CN115125997A - Construction equipment and construction method of combined multi-cavity comprehensive pipe gallery - Google Patents

Construction equipment and construction method of combined multi-cavity comprehensive pipe gallery Download PDF

Info

Publication number
CN115125997A
CN115125997A CN202210917798.0A CN202210917798A CN115125997A CN 115125997 A CN115125997 A CN 115125997A CN 202210917798 A CN202210917798 A CN 202210917798A CN 115125997 A CN115125997 A CN 115125997A
Authority
CN
China
Prior art keywords
pipe gallery
construction
support
side wall
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210917798.0A
Other languages
Chinese (zh)
Other versions
CN115125997B (en
Inventor
徐磊
朱毅敏
张忆州
童一倡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction No 1 Group Co Ltd
Priority to CN202210917798.0A priority Critical patent/CN115125997B/en
Publication of CN115125997A publication Critical patent/CN115125997A/en
Application granted granted Critical
Publication of CN115125997B publication Critical patent/CN115125997B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Abstract

The application relates to a technical field of piping lane construction discloses modular multi-chamber utility tunnel's construction equipment, include: a support; the sliding structure is used for supporting the bracket and driving the bracket to move; a template; the control structure is used for controlling the template to move towards the direction close to or far away from the bracket; also discloses a construction method of the combined multi-cavity comprehensive pipe gallery, which comprises the following steps: s1: constructing a support structure, excavating a foundation pit, and arranging a plurality of supports along with excavation until the support is excavated to the elevation of the bottom plate of the pipe gallery; s2: performing cast-in-place construction on the bottom plate of the pipe gallery; s3: constructing the side walls of the pipe gallery from bottom to top in multiple layers according to the vertical height of the pipe gallery; s4: carrying out flow construction on the multilayer side walls; s5: constructing a horizontal partition plate and an intermediate wall; s6: constructing a pipe gallery top plate, and meanwhile, completing the connection of the intermediate wall and the top plate; s7: and (5) installing a foundation structure and backfilling earthwork. This application has stronger adaptability to the multi-chamber utility tunnel construction that has more branch storehouse.

Description

Construction equipment and construction method of combined multi-cavity comprehensive pipe gallery
Technical Field
The application relates to the technical field of pipe gallery construction, in particular to construction equipment and a construction method of a combined multi-cavity comprehensive pipe gallery.
Background
The utility tunnel is built underground in a city and is used for intensively laying public tunnels of municipal pipelines such as electric power, communication, radio and television, water supply and the like. Technicians do not need to repeatedly dig the road surface, and can carry out first-aid repair, maintenance, expansion reconstruction and the like on various pipelines in the pipe gallery; meanwhile, the first-aid repair time of the pipeline is greatly shortened.
Among the correlation technique, when being under construction to utility tunnel, often adopt the template to carry out supplementary construction, common construction template is integral multiaspect construction template, and usable above-mentioned template carries out whole construction to utility tunnel, and the efficiency of construction is high, and the whole shaping effect of pipe gallery is better.
However, the integral multi-face construction template is only suitable for the comprehensive pipe gallery in a regular shape, the pipe gallery with the rectangular cross section is common, and the template in the related art is not suitable for the comprehensive pipe gallery needing to be separated.
Disclosure of Invention
The utility model aims at providing a modular multi-chamber utility tunnel's construction equipment and construction method compares in integral multiaspect construction template, and this application uses more in a flexible way, simultaneously, also can utilize many sets of side wall construction equipment to realize the construction of multistage flowing water overlap joint, to having the multi-chamber utility tunnel construction in more branch storehouse, has stronger adaptability.
First aspect, the application provides a modular multi-chamber utility tunnel's construction equipment adopts following technical scheme:
a modular multi-chamber utility tunnel's construction equipment, construction equipment includes:
a support;
the sliding structure is arranged at the bottom of the support and used for supporting the support and driving the support to move;
the template is positioned on one side of the support close to the pipe gallery enclosure structure;
the control structure is installed on the support and used for controlling the template to move towards the direction close to or far away from the support, and the control structure at least comprises an output shaft used for being connected with the template.
Through adopting above-mentioned technical scheme, in the construction equipment use, can erect construction equipment to the track that slides of laying in the piping lane structure, then utilize sliding structure to drive the support and remove to assigned position department, the position of control structure adjustment template begins concrete placement, and after concrete curing was accomplished, control structure adjustment template carries out the demolding, and construction equipment removes to next position construction. Compare in integral multiaspect construction template, this application uses more in a flexible way, and simultaneously, also can utilize many sets of side wall construction equipment to realize the construction of multistage flowing water overlap joint, to having the construction of more multi-chamber utility tunnel in branch storehouse, has stronger adaptability.
Optionally, a horizontal telescopic rod is installed on one side, close to the template, of the support, the horizontal telescopic rod comprises a base and a movable rod slidably installed on the base, the base of the horizontal telescopic rod is installed on the support, and one end, far away from the base, of the movable rod is connected with the template.
Through adopting above-mentioned technical scheme, when control structure drove the template and move towards the direction of being close to or keeping away from the support, the movable rod slided on the base in step, has improved the template formwork and has retreated the stability of mould in-process.
Optionally, a telescopic connecting rod is arranged on the support, one end of the telescopic connecting rod is hinged to the support, and the other end of the telescopic connecting rod is hinged to one end, far away from the base, of the movable rod.
Through adopting above-mentioned technical scheme, the gliding in-process of movable rod on the base, the angle of branch changes thereupon for the movable rod can keep comparatively stable horizontality to remove, and then stability when having improved the template action.
Optionally, the number of the telescopic connecting rods is two, and the two telescopic connecting rods are symmetrically arranged around the horizontal telescopic rod.
Through adopting above-mentioned technical scheme, set up the quantity of flexible connecting rod into two, can cooperate the support to form isosceles triangle, stability when further having improved the movable rod motion.
Optionally, the support includes top cap, lower back timber and vertical support pole, vertical support pole's both ends respectively with the tip fixed connection of top cap and lower back timber, the one end that vertical support pole was kept away from to the top cap is installed respectively at top cap and lower back timber to control structure.
Through adopting above-mentioned technical scheme, install control structure respectively on upper header and lower back timber for the template atress is even, uses more stably.
In a second aspect, the construction method of the combined multi-cavity comprehensive pipe gallery provided by the application adopts the following technical scheme:
a construction method of a combined multi-cavity comprehensive pipe gallery comprises the following construction steps:
s1: constructing a support structure, excavating a foundation pit, and arranging a plurality of supports along with excavation until the support is excavated to the elevation of the bottom plate of the pipe gallery;
s2: casting the bottom plate of the pipe gallery in situ;
s3: laying a sliding track on a bottom plate of the pipe gallery along the length direction of the pipe gallery, erecting the construction equipment as claimed in any one of claims 1 to 5 on the sliding track, and constructing the side walls of the pipe gallery from bottom to top in multiple layers according to the vertical height of the pipe gallery;
s4: equally dividing each layer of pipe rack side wall into N sections, performing multilayer flow construction on the pipe rack side walls, and constructing the lower layer of pipe rack side wall in the two adjacent layers of pipe rack side walls in advance of the upper layer of pipe rack side wall;
s5: when the pipe gallery side wall is constructed to the elevation of the horizontal partition plate, constructing the horizontal partition plate and the intermediate wall, laying a sliding rail, erecting the construction equipment on the sliding rail to continue to construct the next layer of pipe gallery side wall, wherein before constructing each layer of pipe gallery side wall, a support influencing the construction needs to be dismantled;
s6: after the construction of the side wall of the pipe gallery on the uppermost layer is finished, the construction equipment is unloaded, then the top plate of the pipe gallery is constructed, and meanwhile, the connection of the intermediate wall and the top plate is finished;
s7: and (4) installing various pipelines and foundation structures inside the comprehensive pipe gallery, backfilling earthwork at the top of the pipe gallery, and finishing construction of the pipe gallery.
By adopting the technical scheme, when the side wall of the pipe gallery is constructed, a layered construction mode is adopted, construction can be carried out according to regions, construction flexibility is higher, and the construction efficiency is improved due to the flow construction of multiple layers of pipe galleries; to the construction that has the multicavity utility tunnel in more branch storehouse, perhaps have the piping lane structure of irregular shape, have stronger adaptability.
Optionally, in S5, the mid-board both sides all are provided with horizontal separators, and after the horizontal separator construction was accomplished, set up the bracket on the side wall to lay the track that slides on the bracket.
Through adopting above-mentioned technical scheme, set up the bracket on the side wall, the convenience is installed construction equipment, and makes things convenient for the later stage to demolish.
Optionally, among S5, only one side of mid-board is provided with horizontal baffle, need additionally set up the foundation ditch in horizontal structure disappearance department and trade and prop to set up the bracket on the side wall, set up the track that slides on the bracket.
Through adopting above-mentioned technical scheme, when the mid-board only had one side to be provided with horizontal baffle, in order to keep the stability of piping lane structure, need additionally set up the foundation ditch in horizontal structure disappearance department and trade and prop, as the interim support of mid-board, improved the security of construction.
Optionally, in S5, the mid-board both sides all are provided with horizontal partition, and there is horizontal floor in the side wall elevation position, and the track that slides directly lays on horizontal floor.
Through adopting above-mentioned technical scheme, when the pipe gallery structure construction has horizontal floor, can directly lay the track that slides to horizontal floor on, avoid constructing the bracket structure again.
Optionally, in S5, horizontal partition, mid-board all adopt the prefabricated construction, in S6, the piping lane roof also adopts the prefabricated construction.
Through adopting above-mentioned technical scheme, horizontal separation board, mid-board and piping lane roof all adopt prefabricated construction, can show ground improvement efficiency of construction.
In summary, the present application includes at least one of the following beneficial technical effects:
1. in the construction equipment use, can erect construction equipment to the track that slides of laying in the piping lane structure, then utilize the sliding structure to drive the support and remove to assigned position department, the position of control structure adjustment template begins concrete placement, and after concrete curing was accomplished, control structure adjustment template carries out the demolding, and construction equipment removes to next position construction. Compared with an integral multi-face construction template, the construction template is more flexible to use, meanwhile, multi-section flow overlapping construction can be achieved by utilizing multiple sets of side wall construction equipment, and the construction template has stronger adaptability to multi-cavity comprehensive pipe gallery construction with more separated bins;
2. when the side wall of the pipe gallery is constructed, a layered construction mode is adopted, construction can be carried out according to regions, construction flexibility is higher, and the construction method has stronger adaptability to the construction of a multi-cavity comprehensive pipe gallery with more separated bins or a pipe gallery structure with an irregular shape;
3. through setting up horizontal telescopic link, when control structure drove the direction motion that the template orientation was close to or was kept away from the support, the movable rod slided on the base in step, has improved the template formwork and has moved back the stability of mould in-process.
Drawings
Fig. 1 is a schematic view of the overall structure of construction equipment in an embodiment of the present application;
FIG. 2 is a construction flow chart of a construction method in an embodiment of the present application;
FIG. 3 is a schematic structural diagram of a bottom plate after construction in the embodiment of the present application;
FIG. 4 is a schematic structural diagram of a first-layer pipe gallery side wall in the construction of the embodiment of the application;
fig. 5 is a schematic structural diagram of the second-layer pipe rack side wall in the case that horizontal partition plates connected with the constructed pipe rack side wall are arranged on both sides of the partition wall according to the embodiment of the application;
FIG. 6 is a schematic structural diagram of the pipe gallery structure after construction is completed under the condition that horizontal partition plates connected with the constructed pipe gallery side walls are arranged on both sides of the partition wall in the embodiment of the application;
FIG. 7 is a schematic structural diagram of a second floor of pipe gallery side wall in the case that only one side of the partition wall is provided with a horizontal partition plate connected with the constructed pipe gallery side wall according to the embodiment of the application;
FIG. 8 is a schematic structural diagram of the pipe gallery structure after construction is completed in the case that only one side of the partition wall is provided with a horizontal partition plate connected with the side wall of the constructed pipe gallery according to the embodiment of the application;
fig. 9 is a schematic structural diagram of the second-layer pipe rack side wall construction in the case where horizontal partition plates connected to the constructed pipe rack side walls are arranged on both sides of the partition wall and a horizontal floor slab is present at the elevation position of the side wall in the embodiment of the present application;
fig. 10 is a schematic structural diagram of the pipe gallery structure after construction is completed in the case that horizontal partition plates connected with the constructed pipe gallery side walls are arranged on two sides of the partition wall and horizontal floor slabs exist at elevation positions of the side walls in the embodiment of the application.
Fig. 11 is a schematic structural diagram showing the flow construction of the side wall of the multilayer pipe rack according to the embodiment of the present application.
In the figure, 1, a bracket; 11. an upper top beam; 12. a lower top beam; 13. a vertical support bar; 2. a sliding structure; 21. a fixed seat; 22. a sliding wheel; 3. a template; 4. a control structure; 5. a horizontal telescopic rod; 6. a telescopic connecting rod; 7. an enclosure structure; 8. a first layer of concrete supports; 9. a second layer of concrete supports; 10. a base plate; 14. a first layer of pipe gallery side wall; 15. a second layer of pipe gallery side wall; 16. a horizontal partition plate; 17. an intermediate wall; 18. a sliding track; 19. replacing a support of the foundation pit; 20. a bracket; 23. a horizontal floor slab; 24. a top plate.
Detailed Description
The present application is described in further detail below with reference to fig. 1-11.
The embodiment of the application discloses modular multi-chamber utility tunnel's construction equipment.
The utility model provides a modular multi-chamber utility tunnel's construction equipment, refer to figure 1, including support 1, sliding construction 2, template 3 and control structure 4, wherein, template 3 is located one side that support 1 is close to envelope 7, on the control structure 4 installing support 1 for control template 3 orientation is close to or keeps away from the direction motion of support 1, and control structure 4 includes at least that an output shaft is used for being connected with template 3, sliding construction 2 installs in the bottom of support 1, is used for bearing support 1, and drives support 1 and remove.
In the construction equipment use, can erect construction equipment on the track 18 that slides of laying in the piping lane structure, then utilize sliding structure 2 to drive support 1 and remove to assigned position department, the position of control structure 4 adjustment template 3 begins to be under construction to the lateral wall of piping lane structure, compare in integral multiaspect construction template 3, this application uses more in a flexible way, and simultaneously, also can utilize many sets of side wall construction equipment to realize the construction of multistage flowing water overlap joint, to the multi-chamber utility tunnel construction that has more branch storehouse, stronger adaptability has.
In the embodiment, the template 3 is a rectangular steel template, and the rectangular shape is suitable for the construction of the side wall of the planar pipe gallery; it should be clear to those skilled in the art that the form 3 may be designed to suit the shape of the side wall of the pipe gallery (e.g., arc shape).
Specifically, the support 1 includes an upper top beam 11, a lower top beam 12 and a vertical support rod 13, wherein two ends of the vertical support rod 13 are respectively and fixedly connected with the ends of the upper top beam 11 and the lower top beam 12, and the fixed connection mode can be welding, riveting or bolt connection, and the like; and go up roof beam 11 and lower back timber 12 and parallel, vertical support bar 13 sets up with the two is perpendicular, and simultaneously, two adjacent vertical support bar 13 welding have the crossbeam, utilize crossbeam cooperation vertical support bar 13 to constitute square frame for it is whole comparatively stable. The control structure 4 is mounted at the ends of the upper top beams 11 and the lower top beams 12 far away from the vertical support rod 13.
Further, control structure 4 includes a plurality of electric telescopic handle, and wherein, electric telescopic handle's outer tube fixed mounting is at the one end that vertical support bar 13 was kept away from to upper beam 11 and lower beam 12, and specific mounting means, accessible bolt are fixed, and electric telescopic handle's piston end passes through screw and 3 looks fixed connection of template. The electric telescopic rod drives the template 3 to move towards the direction close to or far away from the support 1 through the extension and retraction of the piston rod, and has high adjustment precision.
In order to improve the stability when the control structure 4 drives the template 3 to move, the bracket 1 is also provided with a horizontal telescopic rod 5. Specifically, horizontal telescopic rod 5 includes cylindric base and slidable mounting's movable rod on the base, and the one end protrusion of movable rod sets up in the base to pass through screw fixed connection with template 3. When the control structure 4 drives the template 3 to move towards the direction close to or far away from the support 1, the movable rod synchronously slides on the base, so that the stability of the template 3 in the process of template supporting and template withdrawing is improved.
Further, in order to better control the stability of the template 3 during the action, the support 1 is further provided with a telescopic connecting rod 6, one end of the telescopic connecting rod 6 is hinged with the vertical supporting rod 13 of the support 1, and the other end of the telescopic connecting rod is hinged with one end of the movable rod far away from the base. Preferably, the telescopic link 6 is a hydraulic telescopic link. The gliding in-process of movable rod on the base, the angle of branch changes thereupon for the movable rod can keep comparatively stable horizontality to remove, and then the stability when having improved 3 actions of template.
Preferably, the quantity of branch sets up to two, and two branches set up about 5 symmetries of horizontal telescopic link, and this kind of setting mode can cooperate vertical support pole 13 to form isosceles triangle, has further improved the stability when the movable rod moves.
Specifically, sliding construction 2 includes fixing base 21 and movable pulley 22, and fixing base 21 passes through the bolt and installs in the bottom of back timber 12 down, and movable pulley 22 rotates and installs on fixing base 21, and during the concrete use, movable pulley 22 cooperates with the track 18 that slides on the pipe gallery structure, and under cooperation between them, the staff can promote support 1 to assigned position. In another embodiment, a driving motor may also be installed on the lower top beam 12, and the driving motor is used to drive the sliding wheel 22 to rotate, so as to achieve automatic adjustment of the position of the support 1, and in particular, transmission and deceleration between the driving motor and the sliding wheel 22 may be achieved through a speed reducer.
The embodiment of the application also discloses a construction method of the combined multi-cavity comprehensive pipe gallery.
A construction method of a combined multi-cavity comprehensive pipe gallery is disclosed, referring to fig. 2, and comprises the following construction steps:
s1: referring to fig. 2 and 3, the building enclosure 7 is constructed, foundation pit earthwork excavation and concrete support pouring are alternately performed until the excavation reaches the elevation of the pipe gallery bottom plate 10, in this embodiment, the building enclosure 7 is an underground continuous wall, and the concrete supports are arranged into two layers, namely a first concrete support 8 and a second concrete support 9 from top to bottom;
specifically, the building envelope 7 construction comprises the following steps:
step 1: the construction of the guide wall, the guide wall is poured by reinforced concrete, the section of the guide wall is generally in the shape of "," "or" the shape of "", the function of the guide wall is as the direction of the slot-cutting machine, hold and store the mud and prevent the collapse of the earth on the surface;
step 2: excavating the groove sections, wherein before excavating the grooves, the underground wall is divided into a plurality of construction groove sections in advance, and the length of each groove section is 3-7 m; in the process of digging the groove, the groove is always kept full of slurry; after the excavation of the groove section is finished and before the concrete of the groove section is poured, bottom cleaning and slurry changing work of the groove section is carried out to remove sediments at the bottom of the groove;
and step 3: placing a steel reinforcement cage and a joint pipe, completing the binding of the steel reinforcement cage, hoisting the steel reinforcement cage into the dug groove section, hoisting the joint pipe into the groove section by using a crane, and driving the bottom end of the joint pipe into the bottom of the groove;
and 4, step 4: and pouring concrete into the groove, and pulling out the joint pipe after the concrete is poured for 2-3 h.
The concrete supporting and pouring method comprises the following steps:
step 1: excavating a foundation trench, sequentially excavating along a support design road section by an excavator, and manually cleaning a foundation when excavating to about 30cm of a design elevation;
step 2: treating the bottom of the tank, after manually cleaning the bottom, paving 10 cm-thick broken stones on the bottom if the muddy soil on the substrate is not easy to clean, and performing M5 mortar surface treatment with the thickness of 2 cm;
and step 3: binding and installing the steel bars, and hoisting the steel bars into the corresponding base grooves after the binding is finished;
and 4, step 4: installing a template, wherein the template is installed from one end to the other end, the splicing seams of the template are sealed by adhesive tape paper, and the template is watered to be wet and washed clean before concrete is poured;
and 5: pouring concrete, and checking the template, the steel bars and the embedded parts again before pouring, and clearing impurities in the template;
step 6: and (5) curing the concrete, finishing the finishing and plastering of the concrete, and carrying out curing work, wherein the geotextile is covered by sprinkling water for curing during curing.
S2: cast-in-place construction of piping lane bottom plate 10, concrete construction steps are as follows:
step 1: constructing a cushion layer, wherein the cushion layer of the corridor bottom plate 10 in the embodiment adopts 100mm thick C15 plain concrete;
step 2: waterproof construction, the following steps are sequentially constructed from bottom to top: DSM20 mortar leveling → RMO flexible waterproof layer → plastic film protective layer → C20 fine stone concrete protective layer → C35P6 reinforced concrete self-waterproof → permeable DPS spraying waterproof layer;
and 3, step 3: binding and installing structural steel bars of the bottom plate 10;
and 4, step 4: installing a template, wherein the template is installed from one end to the other end, the splicing seams of the template are sealed by adhesive tape paper, and the template is watered to be wet and washed clean before concrete is poured;
and 5: pouring concrete, and checking the template, the steel bars and the embedded parts again before pouring, and clearing impurities in the template;
and 6: and (5) curing the concrete, and finishing the concrete finishing and plastering to perform curing work.
S3: referring to fig. 3 and 4, after the maintenance of the pipe gallery bottom plate 10 is completed, the sliding rail 18 is laid on the pipe gallery bottom plate 10 along the length direction of the pipe gallery, in this embodiment, the sliding rail 18 is made of i-steel, the construction equipment is erected on the sliding rail 18, and in the specific working process of the construction equipment, the sliding wheel 22 is matched with the sliding rail 18 and slides on the sliding rail 18, so that the movement of the construction equipment is realized.
Simultaneously, according to the pipe gallery vertical height, divide the multilayer with the pipe gallery side wall from bottom to top and construct, for the ease of understanding, divide into two-layer side wall structure about the pipe gallery side wall in this embodiment. Through the mode of layering construction, can be so that the construction is more nimble, simultaneously, to the construction that has the multi-chamber utility tunnel in more branch storehouse, perhaps the utility tunnel of irregular shape, have stronger adaptability. The side wall can be constructed closely to the enclosure structure 7.
S4: referring to fig. 11, equally divide each layer piping lane side wall into the N section, the construction of piping lane side wall multilayer flowing water, and in the adjacent two-layer piping lane side wall, lower floor's piping lane side wall is in advance in the construction of upper pipe lane side wall.
Specifically, at first, construct first layer piping lane side wall 14, lower floor's side wall promptly, before constructing first layer piping lane side wall 14, should demolish second pipeline concrete support 9 earlier, avoid causing the influence to piping lane side wall construction.
Further, when constructing first layer pipe rack side wall 14, can divide into the N section with first layer pipe rack side wall 14 along pipe rack length direction and construct. Pour first section pipe gallery side wall earlier, first section pipe gallery side wall concrete curing accomplishes the back, and construction equipment moves back the mould and slides along the track 18 that slides and carry out second section pipe gallery side wall construction to this step of repetition is under construction first layer pipe gallery side wall 14.
In this embodiment, when constructing arbitrary section of second section pipe rack side wall to N section pipe rack side wall of first layer pipe rack side wall 14, can begin flowing water construction second layer pipe rack side wall 15 at any time, also divide into the N section during the construction of second layer pipe rack side wall 15, and every section all is the same with first layer pipe rack side wall 14's length, constructs second layer pipe rack side wall 15 according to the segmentation in proper order.
S5: referring to fig. 5 and 6, when the pipe gallery side walls are constructed to the level of the horizontal partition 16, for the sake of understanding, in the present embodiment, after the first layer of pipe gallery side walls 14 is constructed, that is, the level of the horizontal partition 16 is reached, the horizontal partition 16 and the intermediate wall 17 are constructed.
In this embodiment, the horizontal partition 16 and the intermediate wall 17 are both prefabricated structures, which can significantly improve the construction efficiency, and the intermediate wall 17 at this position is a lower prefabricated intermediate wall 17; and in order to avoid the intermediate wall 17 from affecting the construction of the side walls of the upper pipe gallery, the height of the intermediate wall 17 should be flush with the height of the constructed pipe gallery partition wall. Then, paving a sliding rail 18, erecting construction equipment on the sliding rail 18, and continuing to construct the next layer of pipe gallery side wall, wherein before constructing each layer of pipe gallery side wall, supports influencing the construction need to be dismantled;
specifically, under this operating mode, after 14 concrete of first layer pipe gallery side wall reached the strength requirement, it is different according to pipe gallery cavity layout form, mainly can divide into following 3 operating modes:
(1) referring to fig. 5 and 6, the pipe gallery structure includes horizontal partition plates 16, that is, horizontal partition plates 16 connected with the side walls of the constructed pipe gallery are arranged on both sides of the partition wall, and at this time, a foundation pit support replacing 19 (temporary support) is not required to be additionally arranged; because the strength of the horizontal partition plate 16 is relatively low, in order to ensure the safety during construction, a bracket 20 is arranged on the constructed side wall, a sliding rail 18 is erected on the bracket 20, construction equipment is erected on the sliding rail 18, and then the first concrete support 8 is removed to construct the side wall of the previous layer of pipe gallery;
(2) referring to fig. 7 and 8, the pipe rack structure includes a part of horizontal partition plates 16, that is, only one side of the partition wall is provided with the horizontal partition plate 16 connected with the constructed pipe rack side wall, and the other side is not provided with the horizontal partition plate 16 or other connecting platforms connected with the constructed pipe rack side wall, under the working condition, in order to avoid the problem that the upper pipe rack side wall lacks horizontal support in the subsequent construction, a foundation pit support replacing 19 needs to be additionally arranged at the missing part of the horizontal structure, and similarly, a bracket 20 is arranged on the side wall, a sliding rail 18 is erected on the bracket 20, construction equipment is erected on the sliding rail 18, and then a first concrete support 8 is removed to construct the upper pipe rack side wall;
(3) referring to fig. 9 and 10, the pipe gallery structure comprises horizontal partition plates 16, that is, the horizontal partition plates 16 connected with the constructed pipe gallery side wall are arranged on both sides of the partition wall, and a horizontal floor slab 23 is arranged at the elevation position of the side wall, so that the pipe gallery structure has higher strength after the horizontal floor slab 23 is constructed, at this time, a foundation pit support replacing 19 is not required to be additionally arranged, and the horizontal floor slab 23 is also constructed by adopting a prefabricated structure; because horizontal floor 23 intensity is relatively higher, so slip track 18 can directly be laid on horizontal floor 23 to demolish the first support, erect construction equipment to this slip track 18 on, then demolish first concrete support 8, with the construction of last floor pipe gallery side wall.
S6: after the construction of the side wall of the pipe gallery on the uppermost layer is finished, namely the construction of the side wall of the pipe gallery on the upper layer is finished, unloading construction equipment, lifting and constructing a top plate 24 of the pipe gallery, wherein the top plate 24 of the pipe gallery is also constructed in a prefabricated structure, and simultaneously, lifting an upper prefabricated intermediate wall 17 to the prefabricated intermediate wall 17 on the lower layer which is constructed, connecting the upper prefabricated intermediate wall 17 and the lower prefabricated intermediate wall, and finishing the connection of the upper prefabricated intermediate wall 17 and the top plate 24;
s7: and (3) installing various pipelines and foundation structures in the comprehensive pipe gallery, backfilling earthwork at the top of the pipe gallery to complete the construction of the pipe gallery, wherein the step adopts a construction method in the prior art, and the step can be implemented by the personnel in the field according to common knowledge and by combining the prior art, so the step is not repeated herein.
The implementation principle of the embodiment of the application is as follows:
the implementation principle of the construction equipment is as follows: when the construction equipment is used, the construction equipment is erected on a sliding track 18 laid in a pipe gallery structure, then the sliding structure 2 is used for driving the support 1 to move to a specified position, and at the moment, the electric telescopic rod extends to drive the template 3 to move towards the direction of the enclosure structure 7, so that the template support is realized; then, side wall pouring is started, and after the poured concrete is cured, the electric telescopic rod contracts to drive the template 3 to move towards the direction far away from the building envelope 7, so that the template is withdrawn;
compare in integral multiaspect construction forms 3, this application uses more in a flexible way, and simultaneously, also can utilize many sets of side wall construction equipment to realize the construction of multistage flowing water overlap joint, to having the multi-chamber utility tunnel construction in more branch storehouse, perhaps having the piping lane structure of irregular shape, has stronger adaptability.
The construction method has the implementation principle that: when the side wall of the gallery is constructed, a layered and segmented construction mode is adopted, so that the construction flexibility is higher, and the adaptability is stronger; meanwhile, the horizontal partition plate 16, the intermediate wall 17, the pipe gallery top plate 24 and the horizontal floor slab 23 are all of prefabricated structures, and construction efficiency can be remarkably improved.
The embodiments of the present invention are preferred embodiments of the present application, and the protection scope of the present application is not limited thereby, wherein like parts are denoted by like reference numerals. Therefore, the method comprises the following steps: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. The utility model provides a modular multi-chamber utility tunnel's construction equipment which characterized in that, construction equipment includes:
a support (1);
the sliding structure (2) is arranged at the bottom of the support (1), and the sliding structure (2) is used for supporting the support (1) and driving the support (1) to move;
the template (3) is positioned on one side, close to the pipe gallery enclosure structure (7), of the support (1);
the control structure (4), control structure (4) are installed on support (1) for control template (3) orientation is close to or is kept away from the direction motion of support (1), control structure (4) include at least one output shaft and are used for being connected with template (3).
2. The construction equipment of a combined multi-cavity comprehensive pipe gallery according to claim 1, wherein a horizontal telescopic rod (5) is installed on one side of the support (1) close to the formwork (3), the horizontal telescopic rod (5) comprises a base and a movable rod slidably installed on the base, the base of the horizontal telescopic rod (5) is installed on the support (1), and one end of the movable rod, far away from the base, is connected with the formwork (3).
3. A construction equipment of a combined multi-cavity comprehensive pipe gallery according to claim 2, characterized in that the support (1) is provided with a telescopic connecting rod (6), one end of the telescopic connecting rod (6) is hinged with the support (1), and the other end is hinged with one end of the movable rod far away from the base.
4. A construction equipment of a combined multi-cavity utility tunnel according to claim 3, characterized in that the number of telescopic links (6) is two and the two telescopic links (6) are symmetrically arranged about the horizontal telescopic rod (5).
5. A construction equipment of a combined multi-cavity utility tunnel according to claim 1, wherein the support (1) comprises an upper top beam (11), a lower top beam (12) and a vertical support rod (13), both ends of the vertical support rod (13) are fixedly connected with the ends of the upper top beam (11) and the lower top beam (12), respectively, and the control structure (4) is installed at one end of the upper top beam (11) and the lower top beam (12) far away from the vertical support rod (13), respectively.
6. The construction method of the combined multi-cavity comprehensive pipe gallery is characterized by comprising the following construction steps:
s1: constructing a support structure (7), excavating a foundation pit, and arranging a plurality of supports along with excavation until the support is excavated to the elevation of a bottom plate (10) of the pipe gallery;
s2: performing cast-in-place construction on the pipe gallery bottom plate (10);
s3: laying a sliding rail (18) on a bottom plate (10) of the pipe gallery along the length direction of the pipe gallery, erecting the construction equipment according to any one of claims 1 to 5 on the sliding rail (18), and constructing the side walls of the pipe gallery from bottom to top in multiple layers according to the vertical height of the pipe gallery;
s4: equally dividing each layer of pipe rack side wall into N sections, performing multilayer flow construction on the pipe rack side walls, and constructing the lower layer of pipe rack side wall in the two adjacent layers of pipe rack side walls in advance of the upper layer of pipe rack side wall;
s5: when the pipe gallery side wall is constructed to the elevation of the horizontal partition plate (16), then the horizontal partition plate (16) and the intermediate wall (17) are constructed, a sliding rail (18) is laid, the construction equipment is erected on the sliding rail (18) to continue to construct the next layer of pipe gallery side wall, wherein before each layer of pipe gallery side wall is constructed, supports influencing the construction need to be dismantled;
s6: after the construction of the side wall of the pipe gallery on the uppermost layer is finished, the construction equipment is unloaded, then a pipe gallery top plate (24) is constructed, and meanwhile, the connection of the intermediate wall (17) and the top plate (24) is finished;
s7: and (4) installing various pipelines and foundation structures inside the comprehensive pipe gallery, backfilling earthwork at the top of the pipe gallery, and finishing construction of the pipe gallery.
7. The method for constructing a combined multi-cavity utility tunnel according to claim 6, wherein horizontal partitions (16) are provided at both sides of the intermediate wall (17) in the step S5, and after the horizontal partitions (16) are constructed, the corbels (20) are provided on the side walls and the slip rails (18) are laid on the corbels (20).
8. The method for constructing a combined multi-cavity utility tunnel according to claim 6, wherein in the step S5, only one side of the middle wall (17) is provided with a horizontal partition (16), a foundation pit support (19) is additionally arranged at the position of the horizontal structure loss, the side walls are provided with brackets (20), and the brackets (20) are provided with a sliding rail (18).
9. The method for constructing a combined multi-cavity utility tunnel according to claim 6, wherein in the step S5, horizontal partition boards (16) are arranged on both sides of the intermediate wall (17), horizontal floor slabs (23) are arranged at the elevation positions of the side walls, and the sliding rails (18) are directly laid on the horizontal floor slabs (23).
10. The method of claim 6, wherein in the step S5, the horizontal partition plate (16) and the intermediate wall (17) are constructed in a prefabricated structure, and in the step S6, the top plate (24) of the pipe gallery is also constructed in a prefabricated structure.
CN202210917798.0A 2022-08-01 2022-08-01 Construction equipment and construction method for combined multi-cavity comprehensive pipe rack Active CN115125997B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210917798.0A CN115125997B (en) 2022-08-01 2022-08-01 Construction equipment and construction method for combined multi-cavity comprehensive pipe rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210917798.0A CN115125997B (en) 2022-08-01 2022-08-01 Construction equipment and construction method for combined multi-cavity comprehensive pipe rack

Publications (2)

Publication Number Publication Date
CN115125997A true CN115125997A (en) 2022-09-30
CN115125997B CN115125997B (en) 2024-05-07

Family

ID=83384939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210917798.0A Active CN115125997B (en) 2022-08-01 2022-08-01 Construction equipment and construction method for combined multi-cavity comprehensive pipe rack

Country Status (1)

Country Link
CN (1) CN115125997B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101761092A (en) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 Construction method of movable side wall of large overall template of large-span deep foundation pit
KR101814726B1 (en) * 2017-08-03 2018-01-30 최해순 Size changeable type movable steel form for cable tunnel structure
CN109440817A (en) * 2018-12-17 2019-03-08 中国十九冶集团有限公司 Piping lane construction method
CN109487814A (en) * 2018-10-29 2019-03-19 杭州市市政工程集团有限公司 Cast-in-place piping lane integrated moveable formwork jumbo construction method
CN109763839A (en) * 2018-12-27 2019-05-17 中铁广州工程局集团有限公司 A kind of tunneling boring self-propelled hydraulic trolley formwork construction method
CN109972655A (en) * 2018-06-30 2019-07-05 中铁二十二局集团第三工程有限公司 A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form and installation method open
CN209082555U (en) * 2018-06-30 2019-07-09 中铁二十二局集团第三工程有限公司 A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form open
CN110629793A (en) * 2019-10-11 2019-12-31 中铁隧道集团二处有限公司 Rapid supporting die frame for pipe gallery and construction method thereof
CN212561612U (en) * 2020-03-30 2021-02-19 中国十七冶集团有限公司 Supporting structure system in piping lane

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101761092A (en) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 Construction method of movable side wall of large overall template of large-span deep foundation pit
KR101814726B1 (en) * 2017-08-03 2018-01-30 최해순 Size changeable type movable steel form for cable tunnel structure
CN109972655A (en) * 2018-06-30 2019-07-05 中铁二十二局集团第三工程有限公司 A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form and installation method open
CN209082555U (en) * 2018-06-30 2019-07-09 中铁二十二局集团第三工程有限公司 A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form open
CN109487814A (en) * 2018-10-29 2019-03-19 杭州市市政工程集团有限公司 Cast-in-place piping lane integrated moveable formwork jumbo construction method
CN109440817A (en) * 2018-12-17 2019-03-08 中国十九冶集团有限公司 Piping lane construction method
CN109763839A (en) * 2018-12-27 2019-05-17 中铁广州工程局集团有限公司 A kind of tunneling boring self-propelled hydraulic trolley formwork construction method
CN110629793A (en) * 2019-10-11 2019-12-31 中铁隧道集团二处有限公司 Rapid supporting die frame for pipe gallery and construction method thereof
CN212561612U (en) * 2020-03-30 2021-02-19 中国十七冶集团有限公司 Supporting structure system in piping lane

Also Published As

Publication number Publication date
CN115125997B (en) 2024-05-07

Similar Documents

Publication Publication Date Title
CN101967985B (en) Self-propelled inverted arch template construction method
CN106320377B (en) A kind of rich water soft clay area deep basal pit covered back-digging construction method
CN111576431A (en) Excavation method for foundation pit of four-layer subway station
CN105421463B (en) Longitudinal excavation construction method of long-span dense-support super-long deep foundation pit
CN107059920A (en) Loess formation piping lane construction technology
CN109488347B (en) Excavation construction method for special stratum chamber
CN112813991A (en) Excavation and support construction method for deep foundation pit of subway transfer station
CN112575670A (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN114263168A (en) Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN117027824A (en) Deep and long frozen inclined shaft digging and building parallel operation construction method
CN108571010B (en) Method for integrating open cut method engineering prefabricated main structure and supporting structure
CN115125997B (en) Construction equipment and construction method for combined multi-cavity comprehensive pipe rack
CN112343614B (en) U-shaped shield tunneling machine-based overlapped-spliced comprehensive pipe gallery construction method
CN115324104A (en) Permanent and temporary combined assembly type station and construction method thereof
CN210151784U (en) Integration template piping lane
CN113338340A (en) Reverse construction method for vertical shaft ensuring normal use of existing pipeline
CN110685719A (en) Quick construction method for double-span simply-supported inverted arch trestle
JPH09151471A (en) Movable form device and work execution method for underground structure using the device
CN113152521B (en) Prefabricated comprehensive pipe gallery jacking construction method
CN111456087B (en) Basement structure regional small-section earthwork excavation method
CN117536262B (en) Underground-cover-excavation-combined subway station structure and construction method
CN109025364B (en) House moving method in building construction
CN220704323U (en) Integrated bridging equipment
KR200291370Y1 (en) Concrete caisson structure for earth and sand guard of pier's basis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant