CN115733243A CN202211336318.8A CN202211336318A CN115733243A CN 115733243 A CN115733243 A CN 115733243A CN 202211336318 A CN202211336318 A CN 202211336318A CN 115733243 A CN115733243 A CN 115733243A
Authority
CN
China
Prior art keywords
data
module
power
sewage treatment
electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211336318.8A
Other languages
Chinese (zh)
Inventor
徐巍峰
钟晓红
罗曼
於岳祥
沈海江
周建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Zhejiang Xiaoshan District Power Supply Co ltd
Zhejiang Zhongxin Electric Power Engineering Construction Co Ltd
Original Assignee
State Grid Zhejiang Xiaoshan District Power Supply Co ltd
Zhejiang Zhongxin Electric Power Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Zhejiang Xiaoshan District Power Supply Co ltd, Zhejiang Zhongxin Electric Power Engineering Construction Co Ltd filed Critical State Grid Zhejiang Xiaoshan District Power Supply Co ltd
Priority to CN202211336318.8A priority Critical patent/CN115733243A/en
Publication of CN115733243A publication Critical patent/CN115733243A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of power systems, and discloses an information control processing system and a processing method of a power system, which comprise an information data acquisition module, a data processing module, a storage library module, a CPU control module, a power controller module, a fault early warning module and a man-machine interaction module, wherein the information data acquisition module is used for acquiring electric quantity data and sewage treatment quantity data of a sewage treatment plant and transmitting the acquired data to the data processing module, and the data processing module is used for classifying, calculating, counting and comparing the electric quantity data and the sewage treatment quantity data of the sewage treatment plant and then transmitting the data to a storage library module and the CPU control module.

Description

Information control processing system and processing method of power system
Technical Field
The invention relates to the technical field of power systems, in particular to an information control processing system and a processing method of a power system.
Background
The electric power system is an electric energy production and consumption system composed of links such as a power plant, a power transmission and transformation line, a power supply and distribution station, electricity utilization and the like, along with rapid development of times and large energy consumption, because human beings have high consumption and high emission to nature, the living environment of the people is increasingly damaged, natural resources are increasingly reduced, in order to realize sustainable development, the treated sewage resources are water resource protection, the use of a sewage treatment plant needs the electric power system to make corresponding information and control in each link, so that the reasonable consumption of the electric power of the sewage treatment plant is ensured, a large amount of electric energy and chemical agents are needed in the sewage treatment process of the sewage treatment plant, the energy consumption and the operation cost exist, and great obstruction is played on the construction and development of the urban sewage treatment plant.
In the prior art, low-energy-consumption water pump equipment is selected for saving energy of a sewage treatment plant, exploration and research are carried out on the frequency conversion aspect of the equipment, and the equipment is optimized, so that the power consumption of the water pump is reduced, but the mode saves energy to a certain extent, but the effect is not obvious, and therefore a better energy consumption saving method is urgently needed.
Disclosure of Invention
Solves the technical problem
In order to overcome the defects in the prior art, the invention provides an information control processing system and a processing method of an electric power system, which control the electric power of each electric device of a sewage treatment plant, utilize the sewage fall to store electric power and supply power supply control during power failure through a CPU control module, and provide a better method for saving electric quantity and energy consumption for the sewage treatment plant so as to solve the problems provided in the background technology.
Technical scheme
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides an information control processing system of electric power system, includes information data acquisition module, data processing module, storage module, CPU control module, electric power controller module, trouble early warning module and man-machine interaction module, information data acquisition module is used for sewage treatment plant electric quantity data acquisition and sewage treatment capacity data to gather the data transmission to data processing module, data processing module is used for sewage treatment plant's electric quantity data and sewage treatment capacity data to classify, calculate, count, contrast and handle the back with data transmission to storage module and CPU control module, CPU control module is used for the electric power control of each consumer of sewage treatment plant, utilizes the power supply control when sewage fall electrical storage control and outage, if electric power breaks down with information transmission to electric power trouble early warning module.
In a preferred embodiment, the CPU control module includes an electrical equipment control unit, a power generation control unit, and a power outage replenishment control unit, the electrical equipment control unit automatically controls the power supply of a certain electrical equipment of the sewage treatment plant to be turned on or off according to the data analysis result processed by the data processing module, the electrical equipment includes a water pump, a feeding device, lighting and other equipment power consumption, and the data analysis result is divided into two cases: firstly, in the change of rain and snow weather and drought weather, the water quantity in the sewage pool is increased due to the increase of the rain and snow quantity in the rain and snow weather, the numerical values of the flow meter and the water level meter are increased, and the opposite is true in the drought weather; according to the change of summer and winter, the water consumption of people is high in summer and the water consumption is low in winter, the data processing module compares data and transmits the information to the electric equipment control unit, and the electric equipment control unit turns on or off a power switch of the electric equipment; the power generation control unit is used for treating sewage in a sewage treatment plant and then enabling the treated sewage to enter a water collecting well, and a hydraulic generator is arranged in the water collecting well to convert kinetic energy of water into electric energy by utilizing the principle of water level drop, and the electric energy is used for supplying power to each electric device of the sewage treatment plant; the power-off supply control unit supplies the generated electric energy to the sewage treatment plant or the city in time when the sewage treatment plant or the city power grid is powered off.
In a preferred embodiment, the repository module is used for the sewage treatment plant to store the data of the power consumption and the sewage treatment capacity according to time, season or other manners, the power failure early warning module is used for each power consumption device of the sewage treatment plant, if a certain device fails, a failure signal and a positioning signal are transmitted to the human-computer interaction module, and the human-computer interaction module is used for receiving and transmitting information of a mobile phone and a PC of a power operation and maintenance worker.
In a preferred embodiment, the data acquisition module comprises an electric quantity data acquisition unit and a sewage treatment capacity acquisition unit, the electric quantity data acquisition unit adopts an intelligent ammeter to acquire the electric quantity used by a sewage treatment plant, the intelligent ammeter adopts a current sensor to convert a current signal into an electronic measurement signal, a voltage divider resistor or a voltage transformer is used to convert a voltage signal into the electronic measurement signal, a measurement chip is used to convert analog signals of the voltage transformer and the current transformer into data signals, a mathematical integral operation is used to output a pulse signal with the frequency in direct proportion to the electric energy, and the pulse signal is sent to a microcomputer to be processed and then displayed on a liquid crystal display screen; the sewage treatment capacity acquisition unit acquires the sewage inflow rate by using the flowmeter and acquires the sewage storage capacity in the sewage pool by using the water level meter.
In a preferred embodiment, the data processing module comprises an electric quantity data processing unit and a sewage treatment quantity data processing unit, the electric quantity data processing unit performs data completion and distortion data smoothing on missing data of the intelligent electric meter, automatically processes zero-returning replacement mutual inductance metering service according to characteristics of an electric quantity system, and performs compensation on electric quantity data according to a comparison and verification result of the electric quantity data; the sewage treatment capacity data processing unit establishes a curve graph for the relation among the water level flow, the water level area and the water level flow rate, analyzes and checks the rationality of the water level flow curve, calculates an average flow meter according to a daily, weekly, monthly or yearly mode, compares data and prepares electricity utilization and sewage treatment in advance for the CPU control module.
In a preferred embodiment, the repository module loads archive data by using a preposed communication platform relational database, and the communication platform relational database is used for data frame analysis and original data unloading, converts an original binary data frame into data in a CPU identification format, converts the data into service data, and stores the service data into the application data processing module.
In a preferred embodiment, the power failure early warning module comprises a power failure information transmission unit and a fault equipment positioning information transmission unit, wherein the power failure information transmission unit transmits a signal to the man-machine interaction module when no current or voltage is transmitted on the electric equipment; the fault equipment positioning information transmission unit is installed on the electric equipment, positioning information is timely transmitted to the man-machine interaction module when a certain power utilization fault occurs, the man-machine interaction module receives power fault early warning information through a mobile phone and a PC (personal computer) on a power operation and maintenance worker by utilizing network communication, and the man-machine interaction module quickly finds the position where the power failure information occurs according to positioning.
An information control processing method of an electric power system comprises the following specific steps:
101. the information data acquisition module acquires electric quantity data and sewage treatment capacity data of a sewage treatment plant, transmits the acquired data to the data processing module, and then the data processing module classifies, calculates, counts and contrasts the electric quantity data and the sewage treatment capacity data of the sewage treatment plant and transmits the data to the repository module and the CPU control module;
102. the repository module is used for storing the electric quantity data used by the sewage treatment plant and the sewage treatment quantity data in a classified manner according to time, seasons or other modes;
103. the CPU control module controls the power of each electric device of the sewage treatment plant, utilizes the sewage fall to store electricity and supplies power when the power is cut off, and transmits information to the power failure early warning module if the power fails;
104. the electric power failure early warning module is used for each electric device of a sewage treatment plant, if a certain device fails, a failure signal and a positioning signal are transmitted to the man-machine interaction module, and the man-machine interaction module is used for receiving and transmitting information of a mobile phone and a PC (personal computer) on an electric power operation and maintenance worker.
Advantageous effects
The invention provides an information control processing system and a processing method of a power system, which have the following beneficial effects:
according to the information control processing system and the information control processing method of the power system, the CPU control module is used for controlling the power of each electric device of the sewage treatment plant, controlling the electric power by using the sewage fall to store the electric power and controlling the power supply during power failure, so that a better method for saving electric quantity and energy consumption is provided for the sewage treatment plant.
Drawings
FIG. 1 is an overall system diagram of the present invention.
FIG. 2 is a block diagram of an information data collection module according to the present invention.
FIG. 3 is a block diagram of a data processing system according to the present invention.
FIG. 4 is a block diagram of the CPU control module of the present invention.
Fig. 5 is a block diagram of the power failure early warning system of the present invention.
Detailed Description
Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art.
Meanwhile, it should be understood that the sizes of the respective portions shown in the drawings are not drawn in an actual proportional relationship for the convenience of description.
The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the application, its application, or uses.
Techniques, methods, and apparatus known to those of ordinary skill in the relevant art may not be discussed in detail but are intended to be part of the specification where appropriate.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, further discussion thereof is not required in subsequent figures.
Embodiments of the application are applicable to computer systems/servers that are operational with numerous other general purpose or special purpose computing system environments or configurations. Examples of well known computing systems, environments, and/or configurations that may be suitable for use with computer systems/servers include, but are not limited to: personal computer systems, server computer systems, thin clients, thick clients, hand-held or laptop devices, microprocessor-based systems, set-top boxes, programmable consumer electronics, network personal computers, small computer systems, mainframe computer systems, and distributed cloud computing environments that include any of the above, and the like.
The computer system/server may be described in the general context of computer system-executable instructions, such as program modules, being executed by a computer system. Generally, program modules may include routines, programs, objects, components, logic, data structures, etc. that perform particular tasks or implement particular abstract data types. The computer system/server may be practiced in distributed cloud computing environments where tasks are performed by remote processing devices that are linked through a communications network. In a distributed cloud computing environment, program modules may be located in both local and remote computer system storage media including memory storage devices.
The invention provides a technical scheme that: the information control processing system of the power system comprises an information data acquisition module, a data processing module, a storage base module, a CPU control module, a power controller module, a fault early warning module and a human-computer interaction module, wherein the information data acquisition module is used for acquiring electric quantity data and sewage treatment quantity data of a sewage treatment plant and transmitting the acquired data to the data processing module, the data processing module is used for classifying, calculating, counting and comparing the electric quantity data and the sewage treatment quantity data of the sewage treatment plant and then transmitting the data to the storage base module and the CPU control module, the storage base module is used for classifying and storing the data of the electric quantity and the sewage treatment quantity of the sewage treatment plant according to time, season or other modes, the CPU control module is used for power control of each electric device of the sewage treatment plant, power supply and supply control by using sewage fall for power storage control and power supply during power failure, if power fails, information is transmitted to the power fault early warning module, the power fault early warning module is used for each electric device of the sewage treatment plant, and transmits a fault signal and a positioning signal to the human-computer interaction module when a certain device fails, and a human-computer interaction receiving personnel on the power interaction module.
The present embodiment is different from the prior art in that the CPU control module includes a consumer control unit, a power generation control unit, and a power outage replenishment control unit.
An information control processing system and a processing method of an electric power system are disclosed, which specifically comprise the following steps:
101. firstly, an information data acquisition module acquires electric quantity data and sewage treatment capacity data of a sewage treatment plant, transmits the acquired data to a data processing module, and then the data processing module classifies, calculates, counts and contrasts the electric quantity data and the sewage treatment capacity data of the sewage treatment plant and transmits the data to a repository module and a CPU control module;
in this embodiment, it is specifically noted that the data acquisition module includes an electric quantity data acquisition unit and a sewage treatment capacity acquisition unit, wherein the electric quantity data acquisition unit adopts an intelligent electric meter to acquire the power consumption of a sewage treatment plant, the intelligent electric meter adopts a current sensor to convert a current signal into an electronic measurement signal, a voltage divider resistor or a voltage transformer is used to convert a voltage signal into the electronic measurement signal, a measurement chip is used to convert analog signals of the voltage transformer and the current transformer into data signals, a mathematical integral operation is used to output a pulse signal with a frequency proportional to electric energy, and the pulse signal is sent to a microcomputer to be processed and then displayed on a liquid crystal display screen; the sewage treatment capacity acquisition unit acquires the sewage inflow rate by using the flowmeter and acquires the sewage storage capacity in the sewage tank by using the water level meter.
In this embodiment, it is specifically explained that the data processing module includes an electric quantity data processing unit and a sewage treatment quantity data processing unit, where the electric quantity data processing unit performs data completion and distortion data smoothing on missing data of the smart meter, automatically processes zero-returning replacement mutual inductance metering service according to characteristics of an electric quantity system, and performs compensation on electric quantity data according to a comparison and verification result of the electric quantity data, so as to ensure integrity and accuracy of the electric quantity data; the sewage treatment capacity data processing unit establishes a curve graph for the relation among the water level flow, the water level area and the water level flow velocity, analyzes and checks the reasonability of the water level flow curve, calculates an average flow meter according to a daily, weekly, monthly or yearly mode, compares data, and prepares electricity utilization preparation and sewage treatment preparation for a CPU control module in advance.
102. The repository module stores the electric quantity data used by the sewage treatment plant and the sewage treatment quantity data in a classified manner according to time, season or other manners;
in this embodiment, it is specifically explained that the repository module loads archive data by using a pre-communication platform relational database, where the communication platform relational database is used for data frame analysis and raw data dump, and converts raw binary data frames into data in a CPU identification format, and converts the data into service data, and stores the service data to the application data processing module.
103. The CPU control module controls the power of each electric device of the sewage treatment plant, utilizes the sewage fall to store electricity and supplies power to supply power when the power is cut off, and transmits information to the power failure early warning module if the power fails;
in this embodiment, it needs to be specifically stated that the CPU control module includes an electrical equipment control unit, a power generation control unit, and a power outage replenishment control unit, where the electrical equipment control unit automatically controls the power of a certain electrical equipment of the sewage treatment plant to be turned on or off according to a data analysis result processed by the data processing module, the electrical equipment includes a water pump, a feeding device, lighting, and other equipment power consumption, and the data analysis result is divided into two cases: firstly, in the change of rain and snow weather and dry weather, the accumulated water amount in the sewage pool is increased due to the increase of the rain and snow amount in the rain and snow weather, the numerical values of the flow meter and the water level meter are increased, and the opposite is true in the dry weather; secondly, according to changes in summer and winter, people use high water consumption in summer and use low water consumption in winter, the data processing module transmits information to the electric equipment control unit after comparing data, and the electric equipment control unit turns on or off a power switch of the electric equipment to achieve the purpose of saving electricity according to changes in conditions; the power generation control unit is used for treating sewage in a sewage treatment plant and then enabling the treated sewage to enter a water collecting well, and a hydraulic generator is arranged in the water collecting well to convert kinetic energy of water into electric energy by utilizing the principle of water level drop, and the electric energy is used for supplying power to each electric device of the sewage treatment plant; the power-off supply control unit supplies the generated electric energy to the sewage treatment plant or the city in time when the sewage treatment plant or the city power grid is powered off,
the present embodiment is not particularly limited.
101. The electric power failure early warning module is used for each electric device of a sewage treatment plant, if a certain device fails, a failure signal and a positioning signal are transmitted to the man-machine interaction module, and the man-machine interaction module is used for receiving and transmitting information of a mobile phone and a PC (personal computer) on an electric power operation and maintenance worker.
In this embodiment, it is specifically explained that the power failure early warning module includes a power failure information transmission unit and a failure device positioning information transmission unit, where the power failure information transmission unit transmits a signal to the human-computer interaction module when no current or voltage is transmitted on the electric device; the fault equipment positioning information transmission unit is installed on the electric equipment, positioning information is timely transmitted to the man-machine interaction module when a certain power utilization fault occurs, the man-machine interaction module receives power failure early warning information through a mobile phone and a PC (personal computer) on power operation and maintenance personnel by utilizing network communication, and the man-machine interaction module quickly finds the position where power failure information occurs according to positioning.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. An information control processing system of an electric power system, characterized in that: the system comprises an information data acquisition module, a data processing module, a storage base module, a CPU control module, a power controller module, a fault early warning module and a man-machine interaction module, wherein the information data acquisition module is used for acquiring electric quantity data and sewage treatment quantity data of a sewage treatment plant and transmitting the acquired data to the data processing module, the data processing module is used for classifying, calculating, counting and comparing the electric quantity data and the sewage treatment quantity data of the sewage treatment plant and then transmitting the data to the storage base module and the CPU control module, the CPU control module is used for controlling the power of each electric device of the sewage treatment plant, controlling the electric power by utilizing sewage fall and storing the electric power and supplying the power when the power is cut off, and transmitting the information to the power fault early warning module if the power fails.
2. The information control processing system of an electric power system according to claim 1, characterized in that: the CPU control module comprises an electric equipment control unit, a power generation control unit and a power-off supply control unit, the electric equipment control unit automatically controls the power supply of certain electric equipment of a sewage treatment plant to be switched on or switched off according to a data analysis result processed by the data processing module, the electric equipment comprises a water pump, a feeding device, illumination and other equipment power consumption, and the data analysis result is divided into two conditions: firstly, in the change of rain and snow weather and dry weather, the accumulated water amount in the sewage pool is increased due to the increase of the rain and snow amount in the rain and snow weather, the numerical values of the flow meter and the water level meter are increased, and the opposite is true in the dry weather; according to the change of summer and winter, the water consumption of people in summer is high, the water consumption in winter is low, the data processing module compares the data and then transmits the information to the electric equipment control unit, and the electric equipment control unit turns on or off a power switch of the electric equipment; the power generation control unit is used for treating sewage in a sewage treatment plant and then enabling the treated sewage to enter a water collecting well, and a hydraulic generator is arranged in the water collecting well to convert kinetic energy of water into electric energy by utilizing the principle of water level drop, and the electric energy is used for supplying power to each electric device of the sewage treatment plant; the power-off supply control unit supplies the generated electric energy to the sewage treatment plant or the city in time when the sewage treatment plant or the city power grid is powered off.
3. The information control processing system of an electric power system according to claim 1, characterized in that: the system comprises a repository module, an electric power failure early warning module, a man-machine interaction module and a power operation and maintenance personnel, wherein the repository module is used for storing data of power consumption and sewage treatment capacity of a sewage treatment plant in a classified manner according to time, seasons or other modes, the electric power failure early warning module is used for each electric power utilization device of the sewage treatment plant, if a certain device fails, a failure signal and a positioning signal are transmitted to the man-machine interaction module, and the man-machine interaction module is used for receiving and transmitting information of a mobile phone and a PC (personal computer) on the power operation and maintenance personnel.
4. The information control processing system of an electric power system according to claim 1, characterized in that: the data acquisition module comprises an electric quantity data acquisition unit and a sewage treatment capacity acquisition unit, the electric quantity data acquisition unit adopts an intelligent ammeter to acquire the power consumption of a sewage treatment plant, the intelligent ammeter adopts a current sensor to convert a current signal into an electronic measurement signal, a divider resistor or a voltage transformer is used to convert a voltage signal into the electronic measurement signal, a measurement chip is used to convert analog signals of the voltage transformer and the current transformer into data signals, a pulse signal with the frequency in direct proportion to electric energy is output by using mathematical integral operation, and the pulse signal is sent to a microcomputer to be processed and then displayed on a liquid crystal display screen; the sewage treatment capacity acquisition unit acquires the sewage inflow rate by using the flowmeter and acquires the sewage storage capacity in the sewage pool by using the water level meter.
5. The information control processing system of an electric power system according to claim 1, characterized in that: the data processing module comprises an electric quantity data processing unit and a sewage treatment quantity data processing unit, the electric quantity data processing unit is used for supplementing missing data of the intelligent electric meter and smoothing distorted data, automatic processing is carried out on zero return replacement mutual inductance metering service according to the characteristics of an electric quantity system, and electric quantity data is supplemented by a comparison and verification result of the electric quantity data; the sewage treatment capacity data processing unit establishes a curve graph for the relation among the water level flow, the water level area and the water level flow rate, analyzes and checks the rationality of the water level flow curve, calculates an average flow meter according to a daily, weekly, monthly or yearly mode, compares data and prepares electricity utilization preparation and sewage treatment preparation in advance for the CPU control module.
6. The information control processing system of an electric power system according to claim 1, characterized in that: the storage library module loads archive data by adopting a preposed communication platform relational database, the communication platform relational database is used for data frame analysis and original data unloading, converts an original binary data frame into data in a CPU (central processing unit) identification format, converts the data into service data and stores the service data into the application data processing module.
7. The information control processing system of an electric power system according to claim 3, characterized in that: the power failure early warning module comprises a power failure information transmission unit and a fault equipment positioning information transmission unit, and the power failure information transmission unit transmits a signal to the man-machine interaction module when no current or voltage is transmitted on the electric equipment; the fault equipment positioning information transmission unit is installed on the electric equipment, positioning information is timely transmitted to the man-machine interaction module when a certain power utilization fault occurs, the man-machine interaction module receives power fault early warning information through a mobile phone and a PC (personal computer) on a power operation and maintenance worker by utilizing network communication, and the man-machine interaction module quickly finds the position where the power failure information occurs according to positioning.
8. The information control processing method of an electric power system according to claim 1, characterized in that: the method comprises the following specific steps:
the information data acquisition module acquires electric quantity data and sewage treatment capacity data of a sewage treatment plant, transmits the acquired data to the data processing module, and then the data processing module classifies, calculates, counts and contrasts the electric quantity data and the sewage treatment capacity data of the sewage treatment plant and transmits the data to the repository module and the CPU control module;
the repository module is used for storing the electric quantity data used by the sewage treatment plant and the sewage treatment quantity data in a classified manner according to time, seasons or other modes;
the CPU control module controls the power of each electric device of the sewage treatment plant, utilizes the sewage fall to store electricity and supplies power when the power is cut off, and transmits information to the power failure early warning module if the power fails;
the electric power failure early warning module is used for each electric device of a sewage treatment plant, if a certain device fails, a failure signal and a positioning signal are transmitted to the man-machine interaction module, and the man-machine interaction module is used for receiving and transmitting information of a mobile phone and a PC (personal computer) on an electric power operation and maintenance worker.
CN202211336318.8A 2022-10-28 2022-10-28 Information control processing system and processing method of power system Pending CN115733243A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211336318.8A CN115733243A (en) 2022-10-28 2022-10-28 Information control processing system and processing method of power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211336318.8A CN115733243A (en) 2022-10-28 2022-10-28 Information control processing system and processing method of power system

Publications (1)

Publication Number Publication Date
CN115733243A true CN115733243A (en) 2023-03-03

Family

ID=85295013

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211336318.8A Pending CN115733243A (en) 2022-10-28 2022-10-28 Information control processing system and processing method of power system

Country Status (1)

Country Link
CN (1) CN115733243A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117993689A (en) * 2024-04-03 2024-05-07 国电环境保护研究院有限公司 Water treatment method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117993689A (en) * 2024-04-03 2024-05-07 国电环境保护研究院有限公司 Water treatment method and system

Similar Documents

Publication Publication Date Title
CN110535845A (en) A kind of GROUP OF HYDROPOWER STATIONS remote date transmission method, system, terminal and storage medium based on Internet of Things
CN104616121A (en) Regional energy comprehensive coordination management and control system
CN102855525B (en) A kind of resident's load prediction analytic system and method
CN106780161A (en) A kind of building energy management system and data processing method
KR20130067678A (en) Micro-grid simulation apparatus and power management system
CN111899143A (en) Regional water environment intelligent management and control system based on big data analysis strategy
CN104201780A (en) Load data collecting, transmitting and analyzing device used for rural power distribution area
CN202522906U (en) Comprehensive electric energy information collector based on photovoltaic power station information system
CN111882167B (en) Intelligent energy diversified operation management system
CN115733243A (en) Information control processing system and processing method of power system
CN113033996A (en) Electric power system information processing system based on electric power big data
CN202013506U (en) Energy source management and control system
CN208028843U (en) A kind of solar panel dust pelletizing system and photovoltaic generating system
CN204190487U (en) For the load data collect and transmit analytical equipment in rural power dispensing table district
CN201730136U (en) Processing device for supplying auxiliary scheduling data of water supply network
CN209842406U (en) Railway energy consumption data acquisition device and energy management system
CN116992216A (en) Short-term load prediction method based on power user data
Asenov et al. Using of Batteryless LoRaWAN Ultrasonic Sensor Node for Smart Garbage Collection
CN106771707A (en) A kind of line loss analyzing service terminal
CN207366542U (en) Water quality monitoring system based on big data
CN210806849U (en) Photovoltaic microgrid control system
CN117200463B (en) Intelligent power monitoring system and method
Mikhnev et al. The introduction of intelligent electrical networks in Russia
CN219875190U (en) 5G-based solar intelligent efficient water lifting system
CN116845985B (en) Source network load storage collaborative scheduling system based on data analysis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination