CN115940403A - Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium - Google Patents

Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium Download PDF

Info

Publication number
CN115940403A
CN115940403A CN202211397190.6A CN202211397190A CN115940403A CN 115940403 A CN115940403 A CN 115940403A CN 202211397190 A CN202211397190 A CN 202211397190A CN 115940403 A CN115940403 A CN 115940403A
Authority
CN
China
Prior art keywords
power failure
failure operation
operation ticket
ticket
switch cabinet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211397190.6A
Other languages
Chinese (zh)
Inventor
谭硕
陈晓航
曹德发
廖明
东岳
吴海
林松春
王文超
李伟忠
张雅方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN202211397190.6A priority Critical patent/CN115940403A/en
Publication of CN115940403A publication Critical patent/CN115940403A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a method, a device and equipment for generating a power failure operation ticket of a switch cabinet and a readable storage medium. The method for generating the power failure operation ticket of the switch cabinet specifically comprises the following steps: performing power failure operation simulation on the switch cabinet in a power failure module of the power grid management platform; crawling power failure operation in the power failure operation simulation process in the power failure module; judging whether the crawling power failure operation meets the standard or not; when the content of the power failure operation ticket meets the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; and generating a power failure operation ticket of the switch cabinet. According to the embodiment of the invention, through power failure operation simulation and judgment on whether the power failure operation in the crawling power failure operation simulation process meets the standard or not, the problems that the station name or the line name and the switch name are wrongly numbered and the logical relationship does not correspond are solved, the error rate of the operation task of the operation ticket can be reduced, the occurrence of an accident is avoided, and the accuracy and the efficiency of the power failure operation ticket are improved.

Description

Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium
Technical Field
The embodiment of the invention relates to the technical field related to power failure operation tickets, in particular to a method, a device and equipment for generating a power failure operation ticket of a switch cabinet and a readable storage medium.
Background
With the continuous development of power grids, switch cabinets in cities are increasingly put into operation, along with planned power failure transformation, the power failure operation of emergency accident treatment is more frequent, in the operation processes, more electric operation tickets corresponding to manual operation are needed to operate the switch cabinets, and the following problems can occur in the writing process of the operation tickets:
firstly, the operation task of the operation ticket is wrongly written; the station name or the line name and the switch name are wrongly written; thirdly, the logical relationship of the operation tickets does not correspond. These errors may cause errors in operation, resulting in accidents.
Disclosure of Invention
The invention provides a method, a device and equipment for generating a power failure operation ticket of a switch cabinet and a readable storage medium, so as to realize the safe and reliable processing of power failure operation and improve the efficiency of compiling an electrical operation ticket.
In a first aspect, an embodiment of the present invention provides a method for generating a power failure operation ticket of a switch cabinet, which specifically includes:
performing power failure operation simulation on the switch cabinet in a power failure module of the power grid management platform;
crawling power failure operation in the power failure operation simulation process in the power failure module;
judging whether the crawling power failure operation meets the standard or not;
when the content of the power failure operation ticket meets the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform;
and generating a power failure operation ticket of the switch cabinet.
Further, before carrying out the power failure operation simulation to the cubical switchboard in the power failure module of power grid management platform, specifically still include:
and recording the basic data of the power failure plan of the switch cabinet, wherein the basic data of the power failure plan of the switch cabinet comprises at least one of power failure time, a power failure circuit, a power failure range, power failure safety measures and work transfer measures.
Optionally, judge whether the power failure operation of crawling accords with the specification, specifically include:
and judging whether the crawled power failure operation content is complete, the sequence is correct and the description is standard.
Further, whether the crawling power failure operation content is complete, whether the order is correct and whether the description is standard are judged, and the method specifically comprises the following steps:
and judging whether the crawled power failure operation contents are complete, the sequence is correct and whether the description is standard or not according to the standard safety measures in the preset safety measure comparison table, the standard expression language in the preset standard expression comparison table and the standard line equipment in the preset line equipment database.
Optionally, the operation ticket generating method specifically further includes:
and when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the crawled power failure operation.
Further, when the power failure operation ticket content does not accord with the standard, the power failure operation of crawling is corrected and perfected, and the method specifically comprises the following steps:
acquiring a historical power failure operation ticket and/or a typical power failure operation ticket;
and according to the operation content, the operation sequence and the operation description of the historical power failure operation ticket and/or the typical power failure operation ticket, the crawling power failure operation is perfected.
Optionally, when the content of the power failure operation ticket meets the specification, after the content of the power failure operation ticket is automatically entered into the power failure operation ticket in an operation ticket module of the power grid management platform, the method specifically further includes:
generating a manual auditing process and an interface;
acquiring a manual auditing result, wherein the manual auditing result comprises a passing instruction and a non-passing instruction;
generate cubical switchboard power failure operation ticket specifically includes:
and generating a power failure operation ticket of the switch cabinet after the obtained manual auditing result is a pass instruction.
Further, after obtaining the manual review result, the method specifically includes:
and when the obtained manual auditing result is that the instruction does not pass, generating a power failure operation ticket error early warning popup window.
Further, when the obtained manual audit result is that the instruction is not passed, the power failure operation ticket error early warning popup is generated, and the method specifically comprises the following steps:
generating a power failure operation ticket modification suggestion popup window;
generate cubical switchboard power failure operation ticket, still include:
acquiring a modification suggestion in a power failure operation ticket modification suggestion popup window;
and according to the modification suggestion, modifying the power failure operation ticket and generating a power failure operation ticket of the switch cabinet.
In a second aspect, an embodiment of the present invention further provides a device for generating a power failure operation ticket of a switch cabinet, where the device includes:
the simulation module is used for simulating power failure operation of the switch cabinet in the power failure module of the power grid management platform;
the crawling module is used for crawling the power failure operation in the power failure operation simulation process in the power failure module;
the verification module is used for judging whether the crawled power failure operation meets the standard or not;
the recording module is used for automatically recording the content of the power failure operation ticket into the power failure operation ticket in the operation ticket module of the power grid management platform when the content of the power failure operation ticket meets the standard;
and the generation module is used for generating a power failure operation ticket of the switch cabinet.
In a third aspect, an embodiment of the present invention further provides an apparatus, where the apparatus includes:
one or more processors;
a storage device for storing one or more programs,
when the one or more programs are executed by the one or more processors, the one or more processors implement the method for generating the power failure operation ticket of the switch cabinet.
In a fourth aspect, an embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored, where the computer program, when executed by a processor, implements any one of the above methods for generating a power failure operation ticket for a switch cabinet.
According to the technical scheme of the embodiment, the power failure operation simulation is performed on the switch cabinet in the power failure module of the power grid management platform; crawling power failure operation in the power failure operation simulation process in a power failure module; then judging whether the power failure operation of crawling meets the standard or not; when the content of the power failure operation ticket meets the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; and finally, generating a power-off operation ticket of the switch cabinet, solving the problems that the station name or the line name and the switch name number are wrongly written and the logic relation is not corresponding, reducing the error rate of the operation task of the operation ticket, avoiding accidents and improving the accuracy and efficiency of the power-off operation ticket.
Drawings
Fig. 1 is a flowchart of a method for generating a power failure operation ticket of a switch cabinet according to an embodiment of the present invention;
fig. 2 is a flowchart of a procedure of a method for generating a power failure operation ticket of a switch cabinet according to an embodiment of the present invention;
fig. 3 is a flowchart of a method for generating a power failure operation ticket of a switch cabinet according to a second embodiment of the present invention;
fig. 4 is a flowchart of a procedure of a method for generating a power failure operation ticket of a switch cabinet according to a second embodiment of the present invention;
fig. 5 is a flowchart of a method for generating a power failure operation ticket of a switch cabinet according to a third embodiment of the present invention;
fig. 6 is a flowchart of a procedure of a method for generating a power failure operation ticket of a switch cabinet according to a third embodiment of the present invention;
fig. 7 is a schematic diagram of a switch cabinet power failure operation ticket generating device according to a fourth embodiment of the present invention;
fig. 8 is a schematic structural diagram of a switchgear power outage operation ticket generating apparatus according to a fifth embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not to be construed as limiting the invention. It should be further noted that, for the convenience of description, only some structures related to the present invention are shown in the drawings, not all of them.
Example one
Fig. 1 is a flowchart of a method for generating a power failure operation ticket for a switch cabinet according to an embodiment of the present invention, where the embodiment is applicable to a situation of generating a power failure operation ticket for a switch cabinet, and the method can be executed by a device for generating a power failure operation ticket for a switch cabinet, where the device can be implemented by hardware or software, and specifically includes the following steps:
s110, performing power failure operation simulation on the switch cabinet in a power failure module of the power grid management platform;
the power failure operation simulation of the switch cabinet in the power failure module refers to power failure operation simulation of the whole process of power failure of the switch cabinet.
S120, crawling power failure operation in the power failure operation simulation process in the power failure module;
the crawling power failure operation refers to automatically capturing content information of the power failure operation generated in a power failure module of the power grid management platform through a network crawler, and the content information includes but is not limited to operation content, operation sequence, operation description and the like, the process is a network crawler process in essence, and the crawling power failure operation is realized through a network crawler program.
S130, judging whether the crawling power failure operation meets the standard or not;
in the crawling process, a bug may exist or data cannot be generated according to the logic of the operation ticket, so that power failure operation obtained by crawling needs to be judged. Whether the crawled power failure operation meets the standard or not is judged according to the operation content, the operation sequence and the operation description in the existing power failure operation ticket.
S140, when the content of the power failure operation ticket meets the specification, automatically inputting the content of the power failure operation ticket into the power failure operation ticket in an operation ticket module of the power grid management platform;
the content of the power failure operation ticket is simulation content which is judged to be in accordance with the standard after power failure operation simulation, and can comprise the crawled power failure operation and/or the power failure operation ticket content generated by inputting basic data. This process has realized being connected of power failure simulation and power failure operation ticket among the power grid management platform in essence, can utilize the power failure operation preparation power failure operation ticket that the power failure module generated in the simulation process, has realized that the machine replaces the problem of artifical automatic filling, can guarantee certain accurate standard simultaneously, solves the problem that artifical filling is easy to be wrong.
And S150, generating a power failure operation ticket of the switch cabinet.
The process is realized in a power failure operation ticket module of the power grid platform, and the power failure operation ticket module automatically generates the power failure operation ticket. The generation of the power failure operation ticket of the switch cabinet operated by the process greatly reduces the working pressure of workers, shortens the working period, and improves the accuracy and the generation efficiency of compiling the power failure operation ticket of the switch cabinet by crawling the power failure operation and judgment in the power failure operation simulation process in the power failure module.
Fig. 2 is a flowchart of a procedure of a method for generating a power failure operation ticket of a switch cabinet according to an embodiment of the present invention, and an actual generation process of the power failure operation ticket is described below with reference to fig. 2: the method comprises the following steps of writing a power failure operation ticket of a switch cabinet: firstly, performing power failure operation simulation on a switch cabinet in a power failure module of a power grid management platform according to input data; secondly, crawling the power failure operation in the power failure operation simulation process in a power failure module; judging whether the crawled power failure operation meets the standard or not according to the operation content, the operation sequence and the operation description in the existing power failure operation ticket; when the content of the power failure operation ticket is judged to be in accordance with the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform, namely a plan number is generated; and finishing the compiling of the power failure plan, and finally outputting a power failure operation ticket of the switch cabinet.
According to the technical scheme of the embodiment, the power failure operation simulation is performed on the switch cabinet in the power failure module of the power grid management platform; then, crawling power failure operation in the power failure operation simulation process in a power failure module; judging whether the crawling power failure operation meets the standard or not; when the content of the power failure operation ticket meets the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; and generating a power failure operation ticket of the switch cabinet. The embodiment of the invention solves the problems that the serial numbers of the station names or the line names and the switch names are wrongly written and the logic relation does not correspond, reduces the error rate of the operation tasks of the operation tickets, avoids accidents and improves the accuracy and the efficiency of the power-off operation tickets.
Optimization is performed on the basis of the technical scheme, and further, before performing power failure operation simulation on the switch cabinet in the power failure module of the power grid management platform in step S110, steps can be added to specifically include:
recording power failure plan basic data of the switch cabinet, wherein the power failure plan basic data of the switch cabinet comprises at least one of power failure time, power failure lines, power failure range, power failure safety measures and work transfer measures;
the switching measures include, but are not limited to, the change of the working state of the starting, standby and closing of the relevant machines and the connection and disconnection of the relevant lines. Recording the basic data of the power failure plan of the switch cabinet is a necessary process for power failure simulation, and corresponding operation requirements such as power failure time, lines and range need to be provided; of course, the corresponding operation content is also formulated, such as a work transfer measure; and the method can also comprise some basic safety regulations in the power failure process, namely power failure safety measures. Therefore, the power failure module in the power grid management platform can normally perform the power failure module, and corresponding power failure operation contents are generated.
Further, the step S130 of determining whether the crawled power failure operation meets the specification may be further refined, and the specific optimization includes: and judging whether the crawled power failure operation content is complete, the sequence is correct and the description is standard.
The operation logic in the general operation ticket can determine the normalization and the accuracy of the whole operation ticket from the content, the sequence and the expression, and the process is essentially the process of judging the normalization and the accuracy of the crawled power failure operation from the three aspects.
Further, judging whether the crawled power failure operation content is complete may specifically include:
and judging whether the crawled power failure operation contents are complete, the sequence is correct and whether the description is standard or not according to the standard safety measures in the preset safety measure comparison table, the standard expression language in the preset standard expression comparison table and the standard line equipment in the preset line equipment database.
The safety measure comparison table, the standard expression comparison table and the line equipment database are preset three databases, correct and standard safety measure data, measure expression data and corresponding equipment line names are stored in the three databases, and the three databases can be combined through languages to generate all possible standard operations in the power failure operation ticket. In the step, whether the crawled power failure operation content is complete or not is judged, the power failure operation in the crawled power failure operation simulation process needs to be compared with standard safety measures in a preset safety measure comparison table, standard expression languages in a preset standard expression comparison table and standard line equipment in a preset line equipment database one by one, and after positive results are obtained, the crawled power failure operation content is considered to be complete, the sequence is correct and the description is standard.
Example two
Fig. 3 is a flowchart of a method for generating a power failure operation ticket of a switch cabinet according to a second embodiment of the present invention, and referring to fig. 3, the second embodiment further optimizes a scheme of the first embodiment, where optionally, on the basis of the first embodiment, steps may be further added: and when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the crawled power failure operation.
Further, on the basis of the first embodiment, after the step S140, the following two steps may be further included:
generating a manual auditing process and an interface;
and acquiring a manual checking result, wherein the manual checking result comprises a pass instruction and a fail instruction.
On this basis, step S150, generating a power failure operation ticket of the switch cabinet may specifically include:
and generating a power failure operation ticket of the switch cabinet after the obtained manual auditing result is a pass instruction.
Please refer to the first embodiment for a detailed description of the present embodiment.
As shown in fig. 3, a flowchart of a method for generating a power failure operation ticket of a switch cabinet according to a second embodiment of the present invention includes the following steps:
s210, performing power failure operation simulation on the switch cabinet in a power failure module of the power grid management platform;
s220, crawling power failure operation in the power failure operation simulation process in the power failure module;
s230, judging whether the crawling power failure operation meets the standard or not;
and S231, when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the crawled power failure operation.
When at least one of the crawled power failure operations is judged to be not in accordance with the specifications according to the operation contents, the operation sequence and the operation description in the existing power failure operation ticket, the crawled power failure operations need to be correspondingly corrected and perfected, manual automatic generation is replaced, the accuracy of the power failure operation ticket is improved, and the fact that all operations in the automatically generated operation ticket are in accordance with the specifications is guaranteed.
S240, when the content of the power failure operation ticket meets the specification, automatically inputting the content of the power failure operation ticket into the power failure operation ticket in an operation ticket module of the power grid management platform;
s241, generating a manual review flow and an interface;
the manual auditing process and the manual auditing interface can be used for verifying power failure operation simulation and actual power failure operation conditions of the switch cabinet by an operator self-auditing process, a guardian preliminary auditing process and a duty responsible person reexamining process, so that the power failure operation ticket is ensured to be correct and reliable, and the examiner can be a plurality of persons or comprises one person and has a plurality of roles. The process is also used for improving the correctness and the standard of the power failure operation ticket, the manual auditing process is provided on the basis of automatic auditing and correcting of the machine, and the standardization and the accuracy of the power failure operation ticket can be greatly improved by using double auditing of the machine and manual and multistage manual auditing.
S242, acquiring a manual auditing result, wherein the manual auditing result comprises a pass instruction and a fail instruction;
the manual auditing result is a verification result of the power failure operation simulation and the actual power failure operation condition of the switch cabinet fed back by the auditing personnel, and comprises a pass instruction and a fail instruction.
And S250, generating a power failure operation ticket of the switch cabinet after the obtained manual auditing result is a pass instruction.
And the obtained manual auditing results are all pass instructions, and a power failure operation ticket of the switch cabinet is generated.
By the method for operating the power failure operation ticket of the switch cabinet through the process, the process of correcting and perfecting the crawled power failure operation and manually auditing the crawled power failure operation when the content of the power failure operation ticket is not in accordance with the standard is additionally arranged, so that the accuracy of compiling the power failure operation ticket of the switch cabinet can be improved, the generation efficiency of the operation ticket is improved, and the power failure operation ticket of the switch cabinet can be accurately compiled.
Fig. 4 is a flowchart of a procedure of a method for generating an operation ticket of a switch cabinet during power failure according to a second embodiment of the present invention, and an actual procedure of generating the operation ticket according to the second embodiment is described below with reference to fig. 4: similarly, the power failure operation ticket of the switch cabinet is written: firstly, power failure operation simulation is carried out on a switch cabinet in a power failure module of a power grid management platform according to existing data; crawling power failure operation in the power failure operation simulation process in a power failure module; judging whether the crawled power failure operation meets the standard or not according to the operation content, the operation sequence and the operation description in the existing power failure operation ticket; if the judgment result shows that the operation order does not meet the standard, self-correction and improvement are carried out according to the existing corresponding rule until the compiled power failure operation order of the switch cabinet meets the standard; after the power failure operation ticket of the switch cabinet is judged to be in accordance with the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; then, generating a manual review flow and an interface, and performing manual review; when the obtained manual auditing result is a pass instruction, generating a power failure operation ticket of the switch cabinet, namely generating a plan number; and (5) finishing compiling the power failure plan, and outputting a power failure operation ticket of the switch cabinet.
According to the technical scheme of the embodiment, the power failure operation simulation is performed on the switch cabinet in the power failure module of the power grid management platform; crawling power failure operation in the power failure operation simulation process in the power failure module; then judging whether the crawling power failure operation meets the standard or not; when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the crawled power failure operation; when the content of the power failure operation ticket meets the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; then generating a manual review process and an interface; acquiring a manual auditing result as a pass instruction; and finally generating a power failure operation ticket of the switch cabinet. The second embodiment also solves the problems that the station names or the line names and the switch name numbers are wrongly written and the logic relations do not correspond, reduces the error rate of the operation tasks of the operation tickets, avoids accidents, and additionally provides the procedures of correcting, perfecting and manually auditing the crawled power failure operation when the contents of the power failure operation tickets are not in accordance with the standard, so that the accuracy of writing the power failure operation tickets of the switch cabinet can be improved, the generation efficiency of the operation tickets is improved, and the power failure operation tickets of the switch cabinet can be accurately written.
Optimizing on the basis of the technical scheme, further, when the contents of the power failure operation ticket in the step S131 do not meet the specifications, modifying and perfecting the crawled power failure operation, and specifically comprising:
when power failure operation ticket content does not accord with the standard, revise and perfect the power failure operation of crawling, include:
acquiring a historical power failure operation ticket and/or a typical power failure operation ticket;
and according to the operation content, the operation sequence and the operation description of the historical power failure operation ticket and/or the typical power failure operation ticket, the crawling power failure operation is perfected.
In the automatic generation process of the operation ticket provided by the embodiment, when the operation ticket is not standard, the historical power failure operation ticket and the typical power failure operation ticket are used as standards, so that corresponding operation is corrected and perfected, and the normalization of the whole automatic generation operation ticket is realized.
EXAMPLE III
Fig. 5 is a flowchart of a method for generating a power outage operation ticket for a switchgear according to a third embodiment of the present invention, and referring to fig. 5, the third embodiment is a further optimization of the second embodiment, wherein optionally, on the basis of the second embodiment, before performing power outage operation simulation on the switchgear in a power outage module of a power grid management platform in step S110, steps are added: recording power failure plan basic data of the switch cabinet, wherein the power failure plan basic data of the switch cabinet comprises at least one of power failure time, power failure lines, power failure range, power failure safety measures and work transfer measures;
optionally, on the basis of the second embodiment, in step S131, after the power outage operation performed by the crawling is corrected and completed when the content of the power outage operation ticket does not meet the specification, the following steps may be added: according to the operation content, the operation sequence and the operation description of the historical power failure operation ticket and/or the typical power failure operation ticket, the crawling power failure operation is perfected;
further, on the basis of the second embodiment, in step S142, a manual review result may be obtained, where the manual review result includes a pass instruction and a no-pass instruction, and then steps are sequentially added:
when the obtained manual auditing result is that the command does not pass, generating a power failure operation ticket error early warning popup window;
generating a power failure operation ticket modification suggestion popup;
acquiring a modification suggestion in a power failure operation ticket modification suggestion popup window;
on this basis, step S150, generating a power failure operation ticket of the switch cabinet may specifically include:
and according to the modification suggestion, modifying the power failure operation ticket and generating a power failure operation ticket of the switch cabinet.
For a detailed description of the present embodiment, please refer to the first embodiment and the second embodiment.
As shown in fig. 5, a flowchart of a method for generating a power failure operation ticket of a switch cabinet according to a third embodiment of the present invention includes the following steps:
s300, inputting power failure plan basic data of the switch cabinet, wherein the power failure plan basic data of the switch cabinet comprises at least one of power failure time, power failure lines, power failure ranges, power failure safety measures and work transfer measures;
s310, performing power failure operation simulation on the switch cabinet in a power failure module of the power grid management platform;
s320, crawling power failure operation in the power failure operation simulation process in the power failure module;
s330, judging whether the crawled power failure operation meets the specification;
and S331, when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the power failure operation of crawling.
According to the method, at least one of the crawled power failure operations is judged to be not in accordance with the specifications according to the operation content, the operation sequence and the operation description in the existing power failure operation ticket, the crawled power failure operations are correspondingly corrected and perfected, the accuracy of the power failure operation ticket can be improved, the working time is shortened, and the efficiency is improved.
S3311, according to the operation content, operation sequence and operation description of the historical power failure operation ticket and/or the typical power failure operation ticket, the crawl power failure operation is perfected.
The inherent format and corresponding logic of the operation are solidified according to the safety standard, the two-ticket management rule and the typical ticket, the corresponding rule is summarized and concluded, and the service support is provided for automatically generating the switch cabinet operation ticket of the type for subsequent judgment.
S340, when the content of the power failure operation ticket meets the specification, automatically inputting the content of the power failure operation ticket into the power failure operation ticket in an operation ticket module of the power grid management platform;
s341, generating a manual review flow and an interface;
s342, acquiring a manual auditing result, wherein the manual auditing result comprises a pass instruction and a fail instruction;
and S3421, generating a power failure operation ticket error early warning popup window when the obtained manual auditing result is that the command does not pass.
The error early warning popup window can play the early warning and prompting roles for examiners so as to think and perform related operations on early-warned errors.
S3422, generating a power failure operation ticket modification suggestion popup;
the modification suggestion popup window can provide related reference modification suggestions for examiners for early-warning errors according to the operation content, operation sequence and operation description of the existing power failure operation ticket so as to standardize modification.
S3423, acquiring a modification suggestion in the power failure operation ticket modification suggestion popup window;
wherein the modification suggestion can include a related reference modification suggestion and a modification prompt to specify the modification.
S3424, according to the modification suggestion, modifying the power failure operation ticket and generating a switch cabinet power failure operation ticket.
The modification of the power failure operation ticket comprises manual modification and manual acceptance of modification suggestions.
And S350, generating a power failure operation ticket of the switch cabinet after the obtained manual auditing result is a pass instruction.
It can be understood that the method for operating the power failure operation ticket of the switch cabinet through the process solves the problems that the station name or the line name and the switch name number are wrongly written and the logic relationship does not correspond, reduces the error rate of the operation task of the operation ticket, avoids accidents, corrects and perfects the crawled power failure operation when the content of the power failure operation ticket does not meet the specification, generates the power failure operation ticket error early warning popup window and the modification suggestion popup window and provides suggestions for manual modification through the manual auditing process when the obtained manual auditing result is that the instruction does not pass, greatly improves the accuracy of writing the power failure operation ticket of the switch cabinet, improves the generation efficiency of the operation ticket, and further can accurately write the power failure operation ticket of the switch cabinet.
Fig. 6 is a program flow chart of a method for generating a power-off operation ticket of a switch cabinet according to a third embodiment of the present invention, and the following describes an actual generation process of the power-off operation ticket according to the third embodiment with reference to fig. 6: the method comprises the following steps of writing a power failure operation ticket of a switch cabinet: firstly, manually inputting at least one of power failure time, power failure line, power failure range, power failure safety measure and power transfer measure into the power failure plan basic data of the switch cabinet; then, power failure operation simulation is carried out on the switch cabinet in a power failure module of the power grid management platform according to the existing data; crawling the power failure operation in the power failure operation simulation process in the power failure module again, crawling the power grid management platform asset domain distribution network comprehensive power failure on the system to the switch cabinet power failure module details, and simultaneously crawling the primary safety measure key field in the power failure simulation: the method comprises the following steps of storing fields such as a transformer substation name, a line name, a switch cabinet name, a switch number and a grounding switch number in a local database, providing data preparation for automatically generating an operation ticket on the next step, and identifying and analyzing key fields of primary safety measures in power failure simulation: the method comprises the following steps that key fields such as a transformer substation name, a line name, a switch cabinet name, a switch number and a grounding switch number and the like and the influence of a power failure simulation scene on automatic generation of an operation ticket request are determined, typical scenes (such as operation-to-hot standby, hot standby-to-overhaul, operation-to-overhaul, overhaul-to-hot standby, overhaul-to-operation and the like) needing to be automatically generated by the operation ticket are determined, corresponding rules are summarized, and service support is provided for automatically generating the type of the operation ticket of the switch cabinet by subsequent judgment; then, judging whether the crawled power failure operation meets the standard or not according to the operation content, the operation sequence and the operation description in the existing power failure operation ticket; when any one of the operation content, the operation sequence and the operation description in the power failure operation ticket is not in accordance with the standard, self-correction and improvement are carried out according to the existing corresponding rule until the compiled switch cabinet power failure operation ticket is in accordance with the standard; when the power failure operation ticket of the switch cabinet is judged to be in accordance with the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; then, generating a manual auditing flow and an interface, and performing manual auditing; when the obtained manual auditing result is a non-passing instruction, generating a power failure operation ticket error early warning popup window, simultaneously generating a power failure operation ticket modification suggestion popup window, obtaining a modification suggestion in the power failure operation ticket modification suggestion popup window, modifying the power failure operation ticket according to the modification suggestion, and generating a switch cabinet power failure operation ticket; when the obtained manual auditing result is a pass instruction, generating a power failure operation ticket of the switch cabinet, namely generating a plan number; and (5) finishing compiling the power failure plan, and outputting a power failure operation ticket of the switch cabinet.
According to the technical scheme, power failure operation simulation is performed on the switch cabinet in a power failure module of the power grid management platform; crawling power failure operation in the power failure operation simulation process in the power failure module; then judging whether the crawled power failure operation meets the standard or not; when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the crawled power failure operation; when the content of the power failure operation ticket meets the standard, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform; then generating a manual auditing process and an interface; when the obtained manual auditing result is that the instruction does not pass, generating a power failure operation ticket error early warning popup window, and simultaneously generating a power failure operation ticket modification suggestion popup window to obtain a modification suggestion in the power failure operation ticket modification suggestion popup window; according to the modification suggestion, modifying the power failure operation ticket and generating a power failure operation ticket of the switch cabinet; finally, acquiring a manual auditing result as a passing instruction; and generating a power failure operation ticket of the switch cabinet. The third embodiment also solves the problems that the serial numbers of the station names or the line names and the switch names are wrongly written and the logic relations do not correspond, reduces the error rate of the operation tasks of the operation tickets, avoids accidents, generates the power failure operation ticket error early warning popup windows and the modification suggestion popup windows and provides suggestions for manual modification when the obtained manual auditing result is that the instruction is not passed through the manual auditing process, greatly improves the accuracy of writing the power failure operation tickets of the switch cabinet, improves the generation efficiency of the operation tickets, and further can accurately write the power failure operation tickets of the switch cabinet.
Example four
An embodiment of the present invention further provides a device for generating a power failure operation ticket of a switch cabinet, fig. 7 is a schematic diagram of a device for generating a power failure operation ticket of a switch cabinet according to a fourth embodiment of the present invention, and referring to fig. 7, the device includes:
the simulation module 110 is used for simulating power failure operation of the switch cabinet in a power failure module of the power grid management platform;
the crawling module 120 is used for crawling the power failure operation in the power failure operation simulation process in the power failure module;
wherein, the operation of crawling the module includes crawling the key field of a safety measure in the power failure simulation: and fields such as the name of the transformer substation, the name of a line, the name of a switch cabinet, a switch number, a grounding switch number and the like are stored in a local database, and data preparation is provided for automatically generating an operation ticket in the next step.
The verification module 130 is used for judging whether the crawled power failure operation meets the specification;
the recording module 140 is used for automatically recording the content of the power failure operation ticket into the power failure operation ticket in the operation ticket module of the power grid management platform when the content of the power failure operation ticket meets the specification;
and the generating module 150 is used for generating a power failure operation ticket of the switch cabinet.
It can be understood that, in the device for generating the power failure operation ticket of the switch cabinet provided by the embodiment, the simulation module starts to perform power failure operation simulation on the switch cabinet in the power failure module of the power grid management platform; crawling power failure operation in a power failure operation simulation process in a power failure module by a crawling module; then judging whether the crawling power failure operation meets the standard or not by a verification module; when the content of the power failure operation ticket meets the standard, the recording module automatically records the content of the power failure operation ticket into the power failure operation ticket in an operation ticket module of the power grid management platform; and finally, generating a power failure operation ticket of the switch cabinet by a generating module. By implementing any method provided by the embodiment, the device of the embodiment can solve the problems that the serial numbers of the station names or the line names and the switch names are wrongly written and the logical relations are not corresponding, reduce the error rate of the operation tasks of the operation tickets, avoid accidents and improve the accuracy and efficiency of the power failure operation tickets.
The switch cabinet power failure operation ticket generating device provided by the embodiment is optimized, and further the verification module specifically comprises a correction and improvement unit for correcting and improving the crawled power failure operation when the content of the power failure operation ticket does not meet the standard;
further, the entry module specifically comprises an auditing unit, an obtaining unit and a generating unit; the auditing unit is used for generating a manual auditing flow and an interface; the acquisition unit is used for acquiring a manual auditing result, wherein the manual auditing result comprises a pass instruction and a fail instruction, and specifically can be used for generating a power failure operation ticket error early warning popup window, generating a power failure operation ticket modification suggestion popup window, acquiring a modification suggestion in the power failure operation ticket modification suggestion popup window and modifying the power failure operation ticket according to the modification suggestion when the acquired manual auditing result is the fail instruction; and the generating unit is used for generating a power failure operation ticket of the switch cabinet after the obtained manual auditing result is a pass instruction.
By implementing any method provided by the embodiment, the device of the embodiment can solve the problems that the serial numbers of the station names or the line names and the switch names are wrongly written and the logic relations are not corresponding, reduce the error rate of the operation tasks of the operation tickets, avoid accidents, improve the accuracy and the efficiency of the power failure operation tickets, increase the process of multi-user auditing and feedback by the auditing unit and the acquiring unit, and improve the accuracy and the efficiency of the power failure operation ticket generation of the switch cabinet.
EXAMPLE five
Fig. 8 is a schematic structural diagram of a switchgear power outage operation ticket generating apparatus according to a fifth embodiment of the present invention. As shown in fig. 8, an apparatus provided in the fourth embodiment of the present invention includes: one or more processors 41 and storage 42; the processor 41 in the device may be one or more, and fig. 8 illustrates one processor 41 as an example; storage 42 is used to store one or more programs; the one or more programs are executed by the one or more processors 41, so that the one or more processors 41 implement the method for generating the power failure operation ticket of the switch cabinet according to any one of the embodiments of the present invention.
The above apparatus may further include: an input device 43 and an output device 44.
The processor 41, the storage means 42, the input means 43 and the output means 44 in the device may be connected by a bus or other means, as exemplified by the bus connection in fig. 8.
The storage device 42 in the apparatus is used as a computer-readable storage medium, and can be used for storing one or more programs, where the program may be a software program, a computer-executable program, and a module, such as a module corresponding to the method for generating the power failure operation ticket for the switch cabinet provided in the first, second, or third embodiment of the present invention (for example, the simulation module 110 is used to perform power failure operation simulation on the switch cabinet in the power failure module of the power grid management platform, the crawling module 120 is used to crawl the power failure operation in the power failure operation simulation process in the power failure module, the verification module 130 is used to determine whether the crawled power failure operation meets the specification, the entry module 140 is used to automatically enter the content of the power failure operation ticket into the power failure operation ticket in the operation ticket module of the power grid management platform when the content of the power failure operation ticket meets the specification, and the generation module 150 is used to generate the power failure operation ticket for the switch cabinet. The processor 41 executes various functional applications and data processing of the terminal device by running software programs, instructions and modules stored in the storage device 42, that is, the method for generating the power failure operation ticket of the switch cabinet in the above embodiment of the method is realized.
The storage device 42 may include a storage program area and a storage data area, wherein the storage program area may store an operating system, an application program required for at least one function; the storage data area may store data created according to use of the device, and the like. Further, the storage 42 may include high speed random access memory, and may also include non-volatile memory, such as at least one magnetic disk storage device, flash memory device, or other non-volatile solid state storage device. In some examples, storage 42 may further include memory located remotely from processor 41, which may be connected to the device over a network. Examples of such networks include, but are not limited to, the internet, intranets, local area networks, mobile communication networks, and combinations thereof.
The input device 43 may be used to receive input numeric or character information and to generate key signal inputs relating to user settings and function controls of the apparatus. The output device 44 may include a display device such as a display screen.
And when the one or more programs included in the apparatus are executed by the one or more processors 41, the programs perform and complete any of the operations of the above embodiments.
EXAMPLE six
In a fourth aspect, an embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored, where the computer program, when executed by a processor, implements any one of the above methods for generating a power failure operation ticket for a switch cabinet.
The computer readable storage medium can be any computer readable storage medium for realizing the operation ticket generating method, is not limited to specific elements and models, and can store and record all data in power failure plan basic data of the switch cabinet, such as power failure time, power failure lines, power failure ranges, power failure safety measures and transfer measures, all crawled data of power failure operation, operation contents, operation sequences, all data of operation descriptions of historical power failure operation tickets and/or typical power failure operation tickets, and other related operations and data.
Of course, the storage medium provided by the embodiment of the present invention includes computer-executable instructions, and the computer-executable instructions are not limited to the method operations described above, and may also perform related operations in the method for generating the power failure operation ticket of the switch cabinet provided by any embodiment of the present invention.
From the above description of the embodiments, it is obvious for those skilled in the art that the present invention can be implemented by software and necessary general hardware, and certainly, can also be implemented by hardware, but the former is a better embodiment in many cases. Based on such understanding, the technical solutions of the present invention or portions thereof contributing to the prior art may be embodied in the form of a software product, where the computer software product may be stored in a computer-readable storage medium, such as a floppy disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a FLASH Memory (FLASH), a hard disk or an optical disk of a computer, and includes several instructions for enabling a computer device (which may be a personal computer, a server, or a network device) to execute the method for generating a switch cabinet power outage operation ticket according to the embodiments of the present invention.
It should be noted that, in the embodiment of the search apparatus, each included unit and each included module are merely divided according to functional logic, but are not limited to the above division, as long as corresponding functions can be implemented; in addition, specific names of the functional units are only for convenience of distinguishing from each other, and are not used for limiting the protection scope of the present invention.
It is to be noted that the foregoing is only illustrative of the preferred embodiments of the present invention and the technical principles employed. It will be understood by those skilled in the art that the present invention is not limited to the particular embodiments described herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the invention. Therefore, although the present invention has been described in greater detail by the above embodiments, the present invention is not limited to the above embodiments, and may include other equivalent embodiments without departing from the spirit of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims (12)

1. A method for generating a power failure operation ticket of a switch cabinet is characterized by comprising the following steps:
performing power failure operation simulation on the switch cabinet in a power failure module of the power grid management platform;
crawling power failure operation in the power failure operation simulation process in the power failure module;
judging whether the crawling power failure operation meets the standard or not;
when the content of the power failure operation ticket meets the specification, the content of the power failure operation ticket is automatically recorded into the power failure operation ticket in an operation ticket module of the power grid management platform;
and generating a power failure operation ticket of the switch cabinet.
2. The operation ticket generating method according to claim 1, wherein before the power failure operation simulation is performed on the switch cabinet in the power failure module of the power grid management platform, the method further comprises:
and recording the basic data of the power failure plan of the switch cabinet, wherein the basic data of the power failure plan of the switch cabinet comprises at least one of power failure time, power failure lines, power failure range, power failure safety measures and work transfer measures.
3. The operation ticket generating method according to claim 1, wherein the judging whether the crawled power-off operation meets the specification comprises:
and judging whether the crawled power failure operation content is complete, the sequence is correct and the description is standard.
4. The operation ticket generating method according to claim 3, wherein the judging whether the contents of the crawled power-off operations are complete, the order is correct, and the description is normative includes:
and judging whether the crawled power failure operation contents are complete, the sequence is correct and the description is standard or not according to the standard safety measures in the preset safety measure comparison table, the standard expression language in the preset standard expression comparison table and the standard line equipment in the preset line equipment database.
5. The operation ticket generating method according to claim 3, further comprising:
and when the contents of the power failure operation ticket do not meet the specifications, correcting and perfecting the crawled power failure operation.
6. The operation ticket generating method according to claim 5, wherein when the contents of the power-off operation ticket do not meet the specification, modifying and improving the crawled power-off operation comprises:
acquiring a historical power failure operation ticket and/or a typical power failure operation ticket;
and according to the operation content, the operation sequence and the operation description of the historical power failure operation ticket and/or the typical power failure operation ticket, the crawling power failure operation is perfected.
7. The operation ticket generating method according to claim 1, wherein when the content of the power failure operation ticket meets a specification, after the content of the power failure operation ticket is automatically entered into the power failure operation ticket in an operation ticket module of the power grid management platform, the method further comprises:
generating a manual auditing process and an interface;
acquiring a manual auditing result, wherein the manual auditing result comprises a passing instruction and a non-passing instruction;
generate cubical switchboard power failure operation ticket includes:
and generating the power failure operation ticket of the switch cabinet after the obtained manual auditing result is a pass instruction.
8. The operation ticket generating method according to claim 7, after obtaining the result of the manual review, further comprising:
and when the obtained manual auditing result is that the instruction does not pass, generating a power failure operation ticket error early warning popup window.
9. The operation ticket generating method according to claim 8, wherein when the obtained manual audit result is that the instruction is not passed, the method generates a power failure operation ticket error early warning popup, and further comprises:
generating a power failure operation ticket modification suggestion popup;
generate cubical switchboard power failure operation ticket still includes:
acquiring a modification suggestion in a power failure operation ticket modification suggestion popup window;
and according to the modification suggestion, modifying the power failure operation ticket and generating the power failure operation ticket of the switch cabinet.
10. The utility model provides a cubical switchboard power failure operation ticket generates device which characterized in that includes:
the simulation module is used for simulating power failure operation of the switch cabinet in the power failure module of the power grid management platform;
the crawling module is used for crawling the power failure operation in the power failure operation simulation process in the power failure module;
the verification module is used for judging whether the crawled power failure operation meets the standard or not;
the recording module is used for automatically recording the content of the power failure operation ticket into the power failure operation ticket in the operation ticket module of the power grid management platform when the content of the power failure operation ticket meets the standard;
and the generation module is used for generating a power failure operation ticket of the switch cabinet.
11. An apparatus, characterized in that the apparatus comprises:
one or more processors;
a storage device for storing one or more programs,
when the one or more programs are executed by the one or more processors, the one or more processors are caused to implement the switch cabinet power failure operation ticket generating method according to any one of claims 1-9.
12. A computer-readable storage medium, on which a computer program is stored, which, when being executed by a processor, implements the switch cabinet power off operation ticket generating method according to any one of claims 1 to 9.
CN202211397190.6A 2022-11-09 2022-11-09 Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium Pending CN115940403A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211397190.6A CN115940403A (en) 2022-11-09 2022-11-09 Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211397190.6A CN115940403A (en) 2022-11-09 2022-11-09 Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium

Publications (1)

Publication Number Publication Date
CN115940403A true CN115940403A (en) 2023-04-07

Family

ID=86653075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211397190.6A Pending CN115940403A (en) 2022-11-09 2022-11-09 Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium

Country Status (1)

Country Link
CN (1) CN115940403A (en)

Similar Documents

Publication Publication Date Title
CN106157167B (en) Secondary equipment remote control operation ticket system and implementation method of secondary equipment remote control operation ticket
CN102591223B (en) Intelligentized diagnostic system of substation-operation operation tickets
CN112508249A (en) Method and device for constructing emergency deduction graph structure and method and device for deducting emergency
CN110134053B (en) Monitoring configuration method, device and equipment for distribution transformer fault power failure quick response
CN111625964B (en) Method, system and equipment for constructing transformer substation graph model based on logical relationship
CN110069279B (en) Method, device and storage medium for checking direct current control protection program
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN109389294B (en) Usability evaluation method and device of nuclear security level DCS (distributed control System)
CN117614115A (en) Substation debugging and acceptance checking system and method based on artificial intelligence
Hong et al. Design of an intelligent system for comprehensive validation of protection settings
CN109446642B (en) Intelligent writing method and device for power grid equipment starting scheme
CN115940403A (en) Method, device and equipment for generating power failure operation ticket of switch cabinet and readable storage medium
CN116186192A (en) SCD file verification method and device based on standard virtual terminal loop expert database
CN114519650A (en) Intelligent ticket checking method, equipment and storage medium for dispatching operation tickets of urban power grid
CN109066419B (en) Diagnosis method and system for secondary equipment maintenance safety measure operation and terminal equipment
CN113553117A (en) Method and device for automatically generating configuration data of automatic train supervision system
CN115481964A (en) Intelligent ticket forming method and device
CN113033019A (en) Production system graphic billing method based on simulated rehearsal
JP2002055717A (en) Failure diagnostic system
Yunguang et al. Research on secondary circuit identification technology and condition-based maintenance mode of intelligent substation
CN113159729B (en) Point table checking system and method for shortening point table checking time
CN113672647B (en) Planned power outage specification verification method and device
CN113935579A (en) Method, device and system for processing sequence control operation order of secondary equipment of intelligent substation
Saeed et al. Robust Requirements Specifications for Safety—Critical Systems
CN112799870A (en) Data processing method and device for realizing data restoration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination