CN115170068A CN202210774798.XA CN202210774798A CN115170068A CN 115170068 A CN115170068 A CN 115170068A CN 202210774798 A CN202210774798 A CN 202210774798A CN 115170068 A CN115170068 A CN 115170068A
Authority
CN
China
Prior art keywords
construction
constructor
target
green
steps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210774798.XA
Other languages
Chinese (zh)
Inventor
沈海荣
周平
赵波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wujiang Construction Engineering Group Co ltd
Original Assignee
Wujiang Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wujiang Construction Engineering Group Co ltd filed Critical Wujiang Construction Engineering Group Co ltd
Priority to CN202210774798.XA priority Critical patent/CN115170068A/en
Publication of CN115170068A publication Critical patent/CN115170068A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C21/00Navigation; Navigational instruments not provided for in groups G01C1/00 - G01C19/00
    • G01C21/26Navigation; Navigational instruments not provided for in groups G01C1/00 - G01C19/00 specially adapted for navigation in a road network
    • G01C21/34Route searching; Route guidance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/29Geographical information databases
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/30Individual registration on entry or exit not involving the use of a pass
    • G07C9/32Individual registration on entry or exit not involving the use of a pass in combination with an identity check

Abstract

The application relates to the technical field of information systems of the Internet of things, in particular to a green construction informatization management method, a system, a terminal and a medium, aiming at solving the problems that in the prior art, the access control system only limits the checking of constructors to whether the constructors are recorded in a database or not and is difficult to finely manage and assist the constructors, and the technical scheme is the green construction informatization management method which comprises the following steps: acquiring a construction plan of a target construction site; acquiring identity information of a constructor, wherein the identity information at least comprises a work type of the constructor; comparing the work types of the constructors with the construction work types; if the construction work type comprises the work type of the constructor, an access authorization signal is generated, the constructor is subjected to work type division management based on a construction plan, and therefore the fine degree effect of the construction site personnel management is improved.

Description

Green construction informatization management method, system, terminal and medium
Technical Field
The application relates to the technical field of information systems of the Internet of things, in particular to a green construction informatization management method, a green construction informatization management system, a green construction informatization management terminal and a green construction informatization management medium.
Background
With the continuous advance of industrialization and urbanization, residents have extremely urgent needs for improving the living environment, and the scale of the building industry is expanded along with the development. Construction sites for construction work involve production activities in various stages of construction implementation, involve work in various stages from preparation for construction, earth breaking work to completion acceptance, and are extremely complicated production processes.
Due to the complexity of building construction, the environment of a construction site is complex, and a lot of personnel are needed to perform fine management on the personnel of the construction site in order to perform engineering projects.
At present, the management of personnel on a construction site is generally performed through an access control system on the construction site, the access control system performs identity verification on the personnel entering and exiting the construction site, and after the verification is passed, the access control system releases the checked personnel and records the entering and exiting behaviors of related personnel.
In the process of implementing the present application, the inventors found that the above-mentioned technology has at least the following problems:
the access control system only records whether the constructors are in the database or not, and is difficult to finely manage and assist the constructors.
Disclosure of Invention
In order to manage the construction workers according to different types of work based on a construction plan and improve the refinement degree of the construction site worker management, the application provides a green construction informatization management method, a system, a terminal and a medium.
In a first aspect, the application provides a method for managing green construction informatization, which adopts the following technical scheme:
a green construction informatization management method comprises the following steps:
obtaining a construction plan of a target construction site, wherein the construction plan at least comprises a construction area and a construction work type;
acquiring identity information of a constructor, wherein the identity information at least comprises a work type of the constructor;
comparing the work category of the constructor with the construction work category;
and if the construction work type comprises the work type of the constructor, generating an access authorization signal.
Through adopting above-mentioned technical scheme, acquire the construction plan in order to acquire the required construction work type of construction of the present time interval of building site through the construction plan, manage the personnel that need get into the construction site through the construction work type to help avoiding entering the place with the work type that the construction plan that carries on in the current time quantum building site is irrelevant, help reducing constructor and be unfamiliar with the construction operation and lead to disturbing the possibility of construction progress, thereby help improving the security of construction site and guarantee construction plan's completion efficiency.
In a specific embodiment, the method further comprises:
acquiring geographic information of the target construction site based on a preset GIS system;
establishing an electronic map of the target worksite based on the geographic information;
and identifying a construction area on the electronic map.
By adopting the technical scheme, the geographic information of the target construction site is acquired on the basis of the GIS system, the electronic map is established, the electronic map is favorable for visually displaying the construction site through the electronic map, meanwhile, the construction area is identified, and the position information of the construction area can be found on the electronic map intuitively by constructors, so that the possibility that the constructors find the construction area mistakenly is reduced, and the efficiency of finding the construction area by the constructors is improved.
In a specific implementation manner, after identifying the construction area on the electronic map, the method further includes:
acquiring a target construction area corresponding to the work type of the constructor;
and when an access authorization signal is generated, broadcasting the target construction area, and highlighting the target construction area on an electronic map.
By adopting the technical scheme, after the target construction area corresponding to the type of the construction worker is obtained, the corresponding target construction area of the construction worker is prompted in a highlight display and broadcast mode, so that the construction worker can obtain the related information of the target construction area from two senses of vision and hearing, and the auxiliary effect of finding the target construction area for the construction worker is improved.
In a specific possible embodiment, the method further comprises:
acquiring the real-time position of a constructor;
and when the real-time position of the constructor is not in the target construction area, sending a deviation prompt to the constructor.
Through adopting above-mentioned technical scheme, through the real-time supervision to constructor position, deviate when constructor deviates target construction area and remind, help managing and supplementary the inside constructor in real time of construction site.
In a specific implementation manner, after sending a deviation prompt to the constructor when the real-time position of the constructor is not in the target construction area, the method further includes:
and generating route guidance through a preset path navigation model based on the real-time position of the constructor and the electronic map.
By adopting the technical scheme, the guidance of the return route is carried out on the constructors deviating from the construction area through the electronic map, and the auxiliary effect on the constructors is improved.
In a specific embodiment, the method further comprises:
and updating the construction plan progress information according to a preset time period.
By adopting the technical scheme, the progress information of the construction plan is periodically updated, so that the management of the construction information management system based on the latest construction progress is facilitated, and the effectiveness of the personnel management of the construction site is facilitated to be ensured.
In a second aspect, the present application provides a green construction informatization management system, which adopts the following technical scheme:
a green construction informatization management system, the system comprising:
the construction planning module is used for obtaining a construction plan of a target construction site, and the construction plan at least comprises a construction area and a construction work type;
the system comprises a personnel information module, a construction personnel management module and a data processing module, wherein the personnel information module is used for acquiring identity information of construction personnel, and the identity information at least comprises the work type of the construction personnel;
the information checking module is used for comparing the work types of the constructors with the construction work types;
and the access authorization module is used for generating an access authorization signal if the construction work type comprises the work type of the constructor.
Through adopting above-mentioned technical scheme, acquire the construction plan in order to acquire the required construction worker type of building site current period construction through the construction plan, manage the personnel that need get into the construction site through the construction worker type to help avoiding getting into the place with the construction plan irrelevant work type that goes on in the time quantum building site, help reducing constructor and be unfamiliar with the construction operation and lead to disturbing the possibility of construction progress, thereby help improving the security of construction site and guarantee construction plan's completion efficiency.
In a third aspect, the present application provides an intelligent terminal, which adopts the following technical scheme:
an intelligent terminal, comprising a processor and a memory, wherein the memory stores at least one instruction, at least one program, a code set, or an instruction set, and the at least one instruction, the at least one program, the code set, or the instruction set is loaded and executed by the processor to implement the method for managing green construction informatization according to any one of the first aspects.
By adopting the technical scheme, the processor in the intelligent terminal can realize the green construction informatization management method according to the related computer program stored in the memory, and further contributes to carrying out the division and classification management on constructors based on the construction plan, so that the refinement degree of the construction site personnel management is improved.
In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solutions:
a computer readable storage medium having stored therein at least one instruction, at least one program, a set of codes, or a set of instructions, which is loaded and executed by a processor to implement a method for greenery construction informatization management as recited in any one of the first aspects.
Through adopting above-mentioned technical scheme, can save corresponding procedure, and then help carrying out the branch work kind management to constructor based on the construction plan to improve the degree that becomes more meticulous of construction site personnel management.
In summary, the present application includes at least one of the following beneficial technical effects:
the construction plan is obtained so that construction types required by construction of the construction site in the current time period can be obtained through the construction plan, and personnel needing to enter the construction site are managed through the construction types, so that the situation that the construction types irrelevant to the construction plan performed in the construction site in the current time period enter the site is avoided, the possibility that construction progress is interfered due to the fact that the construction personnel are unfamiliar with construction operation is reduced, and the safety of the construction site is improved and the completion efficiency of the construction plan is guaranteed;
after the target construction area corresponding to the work type of the constructor is obtained, the corresponding target construction area of the constructor is prompted in a highlight display and broadcast mode, so that the constructor can obtain related information of the target construction area from two senses of vision and hearing, and the auxiliary effect of searching for the target construction area by the constructor is improved;
through the real-time supervision to constructor position, deviate when constructor deviates from target construction area and remind, help managing and supplementary the inside constructor in the construction place in real time.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
FIG. 1 is a flow chart of a method for managing green construction information in an embodiment of the present application;
FIG. 2 is a system flow chart of a method for managing green construction information in the embodiment of the present application;
fig. 3 is a schematic structural diagram of the intelligent terminal shown in the embodiment of the present application.
Detailed Description
The present embodiments are only illustrative and not restrictive, and those skilled in the art can make modifications to the embodiments without inventive contribution as required after reading the present specification, but the technical solutions in the embodiments of the present application will be described clearly and completely in the following with reference to fig. 1 to 3 of the embodiments of the present application as long as they are protected by patent laws within the scope of the claims of the present application to make the objects, technical solutions and advantages of the embodiments of the present application clearer, and it is obvious that the described embodiments are a part of the embodiments of the present application, but not all of the embodiments.
The embodiment of the application provides a green construction informatization management method which can be applied to a construction site, wherein an execution main body can be an intelligent terminal and can be realized in an auxiliary way by entrance guard equipment laid on the construction site and information storage equipment which is carried by constructors and can be matched with the entrance guard equipment. Specifically, information storage equipment can save constructor's identity information, and entrance guard's equipment can communicate with information storage equipment through near field wireless communication technique, through the communication relation of information storage equipment and entrance guard's equipment, when constructor was close to entrance guard's equipment, entrance guard's equipment can read constructor's identity information and finally sends to intelligent terminal.
The process flow shown in fig. 1 will be described in detail below with reference to specific embodiments, and the contents may be as follows:
step 101, obtaining a construction plan of a target construction site, wherein the construction plan at least comprises a construction area and a construction work type.
In implementation, the intelligent terminal may obtain a construction plan of a target construction site in advance, where the construction plan at least includes a construction area and a construction type. Specifically, the construction areas may be divided by a technician based on an overall area map of the target site, and the separation between different construction areas may be performed in numerical azimuth coordinates. The construction labor can be preset by a technician so as to perform classified management on workers of different functions participating in construction of the target construction site, thereby contributing to improvement of the personnel management efficiency of the construction site.
Like this, intelligent terminal can acquire construction area and construction work through the construction plan, carries out the subregion management with the target building site through construction area, carries out classification management with constructor through construction work, helps improving construction building site's managerial efficiency.
In one embodiment, in order to improve the efficiency of digital management of multiple construction areas, the method for managing green construction information may further include the following processing steps: acquiring geographic information of the target construction site based on a preset GIS system; establishing an electronic map of the target worksite based on the geographic information; and identifying a construction area on the electronic map.
In implementation, the intelligent terminal can obtain a building information model of the construction area through technicians, and combine the building information model with the GIS system to obtain the geographic information of the construction area. After the intelligent terminal acquires the geographic information of the construction area, a two-dimensional coordinate system can be established, and an electronic map of the target construction site is established based on the relative size or actual parameters of the construction area. Furthermore, when there are stories or building structures with high and low drop heights on the target site, a three-dimensional coordinate system may be established to identify the building structure in a vertical direction.
Like this, help showing the construction site building site in a visual way through electronic map, carry out the sign with the construction area simultaneously, help making constructor can find construction area's positional information on electronic map directly perceivedly to reduce the possibility that constructor found construction area's the condition emergence of mistake, improve constructor's efficiency of looking for construction area simultaneously.
In one embodiment, in order to enhance the assisting effect for the constructors, the green construction informatization management method may further include the following processing steps: acquiring a target construction area corresponding to the work type of the constructor; and when an access authorization signal is generated, broadcasting the target construction area, and highlighting the target construction area on an electronic map.
Therefore, the intelligent terminal prompts the corresponding target construction area of the constructor in a highlight display and broadcasting mode, so that the constructor can obtain related information of the target construction area from two senses of vision and hearing, and the auxiliary effect of finding the target construction area for the constructor is improved.
In one embodiment, in order to improve the assistance effect on the constructors, the green construction informatization management method can further comprise the following processing steps of: acquiring the real-time position of a constructor; when the real-time position of the constructor is not in the target construction area, sending a deviation prompt to the constructor; and generating route guidance through a preset path navigation model based on the real-time position of the constructor and the electronic map.
Like this, intelligent terminal is through the real-time supervision to constructor position, carries out skew warning when constructor skew target construction area, helps managing and supplementary to the inside constructor in construction place in real time, carries out the guide of route to the constructor of skew construction area through electronic map, helps improving the supplementary effect to the constructor.
102, acquiring identity information of a constructor, wherein the identity information at least comprises a work type of the constructor.
In implementation, when a constructor is close to an entrance guard device, the intelligent terminal can acquire identity information stored in an information storage device carried by the constructor through the entrance guard device, wherein the identity information at least comprises the work type of the constructor and can also comprise a unique identity mark of the constructor and the like.
And 103, comparing the work types of the constructors with the construction work types.
In implementation, the intelligent terminal can compare the read work types to which the constructors belong with the construction work types required by the current target construction site, so as to judge whether the constructors have the entrance requirements for entering the target construction site.
And 104, if the construction work type comprises the work type of the constructor, generating an access authorization signal.
In implementation, if the intelligent terminal detects that the type of work of the constructor is matched with the type of work required by the current target construction site, the intelligent terminal can judge that the constructor can enter the target construction site, and at the moment, the intelligent terminal can generate an access authorization signal so as to open the entrance guard equipment and enable the constructor to enter the target construction site.
In one embodiment, in order to improve timeliness of worksite management, the green construction informatization management system may further include the following processing steps: and updating the construction plan progress information according to a preset time period.
In implementation, the construction schedule information can be uploaded by technicians, and the construction schedule can be updated after the intelligent terminal acquires the construction schedule information. The time period of the update may be preset by a technician, and may be 1 hour, 2 hours, and the like, and the specific update period may be set by the technician.
Like this, the progress information of construction plan is periodically updated to intelligent terminal, helps making the inside management based on latest construction progress of construction information-based management system to help guaranteeing the validity of construction site personnel management.
Based on the same technical concept, an embodiment of the present invention further provides a green construction informatization management system, and referring to fig. 2, the system includes:
the construction planning module is used for obtaining a construction plan of a target construction site, and the construction plan at least comprises a construction area and a construction work type;
the system comprises a personnel information module, a construction personnel management module and a data processing module, wherein the personnel information module is used for acquiring identity information of construction personnel, and the identity information at least comprises the work type of the construction personnel;
the information checking module is used for comparing the work types of the constructors with the construction work types;
and the access authorization module is used for generating an access authorization signal if the construction work type comprises the work type of the constructor.
In a specific embodiment, a green construction informatization management system further comprises:
the electronic map module is used for acquiring the geographic information of the target construction site based on a preset GIS system; establishing an electronic map of the target worksite based on the geographic information; and identifying a construction area on the electronic map.
In a specific embodiment, a green construction informatization management system further comprises:
the region prompting module is used for acquiring a target construction region corresponding to the work type of the constructor; and when an access authorization signal is generated, broadcasting the target construction area, and highlighting the target construction area on an electronic map.
In a specific embodiment, a green construction informatization management system further comprises:
the deviation monitoring module is used for acquiring the real-time position of a constructor; and when the real-time position of the constructor is not in the target construction area, sending a deviation prompt to the constructor.
In a specific embodiment, a green construction informatization management system further comprises:
and the route guidance module is used for generating route guidance through a preset path navigation model based on the real-time position of the constructor and the electronic map.
In a specific implementation manner, the green construction informatization management system further comprises:
and the construction progress updating module is used for updating the construction plan progress information according to a preset time period.
The embodiment of the application also discloses an intelligent terminal, and referring to fig. 3, the intelligent terminal includes a memory and a processor, and the memory stores a computer program which can be loaded by the processor and execute the green construction informatization management method.
Based on the same technical concept, the embodiment of the application further discloses a computer-readable storage medium, which comprises various steps that can be carried out in the flow of the green construction informatization management method when the computer-readable storage medium is loaded and executed by a processor.
The computer-readable storage medium includes, for example: various media capable of storing program codes, such as a usb disk, a removable hard disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a magnetic disk, or an optical disk.
It is obvious to those skilled in the art that, for convenience and simplicity of description, only the division of the functional modules is illustrated, and in practical applications, the above functions may be distributed by different functional modules according to needs, that is, the internal structure of the apparatus is divided into different functional modules to complete all or part of the above described functions.
The integrated unit, if implemented in the form of a software functional unit and sold or used as a separate product, may be stored in a computer readable storage medium. With this understanding, the technical solution of the present application may be substantially implemented or contributed to by the prior art, or all or part of the technical solution may be embodied in a software product, which is stored in a storage medium and includes instructions for causing a computer device (which may be a personal computer, a server, a network device, or the like) or a processor (processor) to execute all or part of the steps of the method of the embodiments of the present application. And the aforementioned storage medium includes: u disk, removable hard disk, read only memory, random access memory, magnetic or optical disk, etc. for storing program codes.
The above embodiments are only used to describe the technical solutions of the present application in detail, but the above embodiments are only used to help understanding the method and the core idea of the present application, and should not be construed as limiting the present application. Those skilled in the art should also appreciate that various modifications and substitutions can be easily made without departing from the scope of the present disclosure.

Claims (9)

1. A green construction informatization management method is characterized by comprising the following steps:
obtaining a construction plan of a target construction site, wherein the construction plan at least comprises a construction area and a construction work type;
acquiring identity information of a constructor, wherein the identity information at least comprises a work type of the constructor;
comparing the work category of the constructor with the construction work category;
and if the construction work type comprises the work type of the constructor, generating an access authorization signal.
2. The green construction informatization management method according to claim 1, characterized by comprising the following steps: the method further comprises the following steps:
acquiring geographic information of the target construction site based on a preset GIS system;
establishing an electronic map of the target worksite based on the geographic information;
and identifying a construction area on the electronic map.
3. The green construction informatization management method according to claim 2, characterized by comprising the following steps: the method further comprises the following steps after the construction area is identified on the electronic map:
acquiring a target construction area corresponding to the work type of the constructor;
and when an access authorization signal is generated, broadcasting the target construction area, and highlighting the target construction area on an electronic map.
4. The green construction informatization management method according to claim 2, characterized by comprising the following steps: the method further comprises the following steps:
acquiring the real-time position of a constructor;
and when the real-time position of the constructor is not in the target construction area, sending a deviation prompt to the constructor.
5. The green construction informatization management method according to claim 4, characterized by comprising the following steps: when the real-time position of the constructor is not in the target construction area, after sending a deviation prompt to the constructor, the method further comprises the following steps:
and generating route guidance through a preset path navigation model based on the real-time position of the constructor and the electronic map.
6. The green construction informatization management method according to claim 1, characterized by comprising the following steps: the method further comprises the following steps:
and updating the construction plan progress information according to a preset time period.
7. A green construction informatization management system is characterized by comprising:
the construction planning module is used for obtaining a construction plan of a target construction site, and the construction plan at least comprises a construction area and a construction work type;
the system comprises a personnel information module, a construction personnel management module and a data processing module, wherein the personnel information module is used for acquiring identity information of construction personnel, and the identity information at least comprises the work types of the construction personnel;
the information checking module is used for comparing the work types of the constructors with the construction work types;
and the access authorization module is used for generating an access authorization signal if the construction work type comprises the work type of the constructor.
8. An intelligent terminal, comprising a processor and a memory, wherein the memory stores at least one instruction, at least one program, a code set, or a set of instructions, and the at least one instruction, the at least one program, the code set, or the set of instructions is loaded and executed by the processor to implement a green construction informatization management method according to any one of claims 1 to 6.
9. A computer-readable storage medium, wherein at least one instruction, at least one program, a set of codes, or a set of instructions is stored in the storage medium, and the at least one instruction, the at least one program, the set of codes, or the set of instructions is loaded and executed by a processor to implement a green construction informatization management method according to any one of claims 1 to 6.
CN202210774798.XA 2022-07-01 2022-07-01 Green construction informatization management method, system, terminal and medium Pending CN115170068A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210774798.XA CN115170068A (en) 2022-07-01 2022-07-01 Green construction informatization management method, system, terminal and medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210774798.XA CN115170068A (en) 2022-07-01 2022-07-01 Green construction informatization management method, system, terminal and medium

Publications (1)

Publication Number Publication Date
CN115170068A true CN115170068A (en) 2022-10-11

Family

ID=83488331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210774798.XA Pending CN115170068A (en) 2022-07-01 2022-07-01 Green construction informatization management method, system, terminal and medium

Country Status (1)

Country Link
CN (1) CN115170068A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115619204A (en) * 2022-12-20 2023-01-17 天津建设发展集团有限公司 Engineering field monitoring method and system based on wireless Internet of things

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115619204A (en) * 2022-12-20 2023-01-17 天津建设发展集团有限公司 Engineering field monitoring method and system based on wireless Internet of things

Similar Documents

Publication Publication Date Title
CN109141464B (en) Navigation lane change prompting method and device
CN113724520B (en) Vehicle-road cooperative information processing method and device, electronic equipment and storage medium
CN108253973B (en) Method and device for associating high-precision map with standard map
CN110837539B (en) Railway electronic map construction method and electronic map position matching method
CN112432650B (en) High-precision map data acquisition method, vehicle control method and device
CN115170068A (en) Green construction informatization management method, system, terminal and medium
CN112509355A (en) Vehicle searching method, device and system based on parking lot and storage medium
AU2018226491A1 (en) Maintenance trajectory tracing for elevator system
CN110208001A (en) A kind of road test method and apparatus of vehicle
CN112241442A (en) Map updating method, map updating device, computer equipment and storage medium
CN111866734A (en) Method, terminal, server and storage medium for positioning routing inspection track
CN111258974A (en) Vehicle offline scene data processing method and system
CN114186011A (en) Management method and device based on electronic fence, computer equipment and storage medium
CN112163063A (en) Method, apparatus and computer-readable storage medium for generating high-precision map
CN111401255B (en) Method and device for identifying bifurcation junctions
CN113110462A (en) Obstacle information processing method and device and operating equipment
CN114495057A (en) Data acquisition method, electronic device and storage medium
CN113177774A (en) Building construction supervision method based on BIM
CN108171605A (en) A kind of vehicle secondary mortgage alarm method, device, server and storage medium
CN104977016B (en) Navigation processing method and mobile intelligent terminal
CN112562388B (en) Vehicle connection management method and device and storage medium
CN112015956A (en) Similarity determination method, device, equipment and storage medium for mobile object
CN113918666A (en) Map data processing method, device, system and storage medium
CN115297437B (en) Positioning sign-in method, system, equipment and medium applied to positioning watch
CN114863710B (en) Parking indication system based on automatic navigation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination