CN116201344A - A lifting construction platform for hoistway elevator steel structure installation - Google Patents

A lifting construction platform for hoistway elevator steel structure installation Download PDF

Info

Publication number
CN116201344A
CN116201344A CN202310020614.5A CN202310020614A CN116201344A CN 116201344 A CN116201344 A CN 116201344A CN 202310020614 A CN202310020614 A CN 202310020614A CN 116201344 A CN116201344 A CN 116201344A
Authority
CN
China
Prior art keywords
frame
lifting
lifting frame
steel structure
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310020614.5A
Other languages
Chinese (zh)
Inventor
赵家禹
赵成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huasen Tianao Chongqing Electromechanical Co ltd
Original Assignee
Huasen Tianao Chongqing Electromechanical Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huasen Tianao Chongqing Electromechanical Co ltd filed Critical Huasen Tianao Chongqing Electromechanical Co ltd
Priority to CN202310020614.5A priority Critical patent/CN116201344A/en
Publication of CN116201344A publication Critical patent/CN116201344A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B50/00Energy efficient technologies in elevators, escalators and moving walkways, e.g. energy saving or recuperation technologies

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

The invention relates to a lifting construction platform for mounting a steel structure of a hoistway elevator, which belongs to the technical field of elevators and comprises an outer lifting frame; an inner lifting frame slidably mounted in the inner lifting frame; the workbench is arranged at one end of the inner lifting frame far away from the outer lifting frame; one end of the bidirectional lifting piece is connected with the outer lifting frame, and the other end is connected with the inner lifting frame. According to the invention, the outer lifting frame and the inner lifting frame are in lifting fit, the workbench is arranged on the inner lifting frame, and the whole lifting construction platform can gradually pass through the inner lifting frame and the outer lifting frame which are in telescopic fit from the bottom, so that ascending and descending are realized; the problems that four sides are required to be constructed independently, the danger coefficient is high, the efficiency is low and the like are avoided, the height of the inner frame can be automatically adjusted in the construction process, and the construction is more convenient.

Description

一种用于井道电梯钢结构安装的升降施工平台A lifting construction platform for hoistway elevator steel structure installation

技术领域technical field

本发明涉及电梯技术领域,具体是一种用于井道电梯钢结构安装的升降施工平台。The invention relates to the technical field of elevators, in particular to an elevating construction platform used for installing a hoistway elevator steel structure.

背景技术Background technique

电梯钢结构是电梯的重要部分,负担着承重的艰巨任务。电梯钢结构的力学状况直接影响到电梯运行的安全性。The steel structure of the elevator is an important part of the elevator, which bears the arduous task of load-bearing. The mechanical condition of the elevator steel structure directly affects the safety of the elevator operation.

在观光电梯和旧房加装电梯时,传统方式是在加装电梯钢结构井道外部搭设施工架管,以架管为着力固定点用卷扬机向上牵引钢结构材料,施工人员在架管上作业。这种施工方法缺陷在于:一是因施工人员缺少作业平台及频繁通过架管上下安全隐患较大;二是搭设架管占用面积空间较大,影响环境;三是搭设架管施工时间较长、成本较高;四是因作业环境限制安装工艺质量难于控制;五是目前的作业平台需要四个面单独施工,存在危险系数大、效率低等问题,无法实现逐步向上施工。When adding elevators to sightseeing elevators and old houses, the traditional method is to build construction pipes outside the elevator steel structure shaft, use the pipes as the fixed point to pull the steel structure materials upwards with a hoist, and construction workers work on the pipes. The disadvantages of this construction method are: first, the construction personnel lack the operating platform and frequently pass the erection pipe up and down the safety hazards are relatively large; second, the erection of the erection pipe occupies a large area and affects the environment; The cost is high; the fourth is that the quality of the installation process is difficult to control due to the limitation of the working environment; the fifth is that the current working platform requires separate construction on four sides, which has problems such as high risk factor and low efficiency, and it is impossible to realize gradual upward construction.

发明内容Contents of the invention

本发明的目的在于提供一种用于井道电梯钢结构安装的升降施工平台,在井道内升降安装有升降施工平台组件,施工平台组件通过升降结构逐级向上爬升施工,施工平台组件分成四个升缩的施工平台,适应不同位置的施工作业。The object of the present invention is to provide a lifting construction platform used for the installation of the hoistway elevator steel structure. The lifting construction platform assembly is installed in the hoistway. The construction platform assembly climbs upwards step by step through the lifting structure. The shrinkable construction platform is suitable for construction operations in different positions.

为实现上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:

一种用于井道电梯钢结构安装的升降施工平台,包括:A lifting construction platform for hoistway elevator steel structure installation, comprising:

外升降框架;External lifting frame;

内升降框架,滑动安装在所述外升降框架内;The inner lifting frame is slidably installed in the outer lifting frame;

工作台,安装在所述内升降框架远离外升降框架的一端;The workbench is installed on the end of the inner lifting frame away from the outer lifting frame;

双向升降件,一端与所述外升降框架相连,另一端与所述内升降框架相连。The two-way lifting part is connected with the outer lifting frame at one end and connected with the inner lifting frame at the other end.

作为本发明的进一步技术方案,所述外升降框架包括:As a further technical solution of the present invention, the outer lifting frame includes:

外框架;outer frame;

外框架下端连接梁,固定安装在所述外框架一端;The connecting beam at the lower end of the outer frame is fixedly installed at one end of the outer frame;

外框架上端连接梁,固定安装在所述外框架远离外框架下端连接梁的一端。The connecting beam at the upper end of the outer frame is fixedly installed at the end of the outer frame away from the connecting beam at the lower end of the outer frame.

作为本发明的更进一步技术方案,所述外升降框架还包括:As a further technical solution of the present invention, the outer lifting frame also includes:

外框架伸缩支撑梁,固定安装在所述外框架下端连接梁上;The telescopic support beam of the outer frame is fixedly installed on the connecting beam at the lower end of the outer frame;

第一固定支脚,安装在所述外框架伸缩支撑梁一端;The first fixed foot is installed at one end of the telescopic support beam of the outer frame;

第二固定支脚,安装在所述外框架伸缩支撑梁远离第一固定支脚的一端。The second fixed foot is installed on the end of the telescopic support beam of the outer frame away from the first fixed foot.

作为本发明的再进一步技术方案,所述第一固定支脚和第二固定支脚上均安装有第一旋紧螺栓。As a further technical solution of the present invention, first tightening bolts are installed on the first fixing leg and the second fixing leg.

作为本发明的再进一步技术方案,所述内升降框架包括:As a further technical solution of the present invention, the inner lifting frame includes:

内框架上端连接梁,固定安装在所述内框架一端;The connecting beam at the upper end of the inner frame is fixedly installed at one end of the inner frame;

内框架下端连接梁,固定安装在所述内框架远离内框架上端连接梁的一端。The connecting beam at the lower end of the inner frame is fixedly installed at the end of the inner frame away from the connecting beam at the upper end of the inner frame.

作为本发明的再进一步技术方案,所述内升降框架还包括:As a further technical solution of the present invention, the inner lifting frame also includes:

内框架伸缩支撑梁,固定安装在所述内框架下端连接梁上;The telescopic support beam of the inner frame is fixedly installed on the connecting beam at the lower end of the inner frame;

第三固定支脚,安装在所述内框架伸缩支撑梁一端;The third fixed foot is installed at one end of the telescopic support beam of the inner frame;

第四固定支脚,安装在所述内框架伸缩支撑梁远离第三固定支脚的一端。The fourth fixed foot is installed on the end of the telescopic support beam of the inner frame away from the third fixed foot.

作为本发明的再进一步技术方案,所述第三固定支脚和第四固定支脚上均安装有第二旋紧螺栓。As a further technical solution of the present invention, second tightening bolts are installed on the third fixing leg and the fourth fixing leg.

作为本发明的再进一步技术方案,所述双向升降件为双向液压油缸,液压杆的一端连接外框架下端连接梁,另一端连接内框架的上端连接梁。As a further technical solution of the present invention, the two-way lifting member is a two-way hydraulic cylinder, one end of the hydraulic rod is connected to the lower connecting beam of the outer frame, and the other end is connected to the upper connecting beam of the inner frame.

作为本发明的再进一步技术方案,所述的外升降框架四个角为中空的C形立柱,所述的内升降框架四个角为矩管立柱,内升降框架的矩管立柱与外升降框架的C形间隙配合,内升降框架能在动力的带动下在外升降框架内自由滑动。As a further technical solution of the present invention, the four corners of the outer lifting frame are hollow C-shaped columns, the four corners of the inner lifting frame are rectangular tube columns, and the rectangular tube columns of the inner lifting frame are connected with the outer lifting frame. C-shaped clearance fit, the inner lifting frame can slide freely in the outer lifting frame under the drive of power.

作为本发明的再进一步技术方案,所述外框架和内框架上均安装有交叉设置的斜拉杆,所述斜拉杆两端安装有斜拉杆支耳。As a further technical solution of the present invention, the outer frame and the inner frame are equipped with diagonally arranged cross-stay rods, and the two ends of the diagonally-stayed rods are installed with diagonally-stayed rod lugs.

作为本发明的再进一步技术方案,所述工作台包括:As a further technical solution of the present invention, the workbench includes:

工作支撑台,固定安装在所述内框架上端连接梁上;The working support platform is fixedly installed on the connecting beam at the upper end of the inner frame;

架体,固定安装在所述工作支撑台远离内框架上端连接梁的一侧。The frame body is fixedly installed on the side of the working support table away from the connecting beam at the upper end of the inner frame.

作为本发明的再进一步技术方案,所述工作支撑台四周分别安装有与其滑动连接的第一可伸缩作业平台、第二可伸缩作业平台、第三可伸缩作业平台和第四可伸缩作业平台。As a further technical solution of the present invention, a first telescopic work platform, a second telescopic work platform, a third telescopic work platform and a fourth telescopic work platform are respectively installed around the working support platform in sliding connection with it.

与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:

1、外升降框架的第一支脚和第二支脚固定在钢结构横梁上时,液压杆油缸带动内升降框架向上推出,到达位置后内升降框架通过第三和第四支脚固定在横梁上,此时工作台上的四个伸缩平台可根据需要伸出进行作业。其次,当作业完成后,外升降框架的第一支脚和第二支脚收回,液压杆油缸带动外升降框架向上拉升,内外升降框架位置重合,此时将外框架通过第一支脚和第二支脚固定。就这样,通过液压油缸杆的配合,先将外升降框架固定,然后将内升降框架推出,作业完成后,将内升降框架固定,外升降框架向上拉升,通过内外框架的配合运动,完成整个装置的自身逐步爬升。1. When the first leg and the second leg of the outer lifting frame are fixed on the steel structure beam, the hydraulic rod cylinder drives the inner lifting frame to push upward. After reaching the position, the inner lifting frame is fixed on the beam through the third and fourth legs. The four telescopic platforms on the workbench can be stretched out for operation as needed. Secondly, when the operation is completed, the first leg and the second leg of the outer lifting frame are retracted, and the hydraulic rod cylinder drives the outer lifting frame to be pulled up, and the positions of the inner and outer lifting frames coincide. At this time, the outer frame passes through the first leg and the second leg fixed. In this way, through the cooperation of the hydraulic cylinder rod, the outer lifting frame is fixed first, and then the inner lifting frame is pushed out. After the operation is completed, the inner lifting frame is fixed, and the outer lifting frame is pulled upwards. The device itself climbs step by step.

2、当整个装置需要向下运动的时,将内升降框架固定,外框架向下升出,作业完成后,将外框架固定,内框架向下缩回。2. When the whole device needs to move downward, fix the inner lifting frame and lift the outer frame downward. After the work is completed, fix the outer frame and retract the inner frame downward.

3、爬升过程中,内升降框架向上运动时,四个伸缩平台需要为收回状态,外升降框架向上拉升时,四个伸缩平台可无须收回。下降过程中,外升降框架向下运动时,四个伸缩平台可无须收回,内升降框架向下运动时,四个伸缩平台需要为收回状态。3. During the climbing process, when the inner lifting frame moves upwards, the four telescopic platforms need to be retracted, and when the outer lifting frame is pulled upwards, the four telescopic platforms do not need to be retracted. During the descent, when the outer lifting frame moves downwards, the four telescopic platforms need not be retracted, and when the inner lifting frame moves downwards, the four telescopic platforms need to be retracted.

4、通过外升降框架和内升降框架配合,实现了多位置的稳定固定,施工的时候,能自由上升或者下降;四个伸缩作业平台能够独立伸出,既方便了对电梯钢结构的施工,也方便了工人同时进行外墙幕墙的安装等,实现更宽领域的作业;升降施工平台从电梯井道内部逐级向上爬升,避免占用了外侧的施工空间。4. Through the cooperation of the outer lifting frame and the inner lifting frame, the stable fixing of multiple positions is realized. During construction, it can rise or fall freely; the four telescopic work platforms can be extended independently, which is convenient for the construction of the steel structure of the elevator. It is also convenient for workers to install exterior walls and curtain walls at the same time to achieve wider field operations; the lifting construction platform climbs up step by step from the inside of the elevator shaft to avoid occupying the construction space outside.

5、避免了外侧安装升降机进行作业,需要四个面单独施工,危险系数大效率低等问题,同时能实现逐端向上施工,施工更加便捷。5. It avoids the problem of installing a lift on the outside for operation, requiring separate construction on four sides, high risk factor and low efficiency. At the same time, it can realize end-by-end upward construction, and the construction is more convenient.

附图说明Description of drawings

图1为本发明内升降框架伸出的侧视图;Fig. 1 is the side view that lifting frame stretches out in the present invention;

图2为本发明内升降框架伸出的主视图;Fig. 2 is the front view that the lifting frame of the present invention stretches out;

图3为本发明内升降框架未伸出的侧视图;Fig. 3 is the side view that lifting frame of the present invention does not stretch out;

图4为本发明内升降框架未伸出的主视图;Fig. 4 is the front view of the inner lifting frame of the present invention that does not stretch out;

图5为本发明中外升降框架的局部仰视图;Fig. 5 is a partial bottom view of the outer lifting frame of the present invention;

图6为本发明中外升降框架的局部俯视图;Fig. 6 is a partial top view of the outer lifting frame of the present invention;

图7为本发明中外升降框架的俯视图;Fig. 7 is the top view of the outer lifting frame of the present invention;

图8为图7中A处的放大结构示意图;Fig. 8 is a schematic diagram of an enlarged structure at A in Fig. 7;

图9为本发明中内升降框架的局部俯视图;Fig. 9 is a partial top view of the inner lifting frame in the present invention;

图10为本发明中内升降框架的局部仰视图;Fig. 10 is a partial bottom view of the inner lifting frame in the present invention;

图11为本发明中内升降框架的俯视图。Fig. 11 is a top view of the inner lifting frame in the present invention.

图中:1-外升降框架、11-外框架伸缩支撑梁、12-第一固定支脚、13-第二固定支脚、14-第一旋紧螺栓、15-C型立柱、101-外框架下端连接梁、102-外框架上端连接梁、2-内升降框架、21-内框架伸缩支撑梁、22-第三固定支脚、23-第四固定支脚、24-第二旋紧螺栓、25-斜拉杆、26-斜拉杆支耳、27-矩管立柱、201-内框架上端连接梁、202-内框架下端连接梁、3-工作台、31-工作支撑台、32-架体、33-第一可伸缩作业平台、34-第二可伸缩作业平台、35-第三可伸缩作业平台、36-第四可伸缩作业平台、4-支座、5-双向升降件。In the figure: 1-outer lift frame, 11-outer frame telescopic support beam, 12-first fixed foot, 13-second fixed foot, 14-first tightening bolt, 15-C-type column, 101-lower end of outer frame Connecting beam, 102-connecting beam at the upper end of outer frame, 2-inner lifting frame, 21-telescopic support beam of inner frame, 22-third fixed foot, 23-fourth fixed foot, 24-second tightening bolt, 25-oblique Tie rod, 26-diagonal tie rod lug, 27-rectangular tube column, 201-connecting beam at the upper end of the inner frame, 202-connecting beam at the lower end of the inner frame, 3-workbench, 31-working support platform, 32-frame body, 33-the first One telescopic work platform, 34-the second telescopic work platform, 35-the third telescopic work platform, 36-the fourth telescopic work platform, 4-support, 5-two-way lifter.

具体实施方式Detailed ways

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In describing the present invention, it should be understood that the terms "center", "longitudinal", "transverse", "length", "width", "thickness", "upper", "lower", "front", " Back", "Left", "Right", "Vertical", "Horizontal", "Top", "Bottom", "Inner", "Outer", "Clockwise", "Counterclockwise", "Axial", The orientation or positional relationship indicated by "radial", "circumferential", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying the referred device or element Must be in a particular orientation, be constructed in a particular orientation, and operate in a particular orientation, and therefore should not be construed as limiting the invention.

此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本发明的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be interpreted as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Thus, a feature defined as "first" and "second" may explicitly or implicitly include one or more of these features. In the description of the present invention, "plurality" means two or more, unless otherwise specifically defined.

在本发明中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, unless otherwise clearly specified and limited, terms such as "installation", "connection", "connection" and "fixation" should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection , or integrated; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary, and it can be the internal communication of two components or the interaction relationship between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention according to specific situations.

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the drawings in the embodiments of the present invention.

本发明实施例是这样实现的,如图1至图4所示的用于井道电梯钢结构安装的升降施工平台,包括:The embodiment of the present invention is achieved in this way, as shown in Figure 1 to Figure 4, the hoisting construction platform for hoistway elevator steel structure installation includes:

外升降框架1;Outer lifting frame 1;

内升降框架2,滑动安装在所述外升降框架1内;The inner lifting frame 2 is slidably installed in the outer lifting frame 1;

工作台3,安装在所述内升降框架2远离外升降框架1的一端;The workbench 3 is installed on the end of the inner lifting frame 2 away from the outer lifting frame 1;

双向升降件5,为双向液压油缸,液压油缸的一端通过支座4连接外框架下端连接梁,另一端连接内框架的上端连接梁。The two-way lifter 5 is a two-way hydraulic cylinder, one end of the hydraulic cylinder is connected to the lower connecting beam of the outer frame through the support 4, and the other end is connected to the upper connecting beam of the inner frame.

本发明在实际应用时,用于井道电梯钢结构安装的升降施工平台,先将外框架通过支脚固定在钢结构横梁上,通过液压油缸先内升降框架2向上升出,再将外升降框1向上升出,逐步随着安装好的钢结构横梁边施工边爬升。When the present invention is actually applied, the lifting construction platform used for hoistway elevator steel structure installation first fixes the outer frame on the steel structure beam through the feet, first lifts the inner lifting frame 2 upwards through the hydraulic cylinder, and then lifts the outer lifting frame 1 Rise upwards, and gradually climb along with the installed steel structure beams while constructing.

如图1至图11所示,作为本发明一个优选的实施例,所述外升降框架1包括:As shown in Figures 1 to 11, as a preferred embodiment of the present invention, the outer lifting frame 1 includes:

外框架;outer frame;

C型立柱15,固定安装在所述外框架上;C-shaped column 15, fixedly installed on the outer frame;

外框架下端连接梁101,固定安装在所述外框架一端;The connecting beam 101 at the lower end of the outer frame is fixedly installed at one end of the outer frame;

外框架上端连接梁102,固定安装在所述外框架远离外框架下端连接梁101的一端;The connecting beam 102 at the upper end of the outer frame is fixedly installed on the end of the outer frame away from the connecting beam 101 at the lower end of the outer frame;

外框架伸缩支撑梁11,固定安装在所述外框架下端连接梁101上;The telescopic support beam 11 of the outer frame is fixedly installed on the connecting beam 101 at the lower end of the outer frame;

第一固定支脚12,安装在所述外框架伸缩支撑梁11一端;The first fixed foot 12 is installed on one end of the telescopic support beam 11 of the outer frame;

第二固定支脚13,安装在所述外框架伸缩支撑梁11远离第一固定支脚12的一端;The second fixed foot 13 is installed on the end of the outer frame telescopic support beam 11 away from the first fixed foot 12;

第一旋紧螺栓14,安装在所述第一固定支脚12和第二固定支脚13上;The first tightening bolt 14 is installed on the first fixed foot 12 and the second fixed foot 13;

所述内升降框架2包括:The inner lifting frame 2 includes:

内框架上端连接梁201,固定安装在所述内框架一端;The connecting beam 201 at the upper end of the inner frame is fixedly installed at one end of the inner frame;

内框架下端连接梁202,固定安装在所述内框架远离内框架上端连接梁201的一端;The connecting beam 202 at the lower end of the inner frame is fixedly installed on the end of the inner frame away from the upper connecting beam 201 of the inner frame;

内框架伸缩支撑梁21,固定安装在所述内框架下端连接梁202上;The telescopic support beam 21 of the inner frame is fixedly installed on the connecting beam 202 at the lower end of the inner frame;

第三固定支脚22,安装在所述内框架伸缩支撑梁21一端;The third fixed leg 22 is installed on one end of the telescopic support beam 21 of the inner frame;

第四固定支脚23,安装在所述内框架伸缩支撑梁21远离第三固定支脚22的一端;The fourth fixed foot 23 is installed on the end of the inner frame telescopic support beam 21 away from the third fixed foot 22;

第二旋紧螺栓24,安装在所述第三固定支脚22和第四固定支脚23上。The second tightening bolt 24 is installed on the third fixing leg 22 and the fourth fixing leg 23 .

在本实施例的一种情况中,内框架与内框架上端连接梁201和内框架下端连接梁202组成的整体,外升降框架四个角为C形立柱,内升降框架四个角为矩管立柱27,内升降框架的矩管27与外升降框架的C形立柱15间隙配合,外升降框架的C形立柱15起到导向的作用,内升降框架能在动力的带动下在外升降框架内自由滑动;优选的,多个支脚通过电机控制进行伸缩,支脚通过电机控制伸出,外框架伸缩支撑梁11和电梯钢结构的上表面接触,四个支脚固定卡接在横梁上,进行下端的固定;进一步的,为了适应任意位置,可启动双向升降件5,双向升降件5为双向液压油缸,此时内升降框架2移出,向上移动到合适的位置即可进行电梯主体钢结构的拧螺丝,焊接等操作;当操作完成后,内升降框架四个支脚收回伸出固定,外升降框架的四个支脚收回,外升降框架向上升出,内外升降框架重叠,需要再次爬升时,继续固定外框架的四个支脚,内框架再次向上推出,继续循环爬升。反之需要向下运动时,将内升降框架的支脚伸出固定,外框架向下升出,作业完成后,将外框架固定,内框架向下缩回;进一步的,为了保证强度,所述外框架和内框架上均安装有交叉设置的斜拉杆25,所述斜拉杆25两端安装有斜拉杆支耳26,即一个斜拉杆25两端分别与外框架左上方和右下方的斜拉杆支耳26连接,另一个斜拉杆25两端分别与外框架右上方和左下方的斜拉杆支架26连接,如此实现斜拉杆25的交叉设置,增加了一个X形的斜拉杆25,增加稳定性;优选的,固定支脚通过旋紧螺栓进行紧固,也可以内置电机及开关,开关按下后,电机启动锁紧螺栓固定。In one case of this embodiment, the inner frame is integrated with the upper connecting beam 201 of the inner frame and the lower connecting beam 202 of the inner frame, the four corners of the outer lifting frame are C-shaped columns, and the four corners of the inner lifting frame are rectangular tubes. The column 27, the rectangular tube 27 of the inner lifting frame is in clearance fit with the C-shaped column 15 of the outer lifting frame, and the C-shaped column 15 of the outer lifting frame plays a guiding role, and the inner lifting frame can be driven freely in the outer lifting frame Sliding; preferably, a plurality of legs are telescopically controlled by a motor, and the legs are stretched out by a motor control, the telescopic support beam 11 of the outer frame is in contact with the upper surface of the steel structure of the elevator, and the four legs are fixedly clamped on the beam to fix the lower end Further, in order to adapt to any position, the two-way lifting part 5 can be started, and the two-way lifting part 5 is a two-way hydraulic oil cylinder. At this time, the inner lifting frame 2 is moved out and moved upward to a suitable position to screw the steel structure of the elevator body. Welding and other operations; when the operation is completed, the four legs of the inner lifting frame are retracted and stretched out to fix, the four legs of the outer lifting frame are retracted, the outer lifting frame is lifted upwards, the inner and outer lifting frames overlap, and when it is necessary to climb again, continue to fix the outer frame With the four legs, the inner frame is pushed upwards again, continuing to climb circularly. Conversely, when it is necessary to move downward, extend the legs of the inner lifting frame and fix it, and lift the outer frame downward. After the operation is completed, fix the outer frame and retract the inner frame downward; further, in order to ensure the strength, the outer frame Both the frame and the inner frame are equipped with diagonal stay rods 25 arranged crosswise, and the two ends of the diagonal stay rods 25 are equipped with diagonal stay rod lugs 26, that is, the two ends of a diagonal stay rod 25 respectively connect with the diagonal stay rods on the upper left and lower right of the outer frame. The ears 26 are connected, and the two ends of the other diagonal stay rod 25 are respectively connected with the diagonal stay rod brackets 26 on the upper right and lower left of the outer frame, so that the cross setting of the diagonal stay rods 25 is realized, and an X-shaped diagonal stay rod 25 is added to increase stability; Preferably, the fixing feet are fastened by tightening bolts, and a motor and a switch may also be built in. After the switch is pressed, the motor starts to lock the bolts to fix.

如图1、图2所示,作为本发明另一个优选的实施例,所述工作台3包括:As shown in Figure 1 and Figure 2, as another preferred embodiment of the present invention, the workbench 3 includes:

工作支撑台31,固定安装在所述内框架上端连接梁201上;The working support platform 31 is fixedly installed on the connecting beam 201 at the upper end of the inner frame;

架体32,固定安装在所述工作支撑台31远离内框架上端连接梁201的一侧。The frame body 32 is fixedly installed on the side of the working support platform 31 away from the connecting beam 201 at the upper end of the inner frame.

在本实施例的一种情况中,所述工作支撑台31四周分别安装有与其滑动连接的第一可伸缩作业平台33、第二可伸缩作业平台34、第三可伸缩作业平台35和第四可伸缩作业平台36,当需要进行电梯主体钢结构的拧螺丝,焊接等操作时,因为常常需要到外侧进行拧螺丝,或者是作业,因此,工作支撑台31上端设置有可伸缩作业平台,可伸缩作业平台与工作支撑台31连接,当需要推出进行外侧操作,可伸缩作业平台向外滑出,人从工作支撑台31走到第一可伸缩作业平台33和第二可伸缩作业平台34上进行操作;当一段区域内操作完成后,需要继续向上安装电梯钢结构的时候,伸缩作业平台回缩,外升降框和内升降框通过液压油缸向上爬升,继续向上实现施工操作,这样既避免了外侧安装升降机进行作业,需要四个面单独施工,危险系数大效率低等问题,同时能实现逐步向上施工,施工过程中还能自动调节内框的高度,施工更加便捷。In one case of this embodiment, the first telescopic working platform 33, the second telescopic working platform 34, the third telescopic working platform 35 and the fourth Retractable work platform 36, when needing to carry out operations such as screwing of elevator main body steel structure, welding, because often need to carry out screwing to the outside, perhaps operation, therefore, the work support platform 31 upper end is provided with retractable work platform, can The telescopic work platform is connected with the work support platform 31. When it needs to be pushed out for outside operation, the telescopic work platform slides out, and people walk from the work support platform 31 to the first telescopic work platform 33 and the second telescopic work platform 34 Carry out operation; when the operation in a certain area is completed, when it is necessary to continue to install the steel structure of the elevator upward, the telescopic work platform retracts, and the outer lifting frame and the inner lifting frame climb upward through the hydraulic cylinder to continue upward to realize the construction operation, which avoids The elevator is installed on the outside for operation, which requires separate construction on four sides, high risk factor and low efficiency. At the same time, it can realize gradual upward construction, and the height of the inner frame can be automatically adjusted during the construction process, making the construction more convenient.

对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。It will be apparent to those skilled in the art that the invention is not limited to the details of the above-described exemplary embodiments, but that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Accordingly, the embodiments should be regarded in all points of view as exemplary and not restrictive, the scope of the invention being defined by the appended claims rather than the foregoing description, and it is therefore intended that the scope of the invention be defined by the appended claims rather than by the foregoing description. All changes within the meaning and range of equivalents of the elements are embraced in the present invention. Any reference sign in a claim should not be construed as limiting the claim concerned.

此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。In addition, it should be understood that although this specification is described according to implementation modes, not each implementation mode only includes an independent technical solution, and this description in the specification is only for clarity, and those skilled in the art should take the specification as a whole , the technical solutions in the various embodiments can also be properly combined to form other implementations that can be understood by those skilled in the art.

Claims (10)

1.一种用于井道电梯钢结构安装的升降施工平台,其特征在于,包括:1. A lifting construction platform for hoistway elevator steel structure installation, characterized in that, comprising: 外升降框架;External lifting frame; 内升降框架,滑动安装在所述外升降框架内;The inner lifting frame is slidably installed in the outer lifting frame; 工作台,安装在所述内升降框架远离外升降框架的一端;The workbench is installed on the end of the inner lifting frame away from the outer lifting frame; 双向升降件,一端与所述外升降框架相连,另一端与所述内升降框架相连。The two-way lifting part is connected with the outer lifting frame at one end and connected with the inner lifting frame at the other end. 2.根据权利要求1所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述外升降框架包括:2. The lifting construction platform for hoistway elevator steel structure installation according to claim 1, characterized in that, the outer lifting frame comprises: 外框架;outer frame; 外框架下端连接梁,固定安装在所述外框架一端;The connecting beam at the lower end of the outer frame is fixedly installed at one end of the outer frame; 外框架上端连接梁,固定安装在所述外框架远离外框架下端连接梁的一端。The connecting beam at the upper end of the outer frame is fixedly installed at the end of the outer frame away from the connecting beam at the lower end of the outer frame. 3.根据权利要求2所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述外升降框架还包括:3. The lifting construction platform for hoistway elevator steel structure installation according to claim 2, characterized in that, the outer lifting frame also includes: 外框架伸缩支撑梁,固定安装在所述外框架下端连接梁上;The telescopic support beam of the outer frame is fixedly installed on the connecting beam at the lower end of the outer frame; 第一固定支脚,安装在所述外框架伸缩支撑梁一端;The first fixed foot is installed at one end of the telescopic support beam of the outer frame; 第二固定支脚,安装在所述外框架伸缩支撑梁远离第一固定支脚的一端。The second fixed foot is installed on the end of the telescopic support beam of the outer frame away from the first fixed foot. 4.根据权利要求3所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述第一固定支脚和第二固定支脚上均安装有第一旋紧螺栓。4. The elevating construction platform for hoistway elevator steel structure installation according to claim 3, characterized in that first fastening bolts are installed on the first fixed leg and the second fixed leg. 5.根据权利要求2所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述内升降框架包括:5. The lifting construction platform for hoistway elevator steel structure installation according to claim 2, characterized in that, the inner lifting frame comprises: 内框架上端连接梁,固定安装在所述内框架一端;The connecting beam at the upper end of the inner frame is fixedly installed at one end of the inner frame; 内框架下端连接梁,固定安装在所述内框架远离内框架上端连接梁的一端。The connecting beam at the lower end of the inner frame is fixedly installed at the end of the inner frame away from the connecting beam at the upper end of the inner frame. 6.根据权利要求5所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述内升降框架还包括:6. The lifting construction platform for hoistway elevator steel structure installation according to claim 5, characterized in that, the inner lifting frame further comprises: 内框架伸缩支撑梁,固定安装在所述内框架下端连接梁上;The telescopic support beam of the inner frame is fixedly installed on the connecting beam at the lower end of the inner frame; 第三固定支脚,安装在所述内框架伸缩支撑梁一端;The third fixed foot is installed at one end of the telescopic support beam of the inner frame; 第四固定支脚,安装在所述内框架伸缩支撑梁远离第三固定支脚的一端。The fourth fixed foot is installed on the end of the telescopic support beam of the inner frame away from the third fixed foot. 7.根据权利要求6所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述第三固定支脚和第四固定支脚上均安装有第二旋紧螺栓。7. The elevating construction platform for hoistway elevator steel structure installation according to claim 6, characterized in that, second tightening bolts are installed on the third fixed leg and the fourth fixed leg. 8.根据权利要求5所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述外框架和内框架上均安装有交叉设置的斜拉杆,所述斜拉杆两端安装有斜拉杆支耳。8. The lifting construction platform for hoistway elevator steel structure installation according to claim 5, characterized in that, the outer frame and the inner frame are equipped with diagonal stay rods arranged crosswise, and the two ends of the diagonal stay rods are installed with Tie rod lugs. 9.根据权利要求5所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述工作台包括:9. The lifting construction platform for hoistway elevator steel structure installation according to claim 5, characterized in that, the workbench comprises: 工作支撑台,固定安装在所述内框架上端连接梁上;The working support platform is fixedly installed on the connecting beam at the upper end of the inner frame; 架体,固定安装在所述工作支撑台远离内框架上端连接梁的一侧。The frame body is fixedly installed on the side of the working support table away from the connecting beam at the upper end of the inner frame. 10.根据权利要求9所述的用于井道电梯钢结构安装的升降施工平台,其特征在于,所述工作支撑台四周分别安装有与其滑动连接的第一可伸缩作业平台、第二可伸缩作业平台、第三可伸缩作业平台和第四可伸缩作业平台。10. The elevating construction platform for hoistway elevator steel structure installation according to claim 9, characterized in that a first telescopic work platform and a second telescopic work platform are respectively installed around the work support platform in sliding connection with it. platform, the third retractable work platform and the fourth retractable work platform.
CN202310020614.5A 2023-01-06 2023-01-06 A lifting construction platform for hoistway elevator steel structure installation Pending CN116201344A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310020614.5A CN116201344A (en) 2023-01-06 2023-01-06 A lifting construction platform for hoistway elevator steel structure installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310020614.5A CN116201344A (en) 2023-01-06 2023-01-06 A lifting construction platform for hoistway elevator steel structure installation

Publications (1)

Publication Number Publication Date
CN116201344A true CN116201344A (en) 2023-06-02

Family

ID=86507035

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310020614.5A Pending CN116201344A (en) 2023-01-06 2023-01-06 A lifting construction platform for hoistway elevator steel structure installation

Country Status (1)

Country Link
CN (1) CN116201344A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5230404A (en) * 1991-03-01 1993-07-27 Inventio Ag Erection scaffolding which is movable in an elevator shaft for the mounting of shaft equipment
CN2680772Y (en) * 2003-03-23 2005-02-23 徐跃华 Lifting platform
CN108590151A (en) * 2018-07-26 2018-09-28 申锡机械有限公司 A kind of scalable elevator hanging basket in four sides
CN110439251A (en) * 2019-08-13 2019-11-12 广东博智林机器人有限公司 A kind of hoistway climbing frame
CN111877728A (en) * 2020-07-14 2020-11-03 中国一冶集团有限公司 Lifting type movable operation platform for steel structure overhanging construction
CN113279558A (en) * 2021-06-22 2021-08-20 中建三局集团有限公司 Self-climbing operation platform in vertical shaft
CN219175821U (en) * 2023-01-06 2023-06-13 华森天奥(重庆)机电有限公司 Lifting construction platform for mounting steel structure of elevator in well

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5230404A (en) * 1991-03-01 1993-07-27 Inventio Ag Erection scaffolding which is movable in an elevator shaft for the mounting of shaft equipment
CN2680772Y (en) * 2003-03-23 2005-02-23 徐跃华 Lifting platform
CN108590151A (en) * 2018-07-26 2018-09-28 申锡机械有限公司 A kind of scalable elevator hanging basket in four sides
CN110439251A (en) * 2019-08-13 2019-11-12 广东博智林机器人有限公司 A kind of hoistway climbing frame
CN111877728A (en) * 2020-07-14 2020-11-03 中国一冶集团有限公司 Lifting type movable operation platform for steel structure overhanging construction
CN113279558A (en) * 2021-06-22 2021-08-20 中建三局集团有限公司 Self-climbing operation platform in vertical shaft
CN219175821U (en) * 2023-01-06 2023-06-13 华森天奥(重庆)机电有限公司 Lifting construction platform for mounting steel structure of elevator in well

Similar Documents

Publication Publication Date Title
JP6498361B2 (en) Pile frame and its use and installation method
JP2009280367A (en) Tower crane
CN219175821U (en) Lifting construction platform for mounting steel structure of elevator in well
CN116201344A (en) A lifting construction platform for hoistway elevator steel structure installation
CN107055367A (en) The central jack-up system of internally climbing tower crane
JP2010265107A (en) Tower crane support structure and climbing method
CN114197860A (en) Quick-construction double-layer creeping formwork system and creeping formwork construction method
JPH08100517A (en) Elevating workbench
CN113605684A (en) Vortex screw lifting elevator shaft creeping formwork system and operation method thereof
CN210152203U (en) Installation operation platform for housing construction
CN107043072A (en) Exempt from the integration of falling beam inner climbing crane tower support meanss and implementation
CN207960496U (en) Be easily installed drilling tool from hoisting type horizontal boring machine
CN116163535B (en) Construction method for lifting prefabricated part in delta shape by walking on top of column
CN212388380U (en) Support type mounting system of steel cable tower
CN210340229U (en) Hydraulic lifting assembly and hydraulic jacking equipment
CN110077952B (en) Building template cross-floor transportation equipment and transportation method
CN214575533U (en) A lifting mechanism mounting frame
CN110258629B (en) Assembling equipment and assembling method for prefabricated parts
CN219730313U (en) Succinct formula lift column foot structure
CN114753651A (en) Simple large-size partition plate vertical plate machine
JPH06219669A (en) Elevator car assembling frame
CN223707667U (en) Installation component of prefabricated two lining steel reinforcement skeleton of tunnel and construction trolley for tunnel
CN113463896B (en) Sandwich steel beam mounting platform with multi-direction moving structure
CN220747831U (en) Self-lifting descending device for attached holding pole
CN220353331U (en) Building construction frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20230602