CN115795598A - BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium - Google Patents

BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium Download PDF

Info

Publication number
CN115795598A
CN115795598A CN202211368523.2A CN202211368523A CN115795598A CN 115795598 A CN115795598 A CN 115795598A CN 202211368523 A CN202211368523 A CN 202211368523A CN 115795598 A CN115795598 A CN 115795598A
Authority
CN
China
Prior art keywords
plan
construction plan
current task
bim
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211368523.2A
Other languages
Chinese (zh)
Inventor
徐荣梅
杨奇
王亚康
韩雯靖
熊文文
张文露
胡宋舒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI JIANKE ENGINEERING CONSULTING CO LTD
Original Assignee
SHANGHAI JIANKE ENGINEERING CONSULTING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI JIANKE ENGINEERING CONSULTING CO LTD filed Critical SHANGHAI JIANKE ENGINEERING CONSULTING CO LTD
Priority to CN202211368523.2A priority Critical patent/CN115795598A/en
Publication of CN115795598A publication Critical patent/CN115795598A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium, and belongs to the field of constructional engineering. The method comprises the following steps: establishing a BIM model of a current task and compiling a construction plan of the current task; according to the mapping relation, the BIM of the current task is associated with the construction plan of the current task; judging whether the BIM model of the current task is changed or not and judging whether the construction plan of the current task is changed or not; if the BIM model of the current task is changed, updating the construction plan of the current task according to the changed BIM model and the mapping relation; if the construction plan of the current task changes, updating the BIM model of the current task through a BIM-based control platform according to the changed construction plan and the mapping relation; and guiding engineering construction according to the updated construction plan or the changed construction plan. The invention provides consistency of the BIM model with the actual construction plan.

Description

BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium
Technical Field
The invention relates to the field of constructional engineering, in particular to a BIM model and construction plan bidirectional linkage method, system, equipment and medium.
Background
A Building Information Modeling (BIM) is an important technical means for digital management in the Building field, and supports Information sharing and cooperative work of numerous participating parties in each stage and among the stages through the whole life cycle of a whole Building from planning and designing to engineering construction to operation and maintenance. In actual work, a design side provides a BIM model to a construction unit, and the construction unit deepens the model and associates the model with a progress plan to guide engineering construction. However, in the construction process, not only the designed BIM model is changed for many times, but also the construction plan is changed, the change of the BIM model cannot be timely updated to the construction plan, and the change of the construction plan cannot be timely updated to the BIM model, so that the BIM model cannot be consistent with the actual construction plan, and the construction work cannot be effectively guided.
Disclosure of Invention
The invention aims to provide a BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium, so as to solve the problem that the BIM model in the prior art cannot be consistent with an actual construction plan.
In order to achieve the purpose, the invention provides the following scheme:
a BIM model and construction plan bidirectional linkage method comprises the following steps:
creating a BIM model of the current task and compiling a construction plan of the current task;
associating the BIM model of the current task with the construction plan of the current task according to the mapping relation; the mapping relation is the mapping relation between the BIM model and the construction plan; the mapping relation is constructed according to an initial BIM model and an initial construction plan;
judging whether the BIM model of the current task is changed or not, and judging whether the construction plan of the current task is changed or not;
if the BIM model of the current task is changed, updating the construction plan of the current task according to the changed BIM model and the mapping relation;
if the construction plan of the current task changes, updating the BIM model of the current task through a BIM-based control platform according to the changed construction plan and the mapping relation;
and guiding engineering construction according to the updated construction plan or the changed construction plan.
Optionally, the method further comprises:
and if the BIM model is not changed and the construction plan is not changed, guiding engineering construction according to the BIM model and the construction plan.
Optionally, the mapping relationship is constructed according to the initial BIM model and the initial construction plan, and specifically includes:
acquiring an initial BIM model and an initial construction plan;
decomposing the initial BIM model into a plurality of components;
decomposing the initial construction plan into a plurality of inspection lots;
and associating the component with the inspection batch by using the task number to obtain a mapping relation.
Optionally, the change condition of the BIM model of the current task includes a model component information change;
the model component information change comprises component design parameter modification, component adding, component deleting, component combination model group and component model group splitting.
Optionally, the change condition of the construction plan of the current task includes a plan time change and a plan content change; the plan content change includes an addition plan, a deletion plan, and a construction content change included in the plan.
Optionally, the updating the construction plan of the current task according to the changed BIM model and the mapping relationship specifically includes:
if the change condition is modification of component design parameters, not updating the construction plan of the current task;
if the changed condition is a newly added component, adding a plan associated with the newly added component in the construction plan of the current task according to the mapping relation, or associating the newly added component to an existing construction plan;
if the change condition is the deletion of the component, deleting the component in the construction plan of the current task according to the mapping relation;
if the change condition is a component combination model group, deleting a plan related to the construction before combination, adding a plan of a component combination model group in the construction plan of the current task according to the mapping relation, or relating the added component combination model group to the existing construction plan;
and if the change condition is that the component model group is split, deleting the plan associated with the model group from the construction plan of the current task according to the mapping relation, adding a plan associated with the split component, or associating the split component to the existing construction plan.
Optionally, the updating, according to the changed construction plan and the mapping relationship, the BIM model of the current task through a BIM-based management and control platform specifically includes:
if the change condition is the change of the plan time, updating a component time attribute associated with the time-changed plan in the BIM model of the current task through the BIM-based control platform according to the mapping relation;
if the change condition is a new plan, adding a member related to the new plan in the BIM model of the current task through the BIM-based control platform according to the mapping relation;
if the change condition is a deletion plan, releasing a component associated with the deletion plan into an empty task in the BIM model of the current task through the BIM-based control platform according to the mapping relation;
and if the change situation is the change of the construction content contained in the plan, deleting the components related to the construction content contained in the plan before the change in the BIM model of the current task according to the mapping relation, and adding the components related to the construction content contained in the plan after the change.
A BIM model and construction plan bi-directional linkage system, comprising:
the model creating and planning module is used for creating a BIM model of the current task and planning a construction plan of the current task;
the correlation module is used for correlating the BIM model of the current task with the construction plan of the current task according to the mapping relation; the mapping relation is the mapping relation between the BIM and the construction plan; the mapping relation is constructed according to an initial BIM model and an initial construction plan;
the judging module is used for judging whether the BIM model of the current task is changed or not and judging whether the construction plan of the current task is changed or not;
the first updating module is used for updating the construction plan of the current task according to the changed BIM and the mapping relation if the BIM of the current task is changed;
the second updating module is used for updating the BIM model of the current task through a BIM-based control platform according to the changed construction plan and the mapping relation if the construction plan of the current task is changed;
and the guiding module is used for guiding engineering construction according to the updated construction plan or the changed construction plan.
An electronic device, comprising: the memory is used for storing a computer program, and the processor runs the computer program to enable the electronic equipment to execute the BIM model and construction plan bidirectional linkage method.
A computer-readable storage medium storing a computer program which, when executed by a processor, implements the above-described BIM model and construction plan bidirectional linkage method.
According to the specific embodiment provided by the invention, the invention discloses the following technical effects:
the invention provides a bidirectional linkage method of a BIM model and a construction plan, which comprises the steps of establishing a BIM model of a current task and compiling the construction plan of the current task; associating the BIM model of the current task with the construction plan of the current task according to the mapping relation; judging whether the BIM model of the current task is changed or not, and judging whether the construction plan of the current task is changed or not; if the BIM of the current task is changed, updating the construction plan of the current task according to the changed BIM and the mapping relation; if the construction plan of the current task changes, updating the BIM model of the current task through a BIM-based control platform according to the changed construction plan and the mapping relation; and guiding engineering construction according to the updated construction plan or the changed construction plan. The invention transmits the change of the BIM model to the construction plan without damage through the mapping relation, and keeps the correlation between the change of the construction plan and the BIM model, so that the BIM model is kept consistent with the actual construction plan, the problems that the change of the BIM model cannot be timely updated to the construction plan and the change of the construction plan cannot be timely updated to the BIM model are avoided, the BIM model and the actual construction plan effectively guide the construction work in the engineering construction, and the value of BIM cooperative work is really realized.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without inventive exercise.
FIG. 1 is a flow chart of a bi-directional linkage method of a BIM model and a construction plan provided by the invention;
FIG. 2 is a flow chart of the method of the present invention in practical application;
fig. 3 is a schematic diagram of mapping relationship construction.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
The invention aims to provide a bidirectional linkage method of a BIM (building information modeling) model and a construction plan, and aims to solve the problem that the BIM model and the actual construction plan in the prior art cannot be consistent.
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in further detail below.
Example one
FIG. 1 is a flow chart of a bi-directional linkage method of a BIM model and a construction plan provided by the present invention; FIG. 2 is a flow chart of the method of the present invention in practical application; as shown in fig. 1 and 2, the bi-directional linkage method of the BIM model and the construction plan of the present invention includes:
step 101: and creating a BIM model of the current task and compiling a construction plan of the current task.
In practical application, the BIM model is divided into an independent model file, a combined model file and a model unit contained by the model. The construction plan should be refined to the planned construction time for each inspection lot.
The BIM model should have project information, identity information, positioning information, system information, and technical information. The identity information consists of identification information and a unique code. The identification information may be reused, such as component type and process attributes.
Step 102: associating the BIM model of the current task with the construction plan of the current task according to the mapping relation; the mapping relation is the mapping relation between the BIM and the construction plan; and the mapping relation is constructed according to the initial BIM model and the initial construction plan. In practical application, the BIM model is associated with a control plan (construction plan) according to the mapping relation, and the BIM model is uploaded to a BIM-based control platform, so that engineering implementation is known.
Further, the mapping relationship is constructed according to the initial BIM model and the initial construction plan, and specifically includes:
and acquiring an initial BIM model and an initial construction plan.
Decomposing the initial BIM model into a plurality of components.
Decomposing the initial construction plan into a plurality of inspection lots.
And associating the component with the inspection batch by using the task number to obtain a mapping relation.
In actual application, a mapping relationship is constructed, as shown in fig. 3. The method comprises the steps of carrying out model decomposition on a BIM model, decomposing the BIM model into a floor and a professional system, obtaining a plurality of members according to the floor and the professional system, carrying out engineering decomposition on an engineering entity, sequentially decomposing the engineering entity into unit engineering, subsection engineering and project division, finally obtaining a plurality of inspection batches, and associating the members with the inspection batches through task numbers. One task may correspond to 1 to n inspection lots, such as: 1 cast-in-situ bored pile task corresponds to 1 pile foundation inspection lot, and 1 concrete structure task corresponds to 5 inspection lots of a template, a reinforcing steel bar, prestress, concrete pouring and cast-in-situ structure; one task may correspond to 1 to n members, for example, 1 bored pile task corresponds to 1 pile foundation member, and 1 concrete structure task corresponds to a plurality of floors, beams, and columns. The inspection batch comprises a construction plan, an inspection batch number and design parameters; the component includes engineering information, component coding, and geometric information.
Step 103: and judging whether the BIM model of the current task is changed or not, and judging whether the construction plan of the current task is changed or not.
Step 104: and if the BIM model of the current task is changed, updating the construction plan of the current task according to the changed BIM model and the mapping relation.
And the change condition of the BIM of the current task comprises model component information change and model file information change. The model component information change comprises component design parameter modification, component addition, component deletion, component combination model group and component model group splitting.
Wherein, the modification of the component design parameters comprises the change of positioning information, system information and technical information. If the identity information changes, the change is classified as the deletion and the addition of one component of the original component.
The newly added component is a component which is newly added with unique identity information; deleting the component, namely deleting the unique identity information; the component combination model group is to combine a plurality of components with unique identity information into a new model group with unique identity information, and the unique identity information of each component before combination needs to be deleted; the component model group splitting is to split a component model group with unique identity information into a plurality of components with unique identity information, the unique identity information of the split model group needs to be deleted, and the unique identity information of each split component is newly added; the addition and the reduction of the components in the model group only affect the design parameters of the model group and do not affect the unique identity information.
Further, the step 104 specifically includes:
and if the change condition is the modification of the component design parameters, not updating the construction plan of the current task.
And if the changed condition is a new component, adding a plan associated with the new component in the construction plan of the current task according to the mapping relation, or associating the new component to the existing construction plan.
And if the change condition is that a component is deleted, deleting the component in the construction plan of the current task according to the mapping relation.
And if the change condition is a component combination model group, deleting a plan related to the construction before combination, adding a plan of a component combination model group in the construction plan of the current task according to the mapping relation, or relating the added component combination model group to the existing construction plan.
And if the change condition is that the component model group is split, deleting the plan associated with the model group from the construction plan of the current task according to the mapping relation, adding the plan associated with the split component, or associating the split component to the existing construction plan.
In practical application, the attributes of the changed BIM model are extracted and then updated to the construction plan. Specifically, the component which has not changed the unique identity information inherits the original plan attribute. The change of the unique identity information occurs: the method comprises the following steps: (1) adding a new component, and adding unique identity information of an unallocated plan; (2) deleting the component, and deleting the plan associated with the component represented by the unique identity information in the construction plan; (3) the model group is combined, the unique identity information of each component before combination is deleted in the plan, and the unique identity information of the model group to be distributed is newly added; (4) and (3) component model group splitting: and deleting the unique identity information of the model group before splitting in the plan, and adding the unique identity information of each component to be distributed.
Step 105: and if the construction plan of the current task changes, updating the BIM model of the current task through a BIM-based control platform according to the changed construction plan and the mapping relation. The change condition of the construction plan of the current task comprises a plan time change and a plan content change; the plan content change comprises an addition plan, a deletion plan and construction content change contained in the plans.
Further, the step 105 specifically includes:
and if the change condition is the plan time change, updating the component time attribute associated with the plan of the time change in the BIM model of the current task through a BIM-based control platform according to the mapping relation.
And if the change condition is a new added plan, adding a member related to the new added plan in the BIM model of the current task through a BIM-based control platform according to the mapping relation.
And if the change condition is a deletion plan, releasing a component associated with the deletion plan into an empty task in the BIM model of the current task through a BIM-based control platform according to the mapping relation.
And if the change situation is the change of the construction content contained in the plan, deleting the components related to the construction content contained in the plan before the change in the BIM model of the current task according to the mapping relation, and adding the components related to the construction content contained in the plan after the change.
In practical applications, the planning time is changed only by adjusting the planning time, and the attribute of the BIM model can be changed accordingly. The changes in the plan content include addition plans, deletion plans, and changes in the construction content included in the plans. The newly added plans can be automatically associated only by hanging the members of the BIM model to the construction plan; after the plan is deleted, all components related to the plan are automatically released; the change of construction content contained in the plan requires that the original components not in the new plan are deleted, the newly added components are hooked, and the original components are reserved. The updating of the construction plan in the BIM model can be realized.
Step 106: and guiding engineering construction according to the updated construction plan or the changed construction plan. And forming a completion BIM (completion model) and control data until completion of the project, and storing the completion BIM and the control data into a completion file.
And if the BIM model is not changed and the construction plan is not changed, guiding engineering construction according to the BIM model of the current task and the construction plan of the current task.
Example two
In order to implement a corresponding method of the above embodiment to achieve corresponding functions and technical effects, the following provides a bi-directional linkage system of a BIM model and a construction plan, including:
and the model creating and planning module is used for creating a BIM model of the current task and planning a construction plan of the current task.
The association module is used for associating the BIM model of the current task with the construction plan of the current task according to the mapping relation; the mapping relation is the mapping relation between the BIM and the construction plan; and the mapping relation is constructed according to the initial BIM model and the initial construction plan.
And the judging module is used for judging whether the BIM model of the current task is changed or not and judging whether the construction plan of the current task is changed or not.
And the first updating module is used for updating the construction plan of the current task according to the changed BIM and the mapping relation if the BIM of the current task is changed.
And the second updating module is used for updating the BIM model of the current task through the BIM-based control platform according to the changed construction plan and the mapping relation if the construction plan of the current task is changed.
And the guiding module is used for guiding engineering construction according to the updated construction plan and/or the updated BIM model.
EXAMPLE III
The present invention also provides an electronic device, comprising: the memory is used for storing a computer program, and the processor runs the computer program to enable the electronic equipment to execute the BIM model and construction plan bidirectional linkage method in the first embodiment.
Example four
The invention also provides a computer readable storage medium, which stores a computer program, and when the computer program is executed by a processor, the BIM model and construction plan bidirectional linkage method of the first embodiment is realized.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. For the system disclosed by the embodiment, the description is relatively simple because the system corresponds to the method disclosed by the embodiment, and the relevant points can be referred to the description of the method part.
The principles and embodiments of the present invention have been described herein using specific examples, which are provided only to help understand the method and the core concept of the present invention; meanwhile, for a person skilled in the art, according to the idea of the present invention, the specific embodiments and the application range may be changed. In view of the above, the present disclosure should not be construed as limiting the invention.

Claims (10)

1. A BIM model and construction plan bidirectional linkage method is characterized by comprising the following steps:
creating a BIM model of the current task and compiling a construction plan of the current task;
associating the BIM model of the current task with the construction plan of the current task according to the mapping relation; the mapping relation is the mapping relation between the BIM model and the construction plan; the mapping relation is constructed according to the initial BIM model and the initial construction plan;
judging whether the BIM model of the current task is changed or not, and judging whether the construction plan of the current task is changed or not;
if the BIM model of the current task is changed, updating the construction plan of the current task according to the changed BIM model and the mapping relation;
if the construction plan of the current task changes, updating the BIM model of the current task through a BIM-based control platform according to the changed construction plan and the mapping relation;
and guiding engineering construction according to the updated construction plan or the changed construction plan.
2. The BIM model and construction plan bidirectional linkage method according to claim 1, further comprising:
and if the BIM model is not changed and the construction plan is not changed, guiding engineering construction according to the BIM model and the construction plan.
3. The BIM and construction plan bidirectional linkage method according to claim 1, wherein the mapping relationship is constructed according to an initial BIM and an initial construction plan, and specifically comprises:
acquiring an initial BIM model and an initial construction plan;
decomposing the initial BIM model into a plurality of components;
decomposing the initial construction plan into a plurality of inspection lots;
and associating the component with the inspection batch by using the task number to obtain a mapping relation.
4. The BIM and construction plan bidirectional linkage method according to claim 1, wherein the change condition of the BIM of the current task includes a model component information change;
the model component information change comprises component design parameter modification, component adding, component deleting, component combination model group and component model group splitting.
5. The BIM model and construction plan bidirectional linkage method according to claim 1, wherein the change condition of the construction plan of the current task includes a plan time change and a plan content change; the plan content change comprises an addition plan, a deletion plan and construction content change contained in the plans.
6. The BIM model and construction plan bidirectional linkage method according to claim 4, wherein the updating of the construction plan of the current task according to the changed BIM model and the mapping relationship specifically comprises:
if the change condition is modification of component design parameters, not updating the construction plan of the current task;
if the changed condition is a newly added component, adding a plan associated with the newly added component in the construction plan of the current task according to the mapping relation, or associating the newly added component to an existing construction plan;
if the change condition is the deletion of the component, deleting the component in the construction plan of the current task according to the mapping relation;
if the change condition is a component combination model group, deleting a plan related to the construction before combination, adding a plan of a component combination model group in the construction plan of the current task according to the mapping relation, or relating the added component combination model group to the existing construction plan;
and if the change condition is that the component model group is split, deleting the plan associated with the model group from the construction plan of the current task according to the mapping relation, adding the plan associated with the split component, or associating the split component to the existing construction plan.
7. The BIM model and construction plan bidirectional linkage method according to claim 5, wherein the step of updating the BIM model of the current task through a BIM-based management and control platform according to the changed construction plan and the mapping relationship specifically comprises the steps of:
if the change condition is plan time change, updating a component time attribute associated with the time change plan in the BIM model of the current task through the BIM-based control platform according to the mapping relation;
if the change condition is a newly added plan, according to the mapping relation, newly adding a component related to the newly added plan in the BIM model of the current task through the BIM-based control platform;
if the change condition is a deletion plan, releasing a component associated with the deletion plan into an empty task in the BIM model of the current task through the BIM-based control platform according to the mapping relation;
and if the change situation is the change of the construction content contained in the plan, deleting the components related to the construction content contained in the plan before the change in the BIM model of the current task according to the mapping relation, and adding the components related to the construction content contained in the plan after the change.
8. The utility model provides a BIM model and construction plan bidirectional linkage system which characterized in that includes:
the model creating and planning module is used for creating a BIM model of the current task and planning a construction plan of the current task;
the association module is used for associating the BIM model of the current task with the construction plan of the current task according to the mapping relation; the mapping relation is the mapping relation between the BIM model and the construction plan; the mapping relation is constructed according to the initial BIM model and the initial construction plan;
the judging module is used for judging whether the BIM model of the current task is changed or not and judging whether the construction plan of the current task is changed or not;
the first updating module is used for updating the construction plan of the current task according to the changed BIM and the mapping relation if the BIM of the current task is changed;
the second updating module is used for updating the BIM model of the current task through the BIM-based control platform according to the changed construction plan and the mapping relation if the construction plan of the current task is changed;
and the guiding module is used for guiding the engineering construction according to the updated construction plan or the changed construction plan.
9. An electronic device, comprising: a memory for storing a computer program and a processor for operating the computer program to cause the electronic device to perform the BIM model and construction plan bi-directional linkage method of any one of claims 1-7.
10. A computer-readable storage medium, wherein a computer program is stored, and when executed by a processor, the computer program implements the BIM model and construction plan bidirectional linkage method according to any one of claims 1 to 7.
CN202211368523.2A 2022-11-03 2022-11-03 BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium Pending CN115795598A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211368523.2A CN115795598A (en) 2022-11-03 2022-11-03 BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211368523.2A CN115795598A (en) 2022-11-03 2022-11-03 BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium

Publications (1)

Publication Number Publication Date
CN115795598A true CN115795598A (en) 2023-03-14

Family

ID=85435201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211368523.2A Pending CN115795598A (en) 2022-11-03 2022-11-03 BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium

Country Status (1)

Country Link
CN (1) CN115795598A (en)

Similar Documents

Publication Publication Date Title
CN110362887B (en) Revit-based rapid modeling method
CN109785436B (en) BIM technology-based reinforcing steel bar information full life cycle management method
CN111400812A (en) BIM-based method for designing machining drawing of assembled structure shear wall
CN113934684B (en) Data format automatic conversion method and device, electronic equipment and storage medium
CN113051650B (en) Real-time acquisition method and device for building information model component data
CN112784340B (en) Conversion method and conversion device for construction BIM model
CN112560134A (en) Batch deepening design method of assembled structure laminated slab based on CAD and BIM
Laurini et al. Technology 4.0 for buildings management: from building site to the interactive building book
CN111581700A (en) Method for adding BIM attribute and outputting BIM attribute table based on CATIA model
CN109977481B (en) Method for creating concrete assembly template and member steel bar based on CATIA
CN117112515A (en) Tunnel design and construction information sharing method, device, equipment and storage medium
CN115795598A (en) BIM (building information modeling) model and construction plan bidirectional linkage method, system, equipment and medium
Lapidus et al. Development software for the non-destructive control of monolithic structures in housing construction
CN116663098A (en) Construction scene graphical management method and device based on BIM
CN116541929A (en) Construction method of parameterized BIM model of outdoor storage yard civil engineering standardization unit
CN114077765A (en) Dynamo project data management method and device and computer equipment
CN111753348B (en) Method and device for deepening building data model component and readable storage medium
CN114896677A (en) Construction simulation method and system based on BIM model
CN113919033A (en) Method and device for determining steel bar throwing in construction section
CN113434937A (en) Method, apparatus, device and medium for converting design model into computation model
CN111753344A (en) Generation method of assembly type component data set, CAD platform and storage medium
Ma et al. An automation tool for exporting structure models from Revit to Tekla Structure
CN115965207B (en) Resource allocation method, system and storage medium
Salim et al. Design-integrated process planner for rebar placement
CN111753343B (en) Window-based assembly type component data set creation method, device and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination