CN115801093A - A path planning method to guarantee the end-to-end deterministic delay of satellite network - Google Patents

A path planning method to guarantee the end-to-end deterministic delay of satellite network Download PDF

Info

Publication number
CN115801093A
CN115801093A CN202211262254.1A CN202211262254A CN115801093A CN 115801093 A CN115801093 A CN 115801093A CN 202211262254 A CN202211262254 A CN 202211262254A CN 115801093 A CN115801093 A CN 115801093A
Authority
CN
China
Prior art keywords
node
satellite
time
task
path
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211262254.1A
Other languages
Chinese (zh)
Other versions
CN115801093B (en
Inventor
崔涛
李小军
沈俊
和欣
周诠
黎军
李勃
李静玲
梁薇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Institute of Space Radio Technology
Original Assignee
Xian Institute of Space Radio Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Institute of Space Radio Technology filed Critical Xian Institute of Space Radio Technology
Priority to CN202211262254.1A priority Critical patent/CN115801093B/en
Publication of CN115801093A publication Critical patent/CN115801093A/en
Application granted granted Critical
Publication of CN115801093B publication Critical patent/CN115801093B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D30/00Reducing energy consumption in communication networks
    • Y02D30/70Reducing energy consumption in communication networks in wireless communication networks

Landscapes

  • Radio Relay Systems (AREA)

Abstract

一种保证卫星网络端到端确定性时延的路径规划方法,首先,面向业务特征构建卫星网络时空图,根据任务业务量和卫星链路容量计算传输时隙,并以此时隙对任务作用时间域进行划分,然后根据时隙内卫星网络节点的连通关系和连通时长建立卫星网络时空图;接着针对卫星链路时变特征,以任务业务量大小、卫星节点连通链路容量与卫星节点资源分配为约束条件,以及业务传输起止时间与链路连通时间为判断条件的路径规划计算方法;最后以任务接入卫星节点作为第一跳起点,在所有连通的相邻节点中依据路径规划计算方法寻找下一跳路径节点,直至目的节点,由此获得卫星网络的确定性传输路径,从而形成具有确定性时延保证的卫星网络路径规划方法。

Figure 202211262254

A path planning method that guarantees the end-to-end deterministic delay of the satellite network. Firstly, the space-time map of the satellite network is constructed for the service characteristics, and the transmission time slot is calculated according to the task traffic and the capacity of the satellite link, and the role of the time slot on the task is calculated. The time domain is divided, and then the satellite network space-time diagram is established according to the connection relationship and connection duration of the satellite network nodes in the time slot; then, according to the time-varying characteristics of the satellite link, the task traffic size, the satellite node connection link capacity and the satellite node resource Allocation is a constraint condition, and the path planning calculation method is determined by the business transmission start and end time and link connection time; finally, the task access satellite node is used as the first hop starting point, and the path planning calculation method is used in all connected adjacent nodes. Find the next hop path node until the destination node, thereby obtaining the deterministic transmission path of the satellite network, thereby forming a satellite network path planning method with deterministic delay guarantee.

Figure 202211262254

Description

一种保证卫星网络端到端确定性时延的路径规划方法A path planning method to guarantee the end-to-end deterministic delay of satellite network

技术领域technical field

本发明涉及一种保证卫星网络端到端确定性时延的路径规划方法,属于通信技术领域。The invention relates to a path planning method for ensuring end-to-end deterministic time delay of a satellite network, and belongs to the technical field of communication.

背景技术Background technique

空间信息网络需要在应急通信、应急救援、导航定位、遥感遥测、国防安全、智慧城市等领域为不同类型业务构建稳健传输路径,保障关键业务数据的确定性可达。但由于卫星不同周期的高速运动、网络承载业务负荷随时间的动态变化,导致空间信息网络拓扑和多维网络资源(如链路容量、节点存储等)具有时变性,造成端到端确定性传输路径难构建,难以保障确定性时延和时延抖动等服务质量。Spatial information networks need to build robust transmission paths for different types of services in areas such as emergency communications, emergency rescue, navigation and positioning, remote sensing and telemetry, national defense security, and smart cities to ensure the deterministic accessibility of key business data. However, due to the high-speed movement of satellites in different periods and the dynamic change of network load over time, the spatial information network topology and multi-dimensional network resources (such as link capacity, node storage, etc.) are time-varying, resulting in end-to-end deterministic transmission paths. It is difficult to build, and it is difficult to guarantee the quality of service such as deterministic delay and delay jitter.

已有的卫星网络路由算法(如开放式最短路径路由、连通图路由等方法),以静态图论为设计依据,未考虑网络业务以及资源自身的随机特性,会造成业务报文在卫星节点的到达时间不一致,同时链路状态不稳定也会造成业务报文需要进行存储等待,这样导致业务端到端时延有长尾效应,造成了时延的不确定性,影响确定性业务的“准时、准确”传输和业务报文的时效性。Existing satellite network routing algorithms (such as open shortest path routing, connected graph routing, etc.) are designed based on static graph theory, without considering the random characteristics of network services and resources themselves, which will cause service packets to be lost in satellite nodes. Inconsistent arrival times and unstable link status will also cause service packets to be stored and waited for, resulting in a long-tail effect of service end-to-end delay, resulting in delay uncertainty and affecting the "punctuality" of deterministic services. , accurate" transmission and the timeliness of business messages.

发明内容Contents of the invention

本发明要解决的技术问题是:克服现有技术的不足,解决了保证卫星网络端到端确定性时延条件下的路径规划问题。The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and solve the path planning problem under the condition of ensuring the end-to-end deterministic time delay of the satellite network.

本发明目的通过以下技术方案予以实现:The object of the invention is achieved through the following technical solutions:

一种保证卫星网络端到端确定性时延的路径规划方法,包括:A path planning method for ensuring end-to-end deterministic delay of a satellite network, comprising:

根据任务业务量和卫星链路容量计算传输时隙,并以此时隙对任务作用时间域进行划分,然后根据时隙内卫星网络节点的连通关系和连通时长建立卫星网络时空图;Calculate the transmission time slot according to the task traffic and satellite link capacity, and divide the task action time domain according to this time slot, and then establish the satellite network space-time diagram according to the connection relationship and connection duration of the satellite network nodes in the time slot;

以任务接入卫星节点作为第一跳起点,在所有连通的相邻节点中依据路径规划方法寻找下一跳路径节点,直至目的节点,由此获得卫星网络的确定性传输路径,从而形成具有确定性时延保证的卫星网络路径规划方法;Take the task access satellite node as the first hop starting point, find the next hop path node in all connected adjacent nodes according to the path planning method, until the destination node, thereby obtaining the deterministic transmission path of the satellite network, thus forming a deterministic Satellite network path planning method with permanent delay guarantee;

其中路径规划方法具体为:以任务业务量大小、卫星节点连通链路容量、卫星节点资源分配为约束条件,以业务传输起止时间与链路连通时间为判断条件,进行路径规划。The path planning method is specifically: taking the size of the task traffic, the link capacity of the satellite node connection, and the resource allocation of the satellite node as the constraint conditions, and taking the start and end time of the service transmission and the link connection time as the judgment conditions to perform path planning.

优选的,以任务包含所有业务量的最大公约数vφ和星间链路容量参数C(t)计算基本单位时间τ;以此基本单位时间为时隙对任务作用时间域进行划分。Preferably, the basic unit time τ is calculated based on the greatest common divisor v φ of all traffic volumes included in the task and the capacity parameter C(t) of the inter-satellite link; the basic unit time is used as time slots to divide the task action time domain.

优选的,根据卫星网络时空图,能够得到任意两个卫星节点(u,v)在任意m个时刻之间(ti,ti+m)的连续连通时间Δtuv(ti,ti+m)。Preferably, according to the space - time diagram of the satellite network, the continuous connection time Δt uv (t i ,t i + m ).

优选的,路径规划方法具体为:Preferably, the path planning method is specifically:

若寻路的起始节点为任务接入卫星源节点S,则起始时间为任务接入时间ts_start,根据起始节点与连通卫星节点间的链路容量C(s,k),计算出该任务业务量在该条卫星链路上的传输结束时间tsk_end,计算方法为:

Figure BDA0003891589510000021
则该任务业务量传输时间Δtsk(M)=tsk_end-ts_start,在集合Q中选取与起始节点所连通的卫星节点,若Δtsk(M)在卫星节点(s,k)连通时间的连续区间内,即Δtsk(M)≤Δtuv(ti,ti+m),u=s,v=k,ts_start≥ti,tsk_end≤ti+m,则将卫星节点k作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtsk(M)>Δtuv(ti,ti+m),u=s,v=k,即该任务业务量不能在卫星节点(s,k)连通时间的连续区间内完成传输,则卫星节点k不满足要求;If the starting node of the pathfinding is the task access satellite source node S, then the starting time is the task access time t s_start , according to the link capacity C(s,k) between the starting node and the connected satellite node, calculate The transmission end time t sk_end of the task traffic on the satellite link is calculated as:
Figure BDA0003891589510000021
Then the task traffic transmission time Δt sk (M) = t sk_end -t s_start , select the satellite node connected to the starting node in the set Q, if Δt sk (M) is within the satellite node (s,k) connection time In the continuous interval of , that is, Δt sk (M)≤Δt uv (t i ,t i+m ), u=s,v=k,t s_start ≥t i ,t sk_end ≤t i+m , then the satellite node k as the current path-finding node, and write it into the deterministic path node set P, and delete this node from the set Q; if Δt sk (M)>Δt uv (t i ,t i+m ), u= s, v=k, that is, the task traffic cannot complete the transmission within the continuous interval of the satellite node (s, k) connection time, then the satellite node k does not meet the requirements;

若寻路的起始节点为卫星网络中间节点k,在集合Q中与该节点k相连通的下一跳卫星节点j,其连续连通时间的起始时间为tkj_start,ts_start<tkj_start≤tsk_end;根据起始节点与连通卫星节点间的链路容量C(k,j),计算出该任务业务量在该条卫星链路上的传输结束时间tkj_end,计算方法为:

Figure BDA0003891589510000031
同时满足节点k的缓存约束:
Figure BDA0003891589510000032
则该任务业务量传输时间Δtkj(M)=tkj_end-tkj_start,若Δtkj(M)在卫星节点(k,j)连通时间的连续区间内,即Δtkj(M)≤Δtuv(ti,ti+m),u=k,v=j,tkj_start≥ti,tkj_end≤ti+m,则将卫星节点j作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtkj(M)>Δtuv(ti,ti+m),u=k,v=j,则表示该任务业务量不能在卫星节点(k,j)连通时间的连续区间内完成传输,则卫星节点j不满足要求;If the starting node of the pathfinding is the intermediate node k of the satellite network, the next hop satellite node j connected to the node k in the set Q, the starting time of its continuous connection time is t kj_start , t s_start <t kj_start ≤ t sk_end ; According to the link capacity C(k,j) between the starting node and the connected satellite node, calculate the transmission end time t kj_end of the task traffic on the satellite link, and the calculation method is:
Figure BDA0003891589510000031
Simultaneously satisfy the cache constraint of node k:
Figure BDA0003891589510000032
Then the task traffic transmission time Δt kj (M) = t kj_end -t kj_start , if Δt kj (M) is within the continuous interval of the satellite node (k, j) connection time, that is, Δt kj (M)≤Δt uv ( t i ,t i+m ),u=k,v=j,t kj_start ≥t i ,t kj_end ≤t i+m , then take the satellite node j as the current path-finding node and write it into the deterministic path node in the set P, and delete the node from the set Q; if Δt kj (M)>Δt uv (t i ,t i+m ), u=k, v=j, it means that the task traffic cannot be If the transmission is completed within the continuous interval of the connection time of node (k, j), the satellite node j does not meet the requirements;

若j=D,即寻路到目的卫星节点时,则寻路结束;若j≠D,即未寻路到目的卫星节点时,重新进行寻路。If j=D, that is, when the destination satellite node is found, the path finding ends; if j≠D, that is, when the destination satellite node is not found, the path finding is performed again.

一种保证卫星网络端到端确定性时延的路径规划方法,包括:A path planning method for ensuring end-to-end deterministic delay of a satellite network, comprising:

S1、确定任务需求;确定不同时刻卫星网络星间链路容量参数C(t);S1. Determine the task requirements; determine the capacity parameter C(t) of the inter-satellite link of the satellite network at different times;

S2、计算任务包含的所有业务传输的基本单位时间为时隙,计算基本单位时间τ,以此基本单位时间为时隙对任务作用时间域进行划分;S2. Calculate the basic unit time of all business transmissions included in the task as time slots, calculate the basic unit time τ, and use the basic unit time as time slots to divide the task action time domain;

S3、获取任务作用时间域T内的所有卫星节点连通关系图;S3. Obtain the connectivity diagram of all satellite nodes in the task action time domain T;

S4、设定确定性路径节点集合为P,以任务接入卫星节点为源节点S,将该节点写入确定性路径节点集合P;S4. Set the deterministic path node set as P, take the task access satellite node as the source node S, and write this node into the deterministic path node set P;

S5、设置卫星网络除源节点S外的所有卫星节点为集合Q,并判断集合Q是否为空,若为空,则进行步骤S7;若非空,则进行步骤S6S5. Set all satellite nodes in the satellite network except the source node S as a set Q, and judge whether the set Q is empty, if it is empty, proceed to step S7; if not empty, proceed to step S6

S6、以任务接入时间为起始时间ts-start,根据业务传输时间Δt(M)、卫星节点缓存容量Buffer(u)以及卫星节点间连通时间Δtuv(ti,ti+m)的关系确定下一跳卫星节点;S6. Taking the task access time as the starting time t s-start , according to the service transmission time Δt(M), the satellite node buffer capacity Buffer(u) and the connection time between satellite nodes Δt uv (t i ,t i+m ) The relationship between determines the next hop satellite node;

S7、判断确定性路径节点集合为P是否为最终的确定性路径集合;若目的卫星节点D在确定性路径节点集合P中,即D∈P,则寻路结束,该确定性路径节点集合P中的卫星节点按序组合成路径,并记录该任务业务量在各节点间的传输时间,即为该路径的端到端传输确定性时延;若

Figure BDA0003891589510000042
则表示不存在符合条件的路径,寻路结束。S7. Determine whether the deterministic path node set P is the final deterministic path set; if the destination satellite node D is in the deterministic path node set P, that is, D∈P, then the pathfinding ends, and the deterministic path node set P The satellite nodes in the path are combined into paths in sequence, and the transmission time of the task traffic between each node is recorded, which is the end-to-end transmission deterministic delay of the path; if
Figure BDA0003891589510000042
It means that there is no path that meets the condition, and the pathfinding ends.

优选的,任务需求包括任务业务量M、任务包含业务种类N、每种业务的业务量为Vi(i=1,2,…,N)、任务起始接入卫星节点S、任务目的卫星节点D、任务作用时间域T。Preferably, the task requirements include the task traffic volume M, the task contains the business category N, the traffic volume of each business is V i (i=1, 2, ..., N), the mission start access satellite node S, the mission destination satellite node Node D, task action time domain T.

优选的,根据任务作用时间域T内的所有卫星节点连通关系图,能够得到任意两个卫星节点(u,v)在任意m个时刻之间(ti,ti+m)的连续连通时间Δtuv(ti,ti+m),m∈(1,2,…,n)。Preferably, according to the connection relationship diagram of all satellite nodes in the task action time domain T, the continuous connection time between any two satellite nodes (u, v) at any m moments (t i , t i+m ) can be obtained Δt uv (t i ,t i+m ), m∈(1,2,...,n).

优选的,以任务包含所有业务量的最大公约数vφ和星间链路容量参数C(t)计算基本单位时间τ。Preferably, the basic unit time τ is calculated by using the greatest common divisor v φ of all traffic in the task and the capacity parameter C(t) of the inter-satellite link.

优选的,步骤S6具体为:Preferably, step S6 is specifically:

S61、若寻路的起始节点为任务接入卫星源节点S,则起始时间为任务接入时间ts_start,根据起始节点与连通卫星节点间的链路容量C(s,k),计算出该任务业务量在该条卫星链路上的传输结束时间tsk_end,计算方法为:

Figure BDA0003891589510000041
则该任务业务量传输时间Δtsk(M)=tsk_end-ts_start,在集合Q中选取与起始节点所连通的卫星节点,若Δtsk(M)在卫星节点(s,k)连通时间的连续区间内,即Δtsk(M)≤Δtuv(ti,ti+m),u=s,v=k,ts_start≥ti,tsk_end≤ti+m,则将卫星节点k作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtsk(M)>Δtuv(ti,ti+m),u=s,v=k,即该任务业务量不能在卫星节点(s,k)连通时间的连续区间内完成传输,则卫星节点k不满足要求,返回步骤S5;S61. If the starting node of the pathfinding is the task access satellite source node S, then the starting time is the task access time t s_start . According to the link capacity C(s,k) between the starting node and the connected satellite node, Calculate the transmission end time t sk_end of the task traffic on the satellite link, and the calculation method is:
Figure BDA0003891589510000041
Then the task traffic transmission time Δt sk (M) = t sk_end -t s_start , select the satellite node connected to the starting node in the set Q, if Δt sk (M) is within the satellite node (s,k) connection time In the continuous interval of , that is, Δt sk (M)≤Δt uv (t i , t i+m ), u=s, v=k, t s_start ≥t i , t sk_end ≤t i+m , then the satellite node k as the current path-finding node, and write it into the deterministic path node set P, and delete this node from the set Q; if Δt sk (M)>Δt uv (t i ,t i+m ), u= s, v=k, that is, the task traffic cannot be transmitted within the continuous interval of the satellite node (s, k) connection time, then the satellite node k does not meet the requirements, and returns to step S5;

S62、若寻路的起始节点为卫星网络中间节点k,在集合Q中与该节点k相连通的下一跳卫星节点j,其连续连通时间的起始时间为tkj_start,ts_start<tkj_start≤tsk_end;根据起始节点与连通卫星节点间的链路容量C(k,j),计算出该任务业务量在该条卫星链路上的传输结束时间tkj_en d,计算方法为:

Figure BDA0003891589510000051
同时满足节点k的缓存约束:
Figure BDA0003891589510000052
则该任务业务量传输时间Δtkj(M)=tkj_end-tkj_start,若Δtkj(M)在卫星节点(k,j)连通时间的连续区间内,即Δtkj(M)≤Δtuv(ti,ti+m),u=k,v=j,tkj_start≥ti,tkj_end≤ti+m,则将卫星节点j作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtkj(M)>Δtuv(ti,ti+m),u=k,v=j,则表示该任务业务量不能在卫星节点(k,j)连通时间的连续区间内完成传输,则卫星节点j不满足要求,返回步骤S5;S62. If the starting node of the pathfinding is the intermediate node k of the satellite network, the next hop satellite node j connected to the node k in the set Q, the starting time of its continuous connection time is t kj_start , t s_start <t kj_start ≤t sk_end ; According to the link capacity C(k , j) between the starting node and the connected satellite node, calculate the transmission end time t kj_end of the task traffic on the satellite link, and the calculation method is:
Figure BDA0003891589510000051
Simultaneously satisfy the cache constraint of node k:
Figure BDA0003891589510000052
Then the task traffic transmission time Δt kj (M) = t kj_end -t kj_start , if Δt kj (M) is within the continuous interval of the satellite node (k, j) connection time, that is, Δt kj (M)≤Δt uv ( t i ,t i+m ),u=k,v=j,t kj_start ≥t i ,t kj_end ≤t i+m , then take the satellite node j as the current path-finding node and write it into the deterministic path node in the set P, and delete the node from the set Q; if Δt kj (M)>Δt uv (t i ,t i+m ), u=k, v=j, it means that the task traffic cannot be If the transmission is completed within the continuous interval of the connection time of node (k, j), then the satellite node j does not meet the requirements, and returns to step S5;

S63若j=D,即寻路到目的卫星节点时,则寻路结束,进行步骤S7;若j≠D,即未寻路到目的卫星节点时,则返回步骤S5。S63 If j=D, that is, when the route is found to the destination satellite node, then the route finding ends, and proceed to step S7; if j≠D, that is, when the destination satellite node is not found, then return to step S5.

一种计算机可读存储介质,其上存储有计算机程序指令,所述计算机程序指令在由处理器加载并运行时,使所述处理器执行上述保证卫星网络端到端确定性时延的路径规划方法。A computer-readable storage medium, on which computer program instructions are stored, and when the computer program instructions are loaded and run by a processor, the processor executes the above-mentioned path planning that guarantees the end-to-end deterministic delay of the satellite network method.

本发明相比于现有技术具有如下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

(1)本发明根据业务量和卫星链路累积流量计算传输时隙,并以此时隙对任务作用时间域内进行划分,然后根据时隙内卫星网络节点的连通关系和连通时长建立卫星网络时间连续图;依据任务业务量大小、业务传输开始时刻和结束时刻以及卫星节点连通链路容量与卫星节点存储占用为约束,形成路径规划计算方法;并以任务接入卫星节点作为第一跳起点,在所有连通的相邻节点中依据路径计算方法寻找下一跳路径节点,直至目的节点,由此获得卫星网络的确定性传输路径,消除了因业务存储造成的等待时延,实现多类型业务的确定性传输。(1) The present invention calculates the transmission time slot according to the traffic volume and the cumulative flow of the satellite link, and divides the task action time domain with this time slot, and then establishes the satellite network time according to the connection relationship and connection duration of the satellite network nodes in the time slot Continuous graph; based on the size of the task business volume, the start time and end time of business transmission, the connection link capacity of the satellite node and the storage occupancy of the satellite node as constraints, a path planning calculation method is formed; and the task access satellite node is used as the first hop starting point, In all connected adjacent nodes, the next hop path node is found according to the path calculation method until the destination node, thereby obtaining the deterministic transmission path of the satellite network, eliminating the waiting delay caused by service storage, and realizing the multi-type service. Deterministic transfer.

(2)本发明方法提出面向业务特征的卫星网络时空图构建方法,根据业务量和卫星链路传输累积流量计算传输时隙,基于此时隙对任务作用时间域进行划分,并在划分时间周期内根据卫星节点连通关系建立卫星网络时空图,能够精确适配不同特征业务的传输要求。(2) The method of the present invention proposes a satellite network spatio-temporal map construction method oriented to service characteristics, calculates the transmission time slot according to the traffic volume and the cumulative flow of satellite link transmission, divides the task action time domain based on this time slot, and divides the time period The space-time map of the satellite network is established based on the connection relationship of satellite nodes, which can accurately adapt to the transmission requirements of different characteristic services.

(3)本发明方法根据不同卫星网络业务特征进行传输时隙计算,获得不同业务的时隙占用,保证在卫星节点连通时间内能够完整传输业务数据包,消除了业务因等待链路连通造成的时延不确定。(3) The method of the present invention carries out transmission time slot calculation according to different satellite network service characteristics, obtains the time slot occupation of different services, guarantees that the service data packet can be completely transmitted within the connection time of the satellite node, and eliminates the problem that the service is caused by waiting for the link to be connected Latency is uncertain.

(4)本发明方法根据不同卫星节点间链路的累积流量确定业务传输起止时刻,精准刻画业务流量传输时间与卫星节点连通时间的关系,构建具有时间属性的确定性时延路径,保障了时变链路条件下的业务端到端确定性传输。(4) The method of the present invention determines the start and end time of service transmission according to the cumulative flow of links between different satellite nodes, accurately describes the relationship between the service flow transmission time and the connection time of satellite nodes, and constructs a deterministic delay path with time attributes, ensuring time End-to-end deterministic transmission of services under variable link conditions.

(5)本发明方法考虑卫星节点间链路的时变特性,依据链路累积流量计算业务传输时间,通过准确控制上下游卫星节点的起始传输时间实现动态链路变化条件下业务的确定性传输。(5) The method of the present invention considers the time-varying characteristics of the links between satellite nodes, calculates the service transmission time according to the cumulative traffic of the link, and realizes the certainty of the service under the dynamic link change condition by accurately controlling the initial transmission time of the upstream and downstream satellite nodes transmission.

附图说明Description of drawings

图1为卫星网络拓扑组成示意图。Figure 1 is a schematic diagram of the composition of the satellite network topology.

图2为卫星节点连通关系图。Figure 2 is a connection diagram of satellite nodes.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明的实施方式作进一步详细描述。In order to make the object, technical solution and advantages of the present invention clearer, the implementation manner of the present invention will be further described in detail below in conjunction with the accompanying drawings.

一种保证卫星网络端到端确定性时延的路径规划方法,首先,面向业务特征构建卫星网络时空图,根据任务业务量和卫星链路容量计算传输时隙,并以此时隙对任务作用时间域进行划分,然后根据时隙内卫星网络节点的连通关系和连通时长建立卫星网络时空图;接着针对卫星链路时变特征,提出一种以任务业务量大小、卫星节点连通链路容量与卫星节点资源分配(如存储占用)为约束条件,以及业务传输起止时间与链路连通时间为判断条件的路径规划计算方法;最后以任务接入卫星节点作为第一跳起点,在所有连通的相邻节点中依据路径规划计算方法寻找下一跳路径节点,直至目的节点,由此获得卫星网络的确定性传输路径,从而形成具有确定性时延保证的卫星网络路径规划方法。A path planning method to ensure the end-to-end deterministic delay of the satellite network. First, construct the space-time map of the satellite network based on the service characteristics, calculate the transmission time slot according to the mission traffic and the capacity of the satellite link, and use this time slot to affect the mission. The time domain is divided, and then the satellite network space-time diagram is established according to the connection relationship and connection duration of the satellite network nodes in the time slot; Satellite node resource allocation (such as storage occupancy) is a constraint condition, and the path planning calculation method is determined by the business transmission start and end time and link connection time; finally, the task access satellite node is used as the first hop starting point, and all connected According to the path planning calculation method, the adjacent nodes find the next hop path node until the destination node, thereby obtaining the deterministic transmission path of the satellite network, thus forming a satellite network path planning method with deterministic delay guarantee.

实施例1:Example 1:

一种保证卫星网络端到端确定性时延的路径规划方法,包括:A path planning method for ensuring end-to-end deterministic delay of a satellite network, comprising:

S1.具有确定性时延保证需求的任务开始时,用户发起任务需求通知卫星网络管理中心,任务需求包括任务业务量M、任务包含业务种类N,每种业务的业务量为Vi(i=1,2,…,N),任务起始接入卫星节点S、任务目的卫星节点D、任务作用时间域T等参数信息,卫星网络管理中心可获取不同时刻卫星网络星间链路容量参数C(t);S1. When a task with a deterministic delay guarantee requirement starts, the user initiates a task requirement and notifies the satellite network management center. The task requirement includes task traffic M, and the task includes service category N, and the traffic volume of each service is V i (i= 1, 2, ..., N), mission start access satellite node S, mission destination satellite node D, mission action time domain T and other parameter information, the satellite network management center can obtain the satellite network inter-satellite link capacity parameter C at different times (t);

S2.计算任务包含的所有业务传输的基本单位时间为时隙,以任务包含所有业务量的最大公约数vφ和星间链路容量参数C(t)计算基本单位时间τ,

Figure BDA0003891589510000071
以此基本单位时间为时隙对任务作用时间域进行划分,得到的时刻数目为n,
Figure BDA0003891589510000072
即t1,t2,…tn。S2. The basic unit time of all business transmissions included in the calculation task is a time slot, and the basic unit time τ is calculated with the greatest common divisor v φ of all traffic volumes included in the task and the capacity parameter C(t) of the inter-satellite link,
Figure BDA0003891589510000071
Using this basic unit of time as the time slot to divide the task action time domain, the number of time obtained is n,
Figure BDA0003891589510000072
That is, t 1 , t 2 , . . . t n .

S3.根据卫星网络拓扑,获取任务作用时间域T内的所有卫星节点连通关系图,可以得到任意两个卫星节点(u,v)在任意m个时刻之间(ti,ti+m)的连续连通时间Δtuv(ti,ti+m),m∈(1,2,…,n);S3. According to the satellite network topology, obtain the connection relationship diagram of all satellite nodes in the task action time domain T, and obtain any two satellite nodes (u, v) between any m moments (t i , t i+m ) The continuous connection time Δt uv (t i ,t i+m ), m∈(1,2,…,n);

S4.设定确定性路径节点集合为P,以任务接入卫星节点为源节点S,将该节点写入确定性路径节点集合P;S4. Set the deterministic path node set as P, take the task access satellite node as the source node S, and write this node into the deterministic path node set P;

S5.设置卫星网络除源节点S外的所有卫星节点为集合Q,并判断集合Q是否为空,若为空,则进行步骤S7;若非空,则进行步骤S6。S5. Set all the satellite nodes in the satellite network except the source node S as the set Q, and judge whether the set Q is empty, if it is empty, go to step S7; if not, go to step S6.

S6.以任务接入时间为起始时间ts-start,根据业务传输时间Δt(M)、卫星节点缓存容量Buffer(u)以及卫星节点间连通时间Δtuv(ti,ti+m)的关系确定下一跳卫星节点。步骤S6具体为:S6. Taking the task access time as the starting time t s-start , according to the service transmission time Δt(M), the satellite node buffer capacity Buffer(u) and the connection time between satellite nodes Δt uv (t i ,t i+m ) The relationship determines the next hop satellite node. Step S6 is specifically:

S61若寻路的起始节点为任务接入卫星源节点S,则起始时间为任务接入时间ts_start,根据起始节点与连通卫星节点间的链路容量C(s,k),计算出该任务业务量在该条卫星链路上的传输结束时间tsk_end,计算方法为:

Figure BDA0003891589510000081
则该任务业务量传输时间Δtsk(M)=tsk_end-ts_start,在集合Q中选取与起始节点所连通的卫星节点,若Δtsk(M)在卫星节点(s,k)连通时间的连续区间内,即Δtsk(M)≤Δtuv(ti,ti+m),u=s,v=k,ts_start≥ti,tsk_end≤ti+m,则将卫星节点k作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除。若Δtsk(M)>Δtuv(ti,ti+m),u=s,v=k,即该任务业务量不能在卫星节点(s,k)连通时间的连续区间内完成传输,则卫星节点k不满足要求,返回步骤S5。S61 If the starting node of the pathfinding is the task access satellite source node S, then the starting time is the task access time t s_start , and according to the link capacity C(s,k) between the starting node and the connected satellite node, calculate Calculate the transmission end time t sk_end of the task traffic on the satellite link, and the calculation method is:
Figure BDA0003891589510000081
Then the task traffic transmission time Δt sk (M) = t sk_end -t s_start , select the satellite node connected to the starting node in the set Q, if Δt sk (M) is within the satellite node (s,k) connection time In the continuous interval of , that is, Δt sk (M)≤Δt uv (t i ,t i+m ), u=s,v=k,t s_start ≥t i ,t sk_end ≤t i+m , then the satellite node k is used as the current path-finding node, and is written into the deterministic path node set P, and the node is deleted from the set Q. If Δt sk (M)>Δt uv (t i ,t i+m ), u=s, v=k, that is, the task traffic cannot be transmitted within the continuous interval of the satellite node (s, k) connection time, Then the satellite node k does not meet the requirements, and returns to step S5.

S62若寻路的起始节点为卫星网络中间节点k,在集合Q中与该节点k相连通的下一跳卫星节点j,其连续连通时间的起始时间为tkj_start,ts_start<tkj_start≤tsk_end。根据起始节点与连通卫星节点间的链路容量C(k,j),计算出该任务业务量在该条卫星链路上的传输结束时间tkj_end,计算方法为:

Figure BDA0003891589510000082
同时满足节点k的缓存约束:
Figure BDA0003891589510000083
则该任务业务量传输时间Δtkj(M)=tkj_end-tkj_start,若Δtkj(M)在卫星节点(k,j)连通时间的连续区间内,即Δtkj(M)≤Δtuv(ti,ti+m),u=k,v=j,tkj_start≥ti,tkj_end≤ti+m,则将卫星节点j作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除。若Δtkj(M)>Δtuv(ti,ti+m),u=k,v=j,则表示该任务业务量不能在卫星节点(k,j)连通时间的连续区间内完成传输,则卫星节点j不满足要求,返回步骤S5。S62 If the starting node of the pathfinding is the intermediate node k of the satellite network, the next hop satellite node j connected to the node k in the set Q, the starting time of its continuous connection time is t kj_start , t s_start <t kj_start ≤tsk_end . According to the link capacity C(k,j) between the starting node and the connected satellite node, calculate the transmission end time t kj_end of the task traffic on the satellite link, and the calculation method is:
Figure BDA0003891589510000082
Simultaneously satisfy the cache constraint of node k:
Figure BDA0003891589510000083
Then the task traffic transmission time Δt kj (M) = t kj_end -t kj_start , if Δt kj (M) is within the continuous interval of the satellite node (k, j) connection time, that is, Δt kj (M)≤Δt uv ( t i ,t i+m ),u=k,v=j,t kj_start ≥t i ,t kj_end ≤t i+m , then take the satellite node j as the current path-finding node and write it into the deterministic path node In the set P, and delete the node from the set Q. If Δt kj (M)>Δt uv (t i ,t i+m ), u=k, v=j, it means that the task traffic cannot be transmitted within the continuous interval of the satellite node (k, j) connection time , then the satellite node j does not meet the requirements, return to step S5.

S63若j=D,即寻路到目的卫星节点时,则寻路结束,进行步骤S7;若j≠D,即未寻路到目的卫星节点时,则返回步骤S5。S63 If j=D, that is, when the route is found to the destination satellite node, then the route finding ends, and proceed to step S7; if j≠D, that is, when the destination satellite node is not found, then return to step S5.

S7.判断确定性路径节点集合为P是否为最终的确定性路径集合。若目的卫星节点D在确定性路径节点集合P中,即D∈P,则寻路结束,该确定性路径节点集合P中的卫星节点按序组合成路径,并记录该任务业务量在各节点间的传输时间,即为该路径的端到端传输确定性时延;若

Figure BDA0003891589510000093
则表示不存在符合条件的路径,寻路结束。S7. Determine whether the deterministic path node set P is the final deterministic path set. If the destination satellite node D is in the deterministic path node set P, that is, D ∈ P, the pathfinding ends, the satellite nodes in the deterministic path node set P are combined into a path in sequence, and the task traffic is recorded at each node The transmission time between is the end-to-end transmission deterministic delay of the path; if
Figure BDA0003891589510000093
It means that there is no path that meets the condition, and the pathfinding ends.

实施例2:Example 2:

一种保证卫星网络端到端确定性时延的路径规划方法,包括:A path planning method for ensuring end-to-end deterministic delay of a satellite network, comprising:

S1.具有确定性时延保证需求的任务开始时,用户发起任务需求通知卫星网络管理中心,任务需求包括任务业务量M为2个单位数据、任务包含业务种类N=2,业务速率为V1=V2=1个单位数据,任务起始接入卫星节点A、任务目的卫星节点D、任务作用时间域T分为6个单位时间等参数信息,卫星网络管理中心获取的卫星网络星间链路容量参数C(t)为1个单位数据;S1. When a task with a deterministic delay guarantee requirement starts, the user initiates a task requirement to notify the satellite network management center. The task requirement includes the task traffic M being 2 units of data, the task includes business types N=2, and the business rate is V 1 =V 2 =1 unit of data, mission start access satellite node A, mission destination satellite node D, mission action time domain T is divided into 6 unit time and other parameter information, the satellite network intersatellite link obtained by the satellite network management center The road capacity parameter C(t) is 1 unit of data;

S2.计算任务包含所有业务传输的基本单位时间,以任务包含所有业务量的最大公约数vφ=1和星间链路容量参数C(t)计算基本单位时间τ,

Figure BDA0003891589510000091
得到τ=1。以此基本单位时间对任务作用时间域进行划分,得到的时刻数目为n,
Figure BDA0003891589510000092
即(t0,t1,t2,t3,t4,t5)。S2. The calculation task includes the basic unit time of all business transmissions, and calculates the basic unit time τ with the task including the greatest common divisor v φ =1 of all traffic volumes and the inter-satellite link capacity parameter C(t),
Figure BDA0003891589510000091
τ=1 is obtained. Based on this basic unit time, the task action time domain is divided, and the number of moments obtained is n,
Figure BDA0003891589510000092
That is (t 0 , t 1 , t 2 , t 3 , t 4 , t 5 ).

S3.假定卫星网络拓扑包含4个卫星节点,如图1所示,获取任务作用时间域T内的所有卫星节点连通关系图,可以得到在任意m个时刻之间(ti,ti+m)的连续连通时间Δtuv(ti,ti+m),m∈(1,2,…,n),如图2所示;S3. Assume that the satellite network topology contains 4 satellite nodes, as shown in Figure 1, obtain the connection relationship diagram of all satellite nodes in the task action time domain T, you can get (t i , t i+m ) of continuous connectivity time Δt uv (t i ,t i+m ), m∈(1,2,…,n), as shown in Figure 2;

S4.设定确定性路径节点集合为P,以任务接入卫星节点为源节点A,将该节点写入确定性路径节点集合P,即P={A};S4. Set the deterministic path node set as P, take the task access satellite node as the source node A, and write this node into the deterministic path node set P, that is, P={A};

S5.设置卫星网络除源节点A外的所有卫星节点的集合为Q={B,C,D},判断集合Q为非空,则进行步骤S6。S5. Set the set of all satellite nodes in the satellite network except the source node A as Q={B, C, D}, and judge that the set Q is not empty, then go to step S6.

S6.以任务接入时间为起始时间ts_start,根据业务传输时间Δt(M)、卫星节点缓存容量Buffer(u)以及卫星节点间连通时间Δtuv(ti,ti+m)的关系确定下一跳卫星节点。步骤S6具体为:S6. Taking the task access time as the starting time t s_start , according to the relationship between the service transmission time Δt(M), the satellite node buffer capacity Buffer(u) and the connection time between satellite nodes Δt uv (t i ,t i+m ) Determine the next hop satellite node. Step S6 is specifically:

S61根据步骤S4,寻路的起始节点为任务接入卫星源节点A,起始时间为任务接入时间t0,在这里为方便计算,假定业务量以链路容量进行满速率传输,则该任务业务量在该条卫星链路上的传输时间Δt(M)=2个单位时间,在该条卫星链路上的传输结束时间为t2。在与起始节点A所有连通的卫星节点(B,C)中,在LAB,LAC两条链路中,LAC链路不具有从t0时间开始的连通时间段,而LAB链路的连通时间段为[t0-t2],则ΔtAB(t0,t2)=Δt(M),满足该任务业务量在连通时间的连续区间内完成传输,tsk_end=t2,则将该卫星节点B作为当前的寻路节点,并写入确定性路径节点集合P中,即P={A,B},将卫星节点B从集合Q中删除,即Q={C,D}。S61 According to step S4, the starting node of the pathfinding is the task access satellite source node A, and the starting time is the task access time t 0 . Here, for the convenience of calculation, assuming that the traffic is transmitted at the full rate of the link capacity, then The transmission time of the task traffic on the satellite link is Δt(M)=2 unit times, and the transmission end time on the satellite link is t 2 . In the satellite nodes (B, C) that are all connected to the starting node A, in the two links of L AB and L AC , the link of L AC does not have a connection time period starting from time t 0 , and the link of L AB The connection time period of the road is [t 0 -t 2 ], then Δt AB (t 0 ,t 2 )=Δt(M), satisfying that the traffic of the task is transmitted within the continuous interval of the connection time, t sk_end =t 2 , then take the satellite node B as the current pathfinding node and write it into the deterministic path node set P, that is, P={A,B}, and delete the satellite node B from the set Q, that is, Q={C, D}.

S62根据步骤S61,当前寻路节点B,则为卫星网络中间节点k=B,与该节点相连通的下一跳卫星节点j=C,D。在与卫星节点B所有连通的卫星节点(C,D)中,其连续连通时间的起始时间tkj_start应满足ts_start<tkj_start≤tsk_end,连通时间应满足Δtkj(M)≥Δt(M)。S62 According to step S61, the current pathfinding node B is the satellite network intermediate node k=B, and the next-hop satellite nodes j=C, D connected to this node. In all satellite nodes (C, D) connected to satellite node B, the starting time t kj_start of its continuous connection time should satisfy t s_start <t kj_start ≤ t sk_end , and the connection time should satisfy Δt kj (M)≥Δt( M).

在LBC,LBD两条链路中,LBD链路的连通时间段为[t3-t5],t0<t3>t2,不满足传输条件。而LBC链路的连通时间段为[t1-t4],则ΔtBC(t1,t4)>Δt(M),并且t0<t1≤t2,其连续连通时间的起始时间为tkj_start=t1,tkj_end=t3,满足满足该任务业务量在连通时间的连续区间内完成传输,则将该卫星节点C作为当前的寻路节点,并写入确定性路径节点集合P中,即P={A,B,C},将卫星节点C从集合Q中删除,即Q={D}。In the two links of L BC and LBD , the connection time period of the LBD link is [t 3 -t 5 ], t 0 <t 3 >t 2 , which does not satisfy the transmission condition. And the connection time period of the L BC link is [t 1 -t 4 ], then Δt BC (t 1 ,t 4 )>Δt(M), and t 0 <t 1 ≤t 2 , the starting point of the continuous connection time is The starting time is t kj_start = t 1 , t kj_end = t 3 , and the task traffic is satisfied to complete the transmission within the continuous interval of the connection time, then the satellite node C is used as the current path-finding node and written into the deterministic path In the node set P, that is, P={A, B, C}, delete the satellite node C from the set Q, that is, Q={D}.

S63根据步骤S62,当前寻路节点C,则为卫星网络中间节点k=C,与该节点相连通的下一跳卫星节点j=D。在与卫星节点C所有连通的卫星节点D中,其连续连通时间的起始时间tkj_start应满足ts_start<tkj_start≤tsk_end,连通时间应满足Δtkj(M)≥Δt(M)。S63 According to step S62, the current pathfinding node C is the satellite network intermediate node k=C, and the next-hop satellite node j=D connected to this node. In satellite nodes D that are all connected to satellite node C, the starting time t kj_start of its continuous connection time should satisfy t s_start <t kj_start ≤ t sk_end , and the connection time should satisfy Δt kj (M)≥Δt(M).

LCD链路的连通时间段为[t0-t1]和[t2-t4],其中ΔtCD(t0,t1)<Δt(M),不满足传输条件。但ΔtCD(t2,t4)=Δt(M),并且t1<t2≤t3,其连续连通时间的起始时间为tkj_start=t2,tkj_end=t4,满足满足该任务业务量在连通时间的连续区间内完成传输,则将该卫星节点D作为当前的寻路节点,并写入确定性路径节点集合P中,即P={A,B,C,D},将卫星节点D从集合Q中删除,即

Figure BDA0003891589510000111
The connection time period of the LCD link is [t 0 -t 1 ] and [t 2 -t 4 ], where Δt CD (t 0 ,t 1 )<Δt(M), does not meet the transmission condition. But Δt CD (t 2 ,t 4 )=Δt(M), and t 1 <t 2 ≤t 3 , the starting time of its continuous connection time is t kj_start =t 2 , t kj_end =t 4 , satisfying the If the task traffic is transmitted within the continuous interval of the connection time, the satellite node D is used as the current pathfinding node and written into the deterministic path node set P, that is, P={A,B,C,D}, Delete the satellite node D from the set Q, namely
Figure BDA0003891589510000111

S64根据步骤S63得到的卫星节点j=D,即寻路到目的卫星节点,则寻路结束,进行步骤S7。S64 According to the satellite node j=D obtained in step S63, that is, the route is found to the destination satellite node, then the route finding ends, and step S7 is performed.

S7.判断确定性路径节点集合为P是否为最终确定性路径集合。D∈P,则寻路结束,该确定性路径节点集合P中的卫星节点按序组合成路径,即A→B→C→D,并记录该任务业务量在各节点间的传输时间,即为该路径的端到端确定性传输时延,该时延值为t4-t0=4个单位时间。S7. Determine whether the deterministic path node set P is the final deterministic path set. D∈P, then the pathfinding ends, the satellite nodes in the deterministic path node set P are combined into a path in sequence, that is, A→B→C→D, and the transmission time of the task traffic between nodes is recorded, namely is the end-to-end deterministic transmission delay of the path, and the delay value is t 4 −t 0 =4 unit times.

本发明说明书中未作详细描述的内容属本领域技术人员的公知技术。The content that is not described in detail in the description of the present invention belongs to the well-known technology of those skilled in the art.

本发明虽然已以较佳实施例公开如上,但其并不是用来限定本发明,任何本领域技术人员在不脱离本发明的精神和范围内,都可以利用上述揭示的方法和技术内容对本发明技术方案做出可能的变动和修改,因此,凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化及修饰,均属于本发明技术方案的保护范围。Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention, and any person skilled in the art can use the methods disclosed above and technical content to analyze the present invention without departing from the spirit and scope of the present invention. Possible changes and modifications are made in the technical solution. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention, which do not depart from the content of the technical solution of the present invention, all belong to the technical solution of the present invention. protected range.

Claims (10)

1.一种保证卫星网络端到端确定性时延的路径规划方法,其特征在于,包括:1. A path planning method that guarantees satellite network end-to-end deterministic delay, is characterized in that, comprises: 根据任务业务量和卫星链路容量计算传输时隙,并以此时隙对任务作用时间域进行划分,然后根据时隙内卫星网络节点的连通关系和连通时长建立卫星网络时空图;Calculate the transmission time slot according to the task traffic and satellite link capacity, and divide the task action time domain according to this time slot, and then establish the satellite network space-time diagram according to the connection relationship and connection duration of the satellite network nodes in the time slot; 以任务接入卫星节点作为第一跳起点,在所有连通的相邻节点中依据路径规划方法寻找下一跳路径节点,直至目的节点,由此获得卫星网络的确定性传输路径,从而形成具有确定性时延保证的卫星网络路径规划方法;Take the task access satellite node as the first hop starting point, find the next hop path node in all connected adjacent nodes according to the path planning method, until the destination node, thereby obtaining the deterministic transmission path of the satellite network, thus forming a deterministic Satellite network path planning method with permanent delay guarantee; 其中路径规划方法具体为:以任务业务量大小、卫星节点连通链路容量、卫星节点资源分配为约束条件,以业务传输起止时间与链路连通时间为判断条件,进行路径规划。The path planning method is specifically: taking the size of the task traffic, the link capacity of the satellite node connection, and the resource allocation of the satellite node as the constraint conditions, and taking the start and end time of the service transmission and the link connection time as the judgment conditions to perform path planning. 2.根据权利要求1所述的路径规划方法,其特征在于,以任务包含所有业务量的最大公约数vφ和星间链路容量参数C(t)计算基本单位时间τ;以此基本单位时间为时隙对任务作用时间域进行划分。2. path planning method according to claim 1, is characterized in that, comprises the greatest common divisor v φ of all traffic volumes and inter-satellite link capacity parameter C (t) with task and calculates basic unit time τ; With this basic unit Time is the time slot to divide the task action time domain. 3.根据权利要求1所述的路径规划方法,其特征在于,根据卫星网络时空图,能够得到任意两个卫星节点(u,v)在任意m个时刻之间(ti,ti+m)的连续连通时间Δtuv(ti,ti+m)。3. The path planning method according to claim 1, characterized in that, according to the satellite network space-time diagram, it is possible to obtain any two satellite nodes (u, v) between any m moments (t i , t i+m ) of continuous connection time Δt uv (t i ,t i+m ). 4.根据权利要求1至3中任一项所述的路径规划方法,其特征在于,路径规划方法具体为:4. The path planning method according to any one of claims 1 to 3, wherein the path planning method is specifically: 若寻路的起始节点为任务接入卫星源节点S,则起始时间为任务接入时间ts_start,根据起始节点与连通卫星节点间的链路容量C(s,k),计算出该任务业务量在该条卫星链路上的传输结束时间tsk_end,计算方法为:
Figure FDA0003891589500000011
则该任务业务量传输时间Δtsk(M)=tsk_end-ts_start,在集合Q中选取与起始节点所连通的卫星节点,若Δtsk(M)在卫星节点(s,k)连通时间的连续区间内,即Δtsk(M)≤Δtuv(ti,ti+m),u=s,v=k,ts_start≥ti,tsk_end≤ti+m,则将卫星节点k作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtsk(M)>Δtuv(ti,ti+m),u=s,v=k,即该任务业务量不能在卫星节点(s,k)连通时间的连续区间内完成传输,则卫星节点k不满足要求;
If the starting node of the pathfinding is the task access satellite source node S, then the starting time is the task access time t s_start , according to the link capacity C(s,k) between the starting node and the connected satellite node, calculate The transmission end time t sk_end of the task traffic on the satellite link is calculated as:
Figure FDA0003891589500000011
Then the task traffic transmission time Δt sk (M) = t sk_end -t s_start , select the satellite node connected to the starting node in the set Q, if Δt sk (M) is within the satellite node (s,k) connection time In the continuous interval of , that is, Δt sk (M)≤Δt uv (t i ,t i+m ), u=s,v=k,t s_start ≥t i ,t sk_end ≤t i+m , then the satellite node k as the current path-finding node, and write it into the deterministic path node set P, and delete this node from the set Q; if Δt sk (M)>Δt uv (t i ,t i+m ), u= s, v=k, that is, the task traffic cannot complete the transmission within the continuous interval of the satellite node (s, k) connection time, then the satellite node k does not meet the requirements;
若寻路的起始节点为卫星网络中间节点k,在集合Q中与该节点k相连通的下一跳卫星节点j,其连续连通时间的起始时间为tkj_start,ts_start<tkj_start≤tsk_end;根据起始节点与连通卫星节点间的链路容量C(k,j),计算出该任务业务量在该条卫星链路上的传输结束时间tkj_end,计算方法为:
Figure FDA0003891589500000021
同时满足节点k的缓存约束:
Figure FDA0003891589500000022
则该任务业务量传输时间Δtkj(M)=tkj_end-tkj_start,若Δtkj(M)在卫星节点(k,j)连通时间的连续区间内,即Δtkj(M)≤Δtuv(ti,ti+m),u=k,v=j,tkj_start≥ti,tkj_end≤ti+m,则将卫星节点j作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtkj(M)>Δtuv(ti,ti+m),u=k,v=j,则表示该任务业务量不能在卫星节点(k,j)连通时间的连续区间内完成传输,则卫星节点j不满足要求;
If the starting node of the pathfinding is the intermediate node k of the satellite network, the next hop satellite node j connected to the node k in the set Q, the starting time of its continuous connection time is t kj_start , t s_start <t kj_start ≤ t sk_end ; According to the link capacity C(k,j) between the starting node and the connected satellite node, calculate the transmission end time t kj_end of the task traffic on the satellite link, and the calculation method is:
Figure FDA0003891589500000021
Simultaneously satisfy the cache constraint of node k:
Figure FDA0003891589500000022
Then the task traffic transmission time Δt kj (M) = t kj_end -t kj_start , if Δt kj (M) is within the continuous interval of the satellite node (k, j) connection time, that is, Δt kj (M)≤Δt uv ( t i ,t i+m ),u=k,v=j,t kj_start ≥t i ,t kj_end ≤t i+m , then take the satellite node j as the current path-finding node and write it into the deterministic path node in the set P, and delete the node from the set Q; if Δt kj (M)>Δt uv (t i ,t i+m ), u=k, v=j, it means that the task traffic cannot be If the transmission is completed within the continuous interval of the connection time of node (k, j), the satellite node j does not meet the requirements;
若j=D,即寻路到目的卫星节点时,则寻路结束;若j≠D,即未寻路到目的卫星节点时,重新进行寻路。If j=D, that is, when the destination satellite node is found, the path finding ends; if j≠D, that is, when the destination satellite node is not found, the path finding is performed again.
5.一种保证卫星网络端到端确定性时延的路径规划方法,其特征在于,包括:5. A path planning method for ensuring end-to-end deterministic delay of a satellite network, characterized in that it comprises: S1、确定任务需求;确定不同时刻卫星网络星间链路容量参数C(t);S1. Determine the task requirements; determine the capacity parameter C(t) of the inter-satellite link of the satellite network at different times; S2、计算任务包含的所有业务传输的基本单位时间为时隙,计算基本单位时间τ,以此基本单位时间为时隙对任务作用时间域进行划分;S2. Calculate the basic unit time of all business transmissions included in the task as time slots, calculate the basic unit time τ, and use the basic unit time as time slots to divide the task action time domain; S3、获取任务作用时间域T内的所有卫星节点连通关系图;S3. Obtain the connectivity diagram of all satellite nodes in the task action time domain T; S4、设定确定性路径节点集合为P,以任务接入卫星节点为源节点S,将该节点写入确定性路径节点集合P;S4. Set the deterministic path node set as P, take the task access satellite node as the source node S, and write this node into the deterministic path node set P; S5、设置卫星网络除源节点S外的所有卫星节点为集合Q,并判断集合Q是否为空,若为空,则进行步骤S7;若非空,则进行步骤S6S5. Set all satellite nodes in the satellite network except the source node S as a set Q, and judge whether the set Q is empty, if it is empty, proceed to step S7; if not empty, proceed to step S6 S6、以任务接入时间为起始时间ts-start,根据业务传输时间Δt(M)、卫星节点缓存容量Buffer(u)以及卫星节点间连通时间Δtuv(ti,ti+m)的关系确定下一跳卫星节点;S6. Taking the task access time as the starting time t s-start , according to the service transmission time Δt(M), the satellite node buffer capacity Buffer(u) and the connection time between satellite nodes Δt uv (t i ,t i+m ) The relationship between determines the next hop satellite node; S7、判断确定性路径节点集合为P是否为最终的确定性路径集合;若目的卫星节点D在确定性路径节点集合P中,即D∈P,则寻路结束,该确定性路径节点集合P中的卫星节点按序组合成路径,并记录该任务业务量在各节点间的传输时间,即为该路径的端到端传输确定性时延;若
Figure FDA0003891589500000031
则表示不存在符合条件的路径,寻路结束。
S7. Determine whether the deterministic path node set P is the final deterministic path set; if the destination satellite node D is in the deterministic path node set P, that is, D∈P, then the pathfinding ends, and the deterministic path node set P The satellite nodes in the path are combined into paths in sequence, and the transmission time of the task traffic between each node is recorded, which is the end-to-end transmission deterministic delay of the path; if
Figure FDA0003891589500000031
It means that there is no path that meets the condition, and the pathfinding ends.
6.根据权利要求5所述的路径规划方法,其特征在于,任务需求包括任务业务量M、任务包含业务种类N、每种业务的业务量为Vi(i=1,2,…,N)、任务起始接入卫星节点S、任务目的卫星节点D、任务作用时间域T。6. The path planning method according to claim 5, wherein the task requirements include task traffic M, the task includes service category N, and the traffic of each kind of business is V i (i=1, 2, ..., N ), mission start access satellite node S, mission destination satellite node D, and mission action time domain T. 7.根据权利要求5所述的路径规划方法,其特征在于,根据任务作用时间域T内的所有卫星节点连通关系图,能够得到任意两个卫星节点(u,v)在任意m个时刻之间(ti,ti+m)的连续连通时间Δtuv(ti,ti+m),m∈(1,2,…,n)。7. The path planning method according to claim 5, characterized in that, according to the connectivity diagrams of all satellite nodes in the task action time domain T, any two satellite nodes (u, v) between any m moments can be obtained The continuous connection time Δt uv (t i ,t i+m ) between (t i ,t i+m ), m∈(1,2,…,n). 8.根据权利要求5所述的路径规划方法,其特征在于,以任务包含所有业务量的最大公约数vφ和星间链路容量参数C(t)计算基本单位时间τ。8. The path planning method according to claim 5, wherein the basic unit time τ is calculated with the greatest common divisor v φ of all traffic volumes included in the task and the capacity parameter C(t) of the inter-satellite link. 9.根据权利要求5至8中任一项所述的路径规划方法,其特征在于,步骤S6具体为:9. The path planning method according to any one of claims 5 to 8, characterized in that step S6 is specifically: S61、若寻路的起始节点为任务接入卫星源节点S,则起始时间为任务接入时间ts_start,根据起始节点与连通卫星节点间的链路容量C(s,k),计算出该任务业务量在该条卫星链路上的传输结束时间tsk_end,计算方法为:
Figure FDA0003891589500000041
则该任务业务量传输时间Δtsk(M)=tsk_end-ts_start,在集合Q中选取与起始节点所连通的卫星节点,若Δtsk(M)在卫星节点(s,k)连通时间的连续区间内,即Δtsk(M)≤Δtuv(ti,ti+m),u=s,v=k,ts_start≥ti,tsk_end≤ti+m,则将卫星节点k作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtsk(M)>Δtuv(ti,ti+m),u=s,v=k,即该任务业务量不能在卫星节点(s,k)连通时间的连续区间内完成传输,则卫星节点k不满足要求,返回步骤S5;
S61. If the starting node of the pathfinding is the task access satellite source node S, then the starting time is the task access time t s_start . According to the link capacity C(s,k) between the starting node and the connected satellite node, Calculate the transmission end time t sk_end of the task traffic on the satellite link, and the calculation method is:
Figure FDA0003891589500000041
Then the task traffic transmission time Δt sk (M) = t sk_end -t s_start , select the satellite node connected to the start node in the set Q, if Δt sk (M) is within the satellite node (s,k) connection time In the continuous interval of , that is, Δt sk (M)≤Δt uv (t i , t i+m ), u=s, v=k, t s_start ≥t i , t sk_end ≤t i+m , then the satellite node k as the current path-finding node, and write it into the deterministic path node set P, and delete this node from the set Q; if Δt sk (M)>Δt uv (t i ,t i+m ), u= s, v=k, that is, the task traffic cannot be transmitted within the continuous interval of the satellite node (s, k) connection time, then the satellite node k does not meet the requirements, and returns to step S5;
S62、若寻路的起始节点为卫星网络中间节点k,在集合Q中与该节点k相连通的下一跳卫星节点j,其连续连通时间的起始时间为tkj_start,ts_start<tkj_start≤tsk_end;根据起始节点与连通卫星节点间的链路容量C(k,j),计算出该任务业务量在该条卫星链路上的传输结束时间tkj_end,计算方法为:
Figure FDA0003891589500000042
同时满足节点k的缓存约束:
Figure FDA0003891589500000043
则该任务业务量传输时间Δtkj(M)=tkj_end-tkj_start,若Δtkj(M)在卫星节点(k,j)连通时间的连续区间内,即Δtkj(M)≤Δtuv(ti,ti+m),u=k,v=j,tkj_start≥ti,tkj_end≤ti+m,则将卫星节点j作为当前的寻路节点,并写入确定性路径节点集合P中,并将该节点从集合Q中删除;若Δtkj(M)>Δtuv(ti,ti+m),u=k,v=j,则表示该任务业务量不能在卫星节点(k,j)连通时间的连续区间内完成传输,则卫星节点j不满足要求,返回步骤S5;
S62. If the starting node of the pathfinding is the intermediate node k of the satellite network, the next hop satellite node j connected to the node k in the set Q, the starting time of its continuous connection time is t kj_start , t s_start <t kj_start ≤t sk_end ; According to the link capacity C(k,j) between the starting node and the connected satellite node, calculate the transmission end time t kj_end of the task traffic on the satellite link, and the calculation method is:
Figure FDA0003891589500000042
Simultaneously satisfy the cache constraint of node k:
Figure FDA0003891589500000043
Then the task traffic transmission time Δt kj (M) = t kj_end -t kj_start , if Δt kj (M) is within the continuous interval of the satellite node (k,j) connection time, that is, Δt kj (M)≤Δt uv ( t i ,t i+m ),u=k,v=j,t kj_start ≥t i ,t kj_end ≤t i+m , then take the satellite node j as the current path-finding node and write it into the deterministic path node in the set P, and delete the node from the set Q; if Δt kj (M)>Δt uv (t i ,t i+m ), u=k, v=j, it means that the task traffic cannot be If the transmission is completed within the continuous interval of the connection time of node (k, j), then the satellite node j does not meet the requirements, and returns to step S5;
S63若j=D,即寻路到目的卫星节点时,则寻路结束,进行步骤S7;若j≠D,即未寻路到目的卫星节点时,则返回步骤S5。S63 If j=D, that is, when the route is found to the destination satellite node, then the route finding ends, and proceed to step S7; if j≠D, that is, when the destination satellite node is not found, then return to step S5.
10.一种计算机可读存储介质,其上存储有计算机程序指令,所述计算机程序指令在由处理器加载并运行时,使所述处理器执行如权利要求1至3中任一项所述的方法。10. A computer-readable storage medium, on which computer program instructions are stored, and when the computer program instructions are loaded and run by a processor, the processor is executed as described in any one of claims 1 to 3. Methods.
CN202211262254.1A 2022-10-14 2022-10-14 Path planning method for guaranteeing end-to-end deterministic time delay of satellite network Active CN115801093B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211262254.1A CN115801093B (en) 2022-10-14 2022-10-14 Path planning method for guaranteeing end-to-end deterministic time delay of satellite network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211262254.1A CN115801093B (en) 2022-10-14 2022-10-14 Path planning method for guaranteeing end-to-end deterministic time delay of satellite network

Publications (2)

Publication Number Publication Date
CN115801093A true CN115801093A (en) 2023-03-14
CN115801093B CN115801093B (en) 2024-07-09

Family

ID=85433010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211262254.1A Active CN115801093B (en) 2022-10-14 2022-10-14 Path planning method for guaranteeing end-to-end deterministic time delay of satellite network

Country Status (1)

Country Link
CN (1) CN115801093B (en)

Citations (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040004939A1 (en) * 2002-07-03 2004-01-08 Ferit Yegenoglu Arrangement for evaluating network capacity, network utilization, and network efficiency in a communications network
US20080151811A1 (en) * 2006-12-20 2008-06-26 Hersham El-Damhougy Interplanetary communications network, interplanetary communications network backbone and method of managing interplanetary communications network
WO2012047880A2 (en) * 2010-10-04 2012-04-12 Telcordia Technologies, Inc. A method and system for determination of routes in leo satellite networks with bandwidth and priority awareness and adaptive rerouting
US20130100942A1 (en) * 2011-10-24 2013-04-25 Harris Corporation Mobile ad hoc network with dynamic tdma slot assignments and related methods
CN104361234A (en) * 2014-11-15 2015-02-18 北京理工大学 Method for optimizing multi-star multitask observation dispatching under complicated constraint condition
US20160037434A1 (en) * 2014-08-03 2016-02-04 Hughes Network Systems, Llc Centralized ground-based route determination and traffic engineering for software defined satellite communications networks
CN106100719A (en) * 2016-06-06 2016-11-09 西安电子科技大学 Moonlet network efficient resource dispatching method based on earth observation task
CN106209624A (en) * 2016-07-12 2016-12-07 哈尔滨工业大学深圳研究生院 Earth observation satellite network minimal-overhead method for routing based on space-time diagram
CN106789661A (en) * 2016-12-29 2017-05-31 北京邮电大学 A kind of information forwarding method and space information network system
CN107070794A (en) * 2016-12-08 2017-08-18 航天东方红卫星有限公司 A kind of low rail information network optimal network benefit delay constraint method for routing
CN107302396A (en) * 2017-07-10 2017-10-27 中国人民解放军国防科学技术大学 Network route planning method between dynamic star based on mixed strategy
CN107370536A (en) * 2017-07-19 2017-11-21 哈尔滨工业大学深圳研究生院 Satellite network multi-broadcast routing method and system based on minimum connected dominating set
CN108551398A (en) * 2017-09-30 2018-09-18 北京邮电大学 A kind of topology reconstruction method for Space laser communications quickly networking
CN109905281A (en) * 2019-03-24 2019-06-18 西安电子科技大学 Multi-path maximum throughput remote sensing service transmission method in constellation network
CN109951335A (en) * 2019-03-24 2019-06-28 西安电子科技大学 A Joint Guaranteed Routing Method for Satellite Network Delay and Rate Based on Time Aggregation Graph
CN110891317A (en) * 2019-10-29 2020-03-17 西南电子技术研究所(中国电子科技集团公司第十研究所) Method for allocating millimeter wave phased array antenna communication resources on demand
CN110896557A (en) * 2019-12-23 2020-03-20 北京邮电大学 Satellite communication routing method and device
CN111182583A (en) * 2020-01-05 2020-05-19 西安电子科技大学 Task delay constraint-oriented low-orbit satellite data transmission method
CN111817774A (en) * 2020-07-22 2020-10-23 西安电子科技大学 Inter-satellite multiple access method for low-orbit satellite network based on propagation delay
CN111835640A (en) * 2020-07-14 2020-10-27 中国电子科技集团公司第二十研究所 A Shortest Delay Routing Method Based on Continuous Time Aggregation Graph
CN113051815A (en) * 2021-03-18 2021-06-29 浙江大学 Agile imaging satellite task planning method based on independent pointer network
CN113238847A (en) * 2021-05-20 2021-08-10 西安电子科技大学 Distribution and scheduling method based on distributed network environment and capable of distributing tasks
CN113422636A (en) * 2021-06-18 2021-09-21 北京邮电大学 On-satellite routing optimization method
CN113572686A (en) * 2021-07-19 2021-10-29 大连大学 An adaptive dynamic QoS routing method based on SDN
CN113992259A (en) * 2021-10-22 2022-01-28 中国人民解放军63921部队 Method for constructing time slot resource expansion diagram
WO2022081830A1 (en) * 2020-10-14 2022-04-21 Georgia Tech Research Corporation A low-overhead online routing scheme for ultra-dense software-defined cubesat networks
CN114884557A (en) * 2022-03-25 2022-08-09 重庆邮电大学 Satellite time-sensitive network path selection method based on network calculation
CN115021793A (en) * 2022-04-27 2022-09-06 哈尔滨工业大学(威海) Method for planning inter-satellite link and distributing power of satellite network based on network coding

Patent Citations (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040004939A1 (en) * 2002-07-03 2004-01-08 Ferit Yegenoglu Arrangement for evaluating network capacity, network utilization, and network efficiency in a communications network
US20080151811A1 (en) * 2006-12-20 2008-06-26 Hersham El-Damhougy Interplanetary communications network, interplanetary communications network backbone and method of managing interplanetary communications network
WO2012047880A2 (en) * 2010-10-04 2012-04-12 Telcordia Technologies, Inc. A method and system for determination of routes in leo satellite networks with bandwidth and priority awareness and adaptive rerouting
US20130100942A1 (en) * 2011-10-24 2013-04-25 Harris Corporation Mobile ad hoc network with dynamic tdma slot assignments and related methods
US20160037434A1 (en) * 2014-08-03 2016-02-04 Hughes Network Systems, Llc Centralized ground-based route determination and traffic engineering for software defined satellite communications networks
CN104361234A (en) * 2014-11-15 2015-02-18 北京理工大学 Method for optimizing multi-star multitask observation dispatching under complicated constraint condition
CN106100719A (en) * 2016-06-06 2016-11-09 西安电子科技大学 Moonlet network efficient resource dispatching method based on earth observation task
CN106209624A (en) * 2016-07-12 2016-12-07 哈尔滨工业大学深圳研究生院 Earth observation satellite network minimal-overhead method for routing based on space-time diagram
CN107070794A (en) * 2016-12-08 2017-08-18 航天东方红卫星有限公司 A kind of low rail information network optimal network benefit delay constraint method for routing
CN106789661A (en) * 2016-12-29 2017-05-31 北京邮电大学 A kind of information forwarding method and space information network system
CN107302396A (en) * 2017-07-10 2017-10-27 中国人民解放军国防科学技术大学 Network route planning method between dynamic star based on mixed strategy
CN107370536A (en) * 2017-07-19 2017-11-21 哈尔滨工业大学深圳研究生院 Satellite network multi-broadcast routing method and system based on minimum connected dominating set
CN108551398A (en) * 2017-09-30 2018-09-18 北京邮电大学 A kind of topology reconstruction method for Space laser communications quickly networking
CN109951335A (en) * 2019-03-24 2019-06-28 西安电子科技大学 A Joint Guaranteed Routing Method for Satellite Network Delay and Rate Based on Time Aggregation Graph
CN109905281A (en) * 2019-03-24 2019-06-18 西安电子科技大学 Multi-path maximum throughput remote sensing service transmission method in constellation network
CN110891317A (en) * 2019-10-29 2020-03-17 西南电子技术研究所(中国电子科技集团公司第十研究所) Method for allocating millimeter wave phased array antenna communication resources on demand
CN110896557A (en) * 2019-12-23 2020-03-20 北京邮电大学 Satellite communication routing method and device
CN111182583A (en) * 2020-01-05 2020-05-19 西安电子科技大学 Task delay constraint-oriented low-orbit satellite data transmission method
CN111835640A (en) * 2020-07-14 2020-10-27 中国电子科技集团公司第二十研究所 A Shortest Delay Routing Method Based on Continuous Time Aggregation Graph
CN111817774A (en) * 2020-07-22 2020-10-23 西安电子科技大学 Inter-satellite multiple access method for low-orbit satellite network based on propagation delay
WO2022081830A1 (en) * 2020-10-14 2022-04-21 Georgia Tech Research Corporation A low-overhead online routing scheme for ultra-dense software-defined cubesat networks
CN113051815A (en) * 2021-03-18 2021-06-29 浙江大学 Agile imaging satellite task planning method based on independent pointer network
CN113238847A (en) * 2021-05-20 2021-08-10 西安电子科技大学 Distribution and scheduling method based on distributed network environment and capable of distributing tasks
CN113422636A (en) * 2021-06-18 2021-09-21 北京邮电大学 On-satellite routing optimization method
CN113572686A (en) * 2021-07-19 2021-10-29 大连大学 An adaptive dynamic QoS routing method based on SDN
CN113992259A (en) * 2021-10-22 2022-01-28 中国人民解放军63921部队 Method for constructing time slot resource expansion diagram
CN114884557A (en) * 2022-03-25 2022-08-09 重庆邮电大学 Satellite time-sensitive network path selection method based on network calculation
CN115021793A (en) * 2022-04-27 2022-09-06 哈尔滨工业大学(威海) Method for planning inter-satellite link and distributing power of satellite network based on network coding

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
SUNYUE GENG: "An optimal delay routing algorithm considering delay variation in the LEO satellite communication network", 《COMPUTER NETWORKS》, 4 March 2020 (2020-03-04) *
WANG BO: "Performance analysis of OSPF in integrated satellite and terrestrial networks", 《2022 INTERNATIONAL SYMPOSIUM ON NETWORKS, COMPUTERS AND COMMUNICATIONS(ISNCC)》, 15 August 2022 (2022-08-15) *
曾鹏程: "时间确定性网络多路径路由算法与协议研究", 《中国优秀硕士学位论文全文数据库-信息科技辑》, 15 April 2022 (2022-04-15) *
李静玲等: "集群卫星网络信息拓扑控制技术探讨", 《空间电子技术》, 25 April 2022 (2022-04-25) *
王鹏: "基于随机时变图的时间确定性网络路由算法", 《通信学报》, 26 July 2021 (2021-07-26) *
雷柳: "基于图模型的DTN网络路由算法研究", 《中国优秀硕士学位论文全文数据库-信息科技辑》, 26 May 2017 (2017-05-26) *

Also Published As

Publication number Publication date
CN115801093B (en) 2024-07-09

Similar Documents

Publication Publication Date Title
Jain et al. Routing in a delay tolerant network
CN107346988A (en) A kind of appearance based on low-track satellite network late/hold circuit network route computing method
US20160065449A1 (en) Bandwidth-Weighted Equal Cost Multi-Path Routing
CN109951335A (en) A Joint Guaranteed Routing Method for Satellite Network Delay and Rate Based on Time Aggregation Graph
CN107294852A (en) A kind of network route method using the scattered short path collection of topology
CN112261681B (en) Low earth orbit satellite DTN network routing path selection method and system
CN113992259B (en) Method for constructing time slot resource expansion graph
Frikha Ad Hoc Networks: Routing, QoS and Optimization
Chen et al. ADA-QKDN: A new quantum key distribution network routing scheme based on application demand adaptation
CN100512231C (en) Routing method
Dai et al. Contact plan design with directional space-time graph in two-layer space communication networks
CN106888492B (en) Satellite network routing method with load-aware cache-constrained intermittent connectivity
CN104158736B (en) A kind of method and apparatus for determining next-hop, issuing routing iinformation
CN108365886B (en) Time division multiplexing inter-satellite network data storing and forwarding method
CN115801093A (en) A path planning method to guarantee the end-to-end deterministic delay of satellite network
CN106792971A (en) Network node system of selection based on ant group algorithm
CN111835640B (en) Shortest time delay routing method based on continuous time aggregation graph
CN105656803B (en) A kind of space delay tolerant network jamming control method based on QoS
CN115206086A (en) Static traffic flow distribution method considering congestion space queuing and overflow
CN100442758C (en) Multicast transfer route setting method, and multicast label switching method for implementing former method
Chenji et al. Raven: Energy aware qos control for drns
WO2018205887A1 (en) Delay collection method and apparatus
Sarangan et al. Capacity-aware state aggregation for interdomain QoS routing
Liu et al. QoS in node-disjoint routing for ad hoc networks
Liu et al. An improved contact graph routing algorithm based on delay constraints

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant