CN114991424B - Assembly tool and assembly method for indoor wrapping pipe of home decoration - Google Patents
Assembly tool and assembly method for indoor wrapping pipe of home decoration Download PDFInfo
- Publication number
- CN114991424B CN114991424B CN202210617807.4A CN202210617807A CN114991424B CN 114991424 B CN114991424 B CN 114991424B CN 202210617807 A CN202210617807 A CN 202210617807A CN 114991424 B CN114991424 B CN 114991424B
- Authority
- CN
- China
- Prior art keywords
- rod
- vertical rod
- screw
- plate
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000005034 decoration Methods 0.000 title claims abstract description 15
- 238000000034 method Methods 0.000 title claims abstract description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 7
- 239000000463 material Substances 0.000 claims description 6
- 230000000149 penetrating effect Effects 0.000 claims description 5
- 238000004806 packaging method and process Methods 0.000 claims description 4
- 125000003003 spiro group Chemical group 0.000 claims description 4
- 238000009434 installation Methods 0.000 claims description 3
- 238000004378 air conditioning Methods 0.000 claims description 2
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 238000007789 sealing Methods 0.000 abstract description 2
- 238000004026 adhesive bonding Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F17/00—Vertical ducts; Channels, e.g. for drainage
- E04F17/08—Vertical ducts; Channels, e.g. for drainage for receiving utility lines, e.g. cables, pipes
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F17/00—Vertical ducts; Channels, e.g. for drainage
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Supports Or Holders For Household Use (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The application relates to the technical field of indoor wrapping pipes of home decoration, in particular to an indoor wrapping pipe assembling tool for home decoration, which comprises the following components: the wall, the outside of the wall has pipelines; the bottom of the second vertical rod is provided with a bottom rod, the bottom of the bottom rod is provided with a rubber strip, the top of the rubber strip is provided with a first vertical rod, the surface of the first vertical rod is provided with a through groove, the inside of the through groove is provided with a lifting plate, the surface of the lifting plate is provided with a second screw hole, the bottom of the lifting plate is provided with a pulling block, the bottom of the pulling block is provided with a second fixing plate, and the surface of the first vertical rod is provided with a fourth screw hole; the inserting frame is arranged at the top of the first vertical rod and the second vertical rod; the application also discloses a plate forming method, which comprises the following steps: pre-fixing, maintaining sealing, splicing and installing; the beneficial effects are as follows: the second vertical rod, the first vertical rod and the splicing frame are of a separated structure, and can be disassembled and transported into a bathroom to be assembled in the bathroom.
Description
Technical Field
The application relates to the technical field of indoor wrapping pipes for home decoration, in particular to an indoor wrapping pipe assembling tool for home decoration and an assembling method thereof.
Background
The vertical pipe is a term for home decoration, namely, when the house is decorated, the vertical pipes of the sewer pipe and the water supply pipeline are packaged by using decorative materials, and the vertical pipe is mainly used for decoration in toilets and kitchens, so that the house decoration is more attractive;
in the prior art, a plurality of groups of decorative materials are needed to be assembled for packaging the exterior of a sewer and a water supply pipeline;
the existing devices for assembling the decorative materials are all undetachable, the space of the bathroom is small, the structure for assembling is not easy to carry and fix, the bottom of the pipeline is in contact with the ground, and water in the bathroom easily flows into a gap between the pipeline and the ground.
Disclosure of Invention
The application aims to provide a home decoration indoor packing tube assembling tool and an assembling method thereof, which are used for solving the problems in the background technology.
In order to achieve the above purpose, the present application provides the following technical solutions: an indoor pillar assembly tool of home decoration, includes:
the wall, the outside of the wall has pipelines;
the bottom of the second vertical rod is provided with a bottom rod, the bottom of the bottom rod is provided with a rubber strip, the surface of the first vertical rod is provided with a through groove, the inside of the through groove is provided with a lifting plate, the surface of the lifting plate is provided with a second screw hole, the bottom of the lifting plate is provided with a pulling block, the bottom of the pulling block is provided with a second fixing plate, and the surface of the first vertical rod is provided with a fourth screw hole; a kind of electronic device with high-pressure air-conditioning system
The inserting frame is arranged at the top of the first vertical rod and the second vertical rod.
Preferably, the bottom rod is installed to the bottom of second pole setting, and the rubber strip is installed to the bottom of bottom rod, and the connecting rod is installed at the both ends of second pole setting, and first pole setting is installed to the tip of connecting rod, and first pole setting has two sets of.
Preferably, the bottom of the first vertical rod is connected to the top of the bottom rod, the top of the first vertical rod is provided with a plug hole, a plug rod is plugged in the plug hole, and a rubber pad is arranged on the surface of the plug rod.
Preferably, the top of the plugging rod is provided with a plugging frame, the surface of the plugging frame is provided with a through hole, and the plugging frame is fixed on the surface of the wall by using a screw rod.
Preferably, the surface mounting of the first upright rod is provided with a fixing plate, one end of the inner plate is inserted into the fixing plate, and the fixing plate fixes one end of the inner plate inside the fixing plate.
Preferably, the surface of the first vertical rod is provided with a through groove, a movable rod is inserted into the through groove, the movable rod can be lifted in the first vertical rod, and the top of the movable rod is connected to the bottom of the lifting plate.
Preferably, the outside cover of movable rod is equipped with the spring, and the second spiro union hole has been seted up on the surface of lifter plate, and the pulling piece is installed to the bottom of lifter plate, and the second fixed plate is installed to the bottom of pulling piece, and the fourth spiro union hole has been seted up on the surface of first pole setting.
Preferably, the surface of the first upright rod is provided with a screw hole, the screw rod can be screwed in the screw hole, and the surface of the second fixing plate is provided with a third screw hole.
An assembling method of an assembling tool for indoor packaging pipes of home decoration comprises the following steps:
step one: pre-fixing, namely pressing down the lifting plate in the through groove, enabling the lifting plate to pass through the third screw hole and the fourth screw hole by using a screw rod, fixing the second fixing plate on the surface of the first vertical rod, and at the moment, retracting the moving rod into the first vertical rod, so that the spring is compressed;
step two: maintaining the sealing, fixing the lifting plate on the surface of the wall by using a screw rod to pass through the second screw joint hole, fixing the first vertical rod on the surface of the wall by using the screw rod to pass through the screw joint hole, loosening the screw rods screwed in the third screw joint hole and the fourth screw joint hole, and pushing the spring on the lifting plate to enable the rubber strip at the bottom of the bottom rod to be tightly pressed down on the ground so as to prevent water from flowing into a gap between the pipeline and the wall from the bottom of the bottom rod;
step three: splicing, namely splicing the splicing rods at the bottom of the splicing frame in the splicing holes, and fixing the splicing frame on the surface of the wall by using the screw rod, so that the splicing frame is conveniently fixed on the surface of the wall;
step four: the installation, peg graft the tip of inner panel in the fixed plate, the fixed plate can be fixed the tip of inner panel, conveniently tailors the other end of inner panel, uses the screw to fix the inner panel on the surface of first pole setting, second pole setting and grafting frame, is gluing the surface at the inner panel with decorative material.
Compared with the prior art, the application has the beneficial effects that:
the second vertical rod, the first vertical rod and the plug-in frame are of a split structure, can be disassembled and transported into a bathroom, are assembled in the bathroom, the rubber strip is arranged at the bottom of the bottom rod, the second fixing plate is fixed in the fourth screw hole by penetrating the third screw hole through the screw rod after the lifting plate is pressed down, the lifting plate is fixed on the surface of a wall by penetrating the second screw hole through the screw rod after penetrating the third screw hole, and the rubber strip can be tightly pressed on the top of the ground under the pushing of the spring after the screw rod in the third screw hole is loosened, so that water is prevented from flowing into a gap between the pipeline and the ground through the rubber strip.
Drawings
FIG. 1 is a schematic perspective view of the present application;
FIG. 2 is a schematic view showing a bottom perspective structure of the present application;
FIG. 3 is a schematic cross-sectional perspective view of the present application;
FIG. 4 is an enlarged schematic view of the structure A in FIG. 1;
fig. 5 is an enlarged schematic view of the structure at B in fig. 3.
In the figure: wall 1, pipeline 2, first pole 3, inner plate 4, bottom rod 5, second pole 6, screw hole 7, connecting rod 8, plug rod 9, plug frame 10, rubber strip 11, plug hole 12, fixing plate 13, lifting plate 14, second screw hole 15, pulling block 16, third screw hole 17, second fixing plate 18, fourth screw hole 19, through slot 20, spring 21, moving rod 22
Detailed Description
In order to make the objects, technical solutions, and advantages of the present application more apparent, the embodiments of the present application will be further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are some, but not all, embodiments of the present application, are intended to be illustrative only and not limiting of the embodiments of the present application, and that all other embodiments obtained by persons of ordinary skill in the art without making any inventive effort are within the scope of the present application.
In the description of the present application, it should be noted that the terms "center," "middle," "upper," "lower," "left," "right," "inner," "outer," "top," "bottom," "side," "vertical," "horizontal," and the like indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, merely to facilitate description of the present application and simplify the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present application. Furthermore, the terms "a," an, "" the first, "" the second, "" the third, "" the fourth, "" the fifth, "and the sixth" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present application, it should be noted that, unless explicitly specified and limited otherwise, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be either fixedly connected, detachably connected, or integrally connected, for example; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present application will be understood in specific cases by those of ordinary skill in the art.
For purposes of brevity and description, the principles of the embodiments are described primarily by reference to examples. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the embodiments. It will be apparent, however, to one of ordinary skill in the art that the embodiments may be practiced without limitation to these specific details. In some instances, well-known methods and structures have not been described in detail so as not to unnecessarily obscure the embodiments. In addition, all embodiments may be used in combination with each other.
Referring to fig. 1 to 5, the present application provides a technical solution: an indoor pillar assembly tool of home decoration, includes: a wall 1, the outside of the wall 1 being provided with a pipe 2;
the bottom rod 5 is arranged at the bottom of the second vertical rod 6, the rubber strip 11 is arranged at the bottom of the bottom rod 5, the connecting rods 8 are arranged at the two ends of the second vertical rod 6, the first vertical rod 3 is arranged at the end part of the connecting rod 8, the first vertical rod 3 is provided with two groups, the surface of the first vertical rod 3 is provided with a through groove 20, a movable rod 22 is inserted into the through groove 20, the movable rod 22 can lift in the first vertical rod 3, the top of the movable rod 22 is connected to the bottom of the lifting plate 14, a spring 21 is sleeved outside the movable rod 22, the surface of the lifting plate 14 is provided with a second screw hole 15, the bottom of the lifting plate 14 is provided with a pulling block 16, the bottom of the pulling block 16 is provided with a second fixed plate 18, the surface of the first vertical rod 3 is provided with a fourth screw hole 19, the bottom of the lifting plate 14 is provided with a pulling block 16, and the surface of the lifting plate 14 is provided with a third screw hole 7, and the surface of the third screw hole 17 is provided with a third screw hole 7;
the grafting frame 10 is located the top of first pole setting 3 and second pole setting 6, the top at the sill bar 5 is connected to the bottom of first pole setting 3, spliced eye 12 has been seted up at the top of first pole setting 3, the surface mounting of first pole setting 3 has fixed plate 13, the one end of inner panel 4 is pegged graft in fixed plate 13, fixed plate 13 fixes the one end of inner panel 4 in the inside of fixed plate 13, peg graft in spliced eye 12 has peg graft pole 9, the surface of peg graft pole 9 is provided with the rubber pad, peg graft frame 10 is installed at the top of peg graft pole 9, the through-hole has been seted up on the surface of peg graft frame 10, use the screw rod to fix the surface at wall 1 with peg graft frame 10.
An assembling method of an assembling tool for indoor packaging pipes of home decoration comprises the following steps:
step one: pre-fixing, namely pressing down the lifting plate 14 in the through groove 20, penetrating the third screw hole 17 and the fourth screw hole 19 by using a screw rod, and fixing the second fixing plate 18 on the surface of the first vertical rod 3, wherein the moving rod 22 is retracted into the first vertical rod 3, and the spring 21 is compressed;
step two: maintaining a seal, fixing the lifting plate 14 on the surface of the wall 1 by using a screw rod to pass through the second screw hole 15, fixing the first upright 3 on the surface of the wall 1 by using the screw rod to pass through the screw hole 7, loosening the screw rods screwed in the third screw hole 17 and the fourth screw hole 19, and pushing the spring 21 on the lifting plate 14 to tightly press the rubber strip 11 at the bottom of the bottom rod 5 on the ground so as to prevent water from flowing into a gap between the pipeline 2 and the wall 1 from the bottom of the bottom rod 5;
step three: splicing, namely splicing the splicing rod 9 at the bottom of the splicing frame 10 into the splicing hole 12, and fixing the splicing frame 10 on the surface of the wall 1 by using a screw rod, so that the splicing frame 10 is conveniently fixed on the surface of the wall 1;
step four: the installation, peg graft the tip of inner panel 4 in fixed plate 13, fixed plate 13 can be fixed the tip of inner panel 4, conveniently tailors the other end of inner panel 4, uses the screw to fix inner panel 4 at the surface of first pole setting 3, second pole setting 6 and grafting frame 10, glues the decorative material at the surface of inner panel 4.
While the foregoing describes illustrative embodiments of the present application so that those skilled in the art may understand the present application, the present application is not limited to the specific embodiments, and all applications and creations utilizing the inventive concepts are within the scope of the present application as long as the modifications are within the spirit and scope of the present application as defined and defined in the appended claims to those skilled in the art.
Claims (2)
1. An indoor package pipe assembly tool of house ornamentation, its characterized in that: comprising the following steps:
a wall (1), wherein a pipeline (2) is arranged outside the wall (1);
the second pole setting (6), bottom pole (5) is installed to the bottom of second pole setting (6), rubber strip (11) is installed to the bottom of bottom pole (5), logical groove (20) has been seted up on the surface of first pole setting (3), the inside of logical groove (20) is provided with lifter plate (14), second spiro union hole (15) have been seted up on the surface of lifter plate (14), pulling block (16) are installed to the bottom of lifter plate (14), second fixed plate (18) are installed to the bottom of pulling block (16), fourth spiro union hole (19) have been seted up on the surface of first pole setting (3), connecting rod (8) are installed at the both ends of second pole setting (6), first pole setting (3) are installed to the tip of connecting rod (8), first pole setting (3) have two sets of, the top at bottom of first pole setting (3) is connected at bottom pole setting (5), peg graft hole (12) have peg graft pole (9) in peg graft hole (9) on the top of peg graft pole (9), the surface of peg graft pole (9) has the rubber pad, peg graft pole (10) have the top of peg graft pole (9) and install the surface mount (10) and make the peg graft the surface mount (10) with the surface mount (10) at the fixed wall (13), one end of the inner plate (4) is inserted into the fixed plate (13), the fixed plate (13) fixes one end of the inner plate (4) inside the fixed plate (13), a through groove (20) is formed in the surface of the first vertical rod (3), a movable rod (22) is inserted into the through groove (20), the movable rod (22) can ascend and descend in the first vertical rod (3), the top of the movable rod (22) is connected to the bottom of the lifting plate (14), a spring (21) is sleeved outside the movable rod (22), a second screw hole (15) is formed in the surface of the lifting plate (14), a pulling block (16) is arranged at the bottom of the lifting plate (14), a second fixed plate (18) is arranged at the bottom of the pulling block (16), a fourth screw hole (19) is formed in the surface of the first vertical rod (3), a screw hole (7) is formed in the surface of the first vertical rod (3), and a third screw hole (17) is formed in the surface of the second fixed plate (18); a kind of electronic device with high-pressure air-conditioning system
The inserting frame (10) is arranged at the tops of the first vertical rod (3) and the second vertical rod (6).
2. A method for assembling an assembly tool for indoor packaging tubes of home decoration as claimed in claim 1, wherein: the processing flow of the product comprises the following steps:
step one: pre-fixing, namely pressing down the lifting plate (14) in the through groove (20), penetrating the third screw hole (17) and the fourth screw hole (19) by using a screw rod, fixing the second fixing plate (18) on the surface of the first vertical rod (3), at the moment, retracting the moving rod (22) into the first vertical rod (3), and compressing the spring (21);
step two: maintaining a seal, fixing the lifting plate (14) on the surface of the wall (1) by using a screw rod to pass through the second screw joint hole (15), fixing the first vertical rod (3) on the surface of the wall (1) by using the screw rod to pass through the screw joint hole (7), loosening the screw rods screwed in the third screw joint hole (17) and the fourth screw joint hole (19), and pushing the spring (21) on the lifting plate (14) so that the rubber strip (11) at the bottom of the bottom rod (5) is tightly pressed down on the ground to prevent water from flowing into a gap between the pipeline (2) and the wall (1) from the bottom of the bottom rod (5);
step three: splicing, namely splicing a splicing rod (9) at the bottom of a splicing frame (10) in a splicing hole (12), and fixing the splicing frame (10) on the surface of a wall (1) by using a screw rod, so that the splicing frame (10) is conveniently fixed on the surface of the wall (1);
step four: the installation, peg graft the tip of inner panel (4) in fixed plate (13), fixed plate (13) can fix the tip of inner panel (4), conveniently tailors the other end of inner panel (4), uses the screw to fix inner panel (4) on the surface of first pole setting (3), second pole setting (6) and grafting frame (10), is sticking the decorative material on the surface of inner panel (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210617807.4A CN114991424B (en) | 2022-06-01 | 2022-06-01 | Assembly tool and assembly method for indoor wrapping pipe of home decoration |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210617807.4A CN114991424B (en) | 2022-06-01 | 2022-06-01 | Assembly tool and assembly method for indoor wrapping pipe of home decoration |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114991424A CN114991424A (en) | 2022-09-02 |
CN114991424B true CN114991424B (en) | 2023-11-17 |
Family
ID=83030977
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210617807.4A Active CN114991424B (en) | 2022-06-01 | 2022-06-01 | Assembly tool and assembly method for indoor wrapping pipe of home decoration |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114991424B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110616806A (en) * | 2019-09-17 | 2019-12-27 | 福建天安建筑钢铁制品有限公司 | Processing method of green energy-saving assembled steel structure |
CN214364276U (en) * | 2020-12-29 | 2021-10-08 | 青岛有住信息技术有限公司 | Assembled non-bearing wall support |
CN214658989U (en) * | 2021-03-25 | 2021-11-09 | 中建八局第一建设有限公司 | Temporary fixing frame for mounting assembly type building wall |
CN113737998A (en) * | 2021-09-18 | 2021-12-03 | 金螳螂精装科技(苏州)有限公司 | Large-scale space assembly type indoor curtain wall with stable and accurate connecting structure |
CN215519415U (en) * | 2021-08-12 | 2022-01-14 | 张永成 | Corner connecting device for glass curtain wall |
CN216557507U (en) * | 2021-12-21 | 2022-05-17 | 亿达装饰工程(大连)有限公司 | Breather for interior decoration |
-
2022
- 2022-06-01 CN CN202210617807.4A patent/CN114991424B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110616806A (en) * | 2019-09-17 | 2019-12-27 | 福建天安建筑钢铁制品有限公司 | Processing method of green energy-saving assembled steel structure |
CN214364276U (en) * | 2020-12-29 | 2021-10-08 | 青岛有住信息技术有限公司 | Assembled non-bearing wall support |
CN214658989U (en) * | 2021-03-25 | 2021-11-09 | 中建八局第一建设有限公司 | Temporary fixing frame for mounting assembly type building wall |
CN215519415U (en) * | 2021-08-12 | 2022-01-14 | 张永成 | Corner connecting device for glass curtain wall |
CN113737998A (en) * | 2021-09-18 | 2021-12-03 | 金螳螂精装科技(苏州)有限公司 | Large-scale space assembly type indoor curtain wall with stable and accurate connecting structure |
CN216557507U (en) * | 2021-12-21 | 2022-05-17 | 亿达装饰工程(大连)有限公司 | Breather for interior decoration |
Also Published As
Publication number | Publication date |
---|---|
CN114991424A (en) | 2022-09-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2535259A1 (en) | Pothead assembly | |
CN114991424B (en) | Assembly tool and assembly method for indoor wrapping pipe of home decoration | |
CN205554764U (en) | Row of inserting packagine machine's wrapping bag struts subassembly | |
CN201202361Y (en) | Hollow glass spacing frame | |
CN204739752U (en) | Broken cold bridge box structure | |
CN209293363U (en) | A kind of cell curtain wall vertical decorative strip | |
CN116607867A (en) | Double-layer glass window structure and assembly method | |
CN206245539U (en) | A kind of concealed special-shaped curtain wall decorative strip connector | |
CN215670207U (en) | Vacuum insulation board | |
CN211776822U (en) | Connecting structure of prefabricated assembled window and wall | |
CN204510567U (en) | A kind of panel built-in type curtain wall | |
CN112031316A (en) | Mounting and positioning structure of assembled soft and hard bag | |
CN113323260A (en) | Wall top closing structure and mounting method thereof | |
CN206053059U (en) | Without glass pair frame Concealed glass curtain wall connecting elements and attachment structure | |
CN207161469U (en) | Adjustable height top line connector and the connection component including the connector | |
CN210067846U (en) | Energy-saving window system with hidden sash window designed by high-low drainage step difference | |
CN211007516U (en) | False beam decoration display rack | |
CN111585242B (en) | Full-cold-shrinkage cable terminal | |
CN220790259U (en) | Energy-saving and environment-friendly glass curtain wall | |
CN220225834U (en) | Building curtain waterproof construction | |
CN218149447U (en) | Invisible detachable tube wrapping bracket unit and invisible detachable tube wrapping bracket thereof | |
CN219182188U (en) | Wall-hung type gardening planting groove | |
CN2317398Y (en) | Plastic pipe structure for arrangement of decorative lighting device | |
CN210369446U (en) | Vacuum sound insulation type light partition wall board convenient to disassemble and assemble | |
CN219080815U (en) | Crystal hanging plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |