CN115369748B - Formwork system construction method for integrated casting of bridge piers and tie beams - Google Patents

Formwork system construction method for integrated casting of bridge piers and tie beams Download PDF

Info

Publication number
CN115369748B
CN115369748B CN202211137288.8A CN202211137288A CN115369748B CN 115369748 B CN115369748 B CN 115369748B CN 202211137288 A CN202211137288 A CN 202211137288A CN 115369748 B CN115369748 B CN 115369748B
Authority
CN
China
Prior art keywords
pier
formwork
tie beam
tie
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211137288.8A
Other languages
Chinese (zh)
Other versions
CN115369748A (en
Inventor
蔡东波
柴少强
王友谊
周银
金川
王雪
孔德高
刘小强
汤伟
闫东杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Seventh Engineering Co Ltd
Original Assignee
CCCC Seventh Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Seventh Engineering Co Ltd filed Critical CCCC Seventh Engineering Co Ltd
Priority to CN202410778665.9A priority Critical patent/CN118547573A/en
Priority to CN202211137288.8A priority patent/CN115369748B/en
Publication of CN115369748A publication Critical patent/CN115369748A/en
Application granted granted Critical
Publication of CN115369748B publication Critical patent/CN115369748B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00—Structural or constructional details of bridges
    • E01D19/02—Piers; Abutments ; Protecting same against drifting ice
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00—Material constitution of bridges
    • E01D2101/20—Concrete, stone or stone-like material
    • E01D2101/24—Concrete
    • E01D2101/26—Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the technical field of bridge pier column construction, and particularly discloses a template system construction method for integrally pouring a pier and a tie beam, wherein S1 and pier column construction are carried out; s2, embedding a bearing upright post: when the pier column of the section before the tie beam is poured is constructed, at least two vertical bearing upright columns are embedded, and the top of each bearing upright column can be propped against and fixed with the bottom of the transverse cantilever beam of the climbing frame; s3, dismantling opposite pier side dies on the pier column and fixedly connecting upright columns on the climbing frame; s4, installing a tie beam bracket: the tie beam support is assembled into a whole on the ground, then is hoisted beside the connecting upright post, and the connecting upright post is fixedly connected with four corner positions of the tie beam support; s5, splicing the bridge pier and the tie beam templates into a whole: fixedly connecting a tie beam side die with a bridge pier side die; s6, placing steel bars in the pier-tie beam integrated template and pouring. The scheme is used for solving the problems that bridge pier appearance damage and high construction danger exist in bridge construction by constructing a bridge construction platform through a penetrating rod in the prior art.

Description

桥墩及系梁一体化浇筑的模板系统施工方法Formwork system construction method for integrated casting of bridge piers and tie beams

技术领域Technical Field

本发明涉及桥梁墩柱施工技术领域,具体涉及桥墩及系梁一体化浇筑的模板系统施工方法。The invention relates to the technical field of bridge pier construction, and in particular to a formwork system construction method for integrated casting of bridge piers and tie beams.

背景技术Background technique

高墩施工较成熟的工艺主要有爬模、滑模和翻模,爬模是爬升模板的简称,它由爬升模板、爬架(也有的爬模没有爬架)和爬升设备三部分组成,爬模施工对混凝土初凝控制要求高,预埋件易于破坏新浇筑混凝土。滑模不仅包含普通或专用等工具式模板,还包括动力滑升设备和配套施工工艺等综合技术,主要以液压顶升设备为滑升动力,在成组顶升设备的同步作用下,带动爬升系统和一米多高的工具式模板沿着安装在墩柱中的爬杆爬升,爬升过程中模板沿着刚成型的混凝土表面滑动,滑模施工对混凝土要求较高、外观控制困难。而翻模是指三角架翻模施工工艺,由传统滑模演变而来的,现广泛应用于高桥墩的施工。The more mature technologies for high pier construction mainly include climbing formwork, sliding formwork and flip formwork. Climbing formwork is the abbreviation of climbing formwork. It consists of three parts: climbing formwork, climbing frame (some climbing formworks do not have climbing frame) and climbing equipment. Climbing formwork construction has high requirements for the initial setting control of concrete, and embedded parts are easy to damage the newly poured concrete. Slip formwork not only includes ordinary or special tool formwork, but also includes comprehensive technologies such as power sliding equipment and supporting construction technology. It mainly uses hydraulic jacking equipment as the sliding power. Under the synchronous action of group jacking equipment, it drives the climbing system and the tool formwork more than one meter high to climb along the climbing pole installed in the pier column. During the climbing process, the formwork slides along the newly formed concrete surface. Slip formwork construction has high requirements for concrete and difficult to control the appearance. Flip formwork refers to the tripod flip formwork construction process, which has evolved from the traditional sliding formwork and is now widely used in the construction of high bridge piers.

针对高桥墩或超高桥墩施工,为改善墩柱的受力结构,往往需要在两个或三个墩柱之间设置起拉杆作用的系梁,系梁能够将相邻墩柱连成整体受力,使墩柱的整体刚度得到加强。系梁的常规施工方式先浇筑墩柱,墩柱施工完毕后,在两墩柱之间搭设系梁施工平台进行系梁施工。对于系梁高度较低的情况,可以搭设满堂支架作为系梁施工的支撑体系;而对于不适用于搭设满堂支架的情况,现有技术中,有采用预埋穿心棒的方式,具体为先在需要加工系梁的两个墩柱的相同高度预埋PVC管,待两个墩柱强度达到要求后,通过吊起工人,让人工配合作业往每个墩柱的PVC管内插入穿心棒,然后在穿心棒伸出墩柱的两端上方安设顶升设备,再由穿心棒上的顶升设备支撑起两根大的支撑梁,之后再在两根大的支撑梁之间平铺多根分配梁,通过分配梁支撑起系梁模板(分配粱和支撑粱组成系梁支架);这种施工方式,在穿心棒安装时没有施工平台,在穿心棒拆卸时同样没有施工平台,故而危险性比较高。In the construction of high or super-high bridge piers, in order to improve the stress structure of the pier column, it is often necessary to set a tie beam that acts as a pull rod between two or three pier columns. The tie beam can connect the adjacent pier columns to bear the stress as a whole, so that the overall rigidity of the pier column is strengthened. The conventional construction method of the tie beam is to cast the pier column first, and after the pier column construction is completed, a tie beam construction platform is set up between the two pier columns for tie beam construction. For the case of a low tie beam height, a full-height bracket can be erected as a support system for tie beam construction; for the case that is not suitable for erecting a full-height bracket, there is a method of pre-embedded through-bars in the prior art, specifically, PVC pipes are first embedded at the same height of the two piers where the tie beams need to be processed, and after the strength of the two piers reaches the requirement, the workers are lifted up and the manual work is done to insert through-bars into the PVC pipes of each pier, and then jacking equipment is installed above the two ends of the through-bars extending out of the piers, and then the jacking equipment on the through-bars supports two large support beams, and then multiple distribution beams are laid flat between the two large support beams, and the tie beam templates (the distribution beams and the support beams form the tie beam bracket) are supported by the distribution beams; this construction method has no construction platform when the through-bars are installed, and there is also no construction platform when the through-bars are removed, so it is relatively dangerous.

发明内容Summary of the invention

本发明意在提供桥墩及系梁一体化浇筑的模板系统施工方法,以解决现有技术中采用穿心棒来搭建系梁施工平台进行系梁施工存在桥墩外观损坏和施工危险性较高的问题。The present invention aims to provide a formwork system construction method for the integrated casting of bridge piers and tie beams, so as to solve the problems in the prior art of using through rods to build a tie beam construction platform for tie beam construction, resulting in damage to the appearance of the bridge piers and high construction risks.

为达到上述目的,本发明采用如下技术方案:In order to achieve the above object, the present invention adopts the following technical scheme:

桥墩及系梁一体化浇筑的模板系统施工方法,需要用到桥墩模板、爬升系统、系梁支架和系梁模板,桥墩模板包括可拆卸连接的多个桥墩侧模,所有桥墩侧模连接后能够围合成桥墩的墩柱;爬升系统包括顶升设备、爬升架、圈梁和操作平台,顶升设备与爬升架连接,顶升设备带动爬升架爬升,圈梁固定在爬升架上,操作平台固定在圈梁上;系梁模板包括系梁底模和位于底模两侧的系梁侧模;还包括如下施工步骤:The formwork system construction method for the integrated casting of piers and tie beams requires the use of pier formwork, climbing system, tie beam bracket and tie beam formwork. The pier formwork includes a plurality of detachably connected pier side forms, and all the pier side forms can be connected to form a pier column of the pier; the climbing system includes a jacking device, a climbing frame, a ring beam and an operating platform. The jacking device is connected to the climbing frame, and the jacking device drives the climbing frame to climb. The ring beam is fixed on the climbing frame, and the operating platform is fixed on the ring beam; the tie beam formwork includes a tie beam bottom formwork and tie beam side forms located on both sides of the bottom formwork; and the following construction steps are also included:

S1、墩柱施工:在底节墩柱施工时,将爬杆安装在墩柱中,以后爬杆随着墩柱的升高而逐节加高,顶升设备安装在爬杆上,通过顶升设备带动爬升架沿着爬杆爬升,每次爬升前,先将桥墩侧模从已浇筑的墩柱上脱离,待爬升系统完成爬升后,再将桥墩侧模与墩柱相抵形成浇筑用的完整桥墩模板;S1. Pier construction: During the construction of the bottom section of the pier, the climbing pole is installed in the pier. Later, the climbing pole is raised section by section as the pier rises. The jacking equipment is installed on the climbing pole. The climbing frame is driven by the jacking equipment to climb along the climbing pole. Before each climbing, the side form of the pier is separated from the cast pier. After the climbing system completes the climbing, the side form of the pier is abutted against the pier to form a complete pier formwork for casting.

S2、预埋承重立柱:在浇筑系梁前一个节段的墩柱施工时,预埋至少两根竖直的承重立柱,爬升架包括多根横挑梁,多根横挑梁横纵设置并呈井形,承重立柱的顶部能够与爬升架上的至少一根横挑梁底部相抵并固定连接;S2. Pre-embedded load-bearing columns: When constructing the pier column of the previous section of the tie beam, at least two vertical load-bearing columns are pre-embedded. The climbing frame includes a plurality of horizontal beams, which are arranged horizontally and vertically in a well shape. The top of the load-bearing column can be abutted against and fixedly connected to the bottom of at least one horizontal beam on the climbing frame.

S3、拆除墩柱上相对的桥墩侧模并在爬升架上固定连接立柱,连接立柱位于桥墩外侧;S3, remove the side formwork of the pier on the pier column and fix the connecting column on the climbing frame, the connecting column is located on the outer side of the pier;

S4、安装系梁支架:系梁支架在地面组装成整体,然后吊装到连接立柱旁,人工能够站在操作平台上将连接立柱与系梁支架的四个角位固定连接;S4. Install the tie beam bracket: The tie beam bracket is assembled into a whole on the ground, and then hoisted to the side of the connecting column. A person can stand on the operating platform to fix the connecting column and the four corners of the tie beam bracket;

S5、桥墩-系梁模板拼装成一体:将组装成整体的系梁模板吊装并放置在系梁支架上,系梁侧模与桥身横向平行,系梁侧模两端与相邻的桥墩侧模固定连接,形成含有桥墩和系梁的一体化模板;S5. Assemble the pier-tie beam formwork into one piece: hoist the assembled tie beam formwork and place it on the tie beam bracket, with the tie beam side formwork parallel to the bridge body, and the two ends of the tie beam side formwork fixedly connected to the adjacent pier side formwork to form an integrated formwork containing the pier and tie beam;

S6、在桥墩-系梁一体化模板内放置钢筋并浇筑。S6. Place and cast steel bars in the integrated pier-tie beam formwork.

本方案的原理及优点是:实际应用时,本方案在进行系梁浇筑时,承重立柱安装时可以在操作平台上预埋,只要在承重立柱满足强度要求后,即可加高承重立柱,以使得承重立柱顶部与横挑梁底部相抵,然后将承重立柱与横挑梁固定,以使得承重立柱来支撑横挑梁。再通过爬升架和连接立柱将系梁支架进行悬挂支撑,以方便通过系梁支架对系梁模板进行支撑和对施工过程中的系梁进行支撑;而连接立柱与爬升架连接时,人工可以站在井形爬升架上或者操作平台上对连接立柱进行安装,人工还可以站在操作平台上将连接立柱与系梁支架的四个角位固定连接;可见为实现对系梁模板的支撑所采取的承重立柱、连接立柱以及与系梁支架的固定连接的整个施工过程均有操作平台或者井形的爬升架进行支撑,不存在现有技术中穿心棒式的施工方式带来的因无操作平台而施工危险的情况。此外,系梁施工完成后,只需要拆除系梁模板、系梁支架和连接立柱即可,承重立柱只要拆除与横挑梁的连接而继续留在墩柱上即可,无需对承重立柱进行拆卸,降低了人工操作成本,同时承重立柱内置在墩柱上,有利于提高墩柱的强度。同时,桥墩模板和系梁模板连接成一体方便墩柱和系梁的一体化施工,提高系梁的和墩柱形成整体的桥墩强度。The principle and advantage of this scheme are: in actual application, when the tie beam is cast, the load-bearing column can be pre-buried on the operating platform when it is installed. As long as the load-bearing column meets the strength requirements, the load-bearing column can be raised so that the top of the load-bearing column is against the bottom of the horizontal beam, and then the load-bearing column is fixed to the horizontal beam so that the load-bearing column supports the horizontal beam. The tie beam bracket is then suspended and supported by the climbing frame and the connecting column, so as to facilitate the support of the tie beam template and the tie beam during the construction process by the tie beam bracket; and when the connecting column is connected to the climbing frame, the person can stand on the well-shaped climbing frame or the operating platform to install the connecting column, and the person can also stand on the operating platform to fix the connecting column with the four corners of the tie beam bracket; it can be seen that the entire construction process of the load-bearing column, the connecting column and the fixed connection with the tie beam bracket adopted to realize the support of the tie beam template is supported by the operating platform or the well-shaped climbing frame, and there is no danger of construction due to the lack of an operating platform caused by the through-rod construction method in the prior art. In addition, after the tie beam construction is completed, only the tie beam template, tie beam bracket and connecting column need to be removed. The load-bearing column only needs to be removed from the cross beam and remain on the pier column. There is no need to dismantle the load-bearing column, which reduces the labor operation cost. At the same time, the load-bearing column is built into the pier column, which is conducive to improving the strength of the pier column. At the same time, the pier template and the tie beam template are connected into one to facilitate the integrated construction of the pier column and the tie beam, and improve the strength of the pier formed by the tie beam and the pier column.

此外,在本方案中,将高墩施工的翻模方式(也即将桥墩模板从墩柱表面脱离的方式)和滑模方式(采用顶升设备和爬升架进行爬升的方式)进行了结合,使得整个墩柱施工中桥墩侧模仅在浇筑墩柱时与墩柱相贴而不会沿着墩柱表面滑动,故而保障了桥墩成型后墩柱的外观,同时本方案也无需像穿心棒的施工方式一样预制水平的PVC管,也不会对墩柱的外观造成损坏。同时利用滑模方式带动整个爬升系统的升降来减少现有翻模时操作平台频繁拆装的问题,也有利于减少施工步骤,缩短施工时间。In addition, in this scheme, the over-molding method (i.e., the method of separating the pier formwork from the pier column surface) and the slip-molding method (the method of climbing using jacking equipment and climbing frames) of high pier construction are combined, so that during the entire pier column construction, the pier side formwork is only attached to the pier column when pouring the pier column and will not slide along the pier column surface, thus ensuring the appearance of the pier column after the pier column is formed. At the same time, this scheme does not need to prefabricate horizontal PVC pipes like the construction method of through-rods, and will not cause damage to the appearance of the pier column. At the same time, the slip-molding method is used to drive the lifting and lowering of the entire climbing system to reduce the problem of frequent disassembly and assembly of the operating platform during the existing over-molding, which is also conducive to reducing construction steps and shortening construction time.

除此之外,本方案中,在系梁施工的前一节段墩柱上预埋了能够承重的承重立柱,承重立柱顶起爬升架上的横挑梁,在桥墩和系梁一体化施工时,系梁重量既有承重立柱来分担,也通过横挑梁分担到与爬升架连接的各个顶升设备上,并通过顶升设备作用在对应的爬杆上,相当于系梁施工所承受的重量由承重立柱和多根爬杆同时支撑,确保了系梁和桥墩的一体化施工的安全性。In addition, in this scheme, load-bearing columns capable of bearing weight are pre-embedded on the piers of the previous section of the tie beam construction. The load-bearing columns support the cross beams on the climbing frame. When the piers and tie beams are constructed in an integrated manner, the weight of the tie beams is shared by the load-bearing columns and also shared by the various jacking devices connected to the climbing frame through the cross beams, and acts on the corresponding climbing poles through the jacking devices. This is equivalent to the weight borne by the tie beam construction being supported by the load-bearing columns and multiple climbing poles at the same time, ensuring the safety of the integrated construction of the tie beams and piers.

优选的,作为一种改进,所述桥墩侧模通过设有的移动器与爬升架形成连接,移动器带动桥墩侧模远离或者靠近墩柱表面。Preferably, as an improvement, the pier side formwork is connected to the climbing frame via a movable device, and the movable device drives the pier side formwork to move away from or closer to the pier column surface.

有益效果:本方案通过移动器的设置,使得在墩柱浇筑过程中,从桥墩表面脱离的桥墩侧模无需吊装到地面上,只需要悬挂在不与墩柱相贴以方便爬升系统爬升即可,爬升完成后,再利用移动器将桥墩侧模贴紧墩柱,以使得多个桥墩侧模围合成完整的桥墩模板,使得整个墩柱的施工操作更加简单快速,有利于缩短墩柱施工所耗时长。Beneficial effect: Through the setting of the mover, this scheme makes it possible that during the pier casting process, the pier side formwork detached from the pier surface does not need to be hoisted to the ground, but only needs to be hung at a place not in contact with the pier to facilitate the climbing of the climbing system. After the climbing is completed, the mover is used to press the pier side formwork close to the pier, so that multiple pier side forms are enclosed into a complete pier formwork, making the construction operation of the entire pier column simpler and faster, which is conducive to shortening the time consumed for pier construction.

优选的,作为一种改进,所述桥墩侧模还包括钢板和背楞,背楞包括水平背楞和竖直背楞,水平背楞和竖直背楞均与钢板固定连接。Preferably, as an improvement, the pier side formwork further includes a steel plate and back ribs, the back ribs include horizontal back ribs and vertical back ribs, and the horizontal back ribs and the vertical back ribs are both fixedly connected to the steel plate.

有益效果:通过在桥墩侧模上设置水平背楞和竖直背楞,能够加大桥墩侧模的强度和刚度,抵抗施工浇注过程中产生的侧压力,保证施工安全和质量。Beneficial effect: By arranging horizontal back ribs and vertical back ribs on the side formwork of the pier, the strength and rigidity of the side formwork of the pier can be increased, the lateral pressure generated during the construction and pouring process can be resisted, and the construction safety and quality can be ensured.

优选的,作为一种改进,所述爬升架上转动连接有能够进行长度调整的抵紧杆,抵紧杆的另一端与桥墩侧模转动连接。Preferably, as an improvement, a clamping rod capable of adjusting its length is rotatably connected to the climbing frame, and the other end of the clamping rod is rotatably connected to the side form of the pier.

有益效果:本方案长度可调的抵紧杆的设计,能够方便再移动器带动桥墩侧模移动到目标位置后,再利用长度能够调整的抵紧杆,将桥墩侧模抵紧在墩柱上,提高桥墩侧模与墩柱的贴合效果,降低墩柱浇筑过程中泥浆漏出的概率。Beneficial effect: The design of the clamping rod with adjustable length in this scheme can facilitate the mover to drive the pier side form to the target position, and then use the clamping rod with adjustable length to clamp the pier side form to the pier column, thereby improving the fit between the pier side form and the pier column and reducing the probability of mud leakage during the pier column pouring process.

优选的,作为一种改进,所述系梁模板还包括系梁端模,系梁端模同时与系梁侧模和系梁底模的端部固定连接,系梁端模向系梁底模外延伸,系梁端模能够与墩柱相贴,系梁端模能够与桥墩侧模可拆卸连接。Preferably, as an improvement, the tie beam formwork also includes a tie beam end formwork, which is fixedly connected to the ends of the tie beam side formwork and the tie beam bottom formwork at the same time, and the tie beam end formwork extends outward from the tie beam bottom formwork, and the tie beam end formwork can be attached to the pier column, and the tie beam end formwork can be detachably connected to the pier side formwork.

有益效果:本方案通过对系梁端模的设置,使得系梁模板可以在地面进行组装,组装完成后即吊装到施工高度,并通过系梁模板上的系梁端模方便系梁模板与墩柱的快速对准,也方便系梁模板与桥墩侧模的快速对接并安装,有利于节约桥墩-系梁一体化模板的安装和拆卸时间。Beneficial effects: This solution allows the tie beam formwork to be assembled on the ground through the setting of the tie beam end formwork, which can be hoisted to the construction height after assembly. The tie beam end formwork on the tie beam formwork facilitates the rapid alignment of the tie beam formwork with the pier column, and also facilitates the rapid docking and installation of the tie beam formwork with the pier side formwork, which is beneficial to saving the installation and disassembly time of the pier-tie beam integrated formwork.

除此之外,向系梁外侧延伸的系梁端模的设置,使得系梁模板两端系梁端模之间的系梁底模正好能够被系梁支架所支撑,为系梁支架支撑系梁模板提供支撑空间。In addition, the arrangement of the tie beam end formwork extending to the outside of the tie beam enables the tie beam bottom formwork between the tie beam end formworks at both ends of the tie beam formwork to be supported by the tie beam bracket, providing support space for the tie beam bracket to support the tie beam formwork.

优选的,作为一种改进,所述系梁支架包括两根支撑梁和多根分配梁,多根分配梁固定在两根支撑梁上方,系梁模板能够放置在分配梁上,支撑梁与连接立柱固定连接。Preferably, as an improvement, the tie beam bracket includes two supporting beams and multiple distribution beams, the multiple distribution beams are fixed above the two supporting beams, the tie beam template can be placed on the distribution beams, and the supporting beams are fixedly connected to the connecting columns.

有益效果:系梁支架可以在地面进行拼装,拼装完成后再整体吊装,方便系梁支架的快速安装。Beneficial effect: The tie beam bracket can be assembled on the ground and then hoisted as a whole after the assembly is completed, which is convenient for the rapid installation of the tie beam bracket.

优选的,作为一种改进,所述圈梁包括多个子圈梁,相邻子圈梁之间可拆卸连接,所有子圈梁连接后将墩柱围合。Preferably, as an improvement, the ring beam comprises a plurality of sub-ring beams, adjacent sub-ring beams are detachably connected to each other, and all the sub-ring beams are connected to enclose the pier.

有益效果:本方案通过对圈梁的结构改进,使得圈梁既可以是所有子圈梁围合组成的整体,也可以是单个的方便与其他子圈梁进行拆装的单个子圈梁,降低圈梁安装时对吊装设备的要求(如单个圈梁吊装则对吊装设备的要求更低)。Beneficial effect: Through the structural improvement of the ring beam, this scheme makes the ring beam either a whole composed of all sub-ring beams or a single sub-ring beam that is easy to disassemble and assemble with other sub-ring beams, thereby reducing the requirements for lifting equipment during the installation of the ring beam (for example, the requirements for lifting equipment are lower when lifting a single ring beam).

优选的,作为一种改进,所述操作平台包括施工操作平台和模板安拆操作平台,施工操作平台位于圈梁的上方,模板安拆操作平台位于圈梁的下方,模板安拆操作平台包括可拆卸子平台和固定子平台,可拆卸子平台与固定子平台、圈梁均可拆卸连接,固定子平台与圈梁固定连接,可拆卸子平台与桥身纵向平行;桥墩模板在浇筑时的顶部低于圈梁底部。Preferably, as an improvement, the operating platform includes a construction operating platform and a formwork installation and removal operating platform, the construction operating platform is located above the ring beam, the formwork installation and removal operating platform is located below the ring beam, the formwork installation and removal operating platform includes a detachable sub-platform and a fixed sub-platform, the detachable sub-platform is detachably connected to the fixed sub-platform and the ring beam, the fixed sub-platform is fixedly connected to the ring beam, and the detachable sub-platform is parallel to the longitudinal direction of the bridge body; the top of the pier formwork is lower than the bottom of the ring beam during casting.

有益效果:本方案通过对操作平台的具体限定,使得施工能够在施工操作平台上进行,而在需要拆卸桥墩侧模时,可以站在模板安拆操作平台上进行,方便人工直接对需要拆卸的桥墩侧模进行拆卸,而无需借助吊装设备;此外,在系梁支架安装前,可以先利用模板安拆操作平台将连接立柱与爬升架固定连接,再拆卸掉可拆卸子平台,为系梁模板和桥墩模板的连接腾出空间,同时工人还可以站在固定子平台上对系梁支架与连接立柱进行固定安装,保证施工过程可以有平台可以站立。Beneficial effects: This solution enables construction to be carried out on the construction operation platform through specific limitations on the operating platform. When it is necessary to dismantle the pier side formwork, it can be done while standing on the formwork installation and disassembly operation platform, making it convenient for manual labor to directly dismantle the pier side formwork that needs to be dismantled without the aid of lifting equipment. In addition, before installing the tie beam bracket, the formwork installation and disassembly operation platform can be used to first fix the connecting column and the climbing frame, and then the detachable sub-platform can be removed to make room for the connection between the tie beam formwork and the pier formwork. At the same time, workers can also stand on the fixed sub-platform to fix and install the tie beam bracket and the connecting column, ensuring that there is a platform to stand on during the construction process.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本发明实施例的桥墩模板结构示意图。FIG1 is a schematic diagram of a pier formwork structure according to an embodiment of the present invention.

图2为本发明实施例的桥墩模板拆卸掉其中一个桥墩侧模后的结构示意图。FIG2 is a schematic diagram of the structure of the pier formwork after one of the pier side forms is removed according to an embodiment of the present invention.

图3为本发明实施例的爬升系统不含操作平台时的结构示意图。FIG3 is a schematic structural diagram of a climbing system according to an embodiment of the present invention without an operating platform.

图4为图3中拆卸其中一个子圈梁后的结构示意图。FIG. 4 is a schematic diagram of the structure after one of the sub-ring beams in FIG. 3 is disassembled.

图5为本发明实施例的爬升系统在墩柱浇筑时的纵桥向墩身断面示意图。5 is a schematic diagram of a cross-section of the pier body in the longitudinal direction of the bridge when the pier column is cast, according to an embodiment of the present invention.

图6为本发明实施例中模板安拆操作平台的结构俯视图。FIG. 6 is a top view of the structure of the template installation and removal operation platform in an embodiment of the present invention.

图7为图5中的抵紧杆的结构示意图。FIG. 7 is a schematic structural diagram of the abutting rod in FIG. 5 .

图8为本发明实施例中系梁模板的结构示意图。FIG8 is a schematic structural diagram of a tie beam template in an embodiment of the present invention.

图9为本发明实施例对应步骤S1并隐藏操作平台时的结构示意图。FIG. 9 is a schematic structural diagram of an embodiment of the present invention corresponding to step S1 when the operating platform is hidden.

图10为本发明实施例在步骤S1时模板安拆操作平台与墩柱、桥墩模板的俯视示意图。FIG. 10 is a schematic top view of the template installation and removal operation platform and the pier columns and pier templates in step S1 according to an embodiment of the present invention.

图11为本发明实施例对应步骤S2并隐藏操作平台时的结构示意图。FIG. 11 is a schematic structural diagram of an embodiment of the present invention corresponding to step S2 when the operating platform is hidden.

图12为本发明实施例对应步骤S3并隐藏操作平台时的结构示意图。FIG. 12 is a schematic diagram of the structure of an embodiment of the present invention corresponding to step S3 when the operating platform is hidden.

图13为本发明实施例对应步骤S4并隐藏操作平台和隐藏部分子圈梁时的结构示意图。FIG. 13 is a schematic structural diagram of an embodiment of the present invention corresponding to step S4 when the operating platform and part of the sub-ring beam are hidden.

图14为本发明实施例对应步骤S5并隐藏操作平台和隐藏部分子圈梁时的结构示意图。FIG. 14 is a schematic structural diagram of an embodiment of the present invention corresponding to step S5 when the operating platform and part of the sub-ring beam are hidden.

图15为本发明实施例在步骤S5时模板安拆操作平台与墩柱、桥墩模板、系梁模板的俯视示意图。15 is a schematic top view of the template installation and removal operation platform and the pier column, pier template, and tie beam template in step S5 according to an embodiment of the present invention.

具体实施方式Detailed ways

下面通过具体实施方式进一步详细说明:The following is further described in detail through specific implementation methods:

说明书附图中的附图标记包括:桥墩模板10、桥墩侧模1、钢板11、背楞12、拉杆13、爬升系统20、爬升架21、横挑梁211、斜撑212、竖梁213、抵紧杆214、丝杆2141、安装套2142、圈梁22、千斤顶23、施工操作平台24、模板安拆操作平台25、上层平台251、下层平台252、支撑梁31、分配梁32、系梁模板40、系梁侧模41、系梁底模42、系梁端模43、爬杆50、承重立柱60、连接立柱70、墩柱100。The figure marks in the drawings of the specification include: pier formwork 10, pier side formwork 1, steel plate 11, back rib 12, pull rod 13, climbing system 20, climbing frame 21, horizontal cantilever beam 211, diagonal brace 212, vertical beam 213, tightening rod 214, screw rod 2141, installation sleeve 2142, ring beam 22, jack 23, construction operation platform 24, formwork installation and disassembly operation platform 25, upper platform 251, lower platform 252, support beam 31, distribution beam 32, tie beam formwork 40, tie beam side formwork 41, tie beam bottom formwork 42, tie beam end formwork 43, climbing pole 50, load-bearing column 60, connecting column 70, pier column 100.

实施例基本如附图1至图15所示:The embodiments are basically as shown in Figures 1 to 15:

桥墩及系梁一体化浇筑的模板系统施工方法,需要用到桥墩模板10、爬升系统20、系梁支架和系梁模板40,结合图1和图2,桥墩模板10包括可拆卸连接的多个桥墩侧模1,所有桥墩侧模1连接后能够围合成桥墩的墩柱100;桥墩侧模1还包括钢板11和背楞12,背楞12包括水平背楞12和竖直背楞12,水平背楞12和竖直背楞12均与钢板11固定连接;相对的桥墩侧模1在将墩柱100围合后,可以通过在相对的桥墩侧模1上安装对拉杆13的方式来增强相对的桥墩侧模1之间的连接强度。The formwork system construction method for the integrated casting of piers and tie beams requires a pier formwork 10, a climbing system 20, a tie beam bracket and a tie beam formwork 40. In conjunction with Figures 1 and 2, the pier formwork 10 includes a plurality of detachably connected pier side forms 1, and all the pier side forms 1 can be connected to enclose a pier column 100 of the pier; the pier side formwork 1 also includes a steel plate 11 and a back rib 12, and the back rib 12 includes a horizontal back rib 12 and a vertical back rib 12, and the horizontal back rib 12 and the vertical back rib 12 are both fixedly connected to the steel plate 11; after the opposite pier side forms 1 enclose the pier column 100, the connection strength between the opposite pier side forms 1 can be enhanced by installing tie rods 13 on the opposite pier side forms 1.

结合图3至图7,爬升系统20包括顶升设备、爬升架21、圈梁22和操作平台,顶升设备与爬升架21连接,顶升设备带动爬升架21爬升(本实施例中顶升设备采用带有液压泵的千斤顶23),结合图3和图4,圈梁22固定在爬升架21上,操作平台固定在圈梁22上;在施工阶段为了增强各部件之间的强度,可以对螺栓连接的两个部件采取焊接加强板的方式形成暂时的固定连接,在需要拆除时,再将加强板切割拆除即可。In conjunction with Figures 3 to 7, the climbing system 20 includes a jacking device, a climbing frame 21, a ring beam 22 and an operating platform. The jacking device is connected to the climbing frame 21, and the jacking device drives the climbing frame 21 to climb (in this embodiment, the jacking device adopts a jack 23 with a hydraulic pump). In conjunction with Figures 3 and 4, the ring beam 22 is fixed on the climbing frame 21, and the operating platform is fixed on the ring beam 22; in order to enhance the strength between the components during the construction stage, the two components connected by bolts can be welded with a reinforcement plate to form a temporary fixed connection. When removal is required, the reinforcement plate can be cut and removed.

具体地,爬升架21包括多根横挑梁211,多根横挑梁211横纵设置并呈井形,相邻横挑梁211之间焊接。圈梁22包括多个子圈梁22,相邻子圈梁22之间通过螺栓连接,所有子圈梁22连接后将墩柱100围合,所有子圈梁22均与爬升架21连接(爬升架21上焊接有斜撑212和竖梁213,斜撑212和竖梁213形成三角形,斜撑212和竖梁213均与子圈梁22固定连接);结合图5和图6,操作平台包括施工操作平台24和模板安拆操作平台25,施工操作平台24固定于圈梁22的上方,模板安拆操作平台25位于圈梁22的下方,模板安拆操作平台25包括可拆卸子平台和固定子平台,可拆卸子平台与固定子平台、圈梁22均通过螺栓连接,固定子平台与圈梁22固定连接,可拆卸子平台与桥身纵向平行;桥墩模板10在浇筑时的顶部低于圈梁22底部。为方便对施工后的墩柱100表面进行修复,模板安拆操作平台25可以做成双层结构(上层平台251和下层平台252),上下两层结构完全相同,如图5所示,以方便工作人员的作业,同时因下层平台252可以设计的比桥墩侧模1位置低,故而能够方便工人在模板安拆操作平台25上对墩柱100表面进行修复。Specifically, the climbing frame 21 includes a plurality of transverse beams 211 , which are arranged horizontally and vertically in a well shape, and adjacent transverse beams 211 are welded. The ring beam 22 includes a plurality of sub-ring beams 22, and adjacent sub-ring beams 22 are connected by bolts. After all the sub-ring beams 22 are connected, the pier 100 is enclosed. All the sub-ring beams 22 are connected to the climbing frame 21 (the climbing frame 21 is welded with diagonal braces 212 and vertical beams 213, the diagonal braces 212 and the vertical beams 213 form a triangle, and the diagonal braces 212 and the vertical beams 213 are fixedly connected to the sub-ring beams 22); in combination with Figures 5 and 6, the operating platform includes a construction operating platform 24 and a template installation and disassembly operating platform 25, the construction operating platform 24 is fixed above the ring beam 22, the template installation and disassembly operating platform 25 is located below the ring beam 22, the template installation and disassembly operating platform 25 includes a detachable sub-platform and a fixed sub-platform, the detachable sub-platform is connected to the fixed sub-platform and the ring beam 22 by bolts, the fixed sub-platform is fixedly connected to the ring beam 22, and the detachable sub-platform is parallel to the longitudinal direction of the bridge body; the top of the pier template 10 is lower than the bottom of the ring beam 22 during casting. In order to facilitate the repair of the surface of the pier 100 after construction, the template installation and disassembly operation platform 25 can be made into a double-layer structure (upper platform 251 and lower platform 252), and the upper and lower structures are exactly the same, as shown in Figure 5, to facilitate the work of the staff. At the same time, because the lower platform 252 can be designed to be lower than the position of the pier side formwork 1, it is convenient for workers to repair the surface of the pier 100 on the template installation and disassembly operation platform 25.

结合图5和图7,爬升架21上转动连接有能够进行长度调整的抵紧杆214,抵紧杆214的另一端与桥墩侧模1转动连接。抵紧杆214包括丝杆2141和安装在丝杆2141两端的安装套2142,丝杆2141上加工有螺旋旋向相反的两个螺纹段,两个安装套2142分别螺纹连接在两段不同的螺纹段上,两个安装套2142一个转动连接在爬升架21上,另一个能够转动连接在桥墩侧模1上;两个螺纹段之间加工有径向的通孔,以方便工人在通孔内插入施力杆,进而旋转丝杆2141,丝杆2141旋转后,两个安装套2142相互靠近以缩短抵紧杆214或者两个安装套2142相互远离以加长抵紧杆214;通过抵紧杆214的伸出以将桥墩侧模1与墩柱100之间的间隙更小,提高桥墩侧模1的侧面抗压能力。5 and 7 , a clamping rod 214 capable of adjusting its length is rotatably connected to the climbing frame 21 , and the other end of the clamping rod 214 is rotatably connected to the pier side mold 1 . The clamping rod 214 includes a screw rod 2141 and mounting sleeves 2142 installed at both ends of the screw rod 2141. The screw rod 2141 is processed with two threaded sections with opposite spiral rotation directions. The two mounting sleeves 2142 are respectively threadedly connected to the two different threaded sections. One of the two mounting sleeves 2142 is rotatably connected to the climbing frame 21, and the other can be rotatably connected to the pier side form 1; a radial through hole is processed between the two threaded sections to facilitate workers to insert the force rod into the through hole, and then rotate the screw rod 2141. After the screw rod 2141 rotates, the two mounting sleeves 2142 approach each other to shorten the clamping rod 214 or the two mounting sleeves 2142 move away from each other to lengthen the clamping rod 214; the gap between the pier side form 1 and the pier column 100 is made smaller by extending the clamping rod 214, thereby improving the side compressive resistance of the pier side form 1.

桥墩侧模1通过设有的移动器与爬升架21形成连接,移动器带动桥墩侧模1远离或者靠近墩柱100表面,移动器带动桥墩侧模1远离墩柱100后,即实现了桥墩模板10从墩柱100上脱离下来的动作;本实施例中移动器可以采用移动小车(图中未视出),移动小车固定在爬升架21上,桥墩侧模1固定在移动小车的输出端。在需要墩柱100上的桥墩侧模1拆除前,需要先将抵紧杆214与桥墩侧模1的连接解除,再通过移动小车带动桥墩侧模1远离墩柱100。The pier side formwork 1 is connected to the climbing frame 21 through a provided mover, and the mover drives the pier side formwork 1 away from or close to the surface of the pier column 100. After the mover drives the pier side formwork 1 away from the pier column 100, the pier formwork 10 is separated from the pier column 100. In this embodiment, the mover can be a moving trolley (not shown in the figure), the moving trolley is fixed on the climbing frame 21, and the pier side formwork 1 is fixed at the output end of the moving trolley. Before the pier side formwork 1 on the pier column 100 needs to be removed, the connection between the clamping rod 214 and the pier side formwork 1 needs to be released first, and then the pier side formwork 1 is driven away from the pier column 100 by the moving trolley.

系梁支架包括两根支撑梁31和多根分配梁32,多根分配梁32固定在两根支撑梁31上方。The tie beam bracket includes two support beams 31 and a plurality of distribution beams 32 , and the plurality of distribution beams 32 are fixed above the two support beams 31 .

结合图8,系梁模板40包括系梁底模42、位于底模两侧的系梁侧模41、同时与系梁侧模41和系梁底模42的端部固定连接的系梁端模43,系梁端模43向系梁底模42外延伸,系梁端模43能够与墩柱100相贴,系梁端模43能够与桥墩侧模1通过螺栓连接;还包括如下施工步骤:8 , the tie beam formwork 40 includes a tie beam bottom formwork 42, tie beam side forms 41 located on both sides of the bottom formwork, and a tie beam end formwork 43 fixedly connected to the ends of the tie beam side formwork 41 and the tie beam bottom formwork 42. The tie beam end formwork 43 extends outward from the tie beam bottom formwork 42. The tie beam end formwork 43 can be attached to the pier column 100, and the tie beam end formwork 43 can be connected to the pier side formwork 1 by bolts. The following construction steps are also included:

S1、墩柱100施工:在底节墩柱100施工时,将爬杆50安装在墩柱100中,以后爬杆50随着墩柱100的升高而逐节加高,顶升设备安装在爬杆50上,通过顶升设备带动爬升架21沿着爬杆50爬升,每次爬升前,先将抵紧杆214的安装套2142从桥墩侧模1上拆卸,并拆除相对桥墩侧模1之间的拉杆13,然后启动移动小车,使得移动小车带动墩侧模从已浇筑的墩柱100上脱离,待爬升系统20完成爬升后,再启动移动小车,使得移动小车将桥墩侧模1与墩柱100相抵,之后安装拉杆13,安装抵紧杆214,以使得桥墩侧模1之间紧固并形成浇筑用的完整桥墩模板10。图9为本实施例以一个桥墩具有3个墩柱100施工为例(为方便理解,将图纸中的操作平台隐藏了),图10为3个墩柱100施工时,模板安拆操作平台25与墩柱100、桥墩模板10的俯视示意图。S1. Construction of pier 100: During the construction of the bottom section pier 100, the climbing rod 50 is installed in the pier 100. Later, the climbing rod 50 is raised section by section as the pier 100 rises. The jacking equipment is installed on the climbing rod 50. The climbing frame 21 is driven by the jacking equipment to climb along the climbing rod 50. Before each climbing, the installation sleeve 2142 of the clamping rod 214 is first removed from the pier side form 1, and the pull rod 13 between the relative pier side form 1 is removed. Then, the mobile trolley is started to drive the pier side form to separate from the poured pier 100. After the climbing system 20 completes the climbing, the mobile trolley is started again to make the mobile trolley abut the pier side form 1 against the pier 100. Then, the pull rod 13 and the clamping rod 214 are installed to tighten the pier side form 1 and form a complete pier formwork 10 for pouring. FIG9 shows an example of the construction of a pier with three pier columns 100 in this embodiment (the operating platform in the drawing is hidden for ease of understanding), and FIG10 is a top view of the template installation and removal operating platform 25, the pier columns 100, and the pier template 10 when the three pier columns 100 are under construction.

S2、预埋承重立柱60:在浇筑系梁前一个节段的墩柱100施工时,预埋至少两根竖直的承重立柱60(如图11所示),承重立柱60的顶部能够与爬升架21上的至少一根横挑梁211底部相抵并固定连接;本实施例中,与承重立柱60相抵的横挑梁211与桥身纵向平行;本实施例中承重立柱60采用工字钢,横挑梁211采用双拼槽钢。S2. Pre-embedded load-bearing columns 60: When constructing the pier 100 of a section before casting the tie beam, at least two vertical load-bearing columns 60 are pre-embedded (as shown in FIG. 11 ). The top of the load-bearing column 60 can abut against and be fixedly connected to the bottom of at least one transverse beam 211 on the climbing frame 21. In this embodiment, the transverse beam 211 abutting against the load-bearing column 60 is parallel to the longitudinal direction of the bridge body. In this embodiment, the load-bearing column 60 is made of I-beam, and the transverse beam 211 is made of double-jointed channel steel.

S3、拆除墩柱100上相对的桥墩侧模1、拆除模板安拆操作平台25上墩柱100相对侧的可拆卸子平台,以为后续系梁支架的安装腾出空间,并将固定子平台的端部增加护栏,以保障安全;之后在与承重立柱60相连的横挑梁211的两端固定连接立柱70,连接立柱70位于桥墩外侧,本实施例中连接立柱70采用工字钢,也即图12所示。S3. Remove the pier side formwork 1 on the pier 100, and remove the detachable sub-platform on the opposite side of the pier 100 on the formwork installation and disassembly operation platform 25 to make room for the subsequent installation of the tie beam bracket, and add guardrails at the ends of the fixed sub-platform to ensure safety; then fix connecting columns 70 at both ends of the cross beam 211 connected to the load-bearing column 60, and the connecting columns 70 are located on the outside of the pier. In this embodiment, the connecting columns 70 are made of I-beams, as shown in Figure 12.

需要拆卸的桥墩侧模1拆卸后,在与桥身纵向平行的横挑梁211两端固定连接立柱70,连接立柱70悬挂固定在横挑梁211上,该操作人工可以站在施工操作平台24上完成。After the pier side formwork 1 that needs to be dismantled is dismantled, connecting columns 70 are fixed at both ends of the transverse cantilever beam 211 parallel to the longitudinal direction of the bridge body, and the connecting columns 70 are suspended and fixed on the transverse cantilever beam 211. This operation can be completed manually standing on the construction operation platform 24.

S4、安装系梁支架:将已经在地面上组装成整体的系梁支架吊装到连接立柱70旁,人工能够站在模板安拆操作平台25的固定平台上将连接立柱70与系梁支架的两个支撑梁31的端部固定连接,使得连接立柱70从系梁支架四个角位挂起系梁支架,也即如图13所示(图中为方便理解,将操作平台从图纸上隐藏并将其中墩柱100相对侧的子圈梁22隐藏)。S4. Install the tie beam bracket: hoist the tie beam bracket that has been assembled into an integral whole on the ground to the side of the connecting column 70, and a person can stand on the fixed platform of the template installation and disassembly operation platform 25 to fix the connecting column 70 with the ends of the two support beams 31 of the tie beam bracket, so that the connecting column 70 hangs the tie beam bracket from the four corners of the tie beam bracket, as shown in Figure 13 (for ease of understanding, the operating platform is hidden from the drawing and the sub-ring beam 22 on the opposite side of the pier 100 is hidden).

S5、桥墩-系梁模板40拼装成一体:将组装成整体的系梁模板40吊装并放置在系梁支架上,使得系梁侧模41与桥身横向平行,两端的系梁端模43分别与两个墩柱100的相对表面相贴并与墩柱100上相邻的桥墩侧模1固定连接,系梁底模42放置在系梁支架的分配梁32上,形成含有桥墩和系梁的一体化模板,也即从图13转变到图14。系梁浇筑前,模板安拆操作平台25与墩柱100、桥墩模板10和系梁模板40的俯视示意图达到如图15所示。S5. Assemble the pier-tie beam template 40 into one piece: hoist the assembled tie beam template 40 and place it on the tie beam support, so that the tie beam side form 41 is parallel to the bridge body in the horizontal direction, the tie beam end form 43 at both ends are respectively attached to the opposite surfaces of the two piers 100 and fixedly connected to the adjacent pier side form 1 on the pier 100, and the tie beam bottom form 42 is placed on the distribution beam 32 of the tie beam support to form an integrated template containing the pier and the tie beam, that is, change from Figure 13 to Figure 14. Before the tie beam is cast, the template installation and removal operation platform 25 and the pier 100, the pier template 10 and the tie beam template 40 are shown in Figure 15.

S6、在桥墩-系梁一体化模板内放置钢筋并浇筑。S6. Place and cast steel bars in the integrated pier-tie beam formwork.

采用本施工方式对桥墩系梁进行施工时,承重立柱60安装时可以在施工操作平台24上预埋,只要在承重立柱60满足强度要求后,即可加高承重立柱60,以使得承重立柱60顶部与横挑梁211底部相抵,然后将承重立柱60与横挑梁211固定,以使得承重立柱60来支撑横挑梁211;再通过横挑梁211和连接立柱70将系梁支架进行悬挂支撑,以方便通过系梁支架对系梁模板40进行支撑和对施工过程中的系梁进行支撑;而连接立柱70与爬升架21连接时,人工可以站在井形爬升架21上或者施工操作平台24上对连接立柱70进行安装,人工可以站在模板安拆操作平台25上将连接立柱70与系梁支架的支撑梁31固定连接;可见为实现对系梁模板40的支撑所采取的承重立柱60、连接立柱70以及与系梁支架的固定连接的整个施工过程均有操作平台或者井形的爬升架21进行支撑,保证了施工的安全性。此外,系梁施工完成后,只需要拆除系梁模板40、系梁支架和连接立柱70即可,承重立柱60只要拆除与横挑梁211的连接而继续留在墩柱100上即可,无需对承重立柱60进行拆卸,降低了人工操作成本,同时承重立柱60内置在墩柱100上,有利于提高墩柱100的强度。同时,桥墩模板10和系梁模板40连接成一体方便墩柱100和系梁的一体化施工,提高系梁的和墩柱100形成整体的桥墩强度。When the present construction method is used to construct the tie beam of the bridge pier, the load-bearing column 60 can be pre-buried on the construction operation platform 24 during installation. As long as the load-bearing column 60 meets the strength requirements, the load-bearing column 60 can be raised so that the top of the load-bearing column 60 is against the bottom of the horizontal beam 211, and then the load-bearing column 60 and the horizontal beam 211 are fixed so that the load-bearing column 60 supports the horizontal beam 211; and then the tie beam bracket is suspended and supported by the horizontal beam 211 and the connecting column 70, so as to facilitate the support of the tie beam formwork 40 by the tie beam bracket and the construction process. The tie beam in the middle is supported; when the connecting column 70 is connected to the climbing frame 21, a person can stand on the well-shaped climbing frame 21 or the construction operation platform 24 to install the connecting column 70, and a person can stand on the template installation and disassembly operation platform 25 to fix the connecting column 70 with the support beam 31 of the tie beam bracket; it can be seen that the entire construction process of the load-bearing column 60, the connecting column 70 and the fixed connection with the tie beam bracket adopted to support the tie beam template 40 is supported by the operation platform or the well-shaped climbing frame 21, which ensures the safety of the construction. In addition, after the tie beam construction is completed, it is only necessary to remove the tie beam template 40, the tie beam bracket and the connecting column 70. The load-bearing column 60 only needs to remove the connection with the cross beam 211 and continue to stay on the pier 100. There is no need to disassemble the load-bearing column 60, which reduces the labor operation cost. At the same time, the load-bearing column 60 is built into the pier 100, which is conducive to improving the strength of the pier 100. At the same time, the pier formwork 10 and the tie beam formwork 40 are connected as one body to facilitate the integrated construction of the pier column 100 and the tie beam, thereby improving the strength of the pier formed by the tie beam and the pier column 100 as a whole.

此外,在本实施例中,将高墩施工的翻模方式(也即将桥墩模板10从墩柱100表面脱离的方式)和滑模方式(采用顶升设备和爬升架21进行爬升的方式)进行了结合,使得整个墩柱100施工中桥墩侧模1仅在浇筑墩柱100时与墩柱100相贴而不会沿着墩柱100表面滑动,故而保障了桥墩成型后墩柱100的外观。同时利用滑模方式带动整个爬升系统20的升降来减少现有翻模时操作平台频繁拆装的问题,也有利于减少施工步骤,缩短施工时间。In addition, in this embodiment, the over-molding method (i.e., the method of separating the pier formwork 10 from the surface of the pier column 100) and the sliding formwork method (the method of climbing using jacking equipment and climbing frame 21) of high pier construction are combined, so that during the construction of the entire pier column 100, the pier side formwork 1 is only attached to the pier column 100 when pouring the pier column 100 and will not slide along the surface of the pier column 100, thereby ensuring the appearance of the pier column 100 after the pier is formed. At the same time, the sliding formwork method is used to drive the lifting of the entire climbing system 20 to reduce the problem of frequent disassembly and assembly of the operating platform during the existing over-molding, which is also conducive to reducing construction steps and shortening construction time.

除此之外,本实施例中,在系梁施工的前一节段墩柱100上预埋了能够承重的承重立柱60,承重立柱60顶起爬升架21上的横挑梁211,在桥墩和系梁一体化施工时,系梁重量既有承重立柱60来分担,也通过横挑梁211分担到与爬升架21连接的各个顶升设备上,并通过顶升设备作用在对应的爬杆50上,相当于系梁施工所承受的重量由承重立柱60和多根爬杆50同时支撑,确保了系梁和桥墩的一体化施工的安全性。In addition, in the present embodiment, a load-bearing column 60 capable of bearing weight is pre-embedded on the pier 100 of the previous segment of the tie beam construction, and the load-bearing column 60 lifts up the cross beam 211 on the climbing frame 21. When the piers and the tie beams are constructed in an integrated manner, the weight of the tie beam is shared by the load-bearing column 60 and is also shared by various lifting devices connected to the climbing frame 21 through the cross beam 211, and acts on the corresponding climbing poles 50 through the lifting devices. This is equivalent to the weight borne by the tie beam construction being supported by the load-bearing column 60 and multiple climbing poles 50 at the same time, ensuring the safety of the integrated construction of the tie beam and the piers.

以上所述的仅是本发明的实施例,方案中公知的具体技术方案和/或特性等常识在此未作过多描述。应当指出,对于本领域的技术人员来说,在不脱离本发明技术方案的前提下,还可以作出若干变形和改进,这些也应该视为本发明的保护范围,这些都不会影响本发明实施的效果和专利的实用性。本申请要求的保护范围应当以其权利要求的内容为准,说明书中的具体实施方式等记载可以用于解释权利要求的内容。The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and/or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, several modifications and improvements can be made without departing from the technical solution of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims (7)

1.桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,需要用到桥墩模板、爬升系统、系梁支架和系梁模板,桥墩模板包括可拆卸连接的多个桥墩侧模,所有桥墩侧模连接后能够围合成桥墩的墩柱;爬升系统包括顶升设备、爬升架、圈梁和操作平台,顶升设备与爬升架连接,顶升设备带动爬升架爬升,圈梁固定在爬升架上,操作平台固定在圈梁上;系梁模板包括系梁底模和位于底模两侧的系梁侧模;操作平台包括施工操作平台和模板安拆操作平台,施工操作平台位于圈梁的上方,模板安拆操作平台位于圈梁的下方,模板安拆操作平台包括可拆卸子平台和固定子平台,可拆卸子平台与固定子平台、圈梁均可拆卸连接,固定子平台与圈梁固定连接,可拆卸子平台与桥身纵向平行;桥墩模板在浇筑时的顶部低于圈梁底部;还包括如下施工步骤:1. A formwork system construction method for integrally casting piers and tie beams, characterized in that a pier formwork, a climbing system, a tie beam support and a tie beam formwork are required, the pier formwork comprises a plurality of detachably connected pier side forms, all of which can be connected to enclose a pier column of the pier; the climbing system comprises a jacking device, a climbing frame, a ring beam and an operating platform, the jacking device is connected to the climbing frame, the jacking device drives the climbing frame to climb, the ring beam is fixed on the climbing frame, and the operating platform is fixed on the ring beam; the tie beam formwork comprises a tie beam bottom formwork and tie beam side forms located on both sides of the bottom formwork; the operating platform comprises a construction operating platform and a formwork installation and removal operating platform, the construction operating platform is located above the ring beam, the formwork installation and removal operating platform is located below the ring beam, the formwork installation and removal operating platform comprises a detachable sub-platform and a fixed sub-platform, the detachable sub-platform is detachably connected to the fixed sub-platform and the ring beam, the fixed sub-platform is fixedly connected to the ring beam, and the detachable sub-platform is parallel to the longitudinal direction of the bridge body; the top of the pier formwork is lower than the bottom of the ring beam during casting; and the following construction steps are also included: S1、墩柱施工:在底节墩柱施工时,将爬杆安装在墩柱中,以后爬杆随着墩柱的升高而逐节加高,顶升设备安装在爬杆上,通过顶升设备带动爬升架沿着爬杆爬升,每次爬升前,先将桥墩侧模从已浇筑的墩柱上脱离,待爬升系统完成爬升后,再将桥墩侧模与墩柱相抵形成浇筑用的完整桥墩模板;S1. Pier construction: During the construction of the bottom section of the pier, the climbing pole is installed in the pier. Later, the climbing pole is raised section by section as the pier rises. The jacking equipment is installed on the climbing pole. The climbing frame is driven by the jacking equipment to climb along the climbing pole. Before each climbing, the side form of the pier is separated from the cast pier. After the climbing system completes the climbing, the side form of the pier is abutted against the pier to form a complete pier formwork for casting. S2、预埋承重立柱:在浇筑系梁前一个节段的墩柱施工时,预埋至少两根竖直的承重立柱,爬升架包括多根横挑梁,多根横挑梁横纵设置并呈井形,承重立柱的顶部能够与爬升架上的至少一根横挑梁底部相抵并固定连接;S2. Pre-embedded load-bearing columns: When constructing the pier column of the previous section of the tie beam, at least two vertical load-bearing columns are pre-embedded. The climbing frame includes a plurality of horizontal beams, which are arranged horizontally and vertically in a well shape. The top of the load-bearing column can be abutted against and fixedly connected to the bottom of at least one horizontal beam on the climbing frame. S3、拆除墩柱上相对的桥墩侧模并在爬升架上固定连接立柱,连接立柱位于桥墩外侧;S3, remove the side formwork of the pier on the pier column and fix the connecting column on the climbing frame, the connecting column is located on the outer side of the pier; S4、安装系梁支架:系梁支架在地面组装成整体,然后吊装到连接立柱旁,人工能够站在操作平台上将连接立柱与系梁支架的四个角位固定连接;S4. Install the tie beam bracket: The tie beam bracket is assembled into a whole on the ground, and then hoisted to the side of the connecting column. A person can stand on the operating platform to fix the connecting column and the four corners of the tie beam bracket; S5、桥墩-系梁模板拼装成一体:将组装成整体的系梁模板吊装并放置在系梁支架上,系梁侧模与桥身横向平行,系梁侧模两端与相邻的桥墩侧模固定连接,形成含有桥墩和系梁的一体化模板;S5. Assemble the pier-tie beam formwork into one piece: hoist the assembled tie beam formwork and place it on the tie beam bracket, with the tie beam side formwork parallel to the bridge body, and the two ends of the tie beam side formwork fixedly connected to the adjacent pier side formwork to form an integrated formwork containing the pier and tie beam; S6、在桥墩-系梁一体化模板内放置钢筋并浇筑。S6. Place and cast steel bars in the integrated pier-tie beam formwork. 2.根据权利要求1所述的桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,所述桥墩侧模通过设有的移动器与爬升架形成连接,移动器带动桥墩侧模远离或者靠近墩柱表面。2. The formwork system construction method for integrated casting of bridge piers and tie beams according to claim 1 is characterized in that the side formwork of the bridge pier is connected to the climbing frame through a movable device, and the movable device drives the side formwork of the bridge pier to move away from or close to the surface of the pier column. 3.根据权利要求2所述的桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,所述桥墩侧模还包括钢板和背楞,背楞包括水平背楞和竖直背楞,水平背楞和竖直背楞均与钢板固定连接。3. According to the formwork system construction method for integrated casting of piers and tie beams as described in claim 2, it is characterized in that the pier side formwork also includes a steel plate and back ribs, the back ribs include horizontal back ribs and vertical back ribs, and the horizontal back ribs and the vertical back ribs are both fixedly connected to the steel plate. 4.根据权利要求3所述的桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,所述爬升架上转动连接有能够进行长度调整的抵紧杆,抵紧杆的另一端与桥墩侧模转动连接。4. The formwork system construction method for integrated casting of bridge piers and tie beams according to claim 3 is characterized in that a clamping rod with adjustable length is rotatably connected to the climbing frame, and the other end of the clamping rod is rotatably connected to the side formwork of the pier. 5.根据权利要求1所述的桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,所述系梁模板还包括系梁端模,系梁端模同时与系梁侧模和系梁底模的端部固定连接,系梁端模向系梁底模外延伸,系梁端模能够与墩柱相贴,系梁端模能够与桥墩侧模可拆卸连接。5. The formwork system construction method for integrated casting of bridge piers and tie beams according to claim 1 is characterized in that the tie beam formwork also includes a tie beam end formwork, which is fixedly connected to the ends of the tie beam side formwork and the tie beam bottom formwork at the same time, and the tie beam end formwork extends outward from the tie beam bottom formwork, the tie beam end formwork can be attached to the pier column, and the tie beam end formwork can be detachably connected to the pier side formwork. 6.根据权利要求5所述的桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,所述系梁支架包括两根支撑梁和多根分配梁,多根分配梁固定在两根支撑梁上方,系梁模板能够放置在分配梁上,支撑梁与连接立柱固定连接。6. The formwork system construction method for integrated casting of piers and tie beams according to claim 5 is characterized in that the tie beam support includes two supporting beams and multiple distribution beams, the multiple distribution beams are fixed above the two supporting beams, the tie beam formwork can be placed on the distribution beams, and the supporting beams are fixedly connected to the connecting columns. 7.根据权利要求5所述的桥墩及系梁一体化浇筑的模板系统施工方法,其特征在于,所述圈梁包括多个子圈梁,相邻子圈梁之间可拆卸连接,所有子圈梁连接后将墩柱围合。7. The formwork system construction method for integrated casting of bridge piers and tie beams according to claim 5 is characterized in that the ring beam includes a plurality of sub-ring beams, adjacent sub-ring beams are detachably connected, and all the sub-ring beams are connected to enclose the pier column.
CN202211137288.8A 2022-09-19 2022-09-19 Formwork system construction method for integrated casting of bridge piers and tie beams Active CN115369748B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202410778665.9A CN118547573A (en) 2022-09-19 2022-09-19 Template system for integrally pouring bridge pier and tie beam
CN202211137288.8A CN115369748B (en) 2022-09-19 2022-09-19 Formwork system construction method for integrated casting of bridge piers and tie beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211137288.8A CN115369748B (en) 2022-09-19 2022-09-19 Formwork system construction method for integrated casting of bridge piers and tie beams

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN202410778665.9A Division CN118547573A (en) 2022-09-19 2022-09-19 Template system for integrally pouring bridge pier and tie beam

Publications (2)

Publication Number Publication Date
CN115369748A CN115369748A (en) 2022-11-22
CN115369748B true CN115369748B (en) 2024-06-04

Family

ID=84071648

Family Applications (2)

Application Number Title Priority Date Filing Date
CN202211137288.8A Active CN115369748B (en) 2022-09-19 2022-09-19 Formwork system construction method for integrated casting of bridge piers and tie beams
CN202410778665.9A Pending CN118547573A (en) 2022-09-19 2022-09-19 Template system for integrally pouring bridge pier and tie beam

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN202410778665.9A Pending CN118547573A (en) 2022-09-19 2022-09-19 Template system for integrally pouring bridge pier and tie beam

Country Status (1)

Country Link
CN (2) CN115369748B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116837737B (en) * 2023-07-17 2025-10-17 中建一局集团第一建筑有限公司 Method for constructing heat pipeline bent cap by using penetrating rod
CN116927099B (en) * 2023-08-31 2025-09-09 中交一公局第七工程有限公司 Operation platform for multi-pier column and tie beam integrated construction
CN116971287B (en) * 2023-08-31 2025-09-12 中交一公局第七工程有限公司 Synchronous lifting system and method for multi-pier construction platform
CN117026828B (en) * 2023-08-31 2025-08-26 中交一公局第七工程有限公司 Integrated construction method of multi-pier column and tie beam
CN116905382B (en) * 2023-08-31 2025-08-26 中交一公局第七工程有限公司 Tie beam casting support structure for column-tie beam integrated construction
CN116927100B (en) * 2023-08-31 2025-09-12 中交一公局第七工程有限公司 Automatic installation and removal system of tie beam formwork for integrated column and tie beam construction
CN117127509B (en) * 2023-08-31 2025-09-09 中交一公局第七工程有限公司 Column tie beam integrated construction system
CN117127510B (en) * 2023-08-31 2025-09-16 中交一公局第七工程有限公司 A tie beam pouring system for integrative construction of post tie beam
CN117385765B (en) * 2023-11-30 2026-05-29 中交一公局第七工程有限公司 Bridge pier template perpendicularity control method
CN117569213B (en) * 2023-12-06 2024-08-13 中交一公局集团有限公司 Construction method of high bridge pier

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003328320A (en) * 2002-05-15 2003-11-19 Taisei Corp Construction method of precast column head and bridge pier column head
CN106930194A (en) * 2017-05-10 2017-07-07 山西路桥第二工程有限公司 Inter-tie and pier stud global formation construction method and template used support
CN207878262U (en) * 2017-12-15 2018-09-18 中铁上海工程局集团有限公司 A kind of high pier shaft binder concrete construction strutting system
CN110396941A (en) * 2019-08-22 2019-11-01 湖南中铁五新钢模有限责任公司 A kind of bridge pier column construction system and construction method
CN110700105A (en) * 2019-10-21 2020-01-17 中交一公局第七工程有限公司 Synchronous construction method for high pier column and tie beam and template used in same
CN215947902U (en) * 2021-06-30 2022-03-04 中建七局第四建筑有限公司 Tie beam template support system in adjustable highway cylinder mound

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003328320A (en) * 2002-05-15 2003-11-19 Taisei Corp Construction method of precast column head and bridge pier column head
CN106930194A (en) * 2017-05-10 2017-07-07 山西路桥第二工程有限公司 Inter-tie and pier stud global formation construction method and template used support
CN207878262U (en) * 2017-12-15 2018-09-18 中铁上海工程局集团有限公司 A kind of high pier shaft binder concrete construction strutting system
CN110396941A (en) * 2019-08-22 2019-11-01 湖南中铁五新钢模有限责任公司 A kind of bridge pier column construction system and construction method
CN110700105A (en) * 2019-10-21 2020-01-17 中交一公局第七工程有限公司 Synchronous construction method for high pier column and tie beam and template used in same
CN215947902U (en) * 2021-06-30 2022-03-04 中建七局第四建筑有限公司 Tie beam template support system in adjustable highway cylinder mound

Also Published As

Publication number Publication date
CN118547573A (en) 2024-08-27
CN115369748A (en) 2022-11-22

Similar Documents

Publication Publication Date Title
CN118547573A (en) Template system for integrally pouring bridge pier and tie beam
CN105908777B (en) A kind of pipe gallery sliding mould and its application method
CN108360380B (en) A kind of bridge pier column construction work platform and construction method thereof
CN110700105A (en) Synchronous construction method for high pier column and tie beam and template used in same
CN111119071A (en) Construction method for assembling precast concrete segment box girder
CN116733504A (en) Method for assembling tunnel arch ring and cable pit side wall two-lining steel mould trolley
CN110878522A (en) Construction system and construction method of beam under main tower
CN113403946B (en) Three leaf round pin hinge formula bridge column mound creeping formwork devices
CN109138431B (en) Super high-rise pump pipe bridge crossing device and construction method thereof
CN107460889A (en) Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery
CN117090581A (en) A construction method for integral hoisting formwork and secondary lining of shaft
CN116084293B (en) Triangular steel arch formwork system and construction method for cast-in-place concrete main arch ring
CN217810535U (en) From climbing formula steel bar locating support
CN109944164B (en) Self-elevating hollow thin-wall pier roller die system and construction method thereof
CN203200664U (en) Slip-form construction device for variable cross-section hollow high pier
CN207512610U (en) A kind of assembled bridge pier construction operation platform
CN114892528A (en) Double-layer formwork construction method for uniform-section thin-wall hollow pier
CN114876209A (en) Steel reinforced beam sectional construction method for limited hoisting
CN116104018B (en) Construction method of variable-section special-shaped steel tower crown installation device
CN220394299U (en) Novel hydraulic climbing formwork overhanging operation platform
CN219604164U (en) Variable cross-section special-shaped steel tower crown mounting device
CN113309256A (en) Construction device and construction method for prefabricated shear wall with post-pouring section
CN218714838U (en) Self-lifting heavy-load construction platform
CN214423182U (en) Cast-in-place case roof beam formwork structure of flat longitudinal curve sectional variable cross section
CN118007536A (en) Civil engineering turnover mould process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant