engineering construction time period of the target sub-engineering; the target sub-project is a sub-project to be implemented currently; the construction condition information comprises environment information, personnel information and material information;
in one embodiment, for example, the project to be managed is divided into 6 sub-projects, and the sub-projects are respectively sub-project 1, sub-project 2, sub-project 3, sub-project 4, sub-project 5 and sub-project 6 according to the construction flow, and after the sub-project 1 is constructed, the sub-project 2 is prepared for construction, and then the sub-project 2 is the target sub-project.
The construction condition information obtained from the sub-project construction time period of the target sub-project will be specifically described below.
Firstly, determining a first time period according to the sub-engineering construction time period and a preset time period selection rule; the first time period is located before the sub-engineering construction time period; for example, the sub-engineering construction period is from 4 months 15 days to 4 months 25 days, and then from 4 months 4 days to 4 months 14 days may be taken as the first period, and the first period is adjacent to the sub-engineering construction period corresponding to the target sub-engineering.
Then, collecting the environment information of the target sub-engineering in the first time period; the environment information comprises temperature information, humidity information and bad weather day information; the temperature information comprises average temperature and temperature change trend, the humidity information comprises average humidity and humidity change trend, and the bad days comprise rainy days, snowy days, typhoons and other days with influence on the construction progress. The electronic device may collect weather forecast information within a first time period within an area where the target sub-project is located according to the area.
Then, predicting the environment information of the sub-project corresponding to the sub-project construction time period of the target sub-project based on the environment information of the first time period, the sub-project construction plan of the target sub-project and the environment information of the historical year; by predicting the environment information of the sub-engineering construction time period of the target sub-engineering construction, the manager can know the weather environment and other conditions of the construction time period in time, and the manager can manage the sub-engineering construction time period in time.
Finally, before the sub-engineering construction time period, acquiring personnel information and material information uploaded by a responsible person at a management terminal; the personnel information comprises the number of constructors, the age of the constructors and the technical grade of the constructors; the material information is construction material type and corresponding supply time and supply amount of each construction material type. For example, in the first period of time, personnel information and material information are transmitted to the electronic device through the management terminal by the responsible person of the target sub-project.
By acquiring environmental information, personnel information, material information and the like before the sub-project construction time period corresponding to the target sub-project, analyzing the sub-project construction progress of the target sub-project by utilizing the environmental information, the personnel information, the material information and the like, and comparing the analyzed target sub-project construction progress with the construction progress of the sub-project construction plan, the construction progress deviation can be predicted in advance, so that the target sub-project construction plan can be adjusted according to the construction progress deviation.
As shown in fig. 2, as an embodiment of predicting the environmental information of the sub-project construction period corresponding to the target sub-project based on the environmental information of the first period, the sub-project construction plan of the target sub-project, and the environmental information of the history year, steps S31 to S41 are included:
step S31, acquiring temperature information, humidity information and severe weather day information of the historical year of the construction area; the temperature information includes an average temperature and a temperature variation trend, and the humidity information includes an average humidity and a humidity variation trend. The temperature information is used for explaining, the average temperature is the average temperature in the first time period, and the temperature change trend is the curve trend that the average temperature of every day is compared and is presented, and the temperature change trend includes stable gentle trend, stable rising trend, sharp falling trend and the like. It should be noted that, when the rapid increasing trend is that some time nodes in the current time period are stable trends, one or more time nodes suddenly rise; and when the rapid descending trend is that some time nodes in the current time period are stable trends, one or more time nodes suddenly descend.
Step S32, taking a time period with the same historical year as the first time period as a node;
in one embodiment, the temperature information, the humidity information and the bad day information of the whole year are recorded in real time, the same time period as the first time period in each historical year is taken as a time node in each historical year, for example, the time period from 4 months 15 days to 4 months 30 days in 2023 is taken as the first time period, the time period from 5 months 1 day to 5 months 15 artificial sub-engineering construction time period, and then the time period from 4 months 15 days to 4 months 30 days in the historical year is taken as the time node.
Step S33, searching temperature information of a second time period which is most similar to the temperature information of the first time period in the time period before and after the node according to the length of the first time period;
step S34, adding the time period difference value between the first time period and the second time period and the sub-engineering construction time period to obtain a first target time period;
in one embodiment, taking a case where the first time period is from 4 months 15 days to 4 months 30 days, and the sub-engineering construction time period is from 5 months 1 day to 5 months 15 people as an example, the temperature information of the second time period most similar to the temperature information of the first time period is searched for from the first 15 days of the 4 months 15 days and the last 15 days of the 4 months 30 days according to the length of the first time period. For example, if the second time period is 4 months 20-5 months 15 days, the time period difference between the first time period and the second time period is 5 days, and the time period difference is added to the sub-engineering construction time period to obtain the first target time period of 5 months 6 days-5 months 21 days.
Step S35, taking the temperature information of the first target time period as the temperature information of the sub-project construction time period corresponding to the target sub-project;
in one embodiment, the historical temperature information of the first time period is used as the temperature information of the target sub-project in the sub-project construction time period, so that the temperature information is predicted, and a manager can know the construction temperature of the target sub-project in advance.
Step S36, searching a third time period which is most similar to the humidity information of the first time period in the time periods before and after the node according to the length of the first time period;
step S37, adding the time period difference value between the first time period and the third time period and the sub-engineering construction time period to obtain a second target time period;
step S38, taking the humidity information of the second target time period as the humidity information of the sub-project construction time period corresponding to the target sub-project;
step S39, searching a fourth time period which is most similar to the severe weather day information of the first time period in the time periods before and after the node according to the length of the first time period;
step S40, adding the time period difference value of the first time period and the fourth time period and the sub-engineering construction time period to obtain a third target time period;
And S41, taking the bad weather day information of the third target time period as the bad weather day information of the sub-project construction time period corresponding to the target sub-project.
In one embodiment, the method for obtaining the humidity information and the day information of bad weather of the target sub-project is the same as the method for obtaining the temperature information, and will not be described herein.
The temperature information, the humidity information and the bad weather day information of the target sub-project are predicted by using the historical environment information, so that the influence of the environment information on the progress of the target sub-project can be analyzed, a manager can conveniently adjust the sub-project construction target of the sub-project, and the possibility of delay of the whole project to be managed is reduced.
As another embodiment for acquiring the environment information according to the sub-project construction time period of the target sub-project, it further includes: inputting the sub-engineering construction time period into a preset environment prediction model, and analyzing the environment information of the sub-engineering construction time period corresponding to the target sub-engineering; the preset environment prediction model is obtained through training of temperature information, humidity information and severe weather day information in the same time period in the historical years.
Taking historical environment information and each sub-engineering construction time period as training samples, training by adopting a preset machine learning algorithm, and generating a preset environment prediction model corresponding to each time period;
Training the relation between the two by presetting a machine learning algorithm, wherein the machine learning algorithm can be as follows: spark machine learning, XGBoost (eXtreme Gradient Boosting, extreme gradient boost) machine learning to predict temperature information, humidity information, and bad weather day information for different time periods.
S4, acquiring construction influence factors of the target sub-engineering; the construction influence factors are any one or more of environmental factors, personnel factors and material factors;
specifically, the construction name, the construction area and the sub-engineering construction time period of the target sub-engineering are input into a preset construction influence factor model, and the construction influence factor of the target sub-engineering is obtained.
In one embodiment, the construction influencing factors of the sub-projects of different construction stages and construction layers are different, for example, some sub-projects are influenced by only one construction influencing factor of the environment information, some sub-projects are influenced by two construction influencing factors of the personnel information and the material information, and some sub-projects are influenced by three construction influencing factors of the environment information, the personnel information and the material information.
It should be noted that the preset construction influence factor model is trained by adopting different construction areas, construction time periods, different construction names and corresponding history sub-projects of the construction influence factors through the neural network model. The construction influencing factors of each type of sub-engineering can be specified according to manual experience.
S5, calculating a first construction progress deviation of a target sub-project according to the construction condition information, the construction influence factors, a preset construction progress deviation calculation rule and a sub-project construction plan corresponding to the target sub-project;
specifically, step S5 includes the following substeps (step S51 to step S61):
step S51, determining condition information to be analyzed in the construction condition information according to the construction influence factors;
in one embodiment, if the construction influence factor of the target sub-project is an environmental factor, determining the condition information to be analyzed as environmental information; if the construction influence factors of the target sub-engineering are personnel factors and material factors, determining that the condition information to be analyzed is personnel information and material information.
Step S52, if the condition information to be analyzed comprises environmental information, searching a plurality of sub-engineering information similar to the environmental information in a historical database;
step S53 of determining at least one piece of first sub-engineering information among the plurality of pieces of sub-engineering information based on the construction area and the construction name;
step S54, if a plurality of first sub-project information exists, taking a first sub-project of which the construction time period is closest to the sub-project construction time period of the target sub-project as a reference sub-project;
Step S55, taking the environmental impact construction progress deviation of the reference sub-project as a first construction progress deviation of the target sub-project;
in one embodiment, sequentially narrowing-down search is performed in the history database according to the environment information, the construction area, the construction name and the construction time period, the reference sub-project is finally determined, the actual influence construction progress deviation of the environment influence project progress of the reference sub-project in the reference history data, and the construction influence progress deviation is used as the first construction progress deviation of the target sub-project.
Step S56, if the condition information to be analyzed comprises personnel information, comparing the age of the constructor of the target sub-project with a preset age interval to obtain an age interval corresponding to the constructor;
step S57, searching engineering quantities corresponding to the age interval and the technical grade in a preset stored engineering scale according to the age interval and the technical grade corresponding to constructors;
step S58, calculating the daily work quantity of the target sub-project according to the engineering quantity corresponding to the age interval and the technical grade and the number of constructors corresponding to each work quantity;
step S59, analyzing a first construction progress deviation of a target sub-project according to the daily work amount and the sub-project construction plan;
Through analyzing constructor quantity, construction age and construction technology in constructor influence analysis, the influence of constructor quantity, constructor age and construction technology on construction progress is effectively displayed, and reliable data are provided for subsequent construction progress analysis.
Step S60, if the condition information to be analyzed comprises material information, judging whether the corresponding supply time and supply amount of each construction material type are met according to the sub-construction plan;
step S61, if not, analyzing the first construction progress deviation of the target sub-project according to the difference value of the supply time and the supply quantity.
In one embodiment, in the construction material influence analysis, by analyzing each type of construction material required for the target sub-project and the corresponding supply time and supply amount, when the supply time and supply amount do not satisfy the sub-project construction plan of the target sub-project, the explanation material information also has an influence on the construction progress of the target sub-project, and further, the first construction progress deviation is analyzed according to the deviation of the supply time.
By analyzing the influence of the construction progress on the environmental information, the personnel information and the material information in advance before the target sub-engineering construction, reliable data is provided for the subsequent sub-engineering construction progress analysis of the target sub-engineering. Before each sub-engineering is constructed, construction influence factors are analyzed in advance, so that management staff can know the construction conditions of the sub-engineering in advance, and the management staff can adjust construction plans such as staff, materials, progress and the like according to the construction conditions.
And S6, generating a visual progress report according to the first construction progress deviation, and sending the visual progress report to a management terminal corresponding to the project to be managed.
In one embodiment, if the construction progress delay is analyzed according to the first construction progress deviation, corresponding alarm information is sent to a management terminal corresponding to the project to be managed, and a corresponding visual progress report of the project to be managed is generated according to the first construction progress deviation, so that management staff can know the overall project progress conveniently, and the project can be adjusted timely.
As one embodiment of generating a visual progress report according to the first construction progress deviation, it includes:
firstly, the electronic equipment establishes a BIM building model of the project to be managed according to the project construction plan;
marking sub-engineering labels corresponding to the sub-engineering in a BIM building model according to the construction nodes of the sub-engineering;
in one embodiment, a manager may build a BIM model from the project construction plan file prior to construction via the electronic device and mark the location of each sub-project on the build model. Each sub-project corresponds to a unique sub-project node and sub-project label, so that a manager can check related conditions of the sub-project conveniently, and the manager can upload actual construction conditions, special conditions and the like at the construction node.
Then, the electronic equipment updates at least one sub-engineering construction time period arranged in the sub-engineering node flow of the real work after the target sub-engineering according to the first construction progress deviation;
controlling corresponding positions in the BIM building model according to the sub-engineering labels to display sub-engineering construction time periods of each sub-engineering, updated sub-engineering construction time periods and construction influence factors;
and generating a visual progress report according to the sub-project construction time period of each sub-project, the updated sub-project construction time period and the construction influence factor BIM building model.
In one embodiment, the electronic device displays information such as predicted construction condition information, influence factor information, sub-project construction time period of each sub-project, updated sub-project construction time period, and the like in the BIM building model. When the construction progress delay is analyzed according to the first construction progress deviation, a visual progress report is generated according to the updated BIM building model, and the visual progress report is sent to a management terminal used by a manager, so that the manager can conveniently check information such as construction progress change conditions of the project to be managed.
As an embodiment of engineering project management, the method further comprises:
In the actual construction process of the target sub-engineering, the electronic equipment acquires construction detection information and sub-engineering plan adjustment information; the construction detection information comprises construction workload; the sub-engineering plan adjustment information is a sub-engineering construction plan adjusted by a manager according to the first construction deviation;
comparing the construction workload with the corresponding construction completion amount in the sub-engineering construction plan to obtain a second construction deviation;
calculating at least one sub-engineering construction time period of the sub-engineering node flow arrangement of the actual work after the target sub-engineering according to the second construction deviation and the first construction deviation, and recording the at least one sub-engineering construction time period as an adjustment time period;
and controlling the corresponding position in the BIM building model to display the sub-project plan adjustment information and the adjustment time period of each sub-project according to the sub-project label.
The actual construction progress of the target sub-project, the sub-project plan adjustment information and the adjustment time period for the subsequent sub-project adjustment according to the actual construction progress are updated in time by tracking in real time according to the sub-project construction plans corresponding to the sub-projects and collecting and recording the result progress and the like of the execution stage in the BIM model, so that a manager can master the current situation of the project construction site and the actual construction progress in time, and meanwhile, problems and the like of the sub-project can be found in time in the process of collecting the construction detection information.
Fig. 4 is a block diagram of an electronic device 300 according to an embodiment of the application.
As shown in fig. 4, the electronic device 300 includes a processor 301 and a memory 302, and may further include one or more of an information input/information output (I/O) interface 303 and a communication component 304, and a communication bus 305.
Wherein the processor 301 is configured to control the overall operation of the electronic device 300 to perform all or part of the steps in the engineering project management method described above; the memory 302 is used to store various types of data to support operation at the electronic device 300, which may include, for example, instructions for any application or method operating on the electronic device 300, as well as application-related data. The memory 302 may be implemented by any type or combination of volatile or non-volatile memory devices, such as static random access memory (Static Random Access Memory,
programmable Read-Only Memory, EPROM), programmable Read-Only Memory (PROM), read-Only Memory (ROM), magnetic Memory, flash Memory, magnetic disk, or optical disk.
The I/O interface 303 provides an interface between the processor 301 and other interface modules, which may be a keyboard, mouse, buttons, etc. These buttons may be virtual buttons or physical buttons. The communication component 304 is used to test wired or wireless communication between the electronic device 300 and other devices. Wireless communication, such as Wi-Fi, bluetooth, near field communication (Near Field Communication, NFC for short), 2G, 3G, or 4G, or a combination of one or more thereof, and accordingly the communication component 304 can include: wi-Fi part, bluetooth part, NFC part.
Communication bus 305 may include a pathway to transfer information between the aforementioned components. The communication bus 305 may be a PCI (Peripheral Component Interconnect, peripheral component interconnect standard) bus or an EISA (Extended Industry Standard Architecture ) bus, or the like. The communication bus 305 may be divided into an address bus, a data bus, a control bus, and the like.
The electronic device 300 may be implemented by one or more application specific integrated circuits (Application SpecificIntegrated Circuit, abbreviated as ASIC), digital signal processors (Digital Signal Processor, abbreviated as DSP), digital signal processing devices (Digital Signal Processing Device, abbreviated as DSPD), programmable logic devices (Programmable Logic Device, abbreviated as PLD), field programmable gate arrays (Field Programmable Gate Array, abbreviated as FPGA), controllers, microcontrollers, microprocessors, or other electronic components for performing the engineering project management methods set forth in the above embodiments.
The electronic device 300 may include, but is not limited to, a mobile terminal such as a digital broadcast receiver, a PDA (personal digital assistant), a PMP (portable multimedia player), etc., and a fixed terminal such as a digital TV, a desktop computer, etc., and may also be a server, etc.
The following describes a computer readable storage medium provided in an embodiment of the present application, where the computer readable storage medium described below and the engineering project management method described above may be referred to correspondingly.
The application also provides a computer readable storage medium, on which a computer program is stored, which when executed by a processor implements the steps of the project management method described above.
The computer readable storage medium may include: a U-disk, a removable hard disk, a read-only memory (ROM), a random access memory (Random Access Memory, RAM), a magnetic disk, or an optical disk, or other various media capable of storing program codes.
The terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
The above description is only illustrative of the preferred embodiments of the present application and of the principles of the technology employed. It will be appreciated by persons skilled in the art that the scope of the application is not limited to the specific combinations of the features described above, but also covers other embodiments which may be formed by any combination of the features described above or their equivalents without departing from the spirit of the application. Such as the above-mentioned features and the technical features having similar functions (but not limited to) applied for in the present application are replaced with each other.

Claims (10)

1. An engineering project management method, comprising:
acquiring project information of a project to be managed; the project information comprises a project type and a project construction plan;
dividing the project construction plan into a plurality of sub-project construction plans arranged in a sub-project node flow according to the project type and a preset construction plan division model; the sub-engineering construction plan comprises a sub-engineering construction time period;
acquiring construction condition information according to a sub-engineering construction time period of a target sub-engineering; the target sub-project is a sub-project to be implemented currently; the construction condition information comprises environment information, personnel information and material information;
acquiring construction influence factors of a target sub-project; the construction influence factors are any one or more of environmental factors, personnel factors and material factors;
calculating a first construction progress deviation of a target sub-project according to the construction condition information, the construction influence factors, a preset construction progress deviation calculation rule and a sub-project construction plan corresponding to the target sub-project;
and generating a visual progress report according to the first construction progress deviation, and sending the visual progress report to a management terminal corresponding to the project to be managed.
2. The project management method according to claim 1, wherein the acquiring the construction condition information according to the sub-project construction period of the target sub-project includes:
determining a first time period according to the sub-engineering construction time period and a preset time period selection rule; the first time period is located before the sub-engineering construction time period;
collecting the environment information of the target sub-engineering in the first time period; the environment information comprises temperature information, humidity information and bad weather day information;
predicting the environmental information of the sub-project construction time period corresponding to the target sub-project based on the environmental information of the first time period, the sub-project construction plan of the target sub-project and the environmental information of the historical year;
before the sub-engineering construction time period, acquiring personnel information and material information uploaded by a responsible person at a management terminal; the personnel information comprises the number of constructors, the age of the constructors and the technical grade of the constructors; the material information is construction material type and corresponding supply time and supply amount of each construction material type.
3. The engineering management method according to claim 2, wherein the temperature information includes an average temperature and a temperature variation trend, and the humidity information includes an average humidity and a humidity variation trend; the sub-engineering construction plan comprises a construction area; the predicting the environment information of the sub-project corresponding to the sub-project construction time period based on the environment information of the first time period, the sub-project construction plan of the target sub-project and the environment information of the historical year includes:
Acquiring temperature information, humidity information and bad weather day information of the history year of the construction area;
taking a time period with the same historical year as the first time period as a node;
searching temperature information of a second time period which is most similar to the temperature information of the first time period in time periods before and after the node according to the length of the first time period;
adding the time period difference value of the first time period and the second time period and the sub-engineering construction time period to obtain a first target time period;
taking the temperature information of the first target time period as the temperature information of the sub-engineering construction time period corresponding to the target sub-engineering;
according to the length of the first time period, searching humidity information of a third time period which is most similar to the humidity information of the first time period in time periods before and after the node;
adding the time period difference value of the first time period and the third time period and the sub-engineering construction time period to obtain a second target time period;
taking the humidity information of the second target time period as the humidity information of the sub-engineering construction time period corresponding to the target sub-engineering;
searching severe weather day information of a fourth time period which is most similar to the severe weather day information of the first time period in the time period before and after the node according to the length of the first time;
Adding the time period difference value of the first time period and the fourth time period and the sub-engineering construction time period to obtain a third target time period;
and taking the bad weather day information of the third target time period as the bad weather day information of the target sub-project corresponding to the sub-project construction time period.
4. A method according to claim 3, wherein the acquiring environmental information according to the sub-project construction period of the target sub-project comprises:
inputting the sub-engineering construction time period into a preset environment prediction model, and analyzing the environment information of the sub-engineering construction time period corresponding to the target sub-engineering; the preset environment prediction model is obtained through training of temperature information, humidity information and severe weather day information in the same time period in the historical years.
5. The project management method according to claim 3 or 4, wherein the sub-project construction plan includes a construction name, and the obtaining of the construction influence factor of the target sub-project includes:
and inputting the construction name, the construction area and the sub-engineering construction time period of the target sub-engineering into a preset construction influence factor model to obtain the construction influence factor of the target sub-engineering.
6. The method of claim 3, wherein calculating the first construction progress deviation of the target sub-project according to the construction condition information, the construction influencing factors, a preset construction progress deviation calculation rule, and the sub-project construction plan corresponding to the target sub-project comprises:
determining condition information to be analyzed in the construction condition information according to the construction influence factors;
if the condition information to be analyzed comprises environmental information, searching a plurality of sub-engineering information similar to the environmental information in a historical database;
determining at least one first sub-engineering information among the plurality of sub-engineering information based on the construction area and the construction name;
if a plurality of first sub-project information exists, taking a first sub-project of which the construction time period is closest to the sub-project construction time period of the target sub-project as a reference sub-project;
taking the environmental influence construction progress deviation of the reference sub-project as a first construction progress deviation of the target sub-project;
if the condition information to be analyzed comprises personnel information, comparing the age of the constructor of the target sub-project with a preset age interval to obtain an age interval corresponding to the constructor;
Searching engineering quantities corresponding to the age interval and the technical grade in a preset stored engineering scale according to the age interval and the technical grade corresponding to constructors;
calculating the daily work quantity of the target sub-project according to the engineering quantity corresponding to the age interval and the technical grade and the number of constructors corresponding to each work quantity;
analyzing a first construction progress deviation of a target sub-project according to the daily work quantity and the sub-project construction plan;
if the condition information to be analyzed comprises material information, judging whether the corresponding supply time and supply quantity of each construction material type are met according to the sub-construction plan;
if the first construction progress deviation is not satisfied, analyzing the first construction progress deviation of the target sub-project according to the difference value of the supply time and the supply quantity.
7. The method of claim 1, wherein the generating a visual progress report from the first construction progress deviation comprises:
building a BIM building model of the project to be managed according to the project construction plan;
marking sub-engineering labels corresponding to the sub-engineering in one-to-one correspondence in the BIM building model according to the construction nodes of the sub-engineering;
Updating at least one sub-engineering construction time period of sub-engineering node flow arrangement of an actual work after the target sub-engineering according to the first construction progress deviation;
controlling corresponding positions in the BIM building model according to the sub-engineering labels to display sub-engineering construction time periods of each sub-engineering, updated sub-engineering construction time periods and construction influence factors;
and generating a visual progress report according to the sub-project construction time period of each sub-project, the updated sub-project construction time period and the construction influence factor BIM building model.
8. The method as recited in claim 7, further comprising:
in the actual construction process of the target sub-engineering, acquiring construction detection information and sub-engineering plan adjustment information; the construction detection information comprises construction workload; the sub-engineering plan adjustment information is a sub-engineering construction plan adjusted by a manager according to the first construction deviation;
comparing the construction workload with the corresponding construction completion amount in the sub-engineering construction plan to obtain a second construction deviation;
calculating at least one sub-engineering construction time period of the sub-engineering node flow arrangement of the actual work after the target sub-engineering according to the second construction deviation and the first construction deviation, and recording the at least one sub-engineering construction time period as an adjustment time period;
And controlling the corresponding position in the BIM building model to display the sub-project plan adjustment information and the adjustment time period of each sub-project according to the sub-project label.
9. An electronic device comprising a processor coupled to a memory;
the processor is configured to execute a computer program stored in the memory to cause the electronic device to perform the method of any one of claims 1 to 8.
10. A computer readable storage medium comprising a computer program or instructions which, when run on a computer, cause the computer to perform the method of any of claims 1-8.
CN202310651275.0A 2023-06-02 2023-06-02 Engineering project management method, equipment and computer readable storage medium Pending CN116796961A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310651275.0A CN116796961A (en) 2023-06-02 2023-06-02 Engineering project management method, equipment and computer readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310651275.0A CN116796961A (en) 2023-06-02 2023-06-02 Engineering project management method, equipment and computer readable storage medium

Publications (1)

Publication Number Publication Date
CN116796961A true CN116796961A (en) 2023-09-22

Family

ID=88040760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310651275.0A Pending CN116796961A (en) 2023-06-02 2023-06-02 Engineering project management method, equipment and computer readable storage medium

Country Status (1)

Country Link
CN (1) CN116796961A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117196544A (en) * 2023-11-07 2023-12-08 恒实建设管理股份有限公司 Intelligent management method and system for engineering information
CN117273394A (en) * 2023-11-17 2023-12-22 中铁四局集团有限公司 Intelligent equipment selection allocation analysis management method based on big data

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117196544A (en) * 2023-11-07 2023-12-08 恒实建设管理股份有限公司 Intelligent management method and system for engineering information
CN117196544B (en) * 2023-11-07 2024-01-30 恒实建设管理股份有限公司 Intelligent management method and system for engineering information
CN117273394A (en) * 2023-11-17 2023-12-22 中铁四局集团有限公司 Intelligent equipment selection allocation analysis management method based on big data
CN117273394B (en) * 2023-11-17 2024-02-06 中铁四局集团有限公司 Intelligent equipment selection allocation analysis management method based on big data

Similar Documents

Publication Publication Date Title
CN116796961A (en) Engineering project management method, equipment and computer readable storage medium
CN111091196B (en) Passenger flow data determination method and device, computer equipment and storage medium
US20150134545A1 (en) Structure Modelling and Maintenance Scheduling
WO2016123729A1 (en) Global general key factor preset array platform for biological population dynamic prediction and analysis
Wang et al. Predicting ENR construction cost index using machine-learning algorithms
JP5698576B2 (en) Graph editing simulation device, graph editing simulation program, and plant maintenance management system
US11068857B2 (en) Systems and methods for managing populations of utility poles
US20230324888A1 (en) System, Method, and Computer Program Product for Optimizing a Manufacturing Process
CN111104589A (en) Decoration enterprise evaluation method and device, computer equipment and storage medium
JP2019204507A (en) AI Headline News
Shrestha et al. Computational algorithm to automate as-built schedule development using digital daily work reports
JP2018206291A (en) Energy saving effect calculating device and method
Graham et al. Estimating the productivity of cyclic construction operations using case-based reasoning
Cha et al. A study on 3D/BIM-based on-site performance measurement system for building construction
CN115511467A (en) Project management method and system based on engineering cost
Patriarca et al. Supporting weather forecasting performance management at aerodromes through anomaly detection and hierarchical clustering
KR100991316B1 (en) Use of simulation to generate predictions pertaining to a manufacturing facility
JP2021112136A (en) Support system and support method
Jungmann et al. Real-time activity duration extraction of crane works for data-driven discrete event simulation
CN117172549A (en) Construction budget generation method, construction budget generation system, terminal equipment and storage medium
JP6502816B2 (en) Planning support system and planning support method
CN116957143A (en) Village air rate prediction method, village air rate prediction device, electronic equipment and readable storage medium
Zhang et al. A nested modelling approach to infrastructure performance characterisation
CN111652282A (en) Big data based user preference analysis method and device and electronic equipment
KR102020209B1 (en) System, method and program for managing facilities

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination