Prior art keywords
charging
piles
pile
power
determining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211582444.1A
Other languages
Chinese (zh)
Inventor
梁唐杰
林全喜
唐霖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei Digital Power Technologies Co Ltd
Original Assignee
Huawei Digital Power Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Digital Power Technologies Co Ltd filed Critical Huawei Digital Power Technologies Co Ltd
Priority to CN202211582444.1A priority Critical patent/CN116039428A/en
Publication of CN116039428A publication Critical patent/CN116039428A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60LPROPULSION OF ELECTRICALLY-PROPELLED VEHICLES; SUPPLYING ELECTRIC POWER FOR AUXILIARY EQUIPMENT OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRODYNAMIC BRAKE SYSTEMS FOR VEHICLES IN GENERAL; MAGNETIC SUSPENSION OR LEVITATION FOR VEHICLES; MONITORING OPERATING VARIABLES OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRIC SAFETY DEVICES FOR ELECTRICALLY-PROPELLED VEHICLES
    • B60L53/00Methods of charging batteries, specially adapted for electric vehicles; Charging stations or on-board charging equipment therefor; Exchange of energy storage elements in electric vehicles
    • B60L53/60Monitoring or controlling charging stations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60LPROPULSION OF ELECTRICALLY-PROPELLED VEHICLES; SUPPLYING ELECTRIC POWER FOR AUXILIARY EQUIPMENT OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRODYNAMIC BRAKE SYSTEMS FOR VEHICLES IN GENERAL; MAGNETIC SUSPENSION OR LEVITATION FOR VEHICLES; MONITORING OPERATING VARIABLES OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRIC SAFETY DEVICES FOR ELECTRICALLY-PROPELLED VEHICLES
    • B60L53/00Methods of charging batteries, specially adapted for electric vehicles; Charging stations or on-board charging equipment therefor; Exchange of energy storage elements in electric vehicles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60LPROPULSION OF ELECTRICALLY-PROPELLED VEHICLES; SUPPLYING ELECTRIC POWER FOR AUXILIARY EQUIPMENT OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRODYNAMIC BRAKE SYSTEMS FOR VEHICLES IN GENERAL; MAGNETIC SUSPENSION OR LEVITATION FOR VEHICLES; MONITORING OPERATING VARIABLES OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRIC SAFETY DEVICES FOR ELECTRICALLY-PROPELLED VEHICLES
    • B60L53/00Methods of charging batteries, specially adapted for electric vehicles; Charging stations or on-board charging equipment therefor; Exchange of energy storage elements in electric vehicles
    • B60L53/60Monitoring or controlling charging stations
    • B60L53/62Monitoring or controlling charging stations in response to charging parameters, e.g. current, voltage or electrical charge
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60LPROPULSION OF ELECTRICALLY-PROPELLED VEHICLES; SUPPLYING ELECTRIC POWER FOR AUXILIARY EQUIPMENT OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRODYNAMIC BRAKE SYSTEMS FOR VEHICLES IN GENERAL; MAGNETIC SUSPENSION OR LEVITATION FOR VEHICLES; MONITORING OPERATING VARIABLES OF ELECTRICALLY-PROPELLED VEHICLES; ELECTRIC SAFETY DEVICES FOR ELECTRICALLY-PROPELLED VEHICLES
    • B60L53/00Methods of charging batteries, specially adapted for electric vehicles; Charging stations or on-board charging equipment therefor; Exchange of energy storage elements in electric vehicles
    • B60L53/60Monitoring or controlling charging stations
    • B60L53/67Controlling two or more charging stations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T10/00Road transport of goods or passengers
    • Y02T10/60Other road transportation technologies with climate change mitigation effect
    • Y02T10/70Energy storage systems for electromobility, e.g. batteries
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T10/00Road transport of goods or passengers
    • Y02T10/60Other road transportation technologies with climate change mitigation effect
    • Y02T10/7072Electromobility specific charging systems or methods for batteries, ultracapacitors, supercapacitors or double-layer capacitors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02T90/10Technologies relating to charging of electric vehicles
    • Y02T90/12Electric charging stations

Abstract

The application provides a charging system, a charging management method and a device, and relates to the technical field of vehicles. Wherein, the charging system includes: a power main line; the charging piles are connected in parallel to the power main line for power taking; the management module is used for determining the power limit value of the plurality of charging piles and the total power required by the charging piles for charging operation; and determining a charging strategy at least according to the power limit value when the total power demand is larger than the power limit value so as to manage the charging operation of the plurality of charging piles. According to the charging system, under the condition that the reserved power capacity of the charging system is limited, the charging operation problem of a plurality of charging piles is solved by determining the charging strategy. When the charging pile is needed to be added, the newly added charging pile is connected with the shared power main line in parallel, so that the installation cost of the charging pile is reduced.

Description

Charging system, charging management method and device
Technical Field
The present invention relates to the field of vehicle technologies, and in particular, to a charging system, a charging management method, and a device.
Background
With the explosive growth of electric devices such as electric automobiles and electric vehicles, the demand of charging piles is also increased. However, the reserved power capacity of the existing charging piles is limited, and when the number of the charging piles reaches the installable limit value, the charging piles cannot be increased, so that the requirement of a user for increasing the charging piles cannot be met. Therefore, under the condition that the reserved power capacity is limited, how to meet the requirement of increasing the charging piles for users after the number of the charging piles reaches the installable limit value is a problem to be solved.
Disclosure of Invention
In order to solve the above-mentioned problems, embodiments of the present application provide a charging system, a charging management method and a device. According to the method, the plurality of charging piles are connected in parallel through the shared power main line, and after the number of the charging piles reaches the mountable limit value, the charging problem of the plurality of charging piles when the reserved power capacity is limited is solved through determining the charging strategy.
For this reason, the following technical solutions are adopted in the embodiments of the present application:
in a first aspect, embodiments of the present application provide a charging system, including: a power main line; the charging piles are connected in parallel to the power main line for power taking; the management module is used for determining the power limit value of the plurality of charging piles and the total power required by the charging piles for charging operation; and determining a charging strategy at least according to the power limit value when the total power demand is greater than the power limit value, so as to manage charging operations of the plurality of charging piles; the charging strategy comprises the determination of the charging sequence of the charging pile for performing the charging operation, the determination of the charging time length, the determination of the charging electric quantity or the determination of the charging power.
In this embodiment, the charging policy includes determining a charging order of the charging posts performing the charging operation based on a sequence in which the charging requests are received or based on priorities of the respective charging posts; or alternately carrying out charging operation on the charging piles which carry out the charging operation based on a preset charging time period or a preset charging electric quantity; or simultaneously charging one or more charging piles in the charging piles for charging with preset charging power. When a plurality of charging piles perform charging operation simultaneously and the total power required is larger than the power limit value, a charging strategy is determined at least under the requirement of the power limit value so as to manage the charging operation of the plurality of charging piles, thereby solving the charging problem when the total power required by the plurality of charging piles is higher than the allowable power capacity. And the installation wiring of the charging pile is carried out in a mode of sharing the electric power main line, when the charging pile needs to be added, the charging wire of the newly added charging pile is directly connected with the shared electric power main line, the repeated installation of the charging pile is not needed, and the installation cost of the charging pile is reduced.
In one embodiment, the power limits of the plurality of charging piles are determined based on a preset power.
In this embodiment, the method of predetermining the power limit value may include a rated power based on the household electricity meter, available power of a remaining power capacity of the power system, or the like. By predetermining the power limit value, the power use condition of the plurality of charging piles in the charging system of the embodiment can be controlled, so that the charging operation of the charging system is completed on the premise of ensuring the electricity utilization safety.
In one embodiment, the power limit is determined based on the power of other loads to which the main line of power is connected.
In this embodiment, since the charging system is a complete set of charging systems, including other loads, such as lighting devices, in addition to the charging posts, the power occupied by the other loads is also changed in real time since the access conditions of the other loads are changed in real time. Therefore, the embodiment considers the situation that the charging system is connected with other loads, and determines the power limit value based on the power of the other loads connected with the power main line, so that the power limit value can be changed in real time, and the utilization rate of available power and the charging efficiency of the charging system are improved.
In one embodiment, a communication module is configured in each charging pile of the plurality of charging piles to implement a communication connection between the management 5 module and each charging pile.
In the embodiment, the communication connection between the management module and each charging pile is realized by configuring the communication module, so that the information interaction problem between the management module and the charging pile is solved. The communication module can transmit the charging strategy, and can also acquire the charging pile working state information of the charging pile in real time, and whether the equipment to be charged is connected with the charging pile or not and whether the equipment to be charged is charged or not
And the pile completes the charging operation and other information, and adjusts the charging strategy. The charging system of this embodiment can perform communication connection, and perform inter-pile networking of the charging piles that are performing the charging operation, and 0.
In one embodiment, the management module is further configured to: and responding to the fact that the number of the charging piles for charging operation is larger than or equal to a preset threshold value, sending activating and networking instructions to a communication module in the charging piles for charging operation, and networking among the charging piles for charging operation, wherein the inter-pile networking refers to communication network connection among the charging piles for charging operation.
In this embodiment, according to the specific situation of the plurality of charging piles of the charging system, by setting a preset threshold,
different networking operations are adopted according to different numbers of charging piles which are in charging operation. For example, when the number of charging piles which are performing charging operation is lower than a preset threshold, the total power required by the charging system is lower than a power limit value, and the charging operation is directly performed without inter-pile networking; when the number of the charging piles which are in charging operation is larger than or equal to a preset threshold value, the total power required by the charging system is larger than or equal to a power limit value, the charging operation is required to be carried out through a charging strategy, and the charging piles which are in charging operation 0 are networked among piles and are used for transmitting the charging strategy. This embodiment uses a charging strategy by setting a preset threshold
The condition of slightly carrying out the charging operation is further limited, and when the number of the charging piles which are carrying out the charging operation is lower than a preset threshold value, the charging operation can be directly carried out, so that the charging efficiency is improved.
In one embodiment, the management module is further configured to obtain charging pile operating status information of the plurality of charging piles,
the charging pile working state information comprises the power consumption of the charging pile and whether the charging pile is in a charging working state; and 5, determining the charging strategy based on the power limit value and the charging pile working state information of the plurality of charging piles.
In this embodiment, when the device to be charged is connected to the charging pile, or the charging pile completes the charging operation, the charging pile working state information of the plurality of charging piles may change, and the charging policy is further related to the charging pile working state information of the plurality of charging piles.
0 in one embodiment, the management module is disposed at each of the plurality of charging posts.
In this embodiment, the management module is set up in each of the plurality of charging piles, compared with the management module of independent peripheral equipment, the related wiring and installation facilities can be avoided, the complexity of the system is reduced, and meanwhile, when the management module in use fails, the management modules of other charging piles can be selected for charging operation, so that the charging operation of the charging system in the event of the management module failure is ensured to be smoothly carried out.
5 in one embodiment, the management module is further configured to select a main charging pile from the plurality of charging piles, the main charging pile
The electric peg is used to determine a charging strategy.
In this embodiment, the workload of the management module can be reduced and the charging efficiency and response performance of the charging system can be improved by further dividing the determination work of the charging strategy. For example, when the management module is separately arranged, the main charging pile performs confirmation
The fixed charging strategy can reduce the workload of the management module and improve the response performance of the management module; when the management module is arranged on each charging pile of the plurality of charging piles 0, the management module of the main charging pile can determine the charging strategy, and the management modules of other charging piles do not perform charging strategy determination work, so that the workload of the management module can be reduced.
In one embodiment, the management module is further configured to receive signal data from a terminal device; the determination of the charging strategy is also related to signal data from the terminal device.
In this embodiment, the signal data from the terminal device includes processing operation information such as fault processing, charging time adjustment, charging pile priority adjustment, and the like for the corresponding charging pile. In determining the charging strategy, it is also necessary to meet the content requirements of the signal data from the terminal device. The user can influence the charging operation of the charging system through the terminal equipment, so that the charging requirement of the user is met, and the user experience is improved.
In one embodiment, the charging strategy comprises: according to the sequence of receiving the charging requests, controlling the charging pile to carry out charging operation; and controlling the corresponding charging piles to perform charging operation in a preset time period; controlling each charging pile to charge based on the priority of each charging pile; controlling each charging pile to alternately perform charging operation based on the preset electric quantity of each charging pile; a plurality of charging piles perform charging operation simultaneously; and alternately performing one or more of the charging operations based on the charging pile numbers of the plurality of charging piles that are performing the charging operation.
In the embodiment, the charging strategy of the charging system is determined by selecting or combining different charging strategies, so that the charging operation requirement of the charging system is met.
In a second aspect, an embodiment of the present application provides a charging management method, including: determining power limit values of a plurality of charging piles and total power required by the charging piles for charging operation; when the total power required is greater than the power limit value, determining a charging strategy at least according to the power limit value so as to manage charging operation of the plurality of charging piles; the charging strategy comprises the steps of determining the charging sequence of the charging pile for charging operation, determining the charging time length, determining the charging electric quantity or determining the charging power.
In one embodiment, the power limits of the plurality of charging piles are determined based on a preset power.
In one embodiment, the power limit is determined based on the power of other loads to which the main line of power is connected.
In one embodiment, before determining the charging strategy at least from the power limit, further comprising: when the number of the charging piles for charging operation is greater than or equal to a preset threshold value, sending activating and networking instructions to a communication module in the charging piles for charging operation, and networking the charging piles for charging operation among piles, wherein the inter-pile networking refers to communication network connection among the charging piles for charging operation.
In one embodiment, before determining the charging strategy at least from the power limit, further comprising: and selecting a main charging pile from the plurality of charging piles, wherein the main charging pile is used for determining a charging strategy.
In one embodiment, the charge management further comprises: acquiring charging pile working state information of the plurality of charging piles, wherein the charging pile working state information comprises the power consumption of the charging piles and whether the charging piles are in a charging working state; and determining the charging strategy based on the power limit value and the charging pile working state information of the plurality of charging piles.
In one embodiment, the charge management further comprises: receiving signal data from a terminal device; and the determination of the charging strategy is also related to signal data from the terminal device.
In one embodiment, the charging strategy comprises: according to the sequence of receiving the charging requests, controlling the charging pile to carry out charging operation; and controlling the corresponding charging piles to perform charging operation in a preset time period; controlling each charging pile to charge based on the priority of each charging pile; controlling each charging pile to alternately perform charging operation based on the preset electric quantity of each charging pile; a plurality of charging piles perform charging operation simultaneously; and alternately performing one or more of the charging operations based on the charging pile numbers of the plurality of charging piles that are performing the charging operation.
In a third aspect, an embodiment of the present application provides a charging management device, including: the receiving and transmitting unit is used for realizing communication connection of the charging management device; the processing unit is used for determining the power limit value of the plurality of charging piles and the total power required by the charging piles for charging operation; and when the total power demand is greater than the power limit, determining a charging strategy at least according to the power limit so as to manage charging operations of the plurality of charging piles; the charging strategy comprises the steps of determining the charging sequence of the charging pile for charging operation, determining the charging time length, determining the charging electric quantity or determining the charging power.
In one embodiment, the processing unit is specifically configured to determine the power limits of the plurality of charging piles based on a preset power.
In one embodiment, the processing unit is specifically configured to determine the power limit value based on a power of other loads to which the main power line is connected.
In an embodiment, the transceiver unit is specifically configured to send activation and networking instructions to a communication module in the charging pile for performing the charging operation when the number of the charging piles for performing the charging operation is greater than or equal to a preset threshold, and perform inter-pile networking on the charging pile for performing the charging operation, where inter-pile networking refers to communication network connection between the charging piles for performing the charging operation.
In one embodiment, the processing unit is specifically configured to select a primary charging pile from the plurality of charging piles, where the primary charging pile is configured to determine a charging policy.
In one embodiment, the processing unit is specifically configured to obtain charging pile working state information of the plurality of charging piles, where the charging pile working state information includes electric power of the charging pile and whether the charging pile is in a charging working state; and determining the charging strategy based on the power limit value and the charging pile working state information of the plurality of charging piles.
In one embodiment, the processing unit is specifically configured to receive signal data from a terminal device; and the determination of the charging strategy is also related to signal data from the terminal device.
In one embodiment, the charging strategy comprises: according to the sequence of receiving the charging requests, controlling the charging pile to carry out charging operation; and controlling the corresponding charging piles to perform charging operation in a preset time period; controlling each charging pile to charge based on the priority of each charging pile; controlling each charging pile to alternately perform charging operation based on the preset electric quantity of each charging pile; a plurality of charging piles perform charging operation simultaneously; and alternately performing one or more of the charging operations based on the charging pile numbers of the plurality of charging piles that are performing the charging operation.
In a fourth aspect, in an embodiment of the present application, there is provided a computing device, including: at least one transceiver, at least one memory, at least one processor for executing instructions stored in the memory to cause the charging stake to perform embodiments as per the second aspect as per the possible implementations.
In a fifth aspect, in an embodiment of the present application, there is provided a charging management system, including: a plurality of charging posts, an electrically powered device, wherein the plurality of charging posts perform embodiments as each possible implementation of the second aspect.
In a sixth aspect, embodiments of the present application provide a computer readable storage medium having a computer program stored thereon, which when executed in a computer causes the computer to perform embodiments as possible in the second aspect.
A seventh aspect is a computer program product, characterized in that the computer program product stores instructions that, when executed by a computer, cause the computer to implement embodiments as possible for the second aspect.
Drawings
The drawings that accompany the detailed description can be briefly described as follows:
fig. 1 is a schematic diagram of a charging system provided in an embodiment of the present application;
FIG. 2 is a schematic diagram of another charging system provided in an embodiment of the present application;
fig. 3 is a schematic architecture diagram of a charging system according to an embodiment of the present application;
fig. 4 is a flowchart of a charging management method of a charging pile provided in an embodiment of the present application;
Fig. 5 is a flowchart of a charging management method establishment procedure provided in an embodiment of the present application;
fig. 6 is a flowchart of a charging management method using process provided in an embodiment of the present application;
fig. 7 is a schematic structural diagram of a charging management device according to an embodiment of the present application;
fig. 8 is a schematic diagram of a computing device according to an embodiment of the present application.
Detailed Description
The technical solutions in the embodiments of the present application will be described below with reference to the drawings in the embodiments of the present application.
The term "and/or" herein is an association relationship describing an associated object, and means that there may be three relationships, for example, a and/or B may mean: a exists alone, A and B exist together, and B exists alone. The symbol "/" herein indicates a relationship in which the associated object is "or", e.g., a/B indicates a or B.
The terms "first" and "second" and the like in the description and in the claims are used for distinguishing between different objects and not for describing a particular sequential order of objects. For example, the first response message and the second response message, etc. are used to distinguish between different response messages, and are not used to describe a particular order of response messages.
In the embodiments of the present application, words such as "exemplary" or "such as" are used to mean serving as an example, instance, or illustration. Any embodiment or design described herein as "exemplary" or "for example" should not be construed as preferred or advantageous over other embodiments or designs. Rather, the use of words such as "exemplary" or "such as" is intended to present related concepts in a concrete fashion.
In the description of the embodiments of the present application, unless otherwise specified, the meaning of "a plurality of" means two or more, for example, a plurality of processing units means two or more processing units and the like; the plurality of elements means two or more elements and the like.
When a user has a need of increasing the charging pile, in order to meet the needs of the user, a solution is provided, and when the user has a need of increasing the charging pile, a newly-increased charging pile is connected in a single wiring mode.
In the above-mentioned solution, need the block terminal to redistribute, under the limited circumstances of reserved power capacity of charging the stake, only can install limited charging stake, after the mountable limit value is reached to the stake quantity of charging, just can't increase the stake of charging, can't satisfy the demand that the user increased the stake of charging. When a newly added charging pile needs to be accessed, the independent wiring mode needs to be used for power distribution room to re-distribute power, electric meter installation and the like. And each time the charging pile is added, the work of installing the charging pile is required to be repeated, and the installation cost of the charging pile is increased.
Accordingly, embodiments of the present application propose another solution, a charging system comprising: a power main line; the charging piles are connected in parallel to the power main line for power taking; a management module for determining a power limit for the plurality of charging piles; and determining a charging strategy at least according to the power limit value so as to manage charging operation of the plurality of charging piles. In this embodiment, when a plurality of charging piles perform charging operation simultaneously, a charging policy is determined at least under the requirement of the power limit value, so as to manage the charging operation of the plurality of charging piles, thereby solving the charging problem when the total power required by the plurality of charging piles is higher than the allowable power capacity.
Fig. 1 is a schematic diagram of a charging system according to an embodiment of the present application. As shown in fig. 1, the system includes a main power line 100, a plurality of charging piles, and a management module 300. The power main line 100 is a bus for supplying input power to a plurality of charging piles, and the plurality of charging piles are connected in parallel to the bus for taking power. The power main line 100 is a bus for supplying input power to a plurality of charging piles, is a dc bus of the charging piles, and is not a power transmission cable of the utility power. In one embodiment, the electric power main line 100 passes through all the parking space positions in a surrounding manner, so that the charging pile can be conveniently connected to the next charging pile. The plurality of charging piles may include, for example, the charging piles 210, 220 as shown in fig. 1. Each charging pile is added, the charging wires of the charging pile need to be connected in parallel to the power main line 100. The management module 300 determines a power limit value of the plurality of charging piles, and manages the plurality of charging piles to perform charging operation by the management module 300 under the limit of the power limit value. The management module 300 may be connected to the plurality of charging piles wirelessly or by a wire.
In one embodiment, the number of the power main lines 100 may be selected according to the power limit value, and when the power limit value is higher, a larger number of the power main lines 100 may be selected, and the connection relationship between the power main lines 100 and the plurality of charging piles in the system architecture of the plurality of power main lines 100 is the same as that in the system architecture of the 1 power main line 100, where the power limit value of the plurality of charging piles of the plurality of power main lines 100 is the sum of the power of the plurality of charging piles of the plurality of power main lines 100, and the plurality of charging piles are connected in parallel to the plurality of buses to obtain power. The present embodiment will be described with 1 power main line 100 as an example.
In one embodiment, a communication module may be provided inside the charging pile, through which inter-pile ad hoc network transmission is performed for a plurality of charging piles. By means of inter-pile ad hoc network transmission, the communication module can acquire the charging pile working state information of the charging pile which is in charging operation at a certain moment, wherein the charging pile working state information comprises the power consumption of the charging pile, whether the charging pile is in a charging operation state or not and the like. The charging pile transmits the charging pile operating state information, and the management module 300 receives the charging pile operating state information, determines and transmits a charging policy, and receives and executes the charging policy by a plurality of charging piles performing charging operation.
In another possible embodiment, the charging piles may not be provided with a communication module, and the management module 300 is used for networking transmission of a plurality of charging piles. The management module 300 may obtain information of a working state of a charging pile in which a charging operation is performed at a certain time, including power consumption of the charging pile, whether the charging pile is in a charging operation state, and the like. The management module 300 determines and transmits a charging policy according to the charging pile operating state information, and a plurality of charging piles performing charging operations receive and execute the charging policy.
Fig. 2 is a schematic diagram of another charging system provided in an embodiment of the present application. As shown in fig. 2, the system includes a main power line 100 and a plurality of charging piles. The power line 100 is connected with a plurality of charging piles, which may include, for example, the charging piles 210 and 220 shown in fig. 2. The power line 100 is a bus for supplying input power to a plurality of charging piles, and each charging pile is added, a charging wire of the charging pile needs to be connected in parallel to the power line 100. And determining the power limit value of the plurality of charging piles, realizing transmission of inter-pile signals by a pile-to-pile ad hoc network mode of the plurality of charging piles under the limit of the power limit value, and controlling the plurality of charging piles to perform charging operation by using a charging strategy mode.
In one embodiment, the charging operation is accomplished by inter-stake networking of charging stakes that are performing the charging operation. The charging pile is provided with a communication module and an internal management module, wherein the internal management module refers to that the charging pile is provided with the management module, and is not a limiting description of the position and the function of the management module. The communication module of the charging pile is in communication connection, and the communication module can acquire the information of the working state of the charging pile, including the power consumption of the charging pile, whether the charging pile is in a charging working state or not, and the like, wherein the charging pile is in a charging working state at a certain moment. And after the charging pile working state information of the charging piles which are in charging operation is obtained, the communication modules of the plurality of charging piles which are in charging operation perform inter-pile ad hoc network. For example, according to the charging pile working state information, the management module inside the charging pile selects the main charging pile from a plurality of charging piles for charging operation, and may also select the main charging pile from all the charging piles. The main charging pile determines and transmits the charging strategy, and all the charging piles for charging operation receive and execute the charging strategy, so that the inter-pile ad hoc network can realize the transmission of the charging strategy. Meanwhile, the communication module can monitor the charging pile working state information of all or preset number of charging piles in real time, update the charging pile working state information in real time and further update the charging strategy in real time.
In another possible embodiment, the charging operation is not achieved by inter-pile ad hoc networking of the charging piles that are performing the charging operation. The charging pile is provided with a communication module and an internal management module. When charging equipment with charging requirements is connected to the charging piles, the preset number or all the charging piles are in communication connection through the communication modules of the charging piles. The communication module can acquire the working state information of the charging pile, including the power consumption of the charging pile, whether the charging pile is in a charging working state or not, and the like, wherein the charging pile is in the charging working state at a certain moment. According to the working state information of the charging piles, the management module in the charging piles selects the main charging pile from a plurality of charging piles for charging operation, and can also select the main charging pile from all the charging piles. The main charging pile determines and transmits a charging strategy, and all the charging piles performing charging operation receive and execute the charging strategy.
The charging pile is internally provided with an internal management module, when the internal management module of the main charging pile fails and cannot determine and send a charging strategy, other charging piles can be selected as the main charging pile to complete the determination and sending of the charging strategy, so that the charging operation is guaranteed. In one embodiment, in the process of selecting the main charging pile, the fault of the plurality of charging piles can be firstly checked, and the charging pile with the fault of the internal management module can be eliminated.
Fig. 3 is a schematic architecture diagram of a charging system according to an embodiment of the present application. As shown in fig. 3, the architecture includes a main power line 100 and a plurality of charging piles, each of which is provided with a communication module and an internal management module. The power line 100 is connected with a plurality of charging piles, which may include, for example, charging piles 210 and 220 as shown in fig. 3. Illustratively, as shown in fig. 3, the charging stake 210 includes a communication module 211, an internal management module 212, and the charging stake 220 includes a communication module 221, an internal management module 222. The communication module can realize communication connection of a plurality of charging piles, and can realize real-time monitoring of the charging operation states of all the charging piles and transmission of charging strategies. And the internal management module selects a main charging pile from a plurality of charging piles for charging operation according to the charging pile working state information, and can also select the main charging pile from all the charging piles. The management module inside the main charging pile determines and transmits the charging strategy, and all the management modules inside the plurality of charging piles for charging operation receive and execute the charging strategy.
In one embodiment, the charging operation is accomplished by inter-stake networking of charging stakes that are performing the charging operation. In one embodiment, the inter-pile ad hoc Network mode with the communication module in the charging pile may be a wireless connection, such as a bluetooth connection, a wireless Network (Wireless Fidelity, wi-Fi) connection, an ethernet connection, a Low-Power Wide-Area Network (LPWAN) connection, etc.; wired connections, such as wire networking of multiple charging posts, e.g., optical fibers, wires, etc., may also be implemented by way of wiring.
In the embodiment of the present application, by determining the power limit value of the plurality of charging piles connected to the power main line 100, the plurality of charging piles are controlled and managed by the management module 300 under the limitation of the power limit value.
In another possible embodiment, the main power line 100 is connected with a household electric meter, and the rated power of the household electric meter is lower than the available power of the remaining power capacity of the power system. The power limit values of the plurality of charging piles connected to the power main line 100 are preset based on the rated power of the service-entering electricity meter. The rated power of the household electricity meter is preset in the management module 300 or the management module 212 inside the plurality of charging piles by using a program instruction mode.
In another possible embodiment, the power main line 100 is not connected to the home meter, or is connected to the home meter, but the rated power of the home meter is higher than the available power of the remaining power capacity reserved to the charging system by the power system, and the power limit value of the power main line 100 is preset based on the available power of the remaining power capacity of the power system. The available power for the remaining power capacity of the power system is preset in the management module 300 or in the management module 212 inside the plurality of charging piles using the manner of program instructions.
In another possible embodiment, the power limit is determined based on the power of other loads to which the main line of power is connected. When the charging system is connected with other loads, such as a lighting device and the like, and changes in real time, the power of the charging system, which can be used by a plurality of charging piles, changes in real time. For example, when other loads are connected, the power limit value of the charging system of the charging pile is obtained by subtracting the power of the other loads from the total power allowed by the power system. The power limit values of the plurality of charging piles are dynamically set based on a preset strategy according to the change of the available power, so that the utilization rate of the available power of the residual power capacity reserved for the charging system by the power system is improved. The preset strategy comprises the following steps: dynamically setting the power limit values of a plurality of charging piles according to the fixed percentage of the power which can be used by the plurality of charging piles after the access load condition of the charging system is changed; and dynamically setting the power limit values of the plurality of charging piles according to the fixed difference value of the power available for the plurality of charging piles after the access load condition of the power system is changed.
In another possible embodiment, when the rated power of the service-entering electricity meter is lower than the available power of the remaining power capacity of the power system by a predetermined threshold value, such as lower than half, the plurality of service meters may be connected in parallel to the plurality of power main lines 100 by arranging the plurality of power main lines 100 instead of 1 power main line 100 in the scheme. In this way, the power limit value is the total power of the household electricity meters of the power main lines 100, so that the utilization rate of available power of the residual power capacity of the power system can be improved, the charging efficiency can be improved, and the user experience can be improved. The utilization rate of available power of the residual power capacity of the power system can be improved by replacing the high-power ammeter.
In one embodiment, a plurality of charging piles are connected to the power main line 100 through a continuous line node T connection mode, so as to form a framework of a multi-pile shared power main line, and one wiring meets the requirement of the connection of the plurality of charging piles. Illustratively, the uninterrupted junction of the power main line 100 is connected to the plurality of charging piles by using a T-connection terminal, such as a disconnection-free connection mode, where the disconnection-free connection mode includes: a wire-break-free wire connector.
Fig. 4 is a flowchart of a charging management method for a charging pile provided in an embodiment of the present application. As shown in fig. 4, the specific process of the charging management method of the charging pile is as follows:
step S401, determining a power limit.
In one embodiment, the power limit is used to limit the total power of the charging piles performing the charging operation, preventing damage to the electrical utility beyond an allowable power maximum.
In one embodiment, the power limit may be a power limit of a plurality of charging piles to which the power main line 100 is connected, that is, a power limit of a total power of the charging piles for which the charging operation is performed simultaneously. The method for determining the power limit comprises the following steps: presetting a power limit value based on rated power of a household ammeter; presetting a power limit value based on available power of the remaining power capacity of the power system; the power limit is dynamically determined based on a pre-set policy. The specific details of the method for determining the power limit are not described here.
In one embodiment, the power limit may be preset to be stored in a management module inside the charging pile.
Step S402, obtaining the working state information of the charging pile.
In one embodiment, the working state information of the charging piles may be obtained by performing communication connection on all or a preset number of charging piles, where the preset number of charging piles are in communication connection when, for example, charging piles used in an emergency or charging piles with special requirements are available. The charging pile working state information comprises the power consumption of the charging pile and whether the charging pile is in a charging working state.
In one embodiment, a predetermined number, or all, of the charging posts are communicatively connected by a communication module of the charging post. The communication module can acquire the working state information of the charging piles which are in charging operation at a certain moment, wherein the working state information comprises the number of the charging piles which are in charging operation, the number of the charging piles and the like. The communication connection can realize the real-time monitoring of the charging operation states of all the charging piles, and the charging pile working state information is updated in real time, so that the charging strategy of charging operation performed by a plurality of charging piles is updated and managed in real time.
In another possible embodiment, the management module 300 obtains the working state information of the charging pile that is performing the charging operation at a certain moment through wired connection or wireless connection, so as to update the charging strategy in real time.
Step S403, selecting a main charging pile.
In one embodiment, the primary charging pile may be selected from the plurality of charging piles that are performing the charging operation based on the charging pile operating state information by inter-pile networking, which may also be referred to as inter-pile ad hoc networking, of the charging piles that are performing the charging operation. The charging piles can be selected from all or a preset number of charging piles through a preset method, and the preset method comprises random selection, selection according to the number of the charging piles and the like.
In one embodiment, the inter-pile ad hoc network is performed on the charging piles according to the charging pile operation state information, and all or a preset number of communication connections of the charging piles can be utilized. The management module in the charging pile can select the main charging pile from a plurality of charging piles for charging operation, and can also select the main charging pile from all the charging piles. Meanwhile, the inter-pile ad hoc network can realize the transmission of charging strategies. When a plurality of charging piles which are being charged are subjected to inter-pile ad hoc network, compared with communication connection, the number of the charging piles for receiving the charging strategy can be reduced, and the transmission efficiency of the charging strategy is improved.
In one embodiment, at least one standby main charging pile may be selected, and when a management module inside the main charging pile fails and a charging strategy cannot be determined and sent, the standby main charging pile may be selected as the main charging pile, so as to complete the determination and sending of the charging strategy, thereby ensuring the performance of the charging operation.
In one embodiment, based on the charging pile working state information, the management module 300 or an internal management module of the charging pile setting determines the number of charging piles performing the charging operation, and when the number of charging piles performing the charging operation is greater than or equal to a preset threshold, such as 1, 10, etc., the sum of the powers of the charging piles performing the charging operation in the charging pile working state information is the required total power, which is greater than or equal to a power limit, and inter-pile ad hoc network is required or a main charging pile is selected. The management module 300 or an internal management module of the charging pile arrangement performs inter-pile networking of the charging piles which are performing the charging operation. In one embodiment, a primary charging pile is selected to determine a charging policy, and an inter-pile ad hoc network transmits the charging policy for managing charging operations performed by a plurality of charging piles.
In one embodiment, the inter-pile networking operation includes:
in step 1, a preset threshold value of the number of charging piles is preset in the management module 212 of the charging pile or the peripheral management module 300. The preset threshold is an integer part of the power limit divided by the power of the single charging pile, wherein when the powers of the charging piles are different, the power of the single charging pile is the power of the charging pile with the largest power.
And 2, monitoring the working state information of the charging piles of the plurality of charging piles in a wired or wireless mode.
And 3, determining the number of charging piles to be charged based on the charging pile working state information.
And 4, when the number of the charging piles is greater than the preset threshold value of the number of the charging piles, the management module 212 of the charging piles or the peripheral management module 300 send activating and networking instructions to the communication module of the charging piles for charging operation.
And 5, the communication module of the charging pile for charging operation performs inter-pile networking, and the charging pile for charging operation is connected through a communication network. The inter-pile networking refers to communication network connection between charging piles for performing charging operation.
In one embodiment, when the number of charging piles in the charging pile working state information, which are performing charging operations, is less than or equal to a preset threshold, for example, 1, 10, etc., the total power required by the charging piles in the charging pile working state information, which are performing charging operations, is less than the power limit, no inter-pile ad hoc network is required or a main charging pile is selected, and when the to-be-charged device is connected to the charging pile, the charging operation can be performed directly according to the actual requirement.
In one embodiment, a method of selecting a primary charging stake includes: according to the number of the charging piles of the plurality of charging piles which are in charging operation, determining the charging pile as the main charging pile, wherein the number is the front; and determining the charging pile as the main charging pile according to the sequence of the received charging requests and the preceding sequence.
In step S404, the primary charging pile determines a charging strategy.
In one embodiment, the management module inside the primary charging stake determines the charging policy based on the charging stake operating status information or the power limit value, and the charging policy is sent through the communication module of the primary charging stake.
In one embodiment, the charging policy may be sent and received by the communication module of the charging stake, or may be sent and received by the management module 300.
In one embodiment, under the requirement of meeting the power limit value, according to the charging pile working state information or the power limit value, for example, when the number of charging piles which are performing charging operation in the charging pile working state information is greater than a preset threshold value, such as 1, 10, etc., or when the total power of the charging piles which are performing charging operation in the charging pile working state information is greater than the power limit value, the main charging pile performs charging operation of the charging pile by determining the charging strategy. And the main charging pile can also perform charging operation of the charging pile by determining a charging strategy according to the charging pile working state information or the power limit value under the condition that whether the charging pile working state information is larger than a preset threshold value or not and whether the charging pile working state information is larger than the power limit value or not is judged.
In one embodiment, the primary charging post and the primary charging post may not be selected to determine the charging policy, and the internal management module of the charging post, which is performing the charging operation, or a preset number of charging posts, or all charging posts, may be used to perform the determination of the charging policy, where the charging policy manages the charging post that determines the charging policy.
In one embodiment, the determination of the charging policy may be performed by the management module 300, either a preset number of charging posts, or all of which are performing the charging operation.
The charging strategies of the embodiments of the present application may be obtained by selecting or combining different charging strategies of the embodiments of the present invention.
Charging strategies of embodiments of the present invention include, but are not limited to: and controlling the charging pile to carry out charging operation according to the sequence of receiving the charging requests. In one embodiment, the charging pile operation is performed on one or more charging piles with previous charging requests, and other charging operations are performed after the charging is completed.
Charging strategies of embodiments of the present invention include, but are not limited to: and controlling the corresponding charging piles to perform charging operation in a preset charging time period. In one embodiment, the charging operation is performed on the plurality of charging piles that perform the charging operation in turn, in accordance with the charging period. By way of example, when the emergency short-distance requirement of the user can be met, the vehicle can be immediately taken away after the vehicle is fully charged with certain electric quantity.
Charging strategies of embodiments of the present invention include, but are not limited to: and controlling each charging pile to charge based on the priority of each charging pile. In the embodiment of the present invention, the management module 300 is further configured to receive signal data from the terminal device. The signal data of the terminal device includes a priority set by the user. And performing charging pile operation on one or more charging piles with the previous priority.
Charging strategies of embodiments of the present invention include, but are not limited to: and controlling each charging pile to alternately perform charging operation based on the preset electric quantity of each charging pile. In one embodiment, the preset amount of electricity alternately charges the plurality of charging piles performing the charging operation. By way of example, when the emergency short-distance requirement of the user can be met, the vehicle can be immediately taken away after the vehicle is full of the preset electric quantity.
Charging strategies of embodiments of the present invention include, but are not limited to: and simultaneously carrying out charging operation by a plurality of charging piles with preset charging power. In one embodiment, the preset charging power is lower than the demand management of the charging stake so that the total power demand of the charging stake to charge is lower than or equal to the power limit. For example, during a charging operation of a vehicle at night, one or more of the charging piles for charging are charged at a low power at the same time, and after the charging is completed, all the charging piles are turned off or dormant to save the electric power.
Charging strategies of embodiments of the present invention include, but are not limited to: the charging operation is alternately performed based on the charging pile numbers of the plurality of charging piles that are performing the charging operation. In one embodiment, the charging posts with the previous charging post numbers are charged first. By way of example, in public parking places, the charging piles with the front charging pile numbers are charged, and management of the charging piles is facilitated. For example, the charging pile with the previous number belongs to the first-in first-out position, for example, the customer grade is set.
In an embodiment, the foregoing charging policy of the embodiment of the present invention may be stored in advance in a management module disposed inside a charging pile, where the method for determining the charging policy by the management module inside the charging pile includes: selecting or combining from preset charging strategies. In an exemplary embodiment, when the total power required by the charging pile with a high priority is lower than the power limit, the charging policy according to the priority may be combined with the charging policy according to the charging period, so as to obtain the final required charging policy. The charging strategies with the priority are used for executing charging operation on the charging piles with the high priority. And the charging strategy which is charged according to the preset time period is used for the charging pile with low priority to execute the charging strategy within the limit of the residual power after the charging strategy with priority is executed, namely the difference value between the power limit value and the total power required by the charging pile with high priority.
In one embodiment, the communication module of the charging pile according to the embodiment of the present invention may further receive signal data from the terminal device and related information of the charging pile sent to the terminal device. The signal data from the terminal device includes processing operation information such as fault handling, charging time adjustment, charging pile priority adjustment, etc. for the corresponding charging pile. The related information of the charging pile sent to the terminal device includes the working state of the charging pile, such as the time required for completing charging, the charging power of the charging pile, the priority of the charging pile, and the like. In one embodiment, when the management module inside the main charging pile determines the charging policy, the content requirements of the signal data from the terminal device also need to be met.
In step S405, the plurality of charging piles execute a charging strategy.
In one embodiment, the charging policy may be received and executed by a plurality of charging posts that are performing a charging operation, and the charging policy may be received and executed by all of the charging posts.
In one embodiment, a plurality of charging piles that are performing charging operations other than the master charging pile may be noted as slave charging piles, which need to receive and execute charging policies. When the main charging pile is a charging pile which is in charging operation, the main charging pile needs to determine and send a charging strategy and also needs to receive and execute the charging strategy. When the main charging pile is a charging pile that does not perform charging operation, the main charging pile needs to determine and transmit a charging policy. All communication modules of a plurality of charging piles which are in charging operation receive a charging strategy, and an internal management module executes the charging strategy.
In one embodiment, the management module inside the slave charging pile may not receive and execute the charging policy, and the management module inside the master charging pile controls the charging operation of the slave charging pile through the charging policy.
In an embodiment, the inter-pile ad hoc network may not be performed, and the related contents of step S403, step S404, and step S405 are executed based on the communication connection.
In the above embodiments, the charging piles involved include, but are not limited to: electric automobile alternating current fills electric pile networking, miniwatt direct current fills electric pile networking. The management module inside the charging pile generally refers to a module with a processing function, which may be a Microprocessor (MCU), an embedded ARM processor, etc., or even a cloud server, and the embodiment of the present application is not limited herein. The communication module of the charging pile generally refers to a module with a communication function, and can be a wired communication assembly or a wireless communication assembly. For example, if the circuit layout is simplified, the communication module of the charging post may be specifically configured as a wireless communication module, for example, a chip module of a wireless network (Wireless Fidelity, wi-Fi), a chip module of bluetooth technology, a chip module of zigbee technology, a chip module of Long Range low power data transmission technology (LoRa), and so on, so that the inter-post ad hoc network of the charging post may perform signal transmission through a wireless communication manner. If the charging safety in the practical application process is improved, the occurrence probability of the charging danger is reduced, and the communication module of the charging pile can be specifically selected as a wired communication component, for example, an RS-232 standard interface component (recommended standard, RS), so that signal transmission is performed between the charging piles of the inter-pile ad hoc network in a wired communication mode. In one embodiment, the charging pile can be provided with a wired communication component and a wireless communication component at the same time so as to meet different requirements in practical application. The embodiments of the present application are not limited herein.
The implementation process of the technical solution of the embodiment of the present application is described below in terms of software.
In this embodiment, for manufacturers of charging piles, in order to implement functions of inter-pile ad hoc network and adaptive power limitation of the charging piles, control software for managing the charging piles needs to be developed and loaded in the charging piles, and in one embodiment, loaded in a management module inside the charging piles. When the preset use condition is met, control software is started to control the charging pile to carry out charging operation, wherein the control software comprises the steps of detecting the working state information of the charging pile, determining, sending, receiving, executing a charging strategy and the like. Fig. 5 is a flowchart of a charging management method establishing process provided in the embodiment of the present application, and as shown in fig. 5, a specific implementation process is as follows:
in step S501, a power limit is determined.
In one embodiment, the control software of the charging stake controls the management module inside the charging stake to acquire data signals from other devices, including whether the home meter is installed, power information of the home meter, available power of the remaining power capacity of the power system, other device information of the power system access, and the like. The internal management module determines a power limit for limiting the charging operation of the charging pile based on data signals acquired from other devices. Wherein the method of determining the power limit comprises: presetting a power limit value based on rated power of a household ammeter; presetting a power limit value based on available power of the remaining power capacity of the power system; the power limit is dynamically determined based on a pre-set policy. And will not be described in detail herein.
Step S502, transmitting the working state information of the charging pile.
In one embodiment, the control software of the charging pile controls the management module inside the charging pile to obtain the charging pile working state information of the charging pile, wherein the charging pile working state information comprises the power consumption of the charging pile, whether the charging pile is in a charging working state or not, and the like. The communication module can send the charging pile working state information of the charging pile to the communication modules of other charging piles through communication connection. Meanwhile, the communication module of the charging pile also receives the charging pile working state information from other charging piles.
Step S503, selecting a main charging pile.
In one embodiment, the inter-pile ad hoc network may be performed, or the main charging pile may be selected from a plurality of charging piles performing the charging operation, or may be selected from all the charging piles, according to the charging pile operation state information of all the charging piles through communication connection. The main charging pile can be selected based on the number of the charging piles, the sequence of charging access, or random selection and other methods. And a plurality of standby main charging piles can be selected for completing the determination and the transmission of the charging strategy by taking the standby main charging piles as the main charging piles when the management module in the main charging piles fails and the determination and the transmission of the charging strategy cannot be performed, so that the charging operation is ensured.
Step S504, judging whether the affiliated charging pile is a main charging pile.
In one embodiment, after the primary charging post is determined, a signal is sent to the primary charging post, and the management module in the inner 5 portions of the charging post receives the signal to determine the charging strategy. If the charging pile receives the signal, judging the charging
If the pile is the main charging pile, the result is yes, and if the signal is not received, the result of judging whether the belonging charging pile is the main charging pile is no. By way of example, the management module inside the main charging pile can execute the work of determining the charging strategy by enabling the signal, and judge whether the charging pile is the main charging pile.
In step S505, the charging policy is determined and transmitted.
0 in one embodiment, this step is performed if the belonging charging stake belongs to the primary charging stake. According to the working state of the charging pile
And (5) information or a power limit value, and the main charging pile performs charging operation of the charging pile by determining a charging strategy. Under the requirement of meeting the power limit value, the management module inside the charging pile determines the charging strategy, and the optimal charging efficiency is realized.
In one embodiment, the charging strategies of embodiments of the present invention include, but are not limited to: according to the sequence of receiving the charging request
Sequentially, controlling the charging piles to perform charging operation; and controlling the corresponding charging piles to perform charging operation for 5 times in a preset time period; controlling each charging pile to charge based on the priority of each charging pile; based on each of the charges
The preset electric quantity of the piles controls each charging pile to alternately perform charging operation; a plurality of charging piles perform charging operation simultaneously; and alternately performing the charging operation based on the charging pile numbers of the plurality of charging piles performing the charging operation. The charging policy of the embodiment of the invention may be stored in advance in a management module disposed in the charging pile, and the method for determining the charging policy by the management module in the charging pile includes: selecting or combining from preset charging strategies.
Step S506, receiving and executing the charging policy.
In one embodiment, the master charging pile or the slave charging pile when the result of judging whether the slave charging pile is the master charging pile is no, wherein the slave charging pile refers to a plurality of charging piles which are not in charging operation and are in charging operation, the charging strategy is received through the communication module, and then the charging strategy is executed through the internal management module, or the charging strategy is received and executed directly through the communication module. The execution actions to execute the charging policy include start of charging, suspension of charging, end of charging, and the like.
Fig. 6 is a flowchart of a charging management method using process provided in an embodiment of the present application. As shown in fig. 6, when there is a standby
When the charging equipment is connected to the charging pile or the charging pile is used for completing charging operation, the method is executed, and the specific steps are as follows:
step S601, transmitting the charging pile operation state information of the charging pile.
In one embodiment, when the to-be-charged device with the charging requirement is connected to the charging pile, or the charging pile completes the charging operation
In operation, the management module inside the charging pile sends the charging pile working state information of the charging pile, and after receiving the charging pile working state information, the 0 management module inside the main charging pile updates the previous charging pile working state information based on the power limit
And determining the charging strategy by the value and the updated charging pile working state information of the plurality of charging piles. For example, when the equipment to be charged is connected to the charging piles, the number of charging piles being charged can be increased, the total power required by the charging piles can be increased, and the determination and the transmission of the charging strategy are required to be carried out again based on the existence of the power limit value; when the charging pile completes the charging operation, the charging pile is charged
The number of electric piles is reduced, residual power is generated based on the existence of the power limit value, and a charging strategy needs to be determined and executed again, 5, so that the utilization rate of available power of the residual power capacity of the power system is improved, and the efficiency of charging work is improved.
In one embodiment, when the device to be charged is connected to the charging pile, or when the charging pile completes the charging operation, it may be determined whether the primary charging pile needs to be selected again, so as to improve the charging efficiency. For example, when executing the charging strategy of alternately charging a plurality of charging piles, the charging piles can be changed into the charging piles with the latter charging piles as the main charging piles, so that the charging piles can be prevented from being required to be confirmed
Two kinds of work of charging strategies are fixed and executed, so that the work efficiency is reduced; when the charging strategy of charging according to the priority is executed, the charging pile with low priority can be changed into the charging pile with low priority as the main charging pile, so that the charging efficiency is improved.
In one embodiment, the charging pile operation state information of the charging pile may be sent through an inter-pile ad hoc network or a communication connection. The ad hoc network component of the communication module of the charging pile or all charging piles being charged is always in an on state, such as a bluetooth component and a wireless network component, and when the charging equipment to be charged is connected to the charging pile, the ad hoc network component of the communication module receives the charging pile working state information of the newly connected charging pile, updates the charging pile working state information to the charging pile working state information of the charging piles being charged, and further determines the charging strategy again. In order to save electric quantity, the self-networking component of the communication module of the main charging pile is always in an on state, and the management modules in the rest charging piles are only started when the self-networking component of the communication module of the main charging pile sends data signals. The ad hoc network components of the communication modules of all the charging piles can be always in a closed state, and when data are required to be sent and received, or when the communication module of the main charging pile receives the charging pile working state information of the newly-accessed charging pile, a starting signal is sent to the communication modules of the rest charging piles through the internal management module of the main charging pile, so that the ad hoc network components of the communication modules of the rest charging piles are started.
Step S602, the charging policy is redetermined and sent.
In one embodiment, the management module controlling the interior of the primary charging peg re-determines the charging policy and the communication module controlling the primary charging peg re-transmits the charging policy.
In one embodiment, to increase the charging efficiency, increase the utilization of the available power of the remaining power of the power system, and increase the user experience, a determination of the charging strategy needs to be made anew.
In one embodiment, when a device to be charged is connected to the charging post, the total power of the charging post being charged is further increased, and the possibility of exceeding the power limit exists. Firstly, the charging pile working state information of the newly accessed charging pile, such as priority and the like, is judged. And secondly, updating the charging pile working state information of the charging pile which is being charged based on the judging result. And finally, re-determining and adjusting the charging strategy based on the updated charging pile working state information of the charging pile which is being charged. The charging policy according to the priority may be combined with a charging policy according to charging in a preset period of time, so as to obtain a final charging policy. Exemplary, wherein the prioritized charging policy is used to perform a charging job on a charging pile with a high priority; and the charging strategy for charging according to the preset time period is used for executing the charging strategy by the charging pile with low priority within the limit of the residual power after the charging strategy with priority is executed.
In one embodiment, when the charging pile completes the charging operation, the remaining power is generated, so that the charging pile operating state information of the charging pile being charged needs to be updated in time, and the charging efficiency is improved. When the charging pile completes the charging operation, the total power of the charging pile which is in charging is lower than the power limit value, the charging pile working state information of the charging pile which is in charging is updated, and the charging strategy of charging according to the preset electric quantity is changed into the charging strategy of directly charging a plurality of charging piles at the same time.
In one embodiment, the charging piles being charged may be re-inter-pile ad hoc for transmitting the charging policy. When the equipment to be charged is connected to the charging pile, or when the charging pile finishes the charging operation, the inter-pile ad hoc network needs to be re-performed due to the change of the charging pile working state information which is in charge, including the number of charging piles in charge and the change of the power used by the charging piles, so as to send a new charging strategy.
In step S603, the charging strategy is received and executed again.
In one embodiment, when a device to be charged is connected to a charging pile, or when the charging pile completes a charging operation, the charging pile which is being charged receives and executes the charging policy again based on the updated charging policy.
In one embodiment, after receiving the charging policy again, the charging stake for executing the charging policy may execute the charging policy again after executing the charging operation to the preset charging stake or after executing the charging operation to the preset charging stake for a preset time or for a preset amount of electricity. After the charging pile that is charging is receiving the charging policy again, the re-received charging policy may be directly executed.
In the embodiment of the invention, when the charging pile which is in charging executes the re-received charging strategy, if the equipment to be charged is connected to the charging pile, or when the condition that the charging pile completes the charging operation occurs, the method is executed again.
Fig. 7 is a schematic structural diagram of a charging management device according to an embodiment of the present application. As shown in fig. 7, the control device 700 includes a transceiver unit 701 and a processing unit 702. Wherein, the cooperative working process among the units is as follows:
a transceiver unit 701, configured to implement communication connection of the charge management device; a processing unit 702 for determining a power limit for a plurality of charging piles; and determining a charging strategy at least according to the power limit value so as to manage charging operation of the plurality of charging piles.
In one embodiment, the processing unit 701 is specifically configured to preset the power limit value.
In one embodiment, the processing unit 701 is specifically configured to determine the power limit value based on the power of other loads accessed by the main power line.
In one embodiment, the transceiver unit 702 is specifically configured to perform inter-pile networking on the charging piles that are performing the charging operation when the number of charging piles that are performing the charging operation is greater than or equal to a preset threshold.
In one embodiment, the processing unit 701 is specifically configured to select a primary charging pile from the plurality of charging piles, where the primary charging pile is used to determine a charging policy.
In one embodiment, the processing unit 701 is specifically configured to obtain charging pile operation state information of the plurality of charging piles, where the charging pile operation state information includes electric power of the charging pile and whether the charging pile is in a charging operation state; and determining the charging strategy based on the power limit value and the charging pile working state information of the plurality of charging piles.
In one embodiment, the processing unit 701 is specifically configured to receive signal data from a terminal device; and the determination of the charging strategy is also related to signal data from the terminal device.
In one embodiment, the charging strategy comprises: according to the sequence of receiving the charging requests, controlling the charging pile to carry out charging operation; and controlling the corresponding charging piles to perform charging operation in a preset time period; controlling each charging pile to charge based on the priority of each charging pile; controlling each charging pile to alternately perform charging operation based on the preset electric quantity of each charging pile; a plurality of charging piles perform charging operation simultaneously; and alternately performing one or more of the charging operations based on the charging pile numbers of the plurality of charging piles that are performing the charging operation.
Fig. 8 is a schematic diagram of a computing device according to an embodiment of the present application. As shown in fig. 8, the charging stake 800 includes a transceiver 801, a processor 802, and a memory 803. The transceiver 801, the processor 802, and the memory 803 are communicatively connected via a bus, and data transmission is performed.
The transceiver 801 may implement input (reception) and output (transmission) of signals. For example, the transceiver 801 may include a transceiver or a radio frequency chip. The transceiver 801 may also include a communication interface. For example, the charging pile 800 may receive, through the transceiver 801, each control instruction and data packet sent by a unit such as a bluetooth module, a wireless network module, etc., and may be a unit such as a bluetooth module, a wireless network module, etc., to perform a corresponding function; the selected one of the control commands may also be sent via the transceiver 801 to an execution unit, such as a management module inside the charging stake, etc.
The processor 802 may be a general-purpose processor or a special-purpose processor. For example, the processor 802 may include a central processing unit (central processing unit, CPU) or a baseband processor. For example, the processor 802 may determine a control instruction according to the priority identifier or the function class information carried in each control instruction, and the specific implementation process may refer to the technical solutions described in fig. 1-6 and the previous section.
The memory 803 may have stored thereon a program (which may also be instructions or code) that can be executed by the processor 802 to cause the processor 802 to perform the methods described in this scenario. In one embodiment, the memory 803 may also have data stored therein. For example, the processor 802 may read data stored in the memory 803, which may be stored at the same memory address as the program, or which may be stored at a different memory address than the program. In this embodiment, the processor 802 and the memory 803 may be provided separately or may be integrated together, for example, on a single board or a System On Chip (SOC).
It should be understood that the architecture illustrated by embodiments of the present application are not intended to constitute a particular limitation on computing devices. In other embodiments of the present application, a computing device may include more or fewer components than shown, or may combine certain components, or split certain components, or a different arrangement of components. The illustrated components may be implemented in hardware, software, or a combination of software and hardware.
The embodiment of the application also provides a terminal device, which comprises a processor, and the processor can execute the technical scheme related to terminal device processing in the technical schemes of corresponding protection as shown in fig. 1-6, so that the terminal device has the technical effects of the technical scheme of protection.
There is also provided in an embodiment of the present application a computer-readable storage medium, on which a computer program is stored, which when executed in a computer causes the computer to perform any one of the methods described in the above fig. 1-6 and corresponding descriptions.
There is also provided in an embodiment of the present application a computer program product storing instructions that, when executed by a computer, cause the computer to implement any of the methods set forth in the above figures 1-6 and corresponding descriptions.
Those of ordinary skill in the art will appreciate that the various illustrative elements and algorithm steps described in connection with the embodiments disclosed herein may be implemented as electronic hardware, or combinations of computer software and electronic hardware. Whether such functionality is implemented as hardware or software depends upon the particular application and design constraints imposed on the solution. Skilled artisans may implement the described functionality in varying ways for each particular application, but such implementation decisions should not be interpreted as causing a departure from the scope of the embodiments of the present application.
Furthermore, various aspects or features of embodiments of the present application may be implemented as a method, apparatus, or article of manufacture using standard programming or engineering techniques. The term "article of manufacture" as used in the embodiments of the present application encompasses a computer program accessible from any computer-readable device, carrier, or media. For example, computer-readable media can include, but are not limited to, magnetic storage devices (e.g., hard disk, floppy disk, or magnetic strips, etc.), optical disks (e.g., compact disk, CD, digital versatile disk, digital versatile disc, DVD, etc.), smart cards, and flash memory devices (e.g., erasable programmable read-only memory, EPROM), cards, sticks, or key drives, etc. Additionally, various storage media described herein can represent one or more devices or other machine-readable media for storing information. The term "machine-readable medium" can include, but is not limited to, wireless channels and various other media capable of storing, containing, or carrying instruction(s) or data.
In the above-described embodiments, the control device 700 in fig. 7 and the charging stake 800 in fig. 8 may be implemented in whole or in part by software, hardware, firmware, or any combination thereof. When implemented in software, may be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When loaded and executed on a computer, produces, in whole or in part, a flow or function according to embodiments of the present application. The computer may be a general purpose computer, a special purpose computer, a computer network, or other programmable apparatus. The computer instructions may be stored in a computer-readable storage medium or transmitted from one computer-readable storage medium to another computer-readable storage medium, for example, the computer instructions may be transmitted from one website, computer, server, or data center to another website, computer, server, or data center by a wired (e.g., coaxial cable, fiber optic, digital subscriber line), or wireless (e.g., infrared, wireless, microwave, etc.). The computer readable storage medium may be any available medium that can be accessed by a computer or a data storage device such as a server, data center, etc. that contains an integration of one or more available media. The usable medium may be a magnetic medium (e.g., a floppy disk, a hard disk, a magnetic tape), an optical medium (e.g., a high-density digital video disc (digital video disc, DVD)), or a semiconductor medium (e.g., a Solid State Disk (SSD)), or the like.
It should be understood that, in various embodiments of the present application, the sequence numbers of the foregoing processes do not mean the order of execution, and the order of execution of the processes should be determined by the functions and internal logic of the processes, and should not constitute any limitation on the implementation process of the embodiments of the present application.

Claims (12)

1. A charging system, comprising:
a power main line;
the charging piles are connected in parallel to the power main line for power taking;
the management module is used for determining the power limit value of the plurality of charging piles and the total power required by the charging piles for charging operation; and responsive to the total power demand being greater than the power limit, determining a charging strategy to manage charging operations of the plurality of charging piles based at least on the power limit; the charging strategy comprises the steps of determining the charging sequence of the charging pile for charging operation, determining the charging time length, determining the charging electric quantity or determining the charging power.
2. The system according to claim 1, wherein the management module is specifically configured to:
determining a power limit value of the plurality of charging piles based on preset power;
Or determining the power limit value of the plurality of charging piles based on the power of other loads, except for the charging piles, which are connected to the power main line.
3. The system of claim 1 or 2, wherein a communication module is disposed in each of the plurality of charging piles;
the management module is further configured to:
and responding to the fact that the number of the charging piles for charging operation is larger than or equal to a preset threshold value, sending activating and networking instructions to a communication module in the charging piles for charging operation, and networking among the charging piles for charging operation, wherein the inter-pile networking refers to communication network connection among the charging piles for charging operation.
4. The system of claim 3, wherein the management module is specifically configured to:
acquiring working state information of each charging pile of inter-pile networking, wherein the working state information of the charging pile comprises power consumption of the charging pile; and
and determining the charging strategy based on the power limit value and the working state information of each charging pile for inter-pile networking.
5. The system of any one of claims 1-4, wherein the management module is disposed in each of the plurality of charging piles;
the management module is further configured to:
and selecting a main charging pile from the charging piles for charging operation, wherein the management module in the main charging pile is used for determining the charging strategy.
6. A charging management method, characterized by comprising:
determining power limit values of a plurality of charging piles and total power required by the charging piles for charging operation;
when the total power required is greater than the power limit value, determining a charging strategy at least according to the power limit value so as to manage charging operation of the plurality of charging piles; the charging strategy comprises the steps of determining the charging sequence of the charging pile for charging operation, determining the charging time length, determining the charging electric quantity or determining the charging power.
7. The method of claim 6, wherein the determining a power limit for the plurality of charging piles comprises:
determining a power limit value of the plurality of charging piles based on preset power;
or determining the power limit value of the plurality of charging piles based on the power of other loads, except for the charging piles, which are connected to the power main line.
8. The method according to claim 6 or 7, further comprising, before determining a charging strategy at least from the power limit value:
when the number of the charging piles for charging operation is greater than or equal to a preset threshold value, sending activating and networking instructions to a communication module in the charging piles for charging operation, and networking the charging piles for charging operation among piles, wherein the inter-pile networking refers to communication network connection among the charging piles for charging operation.
9. The method as recited in claim 8, further comprising:
acquiring working state information of each charging pile for inter-pile networking, wherein the working state information of the charging pile comprises power consumption of the charging pile; and
and determining the charging strategy based on the power limit value and the working state information of each charging pile for inter-pile networking.
10. The method according to any of claims 6-9, further comprising, prior to determining a charging strategy based at least on the power limit value:
and selecting a main charging pile from the plurality of charging piles, wherein the main charging pile is used for determining a charging strategy.
11. A computing device, comprising:
at least one of the transceivers of the at least one transceiver,
at least one of the memories is provided with a memory,
at least one processor for executing instructions stored in a memory to cause a charging pile to perform the method of any one of claims 6-10.
12. A computer readable storage medium having stored thereon a computer program which, when executed in a computer, causes the computer to perform the method of any of claims 6-10.
CN202211582444.1A 2022-12-09 2022-12-09 Charging system, charging management method and device Pending CN116039428A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211582444.1A CN116039428A (en) 2022-12-09 2022-12-09 Charging system, charging management method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211582444.1A CN116039428A (en) 2022-12-09 2022-12-09 Charging system, charging management method and device

Publications (1)

Publication Number Publication Date
CN116039428A true CN116039428A (en) 2023-05-02

Family

ID=86112335

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211582444.1A Pending CN116039428A (en) 2022-12-09 2022-12-09 Charging system, charging management method and device

Country Status (1)

Country Link
CN (1) CN116039428A (en)

Similar Documents

Publication Publication Date Title
US11413984B2 (en) Apparatus and method for charging and discharging electric vehicle under smart grid environment
US8686687B2 (en) Method and system for co-operative charging of electric vehicles
US8106627B1 (en) Method and system for co-operative charging of electric vehicles
CN109414999B (en) Method for controlling the charging of a group of vehicles with reduced power
US20160250942A1 (en) Charging state management method, charging state management device, and program
US20130307466A1 (en) System and Method for Charging Car Batteries
CN108879831B (en) Power distribution system, capacity sharing system, master station, slave station, method and equipment
CN104160546A (en) Method, system and charger for charging a battery of an electric vehicle
CN104170327A (en) In-vehicle communication system
KR101353904B1 (en) Electric vehicle charging system and method interworking with power management system
US20110233997A1 (en) Power supply apparatus, power reception apparatus, and power supply method
US20230173938A1 (en) Power control method and system for battery charging and swap station, medium, apparatus, and battery charging and swap station
US11056911B2 (en) Management system, management method, equipment, and management device
JP2023508135A (en) Electric vehicle charger power supply method
KR101946059B1 (en) Charge control system and method associated with energy storage system
CN108189693A (en) The control method and system that a kind of electric vehicle remotely charges
CN113135111A (en) Charging control method, charging pile and computer-readable storage medium
US20230147695A1 (en) Electric Vehicle Charging System
CN111699720A (en) Device, system and communication method
CN116039428A (en) Charging system, charging management method and device
CN114633652B (en) Charging system, method and device for dynamic power distribution, main charging pile and medium
CN107585048B (en) Multi-charging-pile combined flexible charging system
CN112702448A (en) Slave control unit address distribution method and system of battery management system
JP6328216B2 (en) Management system, management method, device and management apparatus
CN111384732A (en) Method for charging a battery of a vehicle, battery charging device and vehicle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination