CN116518149A - Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof - Google Patents

Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof Download PDF

Info

Publication number
CN116518149A
CN116518149A CN202310611550.6A CN202310611550A CN116518149A CN 116518149 A CN116518149 A CN 116518149A CN 202310611550 A CN202310611550 A CN 202310611550A CN 116518149 A CN116518149 A CN 116518149A
Authority
CN
China
Prior art keywords
dust removing
pipeline
factory building
roof
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310611550.6A
Other languages
Chinese (zh)
Inventor
叶亮
丁志林
崔世杰
郑治飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202310611550.6A priority Critical patent/CN116518149A/en
Publication of CN116518149A publication Critical patent/CN116518149A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/0243Laying or reclaiming pipes on land, e.g. above the ground above ground
    • F16L1/0246Laying or reclaiming pipes on land, e.g. above the ground above ground at a certain height off the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • F16L1/09Accessories therefor, e.g. anchors for bringing two tubular members closer to each other
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • F16L1/11Accessories therefor, e.g. anchors for the detection or protection of pipes in the ground

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a pairing translation installation method of large-diameter dust removal pipelines of a roof of a steel structure factory building, and belongs to the field of building construction. The method comprises the following steps: s1, arranging a traction winch at the top of a steel structure factory building; s2, arranging a translation track at the top of the steel structure factory building; s3, hoisting the segmented dust removal pipeline to a translation track by using a hoisting machine for assembly; s4, dragging the dust removing pipeline pair to an installation position along the translation track by utilizing a traction winch; s5, hoisting and assembling the dust removing pipeline on the translation track continuously, then dragging the assembled new dust removing pipeline pair to the installation position by using the traction winch, and assembling the assembled new dust removing pipeline pair with the installed dust removing pipeline pair in place until the complete dust removing pipeline is installed. The invention has smaller requirement on the hoisting capacity of the hoisting machinery, reduces the construction cost and solves the problem that the dust removing pipeline at the top of the steel structure factory building is difficult to directly hoist in place in the prior art.

Description

Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof
Technical Field
The invention relates to the technical field of building construction, in particular to a method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building.
Background
Five committees of the ecological environment department and the like jointly print opinion on the ultra-low emission of the advanced implementation steel industry on 4 months in 2019, and the ultra-low emission modification of the steel industry formally opens a preamble. In 2020, the ecological environment department issues technical guidelines (revised 2020 edition) for making emergency emission reduction measures in heavy pollution weather major industries, and tightly connects performance grading standards of iron and steel enterprises with ultra-low emission. So far, the effect and the progress of the steel enterprises for completing the ultra-low emission transformation directly influence the production benefit and the future development of the enterprises.
The main method of the ultra-low emission reconstruction of the steelmaking engineering is to increase dust removing points to absorb the unorganized smoke dust in the factory building through newly constructing a dust remover and a dust removing pipeline, thereby playing a role in reducing pollutant emission. Because the process equipment in the steel-making workshop is very many, the layout is compact, and the diameter of the dedusting pipeline is very large, the ultralow-emission pipelines of many steel-making projects are selectively arranged on the roof of the steel-making workshop, but the installation of the dedusting pipeline also brings great difficulty. The conventional installation thought can assemble the dust removing pipeline on the ground, and then hoist the dust removing pipeline to the roof by means of a hoisting machine, but the method can be completed when the dust removing pipeline and the factory building are synchronously constructed, and for the built factory building, the dust removing pipeline is difficult to hoist in place directly because the dust removing pipeline is far away from the roof. Of course, the dust removing pipeline can be assembled in the factory building, then the mast is arranged on the roof, and the mast is used for hoisting the dust removing pipeline in place, but the method has high construction difficulty, belongs to irregular hoisting, and needs to dismantle the corresponding roof encaustic tiles and purlines, so that the construction period is long, and the normal production of equipment in the factory building is influenced.
Through searching, as disclosed in patent application No. 2020112465819, a synchronous construction method of a steel-making factory building and a roof large-caliber pipeline is disclosed, and a reasonable crawler belt refund route is selected before construction; the main construction procedures are as follows: closing each span roof, withdrawing the crawler crane from the roof closing span, installing a roof dust removing bracket, hoisting a section of roof dust removing pipeline in the crawler crane span, and continuing to close the roof and withdrawing the crawler crane from the roof dust removing pipeline. The scheme adopts a mode of synchronously constructing the roof of the steel-making factory building and the dust removing pipeline of the roof. As another patent application of application number 2019103877770, a sectional installation construction method of a large-diameter overlength pipeline across a roof is disclosed, and the pipeline is divided into a left-end pipeline, a roof-across pipeline and a right-end pipeline according to the span of the pipeline in a factory building; and correspondingly arranging a temporary bracket; the two ends of the temporary cross beam of the temporary support are supported by temporary upright posts, the cross roof pipeline is supported by the temporary cross beam, and the temporary upright posts are arranged on crane beams in the factory building; welding a left end pipeline, a roof crossing pipeline and a right end pipeline after hoisting; and finally, removing the temporary support. According to the scheme, the problems that a working face is narrow and a large crane cannot stand can be solved through sectional hoisting, but the setting and the dismounting of the temporary support are also in the current situation of high construction difficulty.
Disclosure of Invention
1. Technical problem to be solved by the invention
The invention aims to provide a pairing translation installation method of large-diameter dust removing pipelines of a roof of a steel structure factory building, which solves the problem that the dust removing pipelines at the top of the steel structure factory building are difficult to directly hoist in place in the prior art.
2. Technical proposal
In order to achieve the above purpose, the technical scheme provided by the invention is as follows:
the invention relates to a pairing translation installation method of large-diameter dust removal pipelines on a roof of a steel structure factory building, which comprises the following steps:
s1, arranging a traction winch at the top of a steel structure factory building and at the installation tail end of a dust removal pipeline;
s2, arranging a translation track at the top of the steel structure factory building along the arrangement direction of the dust removing pipeline;
s3, hoisting each segmented dust removing pipeline to a translation track at the edge of a factory building by using a hoisting machine, and assembling a proper amount of the segmented dust removing pipelines to form a dust removing pipeline pair;
s4, dragging the dust removing pipeline pair to an installation position along the translation track by utilizing a traction winch;
s5, hoisting and assembling the dust removing pipeline on a translation track at the edge of the factory building continuously, then dragging the assembled new dust removing pipeline pair to the installation position by using a traction winch, and assembling the assembled new dust removing pipeline pair with the dust removing pipeline pair which is installed in place before until the complete dust removing pipeline is installed.
Furthermore, the central elevation of the traction winch after the installation in the S1 is higher than the elevation of the bottom of the dust removing pipeline and does not exceed the central elevation of the dust removing pipeline.
Still further, the translation track includes track crossbeam and track landing leg, and track landing leg welds on the purlin of roof, and track crossbeam welds on the track landing leg and parallel arrangement has two sets of for carry out symmetrical support to dust removal pipeline both sides.
Further, the support width of the translation track is 1.3-2 times of the radius of the dust removing pipeline.
Still further, before the translation track sets up, according to the central line of dust removal pipeline and the interval measurement unwrapping wire of track landing leg, confirm the position of track landing leg according to the interval and the unwrapping wire position of factory building roofing purlin, the roofing color slab of cutting corresponding position exposes the factory building roofing purlin of below, welds the track landing leg on the factory building roofing purlin again, welds track crossbeam and track landing leg at last.
Further, the crane mechanical station is positioned on the ground at one side of the factory building, and the dust removing pipeline is hoisted to the translation track from the ground.
Alternatively, within the hoisting capacity of the hoisting machine, the following may be adopted in S3: the method comprises the steps of firstly assembling each sectional dust removing pipeline on the ground to form a dust removing pipeline pair, and then hoisting the dust removing pipeline pair to a translation track at the edge of a factory building by a hoisting machine.
Furthermore, two lifting lugs are symmetrically welded at the lower part of one end of the dust removing pipeline closest to the traction winch, the lifting lugs are connected with a steel wire rope of the traction winch, the traction winch is first driven by a point, and the dust removing pipeline is dragged to the installation position after no problem exists.
Further, when the traction winch drags the subsequent dust removing pipeline, the steel wire rope of the traction winch passes through the front dust removing pipeline.
Furthermore, after the dust removing pipeline is assembled, reinforcing rib plates are welded on the outer sides of the dust removing pipelines, and when the reinforcing rib plates close to the translation track are welded, the reinforcing rib plates cannot be welded, and repair welding is performed after the dust removing pipelines are in place.
3. Advantageous effects
Compared with the prior art, the technical scheme provided by the invention has the following beneficial effects:
(1) According to the translational installation method of the dust removing pipeline assembly, the roof purline is used as the supporting point of the translational track, the supporting point is not required to be additionally arranged, the construction cost is reduced, the encaustic tiles at the supporting leg positions of the track are only required to be cut into small openings during construction, the integral rigidity of the roof encaustic tiles is not affected, operators can still walk freely on the encaustic tiles, and the construction is safer.
(2) According to the method for installing the dust removing pipeline assembly in the horizontal movement mode, the horizontal movement track can be used as an assembly platform, so that the concentricity of the dust removing pipeline can be guaranteed as long as the elevation of the horizontal movement track is guaranteed, the assembly difficulty is low, the assembly can be completed on a roof, the requirement on the hoisting capacity of a hoisting machine is low, and the construction cost is reduced.
(3) According to the translation installation method of the dust removal pipeline assembly, all construction operations are completed on the roof, and the influence on production operations in a factory building is very small.
Drawings
FIG. 1 is a schematic elevation view of a dust removing pipeline in the present invention in a assembled and translational state;
FIG. 2 is a schematic plan view of the assembly and translation states of the dust removing pipelines in the invention;
FIG. 3 is a schematic view of a translation rail and stiffener plate arrangement in the present invention;
fig. 4 is a schematic view of the installation of the residual dust removing pipeline in the present invention.
Reference numerals in the schematic drawings illustrate:
1. a traction winch; 2. purlins for plant roofs;
3. translating the track; 3-1, a track beam; 3-2, track supporting legs;
4. a dust removal pipeline pair; 4-1, pipeline section one; 4-2, pipeline segmentation II; 4-3, pipeline segmentation III;
5. a hoisting machine; 6. lifting lugs; 7. reinforcing rib plates; 8. a new dust removing pipeline pair.
Detailed Description
For a further understanding of the present invention, the present invention will be described in detail with reference to the drawings.
In the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. are based on the directions or positional relationships shown in the drawings, are merely for convenience of describing the present invention and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
The invention is further described below with reference to examples.
Examples
The pairing translation installation method of the large-diameter dust removal pipeline of the steel structure factory building roof comprises the following steps:
s1, arranging a traction winch 1 at the top of a steel structure factory building and at the installation tail end of a dust removal pipeline;
specifically, referring to fig. 1, the traction winch 1 is fixed on a roof of a factory building, and is connected with a purline 2 of the roof of the factory building into a whole through i-steel, so that the traction winch 1 is preferably arranged at a position near the tail end of a dust removal pipeline, the central line of a winding drum of the traction winch 1 is close to the central line of the dust removal pipeline, and a 3t winch can be adopted for the traction winch 1. The central elevation of the traction winch 1 after the installation is slightly higher than the elevation of the bottom of the dust removing pipeline and does not exceed the central elevation of the dust removing pipeline.
S2, arranging a translation track 3 at the top of the steel structure factory building along the arrangement direction of the dust removing pipeline;
with specific reference to fig. 2, the center line of the translation track 3 coincides with the center line of the dust removing duct, and the width of the translation track 3 is preferably 1.3-2 times, preferably 1.5 times, the radius of the dust removing duct, for example, the diameter of the dust removing duct is 3.6m, and the width of the track is preferably 2.7m. The height of the translation track 3 should be determined according to the installation elevation of the dust removal pipeline, so as to ensure that the center elevation of the dust removal pipeline is exactly the installation elevation after the dust removal pipeline is placed on the translation track 3. The translation track 3 is arranged from the outer side of the roof of the steel structure factory building until the final installation position of the dust removing pipeline.
Referring to fig. 1, the translation track 3 is composed of a track beam 3-1 and a track supporting leg 3-2, wherein the track supporting leg 3-2 is preferably made of steel with a letter, and is welded on a purline 2 of a factory building roof, and the track beam 3-1 is preferably made of channel steel and is welded with the track supporting leg 3-2. The elevation and center line errors of the two track beams 3-1 should be within the allowable range. Before the translation track 3 is arranged, the paying-off is measured according to the center line of the dedusting pipeline and the distance between the track supporting legs 3-2, the position of the track supporting legs 3-2 is determined according to the distance between the plant roof purlines 2 and the paying-off position, roof color plates at corresponding positions are cut, the plant roof purlines 2 below are exposed, the track supporting legs 3-2 are welded to the plant roof purlines 2, and finally the track cross beam 3-1 is welded with the track supporting legs 3-2.
S3, hoisting and pairing the dust removal pipeline: hoisting each segmented dust removing pipeline to a translation track 3 at the edge of a factory building by using a hoisting machine 5, and assembling a proper amount of the segmented dust removing pipelines to form a dust removing pipeline pair 4; the hoisting machinery 5 is positioned on the ground at one side of the factory building;
specifically, referring to fig. 1 and 2, in this embodiment, the dust removing pipe pair 4 is composed of a first pipe section 4-1, a second pipe section 4-2 and a third pipe section 4-3, and in actual operation, the dust removing pipe pair 4 can be decomposed into a suitable number of sections according to the need. During construction, the hoisting machine 5 is used for hoisting the first pipeline section 4-1 to a factory building roof, the hoisting capacity of the hoisting machine 5 is limited, when the hoisting machine is used for hoisting, the position of the first pipeline section 4-1 can be at the position of the third pipeline section 4-3 shown in fig. 1, two lifting lugs 6 are symmetrically welded below the first pipeline section 4-1, and the first pipeline section 4-1 is firstly pulled to the position of the second pipeline section 4-2 shown in fig. 1 by the traction winch 1. Hoisting the second pipeline section 4-2 to the position of the third pipeline section 4-3 shown in fig. 1 by using a hoisting machine 5, combining the second pipeline section 4-2 and the first pipeline section 4-1 into a whole, firmly welding, and integrally towing the first pipeline section 4-1 and the second pipeline section 4-2 to the position shown in fig. 1 by using a towing winch 1. Hoisting machine 5 is used to hoist pipe segment three 4-3 to the position shown in FIG. 1 and to form an integral unit with pipe segment one 4-1 and pipe segment two 4-2.
In practice, in the hoisting capacity range of the hoisting machine 5, the segmented dust removal pipelines may be assembled on the ground to form the dust removal pipeline pair 4, and then the hoisting machine 5 hoistes the dust removal pipeline pair 4 onto the translation track 3 at the edge of the factory building, so as to reduce overhead operation as much as possible.
S4, integral translation of the dust removing pipeline pair 4: dragging the dust removing pipeline pair 4 to an installation position along the translation track 3 by utilizing the traction winch 1;
referring to fig. 3, after the dust removing pipeline pair 4 is assembled, the reinforcing rib plates 7 are welded according to requirements, the reinforcing rib plates 7 are arc steel plates with the thickness of 10-12mm and the inner diameter equal to the outer diameter of the dust removing pipeline pair 4, when the welding is performed, the reinforcing rib plates 7 close to the translation track 3 cannot be welded, and repair welding is performed after the dust removing pipeline pair 4 is in place.
Referring to fig. 1 and 2, the wire rope of the traction winch 1 is connected with the lifting lug 6 of the dust removal pipeline pair 4, and the traction winch 1 is clicked until the dust removal pipeline pair 4 is dragged. And (3) checking the states of the traction winch 1 and the translation rail 3, starting the traction winch 1 after determining no problem, and slowly translating the dust removal pipeline pair 4 to the installation position.
S5, remaining dust removal pipeline group pairs: hoisting and assembling the dust removing pipelines on the translation rails 3 at the edge of the factory building, then dragging the assembled new dust removing pipeline pair 8 to the installation position by using the traction winch 1, and assembling the assembled new dust removing pipeline pair with the dust removing pipeline pair 4 which is installed in place before until the complete dust removing pipeline is installed. And the assembling and splicing method of the new dust removing pipeline pair 8 is the same as that of the S3.
Referring to fig. 4, two lifting lugs 6 are symmetrically welded at the lower part of one end of the new dust removing pipeline pair 8 closest to the traction winch 1, and then the steel wire rope of the traction winch 1 passes through the installed dust removing pipeline pair 4 and is connected with the lifting lugs 6 of the new dust removing pipeline pair 8, the new dust removing pipeline pair 8 is translated to the installation position by the traction winch 1, and is butted with the installed dust removing pipeline pair 4, and the translation method refers to the step S4.
All the dust removing pipelines are translated to the installation position by adopting the process, and are in butt joint with the previous dust removing pipelines until all the pipelines are installed. All construction operations of the embodiment can be completed on the roof, the influence on production operations in a factory building is very small, the requirement on the hoisting capacity of the hoisting machinery 5 is small, the construction cost is reduced, the integral rigidity of the roof is not influenced, and the construction is safer.
The invention and its embodiments have been described above by way of illustration and not limitation, but rather one of the embodiments of the invention is not limited thereto. Therefore, if one of ordinary skill in the art is informed by this disclosure, the structural mode and the embodiments similar to the technical scheme are not creatively designed without departing from the gist of the present invention.

Claims (10)

1. The assembling, translating and installing method for the large-diameter dust removing pipeline of the roof of the steel structure factory building is characterized by comprising the following steps of:
s1, a traction winch (1) is arranged at the top of a steel structure factory building and at the installation tail end of a dust removal pipeline;
s2, arranging a translation track (3) at the top of the steel structure factory building along the arrangement direction of the dust removing pipeline;
s3, hoisting each segmented dust removing pipeline to a translation track (3) at the edge of a factory building by using a hoisting machine (5), and assembling a proper amount to form a dust removing pipeline pair (4);
s4, dragging the dust removing pipeline pair (4) to an installation position along the translation track (3) by utilizing the traction winch (1);
s5, hoisting and assembling the dust removing pipelines on the translation rails (3) at the edge of the factory building continuously, then dragging the assembled new dust removing pipeline pair (8) to the installation position by using the traction winch (1), and assembling the assembled new dust removing pipeline pair with the dust removing pipeline pair (4) which is installed in place before until the complete dust removing pipeline is installed.
2. The method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building according to claim 1, which is characterized in that: and S1, the central elevation of the traction winch (1) after the installation is completed is higher than the elevation of the bottom of the dust removing pipeline and does not exceed the central elevation of the dust removing pipeline.
3. The method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building according to claim 1, which is characterized in that: the translation track (3) comprises a track cross beam (3-1) and track supporting legs (3-2), wherein the track supporting legs (3-2) are welded on purlines of a roof, and the track cross beam (3-1) is welded on the track supporting legs (3-2) and is provided with two groups in parallel for symmetrically supporting two sides of the dust removal pipeline.
4. The method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building according to claim 3, wherein the method comprises the following steps of: the supporting width of the translation track (3) is 1.3-2 times of the radius of the dust removing pipeline.
5. The method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building according to claim 3, wherein the method comprises the following steps of: before the translation track (3) is arranged, paying off is measured according to the center line of the dust removal pipeline and the distance between the track support legs (3-2), the position of the track support legs (3-2) is determined according to the distance between the plant roof purlines (2) and the paying off position, roof color plates at corresponding positions are cut, the plant roof purlines (2) below are exposed, the track support legs (3-2) are welded to the plant roof purlines (2), and finally the track cross beam (3-1) and the track support legs (3-2) are welded.
6. The method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building according to claim 1, which is characterized in that: the lifting machine (5) is positioned on the ground at one side of the factory building, and the dust removing pipeline is hoisted to the translation track (3) from the ground.
7. The method for assembling, horizontally moving and installing large-diameter dust removing pipelines on a roof of a steel structure factory building according to claim 1, which is characterized in that: in the hoisting capacity range of the hoisting machinery (5), assembling each segmented dust removing pipeline on the ground to form a dust removing pipeline pair (4) in S3, and hoisting the dust removing pipeline pair (4) onto a translation track (3) at the edge of a factory by the hoisting machinery (5).
8. The method for installing large-diameter dust removal pipelines on a roof of a steel structure factory building in a pairing and translational manner according to any one of claims 1-7, wherein the method comprises the following steps: two lifting lugs (6) are symmetrically welded at the lower part of one end of the dust removing pipeline closest to the traction winch (1), the lifting lugs (6) are connected with a steel wire rope of the traction winch (1), the traction winch (1) is first moved in a point mode, and the dust removing pipeline is dragged to an installation position after no problem exists.
9. The method for assembling, horizontally moving and installing the large-diameter dust removing pipelines on the roof of the steel structure factory building according to claim 8, which is characterized in that: when the traction winch (1) drags the subsequent dust removing pipeline, the steel wire rope of the traction winch should pass through the front dust removing pipeline.
10. The method for installing large-diameter dust removal pipelines on a roof of a steel structure factory building in a pairing and translational manner according to any one of claims 1-7, wherein the method comprises the following steps: after the dust removing pipeline is assembled, reinforcing rib plates (7) are welded on the outer sides of the dust removing pipelines, and when welding, the reinforcing rib plates (7) close to the translation track (3) cannot be welded, and repair welding is performed after the dust removing pipelines are in place.
CN202310611550.6A 2023-05-24 2023-05-24 Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof Pending CN116518149A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310611550.6A CN116518149A (en) 2023-05-24 2023-05-24 Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310611550.6A CN116518149A (en) 2023-05-24 2023-05-24 Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof

Publications (1)

Publication Number Publication Date
CN116518149A true CN116518149A (en) 2023-08-01

Family

ID=87394182

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310611550.6A Pending CN116518149A (en) 2023-05-24 2023-05-24 Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof

Country Status (1)

Country Link
CN (1) CN116518149A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116838110A (en) * 2023-09-01 2023-10-03 北京建工集团有限责任公司 Method for installing large-span steel truss roof lower air pipe

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116838110A (en) * 2023-09-01 2023-10-03 北京建工集团有限责任公司 Method for installing large-span steel truss roof lower air pipe
CN116838110B (en) * 2023-09-01 2023-12-12 北京建工集团有限责任公司 Method for installing large-span steel truss roof lower air pipe

Similar Documents

Publication Publication Date Title
CN111042543A (en) Large-span roof truss construction method
CN102797226A (en) Integral erection construction method of 60m steel box girder
CN116518149A (en) Pairing translation installation method for large-diameter dust removal pipeline of steel structure factory building roof
CN104195948A (en) Bridge hanging pipeline pushing installation and construction method
CN110670488A (en) Full-prefabricated assembled bridge construction platform and construction method
CN115075398A (en) Reverse-order socket construction method for installing Y-shaped steel column
CN110629681A (en) Multi-span steel box girder construction process
CN108396749B (en) Installation system and installation method of steel support in foundation pit
CN110747307B (en) Large steam drum hoisting method in converter energy-saving and environment-friendly reconstruction
CN212599995U (en) Welding installation equipment for hot-melt welded pipe
CN112681138A (en) Segmented assembling and walking type pushing construction method for high-speed rail crossing line
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN211228142U (en) Full prefabricated assembled bridge construction platform
CN112609032B (en) Method for replacing crane beam of casting house
LU502102B1 (en) Construction method for adjustable starting platform assembly for pipe-jacking construction
CN114908968B (en) Construction method of large-span fish-bellied pipe truss in gymnasium
CN211446612U (en) Operating platform for steel box girder aerial work
CN210262748U (en) Cantilever supporting structure for steel box girder pushing construction
CN111139742B (en) Method for mounting and dismounting highway bridge girder erection machine
CN108571894A (en) It is sintered the installation method of owner's exhaust duct
CN114045861B (en) Tower crane foundation connecting structure transferring force to existing column and construction method thereof
CN212714587U (en) Equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN118637498A (en) Converter drum sliding device in original steelmaking workshop and hoisting method
CN220059032U (en) Truss installation supporting device for dry coal shed
CN220550458U (en) Construction device for sliding and installing plate girder on rail in height-limiting environment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination