CN116446574A - Curtain wall connecting structure and curtain wall construction method - Google Patents
Curtain wall connecting structure and curtain wall construction method Download PDFInfo
- Publication number
- CN116446574A CN116446574A CN202310490876.8A CN202310490876A CN116446574A CN 116446574 A CN116446574 A CN 116446574A CN 202310490876 A CN202310490876 A CN 202310490876A CN 116446574 A CN116446574 A CN 116446574A
- Authority
- CN
- China
- Prior art keywords
- screw
- groove
- vertical pipe
- curtain wall
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/885—Curtain walls comprising a supporting structure for flush mounted glazing panels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
- Finishing Walls (AREA)
Abstract
本发明属于建筑幕墙技术领域,公开了一种幕墙的连接结构及幕墙施工方法。该幕墙的连接结构及幕墙施工方法,包括竖管、两个横管和石板,所述竖管固定安装在墙面上,两个横管分设在竖管的两侧并与墙面固定连接,所述石板通过连接机构与竖管和横管固定连接,所述竖管的正面还通过吸附机构与石板连接,所述横管的正面开设有长孔。该幕墙的连接结构及幕墙施工方法,利用连接机构和吸附机构的设计,能够相互配和对石板进行固定,并利用活动杆的位移对拉绳进行拉伸,各结构紧密配合,加强石板安装后的稳定性,减少石板晃动的出现,并且另有上下相邻调控螺杆之间通过环形齿槽的卡接限位能够避免本方案连接结构的松动,解决了背景技术中提出的问题。
The invention belongs to the technical field of building curtain walls, and discloses a curtain wall connection structure and a curtain wall construction method. The curtain wall connection structure and curtain wall construction method include a vertical pipe, two horizontal pipes and stone slabs, the vertical pipe is fixedly installed on the wall, and the two horizontal pipes are respectively arranged on both sides of the vertical pipe and fixedly connected with the wall. The stone slab is fixedly connected to the vertical pipe and the horizontal pipe through a connecting mechanism, the front of the vertical pipe is also connected to the stone slab through an adsorption mechanism, and a long hole is opened on the front of the horizontal pipe. The connection structure of the curtain wall and the construction method of the curtain wall, using the design of the connection mechanism and the adsorption mechanism, can match each other and fix the stone slabs, and use the displacement of the movable rod to stretch the pull rope. The stability of the slab can reduce the occurrence of swaying of the slate, and the clamping limit between the upper and lower adjacent control screws through the annular tooth groove can avoid the loosening of the connection structure of this scheme, and solve the problems raised in the background technology.
Description
技术领域technical field
本发明涉及建筑幕墙的技术领域,具体为一种幕墙的连接结构及幕墙施工方法。The invention relates to the technical field of building curtain walls, in particular to a curtain wall connection structure and a curtain wall construction method.
背景技术Background technique
建筑幕墙指的是建筑物不承重的外墙围护,通常由面板如玻璃、金属板、石板、陶瓷板等和后面的支承结构如铝横梁立柱、钢结构、玻璃肋等等组成。Building curtain wall refers to the non-load-bearing exterior wall enclosure of a building, usually composed of panels such as glass, metal plates, stone plates, ceramic plates, etc., and supporting structures behind such as aluminum beams and columns, steel structures, glass ribs, etc.
针对石板幕墙来说,石板重量较大,由于石材重量沉,所以将石材挂置于墙面上时,必须保证其能牢固地挂置于预制件上,避免石材发生脱落而造成的意外事故,故此我们提出了一种幕墙的连接结构及幕墙施工方法。For the slate curtain wall, the weight of the slab is relatively heavy. Since the stone is heavy, when the stone is hung on the wall, it must be firmly hung on the prefabricated part to avoid accidents caused by the falling of the stone. Therefore, we propose a connection structure of the curtain wall and a construction method of the curtain wall.
发明内容Contents of the invention
本发明的发明目的在于提供了一种幕墙的连接结构及幕墙施工方法,该幕墙的连接结构安装便捷,操作方便,安装牢固,能够降低石板坠落风险,解决了背景技术中提出的问题。The object of the present invention is to provide a curtain wall connection structure and a curtain wall construction method. The curtain wall connection structure is easy to install, easy to operate, firm to install, can reduce the risk of falling stone slabs, and solve the problems raised in the background technology.
为实现以上目的,本发明通过以下技术方案予以实现:一种幕墙的连接结构及幕墙施工方法,包括竖管、两个横管和石板,所述竖管固定安装在墙面上,两个横管分设在竖管的两侧并与墙面固定连接,所述石板通过连接机构与竖管和横管固定连接,所述竖管的正面还通过吸附机构与石板连接,所述横管的正面开设有长孔,横管内滑动连接有活动块,所述活动块与横管靠近竖管的内壁之间通过压缩弹簧连接,活动块的正面安装有夹杆并通过长孔延伸而出;In order to achieve the above object, the present invention is achieved through the following technical solutions: a curtain wall connection structure and curtain wall construction method, including a vertical pipe, two horizontal pipes and stone slabs, the vertical pipe is fixed on the wall, two horizontal pipes The pipes are arranged on both sides of the vertical pipe and fixedly connected with the wall. The stone plate is fixedly connected with the vertical pipe and the horizontal pipe through the connecting mechanism. The front of the vertical pipe is also connected with the stone plate through the adsorption mechanism. The front of the horizontal pipe A long hole is opened, and a movable block is slidably connected in the horizontal tube. The movable block is connected with the inner wall of the horizontal tube close to the vertical pipe through a compression spring. The front of the movable block is equipped with a clamp bar and extends out through the long hole;
所述连接机构包括定位板、调控螺杆、滑块、螺孔、条形孔和挂杆,两个定位板对称固定在竖管的内壁上,调控螺杆穿过两个定位板并通过轴承一活动连接,两个滑块插接在竖管内,且两个滑块均通过其上开设的螺孔与调控螺杆螺纹连接,竖管正面的上下两端均开设有条形孔,挂杆穿过条形孔安装在滑块上,夹杆远离活动块的一端和挂杆远离滑块的一端均卡接在石板侧边的槽内。The connecting mechanism includes a positioning plate, a control screw, a slider, a screw hole, a strip hole and a hanging rod. The two positioning plates are symmetrically fixed on the inner wall of the standpipe, and the control screw passes through the two positioning plates and moves through the bearings. connection, the two sliders are plugged into the vertical tube, and the two sliders are threadedly connected with the control screw through the screw holes opened on it, the upper and lower ends of the front of the vertical tube are provided with strip holes, and the hanging rod passes through the strip The shaped hole is installed on the slide block, and the end of the clamping bar away from the movable block and the end of the hanging bar away from the slide block are all clamped in the groove on the side of the stone slab.
优选的,所述吸附机构包括连接管、连接块、吸盘、活塞槽、活动杆、活塞、侧槽、侧板、定位插槽、定位杆、拉伸螺杆、螺槽、锥形齿轮一和锥形齿轮二,所述连接管的一端固定连接在竖管的中部,连接块的一端固定连接在连接管的另一端,所述连接块的另一端固定安装有吸盘,且吸盘吸附在石板背面,活塞槽开设在连接块靠近竖管的一侧并与吸盘内侧连通,活动杆的一端插接在内并安装有活塞,活塞槽的侧壁上开设有若干个侧槽,侧板插接在侧槽内并与活动杆的侧壁固定连接,侧板靠近竖管的一侧开设有定位插槽,竖管上的定位杆插接在对应的定位插槽内为活动杆定位,活动杆靠近竖管的一侧开设有螺槽,竖管正面对应螺槽的位置通过轴承二活动连接有拉伸螺杆,且拉伸螺杆的一端螺纹连接在螺槽内,拉伸螺杆的另一端延伸至竖管内并固定连接有锥形齿轮一,调控螺杆上的锥形齿轮二与锥形齿轮一啮合。Preferably, the adsorption mechanism includes a connecting pipe, a connecting block, a suction cup, a piston groove, a movable rod, a piston, a side groove, a side plate, a positioning slot, a positioning rod, a stretching screw, a screw groove, a bevel gear-and a cone Shaped gear 2, one end of the connecting pipe is fixedly connected to the middle of the vertical pipe, one end of the connecting block is fixedly connected to the other end of the connecting pipe, the other end of the connecting block is fixedly installed with a suction cup, and the suction cup is adsorbed on the back of the stone slab, The piston groove is set on the side of the connection block close to the vertical pipe and communicates with the inside of the suction cup. One end of the movable rod is inserted into it and a piston is installed. There are several side grooves on the side wall of the piston groove, and the side plates are inserted into the side. The groove is fixedly connected with the side wall of the movable rod. A positioning slot is provided on the side of the side plate close to the vertical pipe. The positioning rod on the vertical pipe is inserted into the corresponding positioning slot to position the movable rod. The movable rod is close to the vertical pipe There is a screw groove on one side of the pipe, and the position corresponding to the screw groove on the front of the standpipe is movably connected with a stretching screw through the bearing two, and one end of the stretching screw is threaded in the screw groove, and the other end of the stretching screw extends into the vertical pipe And bevel gear 1 is fixedly connected, and bevel gear 2 on the control screw rod meshes with bevel gear 1.
优选的,所述侧槽的长度是活塞槽长度的二分之一,所述拉伸螺杆与螺槽底壁接触时活塞与活塞槽底壁空间不与侧槽连通。Preferably, the length of the side groove is half of the length of the piston groove, and the space between the piston and the bottom wall of the piston groove does not communicate with the side groove when the stretching screw is in contact with the bottom wall of the screw groove.
优选的,所述石板的背面固定连接有若干个环形排列的贴板,所述贴板的背面设有挂环,所述连接管上开设有若干个穿孔,侧板上固定连接有拉绳的一端,拉绳的另一端穿过穿孔通过其上的连接环与挂环挂接。Preferably, the back of the slate is fixedly connected with several circularly arranged sticking plates, the back of the sticking plate is provided with a hanging ring, the connecting pipe is provided with several perforations, and the side plate is fixedly connected with a drawstring. At one end, the other end of the stay rope passes through the perforation and is articulated with the hanging ring through the connecting ring thereon.
优选的,两个所述滑块上的螺孔内螺纹相同,调控螺杆上下两部分的螺纹相反。Preferably, the inner threads of the screw holes on the two sliders are the same, and the upper and lower parts of the regulating screw have opposite threads.
优选的,所述调控螺杆的两端均设有环形齿槽,且调控螺杆的底端向下延伸出竖管且低于石板底部。Preferably, both ends of the regulating screw are provided with annular tooth grooves, and the bottom of the regulating screw extends downward out of the vertical pipe and is lower than the bottom of the slate.
优选的,两个所述横管与竖管相垂直,且两个长孔和两个条形孔四者以拉伸螺杆为轴心环形排列。Preferably, the two horizontal tubes are perpendicular to the vertical tube, and the two long holes and the two bar-shaped holes are arranged circularly around the stretching screw as the axis.
一种幕墙连接结构的施工方法,所述施工方法包括以下步骤:A construction method of a curtain wall connection structure, the construction method comprising the following steps:
步骤一,利用膨胀螺丝将竖管和横管安装在墙面上,转动调控螺杆将滑块移动至条形孔远离竖管中部的一端,完成预设;Step 1: Use expansion screws to install the vertical pipe and horizontal pipe on the wall, turn the adjusting screw to move the slider to the end of the strip hole away from the middle of the vertical pipe, and complete the preset;
步骤二,进行石板安装,将两个夹杆卡接在石板侧壁的槽内,使吸盘吸附在石板背面,将两个挂杆卡入石板侧壁的槽内,完成预固定后,转动调控螺杆使两个滑块靠近,两个挂杆夹住石板,将连接环挂在挂环上,同时活动杆由活塞槽内向外拔出抽出吸盘内的空气加强吸盘对石板的吸附,并对拉绳进行拉扯拉紧石板加强固定,上下相邻的幕墙安装时应确保上方的调控螺杆底端与下方调控螺杆的顶端卡接。Step 2, install the stone slab, snap the two clamping rods into the groove on the side wall of the stone slab, make the suction cup adsorb on the back of the stone slab, snap the two hanging rods into the groove on the side wall of the stone slab, after pre-fixing, turn and adjust The screw makes the two sliders approach, the two hanging rods clamp the stone plate, hang the connecting ring on the hanging ring, and at the same time, the movable rod is pulled out from the piston groove to draw out the air in the suction cup to strengthen the suction cup’s adsorption on the stone plate, and The pull rope is used to pull and tighten the stone slab to strengthen and fix it. When installing the upper and lower adjacent curtain walls, ensure that the bottom end of the upper control screw is clamped with the top of the lower control screw.
通过采用前述技术方案,本发明的有益效果是:By adopting the aforementioned technical scheme, the beneficial effects of the present invention are:
该幕墙的连接结构及幕墙施工方法,利用连接机构和吸附机构的设计,能够相互配和对石板进行固定,并利用活动杆的位移对拉绳进行拉伸,各结构紧密配合,加强石板安装后的稳定性,减少石板晃动的出现,并且另有上下相邻调控螺杆之间通过环形齿槽的卡接限位能够避免本方案连接结构的松动,解决了背景技术中提出的问题。The connection structure of the curtain wall and the construction method of the curtain wall, using the design of the connection mechanism and the adsorption mechanism, can match each other and fix the stone slabs, and use the displacement of the movable rod to stretch the pull rope. The stability of the slab can reduce the occurrence of rocking, and the clamping limit between the upper and lower adjacent control screws through the annular tooth groove can avoid the loosening of the connection structure of this scheme, and solve the problems raised in the background technology.
附图说明Description of drawings
图1为本发明正视图;Fig. 1 is the front view of the present invention;
图2为本发明图1中A-A截面图;Fig. 2 is A-A sectional view among Fig. 1 of the present invention;
图3为本发明图2中A处的放大图;Fig. 3 is the enlarged view of place A in Fig. 2 of the present invention;
图4为本发明除去石板后正视图;Fig. 4 is the front view of the present invention after removing the slate;
图5为本发明环形齿槽的结构示意图。Fig. 5 is a schematic structural view of the annular tooth groove of the present invention.
图中:1竖管、2横管、3石板、In the picture: 1 vertical pipe, 2 horizontal pipes, 3 stone slabs,
4连接机构、41定位板、42调控螺杆、43滑块、44螺孔、45条形孔、46挂杆、4 connection mechanism, 41 positioning plate, 42 control screw, 43 slider, 44 screw hole, 45 strip hole, 46 hanging rod,
5吸附机构、51连接管、52连接块、53吸盘、54活塞槽、55活动杆、56活塞、57侧槽、58侧板、59定位插槽、510定位杆、511拉伸螺杆、512螺槽、513锥形齿轮一、514锥形齿轮二、5 adsorption mechanism, 51 connecting pipe, 52 connecting block, 53 suction cup, 54 piston groove, 55 movable rod, 56 piston, 57 side groove, 58 side plate, 59 positioning slot, 510 positioning rod, 511 stretching screw rod, 512 screw Slot, 513 bevel gear one, 514 bevel gear two,
6长孔、7活动块、8压缩弹簧、9夹杆、10贴板、11挂环、12穿孔、13拉绳、14连接环、15环形齿槽。6 long holes, 7 movable blocks, 8 compression springs, 9 clamping rods, 10 sticking plates, 11 hanging rings, 12 perforations, 13 drawstrings, 14 connecting rings, 15 annular tooth grooves.
具体实施方式Detailed ways
请参阅图1-5,本发明提供一种技术方案:一种幕墙的连接结构及幕墙施工方法,包括竖管1、两个横管2和石板3,竖管1固定安装在墙面上,两个横管2分设在竖管1的两侧并与墙面固定连接,石板3通过连接机构4与竖管1和横管2固定连接,竖管1的正面还通过吸附机构5与石板3连接,横管2的正面开设有长孔6,横管2内滑动连接有活动块7,活动块7与横管2靠近竖管1的内壁之间通过压缩弹簧8连接,活动块7的正面安装有夹杆9并通过长孔6延伸而出,压缩弹簧8处于平衡状态时,活动块7处于长孔6靠近竖管1的一端;Please refer to Figures 1-5, the present invention provides a technical solution: a curtain wall connection structure and curtain wall construction method, including a vertical pipe 1, two horizontal pipes 2 and stone slabs 3, the vertical pipe 1 is fixedly installed on the wall, Two horizontal pipes 2 are arranged on both sides of the vertical pipe 1 and are fixedly connected with the wall. The stone plate 3 is fixedly connected with the vertical pipe 1 and the horizontal pipe 2 through the connecting mechanism 4. The front of the vertical pipe 1 is also connected with the stone plate 3 through the adsorption mechanism 5. connection, the front of the horizontal tube 2 is provided with a long hole 6, and a movable block 7 is slidingly connected in the horizontal tube 2, and the movable block 7 is connected with the inner wall of the horizontal tube 2 close to the vertical tube 1 by a compression spring 8, and the front of the movable block 7 A clamping rod 9 is installed and extends out through the long hole 6. When the compression spring 8 is in a balanced state, the movable block 7 is at the end of the long hole 6 close to the vertical pipe 1;
连接机构4包括定位板41、调控螺杆42、滑块43、螺孔44、条形孔45和挂杆46,两个定位板41对称固定在竖管1的内壁上,调控螺杆42穿过两个定位板41并通过轴承一活动连接,两个滑块43插接在竖管1内,且两个滑块43均通过其上开设的螺孔44与调控螺杆42螺纹连接,竖管1正面的上下两端均开设有条形孔45,挂杆46穿过条形孔45安装在滑块43上,夹杆9远离活动块7的一端和挂杆46远离滑块43的一端均卡接在石板3侧边的槽内,夹杆9和挂杆46与石板3侧壁槽卡接的一端均呈L型,且其于石板3接触位置粘接有保护橡胶垫,为石板3提供保护,并且避免硬接触对石板3造成的伤害。The connecting mechanism 4 comprises a positioning plate 41, a control screw 42, a slide block 43, a screw hole 44, a strip hole 45 and a hanging rod 46, and the two positioning plates 41 are symmetrically fixed on the inner wall of the standpipe 1, and the control screw 42 passes through the two A positioning plate 41 is movably connected by a bearing, two slide blocks 43 are plugged in the standpipe 1, and the two slide blocks 43 are threadedly connected with the regulating screw 42 through the screw holes 44 provided thereon, the standpipe 1 front The upper and lower ends of the upper and lower ends are all provided with strip holes 45, and the hanging rod 46 passes through the strip hole 45 and is installed on the slider 43. In the groove on the side of the slate 3, the clamping rod 9 and the hanging rod 46 are L-shaped at the end of the clamping connection with the side wall groove of the slate 3, and a protective rubber pad is bonded to the contact position of the slate 3 to provide protection for the slate 3. , and avoid hard contact damage to slate 3.
吸附机构5包括连接管51、连接块52、吸盘53、活塞槽54、活动杆55、活塞56、侧槽57、侧板58、定位插槽59、定位杆510、拉伸螺杆511、螺槽512、锥形齿轮一513和锥形齿轮二514,连接管51的一端固定连接在竖管1的中部,连接块52的一端固定连接在连接管51的另一端,连接块52的另一端固定安装有吸盘53,且吸盘53吸附在石板3背面,活塞槽54开设在连接块52靠近竖管1的一侧并与吸盘53内侧连通,活动杆55的一端插接在内并安装有活塞56,活塞槽54的侧壁上开设有若干个侧槽57,侧板58插接在侧槽57内并与活动杆55的侧壁固定连接,侧板58靠近竖管1的一侧开设有定位插槽59,竖管1上的定位杆510插接在对应的定位插槽59内为活动杆55定位,活动杆55靠近竖管1的一侧开设有螺槽512,竖管1正面对应螺槽512的位置通过轴承二活动连接有拉伸螺杆511,且拉伸螺杆511的一端螺纹连接在螺槽512内,拉伸螺杆511的另一端延伸至竖管1内并固定连接有锥形齿轮一513,调控螺杆42上的锥形齿轮二514与锥形齿轮一513啮合。Adsorption mechanism 5 comprises connecting pipe 51, connecting block 52, suction cup 53, piston groove 54, movable rod 55, piston 56, side groove 57, side plate 58, positioning slot 59, positioning rod 510, stretching screw rod 511, screw groove 512, bevel gear one 513 and bevel gear two 514, one end of the connecting pipe 51 is fixedly connected to the middle part of the vertical pipe 1, one end of the connecting block 52 is fixedly connected to the other end of the connecting pipe 51, and the other end of the connecting block 52 is fixed A suction cup 53 is installed, and the suction cup 53 is adsorbed on the back of the slate 3. The piston groove 54 is provided on the side of the connection block 52 close to the vertical pipe 1 and communicates with the inside of the suction cup 53. One end of the movable rod 55 is plugged in and a piston 56 is installed. , the side wall of the piston groove 54 is provided with several side slots 57, the side plate 58 is inserted into the side slot 57 and fixedly connected with the side wall of the movable rod 55, and the side plate 58 near the side of the standpipe 1 is provided with a positioning Slot 59, the positioning rod 510 on the standpipe 1 is plugged in the corresponding positioning slot 59 for the positioning of the movable rod 55, and the movable rod 55 is provided with a screw groove 512 near the side of the vertical pipe 1, and the front of the vertical pipe 1 corresponds to the screw groove 512. The position of the groove 512 is movably connected with a stretching screw 511 through the bearing 2, and one end of the stretching screw 511 is screwed into the screw groove 512, and the other end of the stretching screw 511 extends into the standpipe 1 and is fixedly connected with a bevel gear One 513, the bevel gear two 514 on the control screw 42 meshes with the bevel gear one 513.
侧槽57的长度是活塞槽54长度的二分之一,拉伸螺杆511与螺槽512底壁接触时活塞56与活塞槽54底壁空间不与侧槽57连通,活塞槽54内密封不受侧槽57的影响,在长期安装的工况下,能够确保吸盘53与石板3件的密封,同时为提高密封,应选用经过抛光处理的石板3。The length of side groove 57 is 1/2nd of piston groove 54 lengths, and piston 56 is not communicated with side groove 57 with piston groove 54 bottom wall space when stretching screw rod 511 contacts with screw groove 512 bottom walls, and seal is not sealed in piston groove 54. Affected by the side groove 57, under long-term installation conditions, the sealing between the suction cup 53 and the 3 stone slabs can be ensured. At the same time, in order to improve the sealing, the polished slate 3 should be selected.
石板3的背面固定连接有若干个环形排列的贴板10,贴板10可采用粘接或者使用螺栓进行固定,贴板10的背面设有挂环11,连接管51上开设有若干个穿孔12,侧板58上固定连接有拉绳13的一端,拉绳13的另一端穿过穿孔12通过其上的连接环14与挂环11挂接,活动杆55由活塞槽54内拉出时能够绷紧拉绳13,拉动石板3,减少石板3下坠趋势,能够避免石板3受震动的影响。The back side of the slate 3 is fixedly connected with several circularly arranged veneers 10, the veneers 10 can be fixed by bonding or using bolts, the back side of the veneer 10 is provided with a hanging ring 11, and the connecting pipe 51 is provided with several perforations 12 On the side plate 58, one end of the stay cord 13 is fixedly connected, and the other end of the stay cord 13 passes through the perforation 12 and is articulated with the hanging ring 11 through the connecting ring 14 thereon. When the movable rod 55 is pulled out from the piston groove 54, it can Tighten the stay rope 13 to pull the slate 3 to reduce the tendency of the slate 3 to fall and avoid the slate 3 from being affected by the vibration.
两个滑块43上的螺孔44内螺纹相同,调控螺杆42上下两部分的螺纹相反,调控螺杆42正反转可控制两个滑块43靠近或远离。The internal threads of the screw holes 44 on the two slide blocks 43 are the same, and the threads of the upper and lower parts of the regulating screw 42 are opposite.
调控螺杆42的两端均设有环形齿槽15,且调控螺杆42的底端向下延伸出竖管1且低于石板3底部。Both ends of the regulating screw 42 are provided with annular tooth grooves 15 , and the bottom of the regulating screw 42 extends downwards out of the vertical pipe 1 and is lower than the bottom of the slate 3 .
两个横管2与竖管1相垂直,且两个长孔6和两个条形孔45四者以拉伸螺杆511为轴心环形排列。The two horizontal tubes 2 are perpendicular to the vertical tube 1, and the two elongated holes 6 and the two bar-shaped holes 45 are arranged circularly with the stretching screw 511 as the axis.
一种幕墙连接结构的施工方法,施工方法包括以下步骤:A construction method of a curtain wall connection structure, the construction method comprising the following steps:
步骤一,利用膨胀螺丝将竖管1和横管2安装在墙面上,转动调控螺杆42将滑块43移动至条形孔45远离竖管1中部的一端,完成预设;Step 1: Install the vertical pipe 1 and the horizontal pipe 2 on the wall with expansion screws, and turn the control screw 42 to move the slider 43 to the end of the strip hole 45 away from the middle of the vertical pipe 1 to complete the preset;
步骤二,进行石板3安装,将两个夹杆9卡接在石板3侧壁的槽内,使吸盘53吸附在石板3背面,将两个挂杆46卡入石板3侧壁的槽内,完成预固定后,转动调控螺杆42使两个滑块43靠近,两个挂杆46夹住石板3,将连接环14挂在挂环11上,同时活动杆55由活塞槽54内向外拔出抽出吸盘53内的空气加强吸盘53对石板3的吸附,并对拉绳13进行拉扯拉紧石板3加强固定,上下相邻的幕墙安装时应确保上方的调控螺杆42底端与下方调控螺杆42的顶端卡接。Step 2, install the slate 3, clamp the two clamping rods 9 into the grooves on the side wall of the slate 3, make the suction cup 53 adsorb on the back of the slate 3, snap the two hanging rods 46 into the grooves on the side wall of the slate 3, After the pre-fixation is completed, turn the control screw 42 to make the two sliders 43 approach, the two hanging rods 46 clamp the slate 3, hang the connecting ring 14 on the hanging ring 11, and at the same time, the movable rod 55 is pulled out from the piston groove 54 Take out the air in the suction cup 53 to strengthen the adsorption of the suction cup 53 to the slate 3, and pull the pull cord 13 to tighten the slate 3 to strengthen and fix it. When installing the upper and lower adjacent curtain walls, ensure that the bottom of the upper control screw 42 is connected with the lower control screw 42. The top snaps together.
对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其它实施例中实现,因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。Various modifications to these embodiments will be obvious to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present invention, so , the present invention will not be limited to these embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310490876.8A CN116446574B (en) | 2023-05-04 | 2023-05-04 | A curtain wall connection structure and curtain wall construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310490876.8A CN116446574B (en) | 2023-05-04 | 2023-05-04 | A curtain wall connection structure and curtain wall construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN116446574A true CN116446574A (en) | 2023-07-18 |
| CN116446574B CN116446574B (en) | 2025-04-08 |
Family
ID=87133692
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310490876.8A Active CN116446574B (en) | 2023-05-04 | 2023-05-04 | A curtain wall connection structure and curtain wall construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116446574B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117188673A (en) * | 2023-10-26 | 2023-12-08 | 中国二十二冶集团有限公司 | Curtain wall panel mounting structure |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002013233A (en) * | 2000-06-30 | 2002-01-18 | Kajima Corp | Large glass surface support structure |
| CN109457849A (en) * | 2018-11-05 | 2019-03-12 | 湖州礼谦建材贸易有限公司 | A kind of connection structure of building decoration curtain wall and wall |
| CN214034268U (en) * | 2020-11-24 | 2021-08-24 | 苏州美瑞德建筑装饰有限公司 | A design structure of a unitized curtain wall with a fully hidden frame glass unit |
| CN214195117U (en) * | 2020-11-03 | 2021-09-14 | 沈阳众泰幕墙工程有限公司 | A fast-installed curtain wall based on architectural decoration |
| CN113668743A (en) * | 2021-10-21 | 2021-11-19 | 湖南中翔建设集团有限公司 | Building curtain wall with anti-drop protect function |
| CN214941420U (en) * | 2021-05-31 | 2021-11-30 | 薛峰 | Building curtain anti-drop device that can adjust |
| CN215830096U (en) * | 2021-08-16 | 2022-02-15 | 广东凯宏建设工程有限公司 | Curtain strutting arrangement for construction |
| CN217353105U (en) * | 2022-08-04 | 2022-09-02 | 宿迁博辰科技信息有限公司 | Building curtain wall structure with heat preservation performance |
| CN218143704U (en) * | 2021-08-11 | 2022-12-27 | 陈柏玮 | Sucking disc is used in installation of glass curtain wall of adjustable use |
| CN218492795U (en) * | 2022-09-22 | 2023-02-17 | 安徽辰翔建筑工程有限公司 | Curtain wall supporting device applied to building construction |
-
2023
- 2023-05-04 CN CN202310490876.8A patent/CN116446574B/en active Active
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002013233A (en) * | 2000-06-30 | 2002-01-18 | Kajima Corp | Large glass surface support structure |
| CN109457849A (en) * | 2018-11-05 | 2019-03-12 | 湖州礼谦建材贸易有限公司 | A kind of connection structure of building decoration curtain wall and wall |
| CN214195117U (en) * | 2020-11-03 | 2021-09-14 | 沈阳众泰幕墙工程有限公司 | A fast-installed curtain wall based on architectural decoration |
| CN214034268U (en) * | 2020-11-24 | 2021-08-24 | 苏州美瑞德建筑装饰有限公司 | A design structure of a unitized curtain wall with a fully hidden frame glass unit |
| CN214941420U (en) * | 2021-05-31 | 2021-11-30 | 薛峰 | Building curtain anti-drop device that can adjust |
| CN218143704U (en) * | 2021-08-11 | 2022-12-27 | 陈柏玮 | Sucking disc is used in installation of glass curtain wall of adjustable use |
| CN215830096U (en) * | 2021-08-16 | 2022-02-15 | 广东凯宏建设工程有限公司 | Curtain strutting arrangement for construction |
| CN113668743A (en) * | 2021-10-21 | 2021-11-19 | 湖南中翔建设集团有限公司 | Building curtain wall with anti-drop protect function |
| CN217353105U (en) * | 2022-08-04 | 2022-09-02 | 宿迁博辰科技信息有限公司 | Building curtain wall structure with heat preservation performance |
| CN218492795U (en) * | 2022-09-22 | 2023-02-17 | 安徽辰翔建筑工程有限公司 | Curtain wall supporting device applied to building construction |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117188673A (en) * | 2023-10-26 | 2023-12-08 | 中国二十二冶集团有限公司 | Curtain wall panel mounting structure |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116446574B (en) | 2025-04-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210685093U (en) | Quick installation mechanism of curtain | |
| CN116446574B (en) | A curtain wall connection structure and curtain wall construction method | |
| CN211572472U (en) | A scaffolding for building construction | |
| CN219654392U (en) | A prefabricated steel structure factory building structure | |
| CN208934214U (en) | A kind of stone curtain wall fixed structure | |
| CN209040376U (en) | A kind of tempered glass curtain wall for being easy to splice | |
| CN218971989U (en) | Mounting structure convenient to air conditioner galvanized air pipe is dismantled | |
| CN217848883U (en) | Two-way crane span structure antidetonation support of convenient equipment | |
| CN209457786U (en) | A kind of energy-saving heat-insulating insulating aluminum alloy window | |
| CN214034250U (en) | Architectural decoration curtain wall | |
| CN210600443U (en) | Novel water supply and drainage pipe installation and fixation device | |
| CN210105065U (en) | Building curtain wall fixing bracket | |
| CN216479593U (en) | A seismic connection structure for building structure design | |
| CN219473065U (en) | A Rectangular Air Duct Seismic Support and Hanger | |
| CN207177315U (en) | A kind of build concrete hollow brick masonry device | |
| CN217300335U (en) | Energy-saving window with double-layer glass | |
| CN222630779U (en) | Elevator car furred ceiling structure | |
| CN207568015U (en) | A kind of high intensity curtain wall support structure for building | |
| CN219825756U (en) | Assembled building curtain wall mounting structure | |
| CN218091485U (en) | A curtain wall structure that is easy to clean | |
| CN221277299U (en) | Just, tear open structure for aluminum plate curtain installation | |
| CN222161693U (en) | Dry-sealed structure of non-vertical frame glass curtain wall | |
| CN219654024U (en) | Building curtain wall mounting structure | |
| CN222140446U (en) | A ceiling support structure | |
| CN218216483U (en) | An anti-seismic supporting base for cable bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |