CN115404783A - Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge - Google Patents

Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge Download PDF

Info

Publication number
CN115404783A
CN115404783A CN202211141337.5A CN202211141337A CN115404783A CN 115404783 A CN115404783 A CN 115404783A CN 202211141337 A CN202211141337 A CN 202211141337A CN 115404783 A CN115404783 A CN 115404783A
Authority
CN
China
Prior art keywords
steel box
box girder
sliding
oil cylinder
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211141337.5A
Other languages
Chinese (zh)
Inventor
何文生
黄华
盛健
戴凤波
徐咏春
田涛
徐小怀
刘禹浩
徐怀俊
曾友治
杨海昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN202211141337.5A priority Critical patent/CN115404783A/en
Publication of CN115404783A publication Critical patent/CN115404783A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a sliding construction method of an ultra-wide separating type steel box girder of an extra-large cable-stayed bridge, which is characterized in that the ultra-wide separating type steel box girder is hoisted to a placing pier of a supporting structure on the side of a river by a floating crane, an upper beam body and a lower beam body slide through a main tower by a sliding device and then are hoisted by the floating crane, the beams are connected with the upper beam body and the lower beam body by matching pieces and code plates, a left box body, a right box body and the beams synchronously slide to design positions, the line shape is adjusted to meet the monitoring and design requirements, and the realization of the sliding construction comprises the following steps: the device comprises a supporting structure, a steel longitudinal beam, a sliding device, a placing pier and a tensioning structure; the steel longitudinal beam and the placing pier are arranged on the supporting structure and are rigidly connected with the supporting structure; the sliding device consists of a steel rail, a sliding shoe, a jacking oil cylinder, a lateral oil cylinder, a distribution beam, a pushing oil cylinder and a rail clamping device. Compared with the prior art, the ultra-wide separation type steel box girder has the advantages of simple structure, high efficiency, accuracy, safety, synchronous sliding erection, high working efficiency, low labor intensity and safe construction.

Description

一种特大斜拉桥超宽分离式钢箱梁的滑移施工方法A sliding construction method for super-wide separated steel box girders of extra-large cable-stayed bridges

技术领域technical field

本发明涉及钢结构桥梁施工技术领域,尤其是一种用于特大斜拉桥超宽分离式钢箱梁的滑移施工方法。The invention relates to the technical field of steel structure bridge construction, in particular to a sliding construction method for super-wide separated steel box girders of extra-large cable-stayed bridges.

背景技术Background technique

特大双塔斜拉桥由边跨和主跨组成,边跨钢箱梁位于岸侧且距离较长,由于钢箱梁节段较大、重量较重一般采用水路运输。水位较浅时浮吊无法吊装,采用钢箱梁散件预制,桥位需要搭设支架量较大,现场安装工期较长,受大风、雨等不利环境影响,钢箱梁焊接质量不易得到保障。所以,一般不宜采用散件大量安装工法,为保障钢箱梁制造质量、完成钢箱梁架设,采用滑移法施工是一种新的解决办法。The extra-large double-tower cable-stayed bridge consists of a side span and a main span. The steel box girder of the side span is located on the shore and has a long distance. Due to the large section and heavy weight of the steel box girder, it is generally transported by water. When the water level is shallow, the floating crane cannot be hoisted. The prefabricated steel box girder parts are used. The bridge position needs to be erected with a large amount of brackets. Therefore, it is generally not suitable to use a large number of loose parts to install the construction method. In order to ensure the manufacturing quality of the steel box girder and complete the erection of the steel box girder, the construction of the sliding method is a new solution.

现有技术的滑移法施工,采用一端设置卷扬机作为牵引设备,拖拉钢梁滑移,使得钢梁牵引前行,该方法需要设置反力点,钢箱梁下部支撑存在反力影响,对下部支撑受力不利,而且仅能实现纵向前移,无法快速实现梁体的线型和位置调节,滑移过程稳定性和同步性差,滑移间距精确度低,梁段过主塔困难。In the construction of the sliding method in the prior art, a hoist is installed at one end as the traction device, and the steel girder is pulled to slide, so that the steel girder is pulled forward. This method needs to set a reaction force point, and the lower support of the steel box girder has the influence of reaction force, which affects the lower support. The force is unfavorable, and only longitudinal forward movement can be realized, and the line shape and position adjustment of the beam body cannot be quickly realized. The stability and synchronization of the sliding process are poor, the accuracy of the sliding distance is low, and it is difficult for the beam section to pass through the main tower.

发明内容Contents of the invention

本发明的目的是针对现有技术的不足而提供的一种特大斜拉桥超宽分离式钢箱梁的滑移施工方法,采用液压自锁机构的的滑移装置,实现钢箱梁的位置、线形快速调节,滑移装置通过液压自锁机构与滑移轨道夹紧,使钢箱梁前进的顶推反力为内力,钢箱梁支撑结构水平反力较小,大大减少水平力对支架的影响,实现钢箱梁的横、纵向,高程调节,顶推与落梁一体化装置结构简单,使用方便,桥位搭设的支架量少,缩短了现场安装工期,受大风、雨等不利环境的影响小,钢箱梁焊接质量得到了进一步保证,确保了特大斜拉桥超宽分离式钢箱梁高效、高质量架设,具有良好的应用前景。The object of the present invention is to provide a sliding construction method for super-wide separated steel box girders of super-large cable-stayed bridges in view of the deficiencies in the prior art, and adopt a hydraulic self-locking mechanism sliding device to realize the position of the steel box girder. , Linear fast adjustment, the sliding device is clamped by the hydraulic self-locking mechanism and the sliding track, so that the pushing reaction force of the steel box girder forward is the internal force, and the horizontal reaction force of the steel box girder support structure is small, which greatly reduces the horizontal force on the support The impact of the steel box girder can be adjusted horizontally, vertically and vertically. The integrated device of pushing and falling beams has a simple structure and is easy to use. The amount of brackets erected at the bridge position is small, which shortens the on-site installation period. The impact is small, the welding quality of steel box girders is further guaranteed, and the super-wide separated steel box girders of extra-large cable-stayed bridges are ensured to be erected efficiently and with high quality, which has a good application prospect.

实现本发明目的具体技术方案是:一种特大斜拉桥超宽分离式钢箱梁的滑移施工方法,其特点是采用超宽分离式钢箱梁通过浮吊吊装至江侧支撑结构的搁置墩上,通过滑移装置将上下游梁体滑移过主塔后利用浮吊吊装横梁,横梁与上下游梁体通过匹配件、码板连接,左右箱体及横梁同步滑移至设计位置,调整线形符合监控及设计要求。The specific technical solution for realizing the purpose of the present invention is: a sliding construction method of an ultra-wide separated steel box girder of a super-large cable-stayed bridge, which is characterized in that the ultra-wide separated steel box girder is hoisted by a floating crane to the shelving of the supporting structure on the river side On the pier, use the sliding device to slide the upstream and downstream beams through the main tower, and then use the floating crane to lift the beams. The beams and the upstream and downstream beams are connected by matching parts and code plates, and the left and right boxes and beams slide to the design position synchronously. Adjust the line shape to meet the monitoring and design requirements.

该钢箱梁滑移施工的滑移装置以斜拉桥中心线对称布置,实现钢箱梁滑移施工的设施包括:支撑结构、钢纵梁、滑移装置、搁置墩、张拉结构;所述钢纵梁、搁置墩设置于支撑结构上,且与支撑结构刚性连接;所述滑移装置由钢轨、滑靴、顶升油缸、侧向油缸、分配梁、顶推油缸、夹轨器组成;所述钢轨置于钢纵梁上并用卡板卡压,同一滑靴下钢轨根据滑靴结构平行布置;所述滑靴置于钢轨上,钢轨上涂有润滑油减少摩擦系数;所述顶升油缸置于滑靴上,顶升油缸上部设置分配梁;所述侧向油缸与滑靴侧向支架栓接固定;所述钢箱梁下部设置四个滑靴;所述分配梁之间、钢箱梁与分配梁之间通过张拉结构进行连接,以更好的实现钢箱梁的同步滑移;所述张拉结构通过螺纹钢进行张拉紧固;所述搁置墩置于滑移装置的两侧,且与支撑结构焊接连接,用于钢箱梁的落梁,实现滑靴装置的移出,使得后续梁体能够循环滑移。The sliding device of the steel box girder sliding construction is arranged symmetrically with the center line of the cable-stayed bridge, and the facilities for realizing the steel box girder sliding construction include: supporting structure, steel longitudinal beam, sliding device, shelving pier, and tension structure; The steel longitudinal beams and shelving piers are set on the supporting structure and rigidly connected with the supporting structure; the sliding device is composed of steel rails, sliding shoes, jacking cylinders, lateral cylinders, distribution beams, jacking cylinders, and rail clamps The steel rail is placed on the steel longitudinal beam and clamped with a clamp, and the rails under the same sliding shoe are arranged in parallel according to the structure of the sliding shoe; the sliding shoe is placed on the rail, and the rail is coated with lubricating oil to reduce the friction coefficient; the jacking The oil cylinder is placed on the sliding shoe, and the upper part of the jacking oil cylinder is provided with a distribution beam; the lateral oil cylinder is bolted to the lateral support of the sliding shoe; four sliding shoes are arranged at the lower part of the steel box beam; between the distribution beams, steel The box girder and the distribution beam are connected by a tension structure to better realize the synchronous sliding of the steel box girder; the tension structure is tensioned and fastened by threaded steel; the shelving pier is placed on the sliding device The two sides are welded and connected with the supporting structure, and are used for the falling beam of the steel box girder to realize the removal of the sliding shoe device, so that the subsequent beam body can slide cyclically.

所述滑移装置的顶推油缸、顶升油缸、侧向油缸采用液压同步控制技术,实现钢箱梁的前移、线形调整,落梁。The pushing oil cylinder, jacking oil cylinder and side oil cylinder of the sliding device adopt hydraulic synchronous control technology to realize the forward movement, linear adjustment and drop of the steel box girder.

所述钢箱梁滑移线形由滑移起点的梁底标高h1及滑移终点的梁底标高h2所确定的斜直线确定。The slip line shape of the steel box girder is determined by the oblique straight line determined by the girder bottom elevation h1 of the slip start point and the girder bottom elevation h2 of the slip end point.

所述搁置墩对称布置支撑在钢箱梁横隔板刚性较好位置,搁置墩标高由滑移线形插值确定。The shelving pier is symmetrically arranged and supported at the rigid position of the steel box girder diaphragm, and the elevation of the shelving pier is determined by slip linear interpolation.

所述顶升油缸在完全缩缸时高程应小于搁置墩标高,以实现梁体的落梁。The elevation of the jacking oil cylinder should be less than the elevation of the shelving pier when the cylinder is fully retracted, so as to realize the falling of the beam body.

所述侧向油缸与搁置墩的净距不小于50mm,避免滑靴偏移时与搁置墩产生干涉。The clear distance between the lateral oil cylinder and the resting pier is not less than 50 mm to avoid interference with the resting pier when the sliding shoe is offset.

所述张拉结构实现滑移装置、梁体相对之间无位移,使得梁体纵向同步滑移。The tension structure realizes that there is no displacement between the sliding device and the beam body, so that the beam body slides synchronously in the longitudinal direction.

本发明与现有技术相比具有超宽分离式钢箱梁高效、精确、安全、同步滑移架设,结构简单,使用方便,桥位搭设的支架量少,缩短了现场安装工期,实现斜拉桥边跨分离式钢箱梁江侧吊装,向岸侧同步滑移,可精确调整梁段横向位置,使得横梁与两侧箱体精确连接,解决了梁段过主塔的难题。两侧钢箱梁与横梁均采用起重船进行吊装,岸侧无需大型起吊设备,能够使梁段位置、线形的快速调节,缩短了大型起吊设备的使用周期,梁段线形调节效率高,梁段滑移至设计位置后,落至搁置墩上,提高了滑移装置利用率,劳动强度低,经济、高效、安全,具有良好的应用前景。Compared with the prior art, the present invention has ultra-wide separated steel box girder with efficient, accurate, safe and synchronous sliding erection, simple structure, convenient use, less support for bridge erection, shortening the on-site installation period, and realizing cable-staying The bridge side-span separated steel box girder is hoisted on the river side and slides synchronously to the shore side, which can precisely adjust the lateral position of the beam section, so that the beam is accurately connected with the boxes on both sides, and solves the problem that the beam section passes through the main tower. The steel box girders and beams on both sides are hoisted by cranes. No large-scale lifting equipment is required on the shore side, which can quickly adjust the position and line shape of the beam section, shortening the service life of large-scale lifting equipment, and the line shape adjustment efficiency of the beam section is high. After the section slides to the design position, it falls on the shelving pier, which improves the utilization rate of the sliding device, has low labor intensity, is economical, efficient, and safe, and has a good application prospect.

附图说明Description of drawings

图1为实施例的整体结构平面布置图;Fig. 1 is the overall structural plan layout drawing of embodiment;

图2为滑移装置支撑钢箱梁示意图;Fig. 2 is a schematic diagram of a steel box girder supported by a sliding device;

图3为滑移线形示意图;Figure 3 is a schematic diagram of the slip line;

图4为顶升油缸与支撑结构和张拉结构示意图;Fig. 4 is a schematic diagram of a jacking cylinder, a supporting structure and a tensioning structure;

图5为滑移装置结构示意图。Fig. 5 is a schematic diagram of the structure of the sliding device.

具体实施方式Detailed ways

以下通过具体实施对本发明作进一步的详细说明。The present invention will be further described in detail through specific implementation below.

实施例1Example 1

参阅图1~图3,在桥梁中心线的两侧设置支撑结构1, 将工厂内大节段预制的超宽分离式钢箱梁(梁段)6运至桥位,通过浮吊吊装至江侧支撑结构1的搁置墩4上,采用滑移装置3将上、下游梁体滑移过主塔,利用浮吊吊装横梁7,横梁7与上、下游梁体通过匹配件和码板连接梁段6的左、右箱体,以及横梁7同步滑移至设计位置,该钢箱梁6的滑移施工以斜拉桥中心线对称布置。单侧钢箱梁6通过浮吊吊装至江侧支撑结构1的搁置墩4上,滑移过主塔后吊装横梁7,横梁7与上下游梁体匹配连接同步滑移至设计位置落梁至搁置墩上,具体包括以下步骤:Referring to Figures 1 to 3, support structures 1 are set up on both sides of the bridge centerline, and the ultra-wide separated steel box girder (beam section) 6 prefabricated in large sections in the factory is transported to the bridge site and hoisted to the river by floating crane. On the shelving pier 4 of the side support structure 1, use the sliding device 3 to slide the upstream and downstream beams through the main tower, and use the floating crane to lift the beam 7, and the beam 7 and the upstream and downstream beams are connected to the beams through matching parts and code plates The left and right boxes of section 6 and the beam 7 slide synchronously to the design position, and the sliding construction of the steel box girder 6 is symmetrically arranged on the center line of the cable-stayed bridge. The single-sided steel box girder 6 is hoisted to the shelving pier 4 of the supporting structure 1 on the river side by a floating crane, and the beam 7 is hoisted after sliding past the main tower. Putting it on the pier specifically includes the following steps:

S1、超宽钢箱梁工厂内分节段进行预制。S1. Super-wide steel box girders are prefabricated in sections in the factory.

S1、施工支撑结构1,对支撑结构1进行1.1倍荷载预压。S1. Construction support structure 1, carry out 1.1 times load preload on support structure 1.

S2、施工钢纵梁2测量位置、线形、标高符合要求后安装钢轨31。S2. The steel rail 31 is installed after measuring the position, alignment and elevation of the construction steel longitudinal beam 2 to meet the requirements.

S3、制作滑靴32、安装顶升油缸33、侧向油缸34、顶推油缸36、夹轨器37。S3, making the sliding shoe 32, installing the jacking oil cylinder 33, the lateral oil cylinder 34, the jacking oil cylinder 36, and the rail clamp 37.

S4、根据滑移起点的梁底标高h1及滑移终点的梁底标高h2所确定的滑移线形,详见图3所示,插值确定搁置墩4标高,搁置墩4布设在梁段6的隔板下方包络梁段重心。S4. According to the slip line shape determined by the elevation h1 of the beam bottom at the start point of the slippage and the elevation h2 of the beam bottom at the end point of the slippage, see Figure 3 for details, the elevation of the shelving pier 4 is determined by interpolation, and the shelving pier 4 is arranged on the beam section 6 The center of gravity of the enveloping beam segment below the diaphragm.

S5、放样确定滑移装置3位置,使其支撑在钢箱梁6横隔板处。S5. Stake out to determine the position of the sliding device 3 so that it is supported at the transverse diaphragm of the steel box girder 6 .

S6、滑移装置进行接油管、控制电线、电缆、传感器等安装,检查合格后,调试泵站和控制系统,进行空载调试。S6. Install the oil connection pipe, control wires, cables, sensors, etc. for the sliding device. After passing the inspection, debug the pump station and control system, and carry out no-load debugging.

S7、正式滑移过程中对钢箱梁6轴线、滑靴32与钢轨31卡位情况、夹轨器37夹紧情况各点载荷及同步性、支撑结构变形情况进行监测。S7. During the official sliding process, monitor the 6-axis of the steel box girder, the position of the sliding shoe 32 and the rail 31, the clamping of the rail clamp 37, the load and synchronization of each point, and the deformation of the support structure.

S8、滑移到位后钢箱梁6落梁在搁置墩4上,利用滑移装置进行横向位置、纵向位置、高程精定位,完成环焊缝的焊接。S8. After the sliding is in place, the steel box girder 6 falls on the shelving pier 4, and the lateral position, longitudinal position, and elevation are precisely positioned by using the sliding device to complete the welding of the girth weld.

S9、利用卷扬机牵引至江侧钢箱梁吊装区,准备下节梁段的滑移工作。S9. Utilize the hoist to pull to the hoisting area of the steel box girder on the river side, and prepare for the sliding work of the lower girder section.

参阅图4~图5,实现钢箱梁滑移施工的设施包括:支撑结构1、钢纵梁2、滑移装置3、搁置墩4、张拉结构5;所述钢纵梁2、搁置墩4置于支撑结构1上,与支撑结构1刚性连接;所述滑移装置3由钢轨31、滑靴32、顶升油缸33、侧向油缸34、分配梁35、顶推油缸36、夹轨器37组成。所述钢轨31置于钢纵梁2上并用卡板卡压,同一滑靴32下钢轨31根据滑靴32结构平行布置;所述滑靴32置于钢轨31上,钢轨31上涂有润滑油减少摩擦系数;所述顶升油缸33置于滑靴32上,顶升油缸33上部设置分配梁35;所述侧向油缸34由支架与滑靴32栓接固定;所述钢箱梁6下部设置四个滑靴32;所述分配梁35之间、钢箱梁6与分配梁35之间通过张拉结构5进行连接,以更好的实现钢箱梁6的同步滑移;所述张拉结构5通过螺纹钢51进行张拉紧固;所述搁置墩4置于滑移装置3的两侧,与支撑结构1焊接连接,用于钢箱梁6的落梁,实现滑移装置3的移出,使得后续梁体能够循环滑移。Referring to Figures 4 to 5, the facilities for realizing the sliding construction of steel box girders include: supporting structure 1, steel longitudinal beam 2, sliding device 3, shelving pier 4, tension structure 5; said steel longitudinal beam 2, shelving pier 4 Placed on the support structure 1 and rigidly connected with the support structure 1; the sliding device 3 is composed of a steel rail 31, a sliding shoe 32, a jacking cylinder 33, a lateral cylinder 34, a distribution beam 35, a jacking cylinder 36, and a clamping rail device 37. The rails 31 are placed on the steel longitudinal beams 2 and pressed by clamps, and the rails 31 under the same sliding shoe 32 are arranged in parallel according to the structure of the sliding shoes 32; the sliding shoes 32 are placed on the rails 31, and the rails 31 are coated with lubricating oil Reduce the friction coefficient; the jacking cylinder 33 is placed on the sliding shoe 32, and the upper part of the jacking cylinder 33 is provided with a distribution beam 35; the lateral oil cylinder 34 is bolted and fixed by the bracket and the sliding shoe 32; the lower part of the steel box girder 6 Four sliding shoes 32 are set; between the distribution beams 35, between the steel box girder 6 and the distribution beam 35 are connected through the tension structure 5, so as to better realize the synchronous sliding of the steel box girder 6; The tension structure 5 is tensioned and fastened by threaded steel 51; the shelving pier 4 is placed on both sides of the sliding device 3 and welded to the support structure 1, and is used for the falling beam of the steel box girder 6 to realize the sliding device 3 The removal of the beam allows the subsequent beam to slip cyclically.

以上只是对本发明作进一步的说明,并非用以限制本专利,凡为本发明等效实施,均应包含于本专利的权利要求范围之内。The above is only a further description of the present invention, and is not intended to limit this patent. All equivalent implementations of the present invention should be included in the scope of claims of this patent.

Claims (5)

1. The utility model provides a super wide disconnect-type steel box girder's of super large cable-stay bridge construction method that slides, its characterized in that steel box girder's the construction that slides adopts big section prefabricated super wide disconnect-type steel box girder in the mill to transport to the bridge position, hoist to river side bearing structure through the floating crane on shelving the mound, adopt the displacement device will go up, the low reaches roof beam body slides and crosses the king tower, utilize the floating crane hoist and mount crossbeam, the crossbeam with go up, the low reaches roof beam body passes through matching piece, the left and right box of steel box girder is connected to the sign indicating number board, and the crossbeam slides to the design position in step, it is linear to the designing requirement to adjust, the concrete construction of sliding of steel box girder includes following step:
s1, prefabricating ultra-wide steel box girder sections in a factory;
s1, constructing a support structure, and performing 1.1-time load pre-pressing on the support structure;
s2, constructing a steel longitudinal beam, and installing a steel rail after the measured position, line shape and elevation meet the design requirements;
s3, the installation comprises: the sliding device consists of a sliding shoe, a jacking oil cylinder, a lateral oil cylinder, a pushing oil cylinder and a rail clamping device;
s4, determining the elevation of the resting pier by adopting an interpolation method according to the slippage line shape determined by the beam bottom elevation h1 of the slippage starting point and the beam bottom elevation h2 of the slippage finishing point;
s5, lofting to determine the position of the laying pier, and enabling the laying pier to be supported on the diaphragm plate of the beam section;
s6, installing an oil receiving pipe, a control wire and a sensor on the oil cylinder, and debugging a pump station and a control system;
s7, starting the sliding of the steel box girder after the no-load debugging is qualified, and monitoring the axial line of the steel box girder, the clamping condition of the sliding shoes and the steel rail, the clamping condition of a rail clamping device, the load and synchronism of each point and the deformation condition of a supporting structure in the sliding process;
s8, after the beam section slides in place, the beam section is placed on a placing pier, and transverse position, longitudinal position and elevation fine positioning is carried out by using a sliding device to complete welding of a circumferential weld;
and S9, dragging the steel box girder to a river side steel box girder hoisting area by using a winch to prepare for sliding operation of the next section of girder.
2. The slippage construction method for the ultra-wide separated steel box girder of the extra-large cable-stayed bridge according to claim 1, wherein the slippage device comprises: the steel rail is arranged on a steel longitudinal beam of the supporting structure and is clamped and pressed by a clamping plate; the sliding shoes are arranged on the steel rails to support the steel box girders on the upper parts of the steel rails, and the steel rails under the same sliding shoes are arranged in parallel according to the sliding shoe structure; the jacking oil cylinder is arranged on the sliding shoe; the distribution beam is arranged on the jacking oil cylinder; the lateral oil cylinder is arranged on the sliding shoe and is fixedly connected with the sliding shoe through a bracket and a sliding shoe bolt; four sliding shoes are arranged at the lower part of the steel box girder; the distribution beam is connected with the steel box beam through the tensioning structure, so that the sliding device and the beam body do not have displacement, and the beam body longitudinally slides synchronously; and the tensioning structure is tensioned and fastened through deformed steel bars.
3. The slipping construction method of the ultra-wide separating steel box girder of the extra-large cable-stayed bridge according to claim 1 or claim 2, characterized in that the laying piers are arranged at two sides of the slipping device and are symmetrically supported below a diaphragm plate of the steel box girder for the falling of the steel box girder and the moving out of the slipping device, the elevation of the laying piers is determined by the linear interpolation of slipping, and the laying piers and the supporting structure are welded.
4. The slippage construction method for the ultra-wide separate type steel box girder of the extra-large cable-stayed bridge according to claim 1 or claim 2, wherein the slippage line shape of the steel box girder is determined by an inclined straight line determined by a beam bottom elevation h1 of a slippage starting point and a beam bottom elevation h2 of a slippage ending point.
5. The ultra-wide separation type steel box girder sliding construction method for the extra-large cable-stayed bridge according to claim 1 or claim 2, wherein the jacking oil cylinder, the lateral oil cylinder and the jacking oil cylinder are hydraulically and synchronously controlled to realize forward movement, linear adjustment and girder falling of the steel box girder; the elevation of the jacking oil cylinder when the cylinder is completely contracted is smaller than the elevation of the laying pier so as to realize the beam falling of the beam body; the clear distance between the lateral oil cylinder and the placing pier is not less than 50mm, and interference between the lateral oil cylinder and the placing pier is avoided when the sliding shoe deviates.
CN202211141337.5A 2022-09-20 2022-09-20 Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge Pending CN115404783A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211141337.5A CN115404783A (en) 2022-09-20 2022-09-20 Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211141337.5A CN115404783A (en) 2022-09-20 2022-09-20 Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge

Publications (1)

Publication Number Publication Date
CN115404783A true CN115404783A (en) 2022-11-29

Family

ID=84166793

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211141337.5A Pending CN115404783A (en) 2022-09-20 2022-09-20 Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN115404783A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117286807A (en) * 2023-11-01 2023-12-26 保利长大工程有限公司 Bridge sliding equipment and bridge construction system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509229A (en) * 2009-03-31 2009-08-19 四川公路桥梁建设集团有限公司 Method for constructing side span beam section without joist bracket of large-span steel box girder cable-stayed bridge
CN105696469A (en) * 2015-11-16 2016-06-22 中铁四局集团有限公司 Incremental launching installation construction method for large-span bidirectional longitudinal slope steel box girder of super-large bridge
CN110541368A (en) * 2019-09-29 2019-12-06 中交路桥华南工程有限公司 method for mounting steel box girder of cable-stayed bridge
CN216640288U (en) * 2021-12-22 2022-05-31 中交第三航务工程局有限公司 Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN114775436A (en) * 2022-04-29 2022-07-22 中交武汉港湾工程设计研究院有限公司 Steel box girder sliding position-adjusting construction system, sliding vehicle and construction method
CN114855584A (en) * 2022-04-07 2022-08-05 中铁大桥勘测设计院集团有限公司 Separated type ultra-wide prestressed concrete box girder structure and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509229A (en) * 2009-03-31 2009-08-19 四川公路桥梁建设集团有限公司 Method for constructing side span beam section without joist bracket of large-span steel box girder cable-stayed bridge
CN105696469A (en) * 2015-11-16 2016-06-22 中铁四局集团有限公司 Incremental launching installation construction method for large-span bidirectional longitudinal slope steel box girder of super-large bridge
CN110541368A (en) * 2019-09-29 2019-12-06 中交路桥华南工程有限公司 method for mounting steel box girder of cable-stayed bridge
CN216640288U (en) * 2021-12-22 2022-05-31 中交第三航务工程局有限公司 Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN114855584A (en) * 2022-04-07 2022-08-05 中铁大桥勘测设计院集团有限公司 Separated type ultra-wide prestressed concrete box girder structure and construction method thereof
CN114775436A (en) * 2022-04-29 2022-07-22 中交武汉港湾工程设计研究院有限公司 Steel box girder sliding position-adjusting construction system, sliding vehicle and construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
冯殿怡: "超宽分体式钢箱梁吊装安全性能研究", 《铁路与公路》, vol. 42, no. 4, 25 August 2022 (2022-08-25), pages 126 - 127 *
曹新垒: "芜湖长江公路二桥钢箱梁架设特殊施工技术分析", 《建造技术》, vol. 32, no. 2, 15 April 2018 (2018-04-15), pages 239 - 241 *
邓德员: "超宽公轨两用钢箱梁滑移施工技术", 《施工技术》, vol. 45, no. 20, 31 October 2016 (2016-10-31), pages 75 - 78 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117286807A (en) * 2023-11-01 2023-12-26 保利长大工程有限公司 Bridge sliding equipment and bridge construction system
CN117286807B (en) * 2023-11-01 2024-04-30 保利长大工程有限公司 Bridge sliding equipment and bridge construction system

Similar Documents

Publication Publication Date Title
CN100441779C (en) Bridge construction method with prefabricated translation in place in the air
CN101736697A (en) Construction method for pushing and furling complete bracket of steel box girders
CN112176867A (en) Single-track single-span railway steel truss girder dragging, installing and constructing method and single-track single-span railway
CN104532748A (en) Exceeding thousand tons of linear steel trussed beam floating pushing erecting construction method
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN111877162A (en) Assembling construction method for prefabricated segment box girder support of urban viaduct
CN111172892B (en) A double-sided balanced traction device and method for a steel structure frame bridge
CN109629449B (en) Mounting and positioning support and alignment method for steel-concrete combined section of arch foot of steel box arch bridge
CN111455852A (en) Assembling method of movable formwork for bridge construction
CN112281916B (en) Large-axillary-angle single-side wall movable formwork for subway engineering
CN115404783A (en) Sliding construction method for super-wide separated steel box girder of super-large cable-stayed bridge
CN104831632A (en) Upper transverse beam and lower transverse beam construction method for bridge cable bent tower
CN211034860U (en) Hydraulic lifting construction device for steel structure net rack
CN207987749U (en) Ride cable-styled erection crane
CN113774813A (en) Traction deviation rectifying equipment convenient for installing large-section steel truss box girder
CN114351584A (en) Special-shaped steel ladle concrete upper tower column and construction method thereof
CN108086168A (en) Ride cable-styled erection crane
CN110094577B (en) Device and method for installing oversized-diameter inclined dam rear open pipe under strong wind condition
CN204643604U (en) Door-shaped hanging bracket waterborne
CN108004930A (en) The construction method of vertical shift bowstring arch bridge
CN216892057U (en) Large-span steel-concrete composite beam bridge steel box girder section floats and holds in palm top and pushes away construction system
CN215518416U (en) Adjustable sliding device for UHPC steel-concrete composite beam
CN114991006A (en) Basket device is hung with rhombus to construction of super wide bridge floor of many trusses formula
CN115387228A (en) A high-stability steel truss girder jacking and floating drag frame construction method
CN115288035A (en) Sliding device for ultra-wide separated steel box girder of extra-large cable-stayed bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20221129

WD01 Invention patent application deemed withdrawn after publication