CN116187588A - Project task information extraction and cost optimization method and device and electronic equipment - Google Patents

Project task information extraction and cost optimization method and device and electronic equipment Download PDF

Info

Publication number
CN116187588A
CN116187588A CN202310447731.XA CN202310447731A CN116187588A CN 116187588 A CN116187588 A CN 116187588A CN 202310447731 A CN202310447731 A CN 202310447731A CN 116187588 A CN116187588 A CN 116187588A
Authority
CN
China
Prior art keywords
project task
configuration data
data
cost
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310447731.XA
Other languages
Chinese (zh)
Other versions
CN116187588B (en
Inventor
刁锡刚
刘洋
李鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Siweifu Supply Chain Management Co ltd
Original Assignee
Chengdu Siweifu Supply Chain Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Siweifu Supply Chain Management Co ltd filed Critical Chengdu Siweifu Supply Chain Management Co ltd
Priority to CN202310447731.XA priority Critical patent/CN116187588B/en
Publication of CN116187588A publication Critical patent/CN116187588A/en
Application granted granted Critical
Publication of CN116187588B publication Critical patent/CN116187588B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06NCOMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
    • G06N3/00Computing arrangements based on biological models
    • G06N3/02Neural networks
    • G06N3/04Architecture, e.g. interconnection topology
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T10/00Road transport of goods or passengers
    • Y02T10/10Internal combustion engine [ICE] based vehicles
    • Y02T10/40Engine management systems

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Operations Research (AREA)
  • General Business, Economics & Management (AREA)
  • Data Mining & Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Artificial Intelligence (AREA)
  • Biomedical Technology (AREA)
  • Biophysics (AREA)
  • Computational Linguistics (AREA)
  • Evolutionary Computation (AREA)
  • General Health & Medical Sciences (AREA)
  • Molecular Biology (AREA)
  • Computing Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Mathematical Physics (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention belongs to the technical field of engineering cost information processing, and relates to a project task information extraction and cost optimization method, a project task information extraction and cost optimization device and electronic equipment, wherein the project task information extraction and cost optimization method comprises the following steps of: establishing a history project task information base; extracting configuration data and cost data; classifying and labeling; extracting characteristic parameters of configuration data; establishing a neural network model; training to obtain a cost optimization model; inputting characteristic parameters of configuration data of each current project task into a cost optimization model; according to the cost data of the current project task, adjusting the configuration data of the current project task; and outputting the adjusted configuration data and the manufacturing cost data. According to the invention, the cost optimization model is obtained through the neural network model, after configuration data of project tasks are input, a group of cost data which is subjected to optimization processing of the cost optimization model is obtained, and the configuration data is adjusted, so that the optimal configuration scheme of each project task is obtained.

Description

Project task information extraction and cost optimization method and device and electronic equipment
Technical Field
The invention relates to the technical field of engineering cost information processing, in particular to a project task information extraction and cost optimization method and device and electronic equipment.
Background
The construction cost refers to the construction price of the project, and refers to the sum of all the costs expected or actually required for construction of one project period. A plurality of project tasks exist in one engineering project period, and technicians distribute material resources, manpower resources and the like of each project task in the project period in a manner of artificial design, so that labor cost, material cost, management cost and the like generated in the construction process are in a reasonable range.
The project tasks of one project period are often associated with each other, because the number of personnel and the total amount of materials which can be input are constant, the input distribution of one project task can influence the input of other projects and the cost of the whole project period, but in the prior art, the phenomenon of high manufacturing cost easily occurs by manually distributing the design modes of the material resource, the manpower resource and the like of each project task, in the design process, the designer can only consider the configuration scheme of one resource distribution design, the workload is large when considering various configuration schemes, the design result of the resource configuration of each project task is easily influenced by the experience of the designer, and the problem of unreasonable manufacturing cost of the project is easily caused by the imperfect configuration scheme of the resource distribution design, so that the benefit of construction enterprises cannot be ensured.
Disclosure of Invention
In order to solve the technical problems, the invention provides a project task information extraction and cost optimization method and device and electronic equipment.
In a first aspect, the present invention provides a method for extracting project task information and optimizing cost, including:
establishing a historical project task information base, and acquiring historical project task information;
decomposing the historical project task information, and extracting configuration data and cost data of each project task contained in the historical project task information;
classifying and labeling the manufacturing cost data of each project task according to the size of a set range;
extracting characteristic parameters of configuration data of each project task;
processing characteristic parameters of configuration data of each project task, and establishing a neural network model;
training the neural network model by utilizing characteristic parameters of configuration data of each project task and classification labeling results to obtain a cost optimization model;
acquiring current project task information, decomposing to obtain configuration data of each current project task, and extracting characteristic parameters of the configuration data of each current project task;
inputting characteristic parameters of configuration data of each current project task into the cost optimization model;
loading the cost optimization model, and processing characteristic parameters of configuration data of each current project task by using the cost optimization model to obtain cost data of each current project task;
adjusting the configuration data of the current project task according to the manufacturing cost data of the current project task;
and outputting the configuration data of each current project task after adjustment and the manufacturing cost data of each current project task.
The second aspect provides a project task information extraction and cost optimization device, which comprises an acquisition unit, an extraction unit, a classification labeling unit, a first characteristic parameter extraction unit, a neural network model establishment unit, a neural network model training unit, a second characteristic parameter extraction unit, an input unit, a model loading unit, an adjustment unit and an output unit;
the acquisition unit is used for establishing a history project task information base and acquiring history project task information;
the extraction unit is used for decomposing the historical project task information and extracting configuration data and manufacturing cost data of each project task contained in the historical project task information;
the classifying and labeling unit is used for classifying and labeling the manufacturing cost data of each project task according to the size of a set range;
the first characteristic parameter extraction unit is used for extracting characteristic parameters of configuration data of each project task;
the neural network model building unit is used for processing characteristic parameters of the configuration data of each project task and building a neural network model;
the neural network model training unit is used for training the neural network model by utilizing the characteristic parameters of the configuration data of each project task and the classification labeling result to obtain a cost optimization model;
the second characteristic parameter extraction unit is used for acquiring the current project task information, decomposing to obtain configuration data of each current project task, and extracting characteristic parameters of the configuration data of each current project task;
the input unit is used for inputting characteristic parameters of configuration data of each current project task into the cost optimization model;
the model loading unit is used for loading the cost optimization model, and processing characteristic parameters of configuration data of each current project task by utilizing the cost optimization model to obtain cost data of each current project task;
the adjusting unit is used for adjusting the configuration data of the current project task according to the manufacturing cost data of the current project task;
the output unit is used for outputting the configuration data of each current project task after adjustment and the manufacturing cost data of each current project task.
In a third aspect, the present invention discloses an electronic device, comprising:
a processor and a memory;
the memory is used for storing computer operation instructions;
and the processor is used for executing project task information extraction and cost optimization methods by calling the computer operation instructions.
According to the invention, the cost optimization model is obtained through the neural network model, after configuration data of project tasks are input, a group of cost data which is subjected to optimization processing of the cost optimization model is obtained, and the configuration data is adjusted, so that the optimal configuration scheme of each project task is obtained.
On the basis of the technical scheme, the invention can be improved as follows.
Further, extracting configuration data and cost data of each project task contained in the historical project task information includes: and screening the configuration data of the project task in the historical project task information according to a plurality of set interval ranges, and deleting the configuration data and the manufacturing cost data outside the set interval ranges.
Further, the configuration data of the project task comprises the sequence of the project task name and the single project task name in all the project tasks, the material consumption, the use quantity of construction tools, the personnel configuration quantity and the project task period; the order in the project tasks is configured according to the construction order of a single project task in all project tasks; the cost data comprises labor cost data, material cost data, construction tool use cost data, enterprise management cost data and engineering regulation cost data.
Further, extracting characteristic parameters of configuration data of each project task comprises converting sequences of single project tasks in all project tasks, material consumption of the project tasks, using quantity of construction machines, personnel configuration quantity and project task period into characteristic vectors.
Further, processing the characteristic parameters of the configuration data of each project task includes: coding each obtained set interval range; and taking the result of classifying and labeling the characteristic parameters of the configuration data of the project task after encoding and the manufacturing cost data corresponding to the characteristic parameters of the configuration data of the project task as sample data of the manufacturing cost optimization model.
Further, the one-hot coding mode is utilized to code the characteristic parameters of the configuration data of each project task, and the characteristic vector of the characteristic parameters of the configuration data of each project task is determined;
performing two classification on the feature vector by using a softmax function, and determining an output result of the neural network model;
calculating a cross entropy loss value by using the cross entropy loss function;
and determining the accuracy of the output result of the neural network model according to the cross entropy loss value.
Further, after the cost data of each current project task is obtained, the method further comprises the steps of calculating the sum of the cost data of all the current project tasks as an actual value, matching the input historical project task information with the characteristic parameters in the same setting range, calculating the sum of the cost data in all the historical project task information as a reference value, and comparing the actual value with the reference value until the actual value is smaller than the reference value.
Further, adjusting the configuration data of the current project task includes: and adjusting the project task period of the project task name by changing the sequence of a plurality of project task names in all project tasks, or adjusting one or two or three of the material consumption of the project task names or the use quantity of construction machines or the personnel configuration quantity.
Drawings
FIG. 1 is a flow chart of a project task information extraction and cost optimization method provided in embodiment 1 of the present invention;
FIG. 2 is a schematic diagram of a project task information extraction and cost optimization apparatus according to embodiment 2 of the present invention;
fig. 3 is a schematic diagram of an electronic device according to embodiment 3 of the present invention.
Icon: 30-an electronic device; 310-a processor; 320-bus; 330-memory; 340-transceiver.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present invention more apparent, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is apparent that the described embodiments are some embodiments of the present invention, but not all embodiments of the present invention. The components of the embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
Example 1
As an embodiment, as shown in fig. 1, to solve the above technical problem, the present embodiment provides a method for extracting project task information and optimizing cost, including:
establishing a historical project task information base, and acquiring historical project task information;
decomposing the historical project task information, and extracting configuration data and cost data of each project task contained in the historical project task information;
classifying and marking the manufacturing cost data of each project task according to the size of a set range;
extracting characteristic parameters of configuration data of each project task;
processing characteristic parameters of configuration data of each project task, and establishing a neural network model;
training the neural network model by utilizing the characteristic parameters of the configuration data of each project task and the classification labeling result to obtain a cost optimization model;
acquiring current project task information, decomposing to obtain configuration data of each current project task, and extracting characteristic parameters of the configuration data of each current project task;
inputting characteristic parameters of configuration data of each current project task into a cost optimization model;
loading a cost optimization model, and processing characteristic parameters of configuration data of each current project task by using the cost optimization model to obtain cost data of each current project task;
adjusting the configuration data of the current project task according to the manufacturing cost data of the current project task;
and outputting the configuration data of each current project task after adjustment and the manufacturing cost data of each current project task.
Optionally, extracting configuration data and cost data of each project task included in the historical project task information includes: and screening the configuration data of the project task in the history project task information according to a plurality of set interval ranges, and deleting the configuration data and the manufacturing cost data outside the set interval ranges.
Optionally, the configuration data of the project task includes the sequence of the project task name and the single project task name in all project tasks, the material consumption, the use quantity of construction tools, the personnel configuration quantity and the project task period; the order in the project tasks is configured according to the construction order of a single project task in all project tasks; the cost data includes labor cost data, material cost data, construction tool use cost data, enterprise management cost data and engineering regulation cost data.
In the actual application process, acquiring the sequence of the project task names and single project task names in all project tasks in the history project task information, respectively setting different ranges for the project task names of the same sequence according to the material consumption, the construction tool use quantity, the personnel configuration quantity and the project task period, and deleting the project task names with the material consumption, the construction tool use quantity, the personnel configuration quantity and the project task period exceeding the set ranges.
Optionally, extracting the feature parameters of the configuration data of each project task includes converting the sequence of the single project task in all project tasks, the material consumption of the project task, the use quantity of construction tools, the personnel configuration quantity and the project task period into feature vectors.
In the practical application process, a code is set in the interval of each set range value, and simultaneously, the project task name and the sequence of the project task name in all project tasks are coded. For example: the codes of the project task material consumption are 21, 22 and 23 … …, the codes of the construction machine use quantity are 31, 32 and 33 … …, the codes of the personnel configuration quantity are 41, 42 and 43 … …, the codes of the project task period are 51, 52 and 53 … …, the codes of the project task names are 01, 02 and 03 … …, and the sequences of the project task names in all project tasks are 11, 12 and 13 … ….
Optionally, processing the feature parameters of the configuration data of each project task includes: coding each obtained set interval range; and taking the result of classifying and labeling the characteristic parameters of the configuration data of the project task after the encoding and the manufacturing cost data corresponding to the characteristic parameters of the configuration data of the project task as sample data of a manufacturing cost optimization model.
In the practical application process, each group of project task names and a group of material consumption codes, construction machine use quantity codes, personnel configuration quantity codes and project task period codes corresponding to the sequence of the single project task name in all project tasks are coded. And merging each group of project task names with a group of coded material consumption, the number of used construction tools, the number of personnel configuration and project task periods corresponding to the sequence of the project task names in all project tasks to obtain a group of characteristic parameters. For example: the code of the project task name is 01, the order of the project task names in all project tasks is 12, the project task material consumption is in a second range section, the construction machine use number is in a first range section, the personnel configuration number is in a third range section, the project task period is in a second range section, and the project task period is represented as (01,12,22,31,43,52) and is used as sample input data with a plurality of attributes.
Optionally, the one-hot coding mode is utilized to code the characteristic parameters of the configuration data of each project task, and the characteristic vector of the characteristic parameters of the configuration data of each project task is determined;
performing two classification on the feature vector by using a softmax function to determine an output result of the neural network model;
calculating a cross entropy loss value by using the cross entropy loss function;
and determining the accuracy of the output result of the neural network model according to the cross entropy loss value.
And encoding a group of characteristic parameters by using a one-hot encoding mode to obtain characteristic vectors, and performing two-classification on the characteristic vectors by using a softmax function to determine an output result of the neural network model, wherein the output result is two result labels and the probability corresponding to each result.
The parameters of the neural network model are obtained by calculating the value of the cross entropy loss and minimizing the cross entropy loss, the smaller the cross entropy loss is, the more accurate the parameters of the neural network model are, and finally the manufacturing cost optimization model is obtained, so that the model parameters can be adjusted conveniently, and the accuracy of the output result of the neural network model is improved.
Optionally, adjusting the configuration data of the current project task includes: the project task period of the project task names is adjusted by changing the sequence of the project task names in all project tasks, or one or two or three of the material consumption of the project task names or the use quantity of construction tools or the personnel configuration quantity are changed, and the project task period of the project task names is adjusted, which concretely comprises the following steps: after configuration data of each project task is input, a group of cost data subjected to cost optimization model optimization processing can be obtained, the configuration data of the current project task is adjusted by obtaining an optimal configuration scheme of each project task through cost comparison, namely, the order or material consumption, the number of construction machines and tools, the personnel configuration number and the project task period of a single project task name in the configuration data in all the project tasks are adjusted, and the optimization of the cost within a preset range is realized, for example: the project task period is reduced by increasing the personnel configuration quantity, and an optimization scheme with lower manufacturing cost is obtained; or the personnel configuration quantity of the first project task is reduced, and the personnel configuration quantity of the second project task is increased, so that the project task period of the second project task is shortened, and an optimization scheme with lower manufacturing cost is obtained; or the order of the first project task and the second project task is adjusted, and the first project task and the second project task are input into the neural network model again to obtain an optimization scheme with lower manufacturing cost; or the project task period is shortened by changing the material consumption, the use quantity of construction tools and the personnel configuration quantity of project task names, and an optimization scheme with lower manufacturing cost is obtained.
Example 2
Based on the same principle as the method shown in the embodiment 1 of the present invention, as shown in fig. 2, the embodiment of the present invention further provides a project task information extraction and cost optimization device, which includes an acquisition unit, an extraction unit, a classification labeling unit, a first feature parameter extraction unit, a neural network model establishment unit, a neural network model training unit, a second feature parameter extraction unit, an input unit, a model loading unit, an adjustment unit and an output unit;
the acquisition unit is used for establishing a history project task information base and acquiring history project task information;
the extraction unit is used for decomposing the historical project task information and extracting configuration data and cost data of each project task contained in the historical project task information;
the classification marking unit is used for classifying and marking the manufacturing cost data of each project task according to the size of the set range;
a first characteristic parameter extraction unit for extracting characteristic parameters of configuration data of each project task;
the neural network model building unit is used for processing the characteristic parameters of the configuration data of each project task and building a neural network model;
the neural network model training unit is used for training the neural network model by utilizing the characteristic parameters of the configuration data of each project task and the classification labeling result to obtain a cost optimization model;
the second characteristic parameter extraction unit is used for acquiring the task information of the current project, decomposing to obtain configuration data of each current project task, and extracting characteristic parameters of the configuration data of each current project task;
the input unit is used for inputting characteristic parameters of configuration data of each current project task into the cost optimization model;
the model loading unit is used for loading a cost optimization model, and processing characteristic parameters of configuration data of each current project task by using the cost optimization model to obtain cost data of each current project task;
the adjusting unit is used for adjusting the configuration data of the current project task according to the manufacturing cost data of the current project task;
the output unit is used for outputting the configuration data of each current project task after adjustment and the manufacturing cost data of each current project task.
Optionally, extracting configuration data and cost data of each project task included in the historical project task information includes: and screening the configuration data of the project task in the history project task information according to a plurality of set interval ranges, and deleting the configuration data and the manufacturing cost data outside the set interval ranges.
Optionally, the configuration data of the project task includes the project task name and the sequence, the material consumption, the number of construction tools used, the personnel configuration number and the project task period of the single project task in all project tasks; the order in the project tasks is configured according to the construction order of a single project task in all project tasks; the cost data includes labor cost data, material cost data, construction tool use cost data, enterprise management cost data and engineering regulation cost data.
Optionally, extracting the feature parameters of the configuration data of each project task includes converting the sequence of the single project task in all project tasks, the material consumption of the project task, the use quantity of construction tools, the personnel configuration quantity and the project task period into feature vectors.
Optionally, processing the feature parameters of the configuration data of each project task includes: coding each obtained set interval range; and taking the result of classifying and labeling the characteristic parameters of the configuration data of the project task after the encoding and the manufacturing cost data corresponding to the characteristic parameters of the configuration data of the project task as sample data of a manufacturing cost optimization model.
Optionally, the one-hot coding mode is utilized to code the characteristic parameters of the configuration data of each project task, and the characteristic vector of the characteristic parameters of the configuration data of each project task is determined;
performing two classification on the feature vector by using a softmax function to determine an output result of the neural network model;
calculating a cross entropy loss value by using the cross entropy loss function;
and determining the accuracy of the output result of the neural network model according to the cross entropy loss value.
Optionally, the project task information extracting and cost optimizing device further comprises a comparison and verification unit, wherein the comparison and verification unit is used for obtaining the cost data of each current project task, calculating the sum of the cost data of all the current project tasks as an actual value, matching the input historical project task information with the characteristic parameters in the same setting range, calculating the sum of the cost data in all the historical project task information as a reference value, and comparing the actual value with the reference value until the actual value is smaller than the reference value.
Optionally, adjusting the configuration data of the current project task includes: the project task period of the project task names is adjusted by changing the sequence of the project task names in all project tasks, or one or two or three of the material consumption of the project task names or the use quantity of construction machines or the personnel configuration quantity are changed, so that the project task period of the project task names is adjusted.
Example 3
Based on the same principle as the method shown in the embodiment of the present invention, there is also provided an electronic device in the embodiment of the present invention, as shown in fig. 3, which may include, but is not limited to: a processor and a memory; a memory for storing a computer program; and the processor is used for executing the project task information extraction and cost optimization method shown in the embodiment of the invention by calling the computer program.
In an alternative embodiment, an electronic device is provided, the electronic device 30 shown in fig. 3 comprising: a processor 310 and a memory 330. Wherein the processor 310 is coupled to the memory 330, such as via a bus 320.
Optionally, the electronic device 30 may further comprise a transceiver 340, and the transceiver 340 may be used for data interaction between the electronic device and other electronic devices, such as transmission of data and/or reception of data, etc. It should be noted that, in practical applications, the transceiver 340 is not limited to one, and the structure of the electronic device 30 is not limited to the embodiment of the present invention.
The processor 310 may be a CPU (Central Processing Unit ), general purpose processor, DSP (Digital Signal Processor, data signal processor), ASIC (Application Specific Integrated Circuit ), FPGA (Field Programmable Gate Array, field programmable gate array) or other programmable logic device, transistor logic device, hardware components, or any combination thereof. Which may implement or perform the various exemplary logic blocks, modules and circuits described in connection with this disclosure. Processor 310 may also be a combination that performs computing functions, e.g., including one or more microprocessor combinations, a combination of a DSP and a microprocessor, etc.
Bus 320 may include a path that communicates information between the components. Bus 320 may be a PCI (Peripheral Component Interconnect, peripheral component interconnect standard) bus, or EISA (Extended Industry Standard Architecture ) bus, among others. The bus 320 may be classified into an address bus, a data bus, a control bus, and the like. For ease of illustration, only one thick line is shown in fig. 3, but not only one bus or one type of bus.
Memory 330 may be, but is not limited to, ROM (Read Only Memory) or other type of static storage device that can store static information and instructions, RAM (Random Access Memory ) or other type of dynamic storage device that can store information and instructions, EEPROM (Electrically Erasable Programmable Read Only Memory ), CD-ROM (Compact Disc Read Only Memory, compact disc Read Only Memory) or other optical disk storage, optical disk storage (including compact discs, laser discs, optical discs, digital versatile discs, blu-ray discs, etc.), magnetic disk storage media or other magnetic storage devices, or any other medium that can be used to carry or store desired program code in the form of instructions or data structures and that can be accessed by a computer.
The memory 330 is used for storing application program codes (computer programs) for executing the inventive arrangements and is controlled to be executed by the processor 310. The processor 310 is configured to execute the application code stored in the memory 330 to implement what is shown in the foregoing method embodiments.
The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention, but various modifications and variations can be made to the present invention by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. The project task information extraction and cost optimization method is characterized by comprising the following steps:
establishing a historical project task information base, and acquiring historical project task information;
decomposing the historical project task information, and extracting configuration data and cost data of each project task contained in the historical project task information;
classifying and labeling the manufacturing cost data of each project task according to the size of a set range;
extracting characteristic parameters of configuration data of each project task;
processing characteristic parameters of configuration data of each project task, and establishing a neural network model;
training the neural network model by utilizing characteristic parameters of configuration data of each project task and classification labeling results to obtain a cost optimization model;
acquiring current project task information, decomposing to obtain configuration data of each current project task, and extracting characteristic parameters of the configuration data of each current project task;
inputting characteristic parameters of configuration data of each current project task into the cost optimization model;
loading the cost optimization model, and processing characteristic parameters of configuration data of each current project task by using the cost optimization model to obtain cost data of each current project task;
adjusting the configuration data of the current project task according to the manufacturing cost data of the current project task;
and outputting the configuration data of each current project task after adjustment and the manufacturing cost data of each current project task.
2. The method for extracting and optimizing project task information according to claim 1, wherein extracting configuration data and cost data of each project task contained in the history project task information comprises: and screening the configuration data of the project task in the historical project task information according to a plurality of set interval ranges, and deleting the configuration data and the manufacturing cost data outside the set interval ranges.
3. The method for extracting project task information and optimizing cost according to any one of claims 1-2, wherein the configuration data of the project task includes the order of project task names and single project task names in all the project tasks, the material consumption, the number of construction machines and tools used, the number of personnel configuration and the project task period; the order in the project tasks is configured according to the construction order of a single project task in all project tasks; the cost data comprises labor cost data, material cost data, construction tool use cost data, enterprise management cost data and engineering regulation cost data.
4. The method for extracting and optimizing construction cost according to claim 3, wherein extracting the characteristic parameters of the configuration data of each project task includes converting the order of the individual project tasks in all the project tasks, the material consumption of the project tasks, the number of the construction machines, the number of the personnel configuration and the project task period into characteristic vectors.
5. The project task information extraction and cost optimization method according to claim 1, wherein the processing of the characteristic parameters of the configuration data of each project task comprises: coding each obtained set interval range; and taking the result of classifying and labeling the characteristic parameters of the configuration data of the project task after encoding and the manufacturing cost data corresponding to the characteristic parameters of the configuration data of the project task as sample data of the manufacturing cost optimization model.
6. The project task information extraction and cost optimization method according to claim 1, wherein the method is characterized in that the characteristic parameters of the configuration data of each project task are encoded by using a one-hot encoding mode, and the characteristic vector of the characteristic parameters of the configuration data of each project task is determined;
performing two classification on the feature vector by using a softmax function, and determining an output result of the neural network model;
calculating a cross entropy loss value by using the cross entropy loss function;
and determining the accuracy of the output result of the neural network model according to the cross entropy loss value.
7. The method for extracting and optimizing project task information according to claim 1, further comprising calculating a sum of cost data of all the current project tasks as an actual value after obtaining the cost data of each current project task, matching input historical project task information of the characteristic parameters in the same setting range, calculating a sum of the cost data in all the historical project task information as a reference value, and comparing the actual value with the reference value until the actual value is smaller than the reference value.
8. The method for extracting and optimizing project task information as defined in claim 1, wherein the adjusting the configuration data of the current project task comprises: and adjusting the project task period of the project task name by changing the sequence of a plurality of project task names in all project tasks, or adjusting one or two or three of the material consumption of the project task names or the use quantity of construction machines or the personnel configuration quantity.
9. The project task information extraction and cost optimization device is characterized by comprising an acquisition unit, an extraction unit, a classification labeling unit, a first characteristic parameter extraction unit, a neural network model establishment unit, a neural network model training unit, a second characteristic parameter extraction unit, an input unit, a model loading unit, an adjustment unit and an output unit;
the acquisition unit is used for establishing a history project task information base and acquiring history project task information;
the extraction unit is used for decomposing the historical project task information and extracting configuration data and manufacturing cost data of each project task contained in the historical project task information;
the classifying and labeling unit is used for classifying and labeling the manufacturing cost data of each project task according to the size of a set range;
the first characteristic parameter extraction unit is used for extracting characteristic parameters of configuration data of each project task;
the neural network model building unit is used for processing characteristic parameters of the configuration data of each project task and building a neural network model;
the neural network model training unit is used for training the neural network model by utilizing the characteristic parameters of the configuration data of each project task and the classification labeling result to obtain a cost optimization model;
the second characteristic parameter extraction unit is used for acquiring the current project task information, decomposing to obtain configuration data of each current project task, and extracting characteristic parameters of the configuration data of each current project task;
the input unit is used for inputting characteristic parameters of configuration data of each current project task into the cost optimization model;
the model loading unit is used for loading the cost optimization model, and processing characteristic parameters of configuration data of each current project task by utilizing the cost optimization model to obtain cost data of each current project task;
the adjusting unit is used for adjusting the configuration data of the current project task according to the manufacturing cost data of the current project task;
the output unit is used for outputting the configuration data of each current project task after adjustment and the manufacturing cost data of each current project task.
10. An electronic device, comprising:
a processor and a memory;
the memory is used for storing computer operation instructions;
the processor is configured to execute the project task information extraction and cost optimization method according to any one of claims 1 to 8 by calling the computer operation instruction.
CN202310447731.XA 2023-04-24 2023-04-24 Project task information extraction and cost optimization method and device and electronic equipment Active CN116187588B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310447731.XA CN116187588B (en) 2023-04-24 2023-04-24 Project task information extraction and cost optimization method and device and electronic equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310447731.XA CN116187588B (en) 2023-04-24 2023-04-24 Project task information extraction and cost optimization method and device and electronic equipment

Publications (2)

Publication Number Publication Date
CN116187588A true CN116187588A (en) 2023-05-30
CN116187588B CN116187588B (en) 2023-06-27

Family

ID=86452469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310447731.XA Active CN116187588B (en) 2023-04-24 2023-04-24 Project task information extraction and cost optimization method and device and electronic equipment

Country Status (1)

Country Link
CN (1) CN116187588B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140249882A1 (en) * 2012-10-19 2014-09-04 The Curators Of The University Of Missouri System and Method of Stochastic Resource-Constrained Project Scheduling
CN109657420A (en) * 2019-02-21 2019-04-19 中国人民解放军战略支援部队航天工程大学 A kind of equipment Safeguard characteristic Simulation modeling method based on space mission
CN113987904A (en) * 2021-11-17 2022-01-28 广东电网有限责任公司广州供电局 Method, device, equipment and storage medium for measuring and calculating repair cost of power transmission project
CN114066250A (en) * 2021-11-17 2022-02-18 广东电网有限责任公司广州供电局 Method, device, equipment and storage medium for measuring and calculating repair cost of power transmission project
CN114429245A (en) * 2022-01-17 2022-05-03 国网湖北省电力有限公司经济技术研究院 Analysis display method of engineering cost data
CN115481844A (en) * 2021-06-15 2022-12-16 深圳供电局有限公司 Distribution network material demand prediction system based on feature extraction and improved SVR model
CN115630104A (en) * 2022-09-21 2023-01-20 中国铁道科学研究院集团有限公司电子计算技术研究所 Railway engineering project plan data processing method and platform

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140249882A1 (en) * 2012-10-19 2014-09-04 The Curators Of The University Of Missouri System and Method of Stochastic Resource-Constrained Project Scheduling
CN109657420A (en) * 2019-02-21 2019-04-19 中国人民解放军战略支援部队航天工程大学 A kind of equipment Safeguard characteristic Simulation modeling method based on space mission
CN115481844A (en) * 2021-06-15 2022-12-16 深圳供电局有限公司 Distribution network material demand prediction system based on feature extraction and improved SVR model
CN113987904A (en) * 2021-11-17 2022-01-28 广东电网有限责任公司广州供电局 Method, device, equipment and storage medium for measuring and calculating repair cost of power transmission project
CN114066250A (en) * 2021-11-17 2022-02-18 广东电网有限责任公司广州供电局 Method, device, equipment and storage medium for measuring and calculating repair cost of power transmission project
CN114429245A (en) * 2022-01-17 2022-05-03 国网湖北省电力有限公司经济技术研究院 Analysis display method of engineering cost data
CN115630104A (en) * 2022-09-21 2023-01-20 中国铁道科学研究院集团有限公司电子计算技术研究所 Railway engineering project plan data processing method and platform

Also Published As

Publication number Publication date
CN116187588B (en) 2023-06-27

Similar Documents

Publication Publication Date Title
Mittag et al. Statistical methods of quality assurance
CN101482891B (en) performance evaluation simulation
Dengiz et al. Simulation optimization using tabu search
Barrera-Diaz et al. Discrete event simulation output data-handling system in an automotive manufacturing plant
CN108614778B (en) Android App program evolution change prediction method based on Gaussian process regression
CN112651817A (en) Intelligent financial decision big data analysis system
CN115130985A (en) Production control method and related apparatus, storage medium, and program product
CN116187588B (en) Project task information extraction and cost optimization method and device and electronic equipment
CN108416151B (en) Model-based intelligent design system for satellite measurement and control information flow and fault information rapid positioning method
CN112579847A (en) Method and device for processing production data, storage medium and electronic equipment
CN112464970A (en) Regional value evaluation model processing method and device and computing equipment
CN111382068B (en) Hierarchical testing method and device for large-batch data
CN114925895A (en) Maintenance equipment prediction method, terminal and storage medium
CN112685456A (en) User access data processing method and device and computer system
CN111209397B (en) Method for determining enterprise industry category
CN112559589A (en) Remote surveying and mapping data processing method and system
CN105809577A (en) Classification processing method of power plant information data on basis of rules and modules
Pouchard et al. Challenges for implementing fair digital objects with high performance workflows
CN111768282A (en) Data analysis method, device, equipment and storage medium
CN117592911B (en) Management method, system, equipment and medium for metal forming processing resources
CN115640335B (en) Enterprise portrait-based enterprise analysis method, system and cloud platform
CN114049075B (en) Process route creation method, process route creation device, computer equipment and storage medium
CN116738343B (en) Material data identification method and device for construction industry and electronic equipment
CN112580840A (en) Data analysis method and device
CN116629348B (en) Intelligent workshop data acquisition and analysis method and device and computer equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant