CN115478533A - PHC pipe pile core pouring method under confined water condition - Google Patents

PHC pipe pile core pouring method under confined water condition Download PDF

Info

Publication number
CN115478533A
CN115478533A CN202211135213.6A CN202211135213A CN115478533A CN 115478533 A CN115478533 A CN 115478533A CN 202211135213 A CN202211135213 A CN 202211135213A CN 115478533 A CN115478533 A CN 115478533A
Authority
CN
China
Prior art keywords
drainage hose
pile core
reinforcement cage
pile
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211135213.6A
Other languages
Chinese (zh)
Inventor
管聪聪
王敏
张朝晖
李泳键
曾斌
吴爱成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202211135213.6A priority Critical patent/CN115478533A/en
Publication of CN115478533A publication Critical patent/CN115478533A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of construction of building foundations, in particular to a method for pouring a PHC tubular pile core under the condition of confined water; the method comprises the following steps of 1, processing and manufacturing the reinforcement cage; step 2, installing a drain pipe and installing a reinforcement cage; step 3, pouring pile core concrete; and 4, plugging the drain pipe. By adopting the method, the drainage hose is arranged in the reinforcement cage, so that after concrete is poured, because the pressure in the drainage hose is small, underground water gushing out of the pile core can enter the drainage hose and is discharged out of the pile core through the drainage hose, the problem of water seepage or full spring of the pile core is solved, and the anchoring force of the foundation and the pile is ensured.

Description

PHC pipe pile core pouring method under confined water condition
Technical Field
The invention relates to the technical field of construction of building foundations, in particular to a method for pouring a PHC tubular pile core under a confined water condition.
Background
The PHC tubular pile and the foundation form an anchoring connection structure after placing a reinforcement cage to a pile core and pouring concrete, and the concrete is in a gel state under the condition of not initially setting; when underground water systems of a construction site are abundant, under the condition of confined water, pile core concrete is flushed by running water and cannot be solidified, so that water seeps outwards all the time at the position of the pile core, the same problem also exists during pouring of foundation concrete, a spring gushing point is formed inside a foundation, the water seepage problem is caused, and the waterproof performance of the structure and the safety performance of the structure are seriously influenced.
Disclosure of Invention
The invention aims to overcome the defects and provide a method for avoiding the problems of water seepage and spring gushing of a pile core by drainage during pile core pouring and plugging after the pile core is initially set, so that the anchoring force of a foundation and a pile is ensured.
In order to achieve the above object, the present invention is realized by:
a PHC tubular pile core pouring method under the condition of confined water comprises
Step 1, manufacturing a reinforcement cage: processing a pile core reinforcement cage according to the drawing requirements, reserving a 3.5mm round notch at the end plate position of the reinforcement cage, wherein the notch is used for inserting a drainage hose;
step 2, arranging a drainage hose and installing a reinforcement cage:
2.1, determining the length of the drainage hose according to the length of the reinforcement cage, sequentially penetrating the drainage hose through end plates of the pile core reinforcement cage, wherein the end part of the drainage hose exceeds the end plates by not less than 50mm;
step 2.2, after the position of the drainage hose in the pile core reinforcement cage is positioned, the drainage hose is sequentially and firmly bound with the main reinforcement of the reinforcement cage, after the binding is finished, the length of the pipe orifice of the drainage hose exposed out of the pile head is not less than 1000mm,
step 2.3, placing the reinforcement cage obtained in the step 2.2 inside the pile core;
step 3, concrete pouring operation of the pile core:
3.1, inserting a guide pipe into the bottom in the pile core during pouring, wherein the distance between a lower port of the guide pipe and an end plate is 200mm;
and 3.2, keeping the lower port of the conduit to be embedded in the concrete all the time during concrete pouring until the pile core is filled, and simultaneously, paying attention to the pipe orifice protection work of the drainage hose during the pile core pouring process to prevent the concrete from being poured into the pipe orifice to block a water outlet.
Step 4, plugging the drainage hose:
step 4.1, pouring fast-hardening cement mortar into the drainage hose after the pile core concrete is initially set, wherein the grouting amount is not less than the volume amount of the drainage pipe embedded in the reinforcement cage;
and 4.2, after grouting, plugging the pipe orifice to finish the pile core concrete grouting work. At the moment, a closed space is formed inside the tubular pile, namely, the confined water cannot flow through the tubular pile to form dynamic water to flush soil and rock around the tubular pile, so that the bearing capacity of the tubular pile is ensured.
By adopting the method, the drainage hose is arranged in the reinforcement cage, so that after concrete is poured, the pressure in the drainage hose is small, so that the underground water gushed from the pile core can enter the drainage hose and be drained out of the pile core through the drainage hose, the problem of water seepage or full spring of the pile core is solved, and the anchoring force of the foundation and the pile is ensured.
Drawings
Fig. 1 is a schematic structural diagram of a pile core reinforcement cage with a drainage hose.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in figure 1, a PHC tubular pile core pouring method under the condition of confined water comprises
Step 1, manufacturing a reinforcement cage 1: processing a pile core reinforcement cage according to drawing requirements, reserving a 3.5mm round notch at the end plate position of the reinforcement cage 1, wherein the notch is used for inserting a drainage hose 2;
step 2, arranging a drainage hose 2 and installing a reinforcement cage:
2.1, determining the length of the drainage hose 2 according to the length of the reinforcement cage 1, sequentially penetrating the drainage hose 2 through end plates of the pile core reinforcement cage, wherein the end part of the drainage hose 2 exceeds the end plates by not less than 50mm;
step 2.2, after the position of the drainage hose 2 in the pile core reinforcement cage is positioned, the drainage hose 2 is sequentially and firmly bound with the main reinforcement of the reinforcement cage 1, after the binding is finished, the length of the pipe orifice of the drainage hose 2 exposed out of the pile head is not less than 1000mm,
2.3, placing the reinforcement cage 1 obtained in the step 2.2 inside a pile core;
step 3, concrete pouring operation of the pile core:
3.1, inserting a guide pipe into the bottom in the pile core during pouring, wherein the distance between a lower port of the guide pipe and an end plate is 200mm;
and 3.2, keeping the lower port of the conduit to be always embedded in the concrete during concrete pouring until the pile core is fully filled, and simultaneously, paying attention to the pipe orifice protection work of the drainage hose 2 during the pile core pouring process to prevent the concrete from being poured into the pipe orifice to block a water outlet, wherein the poured concrete mixture has vertical pressure, the drainage hose 2 in the pile core is of a hollow structure, the drainage hose 2 forms a pile core drainage pressure relief channel, water can flow out through the drainage hose 2, and the problems that the pressure-bearing water does not have a pressure relief point and erodes the unset concrete mixture all the time in the traditional pouring mode, so that the cement, sand, stone and other mixtures are scoured and separated, the pile core concrete mixture cannot be solidified, and the anchoring force of a pile head and a foundation cannot meet the design requirement are solved.
Step 4, plugging the drainage hose:
step 4.1, pouring fast-hardening cement mortar into the drainage hose after the pile core concrete is initially set, wherein the grouting amount is not less than the volume amount of the drainage pipe embedded in the reinforcement cage;
and 4.2, after grouting, plugging the pipe orifice to finish the pile core concrete grouting work. At the moment, a closed space is formed inside the tubular pile, namely, the confined water cannot flow through the tubular pile to form dynamic water to flush soil and rock around the tubular pile, so that the bearing capacity of the tubular pile is ensured.
By adopting the method, the drainage hose is arranged in the reinforcement cage, so that after concrete is poured, the pressure in the drainage hose is small, so that the underground water gushed from the pile core can enter the drainage hose and be drained out of the pile core through the drainage hose, the problem of water seepage or full spring of the pile core is solved, and the anchoring force of the foundation and the pile is ensured.

Claims (1)

1. A PHC tubular pile core pouring method under the condition of confined water is characterized by comprising the following steps: comprises that
Step 1, manufacturing a reinforcement cage: processing a pile core reinforcement cage according to the drawing requirements, reserving a 3.5mm round notch at the end plate position of the reinforcement cage, wherein the notch is used for inserting a drainage hose;
step 2, arranging a drainage hose and installing a reinforcement cage:
2.1, determining the length of the drainage hose according to the length of the reinforcement cage, sequentially penetrating the drainage hose through end plates of the pile core reinforcement cage, wherein the end part of the drainage hose exceeds the end plates by not less than 50mm;
step 2.2, after the position of the drainage hose in the pile core reinforcement cage is positioned, the drainage hose is tightly bound with the main reinforcement of the reinforcement cage in sequence, after the binding is finished, the length of the pipe orifice of the drainage hose exposed out of the pile head is not less than 1000mm,
step 2.3, placing the reinforcement cage obtained in the step 2.2 inside a pile core;
step 3, concrete pouring operation of the pile core:
3.1, inserting a guide pipe into the bottom in the pile core during pouring, wherein the distance between a lower port of the guide pipe and an end plate is 200mm;
step 3.2, the lower port of the guide pipe is kept to be embedded in the concrete all the time when the concrete is poured until the pile core is filled, and meanwhile, the pile core pouring process is careful about the pipe port protection work of the drainage hose, so that the concrete is prevented from being poured into the pipe port to block a water outlet;
step 4, plugging the drainage hose:
step 4.1, pouring fast-hardening cement mortar into the drainage hose after the pile core concrete is initially set, wherein the grouting amount is not less than the volume amount of the drainage pipe embedded in the reinforcement cage;
step 4.2, after grouting, plugging the pipe orifice to finish the pile core concrete grouting work; at the moment, a closed space is formed inside the pipe pile, namely, the confined water cannot flow through the pipe pile to form dynamic water to flush soil and rock around the pipe pile, so that the bearing capacity of the pipe pile is ensured.
CN202211135213.6A 2022-09-19 2022-09-19 PHC pipe pile core pouring method under confined water condition Pending CN115478533A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211135213.6A CN115478533A (en) 2022-09-19 2022-09-19 PHC pipe pile core pouring method under confined water condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211135213.6A CN115478533A (en) 2022-09-19 2022-09-19 PHC pipe pile core pouring method under confined water condition

Publications (1)

Publication Number Publication Date
CN115478533A true CN115478533A (en) 2022-12-16

Family

ID=84424022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211135213.6A Pending CN115478533A (en) 2022-09-19 2022-09-19 PHC pipe pile core pouring method under confined water condition

Country Status (1)

Country Link
CN (1) CN115478533A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116837906A (en) * 2023-07-04 2023-10-03 上海宝冶集团有限公司 Water burst blocking method for pile head of prefabricated pipe pile

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212001219U (en) * 2020-01-19 2020-11-24 中国建筑第八工程局有限公司 Connecting structure of precast tubular pile and building bottom plate

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212001219U (en) * 2020-01-19 2020-11-24 中国建筑第八工程局有限公司 Connecting structure of precast tubular pile and building bottom plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116837906A (en) * 2023-07-04 2023-10-03 上海宝冶集团有限公司 Water burst blocking method for pile head of prefabricated pipe pile

Similar Documents

Publication Publication Date Title
CN112647498B (en) Construction method for anti-floating anchor cable penetrating through water-rich layer
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN211340827U (en) Structure for newly building bridge by passing through existing bridge piles in subway tunnel
CN112376571A (en) Pile side and pile end integrated grouting device and construction method thereof
CN109372016A (en) Basement bottom plate rear pouring tape structure and construction method under high artesian
CN115478533A (en) PHC pipe pile core pouring method under confined water condition
CN112900512A (en) Basement bottom plate crack punching, reinforcing and repairing construction method
CN215105258U (en) Small-diameter cast-in-place pile for resisting floating
CN113431046B (en) Post-grouting construction method for cast-in-place pile
CN117646497A (en) Basement outer wall post-pouring belt pre-sealing structure and construction method
CN110206071A (en) A kind of diaphram wall seam reinforcement means and device
CN117364789A (en) Soft soil deep foundation pit supporting structure for building construction and supporting construction method thereof
CN109736337B (en) Precipitation device and method for guaranteeing integrity of cushion layer through sediment flowing treatment of foundation elevator shaft sump
CN209040133U (en) Well-covering device for dewatering well suitable for rich groundwater region
CN114922172B (en) Anchor rod pile device capable of eliminating negative frictional resistance of collapsible loess and construction method
CN110820781A (en) Well plugging method for dewatering well
CN110792077A (en) Supporting disc pile device suitable for muddy soft soil and construction process thereof
CN114525781A (en) Prestressed rod core bag grouting combined anti-floating component and construction method
CN113914909A (en) Tunnel water inrush point emergency rescue plugging structure and construction method thereof
CN109989415B (en) Construction method of fabricated foundation
CN113585319A (en) Pile foundation construction method
CN215562841U (en) Newly-built basement is anti to float with installation connecting elements
CN212896374U (en) Foundation pit support structure located in underground space of existing building
CN213836755U (en) Permanent row pile type underground road waterproof wall connecting structure
CN217500224U (en) Grouting device for improving bearing capacity of pile foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20221216

RJ01 Rejection of invention patent application after publication