CN115749165A - Construction method of modified asphalt waterproof coiled material - Google Patents

Construction method of modified asphalt waterproof coiled material Download PDF

Info

Publication number
CN115749165A
CN115749165A CN202211539319.2A CN202211539319A CN115749165A CN 115749165 A CN115749165 A CN 115749165A CN 202211539319 A CN202211539319 A CN 202211539319A CN 115749165 A CN115749165 A CN 115749165A
Authority
CN
China
Prior art keywords
coiled material
waterproof coiled
rod
modified asphalt
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211539319.2A
Other languages
Chinese (zh)
Inventor
谢盼盼
张静文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Yuhong Waterproof Engineering Co ltd
Original Assignee
Hangzhou Yuhong Waterproof Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Yuhong Waterproof Engineering Co ltd filed Critical Hangzhou Yuhong Waterproof Engineering Co ltd
Priority to CN202211539319.2A priority Critical patent/CN115749165A/en
Publication of CN115749165A publication Critical patent/CN115749165A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention belongs to the technical field of waterproof construction, in particular to a construction method of a modified asphalt waterproof coiled material, which comprises the following steps: s1, cleaning a base layer; s2, paving and pasting coiled materials, namely installing the modified asphalt waterproof coiled materials on a paving and pasting device, paving and pasting a first waterproof coiled material belt, a second waterproof coiled material belt, a third waterproof coiled material belt and a fourth waterproof coiled material belt along one side of the construction surface through a construction device in sequence until the construction surface is fully paved, and reserving a gap of 10-15cm between every two adjacent waterproof coiled material belts; s3, checking whether the coiled material is laid and pasted smoothly; s4, rolling the paved waterproof coiled material to ensure that the waterproof coiled material is tightly and firmly bonded; and S5, head closing processing. According to the invention, the orientation of the I-shaped plate is adjusted to be parallel to the orientation of the base layer, so that the positioning of the paving route is completed, and then the first winding drum is enabled to travel along the route of the I-shaped plate during paving, so that the paving is ensured not to be inclined.

Description

Construction method of modified asphalt waterproof coiled material
Technical Field
The invention relates to the technical field of waterproof construction, in particular to a construction method of a modified asphalt waterproof coiled material.
Background
The asphalt waterproof coiled material is the most commonly used waterproof coiled material, accounts for about 70% of the total amount of the market, is a curlable sheet waterproof material prepared by dip-coating asphalt on a base tire (such as raw paper and fiber fabric) and then spreading a powdery or sheet isolation material on the surface, is a main material in waterproof construction operation, and has slightly different waterproof construction methods according to the differences of the waterproof coiled materials.
To autohension modified asphalt waterproofing membrane, its self has viscidity, consequently need not to coat the glue solution when the construction, only need to reveal the barrier film during the construction and remove alright lay, the process is simple, all the other construction steps are almost the same, spread the coiled material after the clearance basic unit, the rolling is carried out after the coiled material is spread and is pasted smoothly, among the current construction method, spread this process of pasting to the coiled material, generally through the manual work with the taut flare-out of coiled material, then slowly lay to the basic unit on, or spread through the mobile device and paste, the mobile device is when marcing, also hardly ensures that the route of marcing is a straight line all the time, consequently the oblique situation of coiled material subsides often appears, so make the improvement.
Disclosure of Invention
Based on the technical problem that the coiled material is easy to stick obliquely in the prior art, the invention provides a construction method of a modified asphalt waterproof coiled material.
The invention provides a construction method of a modified asphalt waterproof coiled material, which comprises the following steps:
s1, cleaning a base layer;
s2, paving and pasting coiled materials, namely installing the modified asphalt waterproof coiled materials on a paving and pasting device, paving and pasting a first waterproof coiled material belt, a second waterproof coiled material belt, a third waterproof coiled material belt and a fourth waterproof coiled material belt along one side of the construction surface through a construction device in sequence until the construction surface is fully paved, and reserving a gap of 10-15cm between every two adjacent waterproof coiled material belts;
s3, checking whether the coiled material is laid and pasted smoothly;
s4, rolling the paved waterproof roll to ensure that the waterproof roll is tightly and firmly bonded;
and S5, head closing processing.
Preferably, the paving and pasting device comprises an I-shaped plate and is characterized in that sliding grooves are formed in two sides of the top of the I-shaped plate, sliding blocks are connected in the sliding grooves, the tops of the two sliding blocks are respectively fixedly connected with a first frame rod and a second frame rod, positioning grooves are formed in the opposite sides of the first frame rod and the second frame rod, the directions of the two positioning grooves are opposite, a same first winding drum is inserted between the two positioning grooves, a second opening is formed in the sliding block, a first opening is formed in one side, away from the sliding block, of the sliding grooves, a pull rod with the same L shape is inserted between the first opening and the second opening, a stop block is fixedly connected to one end, close to the sliding block, of the two pull rods, a same grab handle is fixedly connected with the two pull rods, third openings are formed in the first frame rod and the second frame rod, and a same inserting rod is inserted between the two third openings.
Preferably, the bottom of the I-shaped plate is fixedly connected with four supporting legs which are distributed in corners, the supporting legs are rotatably connected with rollers, and the I-shaped plate is provided with a jacking mechanism.
Preferably, the mechanism is lifted on top is including seting up in the location mouth of worker shaped plate top intermediate position, and location mouthful interpolation is equipped with the montant, montant bottom fixedly connected with backing plate, and the both ends of backing plate form the rake angle, and the guide slot has all been seted up to the both sides of montant, and sliding connection has the guide block in the guide slot, and guide block top fixedly connected with spring, the top of spring and the top inner wall fixed connection of guide slot, fixed connection between guide block and the location mouth.
Preferably, the mounting groove has all been seted up to the front and back of location mouth, rotates between the inner wall of mounting groove both sides to be connected with the clamp plate of same L shape, and the bottom of clamp plate rotates and is connected with the roller, the internal surface contact of roller and backing plate.
Preferably, both ends of the inner surface of the backing plate are provided with positioning convex strips with arc-shaped sections.
Preferably, the front end of the second frame rod is provided with an ear block, the ear block is rotatably connected with an inner shaft, the inner shaft is sleeved with the second winding drum and the locking sleeve, the locking sleeve is in threaded connection with the inner shaft, and the inner shaft is connected with a transmission mechanism.
Preferably, drive mechanism includes loop bar and the axostylus axostyle that distributes from top to bottom, loop bar fixed connection in the lateral surface of second hack lever, and the axostylus axostyle rotates to be connected in the lateral surface of second hack lever, rotates on the loop bar to be connected with the jack-post, all overlaps on jack-post and the axostylus axostyle to be established and is fixed with the band pulley, and the cover is equipped with in the same belt and all overlaps on the axostylus axostyle and is established and be fixed with the gear between two band pulleys, two gear engagement, the jack-post is connected with props tight mechanism.
Preferably, the tightening mechanism comprises a groove plate, the inner side of the groove plate is slidably connected with two movable blocks which are vertically distributed, the inner side of each movable block is fixedly connected with a clamping plate, a bidirectional screw rod is connected in the groove plate in a rotating mode, the bidirectional screw rod is in threaded connection with the movable blocks, the outer side face of the second frame rod is provided with an inlet, the inlet is communicated with the positioning groove, and the two clamping plates extend into the inlet.
Preferably, the outer side of the groove plate is provided with a butt joint rod, and the butt joint rod is inserted into the inner side surface of the shaft column.
Compared with the prior art, the invention provides a construction method of a modified asphalt waterproof coiled material, which has the following beneficial effects:
1. the modified asphalt waterproof coiled material construction method comprises the steps of firstly installing a first reel with a waterproof coiled material on a paving device, then moving the device to the position near a base layer, determining a paving area according to the orientation of the base layer, adjusting the position of the device, enabling the orientation of a I-shaped plate to be parallel to the orientation of the base layer, completing the positioning of a paving route, then pulling out the free end of the coiled material from the first reel, fixing the free end of the coiled material to the paving area, then holding a handle to pull backwards, enabling a pull rod to pull a slider, a first frame rod, a second frame rod, an inserted bar and the whole of the first reel backwards through a stop block, enabling the first reel to release the coiled material, naturally paving the coiled material on the base layer, effectively ensuring that the end of the first reel cannot be inclined when being paved and adhered along a straight line, and being provided with positioning grooves, enabling the first frame rod to pull backwards when the first reel is installed due to the two positioning grooves are opposite in orientation, enabling the first frame rod to be pulled backwards, enabling the first frame rod and enabling the other end of the first frame rod to be inserted into the positioning grooves on the second frame rod, and enabling the other end of the first reel to be conveniently and enabling the first frame rod to be quickly detached.
2. This modified asphalt waterproofing membrane construction method, through being provided with the gyro wheel, can be more convenient laborsaving when removing the device, and can not cause worker's shaped plate and ground to take place to use wearing and tearing, lead to the route location inaccurate, after the location finishes, both hands hold two clamp plates respectively, and push down it simultaneously, the clamp plate rotates, the roller of clamp plate bottom can move to the intermediate position of backing plate, can push down the backing plate and contact with ground, then make the whole of worker's shaped plate supported, make the gyro wheel unsettled, thereby ensure when subsequently laying, the position of device can not take place to remove, thereby guarantee that the coiled material lays along the straight line all the time, and be provided with the location sand grip, when the roller moves to the position between location sand grip and the montant, can form the fender through the outside removal of location sand grip to the roller, thereby ensure that the clamp plate is stable at this position.
3. This modified asphalt waterproofing membrane construction method, through being provided with the second reel, can be when paving and pasting, pull out the free end of barrier film on the coiled material, and fix to the second reel, and promote the whole of frid and splint inwards to the import, make two splint enter into the tip of first reel, then rotate two-way screw rod, make two splint carry out the removal of keeping away from each other, then prop tightly first reel, when subsequently paving, first reel can drive the whole rotation of frid and splint in step, then drive the jack-post through the butt joint pole and rotate, then through the transmission cooperation of belt and two band pulleys, order about the axostylus axostyle and rotate, then through the meshing transmission of two gears, order about interior axle and second reel and rotate, and the turning to of second reel and first reel is opposite, can carry out the rolling to the barrier film through the second reel, thereby prevent that the barrier film from dragging subaerial in the work progress.
Drawings
FIG. 1 is a schematic view of the overall structure of a paving device in the construction method of the modified asphalt waterproof roll material provided by the invention;
FIG. 2 is a schematic view of a driving mechanism installation structure in the construction method of the modified asphalt waterproof roll material provided by the present invention;
FIG. 3 is a schematic view of a first reel installation structure in the construction method of the modified asphalt waterproof roll provided by the present invention;
FIG. 4 is a schematic view of a mounting structure of a tightening mechanism in the construction method of the modified asphalt waterproof roll material according to the present invention;
FIG. 5 is a schematic view of a matching structure of a pull rod and a slide block in the construction method of the modified asphalt waterproof roll material provided by the invention;
FIG. 6 is a schematic view of a mounting structure of a jacking mechanism in the construction method of the modified asphalt waterproof roll provided by the invention;
FIG. 7 is a schematic view of a base plate structure in the construction method of the modified asphalt waterproof roll material according to the present invention;
FIG. 8 is a schematic view of a second reel installation structure in the construction method of the modified asphalt waterproofing membrane according to the present invention;
FIG. 9 is an enlarged schematic structural view of the site A in the construction method of the modified asphalt waterproofing membrane provided by the present invention;
fig. 10 is a schematic structural view of a tightening mechanism in the construction method of the modified asphalt waterproof roll material provided by the invention.
In the figure: 1. a I-shaped plate; 2. a chute; 3. a slider; 4. a first frame bar; 5. a second frame bar; 6. a first opening; 7. a pull rod; 8. a stopper; 9. a second opening; 10. a grab handle; 11. a third opening; 12. inserting a rod; 13. positioning a groove; 14. a first reel; 15. a support leg; 16. a roller; 17. a vertical rod; 18. a backing plate; 19. a guide groove; 20. a guide block; 21. a spring; 22. mounting grooves; 23. pressing a plate; 24. a roll shaft; 25. positioning the convex strip; 26. an ear piece; 27. an inner shaft; 28. a second reel; 29. a locking sleeve; 30. a shaft lever; 31. a loop bar; 32. a column shaft; 33. a gear; 34. a pulley; 35. a belt; 36. a docking rod; 37. a groove plate; 38. a movable block; 39. a splint; 40. a bidirectional screw.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are merely for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention.
Example 1
Referring to fig. 1 to 3 and 5 to 7, the construction method of the modified asphalt waterproof roll includes the following steps:
s1, cleaning a base layer;
s2, paving and pasting coiled materials, namely installing the modified asphalt waterproof coiled materials on a paving and pasting device, sequentially paving and pasting a first waterproof coiled material belt, a second waterproof coiled material belt, a third waterproof coiled material belt and a fourth waterproof coiled material belt along one side of the construction surface through a construction device until the construction surface is fully paved, and reserving a 10cm gap between every two adjacent waterproof coiled material belts;
s3, checking whether the coiled material is laid and pasted smoothly;
s4, rolling the paved waterproof coiled material to ensure that the waterproof coiled material is tightly and firmly bonded;
and S5, head closing processing.
Further, spread and paste the device including worker's shaped plate 1, a serial communication port, spout 2 has all been seted up to worker's shaped plate 1 top both sides, sliding connection has slider 3 in spout 2, 3 tops of two sliders are first hack lever 4 and second hack lever 5 of fixedly connected with respectively, constant head tank 13 has all been seted up to the one side that first hack lever 4 and second hack lever 5 are relative, the orientation of two constant head tank 13 is opposite, it is equipped with same first reel 14 to insert between two constant head tank 13, second opening 9 has been seted up on slider 3, first opening 6 has been seted up to one side that slider 3 was kept away from to spout 2, insert the pull rod 7 that is equipped with same L shape between first opening 6 and the second opening 9, pull rod 7 is close to the one end fixedly connected with dog 8 of slider 3, same grab handle 10 of fixedly connected with between two pull rods 7, third opening 11 has all been seted up on first hack lever 4 and the second hack lever 5, insert between two third openings 11 and be equipped with same inserted bar 12.
Furthermore, the bottom of the I-shaped plate 1 is fixedly connected with four supporting legs 15 which are distributed at corners, the supporting legs 15 are rotatably connected with rollers 16, and the I-shaped plate 1 is provided with a jacking mechanism.
Further, the mechanism is lifted on top is including seting up in the location mouth of 1 top intermediate position of worker's shaped plate, location mouthful interpolation is equipped with montant 17, montant 17 bottom fixedly connected with backing plate 18, the both ends of backing plate 18 form the perk, guide slot 19 has all been seted up to montant 17's both sides, sliding connection has guide block 20 in the guide slot 19, guide block 20 top fixedly connected with spring 21, the top of spring 21 and the top inner wall fixed connection of guide slot 19, fixed connection between guide block 20 and the location mouth.
Further, the front and back of location mouth has all been seted up mounting groove 22, rotates between the inner wall of mounting groove 22 both sides to be connected with the clamp plate 23 of same L shape, and the bottom of clamp plate 23 rotates and is connected with roller 24, the internal surface contact of roller 24 and backing plate 18.
Furthermore, both ends of the inner surface of the backing plate 18 are provided with positioning convex strips 25 with arc-shaped sections.
When the waterproof roll is used, in the step S, the first winding drum 14 wound with the waterproof roll is installed on the paving and pasting device, the device is moved to the position near the base layer, after the paving area is determined according to the orientation of the base layer, the position of the device is adjusted, the orientation of the I-shaped plate 1 is parallel to the orientation of the base layer, the positioning of the paving and pasting route is completed, the free end of the roll is pulled out from the first winding drum 14, the free end of the roll is fixed to the paving and pasting area, the grab handle 10 is held and pulled backwards, the pull rod 7 pulls the whole of the sliding block 3, the first rack rod 4, the second rack rod 5, the inserted rod 12 and the first winding drum 14 backwards through the stop block 8, the first winding drum 14 releases the roll, the roll is naturally paved and pasted on the base layer, so that the roll is effectively ensured not to be paved and pasted along a straight line, and the positioning grooves 13 are arranged, and the orientation of the two positioning grooves 13 is opposite, when the first winding drum 14 is installed, the first frame rod 4 can be pulled backwards firstly, so that the first frame rod 4 and the second frame rod 5 are staggered, then the end part of the first winding drum 14 is inserted into the positioning groove 13 on the second frame rod 5, then the first frame rod 4 is pushed back, so that the other end part of the first winding drum 14 can enter the positioning groove 13 on the first frame rod 4, then the inserted bar 12 is inserted into the third opening 11 on the first frame rod 4, so that the first winding drum 14 can be quickly installed and is convenient to detach, further, the roller 16 is arranged, so that the device can be moved more conveniently and more labor-saving, the work-shaped plate 1 and the ground cannot be worn due to use, the route positioning is inaccurate, after the positioning is finished, two pressing plates 23 are respectively held by two hands and are pressed downwards at the same time, the pressing plates 23 rotate, the roller shaft 24 at the bottom ends of the pressing plates 23 can move towards the middle position of the backing plate 18, can push down backing plate 18 and contact with ground, then make worker's shaped plate 1's whole supported, make gyro wheel 16 unsettled, thereby ensure when subsequently laying, the position of device can not take place to remove, thereby guarantee that the coiled material is laid along the straight line all the time and paste, and be provided with location sand grip 25, when roller 24 removed the position between location sand grip 25 and the montant 17, can form the fender through the outside removal of location sand grip 25 to roller 24, thereby ensure that clamp plate 23 stabilizes in this position.
Example 2
Referring to fig. 1 to 10, the construction method of the modified asphalt waterproof roll includes the following steps:
s1, cleaning a base layer;
s2, paving and pasting a coiled material, namely installing the modified asphalt waterproof coiled material on a paving and pasting device, and paving and pasting a first waterproof coiled material belt, a second waterproof coiled material belt, a third waterproof coiled material belt and a fourth waterproof coiled material belt along one side of the construction surface in sequence through a construction device until the construction surface is fully paved, wherein a 15cm gap is reserved between every two adjacent waterproof coiled material belts;
s3, checking whether the coiled materials are laid and pasted smoothly;
s4, rolling the paved waterproof coiled material to ensure that the waterproof coiled material is tightly and firmly bonded;
and S5, head closing processing.
Further, spread and paste the device including worker's shaped plate 1, a serial communication port, spout 2 has all been seted up to worker's shaped plate 1 top both sides, sliding connection has slider 3 in spout 2, 3 tops of two sliders are first hack lever 4 and second hack lever 5 of fixedly connected with respectively, constant head tank 13 has all been seted up to the one side that first hack lever 4 and second hack lever 5 are relative, the orientation of two constant head tank 13 is opposite, it is equipped with same first reel 14 to insert between two constant head tank 13, second opening 9 has been seted up on slider 3, first opening 6 has been seted up to one side that slider 3 was kept away from to spout 2, insert the pull rod 7 that is equipped with same L shape between first opening 6 and the second opening 9, pull rod 7 is close to the one end fixedly connected with dog 8 of slider 3, same grab handle 10 of fixedly connected with between two pull rods 7, third opening 11 has all been seted up on first hack lever 4 and the second hack lever 5, insert between two third openings 11 and be equipped with same inserted bar 12.
Furthermore, the bottom of the I-shaped plate 1 is fixedly connected with four supporting legs 15 which are distributed at corners, the supporting legs 15 are rotatably connected with rollers 16, and the I-shaped plate 1 is provided with a jacking mechanism.
Further, the mechanism is lifted on top is including seting up in the location mouth of 1 top intermediate position of worker's shaped plate, location mouthful interpolation is equipped with montant 17, montant 17 bottom fixedly connected with backing plate 18, the both ends of backing plate 18 form the perk, guide slot 19 has all been seted up to montant 17's both sides, sliding connection has guide block 20 in the guide slot 19, guide block 20 top fixedly connected with spring 21, the top of spring 21 and the top inner wall fixed connection of guide slot 19, fixed connection between guide block 20 and the location mouth.
Further, the front and back of location mouth has all been seted up mounting groove 22, rotates between the inner wall of mounting groove 22 both sides to be connected with the clamp plate 23 of same L shape, and the bottom of clamp plate 23 rotates and is connected with roller 24, the internal surface contact of roller 24 and backing plate 18.
Furthermore, both ends of the inner surface of the backing plate 18 are provided with positioning convex strips 25 with arc-shaped sections.
Furthermore, the front end of the second frame rod 5 is provided with an ear block 26, the ear block 26 is rotatably connected with an inner shaft 27, the inner shaft 27 is sleeved with a second winding drum 28 and a locking sleeve 29, the locking sleeve 29 is in threaded connection with the inner shaft 27, and the inner shaft 27 is connected with a transmission mechanism.
Further, drive mechanism includes loop bar 31 and axostylus axostyle 30 that distributes from top to bottom, loop bar 31 fixed connection is in the lateral surface of second hack lever 5, axostylus axostyle 30 rotates and connects in the lateral surface of second hack lever 5, it is connected with jack-post 32 to rotate on the loop bar 31, all overlap on jack-post 32 and the axostylus axostyle 30 and establish and be fixed with band pulley 34, it is fixed with gear 33 all to overlap on axle 27 and the axostylus axostyle 30 in the same belt 35 to overlap between two band pulleys 34, two gear 33 meshes, jack-post 32 is connected with props tight mechanism.
Further, prop tight mechanism and include frid 37, frid 37 inboard sliding connection has two movable blocks 38 that distribute from top to bottom, and the inboard fixedly connected with splint 39 of movable block 38, frid 37 internal rotation are connected with two-way screw rod 40, and two-way screw rod 40 and movable block 38 threaded connection, the import has been seted up to the lateral surface of second hack lever 5, and import and constant head tank 13 communicate with each other, and two splint 39 stretch into in the import.
Furthermore, an abutment rod 36 is disposed outside the slot plate 37, and the abutment rod 36 is inserted into the inner side surface of the shaft column 32.
When the waterproof roll is used, in the step S, the first winding drum 14 wound with the waterproof roll is installed on the paving and pasting device, the device is moved to the position near the base layer, after the paving area is determined according to the orientation of the base layer, the position of the device is adjusted, the orientation of the I-shaped plate 1 is parallel to the orientation of the base layer, the positioning of the paving and pasting route is completed, the free end of the roll is pulled out from the first winding drum 14, the free end of the roll is fixed to the paving and pasting area, the grab handle 10 is held and pulled backwards, the pull rod 7 pulls the whole of the sliding block 3, the first rack rod 4, the second rack rod 5, the inserted rod 12 and the first winding drum 14 backwards through the stop block 8, the first winding drum 14 releases the roll, the roll is naturally paved and pasted on the base layer, so that the roll is effectively ensured not to be paved and pasted along a straight line, and the positioning grooves 13 are arranged, and the orientation of the two positioning grooves 13 is opposite, when the first winding drum 14 is installed, the first frame rod 4 can be pulled backwards firstly, so that the first frame rod 4 and the second frame rod 5 are staggered, then the end part of the first winding drum 14 is inserted into the positioning groove 13 on the second frame rod 5, then the first frame rod 4 is pushed back, so that the other end part of the first winding drum 14 can enter the positioning groove 13 on the first frame rod 4, then the inserted bar 12 is inserted into the third opening 11 on the first frame rod 4, so that the first winding drum 14 can be quickly installed and is convenient to detach, further, the roller 16 is arranged, so that the device can be moved more conveniently and more labor-saving, the work-shaped plate 1 and the ground cannot be worn due to use, the route positioning is inaccurate, after the positioning is finished, two pressing plates 23 are respectively held by two hands and are pressed downwards at the same time, the pressing plates 23 rotate, the roller shaft 24 at the bottom ends of the pressing plates 23 can move towards the middle position of the backing plate 18, the backing plate 18 can be pressed down and contacted with the ground, so that the whole of the I-shaped plate 1 is supported, the roller 16 is suspended, the position of the device can not move when the subsequent paving is carried out, the coiled material is guaranteed to be paved along a straight line all the time, the positioning convex strip 25 is arranged, when the roller shaft 24 moves to the position between the positioning convex strip 25 and the vertical rod 17, the outward movement of the roller shaft 24 can be resisted through the positioning convex strip 25, the pressing plate 23 is guaranteed to be stabilized at the position, further, the second winding drum 28 is arranged, the free end of the isolating membrane on the coiled material can be pulled out and fixed on the second winding drum 28 when the paving is carried out, and the whole of the groove plate 37 and the clamping plate 39 is pushed inwards, make two splint 39 enter into the tip of first reel 14 in, then rotate two-way screw 40, make two splint 39 carry out the removal of keeping away from each other, then prop tightly first reel 14, when subsequently laying, first reel 14 can drive the whole rotation of frid 37 and splint 39 simultaneously, then drive the jack post 32 through butt joint pole 36 and rotate, then through the transmission fit of belt 35 and two band pulleys 34, it rotates to drive axostylus axostyle 30, then through the meshing transmission of two gears 33, it rotates to drive interior axle 27 and second reel 28, and the turn-around of second reel 28 and first reel 14 is opposite, can roll up the barrier film through second reel 28, thereby prevent that the barrier film from dragging subaerial in the work progress.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (10)

1. The construction method of the modified asphalt waterproof coiled material is characterized by comprising the following steps:
s1, cleaning a base layer;
s2, paving and pasting coiled materials, namely installing the modified asphalt waterproof coiled materials on a paving and pasting device, paving and pasting a first waterproof coiled material belt, a second waterproof coiled material belt, a third waterproof coiled material belt and a fourth waterproof coiled material belt along one side of the construction surface through a construction device in sequence until the construction surface is fully paved, and reserving a gap of 10-15cm between every two adjacent waterproof coiled material belts;
s3, checking whether the coiled material is laid and pasted smoothly;
s4, rolling the paved waterproof coiled material to ensure that the waterproof coiled material is tightly and firmly bonded;
and S5, head closing processing.
2. The construction method of the modified asphalt waterproof roll according to claim 1, wherein the paving device comprises a I-shaped plate (1), and is characterized in that sliding grooves (2) are formed in two sides of the top of the I-shaped plate (1), sliding blocks (3) are slidably connected in the sliding grooves (2), a first frame rod (4) and a second frame rod (5) are fixedly connected to the tops of the two sliding blocks (3) respectively, positioning grooves (13) are formed in the opposite surfaces of the first frame rod (4) and the second frame rod (5), the two positioning grooves (13) are opposite in direction, the same first bobbin (14) is inserted between the two positioning grooves (13), a second opening (9) is formed in the sliding block (3), a first opening (6) is formed in one side of the sliding groove (2) far away from the sliding block (3), the same L-shaped pull rod (7) is inserted between the first opening (6) and the second opening (9), a stop block (8) is fixedly connected to one end of the pull rod (7) close to the sliding block (3), the same handle (10) is connected between the two pull rods (7), third frame rod (4) and the second frame rod (5) are respectively inserted between the same third opening (11), and a third opening (11) is inserted between the two insertion rods (11).
3. The construction method of the modified asphalt waterproof roll material as claimed in claim 2, wherein the bottom of the I-shaped plate (1) is fixedly connected with four supporting legs (15) which are distributed in corners, the supporting legs (15) are rotatably connected with rollers (16), and the I-shaped plate (1) is provided with a jacking mechanism.
4. The construction method of the modified asphalt waterproof roll according to claim 3, wherein the jacking mechanism comprises a positioning opening arranged in the middle of the top of the I-shaped plate (1), a vertical rod (17) is inserted into the positioning opening, a backing plate (18) is fixedly connected to the bottom of the vertical rod (17), tilt angles are formed at two ends of the backing plate (18), guide grooves (19) are formed in two sides of the vertical rod (17), guide blocks (20) are slidably connected in the guide grooves (19), springs (21) are fixedly connected to the tops of the guide blocks (20), the tops of the springs (21) are fixedly connected with the inner walls of the top of the guide grooves (19), and the guide blocks (20) are fixedly connected with the positioning opening.
5. The construction method of the modified asphalt waterproof roll material as claimed in claim 4, wherein mounting grooves (22) are formed in the front and rear of the positioning opening, the same L-shaped pressing plate (23) is rotatably connected between the inner walls of the two sides of the mounting grooves (22), the bottom end of the pressing plate (23) is rotatably connected with a roller shaft (24), and the roller shaft (24) is in contact with the inner surface of the base plate (18).
6. The construction method of modified asphalt waterproof roll material according to claim 5, characterized in that both ends of the inner surface of the backing plate (18) are provided with positioning ribs (25) having an arc-shaped cross section.
7. The construction method of the modified asphalt waterproof roll as claimed in claim 2, wherein the front end of the second frame rod (5) is provided with an ear block (26), the ear block (26) is rotatably connected with an inner shaft (27), the inner shaft (27) is sleeved with a second winding drum (28) and a locking sleeve (29), the locking sleeve (29) is in threaded connection with the inner shaft (27), and the inner shaft (27) is connected with a transmission mechanism.
8. The construction method of the modified asphalt waterproof roll as claimed in claim 7, wherein the transmission mechanism comprises a loop bar (31) and a shaft rod (30) which are distributed up and down, the loop bar (31) is fixedly connected to the outer side surface of the second frame bar (5), the shaft rod (30) is rotatably connected to the outer side surface of the second frame bar (5), the loop bar (31) is rotatably connected with a shaft column (32), belt wheels (34) are respectively sleeved and fixed on the shaft column (32) and the shaft rod (30), a same belt (35) is sleeved between the two belt wheels (34), an inner shaft (27) and the shaft rod (30) are respectively sleeved and fixed with gears (33), the two gears (33) are engaged, and the shaft column (32) is connected with a tightening mechanism.
9. The construction method of the modified asphalt waterproof roll as claimed in claim 8, wherein the tightening mechanism comprises a groove plate (37), two movable blocks (38) which are distributed up and down are slidably connected to the inner side of the groove plate (37), clamping plates (39) are fixedly connected to the inner sides of the movable blocks (38), a bidirectional screw (40) is rotatably connected to the groove plate (37), the bidirectional screw (40) is in threaded connection with the movable blocks (38), an inlet is formed in the outer side surface of the second frame rod (5), the inlet is communicated with the positioning groove (13), and the two clamping plates (39) extend into the inlet.
10. The construction method of the modified asphalt waterproof roll according to claim 9, wherein the butt joint rod (36) is provided on the outer side of the groove plate (37), and the butt joint rod (36) is inserted into the inner side surface of the shaft column (32).
CN202211539319.2A 2022-12-02 2022-12-02 Construction method of modified asphalt waterproof coiled material Pending CN115749165A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211539319.2A CN115749165A (en) 2022-12-02 2022-12-02 Construction method of modified asphalt waterproof coiled material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211539319.2A CN115749165A (en) 2022-12-02 2022-12-02 Construction method of modified asphalt waterproof coiled material

Publications (1)

Publication Number Publication Date
CN115749165A true CN115749165A (en) 2023-03-07

Family

ID=85342709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211539319.2A Pending CN115749165A (en) 2022-12-02 2022-12-02 Construction method of modified asphalt waterproof coiled material

Country Status (1)

Country Link
CN (1) CN115749165A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116378330A (en) * 2023-06-07 2023-07-04 山西一建集团有限公司 Automatic crawling connection device for high-molecular self-adhesive film waterproof coiled material

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116378330A (en) * 2023-06-07 2023-07-04 山西一建集团有限公司 Automatic crawling connection device for high-molecular self-adhesive film waterproof coiled material
CN116378330B (en) * 2023-06-07 2023-08-15 山西一建集团有限公司 Automatic crawling connection device for high-molecular self-adhesive film waterproof coiled material

Similar Documents

Publication Publication Date Title
CN115749165A (en) Construction method of modified asphalt waterproof coiled material
CN216155170U (en) Cable laying auxiliary device that acts as go-between
CN113758406B (en) Land collection measuring equipment and use method thereof
CN113502834B (en) High steep slope geotechnical material laying device
CN113955591A (en) Winding and unwinding device convenient for winding type cable reel and using method thereof
CN110593540B (en) Building ground cement preliminary laying equipment
CN213595489U (en) Non-woven fabric winding device
CN113406761A (en) Optical fiber laying device and method for concrete pool leakage detection
CN114934428A (en) Concrete road surface curing means
CN212103590U (en) Highway engineering film paving device
CN207918150U (en) Cable unwinding device with cable disk
CN107060603B (en) Preparation method of curtain surface of inorganic fiber composite fireproof rolling curtain
CN216004658U (en) Waterproofing membrane laying device
CN210659005U (en) Waterproofing membrane laying device
CN212533640U (en) Sideline laying-out device is used in construction of highway curb slipform
CN108468558B (en) Tunnel waterproof board laying trolley with multiple degrees of freedom adjusting function
CN218346911U (en) Laminating machine that concrete for building was convenient for clearance
CN218809602U (en) Cable laying device
CN220203227U (en) Building waterproof cloth construction layout device
CN218911539U (en) Automatic bonding waterproof coiled material
CN217420283U (en) Beam-slab roof rigid waterproof construction device
CN220078223U (en) Take-up and pay-off device for urban and rural land planning
CN220598079U (en) Geotextile cutting and laying integrated device
CN210973205U (en) Folding device is used in medical cotton processing of convenient neat rolling
CN216426375U (en) Cable erecting device for building electromechanical installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20230307