CN115306438A - Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure - Google Patents

Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure Download PDF

Info

Publication number
CN115306438A
CN115306438A CN202210944312.2A CN202210944312A CN115306438A CN 115306438 A CN115306438 A CN 115306438A CN 202210944312 A CN202210944312 A CN 202210944312A CN 115306438 A CN115306438 A CN 115306438A
Authority
CN
China
Prior art keywords
tunnel
existing
construction method
existing tunnel
secondary lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210944312.2A
Other languages
Chinese (zh)
Inventor
付勉
古正斌
邓清
蒋文勇
马磊
王�琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202210944312.2A priority Critical patent/CN115306438A/en
Publication of CN115306438A publication Critical patent/CN115306438A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/12Temporary supports for use during building; Accessories
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A construction method for underground excavation and hole entry on an existing tunnel secondary lining structure in a city comprises the following steps: s1, constructing temporary support of the existing tunnel structural steel upright column; s2, excavating a pilot tunnel and constructing a temporary support; s3, reversely expanding and excavating, excavating a standard section of the newly-built tunnel and primarily supporting; s4, constructing a door-shaped frame structure system; s5, dismantling a temporary support of the existing tunnel structure steel upright; s6, monitoring the deformation of the existing tunnel structure, wherein the construction method reduces the damage height of the existing structure through the advanced pilot tunnel and the door-shaped frame structure system, reduces the disturbance to the existing structure, enhances the bearing capacity and stress conversion among the structures, and ensures the safety of the existing tunnel secondary lining structure; safety guarantee is provided for the excavation construction process through temporary steel supports and the advanced large pipe shed; the leakage resistance between the new structure and the old structure is improved by the construction method of the waterproof and drainage reinforcing system.

Description

Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure
Technical Field
The invention relates to the technical field of tunnel engineering, in particular to a construction method for secretly digging a hole in an existing tunnel secondary lining structure in a city.
Background
In the construction of newly-built tunnel engineering, the opening is usually directly opened on a mountain body or a rock surface to enter a hole, the stress condition of surrounding rocks is simple, and the stability is relatively easy to control.
In many urban underground projects, new and old structures are built in stages to be broken and combined to form tunnel groups with cross interfaces. The existing tunnel structure is newly built with an opening, if a common hole entering measure or mode is used, the damage range of the existing tunnel structure is relatively large, the larger the safety disturbance is, and the structural safety cannot be guaranteed. In the construction process, the hole cannot be effectively sealed for a long time, the combination difficulty of a new structure and an old structure is high, the waterproof influence range is relatively large, and the like are all adverse factors required to be faced by a common hole entering mode.
Therefore, it is necessary to design a construction method for excavating a hole in an existing tunnel secondary lining structure to solve some technical problems in the prior art.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a construction method for secretly digging a hole in an existing urban tunnel secondary lining structure, which comprises the following steps:
s1, temporary support construction of existing tunnel structural steel stand columns;
s2, excavating a pilot tunnel and constructing a temporary support;
s3, reversely expanding and excavating, excavating a standard section of the newly-built tunnel and primarily supporting;
s4, constructing a door-shaped frame structure system;
s5, dismantling a temporary support of the existing tunnel structure steel upright;
and S6, monitoring the deformation of the existing tunnel structure.
Preferably, the step S2 includes the steps of:
s21, constructing a big pipe shed by leading a pilot tunnel;
s22, excavating a pilot tunnel;
and S23, constructing a temporary supporting arch frame of the pilot tunnel.
Preferably, the step S4 includes the steps of:
s41, effectively connecting a door-shaped frame structure system with a waterproof layer and a steel bar of an existing tunnel structure, and treating a construction joint;
s42, pouring a door-shaped frame beam structure, grouting a pipe, and reserving a pre-buried pipeline for construction.
Preferably, in step S1, the steel upright temporary supports are connected to each other by steel tie beams, a stiffening rib is disposed at a node, and a top end of the steel upright temporary support is tightly attached to a concrete surface of an existing tunnel arch structure.
Preferably, in step S21, the leading large pipe shed is arranged in 4m and 6m sections, and is driven in sections, and the joints are staggered.
Preferably, in step S23, the temporary arch support of the pilot tunnel needs to apply a foot-locking anchor at each arch foot and arch-raising line node.
Preferably, in step S41, the door-shaped frame structure is welded and fixed to the waterproof layer, and the drainage blind pipe is encrypted to drain at a position where the weld is large, that is, where the water seepage is large.
Compared with the prior art, the invention has the beneficial effects that: the construction method reduces the damage height of the existing structure through the pilot tunnel and the door-shaped frame structure system, reduces the disturbance to the existing structure, strengthens the bearing capacity and stress conversion between the structures, and ensures the safety of the existing tunnel secondary lining structure; safety guarantee is provided for the excavation construction process through temporary steel supports and the advanced large pipe shed; the leakage resistance between the new structure and the old structure is improved by the construction method of the waterproof and drainage reinforcing system.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention. In the drawings:
figure 1 is a plan view of an undercut entry hole in an existing tunnel secondary lining structure.
Figure 2 is a front view of a tunnel being undercut into a hole in an existing tunnel secondary lining structure.
Figure 3 is a side view of a tunnel undercut into a hole in an existing tunnel secondary structure.
In the figure: 1. temporarily supporting the steel upright; 2. leading a hole in advance; 3. a portal frame structure beam; 4. a portal frame structure column; 5. advancing a large pipe shed; 6. a grouting pipe; 7. and reserving a pre-buried pipeline.
Detailed Description
The technical solution of the present invention is described in detail below with reference to the accompanying drawings, but the scope of the present invention is not limited to the embodiments.
Referring to fig. 1 to 3, a construction method for excavating a hole in an existing urban tunnel secondary lining structure includes the following steps:
s1, constructing a temporary support 1 of an existing tunnel structural steel upright column;
s2, excavation and temporary support construction of leading tunnel 2
S21, constructing a leading tunnel 2 in advance of the large pipe shed 5;
s22, excavating the pilot tunnel 2;
s23, constructing a temporary supporting arch frame of the pilot tunnel 2;
s3, reversely expanding and excavating, excavating a standard section of the newly-built tunnel and primarily supporting;
s4, constructing a door-shaped frame structure system: constructing a door-shaped frame structure beam 3 and a door-shaped frame structure upright post 4 in a door-shaped frame structure system;
s41, effectively connecting a door-shaped frame structure system with a waterproof layer and a steel bar of an existing tunnel structure, and treating a construction joint;
s42, pouring a door-shaped frame beam structure, grouting a pipe 6 and reserving a pre-buried pipeline 7 for construction;
s5, dismantling the temporary support 1 of the existing tunnel structure steel upright post;
and S6, monitoring the deformation of the existing tunnel structure.
In the figures 1 and 3, the temporary supports 1 of the steel columns are phi 500, t =16mm hot-rolled seamless steel tubes, the steel columns are connected into a whole by steel connecting beams, the steel connecting beams are triangular wedges welded by matching double-spliced I16-type steel with steel plates, after prestress is applied, C20 concrete is poured and fixed on footing, so that the safety of the existing tunnel structure is ensured, stiffening ribs are arranged at nodes, and the top ends of the temporary supports 1 of the steel columns are tightly attached to the concrete surface of the existing tunnel arch structure.
In the figure 2, outside the excavation outline of the pilot tunnel 2, phi 108 x 6 advanced large pipe sheds 5 with the length of 10M, the ring distance of 0.4M and the inclination angle of 1-2 degrees are constructed, each pipe shed is arranged according to the lengths of 4M and 6M in a segmented manner, the joints are staggered, and M30 cement slurry is adopted for pre-grouting of the advanced large pipe sheds 5, so that safety guarantee is provided in the excavation construction process.
In the figures 2 and 3, the prior pilot tunnel 2 excavation is to reduce the disturbance to the structure as much as possible, so as to ensure short footage, one excavation is carried out, and the temporary support adopts the form of profile steel arch centering matched with anchor net spraying, so as to ensure the structure safety.
In the figures 1 and 3, the temporary support of the pilot tunnel 2 is gradually removed in the process until the wall back of the existing side wall structure is excavated in a reverse expanding mode according to the standard section of the newly-built tunnel, and meanwhile, the preliminary support of the main tunnel is constructed, and the structural safety is ensured by adopting the mode that a profile steel arch frame is matched with an anchor net for spraying. And finally, manually excavating a door-shaped frame structure foundation trench.
In the figure 3, after the gate-type frame structure foundation trench is dug in place, the waterproof layer of the gate-type frame structure is effectively welded with the waterproof layer stripped from the existing structure, a drainage blind pipe is arranged for drainage, a water swelling water stop strip is arranged after the joint concrete surface is cleaned and roughened, the cross section is coated with cement permeable crystalline coating, the treatment quality of the construction joint is ensured, a phi 32 grouting steel pipe is pre-buried before concrete pouring so as to facilitate later-stage grouting, and the structure is guaranteed to be compact and reliable.
In fig. 1 and 3, after the door-shaped frame structure and the first formwork second lining concrete of the newly-built tunnel reach the design strength, the temporary supports 1 of the steel upright posts are orderly removed by manpower, and then the newly-built tunnel is normally constructed.
The construction method reduces the damage height of the existing structure through the pilot tunnel 2 and the door-shaped frame structure system, reduces the disturbance to the existing structure, strengthens the bearing capacity and stress conversion between the structures, and ensures the safety of the existing tunnel secondary lining structure; the temporary steel supports and the advanced large pipe shed 5 provide safety guarantee for the excavation construction process; the leakage resistance between the new structure and the old structure is improved by the construction method of the waterproof and drainage reinforcing system.
As above, while the invention has been shown and described with reference to certain preferred embodiments, it is not to be construed as limited thereto. Various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (7)

1. A construction method for underground excavation and hole entering on a secondary lining structure of an existing tunnel in a city is characterized by comprising the following steps:
s1, temporary support construction of existing tunnel structural steel stand columns;
s2, excavating a pilot tunnel and constructing a temporary support;
s3, reversely expanding and excavating, excavating a standard section of the newly-built tunnel and primarily supporting;
s4, constructing a door-shaped frame structure system;
s5, dismantling a temporary support of the existing tunnel structure steel upright;
and S6, monitoring the deformation of the existing tunnel structure.
2. The construction method for underground excavation and entering of the hole in the secondary lining structure of the urban existing tunnel according to claim 1, wherein the step S2 comprises the following steps:
s21, constructing a big pipe shed by leading a pilot tunnel;
s22, excavating a pilot tunnel;
and S23, constructing a temporary supporting arch frame of the pilot tunnel.
3. The construction method for undercutting and digging a hole in an existing urban tunnel secondary lining structure according to claim 1, wherein the step S4 comprises the following steps:
s41, effectively connecting a door-shaped frame structure system with a waterproof layer and a steel bar of an existing tunnel structure, and treating a construction joint;
s42, pouring a door-shaped frame beam structure, grouting a pipe, and reserving a pre-buried pipeline for construction.
4. The construction method for underground excavation and entering of the secondary lining structure of the urban existing tunnel according to claim 1, wherein in the step S1, the temporary supports of the steel columns are connected into a whole by steel connecting beams, stiffening ribs are arranged at nodes, and the top ends of the temporary supports of the steel columns are tightly attached to the concrete surface of the arch structure of the existing tunnel.
5. The construction method for secretly digging a hole in a secondary lining structure of an existing tunnel in a city according to claim 2, wherein in the step S21, the lengths of the sections of the large advancing pipe shed are arranged according to 4m and 6m, the sections are driven in, and the joints are staggered.
6. The construction method for underground excavation of a hole in a secondary lining structure of an urban existing tunnel according to claim 2, wherein in step S23, the temporary arch support of the pilot tunnel is constructed by applying a foot-locking anchor at each arch foot and arch-raising line node.
7. The construction method for secretly digging and entering a hole in the secondary lining structure of the urban existing tunnel according to claim 2, wherein in the step S41, the door-shaped frame structure is welded and fixed with the waterproof layer, and drainage blind pipes are arranged at positions with larger welding seams, namely positions with larger water seepage for drainage.
CN202210944312.2A 2022-08-08 2022-08-08 Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure Pending CN115306438A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210944312.2A CN115306438A (en) 2022-08-08 2022-08-08 Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210944312.2A CN115306438A (en) 2022-08-08 2022-08-08 Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure

Publications (1)

Publication Number Publication Date
CN115306438A true CN115306438A (en) 2022-11-08

Family

ID=83859978

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210944312.2A Pending CN115306438A (en) 2022-08-08 2022-08-08 Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure

Country Status (1)

Country Link
CN (1) CN115306438A (en)

Similar Documents

Publication Publication Date Title
CN110056369B (en) Construction method for entrance and exit hole of tunnel
CN109826630B (en) Precast concrete open caisson device for pipe jacking construction and construction method thereof
US3412562A (en) Structural wall and method
CN111677520B (en) Construction method for excavating station structure by tunnel-first station-later station pipe curtain hole-pile method
CN108612110A (en) A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting
CN113565133A (en) Semi-covered excavation sequential urban tunnel structure next to subway and construction method
CN111778994A (en) Pipe-jacking working well supporting device for municipal pipeline engineering and construction method
CN110820762A (en) Construction method of stiff-core curtain pile and retaining wall pile anchor combined supporting structure
CN113417649B (en) Underground tunnel small-section to large-section expanding excavation method
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN110777802A (en) Deep foundation pit high-low span supporting structure and construction method thereof
CN105386779B (en) The counterfort method of large underground structure is built in shallow embedding rock stratum
CN107326932B (en) Quasi-semi-reverse construction method for underground garage
CN110616719B (en) Quick construction method for U-shaped groove of upper-span existing culvert
CN114673377B (en) Construction method for retaining and reconstructing exterior wall of historical building and hollow interior
CN115306438A (en) Construction method for underground excavation and hole entering on existing urban tunnel secondary lining structure
CN110735641A (en) Construction method of transfer passage of underpass pipeline
CN115095330A (en) Construction method for excavating holes in hidden mode on secondary lining structure of urban existing tunnel
CN213926387U (en) Simple plugging structure for reserved sleeve of underground structure outer wall
CN215860219U (en) Large pipe shed guide wall structure of underground excavation tunnel
CN215057408U (en) Reinforcing device for intersection of inclined shaft and main tunnel of highway tunnel
CN213448506U (en) Plugging structure arranged between foundation pit fender posts
CN110318419B (en) Construction method of one-lining door opening support of underpass type pipe gallery
CN113847041A (en) Method for treating soft collapse area in tunnel excavation
CN112814003A (en) Rectangular staggered joint assembled well wall structure and assembling method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination