CN115760250A - Engineering cost compiling method and device, electronic equipment and storage medium - Google Patents

Engineering cost compiling method and device, electronic equipment and storage medium Download PDF

Info

Publication number
CN115760250A
CN115760250A CN202211468179.4A CN202211468179A CN115760250A CN 115760250 A CN115760250 A CN 115760250A CN 202211468179 A CN202211468179 A CN 202211468179A CN 115760250 A CN115760250 A CN 115760250A
Authority
CN
China
Prior art keywords
target
cost
algorithm
construction
compilation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211468179.4A
Other languages
Chinese (zh)
Inventor
张学清
王景彤
张家坤
张菊梅
张腾超
息利琳
马赫
许双全
孙浩跃
王堃
戚梦君
李希稷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Weifang Pumped Storage Co ltd
State Grid Xinyuan Co Ltd
Original Assignee
Shandong Weifang Pumped Storage Co ltd
State Grid Xinyuan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Weifang Pumped Storage Co ltd, State Grid Xinyuan Co Ltd filed Critical Shandong Weifang Pumped Storage Co ltd
Priority to CN202211468179.4A priority Critical patent/CN115760250A/en
Publication of CN115760250A publication Critical patent/CN115760250A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method and a device for compiling engineering cost, electronic equipment and a storage medium, wherein the method comprises the following steps: acquiring a project cost establishment task of a target pumped storage power station, wherein the project cost establishment task comprises the following steps: a target construction stage corresponding to the target pumped storage power station at present; acquiring a reference index and a target compilation algorithm corresponding to the target construction stage; calculating the reference index by using the target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station; and generating a cost analysis table based on the project cost information, and displaying the cost analysis table. The invention obtains the project cost information of the current construction stage by automatically obtaining the project cost compilation task and calling the corresponding compilation algorithm for calculation, thereby realizing the intelligent processing of the project cost, reducing the cost and improving the efficiency compared with the calculation of the project cost by manpower, and simultaneously improving the scientificity and the accuracy of the project cost work.

Description

Engineering cost compiling method and device, electronic equipment and storage medium
Technical Field
The invention relates to the technical field of computers, in particular to a method and a device for compiling engineering cost, electronic equipment and a storage medium.
Background
The construction cost of the pumped storage power station relates to economic benefits and long-term development of national network new source companies, a construction cost standardization system is established, the construction cost is reasonably controlled, the investment benefit is improved, and the construction cost is not only a concrete measure for changing a pumped storage development mode, but also a basic guarantee for a key period of pumped storage large development.
The digital and intelligent construction cost working mode can reduce the cost of construction enterprises, improve the efficiency and improve the scientificity and the accuracy of construction cost work of the construction enterprises.
Disclosure of Invention
In order to solve the above technical problems, or at least partially solve the above technical problems, the present invention provides a construction cost compiling method, apparatus, electronic device, and storage medium.
According to an aspect of an embodiment of the present invention, there is provided a method for compiling construction cost, including:
acquiring a project cost compilation task of a target pumped storage power station, wherein the project cost compilation task comprises: a target construction stage corresponding to the target pumped storage power station at present;
acquiring a reference index and a target compilation algorithm corresponding to the target construction stage;
calculating the reference index by using the target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station;
and generating a cost analysis table based on the project cost information, and displaying the cost analysis table.
Further, before acquiring the project cost programming task of the target pumped storage power station, the method further comprises the following steps:
acquiring algorithm configuration information for configuring engineering cost compilation, wherein the algorithm configuration information comprises at least one compilation algorithm;
configuring the compiling algorithm in a preset algorithm library, and acquiring at least one basic parameter for configuring the compiling algorithm from parameter configuration information;
and configuring the basic parameters in corresponding compilation algorithms, and establishing a corresponding relation between the compilation algorithms and the construction stages in the preset algorithm library.
Further, the method further comprises:
acquiring updating maintenance information corresponding to the preset algorithm library, wherein the updating maintenance information is used for updating and maintaining the compiling algorithm in the preset algorithm library;
updating and maintaining basic parameters of the compilation algorithm to be updated by using the updating and maintaining information, and verifying the compilation algorithm after updating and maintaining to obtain a verification result;
and determining to finish the updating and maintenance of the preset algorithm library under the condition that the verification result is that the verification is passed.
Further, the obtaining of the reference index and the target programming algorithm corresponding to the target construction stage includes:
inquiring a preset construction scheme corresponding to the target construction stage, and extracting the reference index from the preset construction scheme;
determining at least one candidate compilation algorithm corresponding to the target construction stage based on the corresponding relation;
and acquiring the characteristic information corresponding to each candidate compilation algorithm, and determining the candidate compilation algorithm of which the characteristic information is matched with the application requirement corresponding to the engineering cost compilation task as the target compilation algorithm.
Further, the calculating the reference index by using the target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station includes:
acquiring basic construction data corresponding to the target construction stage;
and inputting the basic construction data and the reference index into the target programming algorithm for calculation to obtain the engineering cost information.
Further, the inputting the basic construction data and the reference index into the target programming algorithm for calculation to obtain the engineering cost information includes:
combining different construction data with the reference indexes by using the target compilation algorithm, and calculating the engineering cost information corresponding to each combination;
or, the target compilation algorithm is used for calculating the construction data and the reference index to obtain a calculation result, the calculation result is updated, and the engineering cost information is calculated by using the updated calculation result.
Further, before generating the cost analysis table based on the construction cost information, the method further includes:
sending the project cost information to a target auditing terminal so that the target auditing terminal can audit the project cost information;
receiving an auditing result fed back by the target auditing terminal based on the engineering cost information;
and updating the construction cost information by using the auditing result to obtain the updated construction cost information.
According to still another aspect of an embodiment of the present invention, there is provided a construction cost compiling apparatus including:
the acquisition module is used for acquiring a project cost establishment task of the target pumped storage power station, wherein the project cost establishment task comprises the following steps: a target construction stage corresponding to the target pumped storage power station at present;
the query module is used for acquiring the reference index and the target compilation algorithm corresponding to the target construction stage;
the calculation module is used for calculating the reference index by using the target programming algorithm to obtain the current corresponding project cost information of the target pumped storage power station;
and the generating module is used for generating a cost analysis table based on the project cost information and displaying the cost analysis table.
According to another aspect of the embodiments of the present invention, there is also provided a storage medium including a stored program which executes the above steps when the program is executed.
According to another aspect of the embodiments of the present invention, there is also provided an electronic apparatus, including a processor, a communication interface, a memory, and a communication bus, where the processor, the communication interface, and the memory complete communication with each other through the communication bus; wherein: a memory for storing a computer program; a processor for executing the steps of the method by running the program stored in the memory.
Embodiments of the present invention also provide a computer program product containing instructions, which when run on a computer, cause the computer to perform the steps of the above method.
Compared with the prior art, the technical scheme provided by the embodiment of the invention has the following advantages: the method provided by the embodiment of the invention obtains the project cost information of the current construction stage by automatically acquiring the project cost programming task and calling the corresponding programming algorithm to calculate, thereby realizing the intelligent processing of the project cost, reducing the cost and improving the efficiency compared with the method for calculating the project cost by manpower, and simultaneously improving the scientificity and the accuracy of the project cost work.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and together with the description, serve to explain the principles of the invention.
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious for those skilled in the art that other drawings can be obtained according to the drawings without inventive exercise.
FIG. 1 is a flow chart of a construction cost compilation method provided by an embodiment of the invention;
FIG. 2 is a block diagram of an engineering cost construction apparatus according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of an electronic device according to an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, it is obvious that the described embodiments are some, but not all, embodiments of the present invention, and the illustrative embodiments and the description thereof are used to explain the present invention and do not constitute a limitation of the present invention. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention.
It is noted that, in this document, relational terms such as "first" and "second," and the like, are used solely to distinguish one entity or action from another similar entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrases "comprising a," "8230," "8230," or "comprising" does not exclude the presence of additional like elements in a process, method, article, or apparatus that comprises the element.
The embodiment of the invention provides a method and a device for compiling engineering cost, electronic equipment and a storage medium. The method provided by the embodiment of the invention can be applied to any required electronic equipment, for example, the electronic equipment can be electronic equipment such as a server and a terminal, and the method is not particularly limited herein, and is hereinafter simply referred to as electronic equipment for convenience in description.
According to an aspect of the embodiments of the present invention, an embodiment of a method for compiling construction cost is provided, and fig. 1 is a flowchart of a method provided by the embodiment of the present invention, as shown in fig. 1, the method includes:
according to an aspect of an embodiment of the present invention, there is provided a method for compiling construction cost, including:
step S11, obtaining a project cost compilation task of the target pumped storage power station, wherein the project cost compilation task comprises: and the target pumped storage power station corresponds to the current target construction stage.
The method provided by the embodiment of the invention is applied to the intelligent terminal with data processing capability, and the intelligent terminal can be a notebook computer, a mobile phone, an iPad and the like. The user can be based on the engineering cost task of the intelligent terminal generation target pumped storage electricity, and specifically, the user can select the current corresponding target construction stage of the target pumped storage power station on the intelligent terminal at first, and the corresponding application requirements, for example: the application requirements may be: pre-feasibility study investment calculation, feasibility study design approximate calculation, engineering unit price calculation cost and the like. After a user determines a target construction stage and a task requirement, the engineering cost compiling task can be issued at the intelligent terminal.
In the embodiment of the invention, before the project cost programming task of the target pumped storage power station is obtained, the method further comprises the following steps A1-A3:
step A1, algorithm configuration information used for configuring engineering cost compilation is obtained, wherein the algorithm configuration information comprises at least one compilation algorithm.
And A2, configuring the compiling algorithm in a preset algorithm library, and acquiring at least one basic parameter for configuring the compiling algorithm from the parameter configuration information.
In the embodiment of the invention, the programming algorithm mainly comprises the following steps: unit cost index method, project unit price method and quota cost method. Basic parameters of the algorithm mainly comprise: technical conditions, base price, engineering unit price, and the like.
And step A3, configuring the basic parameters in the corresponding compiling algorithm, and establishing the corresponding relation between the compiling algorithm and the construction stage in the preset algorithm library.
In an embodiment of the present invention, the method further comprises: acquiring updating maintenance information corresponding to a preset algorithm library, wherein the updating maintenance information is used for updating and maintaining a compiling algorithm in the preset algorithm library; updating and maintaining basic parameters of the compilation algorithm to be updated by using the updating and maintaining information, and verifying the compilation algorithm after updating and maintaining to obtain a verification result; and under the condition that the verification result is that the verification is passed, determining to finish updating and maintaining the preset algorithm library.
In the embodiment of the invention, the main technical conditions, the basic price and the project unit price of the typical scheme related to the unit cost index, the project unit price method and the quota cost are preset, so that the pumped storage power station can conveniently select a reasonable preset scheme to calculate the index, the project unit price and the quota. When the basic parameters are maintained regularly, basic data and algorithm maintenance needs to be carried out according to different construction cost compiling modes, such as data maintenance of technical parameters, price levels, labor cost and the like of a typical scheme, and the basic data and algorithm maintenance is used as a foundation for project construction cost compiling.
And S12, acquiring a reference index corresponding to the target construction stage and a target compilation algorithm.
In the embodiment of the invention, the reference index and the target compilation algorithm corresponding to the target construction stage are obtained, and the method comprises the following steps B1-B3:
and B1, inquiring a preset construction scheme corresponding to the target construction stage, and extracting a reference index from the preset construction scheme.
In the embodiment of the invention, the preset construction scheme corresponding to the target construction stage is inquired from the database, and the preset construction scheme can be a preset standard construction scheme. The intelligent terminal can analyze the preset construction scheme to obtain related parameters of the target construction stage, and the related parameters are determined as reference indexes.
And B2, determining at least one candidate compilation algorithm corresponding to the target construction stage based on the corresponding relation.
And step B3, acquiring the characteristic information corresponding to each candidate compilation algorithm, and determining the candidate compilation algorithm of which the characteristic information is matched with the application requirement corresponding to the engineering cost compilation task as a target compilation algorithm.
In the embodiment of the invention, because the engineering cost compiling modes required by different construction stages are different, at least one candidate compiling algorithm corresponding to the target construction stage can be determined based on the pre-configured corresponding relation. It should be noted that different construction stages may correspond to multiple candidate compilation algorithms, at this time, application requirements are obtained from a project cost compilation task, and feature information corresponding to each candidate compilation algorithm is matched with the application requirements to obtain a final target compilation algorithm, wherein the feature information of the compilation algorithm includes input parameters and output parameters of the algorithm, and the like.
And S13, calculating the reference index by using a target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station.
In the embodiment of the invention, the reference index is calculated by using a target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station, and the method comprises the following steps C1-C2:
and C1, acquiring foundation construction data corresponding to the target construction stage.
And step C2, inputting the basic construction data and the reference index into a target compilation algorithm for calculation to obtain the engineering cost information.
In the embodiment of the invention, the basic construction data and the reference index are input into a target compilation algorithm for calculation to obtain the engineering cost information, and the method comprises the following steps: and combining different construction data with the reference indexes by using a unit construction cost index algorithm, and calculating the construction cost information corresponding to each combination.
In the embodiment of the invention, the unit cost index algorithm system calculates the following example:
(1) The scheme is selected by adopting an engineering reservoir dam type as an asphalt panel rock-fill dam, and the excavation amount is 966 ten thousand meters 3 The filling (pouring) amount is 634 ten thousand meters 3 The volume of concrete in the drainage gallery is 14332m 3 The width of the annular warehouse road is 10.0m, the thickness of the concrete pavement is 20cm, and the length of the annular warehouse road is 2148m.
(2) And calculating the unit cost index of the secondary project.
(2.1) reservoir excavation engineering Unit is Yuan/m 3 Selecting a cost index of 37.49 according to the description of the example project, wherein the excavation volume is 966 km 3 The calculated estimated value of the cost of single project is 37.49 x 966 ten thousand meters 3 =36215 ten thousand yuan.
(2.2) dam filling engineering Unit is Yuan/m 3 A cost index of 48.22 is selected according to the description of the example project, where the fill volume is 634 ten thousand meters 3 The calculated estimated cost of single project is 48.22X 634 ten thousand meters 3 =30571 ten thousand yuan;
(2.3) drainage gallery Unit is Yuan/m 3 Selecting a cost index of 1001.53 according to the description of the example project; wherein the area of the drainage corridor concrete 14332m 3 The calculated estimated value of the single project cost is 1001.53 x 14332m 3 =1435 ten thousand yuan;
(2.4) the unit of the highway engineering of the ring bank is yuan/m, the construction cost index is selected to be 1371.57 according to the description of the example engineering, wherein the length is 2148m, and the calculated estimated construction cost of the single project is 1371.57 × 2148m =295 ten thousand yuan.
(3) And adjusting coefficients, namely adjusting 5 parameters such as rock level difference, price level, project area difference, elevation, design stage adjustment and the like.
Rock grade difference: the rock grade is IX-X hole excavation XI-XII in open excavation, and is the same as the rock grade of the typical scheme of the general construction cost without adjustment;
price level: in the next half year of 2017, the comprehensive adjustment coefficient calculated according to the method in section 20.1.4 is 0.9223.
Item area differences: the example actual engineering project belongs to the north China area, the project area difference adjustment coefficient is calculated according to the method of section 20.1.5, and the adjustment coefficient of the typical project II is selected to be 1.009.
Elevation of elevation: the elevation of the dam top of the reservoir is 638.5m according to the example practical engineering scheme, the elevation adjustment coefficient is calculated according to a method of 20.1.6 sections, and the adjustment coefficient of a typical scheme II is selected to be 1.0.
Adjusting in a design stage: the project is in a feasibility research stage, the adjustment coefficient in the design stage is calculated according to the method in section 20.1.7, and the adjustment coefficient is selected to be 1.0.
(4) Calculating a comprehensive adjustment coefficient: 1, 9223, 1, 009, 1.0-4=0.9313.
(5) Fifthly, cost accounting: 68517 × 0.9313=63810 ten thousand yuan.
As a comprehensive numerical value, the method can effectively eliminate the influence of differences such as installation and size, and enhance the flexibility, the combinability and the expansibility of the universal construction cost of the pumped storage power station. The unit cost index algorithm can rapidly combine cost estimation of different schemes according to various input coefficients, and carry out comparison of scheme cost, so that construction units can visually see cost estimation conditions of different stages of power station construction, and the method is widely applied to compilation, review and decision-making of pumped storage power station point selection planning investment block calculation, pre-feasibility study investment estimation, feasibility study design approximate calculation and the like.
In the embodiment of the present invention, a system calculation example using an engineering unit price algorithm is as follows:
(1) And selecting a project phase, such as an approximate calculation phase or a budget phase, wherein the approximate calculation phase is selected for calculation in the project.
(2) Taking the unit price adjustment of the stone excavation project as an example, 3 dimensions such as basic unit price selection, transport distance adjustment, adjustment coefficient and the like are performed to participate in the unit price adjustment.
(2.1) basic unit price selection: the engineering dam is excavated by adopting YQ-150 type down-the-hole drill for drilling, bench blasting and a 3m & lt 3 & gt excavator which is provided with 15 t-20 t of self-discharging automobiles for discharging slag. The comparison table 18.3 section of the main project unit price table has the characteristics and the construction method which are basically the same as the project unit price of the open cut dam of the stone square at the 9 th site, and the approximate horizontal unit price of 43.23 yuan/m < 3 > is selected as the basic unit price.
(2.2) adjusting the transport distance: the transport distance of the stone slag of the example engineering stone excavation is 1km, the transport distance of the basic unit price stone slag selected in the previous item is 1.5km, the 3 rd item 'stone transportation (1 km per open cut of a 3m3 loader with 15t dump trucks) in the engineering unit price interval table is adjusted according to the transport distance of 20.2-2, the estimated level is 2.52 yuan/m 3', and the unit price after adjustment is 43.23-2.52/2=41.97 yuan/m 3; (1.5/1).
And (2.3) in the third step, in the aspect of adjusting coefficients, a target unit price is formed mainly aiming at main factors influencing the engineering unit price, such as rock level, price level, project area, elevation and the like.
(2.4) rock grade: XI to XII, and thus the rock level parameter was 1.16.
(2.5) price level: 0.94 is entered according to the latest price index.
(2.6) adjusting the unit price area of the artificial budget: is located in the Zhen of Kaishitengtang in the inner Mongolia autonomous region, and belongs to the class II payroll region, which is 1.05.
(2.7) other direct fee area regulation: is 1.009.
(2.8) elevation: since below 2000 meters, 1 is directly selected.
(4) The comprehensive adjustment coefficient is calculated as 1.16+0.94+1.05+1.009+1-5+1=1.159.
(5) And fifthly, calculating the unit price of the stone excavation project =41.97 × 1.159=48.64 according to the construction data and the reference index, updating the calculation result, and calculating the project cost information by using the updated calculation result.
In the embodiment of the invention, the project unit price calculation cost is used as a basic level and unit of cost management control and is matched with detailed project quantity, a user only needs to input various adjustment parameters, select the corresponding cost types of a power station, such as approximate calculation or budget, then adjust the unit price parameters (including basic unit price, section size, distance adjustment and altitude elevation), and automatically calculate the comprehensive parameters through related parameters to prepare to calculate the unit price of each level of project. Meanwhile, the calculated project unit price is automatically put into a basic database to be used as a reference basis for calculating the project unit price next time, the cost compilation sample data is enhanced, the unit price calculation error rate is verified to be zero in the application process, and the accuracy and precision of cost prediction and control are effectively improved.
In an embodiment of the present invention, the target formulation algorithm further comprises a quota cost algorithm, wherein a system calculation example of the quota cost algorithm is as follows:
(1) The construction phase is selected, e.g. by approximating the quota.
(2) And selecting a construction type and an earthwork.
(3) Selecting construction mode according to construction type, and selecting 3m according to actual condition 3 The loader is used for loading soil and transporting the type III soil by a dump truck.
(4) Combine construction type, construction description (118 kw bulldozer stripping aggregate, 3 m) 3 15t of loading soil of the loader is discharged by self-discharging, the transport distance is 2.6 km), and the corresponding quota number is selected by the construction mode: 10598. 10599, 10253 and fill in the proportions (0.4, 0.6, 1).
(5) The price of each item is calculated by selecting the quantity corresponding to the quota and combining the unit price.
(5.1) direct charge: labor cost 3.7 × 4.9=18.13 yuan, retail material cost 43 × 1=43 yuan, wheel loader 3 mm 3.65 × 216.58=140.78 yuan, bulldozer power 74kw0.22 × 133.91=29.46 yuan, bulldozer power kw 1181.13 × 199.28=225.19 yuan, dump truck diesel type 15t 3.4 × 168.78=573.01 yuan, other machinery use cost 3 × 1=3 yuan, other direct cost 69.7 yuan.
(5.2) indirect cost 146.6 yuan;
(5.3) profit 87.42 yuan;
(5.4) valence difference is 0 yuan;
(5.5) tax 120.27 yuan, total:
18.13+43+140.78+29.46+225.19+573.01+3+69.7+146.6+87.42+120.27=1456.56 yuan of final unit price: 1456.56/100=14.47.
Meanwhile, the quota cost algorithm comprises functions of quota information management, project cost compilation, quota report forms and the like, and provides corresponding functions according to application requirements of users. The specific functions are explained as follows:
(1) The cost comprises: the cost of the water and electricity engineering is composed of engineering cost, independent cost, preparation cost and financing interest in the construction period. The project cost is composed of construction and installation project cost and equipment cost. Construction and installation costs consist of direct costs, indirect costs, profits, material offsets and taxes. According to the water and electricity engineering cost constitution standard, the divided data of the water and electricity engineering is built in and is used as a template for compiling the approximate calculation of the water and electricity engineering.
(2) Rating basic data: the hydropower project quota is suitable for newly built and expanded large and medium hydropower project construction projects; the method is a basis for compiling the approximate calculation quota and related expansion indexes, is a pricing reference for compiling bid and tender bases, bid and quote and contract management of engineering projects, and is a pricing basis for supervising project investment management by related departments and units of China. Managing the price information of the human machine: periodically collecting the price information of the man-machine issued by the state quota institution; the basic unit price is the basis for calculating the project unit price, and different basic unit prices are different according to time and regions, including the unit price of manpower budget, the material budget price, the use cost of construction machinery, the budget price of electricity, wind and water, and the unit price of concrete materials. The quota management of the hydroelectric engineering electromechanical equipment: the electromechanical equipment quota comprises the steps of water turbine installation, hydraulic generator installation, large-scale water pump installation, water inlet valve installation, hydraulic mechanical auxiliary equipment installation, electrical equipment installation, transformer substation equipment installation, communication equipment installation, hoisting equipment installation, gate installation and pressure steel pipe manufacturing and installation.
(3) Single project cost: a new quota scheme is established: newly building a single project (or project) rating establishment scheme, and maintaining information such as establishment units, project types, establishment descriptions, establishment dates and the like of the establishment scheme; quota list import and maintenance: importing a cost list of a cost scheme and providing a maintenance function of the cost list; marking the construction type of the list item; clear item group price: making a cost list unit price by using quota data according to a unit price analysis mode provided in a quota standard; quota consumption calculation: and for the quota subdirectory needing to reckoning the consumption of the human machine, providing a calculation template of the reckoning consumption aiming at a specific reckoning method, inputting original data, and calculating the quota consumption according to an agreed calculation formula.
And S14, generating a cost analysis table based on the project cost information, and displaying the cost analysis table.
In an embodiment of the present invention, before generating the cost analysis table based on the construction cost information, the method further includes: the construction cost information is sent to a target auditing terminal, so that the target auditing terminal can audit the construction cost information; receiving an auditing result fed back by a target auditing terminal based on the engineering cost information; and updating the engineering cost information by using the auditing result to obtain the updated engineering cost information.
In the embodiment of the invention, by checking the programmed construction cost information step by step, the calculation process and the cost comparison of each unit price can be seen in the checking process, so that the cost checking of the auditors at all levels is facilitated, and meanwhile, if the auditors consider that the existing unit price has deviation from the actual distance, the final unit price can be automatically input. After the examination is passed, the data can be used as a basis for approximate calculation, budget, bid and engineering quantity change.
In the embodiment of the invention, after the cost compiling and auditing are finished, a corresponding cost analysis report is exported in a single analysis and summary mode and is used for cost analysis, engineering quantity change and high-level decision.
The method provided by the embodiment of the invention obtains the project cost information of the current construction stage by automatically obtaining the project cost compilation task and calling the corresponding compilation algorithm for calculation, thereby realizing the intelligent processing of the project cost, reducing the cost and improving the efficiency compared with the method for calculating the project cost by manpower, and simultaneously improving the scientificity and the accuracy of the project cost work.
Fig. 2 is a block diagram of an engineering cost programming apparatus provided in an embodiment of the present invention, which may be implemented as part or all of an electronic device by software, hardware, or a combination of the two. As shown in fig. 2, the apparatus includes:
the obtaining module 21 is configured to obtain a project cost compilation task of the target pumped storage power station, where the project cost compilation task includes: and the target pumped storage power station corresponds to the current target construction stage.
And the query module 22 is configured to obtain a reference index corresponding to the target construction stage and a target compilation algorithm.
The calculation module 23 is configured to calculate the reference index by using a target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station;
and the generating module 24 is used for generating a cost analysis table based on the project cost information and displaying the cost analysis table.
In the embodiment of the present invention, the construction cost compiling device further includes: the system comprises a configuration module, a data processing module and a data processing module, wherein the configuration module is used for acquiring algorithm configuration information used for configuring engineering cost compilation, and the algorithm configuration information comprises at least one compilation algorithm; configuring a compilation algorithm in a preset algorithm library, and acquiring at least one basic parameter for configuring the compilation algorithm from parameter configuration information; and configuring the basic parameters in corresponding compiling algorithms, and establishing a corresponding relation between the compiling algorithms and the construction stage in a preset algorithm library.
In the embodiment of the present invention, the construction cost compiling device further includes: the updating and maintaining module is used for acquiring updating and maintaining information corresponding to the preset algorithm library, wherein the updating and maintaining information is used for updating and maintaining the compiling algorithm in the preset algorithm library; updating and maintaining basic parameters of the compiling algorithm to be updated by using the updating and maintaining information, and verifying the compiling algorithm after updating and maintaining to obtain a verification result; and under the condition that the verification result is that the verification is passed, determining to finish updating and maintaining the preset algorithm library.
In the embodiment of the present invention, the query module 22 is configured to query a preset construction scheme corresponding to the target construction stage, and extract a reference index from the preset construction scheme; determining at least one candidate compilation algorithm corresponding to the target construction stage based on the corresponding relation; and acquiring the characteristic information corresponding to each candidate compilation algorithm, and determining the candidate compilation algorithm of which the characteristic information is matched with the application requirement corresponding to the engineering cost compilation task as a target compilation algorithm.
In the embodiment of the present invention, the calculation module 23 is configured to obtain basic construction data corresponding to a target construction stage; and inputting the basic construction data and the reference index into a target compilation algorithm for calculation to obtain the construction cost information.
In the embodiment of the present invention, the calculation module 23 is specifically configured to combine different construction data with reference indexes by using a target compilation algorithm, and calculate the engineering cost information corresponding to each combination; or, calculating the construction data and the reference index by using a target compilation algorithm to obtain a calculation result, updating the calculation result, and calculating the construction cost information by using the updated calculation result.
In an embodiment of the present invention, the construction cost compiling device further includes: the processing module is used for sending the project cost information to the target auditing terminal so that the target auditing terminal can audit the project cost information; receiving an auditing result fed back by a target auditing terminal based on the engineering cost information; and updating the engineering cost information by using the auditing result to obtain the updated engineering cost information.
An embodiment of the present invention further provides an electronic device, as shown in fig. 3, the electronic device may include: the system comprises a processor 1501, a communication interface 1502, a memory 1503 and a communication bus 1504, wherein the processor 1501, the communication interface 1502 and the memory 1503 complete communication with each other through the communication bus 1504.
A memory 1503 for storing a computer program;
the processor 1501 is configured to implement the steps of the above embodiments when executing the computer program stored in the memory 1503.
The communication bus mentioned in the above terminal may be a Peripheral Component Interconnect (PCI) bus, an Extended Industry Standard Architecture (EISA) bus, or the like. The communication bus may be divided into an address bus, a data bus, a control bus, etc. For ease of illustration, only one thick line is shown, but this does not mean that there is only one bus or one type of bus.
The communication interface is used for communication between the terminal and other equipment.
The Memory may include a Random Access Memory (RAM) or a non-volatile Memory (non-volatile Memory), such as at least one disk Memory. Optionally, the memory may also be at least one memory device located remotely from the processor.
The Processor may be a general-purpose Processor, and includes a Central Processing Unit (CPU), a Network Processor (NP), and the like; the Integrated Circuit may also be a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), a Field Programmable Gate Array (FPGA) or other Programmable logic device, a discrete Gate or transistor logic device, or a discrete hardware component.
In yet another embodiment of the present invention, there is provided a computer-readable storage medium having stored therein instructions, which when run on a computer, cause the computer to perform a construction cost compilation method as described in any one of the above embodiments.
In yet another embodiment of the present invention, there is also provided a computer program product containing instructions which, when run on a computer, cause the computer to perform a method of engineering cost compilation as described in any of the above embodiments.
In the above embodiments, the implementation may be wholly or partially realized by software, hardware, firmware, or any combination thereof. When implemented in software, it may be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When loaded and executed on a computer, cause the processes or functions described in accordance with the embodiments of the invention to be performed in whole or in part. The computer may be a general purpose computer, a special purpose computer, a network of computers, or other programmable device. The computer instructions may be stored in a computer readable storage medium or transmitted from one computer readable storage medium to another, for example, the computer instructions may be transmitted from one website, computer, server, or data center to another website, computer, server, or data center by wire (e.g., coaxial cable, fiber optic, digital subscriber line) or wirelessly (e.g., infrared, wireless, microwave, etc.). The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device, such as a server, a data center, etc., that incorporates one or more of the available media. The usable medium may be a magnetic medium (e.g., floppy Disk, hard Disk, magnetic tape), an optical medium (e.g., DVD), or a semiconductor medium (e.g., solid State Disk), among others.
The above description is only for the preferred embodiment of the present invention, and is not intended to limit the scope of the present invention. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention shall fall within the protection scope of the present invention.
The foregoing are merely exemplary embodiments of the present invention, which enable those skilled in the art to understand or practice the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1. A method for compiling construction cost is characterized by comprising the following steps:
acquiring a project cost establishment task of a target pumped storage power station, wherein the project cost establishment task comprises the following steps: a target construction stage corresponding to the target pumped storage power station at present;
acquiring a reference index and a target compilation algorithm corresponding to the target construction stage;
calculating the reference index by using the target programming algorithm to obtain the current corresponding project cost information of the target pumped storage power station;
and generating a cost analysis table based on the project cost information, and displaying the cost analysis table.
2. The method of claim 1, wherein prior to obtaining project cost programming assignments for the target pumped-hydro power storage plant, the method further comprises:
acquiring algorithm configuration information for configuring engineering cost compilation, wherein the algorithm configuration information comprises at least one compilation algorithm;
configuring the compiling algorithm in a preset algorithm library, and acquiring at least one basic parameter for configuring the compiling algorithm from parameter configuration information;
and configuring the basic parameters in corresponding compilation algorithms, and establishing a corresponding relation between the compilation algorithms and the construction stages in the preset algorithm library.
3. The method of claim 2, further comprising:
acquiring updating maintenance information corresponding to the preset algorithm library, wherein the updating maintenance information is used for updating and maintaining the compiling algorithm in the preset algorithm library;
updating and maintaining basic parameters of the compiling algorithm to be updated by using the updating and maintaining information, and verifying the compiling algorithm after updating and maintaining to obtain a verification result;
and determining to finish the updating and maintenance of the preset algorithm library under the condition that the verification result is that the verification is passed.
4. The method according to claim 2, wherein the obtaining of the reference index and the target compilation algorithm corresponding to the target construction stage comprises:
inquiring a preset construction scheme corresponding to the target construction stage, and extracting the reference index from the preset construction scheme;
determining at least one candidate compilation algorithm corresponding to the target construction stage based on the corresponding relation;
and acquiring the characteristic information corresponding to each candidate compilation algorithm, and determining the candidate compilation algorithm of which the characteristic information is matched with the application requirement corresponding to the engineering cost compilation task as the target compilation algorithm.
5. The method of claim 1, wherein the calculating the reference index using the target programming algorithm to obtain the current corresponding construction cost information of the target pumped-storage power station comprises:
acquiring basic construction data corresponding to the target construction stage;
and inputting the basic construction data and the reference index into the target programming algorithm for calculation to obtain the engineering cost information.
6. The method of claim 5, wherein said inputting said foundation construction data and said reference index into said target construction algorithm for calculation to obtain said construction cost information comprises:
combining different construction data with the reference indexes by using the target compilation algorithm, and calculating the engineering cost information corresponding to each combination;
or, the target compilation algorithm is used for calculating the construction data and the reference index to obtain a calculation result, the calculation result is updated, and the engineering cost information is calculated by using the updated calculation result.
7. The method of claim 1, wherein prior to generating a cost analysis table based on the construction cost information, the method further comprises:
sending the project cost information to a target auditing terminal so that the target auditing terminal can audit the project cost information;
receiving an auditing result fed back by the target auditing terminal based on the engineering cost information;
and updating the construction cost information by using the auditing result to obtain the updated construction cost information.
8. A construction cost construction apparatus comprising:
the acquisition module is used for acquiring a project cost establishment task of the target pumped storage power station, wherein the project cost establishment task comprises the following steps: a target construction stage corresponding to the target pumped storage power station at present;
the query module is used for acquiring the reference index and the target compilation algorithm corresponding to the target construction stage;
the calculation module is used for calculating the reference index by using the target programming algorithm to obtain the current corresponding engineering cost information of the target pumped storage power station;
and the generating module is used for generating a cost analysis table based on the project cost information and displaying the cost analysis table.
9. A storage medium, characterized in that the storage medium comprises a stored program, wherein the program is operative to perform the method steps of any of the preceding claims 1 to 7.
10. The electronic equipment is characterized by comprising a processor, a communication interface, a memory and a communication bus, wherein the processor and the communication interface are used for realizing the communication between the processor and the memory through the communication bus; wherein:
a memory for storing a computer program;
a processor for performing the method steps of any of claims 1 to 7 by executing a program stored on a memory.
CN202211468179.4A 2022-11-22 2022-11-22 Engineering cost compiling method and device, electronic equipment and storage medium Pending CN115760250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211468179.4A CN115760250A (en) 2022-11-22 2022-11-22 Engineering cost compiling method and device, electronic equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211468179.4A CN115760250A (en) 2022-11-22 2022-11-22 Engineering cost compiling method and device, electronic equipment and storage medium

Publications (1)

Publication Number Publication Date
CN115760250A true CN115760250A (en) 2023-03-07

Family

ID=85335145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211468179.4A Pending CN115760250A (en) 2022-11-22 2022-11-22 Engineering cost compiling method and device, electronic equipment and storage medium

Country Status (1)

Country Link
CN (1) CN115760250A (en)

Similar Documents

Publication Publication Date Title
Navon et al. Field experiments in automated monitoring of road construction
CN114219289A (en) Construction cost control method based on BIM and Internet of things technology
CN105989546A (en) Power transmission and transformation construction cost basic data collection and analysis system
CN110110376A (en) A kind of hinge dam type scheme analysis method for quantitatively evaluating and device based on BIM
CN103971289B (en) The processing method and processing device of mine ore drawing data
Fang et al. Quota-based carbon tracing model for construction processes in China
Kim et al. A case study on BIM object-based earned value and process management in highway construction
CN113065783A (en) BIM (building information modeling) engineering quantity application method of waste incineration power plant based on BIM technology
CN117035658A (en) Engineering expense processing method and device
CN108549624A (en) Engineeing design for communication budget and illustrate text automation generate system and method
Xu et al. Suggestions for temporary construction facilities’ layout problems in large-scale construction projects
Kim et al. Estimating approximate construction duration of CFRD in the planning stage
CN115760250A (en) Engineering cost compiling method and device, electronic equipment and storage medium
CN115511543A (en) Power transmission and transformation project cost measuring and calculating method
JP2010204740A (en) System for estimating amount of carbon dioxide emitted from construction and method therefor
CN114297358A (en) Engineering cost data splitting method and device and terminal equipment
de Lima et al. Optimization of earthmoving operations planning: a novel approach considering interferences
CN113095296A (en) Civil engineering material calculation system and method based on Internet of things
Burcar Dunovic et al. Method for base estimation of construction time for linear projects in front-end project phases
CN114693424A (en) Building industry asset big data collection and application
Ngo Life cycle costing in public building projects in Vietnam
Pindoria et al. A Critical Review of Identification of Critical Factors Affecting the Productivity of Construction Equipment
CN112258343B (en) BIM multi-dimensional distribution network engineering cost information collection system
Chee Prioritization of Potable Water Infrastructure Investments on the Navajo Nation
Bent Evaluating and calculating contingency

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination